SlideShare ist ein Scribd-Unternehmen logo
1 von 4
Page 1 of 4
RICHARD EDWARDS ID NO: 540929 5140 089
DETAILED WORK HISTORY :
TELEPHONE ELECTRICIAN: 1972 –1974 :
SA POST OFFICE,DURBAN CENTRAL KZN
Customerfaults on telephones and Switchboards
The Faultsman task included fault finding in all disciplines,ie,
Underground cables, Overhead cables,IndoorExchanges and
Subscriberfaults.
CHIEF ARTISAN : 1976 – 1985 :
SIEMENS,DURBAN KZN
In charge of +/- 20 staff doing alterations and testing of Railway
Signalling Equipment
Started with Siemens in Bayhead in Durban as an Installation Artisan.
Installed Points Machines, Signal Tracks and AssociatedCabling.
I moved to the Unit Sectionwhere the function was to take Engineers
modifications and change the wiring in the Points or Signal Unit
accordingly.
I was promoted to Operating the TestMachines which simulated the
function of each unit. The Test Machine had to be programmed with
each modificationso a very good understanding of each units’ function
was crucial.
The Signalling System used at Bayhead was the Siemens Spoorplan
MKII and was modified forLocal Shunting Yards by Mr Hans Doll of
Siemens.
I first assisted Hans with Testing and Commissioning in Bayhead and he
was considered as the Authority on Spoorplanin South Africa. It was a
great honour to learn from him and I feelhis passion of Interlocking,
high work ethics and commitmentto deadlines (occupation dates)
influenced my passion in Railway Signalling.
Page 2 of 4
It was at this time that Siemens selectedonly Two Artisans to be trained
in Commissioning and as One of them I was sent to the EsselenPark,
Railway College forTraining.
I was then sent to Vryheid to Head the Unit Department with
modifications of the MK1 Units used on the Coal Line Project. This also
included the assisting of Commissioning the completeLine from Vryheid
to Richards Bay. At Vryheid we also commissioned the AC/DC Yard
where the Train Type was changed over from AC to DC.
I was also involved in fault finding of the Data TransmissionSystem
(Westronic)used to transmit Data, Track information, Points and Signal
information from Small Relay Rooms back to the CTC in Vryheid.
At the end of this Project I was sent to the New Durban Station
(Spoorplan MKM) I was stationed at the Relay Room (Berea Road)
where I tested Indoor and Outdoor Equipment.
At this time I also attended Natal Technikon to do a National Diploma in
Electrical Engineering part time.
COMMISSIONING ENGINEER: 1985 – 1986
SIEMENS,CAPE TOWN
Commissioning of complete Railway Signalling Installation from Elsies
River to Woodstock.
In Cape Town I arrived at the beginning of the Installation of the Elsies
River Relay Room. I was working with the Installation Foreman advising
them of what was required first, eg staring with the Power Room,Static
Inverters, Battery Room to enable us to start the Charging Procedure of
the Batteries.
In the Relay Room we also started installing the Unit Racks and Cabling
while our outside team was busy installing Trackside Equipment.
We had Junior Technicians make up a TestDesk with Buttons, Route
Indicators,Tracks and Signals so the whole System could be tested
before switching over to CTC.
I worked closelywith the Railway Engineer and just before Occupation
date Hans Doll came down to check that I had commissioned everything
to Siemens standard. This was also a New System being a Railways
Page 3 of 4
Designthe MK1C and Hans assisted us with the Block Designand
Commissioning.
SENIOR PROJECT ENGINEER: 1987 - 1992
SIEMENS,JOHANNESBURG, GAUTENG
Running of R10 million Road Traffic Projects and assisting Junior staff
with smaller projects.
At the end of the Cape Town ProjectI was sent to Head Office where I
assisted with Commissioning of Traffic Light Systems and Fire Detection
Systems.
I was then moved to the Sales and Projecting division where I was
instrumental in building up the Traffic Light Department and securing Big
Projects.
The first big Projectwas the Randburg projectwhere we installed all new
Traffic Controllers (+/- 500) and linked them with a Unique Cabling
System laid in the roadside back to a Control Room with a Mimic Panel
of the whole town. The first Traffic Light Control Room in South Africa.
MANAGING DIRECTOR: 1992 - 2007
EDCOMPTRAFFIC LIGHT SYSTEMS
Director of company installing Traffic Light Intersections for
Johannesburg Roads Agencyand other Municipalities in South Africa
eg. Lesotho,Nelspruit, and Beaufort West.
I left the Corporate world of Siemens after seventeenyears to start my
own Company with Traffic Lights and secured Maintenance Contracts
with Johannesburg Roads Agency.
I also ran a Projectin Pretoria for Plesseywhere we changed all Traffic
Light Controllers (+/- 900)and connected them back via a Telkom Line
Data Transmissionto a Control Room.
Page 4 of 4
MANAGING DIRECTOR: 2007 – 2010
BANOCKBURN MANAGEMENT PTY LTD
Formed new BEE company in accordance with Government
requirements. Installed new Traffic Light Systems and Electrical
Reticulation in Complexes and new houses.
Installation of Traffic Light Controllers for Johannesburg Roads Agency
and upgrading of old Installations (+/- 1000)linking via Radio Link and
Dial up Cell Phone link was tried to Central Control Room in
Johannesburg.
Vandals were stealing the Sim Cards so all Controller Boxes were
changed to Vandal Proof Boxes.
Closed Companydue to disagreementwith BEE partner.
OWNER INSTALLATIONELECTRICIAN : 2010 - 2013
EDCOMPELECTRICAL SERVICES
Installation Electrician (Single and Three Phase) for New House,
Complexand Industrial Wiring and Reticulation.
Currently doing small Electrical jobs (Certificate of Compliance)for
houses and complexes.
CHIEF OPERATIONS OFFICER: NOVEMBER2013 – DECEMBER
2014
AFRICAN ROAD & RAIL ENGINEERING (PTY)LTD
Operations control of Electrical Division, Under Road Drilling Division,
Traffic Light Division and Railway Signalling Division.
Project Management of projects in all divisions.
Health and Safety Representative , attending Site meetings.
Marketing and Quotations for Tenders for all divisions.
Company closed and relocated to Cape Town.

