JACK NEIFT TRUCKING CO.
Project Plan Presented: Pay Load
JUNE 1, 2016
TEAM MUSK:
Logan Rogers, Anirudh Mathur, Prachi Dikshit, Darshana Shetty
Project Integration & Risk Management
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
1
INDEX
S. No. Contents Page No.
1. PROJECT CHARTER 2
2. PROJECT SCOPE STATEMENT 4
3. (a) WORK BREAKDOWN STRUCTURE 6
(b) WORK BREAKDOW PACKAGE 7
4. NETWORK DIAGRAM 8
5. QUALITATIVE RISK ANALYSIS 9
6. (a) QUANTITATIVE RISK ANALYSIS 11
(b) PERT ANALYSIS - SCHEDULE 12
PERT ANALYSIS – COST 16
7. RISK RESPONSE
PLAN # 1 19
PLAN # 2 20
PLAN # 3 21
8. (a) COST RESERVE ANALYSIS 22
(b) SCHEDULE RESERVE ANALYSIS 24
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
2
Project Name: Pay Load
Prepared by: Team MUSK
Date: 4/14/16
Purpose/Business Need:
Reduce deadheading by 75% for Jack Neift Trucking Company.
Product Description:
A web-based software system that quickly brings shipping information, unloading schedules, and truck
routes to all major departments to promote efficient planning and sales techniques that leads to
reduction in deadheading.
Success Criteria:
Reduce deadheading by 75%, and achieve 30% ROI for Team MUSK, and release the software system
within 26 weeks of starting the project.
Project Priorities:
1. Scope – A web-based software system with GPS tracking and scheduling wizard.
2. Schedule – Project should be complete within 6 months.
3. Cost – Estimated cost of project is $850,000 but not to exceed $875,000.
Assumptions:
1. Sales force is able to locate clients and make shipment sales for return routes.
2. Clients publish loading/unloading schedules.
3. All hardware and software 3rd party systems work as expected.
Constraints:
1. Comply with state regulations for the man-hours of the truckers.
2. Sales team and dispatchers working hours between 9am and 5pm (eastern)
Risks:
1. Network crashes could cripple the system for unknown periods of time.
2. Being an in-house system may face critical operational issues that may increase the cost of
project.
3. New system may not be intuitive from usability standpoint and may require additional training
and time for it to be effective.
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
3
Milestones Schedule: (based on working days)
1. Project plan approval – 3 weeks from start of project
2. Core system implemented – 10 weeks from start of project
3. Beta version released – 16 weeks from start of project
4. Beta testing completed – 19 weeks from start of project
5. User testing completed – 21 weeks from start of project
6. Revised version released – 23 weeks from start of project
7. Employee training completed – 24 weeks from start of project
8. System launch – 25 weeks from start of project
9. Project Closing – 26 weeks from start of project
Other:
1. This project will enable Jack Neift Trucking Company to be a modern trucking company in this
competitive market.
2. The technology developed in this project could be a game changer for the entire trucking
industry.
Approvals:
Sponsor: Bea Stoveburden Date: 4/13/2016
Project Manager: Sal Vatation Date: 4/13/2016
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
4
Project Name: Pay Load
Project Manager: Sal Vatation
Prepared by: Team Musk Date: 4/16/2016
Approved by: Bea Stoveburden Date: 4/16/2016
Project Objectives:
 Scope – A web-based software system which will have GPS to tracking and also this will help us in
reducing deadheading.
 Schedule – Project time to complete this project is 26 weeks.
 Cost – Estimated cost for this project shall not exceed $875,000.
Product Scope Description:
This project will produce a software system which will help the company to reduce deadheading by
roughly 75%. It will aid Jack Neift Trucking Company in tracking the truck routes to make efficient travel
plans for their clients' drop-offs and deliveries. This Software will also monitor the truckers' driving time
and will trigger alerts if the driving time approaches the limits set by the Federal Motor Carrier Safety
Administration.
Project Deliverables:
 Project Plan
 GPS Unit
 Server
 Software
 User manuals
 State regulation documents
 GPS software design documents
 Testing reports
 Software User Training
Project Boundaries:
 The project will only include one-time training for employees, no training after that if any new
employee joins the company.
 Software is one-time design won’t allow you to add features once it is launched.
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
5
Product Acceptance Criteria:
 Project plan should be reviewed and accepted by the Project Sponsor.
 Jack Neift Trucking Company needs to send their Quality testing person to do the quality check
for the software before installing them.
 After completion of the testing of GPS units and software the project should be accepted by the
project head.
 75% reduction in deadheading and 30% ROI for Team Musk.
Project Constraints:
 Comply with federal regulations for the man-hours of the truckers.
 Sales team and dispatchers working hours between 9am and 5pm (eastern)
 Due to existing relationship between JNTC and Elon Tracking, only tracking devices from Elon
Tracking may be used.
Project Assumptions:
 Sales force is able to locate clients and make shipment sales for return routes.
 Clients publish loading/unloading schedules.
 All hardware and software 3rd party systems work as expected.
Approval Requirements:
 Project Sponsor: Bea Stoveburden
 Project Manager: Sal Vatation
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
6
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
7
Work Package (WBS#) WP#
Duration Estimate - Days Cost Estimate ($K)
Optimistic
Most
Likely
Pessimistic Optimistic
Most
Likely
Pessimistic
Project Plan 1.1.1 2 3 6 47.5 50 60
Schedule 1.1.2 3 5 10 14.25 15 18
Budget 1.1.3 3 5 10 19 20 24
Communication Plan &
Reporting
1.1.4 2 3 6 9.5 10 12
Dev Tasks listed in Project Plan 1.2.1 13 20 30 190 200 240
Integration with 3rd party
software
1.2.2 6 10 15 47.5 50 60
Integration Testing 1.2.3 6 10 20 47.5 50 60
Write Test Cases 1.2.4 9 15 30 95 100 120
Validate the system 1.3.1 6 10 20 71.25 75 90
Defect Management 1.3.2 6 10 20 23.75 25 30
Server Installation and Testing 1.3.3 6 10 20 95 100 120
Write Training documentation 1.4.1 3 5 10 23.75 25 30
Run UAT sessions 1.4.2 3 5 10 23.75 25 30
Receive and resolve UAT
incidents
1.4.3 3 5 10 57 60 72
Comply with Federal
Regulations
1.4.4 2 3 6 14.25 15 18
Create, review and approve
deployment strategy
1.5.1 2 3 6 19 20 24
Ensure successful
release/deployment
1.5.2 2 3 6 9.5 10 12
Receive signoff from the JNT
Board
1.5.3 1 2 4 4.75 5 6
Start using the new application 1.5.4 1 1 2 9.5 10 12
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
8
1.1.2 3
11-Apr 13-Apr 1.2.1 13 1.2.3 6 1.2.4 9 1.3.1 6
14-Apr 18-Apr 27-Apr 4-May 5-May 17-May 18-May 25-May
1.1.1 2 1.1.3 3
6-Apr 8-Apr 11-Apr 13-Apr
1.1.4 2 1.2.2 6
11-Apr 12-Apr 19-Apr 26-Apr
1.4.4 2 1.4.3 3 1.4.2 3 1.4.1 3 1.3.2 6
16-Jun 20-Jun 13-Jun 15-Jun 8-Jun 10-Jun 3-Jun 7-Jun 26-May 2-Jun
1.5.2 2
21-Jun 23-Jun
1.5.1 2 1.3.3 6
3-Jun 6-Jun 26-May 2-Jun
1.5.3 1 1.5.4 1
24-Jun 24-Jun 25-Jun 25-Jun
Schedule
DevTaskslisted in Project
Plan
Integration Testing WriteTestCases Validatethesystem
ProjectPlan Budget
Communication Plan Integration with 3rd
ServerInstallation &
Testing
Create,review&approve
DeploymentStrategy
WriteTraining
Documentation
Defect
Management
Run UAT Sessions
RecievesignofffromJNT
Board
Startusingthenew
application
Resolve&resolveUAT
Incidents
Complywith Federal
regulations
Ensuresuccessful
release/deployment
START
A
B
C
D
E
F
G
H
I
J
K L
1
2
5 7
6
8 9
3
4
1116
N
M
PQRTU
W X
FINISH
S O
V
1012131415
17
18 19
