SlideShare ist ein Scribd-Unternehmen logo
1 von 46
Downloaden Sie, um offline zu lesen
Design – Build
and the
Standard of Care
Under which Standard? Under whose Care?
ABA Construction Forum
Division 4
Project Delivery
E. Mitchell Swann P.E., C.Eng, LEED AP
Principal
MDCSystems®
www.MDCSystems.com
So why are we here?
Program Overview
• As design-build achieves a broader footprint
both geographically and by project type, not only
are more projects going that way, but there are
more ways for that way to go. In this mix is the
shifting sands upon which the “custom and
practice” of the industry is based – the Standard
of Care. The profession, in fact all professions,
that operate under a Standard of Care recognize
that what was standard at one time can be
archaic and outmoded in another. This program
will look at one example of a project within the
context of a changing standard and some of the
issues that can create.
3
Some Context
• The agency historically used
Design-Bid-Build delivery.
• It’s typical procedures,
specifications and approvals were
applied to the project.
• The designer had worked directly
for the agency in the past.
Contrast and compare…
5
So about this project…
• Government Agency issues an RFP for a
project and it calls for a Design-Build
execution strategy. (~30% complete document set)
6
So about this project…
• Government Agency issues an RFP for a project
and it calls for a Design-Build execution
strategy. (~30% complete document set)
• A Contractor who has not worked for that
agency before decides to bid the job.
7
So about this project…
• Government Agency issues an RFP for a project
and it calls for a Design-Build execution
strategy. (~30% complete document set)
• A Contractor who has not worked for that
agency before decides to bid the job.
• The Contractor retains an engineering firm as a
design sub-consultant who has had prior
experience with the agency.
8
So about this project…
• Government Agency issues an RFP for a project
and it calls for a Design-Build execution
strategy. (~30% complete document set)
• A Contractor who has not worked for that
agency before decides to bid the job.
• The Contractor retains an engineering firm as a
design sub-consultant who has had prior
experience with the agency.
• The D|B team prepares a bid.
There is a stipend ($100k) provided to bidders to prepare
proposals – the design firm is compensated for their work.
9
So about this project…
They win.
10
So about this project…
They win.
(this is where the “madcap hi-jinks” ensue)
11
The Designer’s duties:
• provide technical guidance on
interpreting the RFP documents
• conceptualizing & quantifying bid
quantities used to develop unit
prices & estimate.
12
Sequence of events
(So what had happened was…)
• …the engineer points out
a “potential issue” of
concern,
• …the contractor asks for
“guidance” with respect
to the issue.
AND
As the project proceeded….
Meanwhile the
agency…
• …clarifies the little
“change” in their
approach;
• …extends the Bid Due
date.
…the “potential issue”
became real.
The D|B team
prepares its bid…
So this translates to
$$$
&
TIME
(which equals $$$ too)
14
As the project progressed….
Consider this:
Even in “design|build” there is some portion
of the schedule when you have to “design”.
Quick flashback
16
As the project progressed….
Consider this:
Even in “design|build” there is some portion
of the schedule when you have to “design”.
During construction, it became evident that
there were major features of the project that
had not been developed in the agency issued
RFP documents.
17
As the project progressed….
Consider this:
Even in “design|build” there is some portion of
the schedule when you have to “design”.
During construction, it became evident that
there were major features of the project that
had not been developed in the agency issued
RFP documents.
BUT the need to address them and any project
constraints were.
(and there were some new approaches)
So what are the issues here?
The “Standard of Care”
• …[to] "exercise the average degree of
skill, care, and diligence exercised by
members of the same profession (or
specialty within that profession),
practicing in the same or a similar
locality in light of the present state of
the profession"
• (Gillette v. Tucker). See Black's Law Dictionary, 6th edition. 1404-5.
20
What was the designer hired to do?
Provide professional design services (both Pre &
Post-bid) …
• …to assist in submitting the bid;
• …to insure that design satisfied client design
standards;
• …to insure the design facilitates the submission
a competitive bid;
• …to provide customized quantity calculations;
• …to provide engineering staff as required thru
construction;
• …to provide other Construction Phase Services
• …to cooperate with contractor in a manner
consistent with good design practice.
but…
Perfection
is not
a
reasonable expectation.
22
…and as the project progressed
remember
…even in “design|build” there is some portion
of the schedule when you have to “design”.
The designer “designs” and issues drawings to
the contractor (his client).
However the delivery pace of these IFC
documents made it hard to “see” the escalating
“scope creep” that was developing drawing by
drawing.
Until the “bid design” didn’t look like the “construction design”
Key along the trail of the bidding period:
The Designer alerted Contractor to the
potential issue
AND
the Contractor asked for guidanceinput
from the Designer
AND
the Bid Due date was extended.
The “Standard of Care”
What (or which)
is the applicable and/or prevailing standard of care?
The “Standard of Care”
What (or which)
is the applicable and/or prevailing standard of care?
• For the Proposal
documents?
• For interpreting those
documents?
Is the contractor entitled to ‘reasonably rely
upon’ the materials prepared by the designer?
(even if the designer works for the contractor?)
The “Standard of Care”
What (or which)
is the applicable and/or prevailing standard of care?
• For the Proposal
documents?
• For quantities in the
take off?
• For interpreting those
documents?
• For pricing the work
associated with those
quantities?
Is the contractor entitled to ‘reasonably rely
upon’ the materials prepared by the designer?
(even if the designer works for him?)
Is the traditional design ‘absolution’ from
“means and methods” appropriate?
Is the contractor entitled to ‘reasonably rely
upon’ the materials prepared by the designer?
(even if the designer works for him?)
Is the traditional design “absolution’ from
“means and methods” appropriate?
Is it significant that the designer was
compensated for the pre-bid work (along with
any work performed after award)?
They received fees for service.
No profit or loss sharing agreement.
The “Standard of Care”
• …[to] "exercise the average degree of skill,
care, and diligence exercised by members
of the same profession (or specialty within
that profession), practicing in the same or
a similar locality in light of the present
state of the profession"
• (Gillette v. Tucker). See Black's Law Dictionary, 6th edition. 1404-5.
It wasn’t me!
Everybody had plausible deniability…
• The agency said, “It is a Design-Build
contract and we are not accepting change
orders.”
It wasn’t me!
Everybody had plausible deniability…
• The agency said, “It is a Design-Build
contract and we are not accepting change
orders.”
• The designer said, “The changes are minor
in nature and within the ‘margin of
reasonableness’ (Standard-of-Care) for
any project. We are not responsible for
‘means and methods’, plus we warned of
risks.”
It wasn’t me!
Everybody had plausible deniability…