Weitere ähnliche Inhalte

Was ist angesagt? (19)

NAZEER AHMED GAAD (1)(1)
NAZEER AHMED GAAD (1)(1)NAZEER AHMED GAAD (1)(1)
NAZEER AHMED GAAD (1)(1)
 
Resume 02
Resume 02Resume 02
Resume 02
 
6614b46b-cd0e-473d-b581-67a2d2af21e7 (1)
6614b46b-cd0e-473d-b581-67a2d2af21e7 (1)6614b46b-cd0e-473d-b581-67a2d2af21e7 (1)
6614b46b-cd0e-473d-b581-67a2d2af21e7 (1)
 
Irfan Ashraf CV
Irfan Ashraf CVIrfan Ashraf CV
Irfan Ashraf CV
 
ELECTRICAL TECHNICIAN
ELECTRICAL TECHNICIANELECTRICAL TECHNICIAN
ELECTRICAL TECHNICIAN
 
GERARDO A. QUIZON CV
GERARDO A. QUIZON CVGERARDO A. QUIZON CV
GERARDO A. QUIZON CV
 
arun kumar
arun kumararun kumar
arun kumar
 
Abbas fadhil resume
Abbas fadhil resumeAbbas fadhil resume
Abbas fadhil resume
 
MAZHAR NEW CV with Huawei,ZTE,LCC KSA 3G
MAZHAR NEW CV with Huawei,ZTE,LCC KSA 3GMAZHAR NEW CV with Huawei,ZTE,LCC KSA 3G
MAZHAR NEW CV with Huawei,ZTE,LCC KSA 3G
 
MEP engineer CV
MEP engineer CV MEP engineer CV
MEP engineer CV
 
Neil Todd CV
Neil Todd CVNeil Todd CV
Neil Todd CV
 
AirX Capability Statement 2016
AirX Capability Statement  2016AirX Capability Statement  2016
AirX Capability Statement 2016
 
Transmission_Profile_swatantra tripathi
Transmission_Profile_swatantra tripathiTransmission_Profile_swatantra tripathi
Transmission_Profile_swatantra tripathi
 
MAHMOUD CV
MAHMOUD CVMAHMOUD CV
MAHMOUD CV
 
internship report 2012 (Propel Network Sdn.Bhd)
internship report 2012 (Propel Network Sdn.Bhd)internship report 2012 (Propel Network Sdn.Bhd)
internship report 2012 (Propel Network Sdn.Bhd)
 
Adeel Ahmed- CV
Adeel Ahmed- CVAdeel Ahmed- CV
Adeel Ahmed- CV
 
MY CV
MY CVMY CV
MY CV
 
Glad CV
Glad CVGlad CV
Glad CV
 
S. Bould CV
S. Bould CV S. Bould CV
S. Bould CV
 

Ähnlich wie RICHARD EDWARDS DETAILED WORK HISTORY

Robin Adcock Resume6
Robin Adcock Resume6Robin Adcock Resume6
Robin Adcock Resume6
Robin Adcock
 
