Putting Sprint Development
Into Operation
Ensuring the delivery of a sprint
Jan-2015
www.outsystems.com© OutSystems. All Rights Reserved
Index
1. Goal of this document
2. Challenges of sprint development
3. Team roles
4. Sprint as an assembly line
5. Keep it moving!
www.outsystems.com© OutSystems. All Rights Reserved
1. Goal of this document
This is a practical guide for sprint development. It helps you focus on the main challenges found when
using Agile in the field.
Chapter 2 presents you key points for project success – along with the recommendations to address them
Chapter 4 has a visual diagram with the schedule for sprint activities, following three core principles:
1. sprint starts fully prepared (“ready”)
2. complete delivery with quality within a sprint (“done”)
3. sprint as an assembly line: how sprint activities impact next ones on the chain
Chapter 5 completes the recommendations, focusing on sprint preparation and planning.
In conclusion, the practices here proposed promote a stable, predictable and productive team pace,
resulting in quality and timely deliveries and avoiding unsustainable peaks close to delivery milestones.
This document uses, as basis, the OutSystems Delivery Method.
Target audience: Agile Project Managers (including EMs and DMs)
www.outsystems.com© OutSystems. All Rights Reserved
2. Challenges of sprint development
Focusing on the key points for success
www.outsystems.com© OutSystems. All Rights Reserved
2. Challenges of sprint development
Getting business involved and keeping up with the pace
• Especially in companies with little experience on Agile methodologies, ensuring availability of
users and their direct involvement in specific sprint stages can be as difficult as it is crucial for
project success: key-users must, definitely, be part of the team
Tips
• Key to guarantee business involvement is an early alignment of expectations: at project kick-off it must be clear why
Agile emphasizes communication and collaboration and all expected points of interaction with key-users must be
presented – and scheduled – along with what regular activities are expected from them and the effort those will take
• Scheduling regular status update meetings with business stakeholders is also highly advised to ensure full alignment
Symptoms
These emerge very soon when key-user availability is not verified: unclear priorities, difficulties preparing a sprint to
start, User Story descriptions full of unverified assumptions, demos not meeting expectations, delivered User Stories are
not accepted by business, key-users feel “not keeping up with the pace of the dev team” … including quality issues
The sprint diagrams provided in chapters 3
and 4 can well be used for this alignment
www.outsystems.com© OutSystems. All Rights Reserved
2. Challenges of sprint development
Preparing a sprint to start
• Which is the same as saying “Meeting the definition of READY before sprint start”
• It must be clear to all team that only US that are prioritized, well defined, estimated and unblocked
from dependencies can be allowed into a sprint
• Definition of DONE for US is also part of sprint preparation: consider that a poor definition of done
means poor value for business in the end
Tips
• Planning is key to, consistently, being able to fill a sprint on time while respecting definition of READY
Symptoms
Failing at sprint preparation invariably results in failing estimations and/or quality issues as side-effect (for example
when not knowing well the acceptance criteria to meet, or when incomplete definitions and/or poor estimations result in
more effort to deliver, stealing time away from testing...)