• The agency said, “It is a Design-Build contract
and we are not accepting change orders.”
• The designer said, “The changes are minor in
nature and within the ‘margin of
reasonableness’ (Standard-of-Care) for any
project. We are not responsible for ‘means and
methods’, plus we warned of risks.”
• The contractor said, “These cost overruns
accumulated and not till the end of the
drawing issues did we see the problem and
determine the final installed quantities and
related costs.”
Some Questions
• Does Design-Build Delivery create
new “means and methods”
responsibilities for designers where
they would not exist in traditional
DBB delivery situations?
Some Questions
• Does Design-Build Delivery create
new “means and methods”
responsibilities for designers where
they would not exist in traditional
DBB delivery situations?
• Does Design-Build Delivery require
new awareness on the part of
contractors to the iterative and
uncertain world of conceptual
design?
Things to Consider:
How precise should you make your
bridgingbidding documents?
Is it possible that you could unwittingly
create an ‘impossibility” defense (or a
massive change order) if you ask for
…the impossible?
Things to Consider:
How precise should you make your
bridgingbidding documents?
Is it possible that you could unwittingly create an
‘impossibility” defense if you ask for …the
impossible?
To what extent can the design-build team
‘reasonably rely upon’ any design elements or
spatial project constraints set forth by the RFP?
If those constraints are wrong, who bears the
responsibility to “correct” the eventual problem.
Things to Consider:
How precise should you make your bridgingbidding documents?
Is it possible that you could unwittingly create an ‘impossibility”
defense if you ask for …the impossible?
To what extent can the design-build team ‘reasonably rely upon’ any
design elements or spatial project constraints set forth by the RFP?
If those constraints are wrong, who bears the responsibility to
“correct” the eventual problem.
If you go into a “project specific” design-build should
you set up appropriate incentives (and penalties?) to
properly align the team members’ interests?
Develop special clauses concerning design and estimating liability?
And then there’s this…
The designer had worked for the owner before
(but in design-bid-build arrangements).
The advantage of that prior experience prompted the contractor to select them.
Is it possible that the designer wasn’t really
that ‘enthused’ about the arrangement?
He certainly wouldn’t want the owner to be unsatisfied, but…
Would he be concerned about the financial
position of the contractor?
(As concerned as the contractor?)
Traditional “client focus” for designers is the owner.
Licensure stresses the public safety and welfare.
In a ‘sub-contract’ arrangement to a contractor, the paying client has changed, but
does that change the licensure focus on “public safety and welfare”?
So what do we learn?
Those whose paths are not the sameThose whose paths are not the sameThose whose paths are not the sameThose whose paths are not the same
do not consult one another.do not consult one another.do not consult one another.do not consult one another.
ConfuciusConfuciusConfuciusConfucius
Questions?
Thank you!Thank you!Thank you!Thank you!
E. Mitchell Swann P.E., LEED AP, F.CIBSE, C.Eng
Principal - MDCSystems®
swann@mdcsystems.com
www.MDCSystems.com
MDCSystems® Summary of Services
Program & Project Development
including…
• Performance Assessment &
Benchmarking
Project Modeling including…
• “What if…” Scenario Analyses
• Variability/Sensitivity Analyses
• ‘Out of Bounds’/”Go – No Go”
Limits
Project Planning including…
• Feasibility Studies
• Master Scheduling including…
– Resource & Constraint Analysis
Project Monitoring including…
• Schedule Compliance
• Cash Flow & “Burn rate” projections
• Resource Utilization
Consulting Services including…
• Sustainability/Green Buildings
• Peer Review
• Practice Management
Forensic Analyses including:
• Building Systems:
– Architectural incl. Building Envelope
– HVAC/Mechanical, Electrical & Piping
– Structural
– Instrumentation & Controls
• Design Errors & Omissions (Standard of
Care)
• Differing Site Conditions
Forensic Project Management®
• Schedule Analysis
– Delay, Disruption, Suspension &
Acceleration
• Labor Productivity & Inefficiency
• Scope Definition and Change
• Termination - Default or Convenience
• Procurement - Bid/Award Transparency
Forensic Accounting including…
• Valuation of Damages
– Overhead & General Conditions
• Business Interruption & Lost Profit
MDCSystems®
Providing Expert Project Delivery Solutions Worldwide
MDC Systems is a project and construction management consultancy with over 40
years of experience serving a wide array of clients and industries both nationally and
around the globe.
MDC has worked on projects as diverse as residential property developments to
pharmaceutical plants to highway excavation and construction.
MDC concentrates its services in primarily four areas:
program management, project management consulting, forensic engineering
and construction claims consulting.
One of the key facets of MDC’s professional staff is our expertise in the technology
driven issues that are so frequently at the heart of today’s complex projects.
MDC’s construction claims consulting practice combines all of the skills inherent to
our other service offerings and deploys it for our clients when and where projects don’t
go quite as smoothly as everyone had hoped. MDC is an industry leader in the area of
construction schedule development and analysis including delay, acceleration,
interruption and extended duration. MDC pioneered the court tested and approved
Time Impact Analysis methodology for scientifically analyzing construction schedules
and the impact of events upon their execution and completion.
www.MDCSystems.com
Selected Recent Assignments
Engineering Consulting and Technical Analyses:
• Analysis of Moisture Migration and RH Control
in a Microelectronics Product R&D Facility
(Colorado).
• Analysis and Improvement of Energy
Consumption at a “Green” School
(Pennsylvania)
• Peer Review & Design Supervision for a Radiant
Heating/Cooling Floor System (New Jersey)
• Peer Review of Schematic Engineering Design
Effort for Hospital Complex (Qatar)
• Analysis of Formaldehyde Outgassing from
Construction Materials (Pennsylvania)
• HVAC System Failures in Pharmaceutical
Packaging Facility (New Jersey)
• Analysis of Process Technology Failure at Waste
Treatment Plant (New Jersey)
• Analysis of Piping System Joint Failures at a
Hospital central Plant (New Jersey)
• Assessment and Analyses of Energy Future
Options for Major Municipality
Project Management, Execution & Construction Claims :
• Excess Rock Excavation Claim on a Highway Project
- Unforeseen Conditions (New Jersey)
• Electrical Contractor Inefficiency Claim on Multi-
Prime Project (New Jersey)
• Electrical Usage Charge Dispute Between Landlord
& Tenant (New York)
• Schedule Delays and Change Orders on multiple
Airport Projects for Major Equipment Supplier
(various)
• Schedule Delays and Associated Cost Overruns for
Underwater Pipeline Project (Ireland)
• “Standard of Care” Defense - Design of a Food
Processing Facility (Pennsylvania)
• “Standard of Care” Defense – Design and
Documentation of a Pharmaceutical Plant using 3D
Modeling (Texas)
• “Standard of Care” Plaintiff – Delay and Cost
Overruns for a Pharmaceutical Plant using 3D
Modeling (Singapore)
• Analysis of Destructive VibrationHarmonics on
Large Industrial Compressors at a Chemical Plant
(Louisiana)