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
9
Project Name: Pay Load
Prepared By: Sal Vation
Date: 4 May 2016
Session Facilitator: Sal Vation
Title/Position: Project Manager
Participating Group: All
Location: Worksite
Risk
No.
Identified Risk Probability of
Occurrence*
Potential
Impact**
Risk Rating
Score
Risk
Ranking
Risk Scores >
Threshold = 1.0
Identified by
Whom?
1 Risk of personnel leaving 0.1 4 0.4 5 1.1.4
2 Technical / Design group may
produce incomplete
specifications, like,
missing browser
compatibility
0.5 5 2.5 1 2.5 1.3.3
3 Business Cost / Being an in-house
system may face critical operational
issues that may increase the cost of
project
0.3 3 0.9 4 1.5
4 External / integration with 3rd party
software may take longer than
expected
0.5 4 2 2 2 1.2.3
5 Time / New system may not be
intuitive from usability standpoint and
may require additional training and
time for it to be effective.
0.5 2 1 3 1 1.1.3
1.8Project risk socre = total of top rated risk scores divided by number of top rated risks
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
10
0
0.5
1
1.5
2
2.5
3
1 2 3 4 5
RiskScore
Risk No.
Qualitative Risk Scores
JN Project
*Probability of Occurrence Scale: Very low = 0.1
Low = 0.3
Moderate = 0.5
High = 0.7
Very high = 0.9
** Potential impact scale Very low = 1.0
Low = 2.0
Moderate = 3.0
High = 4.0
Very high = 5.0
Project risk threshold has been set for a risk score equal to or exceeding 1.0
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
11
Project Name: Pay Load
Prepared by: Sal Vation
Date: 18 May 2016
Session Facilitator: Sal Vation
Title/Position: Project Manager
Participating Group: All
Location: Worksite
Risk
No.
Risk Area
(Above Risk Threshold)
Probability
of
Occurrence
Potential
Impact
Expected
Value
WBS
REF.
2 Technical / Design group may
produce incomplete
specifications such as missing
browser
compatibility
0.5 6 weeks 3 weeks 1.3.3
0.5 $45,000 $22,500 1.3.3
4 External / integration with 3rd
party software may take longer
than expected
0.5 5 weeks 2.5 weeks 1.2.3
0.5 $32,000 $16,000 1.2.3
5 Time / New system may not be
intuitive from usability
standpoint and may require
additional training and time for it
to be effective.
0.5 3 weeks 1.5 weeks 1.1.3
0.5 $15,000 $7,500 1.1.3
Total Expected Value $46,000
7 weeks
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
12
Task Duration -Days Expected Variance
No. O M P Te Vd
1
Project Plan 1.1.1 2 3 6
3.3 0.4
2
Schedule 1.1.2 3 5 10
5.5 1.4
3
Budget 1.1.3 3 5 10
5.5 1.4
4 Communication Plan &
Reporting
1.1.4 2 3 6
3.3 0.4
5
Dev Tasks listed in Project Plan 1.2.1 13 20 30
20.5 8.0
6 Integration with 3rd party
software
1.2.2 6 10 15
10.2 2.3
7
Integration Testing 1.2.3 6 10 20
11.0 5.4
8
Write Test Cases 1.2.4 9 15 30
16.5 12.3
9
Validate the system 1.3.1 6 10 20
11.0 5.4
10
Defect Management 1.3.2 6 10 20
11.0 5.4
11
Server Installation and Testing 1.3.3 6 10 20
11.0 5.4
12 Write Training documentation 1.4.1 3 5 10 5.5 1.4
13
Run UAT sessions 1.4.2 3 5 10
5.5 1.4
14 Receive and resolve UAT
incidents
1.4.3 3 5 10
5.5 1.4
15 Comply with Federal
Regulations
1.4.4 2 3 6
3.3 0.4
16 Create, review and approve
deployment strategy
1.5.1 2 3 6
3.3 0.4
17 Ensure successful
release/deployment
1.5.2 2 3 6
3.3 0.4
18 Receive signoff from the JNT
Board
1.5.3 1 2 4
2.2 0.3
19 Start using the new
application
1.5.4 1 1 2
1.2 0.0
WBS#Activities
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
13
Conf. Z Crit. Path Conf. WBS Variance
Level Factor Days Level No. V
99% 2.330 120.7 0.99 1.5.4 0.0
95% 1.648 116.2 0.95 1.5.3 0.0
90% 1.281 113.8 0.90 1.1.1 0.4
75% 0.675 109.8 0.75 1.1.4 0.4
50% 0.000 105.3 0.50 1.4.4 0.4
25% -0.675 100.9 0.25 1.5.1 0.4
10% -1.281 96.9 0.10 1.5.2 0.4
5% -1.684 94.2 0.05 1.1.2 1.4
1% -2.330 89.9 0.01 1.1.3 1.4
1.4.1 1.4
1.4.2 1.4
1.4.3 1.4
1.2.2 2.3
1.2.3 5.4
1.3.1 5.4
1.3.2 5.4
1.3.3 5.4
1.2.1 8.0
1.2.4 12.3
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
14
Network Data Table Confidence Level
Project Network Path ∑Te ∑Vd 0.99 0.95 0.90 0.75 0.50 0.25 0.10 0.05 0.01
1, 2, 5, 7, 8, 9, 10, 12,
13, 14, 15, 17, 18, 19 105.3 43.7 120.7 116.2 113.8 109.8 105.3 100.9 96.9 94.2 89.9
1, 2, 5, 6, 8, 9, 10, 12,
13, 14, 15, 17, 18, 19 104.5 40.5 119.3 115.0 112.6 108.8 104.5 100.2 96.4 93.8 89.7
1, 2, 5, 7, 8, 9, 11, 16,
17, 18, 19 88.8 39.6 103.5 99.2 96.9 93.1 88.8 84.6 80.8 78.2 74.2
1, 2, 5, 6, 8, 9, 11, 16,
17, 18, 19 88.0 36.4 102.1 97.9 95.7 92.1 88.0 83.9 80.3 77.8 73.9
1, 3, 5, 7, 8, 9, 10, 12,
13, 14, 15, 17, 18, 19 105.3 43.7 120.7 116.2 113.8 109.8 105.3 100.9 96.9 94.2 89.9
1, 3, 5, 6, 8, 9, 10, 12,
13, 14, 15, 17, 18, 19 104.5 40.5 119.3 115.0 112.6 108.8 104.5 100.2 96.4 93.8 89.7
1, 3, 5, 7, 8, 9, 11, 16,
17, 18, 19 88.8 39.6 103.5 99.2 96.9 93.1 88.8 84.6 80.8 78.2 74.2
1, 3, 5, 6, 8, 9, 11, 16,
17, 18, 19 88.0 36.4 102.1 97.9 95.7 92.1 88.0 83.9 80.3 77.8 73.9
1, 4, 5, 7, 8, 9, 10, 12,
13, 14, 15, 17, 18, 19 103.2 42.8 118.4 113.9 111.5 107.6 103.2 98.8 94.8 92.2 87.9
1, 4, 5, 6, 8, 9, 10, 12,
13, 14, 15, 17, 18, 19 102.3 39.6 117.0 112.7 110.4 106.6 102.3 98.1 94.3 91.7 87.7
1, 4, 5, 7, 8, 9, 11, 16,
17, 18, 19 86.7 38.7 101.2 96.9 94.6 90.9 86.7 82.5 78.7 76.2 72.2
1, 4, 5, 6, 8, 9, 11, 16,
17, 18, 19 85.8 35.5 99.7 95.6 93.5 89.9 85.8 81.8 78.2 75.8 72.0
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
15BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
16
Project Quantitative Cost Analysis
Task Expected Variance
No. Optimistic Most likely Pessimistic Ce Vc
1 Project Plan 1.1.1 47.5 50 60 51.25 4.34
2 Schedule 1.1.2 14.25 15 18 15.38 0.39
3 Budget 1.1.3 19 20 24
20.50 0.69
4 Communication
Plan & Reporting
1.1.4
9.5 10 12
10.25 0.17
5 Dev Tasks listed in
Project Plan
1.2.1
190 200 240
205.00 69.44
6 Integration with 3rd
party software
1.2.2
47.5 50 60
51.25 4.34
7 Integration Testing 1.2.3
47.5 50 60
51.25 4.34
8 Write Test Cases 1.2.4
95 100 120
102.50 17.36
9 Validate the system 1.3.1
71.25 75 90
76.88 9.77
10 Defect Management 1.3.2
23.75 25 30
25.63 1.09
11 Server Installation
and Testing
1.3.3
95 100 120
102.50 17.36
12 Write Training
documentation
1.4.1
23.75 25 30
25.63 1.09
13 Run UAT sessions 1.4.2 23.75 25 30 25.63 1.09
14 Receive and resolve
UAT incidents
1.4.3
57 60 72
61.50 6.25
15 Comply with
Federal Regulations
1.4.4
14.25 15 18
15.38 0.39
16 Create, review and
approve
deployment strategy
1.5.1
19 20 24
20.50 0.69
17 Ensure successful
release/deployment
1.5.2
9.5 10 12
10.25 0.17
18
Receive signoff
from the JNT Board
1.5.3
4.75 5 6
5.13 0.04
19
Start using the new
application
1.5.4
9.5 10 12
10.25 0.17
20
WBS No. Work Package
Cost - $K
PERT Data Table
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
17
99% 2.330 914.11 0.99
95% 1.648 906.07 0.95
90% 1.281 901.74 0.90
75% 0.675 894.59 0.75
50% 0.000 886.63 0.50
25% -0.675 878.66 0.25
10% -1.281 871.51 0.10
5% -1.684 866.76 0.05
1% -2.330 859.14 0.01
Conf. Level Z Factor Cost $K Conf. Level
Cost Data
Table Confidence Level
∑Ce ∑Vc 99% 95% 90% 75% 50% 25% 10% 5% 1%
Total
Network 886.63 139.19 914.11 906.07 901.74 894.59 886.63 878.66 871.51 866.76 859.14
Conf. Level Data
Table
Probability Dist. Data
Table
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
18
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
19
Project Name: Pay Load Risk No. 4, WBS 1.2.3
Prepared by: Sal Vation
Date: 19 May 2016
Description of Risk Identified:
Integration with 3rd party software may take longer than expected
Risk Owner: Sal Vation
Results from Risk Analysis:
The risk rating is 2.0 out of 5.0. The probability of occurrence is 50% with potential impacts of 5 weeks delay
and $32,000. The expected values are 2.5 weeks schedule delay and $16,000 over budget if no risk response
