WBM Roads 
Definition: The pavement base course made of 
crushed or broken aggregates mechanically 
interlocked by rolling and voids filled by screening 
and binding material with the assistance of water
Salient Features of WBM Roads 
• WBM means Water Bound Macadam. 
• The word Macadam comes from the name of 
Scottish Engineer John L. Macadam. 
• Wearing surface is formed by cleaned, 
crushed aggregates which are spread and 
rolled by sprinkling water.
Salient Features of WBM Roads 
• Low cost 
• Thickness range: 8cm to 30 cm 
• Camber : 2.5% to 3% OR 1:36 to 1:48 
• Surface is better than earthen road but rough 
as compared to bituminous or Concrete roads 
• Can be used as Base Course for Bituminous or 
Concrete roads.
Materials to be used in WBM roads 
• Crushed trap rock – Most Suitable 
• Crushed slag 
• Burnt Brick bats 
• Kankar Aggregate 
• Laterite 
• Screenings to be used as filler material
IRC Recommendations for Course 
Aggregate Grading for WBM Roads 
Grading No Size Range (mm) Sieve Size (mm) % Passing the sieve by 
weight 
1 
2 
3 
90 to 40 
63-40 
50-20 
100 
80 
63 
40 
20 
83 
63 
50 
40 
20 
63 
50 
40 
20 
100 
65-85 
25-60 
0-15 
0-5 
100 
90-100 
30-70 
0-15 
0-5 
100 
95-100 
35-70 
0-10
IRC Recommendations for Grading of 
Screenings 
Classification 
Grading 
Size of Screenings 
mm 
Sieve size 
mm 
% by weight 
passing the sieve 
A 
B 
12.5 
10.0 
12.5 
10.0 
4.75 
0.15 
10.0 
4.75 
0.15 
100 
90-100 
10-30 
0-8 
100 
85-100 
10-30
Construction Procedure of WBM 
Roads 
• 1. Preparation of Sub Grade 
• 2. Preparation of Base Course 
• 3. Intermediate Layer 
• 4. Wearing Surface 
• 5. Shoulders 
Shoulder Wearing Course Shoulder 
Intermediate Course 
Base Course 
Sub Grade
Precautions in Rolling WBM Roads 
• Roller to be used- 8-10 Tonnes 
• Rolling should be done from edges to the centre 
• The successive rolling strips should be overlapped 
• Length of each rolling should be <=200m. 
• Water should be sprinkled and not poured by 
buckets 
• The rolling should be done for 80 passes or until 
the aggregates are broken.

Weitere ähnliche Inhalte

Was ist angesagt?

Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
HARITSEHRAWAT
 

Was ist angesagt? (20)

Highway Materials Unit-III
Highway Materials  Unit-IIIHighway Materials  Unit-III
Highway Materials Unit-III
 
Flexible and-rigid-pavements
Flexible and-rigid-pavementsFlexible and-rigid-pavements
Flexible and-rigid-pavements
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
 
Rigid pavements
Rigid pavements Rigid pavements
Rigid pavements
 
Highway Cross-sectional Elements
Highway Cross-sectional ElementsHighway Cross-sectional Elements
Highway Cross-sectional Elements
 
Pavement design
Pavement designPavement design
Pavement design
 
Pavement
PavementPavement
Pavement
 
Aggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limitsAggregate - coarse aggregates, testing & limits
Aggregate - coarse aggregates, testing & limits
 
Ground Improvement Techniques
Ground Improvement TechniquesGround Improvement Techniques
Ground Improvement Techniques
 
Pavement Materials Bitumen
Pavement Materials  BitumenPavement Materials  Bitumen
Pavement Materials Bitumen
 
Compaction of concrete
Compaction of concreteCompaction of concrete
Compaction of concrete
 
Failures in rigid pavement
Failures in rigid pavementFailures in rigid pavement
Failures in rigid pavement
 
Sinking of well foundation
Sinking of well foundationSinking of well foundation
Sinking of well foundation
 
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)Permanent Way of Railway & Components ?(part -1,2,3,4,5)
Permanent Way of Railway & Components ?(part -1,2,3,4,5)
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavement
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - I
 
Highway failure and their maintenance
Highway failure and their maintenanceHighway failure and their maintenance
Highway failure and their maintenance
 
Test On Bitumen
Test On BitumenTest On Bitumen
Test On Bitumen
 

Ähnlich wie 4. wbm roads 10 sep

Your Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docxYour Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docx
odiliagilby
 

Ähnlich wie 4. wbm roads 10 sep (20)

Road construction pavements flexible rigid
Road construction pavements flexible rigidRoad construction pavements flexible rigid
Road construction pavements flexible rigid
 
CONSTRUCTION OF ROADS
CONSTRUCTION OF ROADSCONSTRUCTION OF ROADS
CONSTRUCTION OF ROADS
 
Cc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumarCc road summer training ppt @akshay kumar
Cc road summer training ppt @akshay kumar
 