Weitere ähnliche Inhalte

Was ist angesagt?

Consensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in ConstructionConsensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in ConstructionDBL Law
 
APM Presents - Why Value Management might reveal just what managing projects...
APM Presents - Why Value Management might reveal just what managing  projects...APM Presents - Why Value Management might reveal just what managing  projects...
APM Presents - Why Value Management might reveal just what managing projects...Association for Project Management
 
Integrated Project Delivery
Integrated Project DeliveryIntegrated Project Delivery
Integrated Project DeliveryMike Purdy
 
Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014SHKLaw
 
Comparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & MaintainComparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & MaintainBob Prieto
 
APM Presents - Contracts and Procurement: what you must know to get the contr...
APM Presents - Contracts and Procurement: what you must know to get the contr...APM Presents - Contracts and Procurement: what you must know to get the contr...
APM Presents - Contracts and Procurement: what you must know to get the contr...Association for Project Management
 
Ipd Convention 2009 Lessons Learned Presentation Final
Ipd Convention 2009 Lessons Learned Presentation FinalIpd Convention 2009 Lessons Learned Presentation Final
Ipd Convention 2009 Lessons Learned Presentation FinalAndrew Huseman
 
Eight Steps to Planning and Delivering Successful Rail Networks_(c) Arup
Eight Steps to Planning and Delivering Successful Rail Networks_(c) ArupEight Steps to Planning and Delivering Successful Rail Networks_(c) Arup
Eight Steps to Planning and Delivering Successful Rail Networks_(c) ArupHeather Ceney
 
Collaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contractsCollaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contractsAssociation for Project Management
 
Integrated project delivery case studies
Integrated project delivery   case studiesIntegrated project delivery   case studies
Integrated project delivery case studiesrosaangelicaportalat1
 
Pm0012 – project finance and budgeting
Pm0012 –  project finance and budgetingPm0012 –  project finance and budgeting
Pm0012 – project finance and budgetingsmumbahelp
 
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1Charles S. Maggio
 
Dispute resolution technique
Dispute resolution techniqueDispute resolution technique
Dispute resolution techniqueSaad Ullah
 
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...Association for Project Management
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...Association for Project Management
 
Fundamental Skills for Real Estate Development Professionals I – Site Selecti...
Fundamental Skills for Real Estate Development Professionals I – Site Selecti...Fundamental Skills for Real Estate Development Professionals I – Site Selecti...
Fundamental Skills for Real Estate Development Professionals I – Site Selecti...Virtual ULI
 