is applied.
Agreed Risk Response (avoidance, transference, mitigation, acceptance): mitigation
Response:
Perform additional research and market analysis. Hold more integration planning review meetings.
Risk Response Cost
Implementation duration (Optimistic, Most Likely, Pessimistic): 0.6, 1.2, 1.8 wks Te = 1.2 wks
Implementation cost (Optimistic, Most Likely, Pessimistic): $800, $1,300, $1,900 Ce = $1,316
Residual Risk Level:
The risk response is estimated to reduce the probability of occurrence from 50% to 25% with resulting expected
values of $8,000 and 1.25 weeks of delay.
Benefit/Cost Ratio:
Sanity Check:
 $16,000 - $8,000 - $1,316 = $6,684
 2.5wks – 1.25 wks – 1.2 wks = 0.05 wks
Benefit/Cost Ratios (Expected ROI from risk response)
 ( $16,000 - $8,000 ) / ( $1,316 ) = $ 6.08
 ( 2.5 wks – 1.25 wks ) / 1.2 wks = 1.042
Secondary Risks: None
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
20
Project Name: Pay Load Risk No. 2, WBS 1.3.3
Prepared by: Sal Vation
Date: 19 May 2016
Description of Risk Identified:
Design group may produce incomplete specifications such as missing browser compatibility
Risk Owner: Sal Vation
Results from Risk Analysis:
The risk rating is 2.5 out of 5.0. The probability of occurrence is 50% with potential impacts of 6 weeks delay
and $45,000. The expected values are 3 weeks schedule delay and $22,500 over budget if no risk response
is applied.
Agreed Risk Response (avoidance, transference, mitigation, acceptance): mitigation
Response: Seek external expert consultant. Requires communication/networking, interviewing, and
contractual agreement. Requires two meetings between consultant and design group.
Risk Response Cost
Implementation duration (Optimistic, Most Likely, Pessimistic): 0.8, 1.2, 2.0 wks Te = 1.267 wks
Implementation cost (Optimistic, Most Likely, Pessimistic): $3000, $4500, $6500 Ce = $4583
Residual Risk Level:
The risk response is estimated to reduce the probability of occurrence from 50% to 10% with resulting
expected values of $4500 and 0.6 weeks of delay.
Benefit/Cost Ratio:
Sanity Check:
 $22,500 - $4,500 - $4,583 = $13,417
 3 wks – 0.6 wks – 1.267 wks = 1.133 wks
Benefit/Cost Ratios (Expected ROI from risk response)
 ( $22,500 - $4,500 ) / ( $4,583 ) = 3.928
 ( 3 wks – 0.6 wks ) / 1.267 wks = 1.894
Secondary Risks: Bringing in expert help from outside the company may leave the technical/design team
feeling insulted. This could lead to damaged egos of the design group resulting in possible turnover of core
team members.
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
21
Project Name: Pay Load Risk No. 5, WBS 1.1.3
Prepared by: Sal Vation
Date: 19 May 2016
Description of Risk Identified: New system may not be intuitive from usability standpoint and may require
additional training and time for it to be effective.
Risk Owner: Sal Vation
Results from Risk Analysis:
The risk rating is 1.0 out of 5.0. The probability of occurrence is 50% with potential impacts of 3 weeks
delay and $15,000. The expected values are 1.5 weeks schedule delay and $7,500 over budget if no risk
response is applied.
Agreed Risk Response (avoidance, transference, mitigation, acceptance): Mitigation
Response: Conduct surveys within Jack Neift Trucking company to understand how the future users rate
the user interface and general flow of the software. Based on customer feedback, include additional
information in the training material so the users get a better understanding without having to be retrained.
Risk Response Cost:
Implementation duration (Optimistic, Most Likely, Pessimistic): 0.4, 0.6, 0.8 wks Te = 0.6 wks
Implementation cost (Optimistic, Most Likely, Pessimistic): $400, $550, $800 Ce = $566
Residual Risk Level: The risk response is estimated to reduce the probability of occurrence from 50% to
5% with resulting expected values of $750 and 0.15 weeks of delay.
Benefit/Cost Ratio:
Sanity Check:
 $7,500 - $750 - $566 = $6,184
 1.5wks – 0.15 wks – 0.6 wks = 0.75 wks
Benefit/Cost Ratios (Expected ROI from risk response)
 ( $7,500 - $750 ) / ( $566 ) = 11.92
 ( 1.5 wks – 0.15 wks ) / 0.6 wks = 2.25
Secondary Risks: None
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
22
1. Common Cause Cost Risk Reserve
As shown in the above table, the project cost estimate is $893,090 at the 50% confidence level and
$912,560 at the 95% confidence level. The baseline budget will become $893,090. The common cause
risk reserve will be the difference the 95% confidence level cost and the 50% confidence level cost
which is:
Common causes risk reserve = $912,560 - $893,090 = $19,470.
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
23
2. Specific Cause Cost Risk Reserve
After mitigation the three high level risks have the following residual expected values for cost as
described in the risk response plan section.
Special Causes Risk Residual Expected Value
Risk No. 2 $4,500
Risk No. 4 $8,000
Risk No. 5 $750
Total special causes cost risk reserve = $4,500 + $8,000 + $750 = $13,250
3. Management Reserve
The reserve for unknown risks will be set arbitrarily at 5% of the baseline project cost or 5% x $893,090
= $44,654.5.
4. Total Cost Reserve
The total cost reserve is the sum of the common causes risk, special causes risk and management
reserves. Total cost reserve = $19,470+ $13250 + $44,654.5= $77,374.5
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
24
1. Common Causes Schedule Risk Reserve
The JNT project will be managed to achieve cost and schedule for the 50% confidence level. However,
cost and schedule reserve will be allocated to provide for a 95% confidence level. There are three risk
mitigation (RM) activities which will be included into existing work packages with the following
mitigation duration requirements.
Risk Mitigation Activity Work Package/Task No. Duration (O, M , P)
RM No.4 1.2.3 0.6, 1.2, 1.8 weeks
RM No.2 1.1.3 0.4, 0.6, 0.8 weeks
RM No.5 1.3.3 0.8, 1.2, 2.0 weeks
Risk mitigation activities No.4 & 5 will be incorporated into Work Package 1.2.3 and performed in
parallel (fast tracked) with the other activities in WP 1.2.3 and will have no impact on the duration of
the existing WP.
Based upon the above analysis, it will be assumed that the project critical path will not change due to
the three top level risk mitigation tasks.
As previously shown in the quantitative schedule risk analysis, the project schedule duration estimate
(critical path) is 105.3 days at the 50% confidence level and 116.2 days at the 95% confidence level.
Common causes schedule risk reserve is 116.2 days - 105.3 days = 10.9` days.
2. Special Causes Schedule Risk Reserve
After risk mitigation the three high level risks have the following residual expected values as described
in the risk response plan section.
Special Causes Risk Residual Expected Value
Risk No. 4 1.25 week or 6.25 days
Risk No. 2 0.6 week or 3 days
Risk No. 5 .15 week or .75 days
BACK TO INDEX
PIRM PROJECT PLAN TEAM MUSK
Pay Load: Jack Neift Trucking Co.
25
Since Risk No. 2 is not on the critical path and has slack of 3 days, its residual expected duration value
of 3 days will not affect the overall project duration and will not be added to the special causes
schedule reserve.
Total special causes schedule risk reserve = 6.25 days + .75 days = 7 days
3. Management Reserve
The reserve for unknown risks will be arbitrarily set at 5% of the baseline project schedule.
Management reserve = 5% x 105.3 = 5.26 days.
4. Total Schedule Risk Reserve
The total schedule reserve is the sum of the common causes risk, special causes risk and management
reserves.
Total schedule reserve = 10.9 days + 7 days + 5.26 days = 23.16 days
BACK TO INDEX

