SlideShare ist ein Scribd-Unternehmen logo
1 von 34
Downloaden Sie, um offline zu lesen
1
Non-Technical Requirements (NTR)
Management in the Bid & Project
Phases
Given by:
Adrian Armorer, eng, MPM, PMP
Qualtiy Assurance Manager, Development
Thales Canada Avionics
Adrian Armorer, eng, MPM, PMP
Aerospace/Avionics experience dating back to 2008
Bachelor of Mechanical Engineering, Concordia
University, 2006
Master’s of Project Management, UQAM, 2013
2
Agenda for the Conference:
Introduction
• What is a Non Technical Requirement?
• Why do Non Technical Requirements need to be managed?
The Process
• Bid Phase
• Project Phase
Best Practices
Discussion and Questions
3
What is a Non-Technical
Requirement?
4
5
 Technical Requirement are dealt with in a complete
different way and are out of scope of this presentation
 Sometimes known as a “Non-Functional Requirement
‘’Any requirement that does not directly impact
the fit, form or function of the product”
Thales Avionics Definition
6
An NTR Example for the purposes of our
discussion:
The first 50 function changes between Joint Definition
Phase (JDP) and Safety of Flight shall be free of charge to
the buyer. The first 25 function changes between First
Flight and Certification shall be free of charge to the
buyer.
Why manage Non-Technical
Requirements?
7
Why Manage Non-Technical Requirements?
8
• Varied, Complex and Far-Reaching
• Cost Drivers
• Required by AS9100
• Customer Satisfaction
NTRs are Varied, Complex and Far-Reaching
• 3 Levels of Requirements can Easily be Flowed Down by
Airframers/Tier 1 firms
9
NTRs are Cost Drivers
• Project/Bid teams reviewing NTRs can spot cost drivers
that generalists can overlook
• Will influence project planning
10
• Examples include: First Article Inspection
System, Document Retention, Safety
Stocks
Required by the Aerospace Quality Management Standard
• Sections 7.2.1 & 7.2.2 of AS9100C relate to requirement
management
11
NTRs Directly Impact Customer Satisfaction
12
PMBOK- From Chapter 5, Scope Management
13
Two Global Standards…
14
…Aligned
Non-Technical Requirement
Management
The Bid Phase
15
Bid and Project Lifecycle
16
Bid or No Bid Decision: Start
of NTR Management
NTR Management
continues until project
closure
Step 1: Capture and Allocate NTRs
• All potential NTRs (contract, SOW, Service Agreement,
etc) are captured, and copied into the matrix
• Initial analysis of NTRs to distinguish from non-
requirements, technical requirements, etc.
• Assigning of NTRs to project work package managers
17
18
PM has proposed this requirement
responsibility to these WPs. Quality
has rejected at this point. Programs
wants to be informed only.
Supply Chain has accepted
responsibility to investigate
compliance into this requirement
Non-Requirements are always
“accepted” by Programs
Step 2: Determining the Nature of the
Requirement
• All requirements must be categorized:
• “in referential”
• Specific NTR
• Special NTR
• Technical Req.
• “Special Requirements” and “Critical Items” are AS9100
concepts that our industry is required to address.
• All requirements must be defined as “critical” or “not”.
19
Step 2: Determining the Nature of the
Requirement (cont’d)
20
Step 2: Determining the Nature of the
Requirement (con’t)
• Technical Requirement
• Requirement judged technical after analysis. Maintained in
the matrix for document integrity
• Special NTR
• Based on AS9100C, chapter 3.2
• Critical Item
• Based on AS9100C, chapter 3.3
21
Step 3: Compliance to the Requirement
• “in referential” requirements are by definition compliant
• Specific, Special NTRs are judged as compliant (C),
partially compliant (PC) or non-compliant (NC) with
justification for the PC and NC.
• Preliminary risk register is populated with Special NTRs
and Critical Items
22
Step 3: Compliance to the Requirement
23
Step 3: Compliance to the Requirement (cont’d)
• First draft of NTR matrix is an input for project estimates.
• The Matrix iterates over the course of the bid!
• Estimates need to be adjusted based on evolving
compliance
• Final compliance matrix frozen at project award.
• Must reflect the contract signed
24
Non-Technical Requirement
Management
The Project Phase
25
26
Non-Technical Requirement
Management
Best Practices
27
Best Practices
• NTRs can be used as negotiating leverage during the
bid phase
• If a non-compliant requirement is accepted without
a scope change a risk should be raised
28
• Propose to the customer to contractualize any
compliance matrices from the bid phase
29
• Include NTR reviews in project schedules
• Include as a comment the justification of
critical and special requirements.
30
31
• Any Suggestions???
32
Questions ?
33
Prochaine conférence
24 novembre 2015
Gestion de requis des clients dans
le développement d’un nouvel avion
avec
Monsieur André Blanchet
Spécialiste Programme et Chef de Groupe
Ingénierie Clientèle Avions C Series
34
Prochaine conférence
24 novembre 2015
Gestion de requis des clients dans
le développement d’un nouvel avion
avec
Monsieur André Blanchet
Spécialiste Programme et Chef de Groupe
Ingénierie Clientèle Avions C Series