Integrated project delivery for more effective development
Integrated project delivery for more effective developmentIntegrated project delivery for more effective development
Integrated project delivery for more effective developmentAllen Matkins
 
Basic Contract Law for PMs webinar Part 2: Building a contract, 6 March 2018
Basic Contract Law for PMs webinar Part 2: Building a contract, 6 March 2018Basic Contract Law for PMs webinar Part 2: Building a contract, 6 March 2018
Basic Contract Law for PMs webinar Part 2: Building a contract, 6 March 2018Association for Project Management
 
Cómo reducir la fricción en el desarrollo de software
Cómo reducir la fricción en el desarrollo de softwareCómo reducir la fricción en el desarrollo de software
Cómo reducir la fricción en el desarrollo de softwareSoftware Guru
 

Was ist angesagt? (20)

Consensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in ConstructionConsensus Docs: Introduction to Integrated Project Delivery in Construction
Consensus Docs: Introduction to Integrated Project Delivery in Construction
 
APM Presents - Why Value Management might reveal just what managing projects...
APM Presents - Why Value Management might reveal just what managing  projects...APM Presents - Why Value Management might reveal just what managing  projects...
APM Presents - Why Value Management might reveal just what managing projects...
 
ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)
 
Integrated Project Delivery
Integrated Project DeliveryIntegrated Project Delivery
Integrated Project Delivery
 
Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014Affinity institute design assist november 25 2014
Affinity institute design assist november 25 2014
 
Comparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & MaintainComparison of Design Bid Build vs. Design Build Finance Operate & Maintain
Comparison of Design Bid Build vs. Design Build Finance Operate & Maintain
 
APM Presents - Contracts and Procurement: what you must know to get the contr...
APM Presents - Contracts and Procurement: what you must know to get the contr...APM Presents - Contracts and Procurement: what you must know to get the contr...
APM Presents - Contracts and Procurement: what you must know to get the contr...
 
Ipd Convention 2009 Lessons Learned Presentation Final
Ipd Convention 2009 Lessons Learned Presentation FinalIpd Convention 2009 Lessons Learned Presentation Final
Ipd Convention 2009 Lessons Learned Presentation Final
 
Eight Steps to Planning and Delivering Successful Rail Networks_(c) Arup
Eight Steps to Planning and Delivering Successful Rail Networks_(c) ArupEight Steps to Planning and Delivering Successful Rail Networks_(c) Arup
Eight Steps to Planning and Delivering Successful Rail Networks_(c) Arup
 
Collaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contractsCollaborative contracting strategies and the use of the NEC3 family of contracts
Collaborative contracting strategies and the use of the NEC3 family of contracts
 
Integrated project delivery case studies
Integrated project delivery   case studiesIntegrated project delivery   case studies
Integrated project delivery case studies
 
Pm0012 – project finance and budgeting
Pm0012 –  project finance and budgetingPm0012 –  project finance and budgeting
Pm0012 – project finance and budgeting
 
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
 
Dispute resolution technique
Dispute resolution techniqueDispute resolution technique
Dispute resolution technique
 
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
What is NEC3? by Dr Jon Broome, with industry examples by John Rayner, 21st A...
 
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
What is NEC 3?, by Dr Jon Broome, 31st March 2015 copyright leadingedgeprojec...
 
Fundamental Skills for Real Estate Development Professionals I – Site Selecti...
Fundamental Skills for Real Estate Development Professionals I – Site Selecti...Fundamental Skills for Real Estate Development Professionals I – Site Selecti...
Fundamental Skills for Real Estate Development Professionals I – Site Selecti...
 
Integrated project delivery for more effective development
Integrated project delivery for more effective developmentIntegrated project delivery for more effective development
Integrated project delivery for more effective development
 
Basic Contract Law for PMs webinar Part 2: Building a contract, 6 March 2018
Basic Contract Law for PMs webinar Part 2: Building a contract, 6 March 2018Basic Contract Law for PMs webinar Part 2: Building a contract, 6 March 2018
Basic Contract Law for PMs webinar Part 2: Building a contract, 6 March 2018
 
Cómo reducir la fricción en el desarrollo de software
Cómo reducir la fricción en el desarrollo de softwareCómo reducir la fricción en el desarrollo de software
Cómo reducir la fricción en el desarrollo de software
 

Ähnlich wie Aba div 4_swann_design_build_standard_of_care_2014_05_27

A Proven Software Development Process for the Non Technical Founder
A Proven Software Development Process for the Non Technical FounderA Proven Software Development Process for the Non Technical Founder
A Proven Software Development Process for the Non Technical FounderFounders Workshop
 
20080704 innovative approach in contracts and tender procurement management
20080704 innovative approach in contracts and tender procurement management20080704 innovative approach in contracts and tender procurement management
20080704 innovative approach in contracts and tender procurement managementraymond_wan2005
 
Moser disruptive practice-arch3.0-2012
Moser disruptive practice-arch3.0-2012Moser disruptive practice-arch3.0-2012
Moser disruptive practice-arch3.0-2012Cliff Moser
 
Андрій Татчин "Software Project Estimation: Theory and Reality"
Андрій Татчин "Software Project Estimation: Theory and Reality" Андрій Татчин "Software Project Estimation: Theory and Reality"
Андрій Татчин "Software Project Estimation: Theory and Reality" Lviv Startup Club
 