Weitere ähnliche Inhalte

Was ist angesagt?

Systems engineering
Systems engineeringSystems engineering
Systems engineeringhepta-sat
 
Planning & Scheduling - Training
Planning & Scheduling - TrainingPlanning & Scheduling - Training
Planning & Scheduling - TrainingMohammed Feroze
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
PMP Training - 05 project scope management
PMP Training - 05 project scope managementPMP Training - 05 project scope management
PMP Training - 05 project scope managementejlp12
 
Project Management Office Vol. 1 - One Page Gold Vol. 1
Project Management Office Vol. 1  - One Page Gold Vol. 1Project Management Office Vol. 1  - One Page Gold Vol. 1
Project Management Office Vol. 1 - One Page Gold Vol. 1ken martin
 
Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5pankajsh10
 
Capella Days 2021 | Enhancing CubeSat design through ARCADIA and Capella: a c...
Capella Days 2021 | Enhancing CubeSat design through ARCADIA and Capella: a c...Capella Days 2021 | Enhancing CubeSat design through ARCADIA and Capella: a c...
Capella Days 2021 | Enhancing CubeSat design through ARCADIA and Capella: a c...Obeo
 
Probability basis of safe life evaluation in small airplanes by w. michael reyer
Probability basis of safe life evaluation in small airplanes by w. michael reyerProbability basis of safe life evaluation in small airplanes by w. michael reyer
Probability basis of safe life evaluation in small airplanes by w. michael reyerJulio Banks
 
Lec 05 wbs & obs 1
Lec 05 wbs & obs 1Lec 05 wbs & obs 1
Lec 05 wbs & obs 1SAJID ALI RUK
 
CapellaDays2022 | Politecnico di Milano | Interplanetary Space Mission as a r...
CapellaDays2022 | Politecnico di Milano | Interplanetary Space Mission as a r...CapellaDays2022 | Politecnico di Milano | Interplanetary Space Mission as a r...
CapellaDays2022 | Politecnico di Milano | Interplanetary Space Mission as a r...Obeo
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path methodPrathima Girish
 
CPDLC - Data Link Services in Brazil
CPDLC -   Data Link Services in BrazilCPDLC -   Data Link Services in Brazil
CPDLC - Data Link Services in BrazilCarlos Pera
 
pRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - SubstationpRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - SubstationRAMESH PANIGRAHI PMP
 
ISO/IEC 42010 Recommended Practice for Architectural description
ISO/IEC 42010 Recommended Practice for Architectural descriptionISO/IEC 42010 Recommended Practice for Architectural description
ISO/IEC 42010 Recommended Practice for Architectural descriptionHongseok Lee
 

Was ist angesagt? (20)

Systems engineering
Systems engineeringSystems engineering
Systems engineering
 
Planning & Scheduling - Training
Planning & Scheduling - TrainingPlanning & Scheduling - Training
Planning & Scheduling - Training
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
PMP Training - 05 project scope management
PMP Training - 05 project scope managementPMP Training - 05 project scope management
PMP Training - 05 project scope management
 
cheat sheet.ppt
cheat sheet.pptcheat sheet.ppt
cheat sheet.ppt
 
113015 - Understanding ALAP
113015 - Understanding ALAP113015 - Understanding ALAP
113015 - Understanding ALAP
 
PMP_Project Integration Management
PMP_Project Integration ManagementPMP_Project Integration Management
PMP_Project Integration Management
 
Excel Project Management
Excel Project ManagementExcel Project Management
Excel Project Management
 
Project Management Office Vol. 1 - One Page Gold Vol. 1
Project Management Office Vol. 1  - One Page Gold Vol. 1Project Management Office Vol. 1  - One Page Gold Vol. 1
Project Management Office Vol. 1 - One Page Gold Vol. 1
 
Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5Project Human Resource Management - PMBOK 5
Project Human Resource Management - PMBOK 5
 
Capella Days 2021 | Enhancing CubeSat design through ARCADIA and Capella: a c...
Capella Days 2021 | Enhancing CubeSat design through ARCADIA and Capella: a c...Capella Days 2021 | Enhancing CubeSat design through ARCADIA and Capella: a c...
Capella Days 2021 | Enhancing CubeSat design through ARCADIA and Capella: a c...
 
Probability basis of safe life evaluation in small airplanes by w. michael reyer
Probability basis of safe life evaluation in small airplanes by w. michael reyerProbability basis of safe life evaluation in small airplanes by w. michael reyer
Probability basis of safe life evaluation in small airplanes by w. michael reyer
 
11.7 Monitor Risks
11.7 Monitor Risks11.7 Monitor Risks
11.7 Monitor Risks
 
Lec 05 wbs & obs 1
Lec 05 wbs & obs 1Lec 05 wbs & obs 1
Lec 05 wbs & obs 1
 
CapellaDays2022 | Politecnico di Milano | Interplanetary Space Mission as a r...
CapellaDays2022 | Politecnico di Milano | Interplanetary Space Mission as a r...CapellaDays2022 | Politecnico di Milano | Interplanetary Space Mission as a r...
CapellaDays2022 | Politecnico di Milano | Interplanetary Space Mission as a r...
 
Cpm critical path method
Cpm   critical path methodCpm   critical path method
Cpm critical path method
 
CPDLC - Data Link Services in Brazil
CPDLC -   Data Link Services in BrazilCPDLC -   Data Link Services in Brazil
CPDLC - Data Link Services in Brazil
 
pRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - SubstationpRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - Substation
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 
ISO/IEC 42010 Recommended Practice for Architectural description
ISO/IEC 42010 Recommended Practice for Architectural descriptionISO/IEC 42010 Recommended Practice for Architectural description
ISO/IEC 42010 Recommended Practice for Architectural description
 

Andere mochten auch

Leveraging ISO 31000 for Effective Integration of Risk Management and Interna...
Leveraging ISO 31000 for Effective Integration of Risk Management and Interna...Leveraging ISO 31000 for Effective Integration of Risk Management and Interna...
Leveraging ISO 31000 for Effective Integration of Risk Management and Interna...International Federation of Accountants
 
Bombardier Integration Plan
Bombardier Integration PlanBombardier Integration Plan
Bombardier Integration PlanAjay Singh
 
Management of Risk and its integration within ITIL
Management of Risk and its integration within ITILManagement of Risk and its integration within ITIL
Management of Risk and its integration within ITILhdoornbos
 
Project Manage My Trip
Project Manage My TripProject Manage My Trip
Project Manage My Tripumyongck
 
Central america travel plan
Central america travel planCentral america travel plan
Central america travel planunionmade
 
Travel project to the Bahamas
Travel project to the Bahamas Travel project to the Bahamas
Travel project to the Bahamas Angelie Bacon
 
Catch! Workshop concept 2 - Improving travel plan monitoring with better, mor...
Catch! Workshop concept 2 - Improving travel plan monitoring with better, mor...Catch! Workshop concept 2 - Improving travel plan monitoring with better, mor...
Catch! Workshop concept 2 - Improving travel plan monitoring with better, mor...Peter Lindgren
 
Strategic Performance & Risk Integration
Strategic Performance & Risk IntegrationStrategic Performance & Risk Integration
Strategic Performance & Risk IntegrationMihai Ionescu
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk ManagementHayat Denzi
 
Risk Management Plan Slides
Risk Management Plan SlidesRisk Management Plan Slides
Risk Management Plan Slidesvivian weeks
 
Post Acquisiton Integration Framework
Post Acquisiton Integration FrameworkPost Acquisiton Integration Framework
Post Acquisiton Integration Frameworktejasoza
 
Production development plan for travel agency
 Production development plan for travel agency Production development plan for travel agency
Production development plan for travel agencyhechmibaccouche
 
Travel and tourism management it project ppt
Travel and tourism management it project pptTravel and tourism management it project ppt
Travel and tourism management it project pptMadhukar Kumar
 

Andere mochten auch (20)

Leveraging ISO 31000 for Effective Integration of Risk Management and Interna...
Leveraging ISO 31000 for Effective Integration of Risk Management and Interna...Leveraging ISO 31000 for Effective Integration of Risk Management and Interna...
Leveraging ISO 31000 for Effective Integration of Risk Management and Interna...
 