Weitere ähnliche Inhalte

Was ist angesagt?

GSEP - PROCESS AND CHECKPOINT
GSEP - PROCESS AND CHECKPOINTGSEP - PROCESS AND CHECKPOINT
GSEP - PROCESS AND CHECKPOINT
Alex Himmelberg
 
Requirement verification & validation
Requirement verification & validationRequirement verification & validation
Requirement verification & validation
Abdul Basit
 
Day 8 fundamentals of_test_closure_v_1.0
Day 8 fundamentals of_test_closure_v_1.0Day 8 fundamentals of_test_closure_v_1.0
Day 8 fundamentals of_test_closure_v_1.0
Raul Chandralez
 
Static analysis and reliability testing (CS 5032 2012)
Static analysis and reliability testing (CS 5032 2012)Static analysis and reliability testing (CS 5032 2012)
Static analysis and reliability testing (CS 5032 2012)
Ian Sommerville
 

Was ist angesagt? (20)

Software Engineering (Testing Activities, Management, and Automation)
Software Engineering (Testing Activities, Management, and Automation)Software Engineering (Testing Activities, Management, and Automation)
Software Engineering (Testing Activities, Management, and Automation)
 
V sdlc se
V sdlc   seV sdlc   se
V sdlc se
 
Presentation V Model
Presentation V ModelPresentation V Model
Presentation V Model
 
GSEP - PROCESS AND CHECKPOINT
GSEP - PROCESS AND CHECKPOINTGSEP - PROCESS AND CHECKPOINT
GSEP - PROCESS AND CHECKPOINT
 
InHand's Project Developement Process
InHand's Project Developement Process InHand's Project Developement Process
InHand's Project Developement Process
 
Software Engineering (Software Process: A Generic View)
Software Engineering (Software Process: A Generic View)Software Engineering (Software Process: A Generic View)
Software Engineering (Software Process: A Generic View)
 
Understanding DO-178: Importance and How It Affects Your Company
Understanding DO-178: Importance and How It Affects Your CompanyUnderstanding DO-178: Importance and How It Affects Your Company
Understanding DO-178: Importance and How It Affects Your Company
 
WaterFall Model & Spiral Mode
WaterFall Model & Spiral ModeWaterFall Model & Spiral Mode
WaterFall Model & Spiral Mode
 
Software Engineering (Software Quality Assurance & Testing: Supplementary Mat...
Software Engineering (Software Quality Assurance & Testing: Supplementary Mat...Software Engineering (Software Quality Assurance & Testing: Supplementary Mat...
Software Engineering (Software Quality Assurance & Testing: Supplementary Mat...
 
Aktuelle BPM-Erfahrungen aus komplexen Branchen. Rainer Elvermann, cbprocess
Aktuelle BPM-Erfahrungen aus komplexen Branchen. Rainer Elvermann, cbprocessAktuelle BPM-Erfahrungen aus komplexen Branchen. Rainer Elvermann, cbprocess
Aktuelle BPM-Erfahrungen aus komplexen Branchen. Rainer Elvermann, cbprocess
 
Software Engineering (Testing Overview)
Software Engineering (Testing Overview)Software Engineering (Testing Overview)
Software Engineering (Testing Overview)
 
class 2.pptx
class 2.pptxclass 2.pptx
class 2.pptx
 
Marjuni.
Marjuni.Marjuni.
Marjuni.
 