PM Project-Charter.pptx
PM Project-Charter.pptxPM Project-Charter.pptx
PM Project-Charter.pptxNimra zaman
 
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITYHOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITYBurns White LLC
 
How to Write Content Strategy SOWs and Contracts
How to Write Content Strategy SOWs and ContractsHow to Write Content Strategy SOWs and Contracts
How to Write Content Strategy SOWs and ContractsJack Molisani
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916George Wilkinson
 
Module Three Exercises 2BA 1200 Foundations of Business.docx
Module Three Exercises  2BA 1200 Foundations of Business.docxModule Three Exercises  2BA 1200 Foundations of Business.docx
Module Three Exercises 2BA 1200 Foundations of Business.docxroushhsiu
 
01 scope of the ba role
01 scope of the ba role01 scope of the ba role
01 scope of the ba rolebanuseymen
 
The Agile BA (Business Analyst)
The Agile BA (Business Analyst)The Agile BA (Business Analyst)
The Agile BA (Business Analyst)Quang Ngoc
 
Jumping Alligators: The Pitfalls of Planning
Jumping Alligators: The Pitfalls of PlanningJumping Alligators: The Pitfalls of Planning
Jumping Alligators: The Pitfalls of PlanningDevelopmentArc LLC
 
PM : Request for Information
PM : Request for InformationPM : Request for Information
PM : Request for InformationTodd Wyatt
 
Integrated-Information-Technology.ppt
Integrated-Information-Technology.pptIntegrated-Information-Technology.ppt
Integrated-Information-Technology.pptSanjeebJha3
 
5 Step Playbook to Designing and Building the Dental Practice of Your Dreams
5 Step Playbook to Designing and Building the Dental Practice of Your Dreams5 Step Playbook to Designing and Building the Dental Practice of Your Dreams
5 Step Playbook to Designing and Building the Dental Practice of Your DreamsDesign Ergonomics, Inc.
 
about start up for you 12
about start up for you 12about start up for you 12
about start up for you 12aliaalistartup
 

Ähnlich wie Aba div 4_swann_design_build_standard_of_care_2014_05_27 (20)

A Proven Software Development Process for the Non Technical Founder
A Proven Software Development Process for the Non Technical FounderA Proven Software Development Process for the Non Technical Founder
A Proven Software Development Process for the Non Technical Founder
 
20080704 innovative approach in contracts and tender procurement management
20080704 innovative approach in contracts and tender procurement management20080704 innovative approach in contracts and tender procurement management
20080704 innovative approach in contracts and tender procurement management
 
Moser disruptive practice-arch3.0-2012
Moser disruptive practice-arch3.0-2012Moser disruptive practice-arch3.0-2012
Moser disruptive practice-arch3.0-2012
 
Андрій Татчин "Software Project Estimation: Theory and Reality"
Андрій Татчин "Software Project Estimation: Theory and Reality" Андрій Татчин "Software Project Estimation: Theory and Reality"
Андрій Татчин "Software Project Estimation: Theory and Reality"
 
PM Project-Charter.pptx
PM Project-Charter.pptxPM Project-Charter.pptx
PM Project-Charter.pptx
 
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITYHOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
HOW TO SURVIVE CONSTRUCTION PROJECTS DURING TIMES OF ECONOMIC INSANITY
 
Design process
Design processDesign process
Design process
 
How to Write Content Strategy SOWs and Contracts
How to Write Content Strategy SOWs and ContractsHow to Write Content Strategy SOWs and Contracts
How to Write Content Strategy SOWs and Contracts
 
01 scope of the ba role
01 scope of the ba role01 scope of the ba role
01 scope of the ba role
 
Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916Ethics and Integated Design-Build services 062916
Ethics and Integated Design-Build services 062916
 
Module Three Exercises 2BA 1200 Foundations of Business.docx
Module Three Exercises  2BA 1200 Foundations of Business.docxModule Three Exercises  2BA 1200 Foundations of Business.docx
Module Three Exercises 2BA 1200 Foundations of Business.docx
 
01 scope of the ba role
01 scope of the ba role01 scope of the ba role
01 scope of the ba role
 
The Agile BA (Business Analyst)
The Agile BA (Business Analyst)The Agile BA (Business Analyst)
The Agile BA (Business Analyst)
 
Mit1 040s09 lec18
Mit1 040s09 lec18Mit1 040s09 lec18
Mit1 040s09 lec18
 
Jumping Alligators: The Pitfalls of Planning
Jumping Alligators: The Pitfalls of PlanningJumping Alligators: The Pitfalls of Planning
Jumping Alligators: The Pitfalls of Planning
 
PM : Request for Information
PM : Request for InformationPM : Request for Information
PM : Request for Information
 
Integrated-Information-Technology.ppt
Integrated-Information-Technology.pptIntegrated-Information-Technology.ppt
Integrated-Information-Technology.ppt
 
Agile Mindset (عقلية وطرق التفكير في الإدارة الرشيقة للمشاريع)
Agile Mindset (عقلية وطرق التفكير في الإدارة الرشيقة للمشاريع)Agile Mindset (عقلية وطرق التفكير في الإدارة الرشيقة للمشاريع)
Agile Mindset (عقلية وطرق التفكير في الإدارة الرشيقة للمشاريع)
 
5 Step Playbook to Designing and Building the Dental Practice of Your Dreams
5 Step Playbook to Designing and Building the Dental Practice of Your Dreams5 Step Playbook to Designing and Building the Dental Practice of Your Dreams
5 Step Playbook to Designing and Building the Dental Practice of Your Dreams
 
about start up for you 12
about start up for you 12about start up for you 12
about start up for you 12
 