RICHARD LEMIN CV 2016
RICHARD LEMIN  CV 2016RICHARD LEMIN  CV 2016
RICHARD LEMIN CV 2016
Richard Lemin
 
Mark Simms-CV updated 08-15-16
Mark Simms-CV updated 08-15-16Mark Simms-CV updated 08-15-16
Mark Simms-CV updated 08-15-16
Mark Simms
 
CURRICULUM__VITAE_NOEL27_08_15
CURRICULUM__VITAE_NOEL27_08_15CURRICULUM__VITAE_NOEL27_08_15
CURRICULUM__VITAE_NOEL27_08_15
Noel Owens
 
Esrar Alam Transmission Engineer
Esrar Alam  Transmission EngineerEsrar Alam  Transmission Engineer
Esrar Alam Transmission Engineer
Esrar Khan
 

Ähnlich wie RICHARD EDWARDS DETAILED WORK HISTORY (20)

eltracs res
eltracs reseltracs res
eltracs res
 
Haider Ali_CV
Haider Ali_CVHaider Ali_CV
Haider Ali_CV
 
Mr johann van der westhuizen full cv.docx
Mr johann van der westhuizen full cv.docxMr johann van der westhuizen full cv.docx
Mr johann van der westhuizen full cv.docx
 
Robin Adcock Resume6
Robin Adcock Resume6Robin Adcock Resume6
Robin Adcock Resume6
 
RICHARD LEMIN CV 2016
RICHARD LEMIN  CV 2016RICHARD LEMIN  CV 2016
RICHARD LEMIN CV 2016
 
John_Buckley_CV_Dec 2016
John_Buckley_CV_Dec 2016John_Buckley_CV_Dec 2016
John_Buckley_CV_Dec 2016
 
CV Marius Short
CV Marius ShortCV Marius Short
CV Marius Short
 
CV-EN+
CV-EN+CV-EN+
CV-EN+
 
my Resume
my Resumemy Resume
my Resume
 
Receiver Module of Smart power monitoring and metering distribution system u...
Receiver Module of Smart power monitoring and metering  distribution system u...Receiver Module of Smart power monitoring and metering  distribution system u...
Receiver Module of Smart power monitoring and metering distribution system u...
 
Mark Simms-CV updated 08-15-16
Mark Simms-CV updated 08-15-16Mark Simms-CV updated 08-15-16
Mark Simms-CV updated 08-15-16
 
Domdad engineering
Domdad engineeringDomdad engineering
Domdad engineering
 
DOMDAD ENGINEERING
DOMDAD ENGINEERINGDOMDAD ENGINEERING
DOMDAD ENGINEERING
 
DOMDAD ENGINEERING
DOMDAD ENGINEERINGDOMDAD ENGINEERING
DOMDAD ENGINEERING
 
CV .Sasikumar.K.V
CV .Sasikumar.K.V CV .Sasikumar.K.V
CV .Sasikumar.K.V
 
LMCV
LMCVLMCV
LMCV
 
Nedal Nemer CV
Nedal Nemer CVNedal Nemer CV
Nedal Nemer CV
 
CV2016
CV2016CV2016
CV2016
 
CURRICULUM__VITAE_NOEL27_08_15
CURRICULUM__VITAE_NOEL27_08_15CURRICULUM__VITAE_NOEL27_08_15
CURRICULUM__VITAE_NOEL27_08_15
 
Esrar Alam Transmission Engineer
Esrar Alam  Transmission EngineerEsrar Alam  Transmission Engineer
Esrar Alam Transmission Engineer
 