Bombardier Integration Plan
Bombardier Integration PlanBombardier Integration Plan
Bombardier Integration Plan
 
Management of Risk and its integration within ITIL
Management of Risk and its integration within ITILManagement of Risk and its integration within ITIL
Management of Risk and its integration within ITIL
 
TV UI Projects
TV UI ProjectsTV UI Projects
TV UI Projects
 
Project Manage My Trip
Project Manage My TripProject Manage My Trip
Project Manage My Trip
 
Travel Project - 2015
Travel Project - 2015Travel Project - 2015
Travel Project - 2015
 
Central america travel plan
Central america travel planCentral america travel plan
Central america travel plan
 
Travel project to the Bahamas
Travel project to the Bahamas Travel project to the Bahamas
Travel project to the Bahamas
 
Travel Website
Travel WebsiteTravel Website
Travel Website
 
Catch! Workshop concept 2 - Improving travel plan monitoring with better, mor...
Catch! Workshop concept 2 - Improving travel plan monitoring with better, mor...Catch! Workshop concept 2 - Improving travel plan monitoring with better, mor...
Catch! Workshop concept 2 - Improving travel plan monitoring with better, mor...
 
joseph john sebastian travel plan
joseph john sebastian travel planjoseph john sebastian travel plan
joseph john sebastian travel plan
 
Luxury travel-to-holland
Luxury travel-to-hollandLuxury travel-to-holland
Luxury travel-to-holland
 
Strategic Performance & Risk Integration
Strategic Performance & Risk IntegrationStrategic Performance & Risk Integration
Strategic Performance & Risk Integration
 
KRI (Key Risk Indicators) & IT
KRI (Key Risk Indicators) & ITKRI (Key Risk Indicators) & IT
KRI (Key Risk Indicators) & IT
 
Travel Demand Management - WRI Beijing Project
Travel Demand Management - WRI Beijing ProjectTravel Demand Management - WRI Beijing Project
Travel Demand Management - WRI Beijing Project
 
Project Risk Management
 Project Risk Management Project Risk Management
Project Risk Management
 
Risk Management Plan Slides
Risk Management Plan SlidesRisk Management Plan Slides
Risk Management Plan Slides
 
Post Acquisiton Integration Framework
Post Acquisiton Integration FrameworkPost Acquisiton Integration Framework
Post Acquisiton Integration Framework
 
Production development plan for travel agency
 Production development plan for travel agency Production development plan for travel agency
Production development plan for travel agency
 
Travel and tourism management it project ppt
Travel and tourism management it project pptTravel and tourism management it project ppt
Travel and tourism management it project ppt
 

Ähnlich wie Project Plan - Risk Management & Integration

DASC 5303 00 – Team 4 - Assignment 6.pptx
DASC 5303 00 – Team 4 - Assignment 6.pptxDASC 5303 00 – Team 4 - Assignment 6.pptx
DASC 5303 00 – Team 4 - Assignment 6.pptx17542Saiteja
 
edSe275 ms project-assignment
edSe275 ms project-assignmentedSe275 ms project-assignment
edSe275 ms project-assignmentharinathinfotech
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesYousef Abugosh, PMP, MA
 
03-2004PDS_Technology_Isom
03-2004PDS_Technology_Isom03-2004PDS_Technology_Isom
03-2004PDS_Technology_IsomJohn Isom
 
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docxITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docxpriestmanmable
 
Project Description The new computer-controlled convey.docx
Project Description The new computer-controlled convey.docxProject Description The new computer-controlled convey.docx
Project Description The new computer-controlled convey.docxbriancrawford30935
 
18 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v718 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v7Michael Cary
 
NEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docx
NEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docxNEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docx
NEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docxhenrymartin15260
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.pptTinotendaChivese
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxtoltonkendal
 
Washington_Course_Project_Week_8
Washington_Course_Project_Week_8Washington_Course_Project_Week_8
Washington_Course_Project_Week_8Douglas Washington
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...Скоробогатов Дмитрий
 
PMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPeter Mello
 
Mgt 402 Success Begins / snaptutorial.com
Mgt 402  Success Begins / snaptutorial.comMgt 402  Success Begins / snaptutorial.com
Mgt 402 Success Begins / snaptutorial.comWilliamsTaylor33
 
Agile process with a fixed cost
Agile process with a fixed costAgile process with a fixed cost
Agile process with a fixed costRalph Johnson
 
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”IRJET Journal
 

Ähnlich wie Project Plan - Risk Management & Integration (20)

DASC 5303 00 – Team 4 - Assignment 6.pptx
DASC 5303 00 – Team 4 - Assignment 6.pptxDASC 5303 00 – Team 4 - Assignment 6.pptx
DASC 5303 00 – Team 4 - Assignment 6.pptx
 
edSe275 ms project-assignment
edSe275 ms project-assignmentedSe275 ms project-assignment
edSe275 ms project-assignment
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
03-2004PDS_Technology_Isom
03-2004PDS_Technology_Isom03-2004PDS_Technology_Isom
03-2004PDS_Technology_Isom
 
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docxITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
 
Project Description The new computer-controlled convey.docx
Project Description The new computer-controlled convey.docxProject Description The new computer-controlled convey.docx
Project Description The new computer-controlled convey.docx
 
18 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v718 Apr 2015 NWFSC PMI presentation v7
18 Apr 2015 NWFSC PMI presentation v7
 
NEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docx
NEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docxNEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docx
NEW YORK DEPARTMENT OF TRANSPORTATION - PROJECT2N.docx
 
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
45ef51191315a8630a639ff030b4cb67a3df6f49-1657701254277.ppt
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
 
Washington_Course_Project_Week_8
Washington_Course_Project_Week_8Washington_Course_Project_Week_8
Washington_Course_Project_Week_8
 
project plan
project planproject plan
project plan
 
Prasanth PV Nambiar
Prasanth PV NambiarPrasanth PV Nambiar
Prasanth PV Nambiar
 
(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...(Presentation) Cis utilization of earned value management for monitoring prod...
(Presentation) Cis utilization of earned value management for monitoring prod...
 
PMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/ManausPMI Global 2007 - Urucu/Manaus
PMI Global 2007 - Urucu/Manaus
 
Mgt 402 Success Begins / snaptutorial.com
Mgt 402  Success Begins / snaptutorial.comMgt 402  Success Begins / snaptutorial.com
Mgt 402 Success Begins / snaptutorial.com
 
Agile process with a fixed cost
Agile process with a fixed costAgile process with a fixed cost
Agile process with a fixed cost
 
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
“OPTIMIZATION OF COST BY ALLOCATION OF RESOURCES USING PRIMAVERA P6”
 