Mehr von Roland_Nikles

Ipd analysis summary metrics asce article_julia_2013_12_17
Ipd analysis summary metrics asce article_julia_2013_12_17Ipd analysis summary metrics asce article_julia_2013_12_17
Ipd analysis summary metrics asce article_julia_2013_12_17Roland_Nikles
 
Aba division 4 presentation outside consultants handling of change orders (8 ...
Aba division 4 presentation outside consultants handling of change orders (8 ...Aba division 4 presentation outside consultants handling of change orders (8 ...
Aba division 4 presentation outside consultants handling of change orders (8 ...Roland_Nikles
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Roland_Nikles
 
Aba february 2013_presentation
Aba february 2013_presentationAba february 2013_presentation
Aba february 2013_presentationRoland_Nikles
 
Division 4 presentation_pumphrey_2013_01_22
Division 4 presentation_pumphrey_2013_01_22Division 4 presentation_pumphrey_2013_01_22
Division 4 presentation_pumphrey_2013_01_22Roland_Nikles
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Roland_Nikles
 

Mehr von Roland_Nikles (6)

Ipd analysis summary metrics asce article_julia_2013_12_17
Ipd analysis summary metrics asce article_julia_2013_12_17Ipd analysis summary metrics asce article_julia_2013_12_17
Ipd analysis summary metrics asce article_julia_2013_12_17
 
Aba division 4 presentation outside consultants handling of change orders (8 ...
Aba division 4 presentation outside consultants handling of change orders (8 ...Aba division 4 presentation outside consultants handling of change orders (8 ...
Aba division 4 presentation outside consultants handling of change orders (8 ...
 
Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)Criterium epc project risks (5.28.13)
Criterium epc project risks (5.28.13)
 
Aba february 2013_presentation
Aba february 2013_presentationAba february 2013_presentation
Aba february 2013_presentation
 
Division 4 presentation_pumphrey_2013_01_22
Division 4 presentation_pumphrey_2013_01_22Division 4 presentation_pumphrey_2013_01_22
Division 4 presentation_pumphrey_2013_01_22
 
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
Aba forum division_4_aurora_light_rail_presentation_shresta_2012_11_27
 

Kürzlich hochgeladen

Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...lizamodels9
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Anamikakaur10
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756dollysharma2066
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Sheetaleventcompany
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...allensay1
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...amitlee9823
 

Kürzlich hochgeladen (20)

Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
Call Girls From Pari Chowk Greater Noida ❤️8448577510 ⊹Best Escorts Service I...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
Chandigarh Escorts Service 📞8868886958📞 Just📲 Call Nihal Chandigarh Call Girl...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
(Anamika) VIP Call Girls Napur Call Now 8617697112 Napur Escorts 24x7
 
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
Call Girls Service In Old Town Dubai ((0551707352)) Old Town Dubai Call Girl ...
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 