Softwarequalityassurance with Abu ul hassan Sahadvi
Softwarequalityassurance with Abu ul hassan SahadviSoftwarequalityassurance with Abu ul hassan Sahadvi
Softwarequalityassurance with Abu ul hassan Sahadvi
 
Requirement verification & validation
Requirement verification & validationRequirement verification & validation
Requirement verification & validation
 
Day 8 fundamentals of_test_closure_v_1.0
Day 8 fundamentals of_test_closure_v_1.0Day 8 fundamentals of_test_closure_v_1.0
Day 8 fundamentals of_test_closure_v_1.0
 
V Model and W Model
V Model and W ModelV Model and W Model
V Model and W Model
 
Change management roles
Change management rolesChange management roles
Change management roles
 
Automated Analysis of Natural-Language Requirements: Industrial Needs and Opp...
Automated Analysis of Natural-Language Requirements: Industrial Needs and Opp...Automated Analysis of Natural-Language Requirements: Industrial Needs and Opp...
Automated Analysis of Natural-Language Requirements: Industrial Needs and Opp...
 
Static analysis and reliability testing (CS 5032 2012)
Static analysis and reliability testing (CS 5032 2012)Static analysis and reliability testing (CS 5032 2012)
Static analysis and reliability testing (CS 5032 2012)
 

Andere mochten auch

Technical non-technical-requirement-of-cots-selection
Technical non-technical-requirement-of-cots-selectionTechnical non-technical-requirement-of-cots-selection
Technical non-technical-requirement-of-cots-selection
Saransh Garg
 
APMP Foundation: Proposal Process Management
APMP Foundation: Proposal Process ManagementAPMP Foundation: Proposal Process Management
APMP Foundation: Proposal Process Management
Bid to Win Ltd
 

Andere mochten auch (20)

NDAS
NDASNDAS
NDAS
 
North America Aerospace Project
North America Aerospace ProjectNorth America Aerospace Project
North America Aerospace Project
 
eInfochips Avionics Capabilities
eInfochips Avionics CapabilitieseInfochips Avionics Capabilities
eInfochips Avionics Capabilities
 
Aerospace Project Integration at OPAL-RT
Aerospace Project Integration at OPAL-RT Aerospace Project Integration at OPAL-RT
Aerospace Project Integration at OPAL-RT
 
Technical non-technical-requirement-of-cots-selection
Technical non-technical-requirement-of-cots-selectionTechnical non-technical-requirement-of-cots-selection
Technical non-technical-requirement-of-cots-selection
 
IT Services Bid Management Enabling Framework
IT Services Bid Management Enabling FrameworkIT Services Bid Management Enabling Framework
IT Services Bid Management Enabling Framework
 
Everything Old is New Again: Getting the Most Out of Your Email Newsletters
Everything Old is New Again: Getting the Most Out of Your Email NewslettersEverything Old is New Again: Getting the Most Out of Your Email Newsletters
Everything Old is New Again: Getting the Most Out of Your Email Newsletters
 
Introduction E-Business & Digital Transformation
Introduction E-Business & Digital TransformationIntroduction E-Business & Digital Transformation
Introduction E-Business & Digital Transformation
 
TRIZ for Information Era, Artificial Intelligence and Systems with a Mind
TRIZ for Information Era, Artificial Intelligence and Systems with a MindTRIZ for Information Era, Artificial Intelligence and Systems with a Mind
TRIZ for Information Era, Artificial Intelligence and Systems with a Mind
 
Ten Slides in Ten Minutes - Bid Management versus Project Management
Ten Slides in Ten Minutes - Bid Management versus Project ManagementTen Slides in Ten Minutes - Bid Management versus Project Management
Ten Slides in Ten Minutes - Bid Management versus Project Management
 
2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...
2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...
2014 PV Performance Modeling Workshop: Optimization strategies with Pvsyst fo...
 