Project Plan - Risk Management & Integration

  • 1. 0 JACK NEIFT TRUCKING CO. Project Plan Presented: Pay Load JUNE 1, 2016 TEAM MUSK: Logan Rogers, Anirudh Mathur, Prachi Dikshit, Darshana Shetty Project Integration & Risk Management
  • 2. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 1 INDEX S. No. Contents Page No. 1. PROJECT CHARTER 2 2. PROJECT SCOPE STATEMENT 4 3. (a) WORK BREAKDOWN STRUCTURE 6 (b) WORK BREAKDOW PACKAGE 7 4. NETWORK DIAGRAM 8 5. QUALITATIVE RISK ANALYSIS 9 6. (a) QUANTITATIVE RISK ANALYSIS 11 (b) PERT ANALYSIS - SCHEDULE 12 PERT ANALYSIS – COST 16 7. RISK RESPONSE PLAN # 1 19 PLAN # 2 20 PLAN # 3 21 8. (a) COST RESERVE ANALYSIS 22 (b) SCHEDULE RESERVE ANALYSIS 24
  • 3. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 2 Project Name: Pay Load Prepared by: Team MUSK Date: 4/14/16 Purpose/Business Need: Reduce deadheading by 75% for Jack Neift Trucking Company. Product Description: A web-based software system that quickly brings shipping information, unloading schedules, and truck routes to all major departments to promote efficient planning and sales techniques that leads to reduction in deadheading. Success Criteria: Reduce deadheading by 75%, and achieve 30% ROI for Team MUSK, and release the software system within 26 weeks of starting the project. Project Priorities: 1. Scope – A web-based software system with GPS tracking and scheduling wizard. 2. Schedule – Project should be complete within 6 months. 3. Cost – Estimated cost of project is $850,000 but not to exceed $875,000. Assumptions: 1. Sales force is able to locate clients and make shipment sales for return routes. 2. Clients publish loading/unloading schedules. 3. All hardware and software 3rd party systems work as expected. Constraints: 1. Comply with state regulations for the man-hours of the truckers. 2. Sales team and dispatchers working hours between 9am and 5pm (eastern) Risks: 1. Network crashes could cripple the system for unknown periods of time. 2. Being an in-house system may face critical operational issues that may increase the cost of project. 3. New system may not be intuitive from usability standpoint and may require additional training and time for it to be effective. BACK TO INDEX
  • 4. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 3 Milestones Schedule: (based on working days) 1. Project plan approval – 3 weeks from start of project 2. Core system implemented – 10 weeks from start of project 3. Beta version released – 16 weeks from start of project 4. Beta testing completed – 19 weeks from start of project 5. User testing completed – 21 weeks from start of project 6. Revised version released – 23 weeks from start of project 7. Employee training completed – 24 weeks from start of project 8. System launch – 25 weeks from start of project 9. Project Closing – 26 weeks from start of project Other: 1. This project will enable Jack Neift Trucking Company to be a modern trucking company in this competitive market. 2. The technology developed in this project could be a game changer for the entire trucking industry. Approvals: Sponsor: Bea Stoveburden Date: 4/13/2016 Project Manager: Sal Vatation Date: 4/13/2016 BACK TO INDEX
  • 5. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 4 Project Name: Pay Load Project Manager: Sal Vatation Prepared by: Team Musk Date: 4/16/2016 Approved by: Bea Stoveburden Date: 4/16/2016 Project Objectives:  Scope – A web-based software system which will have GPS to tracking and also this will help us in reducing deadheading.  Schedule – Project time to complete this project is 26 weeks.  Cost – Estimated cost for this project shall not exceed $875,000. Product Scope Description: This project will produce a software system which will help the company to reduce deadheading by roughly 75%. It will aid Jack Neift Trucking Company in tracking the truck routes to make efficient travel plans for their clients' drop-offs and deliveries. This Software will also monitor the truckers' driving time and will trigger alerts if the driving time approaches the limits set by the Federal Motor Carrier Safety Administration. Project Deliverables:  Project Plan  GPS Unit  Server  Software  User manuals  State regulation documents  GPS software design documents  Testing reports  Software User Training Project Boundaries:  The project will only include one-time training for employees, no training after that if any new employee joins the company.  Software is one-time design won’t allow you to add features once it is launched. BACK TO INDEX
  • 6. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 5 Product Acceptance Criteria:  Project plan should be reviewed and accepted by the Project Sponsor.  Jack Neift Trucking Company needs to send their Quality testing person to do the quality check for the software before installing them.  After completion of the testing of GPS units and software the project should be accepted by the project head.  75% reduction in deadheading and 30% ROI for Team Musk. Project Constraints:  Comply with federal regulations for the man-hours of the truckers.  Sales team and dispatchers working hours between 9am and 5pm (eastern)  Due to existing relationship between JNTC and Elon Tracking, only tracking devices from Elon Tracking may be used. Project Assumptions:  Sales force is able to locate clients and make shipment sales for return routes.  Clients publish loading/unloading schedules.  All hardware and software 3rd party systems work as expected. Approval Requirements:  Project Sponsor: Bea Stoveburden  Project Manager: Sal Vatation BACK TO INDEX
  • 7. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 6 BACK TO INDEX
  • 8. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 7 Work Package (WBS#) WP# Duration Estimate - Days Cost Estimate ($K) Optimistic Most Likely Pessimistic Optimistic Most Likely Pessimistic Project Plan 1.1.1 2 3 6 47.5 50 60 Schedule 1.1.2 3 5 10 14.25 15 18 Budget 1.1.3 3 5 10 19 20 24 Communication Plan & Reporting 1.1.4 2 3 6 9.5 10 12 Dev Tasks listed in Project Plan 1.2.1 13 20 30 190 200 240 Integration with 3rd party software 1.2.2 6 10 15 47.5 50 60 Integration Testing 1.2.3 6 10 20 47.5 50 60 Write Test Cases 1.2.4 9 15 30 95 100 120 Validate the system 1.3.1 6 10 20 71.25 75 90 Defect Management 1.3.2 6 10 20 23.75 25 30 Server Installation and Testing 1.3.3 6 10 20 95 100 120 Write Training documentation 1.4.1 3 5 10 23.75 25 30 Run UAT sessions 1.4.2 3 5 10 23.75 25 30 Receive and resolve UAT incidents 1.4.3 3 5 10 57 60 72 Comply with Federal Regulations 1.4.4 2 3 6 14.25 15 18 Create, review and approve deployment strategy 1.5.1 2 3 6 19 20 24 Ensure successful release/deployment 1.5.2 2 3 6 9.5 10 12 Receive signoff from the JNT Board 1.5.3 1 2 4 4.75 5 6 Start using the new application 1.5.4 1 1 2 9.5 10 12 BACK TO INDEX
  • 9. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 8 1.1.2 3 11-Apr 13-Apr 1.2.1 13 1.2.3 6 1.2.4 9 1.3.1 6 14-Apr 18-Apr 27-Apr 4-May 5-May 17-May 18-May 25-May 1.1.1 2 1.1.3 3 6-Apr 8-Apr 11-Apr 13-Apr 1.1.4 2 1.2.2 6 11-Apr 12-Apr 19-Apr 26-Apr 1.4.4 2 1.4.3 3 1.4.2 3 1.4.1 3 1.3.2 6 16-Jun 20-Jun 13-Jun 15-Jun 8-Jun 10-Jun 3-Jun 7-Jun 26-May 2-Jun 1.5.2 2 21-Jun 23-Jun 1.5.1 2 1.3.3 6 3-Jun 6-Jun 26-May 2-Jun 1.5.3 1 1.5.4 1 24-Jun 24-Jun 25-Jun 25-Jun Schedule DevTaskslisted in Project Plan Integration Testing WriteTestCases Validatethesystem ProjectPlan Budget Communication Plan Integration with 3rd ServerInstallation & Testing Create,review&approve DeploymentStrategy WriteTraining Documentation Defect Management Run UAT Sessions RecievesignofffromJNT Board Startusingthenew application Resolve&resolveUAT Incidents Complywith Federal regulations Ensuresuccessful release/deployment START A B C D E F G H I J K L 1 2 5 7 6 8 9 3 4 1116 N M PQRTU W X FINISH S O V 1012131415 17 18 19 BACK TO INDEX