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
ESTIMATE THE CONSTRUCTION PROCEDURE OF WATER-BOUND MACADAM ROAD
 
Presentation of 5_weeks_summer_training_,dept
Presentation of 5_weeks_summer_training_,deptPresentation of 5_weeks_summer_training_,dept
Presentation of 5_weeks_summer_training_,dept
 
self-compacting concrete
self-compacting concrete self-compacting concrete
self-compacting concrete
 
Dense Bituminous macadam
Dense Bituminous macadamDense Bituminous macadam
Dense Bituminous macadam
 
crri_csir_odisha new tech JULY 2022.pptx
crri_csir_odisha new tech JULY 2022.pptxcrri_csir_odisha new tech JULY 2022.pptx
crri_csir_odisha new tech JULY 2022.pptx
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)
 
Asphaltic concrete pavement.
Asphaltic concrete pavement. Asphaltic concrete pavement.
Asphaltic concrete pavement.
 
Road, Culvert & Bridge Training
Road, Culvert & Bridge TrainingRoad, Culvert & Bridge Training
Road, Culvert & Bridge Training
 
Box pushing technic PPT SEMINAR
Box pushing technic  PPT  SEMINARBox pushing technic  PPT  SEMINAR
Box pushing technic PPT SEMINAR
 
Maintenance of unsurfaced roads, wbm roads
Maintenance of unsurfaced roads, wbm roadsMaintenance of unsurfaced roads, wbm roads
Maintenance of unsurfaced roads, wbm roads
 
Mord specifications for low volume roads
Mord specifications for low volume roadsMord specifications for low volume roads
Mord specifications for low volume roads
 
Ntpc summer training 2017
Ntpc summer training 2017Ntpc summer training 2017
Ntpc summer training 2017
 
Requirements of pdo sp 1279 &amp; 1282
Requirements of pdo sp 1279 &amp; 1282Requirements of pdo sp 1279 &amp; 1282
Requirements of pdo sp 1279 &amp; 1282
 
Road construction
Road constructionRoad construction
Road construction
 
Concrete- types, testing & properties
Concrete- types, testing & propertiesConcrete- types, testing & properties
Concrete- types, testing & properties
 
Your Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docxYour Score 1420Not bad. Your score means youre slightly bette.docx
Your Score 1420Not bad. Your score means youre slightly bette.docx
 
CBR.ppt
CBR.pptCBR.ppt
CBR.ppt
 

Kürzlich hochgeladen

"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Kürzlich hochgeladen (20)

AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
Jaipur ❤CALL GIRL 0000000000❤CALL GIRLS IN Jaipur ESCORT SERVICE❤CALL GIRL IN...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 

4. wbm roads 10 sep

  • 1. WBM Roads Definition: The pavement base course made of crushed or broken aggregates mechanically interlocked by rolling and voids filled by screening and binding material with the assistance of water
  • 2. Salient Features of WBM Roads • WBM means Water Bound Macadam. • The word Macadam comes from the name of Scottish Engineer John L. Macadam. • Wearing surface is formed by cleaned, crushed aggregates which are spread and rolled by sprinkling water.
  • 3. Salient Features of WBM Roads • Low cost • Thickness range: 8cm to 30 cm • Camber : 2.5% to 3% OR 1:36 to 1:48 • Surface is better than earthen road but rough as compared to bituminous or Concrete roads • Can be used as Base Course for Bituminous or Concrete roads.
  • 4. Materials to be used in WBM roads • Crushed trap rock – Most Suitable • Crushed slag • Burnt Brick bats • Kankar Aggregate • Laterite • Screenings to be used as filler material
  • 5. IRC Recommendations for Course Aggregate Grading for WBM Roads Grading No Size Range (mm) Sieve Size (mm) % Passing the sieve by weight 1 2 3 90 to 40 63-40 50-20 100 80 63 40 20 83 63 50 40 20 63 50 40 20 100 65-85 25-60 0-15 0-5 100 90-100 30-70 0-15 0-5 100 95-100 35-70 0-10
  • 6. IRC Recommendations for Grading of Screenings Classification Grading Size of Screenings mm Sieve size mm % by weight passing the sieve A B 12.5 10.0 12.5 10.0 4.75 0.15 10.0 4.75 0.15 100 90-100 10-30 0-8 100 85-100 10-30
  • 7. Construction Procedure of WBM Roads • 1. Preparation of Sub Grade • 2. Preparation of Base Course • 3. Intermediate Layer • 4. Wearing Surface • 5. Shoulders Shoulder Wearing Course Shoulder Intermediate Course Base Course Sub Grade
  • 8. Precautions in Rolling WBM Roads • Roller to be used- 8-10 Tonnes • Rolling should be done from edges to the centre • The successive rolling strips should be overlapped • Length of each rolling should be <=200m. • Water should be sprinkled and not poured by buckets • The rolling should be done for 80 passes or until the aggregates are broken.