Winning Bid
Winning BidWinning Bid
Winning Bid
 
Accenture’s Change Management Strategy for Workday
Accenture’s Change Management Strategy for WorkdayAccenture’s Change Management Strategy for Workday
Accenture’s Change Management Strategy for Workday
 
Accenture Technology Vision for Workday 2016:People First: The primacy of pe...
Accenture Technology Vision for Workday 2016:People First: The primacy of pe...Accenture Technology Vision for Workday 2016:People First: The primacy of pe...
Accenture Technology Vision for Workday 2016:People First: The primacy of pe...
 
APMP Foundation: Proposal Process Management
APMP Foundation: Proposal Process ManagementAPMP Foundation: Proposal Process Management
APMP Foundation: Proposal Process Management
 
Digital Social Justice
Digital Social JusticeDigital Social Justice
Digital Social Justice
 
Work Samples - ASB Digital Savvy Workforce (2013)
Work Samples - ASB Digital Savvy Workforce (2013)Work Samples - ASB Digital Savvy Workforce (2013)
Work Samples - ASB Digital Savvy Workforce (2013)
 
The Digital Leader's New Clothes
The Digital Leader's New ClothesThe Digital Leader's New Clothes
The Digital Leader's New Clothes
 
Multidevice Mambo
Multidevice MamboMultidevice Mambo
Multidevice Mambo
 
Change the World - One Trillion Dollar Market at a time / the opportunity in ...
Change the World - One Trillion Dollar Market at a time / the opportunity in ...Change the World - One Trillion Dollar Market at a time / the opportunity in ...
Change the World - One Trillion Dollar Market at a time / the opportunity in ...
 

Ähnlich wie Aerospace Project Management : Non-Technical Requirements Management in the Bid and Project Phases

Applications Engineer Electrical Sr Specialist
Applications Engineer   Electrical Sr SpecialistApplications Engineer   Electrical Sr Specialist
Applications Engineer Electrical Sr Specialist
mbarulic
 
Week 1 lecture 2 - introduction to re
Week 1   lecture 2 - introduction to reWeek 1   lecture 2 - introduction to re
Week 1 lecture 2 - introduction to re
Hoo Jason
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
jitendra kumar biswas
 
Welding Construction Mngmt_revert
Welding Construction Mngmt_revertWelding Construction Mngmt_revert
Welding Construction Mngmt_revert
Mike Lewin
 
Using Doors® And Taug2® To Support A Simplified
Using Doors® And Taug2® To Support A SimplifiedUsing Doors® And Taug2® To Support A Simplified
Using Doors® And Taug2® To Support A Simplified
cbb010
 
IT Services Management
IT Services ManagementIT Services Management
IT Services Management
Chetan Goenka
 
New York City Department of Buildings Filing rep course_105
New York City Department of Buildings Filing rep course_105New York City Department of Buildings Filing rep course_105
New York City Department of Buildings Filing rep course_105
Safe Rise
 

Ähnlich wie Aerospace Project Management : Non-Technical Requirements Management in the Bid and Project Phases (20)

Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
Requirement phase testing
Requirement phase testingRequirement phase testing
Requirement phase testing
 
Applications Engineer Electrical Sr Specialist
Applications Engineer   Electrical Sr SpecialistApplications Engineer   Electrical Sr Specialist
Applications Engineer Electrical Sr Specialist
 
Owner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilitiesOwner's engineer services - statement of capabilities
Owner's engineer services - statement of capabilities
 
Week 1 lecture 2 - introduction to re
Week 1   lecture 2 - introduction to reWeek 1   lecture 2 - introduction to re
Week 1 lecture 2 - introduction to re
 
Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02Gensolownersengineerservices 140323094758-phpapp02
Gensolownersengineerservices 140323094758-phpapp02
 
Study on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction IndustryStudy on Procurement Method Selection Procedure in Construction Industry
Study on Procurement Method Selection Procedure in Construction Industry
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Welding Construction Mngmt_revert
Welding Construction Mngmt_revertWelding Construction Mngmt_revert
Welding Construction Mngmt_revert
 
Analyst360 2
Analyst360 2Analyst360 2
Analyst360 2
 
Business analyst| Murex training at Analyst360
Business analyst| Murex training at Analyst360Business analyst| Murex training at Analyst360
Business analyst| Murex training at Analyst360
 
Req.Management & Analysis.pptx
Req.Management & Analysis.pptxReq.Management & Analysis.pptx
Req.Management & Analysis.pptx
 