RICHARD EDWARDS DETAILED WORK HISTORY

  • 1. Page 1 of 4 RICHARD EDWARDS ID NO: 540929 5140 089 DETAILED WORK HISTORY : TELEPHONE ELECTRICIAN: 1972 –1974 : SA POST OFFICE,DURBAN CENTRAL KZN Customerfaults on telephones and Switchboards The Faultsman task included fault finding in all disciplines,ie, Underground cables, Overhead cables,IndoorExchanges and Subscriberfaults. CHIEF ARTISAN : 1976 – 1985 : SIEMENS,DURBAN KZN In charge of +/- 20 staff doing alterations and testing of Railway Signalling Equipment Started with Siemens in Bayhead in Durban as an Installation Artisan. Installed Points Machines, Signal Tracks and AssociatedCabling. I moved to the Unit Sectionwhere the function was to take Engineers modifications and change the wiring in the Points or Signal Unit accordingly. I was promoted to Operating the TestMachines which simulated the function of each unit. The Test Machine had to be programmed with each modificationso a very good understanding of each units’ function was crucial. The Signalling System used at Bayhead was the Siemens Spoorplan MKII and was modified forLocal Shunting Yards by Mr Hans Doll of Siemens. I first assisted Hans with Testing and Commissioning in Bayhead and he was considered as the Authority on Spoorplanin South Africa. It was a great honour to learn from him and I feelhis passion of Interlocking, high work ethics and commitmentto deadlines (occupation dates) influenced my passion in Railway Signalling.
  • 2. Page 2 of 4 It was at this time that Siemens selectedonly Two Artisans to be trained in Commissioning and as One of them I was sent to the EsselenPark, Railway College forTraining. I was then sent to Vryheid to Head the Unit Department with modifications of the MK1 Units used on the Coal Line Project. This also included the assisting of Commissioning the completeLine from Vryheid to Richards Bay. At Vryheid we also commissioned the AC/DC Yard where the Train Type was changed over from AC to DC. I was also involved in fault finding of the Data TransmissionSystem (Westronic)used to transmit Data, Track information, Points and Signal information from Small Relay Rooms back to the CTC in Vryheid. At the end of this Project I was sent to the New Durban Station (Spoorplan MKM) I was stationed at the Relay Room (Berea Road) where I tested Indoor and Outdoor Equipment. At this time I also attended Natal Technikon to do a National Diploma in Electrical Engineering part time. COMMISSIONING ENGINEER: 1985 – 1986 SIEMENS,CAPE TOWN Commissioning of complete Railway Signalling Installation from Elsies River to Woodstock. In Cape Town I arrived at the beginning of the Installation of the Elsies River Relay Room. I was working with the Installation Foreman advising them of what was required first, eg staring with the Power Room,Static Inverters, Battery Room to enable us to start the Charging Procedure of the Batteries. In the Relay Room we also started installing the Unit Racks and Cabling while our outside team was busy installing Trackside Equipment. We had Junior Technicians make up a TestDesk with Buttons, Route Indicators,Tracks and Signals so the whole System could be tested before switching over to CTC. I worked closelywith the Railway Engineer and just before Occupation date Hans Doll came down to check that I had commissioned everything to Siemens standard. This was also a New System being a Railways
  • 3. Page 3 of 4 Designthe MK1C and Hans assisted us with the Block Designand Commissioning. SENIOR PROJECT ENGINEER: 1987 - 1992 SIEMENS,JOHANNESBURG, GAUTENG Running of R10 million Road Traffic Projects and assisting Junior staff with smaller projects. At the end of the Cape Town ProjectI was sent to Head Office where I assisted with Commissioning of Traffic Light Systems and Fire Detection Systems. I was then moved to the Sales and Projecting division where I was instrumental in building up the Traffic Light Department and securing Big Projects. The first big Projectwas the Randburg projectwhere we installed all new Traffic Controllers (+/- 500) and linked them with a Unique Cabling System laid in the roadside back to a Control Room with a Mimic Panel of the whole town. The first Traffic Light Control Room in South Africa. MANAGING DIRECTOR: 1992 - 2007 EDCOMPTRAFFIC LIGHT SYSTEMS Director of company installing Traffic Light Intersections for Johannesburg Roads Agencyand other Municipalities in South Africa eg. Lesotho,Nelspruit, and Beaufort West. I left the Corporate world of Siemens after seventeenyears to start my own Company with Traffic Lights and secured Maintenance Contracts with Johannesburg Roads Agency. I also ran a Projectin Pretoria for Plesseywhere we changed all Traffic Light Controllers (+/- 900)and connected them back via a Telkom Line Data Transmissionto a Control Room.
  • 4. Page 4 of 4 MANAGING DIRECTOR: 2007 – 2010 BANOCKBURN MANAGEMENT PTY LTD Formed new BEE company in accordance with Government requirements. Installed new Traffic Light Systems and Electrical Reticulation in Complexes and new houses. Installation of Traffic Light Controllers for Johannesburg Roads Agency and upgrading of old Installations (+/- 1000)linking via Radio Link and Dial up Cell Phone link was tried to Central Control Room in Johannesburg. Vandals were stealing the Sim Cards so all Controller Boxes were changed to Vandal Proof Boxes. Closed Companydue to disagreementwith BEE partner. OWNER INSTALLATIONELECTRICIAN : 2010 - 2013 EDCOMPELECTRICAL SERVICES Installation Electrician (Single and Three Phase) for New House, Complexand Industrial Wiring and Reticulation. Currently doing small Electrical jobs (Certificate of Compliance)for houses and complexes. CHIEF OPERATIONS OFFICER: NOVEMBER2013 – DECEMBER 2014 AFRICAN ROAD & RAIL ENGINEERING (PTY)LTD Operations control of Electrical Division, Under Road Drilling Division, Traffic Light Division and Railway Signalling Division. Project Management of projects in all divisions. Health and Safety Representative , attending Site meetings. Marketing and Quotations for Tenders for all divisions. Company closed and relocated to Cape Town.