  • 10. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 9 Project Name: Pay Load Prepared By: Sal Vation Date: 4 May 2016 Session Facilitator: Sal Vation Title/Position: Project Manager Participating Group: All Location: Worksite Risk No. Identified Risk Probability of Occurrence* Potential Impact** Risk Rating Score Risk Ranking Risk Scores > Threshold = 1.0 Identified by Whom? 1 Risk of personnel leaving 0.1 4 0.4 5 1.1.4 2 Technical / Design group may produce incomplete specifications, like, missing browser compatibility 0.5 5 2.5 1 2.5 1.3.3 3 Business Cost / Being an in-house system may face critical operational issues that may increase the cost of project 0.3 3 0.9 4 1.5 4 External / integration with 3rd party software may take longer than expected 0.5 4 2 2 2 1.2.3 5 Time / New system may not be intuitive from usability standpoint and may require additional training and time for it to be effective. 0.5 2 1 3 1 1.1.3 1.8Project risk socre = total of top rated risk scores divided by number of top rated risks BACK TO INDEX
  • 11. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 10 0 0.5 1 1.5 2 2.5 3 1 2 3 4 5 RiskScore Risk No. Qualitative Risk Scores JN Project *Probability of Occurrence Scale: Very low = 0.1 Low = 0.3 Moderate = 0.5 High = 0.7 Very high = 0.9 ** Potential impact scale Very low = 1.0 Low = 2.0 Moderate = 3.0 High = 4.0 Very high = 5.0 Project risk threshold has been set for a risk score equal to or exceeding 1.0 BACK TO INDEX
  • 12. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 11 Project Name: Pay Load Prepared by: Sal Vation Date: 18 May 2016 Session Facilitator: Sal Vation Title/Position: Project Manager Participating Group: All Location: Worksite Risk No. Risk Area (Above Risk Threshold) Probability of Occurrence Potential Impact Expected Value WBS REF. 2 Technical / Design group may produce incomplete specifications such as missing browser compatibility 0.5 6 weeks 3 weeks 1.3.3 0.5 $45,000 $22,500 1.3.3 4 External / integration with 3rd party software may take longer than expected 0.5 5 weeks 2.5 weeks 1.2.3 0.5 $32,000 $16,000 1.2.3 5 Time / New system may not be intuitive from usability standpoint and may require additional training and time for it to be effective. 0.5 3 weeks 1.5 weeks 1.1.3 0.5 $15,000 $7,500 1.1.3 Total Expected Value $46,000 7 weeks BACK TO INDEX
  • 13. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 12 Task Duration -Days Expected Variance No. O M P Te Vd 1 Project Plan 1.1.1 2 3 6 3.3 0.4 2 Schedule 1.1.2 3 5 10 5.5 1.4 3 Budget 1.1.3 3 5 10 5.5 1.4 4 Communication Plan & Reporting 1.1.4 2 3 6 3.3 0.4 5 Dev Tasks listed in Project Plan 1.2.1 13 20 30 20.5 8.0 6 Integration with 3rd party software 1.2.2 6 10 15 10.2 2.3 7 Integration Testing 1.2.3 6 10 20 11.0 5.4 8 Write Test Cases 1.2.4 9 15 30 16.5 12.3 9 Validate the system 1.3.1 6 10 20 11.0 5.4 10 Defect Management 1.3.2 6 10 20 11.0 5.4 11 Server Installation and Testing 1.3.3 6 10 20 11.0 5.4 12 Write Training documentation 1.4.1 3 5 10 5.5 1.4 13 Run UAT sessions 1.4.2 3 5 10 5.5 1.4 14 Receive and resolve UAT incidents 1.4.3 3 5 10 5.5 1.4 15 Comply with Federal Regulations 1.4.4 2 3 6 3.3 0.4 16 Create, review and approve deployment strategy 1.5.1 2 3 6 3.3 0.4 17 Ensure successful release/deployment 1.5.2 2 3 6 3.3 0.4 18 Receive signoff from the JNT Board 1.5.3 1 2 4 2.2 0.3 19 Start using the new application 1.5.4 1 1 2 1.2 0.0 WBS#Activities BACK TO INDEX
  • 14. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 13 Conf. Z Crit. Path Conf. WBS Variance Level Factor Days Level No. V 99% 2.330 120.7 0.99 1.5.4 0.0 95% 1.648 116.2 0.95 1.5.3 0.0 90% 1.281 113.8 0.90 1.1.1 0.4 75% 0.675 109.8 0.75 1.1.4 0.4 50% 0.000 105.3 0.50 1.4.4 0.4 25% -0.675 100.9 0.25 1.5.1 0.4 10% -1.281 96.9 0.10 1.5.2 0.4 5% -1.684 94.2 0.05 1.1.2 1.4 1% -2.330 89.9 0.01 1.1.3 1.4 1.4.1 1.4 1.4.2 1.4 1.4.3 1.4 1.2.2 2.3 1.2.3 5.4 1.3.1 5.4 1.3.2 5.4 1.3.3 5.4 1.2.1 8.0 1.2.4 12.3 BACK TO INDEX
  • 15. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 14 Network Data Table Confidence Level Project Network Path ∑Te ∑Vd 0.99 0.95 0.90 0.75 0.50 0.25 0.10 0.05 0.01 1, 2, 5, 7, 8, 9, 10, 12, 13, 14, 15, 17, 18, 19 105.3 43.7 120.7 116.2 113.8 109.8 105.3 100.9 96.9 94.2 89.9 1, 2, 5, 6, 8, 9, 10, 12, 13, 14, 15, 17, 18, 19 104.5 40.5 119.3 115.0 112.6 108.8 104.5 100.2 96.4 93.8 89.7 1, 2, 5, 7, 8, 9, 11, 16, 17, 18, 19 88.8 39.6 103.5 99.2 96.9 93.1 88.8 84.6 80.8 78.2 74.2 1, 2, 5, 6, 8, 9, 11, 16, 17, 18, 19 88.0 36.4 102.1 97.9 95.7 92.1 88.0 83.9 80.3 77.8 73.9 1, 3, 5, 7, 8, 9, 10, 12, 13, 14, 15, 17, 18, 19 105.3 43.7 120.7 116.2 113.8 109.8 105.3 100.9 96.9 94.2 89.9 1, 3, 5, 6, 8, 9, 10, 12, 13, 14, 15, 17, 18, 19 104.5 40.5 119.3 115.0 112.6 108.8 104.5 100.2 96.4 93.8 89.7 1, 3, 5, 7, 8, 9, 11, 16, 17, 18, 19 88.8 39.6 103.5 99.2 96.9 93.1 88.8 84.6 80.8 78.2 74.2 1, 3, 5, 6, 8, 9, 11, 16, 17, 18, 19 88.0 36.4 102.1 97.9 95.7 92.1 88.0 83.9 80.3 77.8 73.9 1, 4, 5, 7, 8, 9, 10, 12, 13, 14, 15, 17, 18, 19 103.2 42.8 118.4 113.9 111.5 107.6 103.2 98.8 94.8 92.2 87.9 1, 4, 5, 6, 8, 9, 10, 12, 13, 14, 15, 17, 18, 19 102.3 39.6 117.0 112.7 110.4 106.6 102.3 98.1 94.3 91.7 87.7 1, 4, 5, 7, 8, 9, 11, 16, 17, 18, 19 86.7 38.7 101.2 96.9 94.6 90.9 86.7 82.5 78.7 76.2 72.2 1, 4, 5, 6, 8, 9, 11, 16, 17, 18, 19 85.8 35.5 99.7 95.6 93.5 89.9 85.8 81.8 78.2 75.8 72.0 BACK TO INDEX
  • 16. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 15BACK TO INDEX
  • 17. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 16 Project Quantitative Cost Analysis Task Expected Variance No. Optimistic Most likely Pessimistic Ce Vc 1 Project Plan 1.1.1 47.5 50 60 51.25 4.34 2 Schedule 1.1.2 14.25 15 18 15.38 0.39 3 Budget 1.1.3 19 20 24 20.50 0.69 4 Communication Plan & Reporting 1.1.4 9.5 10 12 10.25 0.17 5 Dev Tasks listed in Project Plan 1.2.1 190 200 240 205.00 69.44 6 Integration with 3rd party software 1.2.2 47.5 50 60 51.25 4.34 7 Integration Testing 1.2.3 47.5 50 60 51.25 4.34 8 Write Test Cases 1.2.4 95 100 120 102.50 17.36 9 Validate the system 1.3.1 71.25 75 90 76.88 9.77 10 Defect Management 1.3.2 23.75 25 30 25.63 1.09 11 Server Installation and Testing 1.3.3 95 100 120 102.50 17.36 12 Write Training documentation 1.4.1 23.75 25 30 25.63 1.09 13 Run UAT sessions 1.4.2 23.75 25 30 25.63 1.09 14 Receive and resolve UAT incidents 1.4.3 57 60 72 61.50 6.25 15 Comply with Federal Regulations 1.4.4 14.25 15 18 15.38 0.39 16 Create, review and approve deployment strategy 1.5.1 19 20 24 20.50 0.69 17 Ensure successful release/deployment 1.5.2 9.5 10 12 10.25 0.17 18 Receive signoff from the JNT Board 1.5.3 4.75 5 6 5.13 0.04 19 Start using the new application 1.5.4 9.5 10 12 10.25 0.17 20 WBS No. Work Package Cost - $K PERT Data Table BACK TO INDEX
  • 18. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 17 99% 2.330 914.11 0.99 95% 1.648 906.07 0.95 90% 1.281 901.74 0.90 75% 0.675 894.59 0.75 50% 0.000 886.63 0.50 25% -0.675 878.66 0.25 10% -1.281 871.51 0.10 5% -1.684 866.76 0.05 1% -2.330 859.14 0.01 Conf. Level Z Factor Cost $K Conf. Level Cost Data Table Confidence Level ∑Ce ∑Vc 99% 95% 90% 75% 50% 25% 10% 5% 1% Total Network 886.63 139.19 914.11 906.07 901.74 894.59 886.63 878.66 871.51 866.76 859.14 Conf. Level Data Table Probability Dist. Data Table BACK TO INDEX
  • 19. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 18 BACK TO INDEX