Using Doors® And Taug2® To Support A Simplified
Using Doors® And Taug2® To Support A SimplifiedUsing Doors® And Taug2® To Support A Simplified
Using Doors® And Taug2® To Support A Simplified
 
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
ASSET LIFE CYCLE COST ESTIMATING AND THE CCRG Rev4
 
CCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference SeminarCCRG 2005 Alberta Assessors Association Conference Seminar
CCRG 2005 Alberta Assessors Association Conference Seminar
 
Microsoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case StudiesMicrosoft Dynamics AX Implementation Stabilization Case Studies
Microsoft Dynamics AX Implementation Stabilization Case Studies
 
IT Services Management
IT Services ManagementIT Services Management
IT Services Management
 
Technical evaluation in cpv systems
Technical evaluation in cpv systemsTechnical evaluation in cpv systems
Technical evaluation in cpv systems
 
New York City Department of Buildings Filing rep course_105
New York City Department of Buildings Filing rep course_105New York City Department of Buildings Filing rep course_105
New York City Department of Buildings Filing rep course_105
 
Data Centers Commissioning
Data Centers Commissioning Data Centers Commissioning
Data Centers Commissioning
 

Mehr von PMI-Montréal

La mobilisation des équipes de projets pour sortir gagnant de la crise
La mobilisation des équipes de projets pour sortir gagnant de la criseLa mobilisation des équipes de projets pour sortir gagnant de la crise
La mobilisation des équipes de projets pour sortir gagnant de la crise
PMI-Montréal
 

Mehr von PMI-Montréal (20)

La mobilisation des équipes de projets pour sortir gagnant de la crise
La mobilisation des équipes de projets pour sortir gagnant de la criseLa mobilisation des équipes de projets pour sortir gagnant de la crise
La mobilisation des équipes de projets pour sortir gagnant de la crise
 
Adoption du changement : êtes-vous prêts?
Adoption du changement : êtes-vous prêts?Adoption du changement : êtes-vous prêts?
Adoption du changement : êtes-vous prêts?
 
Workshop - Lean change & the gang
Workshop - Lean change & the gangWorkshop - Lean change & the gang
Workshop - Lean change & the gang
 
Mentorat du PMI-Montréal - Séance informative mai 2020
Mentorat du PMI-Montréal - Séance informative mai 2020Mentorat du PMI-Montréal - Séance informative mai 2020
Mentorat du PMI-Montréal - Séance informative mai 2020
 
Désinfection (COVID-19) Ce que vous devez savoir pour un chantier productif
Désinfection (COVID-19) Ce que vous devez savoir pour un chantier productifDésinfection (COVID-19) Ce que vous devez savoir pour un chantier productif
Désinfection (COVID-19) Ce que vous devez savoir pour un chantier productif
 
Leadership responsable : mettez votre masque d’oxygène en premier!
Leadership responsable : mettez votre masque d’oxygène en premier!Leadership responsable : mettez votre masque d’oxygène en premier!
Leadership responsable : mettez votre masque d’oxygène en premier!
 
Delegation Poker - Responsabilisez vos équipes et amenez-les vers une grande ...
Delegation Poker - Responsabilisez vos équipes et amenez-les vers une grande ...Delegation Poker - Responsabilisez vos équipes et amenez-les vers une grande ...
Delegation Poker - Responsabilisez vos équipes et amenez-les vers une grande ...
 
Agile et gestion du changement - Au-delà du Manifeste et de la méthodologie
Agile et gestion du changement -  Au-delà du Manifeste et de la méthodologie Agile et gestion du changement -  Au-delà du Manifeste et de la méthodologie
Agile et gestion du changement - Au-delà du Manifeste et de la méthodologie
 
Agilité comportementale – Comment adapter ses comportements en temps de crise...
Agilité comportementale – Comment adapter ses comportements en temps de crise...Agilité comportementale – Comment adapter ses comportements en temps de crise...
Agilité comportementale – Comment adapter ses comportements en temps de crise...
 
Le Design Thinking : Penser et agir autrement pour trouver des solutions diff...
Le Design Thinking : Penser et agir autrement pour trouver des solutions diff...Le Design Thinking : Penser et agir autrement pour trouver des solutions diff...
Le Design Thinking : Penser et agir autrement pour trouver des solutions diff...
 