Aba div 4_swann_design_build_standard_of_care_2014_05_27

  • 1. Design – Build and the Standard of Care Under which Standard? Under whose Care? ABA Construction Forum Division 4 Project Delivery E. Mitchell Swann P.E., C.Eng, LEED AP Principal MDCSystems® www.MDCSystems.com
  • 2. So why are we here? Program Overview • As design-build achieves a broader footprint both geographically and by project type, not only are more projects going that way, but there are more ways for that way to go. In this mix is the shifting sands upon which the “custom and practice” of the industry is based – the Standard of Care. The profession, in fact all professions, that operate under a Standard of Care recognize that what was standard at one time can be archaic and outmoded in another. This program will look at one example of a project within the context of a changing standard and some of the issues that can create.
  • 3. 3 Some Context • The agency historically used Design-Bid-Build delivery. • It’s typical procedures, specifications and approvals were applied to the project. • The designer had worked directly for the agency in the past.
  • 5. 5 So about this project… • Government Agency issues an RFP for a project and it calls for a Design-Build execution strategy. (~30% complete document set)
  • 6. 6 So about this project… • Government Agency issues an RFP for a project and it calls for a Design-Build execution strategy. (~30% complete document set) • A Contractor who has not worked for that agency before decides to bid the job.
  • 7. 7 So about this project… • Government Agency issues an RFP for a project and it calls for a Design-Build execution strategy. (~30% complete document set) • A Contractor who has not worked for that agency before decides to bid the job. • The Contractor retains an engineering firm as a design sub-consultant who has had prior experience with the agency.
  • 8. 8 So about this project… • Government Agency issues an RFP for a project and it calls for a Design-Build execution strategy. (~30% complete document set) • A Contractor who has not worked for that agency before decides to bid the job. • The Contractor retains an engineering firm as a design sub-consultant who has had prior experience with the agency. • The D|B team prepares a bid. There is a stipend ($100k) provided to bidders to prepare proposals – the design firm is compensated for their work.
  • 9. 9 So about this project… They win.
  • 10. 10 So about this project… They win. (this is where the “madcap hi-jinks” ensue)
  • 11. 11 The Designer’s duties: • provide technical guidance on interpreting the RFP documents • conceptualizing & quantifying bid quantities used to develop unit prices & estimate.
  • 12. 12 Sequence of events (So what had happened was…) • …the engineer points out a “potential issue” of concern, • …the contractor asks for “guidance” with respect to the issue. AND As the project proceeded…. Meanwhile the agency… • …clarifies the little “change” in their approach; • …extends the Bid Due date. …the “potential issue” became real. The D|B team prepares its bid…
  • 13. So this translates to $$$ & TIME (which equals $$$ too)
  • 14. 14 As the project progressed…. Consider this: Even in “design|build” there is some portion of the schedule when you have to “design”.
  • 16. 16 As the project progressed…. Consider this: Even in “design|build” there is some portion of the schedule when you have to “design”. During construction, it became evident that there were major features of the project that had not been developed in the agency issued RFP documents.
  • 17. 17 As the project progressed…. Consider this: Even in “design|build” there is some portion of the schedule when you have to “design”. During construction, it became evident that there were major features of the project that had not been developed in the agency issued RFP documents. BUT the need to address them and any project constraints were. (and there were some new approaches)
  • 18. So what are the issues here?
  • 19. The “Standard of Care” • …[to] "exercise the average degree of skill, care, and diligence exercised by members of the same profession (or specialty within that profession), practicing in the same or a similar locality in light of the present state of the profession" • (Gillette v. Tucker). See Black's Law Dictionary, 6th edition. 1404-5.
  • 20. 20 What was the designer hired to do? Provide professional design services (both Pre & Post-bid) … • …to assist in submitting the bid; • …to insure that design satisfied client design standards; • …to insure the design facilitates the submission a competitive bid; • …to provide customized quantity calculations; • …to provide engineering staff as required thru construction; • …to provide other Construction Phase Services • …to cooperate with contractor in a manner consistent with good design practice.
  • 22. 22 …and as the project progressed remember …even in “design|build” there is some portion of the schedule when you have to “design”. The designer “designs” and issues drawings to the contractor (his client). However the delivery pace of these IFC documents made it hard to “see” the escalating “scope creep” that was developing drawing by drawing. Until the “bid design” didn’t look like the “construction design”
  • 23. Key along the trail of the bidding period: The Designer alerted Contractor to the potential issue AND the Contractor asked for guidanceinput from the Designer AND the Bid Due date was extended.
  • 24. The “Standard of Care” What (or which) is the applicable and/or prevailing standard of care?
  • 25. The “Standard of Care” What (or which) is the applicable and/or prevailing standard of care? • For the Proposal documents? • For interpreting those documents?
  • 26. Is the contractor entitled to ‘reasonably rely upon’ the materials prepared by the designer? (even if the designer works for the contractor?)
  • 27. The “Standard of Care” What (or which) is the applicable and/or prevailing standard of care? • For the Proposal documents? • For quantities in the take off? • For interpreting those documents? • For pricing the work associated with those quantities?
  • 28. Is the contractor entitled to ‘reasonably rely upon’ the materials prepared by the designer? (even if the designer works for him?) Is the traditional design ‘absolution’ from “means and methods” appropriate?
  • 29. Is the contractor entitled to ‘reasonably rely upon’ the materials prepared by the designer? (even if the designer works for him?) Is the traditional design “absolution’ from “means and methods” appropriate? Is it significant that the designer was compensated for the pre-bid work (along with any work performed after award)? They received fees for service. No profit or loss sharing agreement.
  • 30. The “Standard of Care” • …[to] "exercise the average degree of skill, care, and diligence exercised by members of the same profession (or specialty within that profession), practicing in the same or a similar locality in light of the present state of the profession" • (Gillette v. Tucker). See Black's Law Dictionary, 6th edition. 1404-5.
  • 31. It wasn’t me! Everybody had plausible deniability… • The agency said, “It is a Design-Build contract and we are not accepting change orders.”
  • 32. It wasn’t me! Everybody had plausible deniability… • The agency said, “It is a Design-Build contract and we are not accepting change orders.” • The designer said, “The changes are minor in nature and within the ‘margin of reasonableness’ (Standard-of-Care) for any project. We are not responsible for ‘means and methods’, plus we warned of risks.”