  • 20. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 19 Project Name: Pay Load Risk No. 4, WBS 1.2.3 Prepared by: Sal Vation Date: 19 May 2016 Description of Risk Identified: Integration with 3rd party software may take longer than expected Risk Owner: Sal Vation Results from Risk Analysis: The risk rating is 2.0 out of 5.0. The probability of occurrence is 50% with potential impacts of 5 weeks delay and $32,000. The expected values are 2.5 weeks schedule delay and $16,000 over budget if no risk response is applied. Agreed Risk Response (avoidance, transference, mitigation, acceptance): mitigation Response: Perform additional research and market analysis. Hold more integration planning review meetings. Risk Response Cost Implementation duration (Optimistic, Most Likely, Pessimistic): 0.6, 1.2, 1.8 wks Te = 1.2 wks Implementation cost (Optimistic, Most Likely, Pessimistic): $800, $1,300, $1,900 Ce = $1,316 Residual Risk Level: The risk response is estimated to reduce the probability of occurrence from 50% to 25% with resulting expected values of $8,000 and 1.25 weeks of delay. Benefit/Cost Ratio: Sanity Check:  $16,000 - $8,000 - $1,316 = $6,684  2.5wks – 1.25 wks – 1.2 wks = 0.05 wks Benefit/Cost Ratios (Expected ROI from risk response)  ( $16,000 - $8,000 ) / ( $1,316 ) = $ 6.08  ( 2.5 wks – 1.25 wks ) / 1.2 wks = 1.042 Secondary Risks: None BACK TO INDEX
  • 21. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 20 Project Name: Pay Load Risk No. 2, WBS 1.3.3 Prepared by: Sal Vation Date: 19 May 2016 Description of Risk Identified: Design group may produce incomplete specifications such as missing browser compatibility Risk Owner: Sal Vation Results from Risk Analysis: The risk rating is 2.5 out of 5.0. The probability of occurrence is 50% with potential impacts of 6 weeks delay and $45,000. The expected values are 3 weeks schedule delay and $22,500 over budget if no risk response is applied. Agreed Risk Response (avoidance, transference, mitigation, acceptance): mitigation Response: Seek external expert consultant. Requires communication/networking, interviewing, and contractual agreement. Requires two meetings between consultant and design group. Risk Response Cost Implementation duration (Optimistic, Most Likely, Pessimistic): 0.8, 1.2, 2.0 wks Te = 1.267 wks Implementation cost (Optimistic, Most Likely, Pessimistic): $3000, $4500, $6500 Ce = $4583 Residual Risk Level: The risk response is estimated to reduce the probability of occurrence from 50% to 10% with resulting expected values of $4500 and 0.6 weeks of delay. Benefit/Cost Ratio: Sanity Check:  $22,500 - $4,500 - $4,583 = $13,417  3 wks – 0.6 wks – 1.267 wks = 1.133 wks Benefit/Cost Ratios (Expected ROI from risk response)  ( $22,500 - $4,500 ) / ( $4,583 ) = 3.928  ( 3 wks – 0.6 wks ) / 1.267 wks = 1.894 Secondary Risks: Bringing in expert help from outside the company may leave the technical/design team feeling insulted. This could lead to damaged egos of the design group resulting in possible turnover of core team members. BACK TO INDEX
  • 22. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 21 Project Name: Pay Load Risk No. 5, WBS 1.1.3 Prepared by: Sal Vation Date: 19 May 2016 Description of Risk Identified: New system may not be intuitive from usability standpoint and may require additional training and time for it to be effective. Risk Owner: Sal Vation Results from Risk Analysis: The risk rating is 1.0 out of 5.0. The probability of occurrence is 50% with potential impacts of 3 weeks delay and $15,000. The expected values are 1.5 weeks schedule delay and $7,500 over budget if no risk response is applied. Agreed Risk Response (avoidance, transference, mitigation, acceptance): Mitigation Response: Conduct surveys within Jack Neift Trucking company to understand how the future users rate the user interface and general flow of the software. Based on customer feedback, include additional information in the training material so the users get a better understanding without having to be retrained. Risk Response Cost: Implementation duration (Optimistic, Most Likely, Pessimistic): 0.4, 0.6, 0.8 wks Te = 0.6 wks Implementation cost (Optimistic, Most Likely, Pessimistic): $400, $550, $800 Ce = $566 Residual Risk Level: The risk response is estimated to reduce the probability of occurrence from 50% to 5% with resulting expected values of $750 and 0.15 weeks of delay. Benefit/Cost Ratio: Sanity Check:  $7,500 - $750 - $566 = $6,184  1.5wks – 0.15 wks – 0.6 wks = 0.75 wks Benefit/Cost Ratios (Expected ROI from risk response)  ( $7,500 - $750 ) / ( $566 ) = 11.92  ( 1.5 wks – 0.15 wks ) / 0.6 wks = 2.25 Secondary Risks: None BACK TO INDEX
  • 23. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 22 1. Common Cause Cost Risk Reserve As shown in the above table, the project cost estimate is $893,090 at the 50% confidence level and $912,560 at the 95% confidence level. The baseline budget will become $893,090. The common cause risk reserve will be the difference the 95% confidence level cost and the 50% confidence level cost which is: Common causes risk reserve = $912,560 - $893,090 = $19,470. BACK TO INDEX
  • 24. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 23 2. Specific Cause Cost Risk Reserve After mitigation the three high level risks have the following residual expected values for cost as described in the risk response plan section. Special Causes Risk Residual Expected Value Risk No. 2 $4,500 Risk No. 4 $8,000 Risk No. 5 $750 Total special causes cost risk reserve = $4,500 + $8,000 + $750 = $13,250 3. Management Reserve The reserve for unknown risks will be set arbitrarily at 5% of the baseline project cost or 5% x $893,090 = $44,654.5. 4. Total Cost Reserve The total cost reserve is the sum of the common causes risk, special causes risk and management reserves. Total cost reserve = $19,470+ $13250 + $44,654.5= $77,374.5 BACK TO INDEX
  • 25. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 24 1. Common Causes Schedule Risk Reserve The JNT project will be managed to achieve cost and schedule for the 50% confidence level. However, cost and schedule reserve will be allocated to provide for a 95% confidence level. There are three risk mitigation (RM) activities which will be included into existing work packages with the following mitigation duration requirements. Risk Mitigation Activity Work Package/Task No. Duration (O, M , P) RM No.4 1.2.3 0.6, 1.2, 1.8 weeks RM No.2 1.1.3 0.4, 0.6, 0.8 weeks RM No.5 1.3.3 0.8, 1.2, 2.0 weeks Risk mitigation activities No.4 & 5 will be incorporated into Work Package 1.2.3 and performed in parallel (fast tracked) with the other activities in WP 1.2.3 and will have no impact on the duration of the existing WP. Based upon the above analysis, it will be assumed that the project critical path will not change due to the three top level risk mitigation tasks. As previously shown in the quantitative schedule risk analysis, the project schedule duration estimate (critical path) is 105.3 days at the 50% confidence level and 116.2 days at the 95% confidence level. Common causes schedule risk reserve is 116.2 days - 105.3 days = 10.9` days. 2. Special Causes Schedule Risk Reserve After risk mitigation the three high level risks have the following residual expected values as described in the risk response plan section. Special Causes Risk Residual Expected Value Risk No. 4 1.25 week or 6.25 days Risk No. 2 0.6 week or 3 days Risk No. 5 .15 week or .75 days BACK TO INDEX
  • 26. PIRM PROJECT PLAN TEAM MUSK Pay Load: Jack Neift Trucking Co. 25 Since Risk No. 2 is not on the critical path and has slack of 3 days, its residual expected duration value of 3 days will not affect the overall project duration and will not be added to the special causes schedule reserve. Total special causes schedule risk reserve = 6.25 days + .75 days = 7 days 3. Management Reserve The reserve for unknown risks will be arbitrarily set at 5% of the baseline project schedule. Management reserve = 5% x 105.3 = 5.26 days. 4. Total Schedule Risk Reserve The total schedule reserve is the sum of the common causes risk, special causes risk and management reserves. Total schedule reserve = 10.9 days + 7 days + 5.26 days = 23.16 days BACK TO INDEX