COVID-19 et Télétravail - Comment garder votre équipe de projet productive et...
COVID-19 et Télétravail - Comment garder votre équipe de projet productive et...COVID-19 et Télétravail - Comment garder votre équipe de projet productive et...
COVID-19 et Télétravail - Comment garder votre équipe de projet productive et...
 
Matinee PMI-Montréal - Softskills, incontournable pour l'ingénieur en gestion...
Matinee PMI-Montréal - Softskills, incontournable pour l'ingénieur en gestion...Matinee PMI-Montréal - Softskills, incontournable pour l'ingénieur en gestion...
Matinee PMI-Montréal - Softskills, incontournable pour l'ingénieur en gestion...
 
Matinée 11 février 2020 - Priorisation d'un portefeuille de projet
Matinée 11 février 2020 - Priorisation d'un portefeuille de projetMatinée 11 février 2020 - Priorisation d'un portefeuille de projet
Matinée 11 février 2020 - Priorisation d'un portefeuille de projet
 
Comment animer un atelier de gestion de risques?
Comment animer un atelier de gestion de risques?Comment animer un atelier de gestion de risques?
Comment animer un atelier de gestion de risques?
 
Se réapproprier la gestion BIM avec annexes
Se réapproprier la gestion BIM avec annexesSe réapproprier la gestion BIM avec annexes
Se réapproprier la gestion BIM avec annexes
 
MATINÉE - BÂTIR UN PROJET DE VILLE/DESTINATION INTELLIGENTE : ENTRE L'UTOPIE ...
MATINÉE - BÂTIR UN PROJET DE VILLE/DESTINATION INTELLIGENTE : ENTRE L'UTOPIE ...MATINÉE - BÂTIR UN PROJET DE VILLE/DESTINATION INTELLIGENTE : ENTRE L'UTOPIE ...
MATINÉE - BÂTIR UN PROJET DE VILLE/DESTINATION INTELLIGENTE : ENTRE L'UTOPIE ...
 
La gestion de projet dans l'industrie 4.0
La gestion de projet dans l'industrie 4.0La gestion de projet dans l'industrie 4.0
La gestion de projet dans l'industrie 4.0
 
Matinée PMI - De gestionnaire de projet à producteur exécutif!
Matinée PMI - De gestionnaire de projet à producteur exécutif!Matinée PMI - De gestionnaire de projet à producteur exécutif!
Matinée PMI - De gestionnaire de projet à producteur exécutif!
 
PMI-Montréal - protection des données conformité gouvernance 2019 06
PMI-Montréal - protection des données conformité gouvernance 2019 06 PMI-Montréal - protection des données conformité gouvernance 2019 06
PMI-Montréal - protection des données conformité gouvernance 2019 06
 
Symposium 2019 : Quand l'industrie des technologies se mobilise
Symposium 2019 : Quand l'industrie des technologies se mobiliseSymposium 2019 : Quand l'industrie des technologies se mobilise
Symposium 2019 : Quand l'industrie des technologies se mobilise
 

Kürzlich hochgeladen

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 

Kürzlich hochgeladen (20)

Micro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdfMicro-Scholarship, What it is, How can it help me.pdf
Micro-Scholarship, What it is, How can it help me.pdf
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 
The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
Beyond_Borders_Understanding_Anime_and_Manga_Fandom_A_Comprehensive_Audience_...
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Wellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptxWellbeing inclusion and digital dystopias.pptx
Wellbeing inclusion and digital dystopias.pptx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 

Aerospace Project Management : Non-Technical Requirements Management in the Bid and Project Phases