  • 33. It wasn’t me! Everybody had plausible deniability… • The agency said, “It is a Design-Build contract and we are not accepting change orders.” • The designer said, “The changes are minor in nature and within the ‘margin of reasonableness’ (Standard-of-Care) for any project. We are not responsible for ‘means and methods’, plus we warned of risks.” • The contractor said, “These cost overruns accumulated and not till the end of the drawing issues did we see the problem and determine the final installed quantities and related costs.”
  • 34. Some Questions • Does Design-Build Delivery create new “means and methods” responsibilities for designers where they would not exist in traditional DBB delivery situations?
  • 35. Some Questions • Does Design-Build Delivery create new “means and methods” responsibilities for designers where they would not exist in traditional DBB delivery situations? • Does Design-Build Delivery require new awareness on the part of contractors to the iterative and uncertain world of conceptual design?
  • 36. Things to Consider: How precise should you make your bridgingbidding documents? Is it possible that you could unwittingly create an ‘impossibility” defense (or a massive change order) if you ask for …the impossible?
  • 37. Things to Consider: How precise should you make your bridgingbidding documents? Is it possible that you could unwittingly create an ‘impossibility” defense if you ask for …the impossible? To what extent can the design-build team ‘reasonably rely upon’ any design elements or spatial project constraints set forth by the RFP? If those constraints are wrong, who bears the responsibility to “correct” the eventual problem.
  • 38. Things to Consider: How precise should you make your bridgingbidding documents? Is it possible that you could unwittingly create an ‘impossibility” defense if you ask for …the impossible? To what extent can the design-build team ‘reasonably rely upon’ any design elements or spatial project constraints set forth by the RFP? If those constraints are wrong, who bears the responsibility to “correct” the eventual problem. If you go into a “project specific” design-build should you set up appropriate incentives (and penalties?) to properly align the team members’ interests? Develop special clauses concerning design and estimating liability?
  • 40. The designer had worked for the owner before (but in design-bid-build arrangements). The advantage of that prior experience prompted the contractor to select them. Is it possible that the designer wasn’t really that ‘enthused’ about the arrangement? He certainly wouldn’t want the owner to be unsatisfied, but… Would he be concerned about the financial position of the contractor? (As concerned as the contractor?) Traditional “client focus” for designers is the owner. Licensure stresses the public safety and welfare. In a ‘sub-contract’ arrangement to a contractor, the paying client has changed, but does that change the licensure focus on “public safety and welfare”?
  • 41. So what do we learn?
  • 42. Those whose paths are not the sameThose whose paths are not the sameThose whose paths are not the sameThose whose paths are not the same do not consult one another.do not consult one another.do not consult one another.do not consult one another. ConfuciusConfuciusConfuciusConfucius
  • 43. Questions? Thank you!Thank you!Thank you!Thank you! E. Mitchell Swann P.E., LEED AP, F.CIBSE, C.Eng Principal - MDCSystems® swann@mdcsystems.com www.MDCSystems.com
  • 44. MDCSystems® Summary of Services Program & Project Development including… • Performance Assessment & Benchmarking Project Modeling including… • “What if…” Scenario Analyses • Variability/Sensitivity Analyses • ‘Out of Bounds’/”Go – No Go” Limits Project Planning including… • Feasibility Studies • Master Scheduling including… – Resource & Constraint Analysis Project Monitoring including… • Schedule Compliance • Cash Flow & “Burn rate” projections • Resource Utilization Consulting Services including… • Sustainability/Green Buildings • Peer Review • Practice Management Forensic Analyses including: • Building Systems: – Architectural incl. Building Envelope – HVAC/Mechanical, Electrical & Piping – Structural – Instrumentation & Controls • Design Errors & Omissions (Standard of Care) • Differing Site Conditions Forensic Project Management® • Schedule Analysis – Delay, Disruption, Suspension & Acceleration • Labor Productivity & Inefficiency • Scope Definition and Change • Termination - Default or Convenience • Procurement - Bid/Award Transparency Forensic Accounting including… • Valuation of Damages – Overhead & General Conditions • Business Interruption & Lost Profit
  • 45. MDCSystems® Providing Expert Project Delivery Solutions Worldwide MDC Systems is a project and construction management consultancy with over 40 years of experience serving a wide array of clients and industries both nationally and around the globe. MDC has worked on projects as diverse as residential property developments to pharmaceutical plants to highway excavation and construction. MDC concentrates its services in primarily four areas: program management, project management consulting, forensic engineering and construction claims consulting. One of the key facets of MDC’s professional staff is our expertise in the technology driven issues that are so frequently at the heart of today’s complex projects. MDC’s construction claims consulting practice combines all of the skills inherent to our other service offerings and deploys it for our clients when and where projects don’t go quite as smoothly as everyone had hoped. MDC is an industry leader in the area of construction schedule development and analysis including delay, acceleration, interruption and extended duration. MDC pioneered the court tested and approved Time Impact Analysis methodology for scientifically analyzing construction schedules and the impact of events upon their execution and completion. www.MDCSystems.com
  • 46. Selected Recent Assignments Engineering Consulting and Technical Analyses: • Analysis of Moisture Migration and RH Control in a Microelectronics Product R&D Facility (Colorado). • Analysis and Improvement of Energy Consumption at a “Green” School (Pennsylvania) • Peer Review & Design Supervision for a Radiant Heating/Cooling Floor System (New Jersey) • Peer Review of Schematic Engineering Design Effort for Hospital Complex (Qatar) • Analysis of Formaldehyde Outgassing from Construction Materials (Pennsylvania) • HVAC System Failures in Pharmaceutical Packaging Facility (New Jersey) • Analysis of Process Technology Failure at Waste Treatment Plant (New Jersey) • Analysis of Piping System Joint Failures at a Hospital central Plant (New Jersey) • Assessment and Analyses of Energy Future Options for Major Municipality Project Management, Execution & Construction Claims : • Excess Rock Excavation Claim on a Highway Project - Unforeseen Conditions (New Jersey) • Electrical Contractor Inefficiency Claim on Multi- Prime Project (New Jersey) • Electrical Usage Charge Dispute Between Landlord & Tenant (New York) • Schedule Delays and Change Orders on multiple Airport Projects for Major Equipment Supplier (various) • Schedule Delays and Associated Cost Overruns for Underwater Pipeline Project (Ireland) • “Standard of Care” Defense - Design of a Food Processing Facility (Pennsylvania) • “Standard of Care” Defense – Design and Documentation of a Pharmaceutical Plant using 3D Modeling (Texas) • “Standard of Care” Plaintiff – Delay and Cost Overruns for a Pharmaceutical Plant using 3D Modeling (Singapore) • Analysis of Destructive VibrationHarmonics on Large Industrial Compressors at a Chemical Plant (Louisiana)