  • 1. 1 Non-Technical Requirements (NTR) Management in the Bid & Project Phases Given by: Adrian Armorer, eng, MPM, PMP Qualtiy Assurance Manager, Development Thales Canada Avionics
  • 2. Adrian Armorer, eng, MPM, PMP Aerospace/Avionics experience dating back to 2008 Bachelor of Mechanical Engineering, Concordia University, 2006 Master’s of Project Management, UQAM, 2013 2
  • 3. Agenda for the Conference: Introduction • What is a Non Technical Requirement? • Why do Non Technical Requirements need to be managed? The Process • Bid Phase • Project Phase Best Practices Discussion and Questions 3
  • 4. What is a Non-Technical Requirement? 4
  • 5. 5  Technical Requirement are dealt with in a complete different way and are out of scope of this presentation  Sometimes known as a “Non-Functional Requirement ‘’Any requirement that does not directly impact the fit, form or function of the product” Thales Avionics Definition
  • 6. 6 An NTR Example for the purposes of our discussion: The first 50 function changes between Joint Definition Phase (JDP) and Safety of Flight shall be free of charge to the buyer. The first 25 function changes between First Flight and Certification shall be free of charge to the buyer.
  • 8. Why Manage Non-Technical Requirements? 8 • Varied, Complex and Far-Reaching • Cost Drivers • Required by AS9100 • Customer Satisfaction
  • 9. NTRs are Varied, Complex and Far-Reaching • 3 Levels of Requirements can Easily be Flowed Down by Airframers/Tier 1 firms 9
  • 10. NTRs are Cost Drivers • Project/Bid teams reviewing NTRs can spot cost drivers that generalists can overlook • Will influence project planning 10 • Examples include: First Article Inspection System, Document Retention, Safety Stocks
  • 11. Required by the Aerospace Quality Management Standard • Sections 7.2.1 & 7.2.2 of AS9100C relate to requirement management 11
  • 12. NTRs Directly Impact Customer Satisfaction 12
  • 13. PMBOK- From Chapter 5, Scope Management 13
  • 16. Bid and Project Lifecycle 16 Bid or No Bid Decision: Start of NTR Management NTR Management continues until project closure
  • 17. Step 1: Capture and Allocate NTRs • All potential NTRs (contract, SOW, Service Agreement, etc) are captured, and copied into the matrix • Initial analysis of NTRs to distinguish from non- requirements, technical requirements, etc. • Assigning of NTRs to project work package managers 17
  • 18. 18 PM has proposed this requirement responsibility to these WPs. Quality has rejected at this point. Programs wants to be informed only. Supply Chain has accepted responsibility to investigate compliance into this requirement Non-Requirements are always “accepted” by Programs
  • 19. Step 2: Determining the Nature of the Requirement • All requirements must be categorized: • “in referential” • Specific NTR • Special NTR • Technical Req. • “Special Requirements” and “Critical Items” are AS9100 concepts that our industry is required to address. • All requirements must be defined as “critical” or “not”. 19
  • 20. Step 2: Determining the Nature of the Requirement (cont’d) 20
  • 21. Step 2: Determining the Nature of the Requirement (con’t) • Technical Requirement • Requirement judged technical after analysis. Maintained in the matrix for document integrity • Special NTR • Based on AS9100C, chapter 3.2 • Critical Item • Based on AS9100C, chapter 3.3 21
  • 22. Step 3: Compliance to the Requirement • “in referential” requirements are by definition compliant • Specific, Special NTRs are judged as compliant (C), partially compliant (PC) or non-compliant (NC) with justification for the PC and NC. • Preliminary risk register is populated with Special NTRs and Critical Items 22
  • 23. Step 3: Compliance to the Requirement 23
  • 24. Step 3: Compliance to the Requirement (cont’d) • First draft of NTR matrix is an input for project estimates. • The Matrix iterates over the course of the bid! • Estimates need to be adjusted based on evolving compliance • Final compliance matrix frozen at project award. • Must reflect the contract signed 24
  • 26. 26
  • 28. Best Practices • NTRs can be used as negotiating leverage during the bid phase • If a non-compliant requirement is accepted without a scope change a risk should be raised 28
  • 29. • Propose to the customer to contractualize any compliance matrices from the bid phase 29
  • 30. • Include NTR reviews in project schedules • Include as a comment the justification of critical and special requirements. 30
  • 31. 31
  • 34. Prochaine conférence 24 novembre 2015 Gestion de requis des clients dans le développement d’un nouvel avion avec Monsieur André Blanchet Spécialiste Programme et Chef de Groupe Ingénierie Clientèle Avions C Series 34 Prochaine conférence 24 novembre 2015 Gestion de requis des clients dans le développement d’un nouvel avion avec Monsieur André Blanchet Spécialiste Programme et Chef de Groupe Ingénierie Clientèle Avions C Series