About the activities involved in sprint preparation:
- Chapter 4 presents a recommended schedule
- Chapter 5 presents tips and best practices
www.outsystems.com© OutSystems. All Rights Reserved
2. Challenges of sprint development
Delivering with quality all User Stories of a sprint (and surviving it)
• Which is the same as saying “Meeting the definition of DONE at sprint end” and, we might add,
“without constantly having to resort to unsustainable peaks”
• First of all, this is tighly related with success on the previous challenge: only with good sprint
preparation can the team commit to the US definitions and completion be correctly evaluated
Tips
• Proper US estimation and sprint planning are at focus here: besides implementation, estimate and plan time so that
testing and handling feedback (defects but also minor changes) also occur within the sprint
Symptoms
When a sprint leaves unfinished work, affecting the delivery capacity of next sprints is hardly avoidable: beware of
“snow-ball” effects here resulting on big impacts on the full scope delivery within the available timebox
Chapters 4 and 5 propose a sizing and planning method in order to, given
good sprint preparations, consistently achieve success on sprint delivery
www.outsystems.com© OutSystems. All Rights Reserved
2. Challenges of sprint development
Fitting demo feedback into the timebox
• Agile highlights the need of good US definitions but also the need to adapt and tune, which comes
naturally from the promoted collaboration during demos
• Pre-reserve, in US estimations, effort for handling feedback related to minor changes
• Major changes must result in new US: do check if the initial sizing of the release reserved some
capacity for these (which can occur, depending on the available information and maturity of
requirements at the time of project budgeting)
Tips
• Know your timebox! Sometimes it doesn’t fit and timebox control must be strict to quickly show it: “something goes in,
something goes out”
• In these situations backlog negotiation is mandatory to keep it healthy
www.outsystems.com© OutSystems. All Rights Reserved
2. Challenges of sprint development
Improving team performance
• Learning from the experience and immediately applying any resulting lessons to the way that team
is working should not be as hard as changing a tire while driving
• More details are available in the OutSystems Delivery Method, Sprint Development stage
checklist and practices
Tips
• Do not underestimate the value of sprint retrospectives: do it regularly within the development team but sometimes
also involving the customer (eventually on a dedicated session), as a way of ensuring full alignment and allowing
improvement also on this side
www.outsystems.com© OutSystems. All Rights Reserved
3. Team roles
Before further analyzing sprint activities let’s have a
quick overview of their executors:
- their main responsibilities
- and recommended availability pattern
www.outsystems.com© OutSystems. All Rights Reserved
3. Team roles: main responsibilities
Key-User
• Clarifies processes and prioritizes requirements
• Attends demos and performs acceptance testing
• At least one key-user should have the
responsibility to gather peer consensus and be
their representative
Project Leader
• Portfolio, budget and project management
• Prioritizes requirements
Business Analyst
• Promotes the complete definition of business
processes next to key-users
• Clarifies processes and prioritizes requirements
towards dev team
• Performs acceptance testing and demos to
business
Tests Coordinator
• Defines test plan for each User Story
• Performs acceptance testing
• Coordinates all tests executed on customer side
(including ones done by key-users and BA)
Engagement Manager
• Maps business vision to a workable solution
design and architecture
• Maintains stakeholders and team aligned with the
business case and with what users really need
• Fufills the role of Business Analyst or Tests
Coordinator when these are are not available
Delivery Manager
• Leads and controls the development team
• Responsible for delivery and for the implemented
technical solution
Developer
• Implements the technical solution
www.outsystems.com© OutSystems. All Rights Reserved
3. Team roles: recommended availability pattern
Sprint 1 Sprint 2 ... Sprint n Sol. Release
Pr. Leader
BA
Tests Coord.
EM
DM
Developer
Release X
Key-User
2 x full time
full time
half time
half to full time full time
half to 2 x full time 1 to 2 x full time
10 to 14h / week
5 to 10h / week 8 to 14h / week
Go Live
scenario with an OutSystems Team “Core” with 2 Dev
up to full time if no BA and/or no Tests Coordinator
www.outsystems.com© OutSystems. All Rights Reserved
4. Sprint as an assembly line
An assembly line provides a very good analogy to
sprint development:
A stage incorrectly or untimely executed results in
less productivity or quality issues for following
stages
www.outsystems.com© OutSystems. All Rights Reserved
4. Sprint as an assembly line
Analysis
Sprint n Sprint n+1Sprint n-1
Int.
demo
User
demo
Delivery Stabilizing
Analysis
& Design
Int.
demo
Settle
ment
Test
plan
Settl.,
A&D
Design
Settl.,
A&D
US
clarification Acceptance testing
Acceptance testing
Portfolio
management
Settle
ment
US
clarification
Implementation
& Testing Stabilizing
Delivery
US
clarification
User
demo
Acc.
testing
Settle
ment
User
demo
M T W T F M T W T F M T W T F M T W T F M T W T F M T W T F
User
demo
Int.
demo
Int.
demo
- Activities related to sprint n start on sprint n-1 and finish on sprint n+1
- For a sprint to be fully delivered until its last day all prior activities in the chain must have been successfully and timely executed
- Take special attention also to the recommended schedule for completing the preparation of a sprint before its start
Pr. Leader
BA
Tests Coord.
EM
DM
Developer
Key-User
www.outsystems.com© OutSystems. All Rights Reserved
4. Sprint as an assembly line
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10
Sprint n n+1n-1
User demo
presents
Int. demo
attends
Acceptance testing
Delivery Demo, testing & stabilizingDesign
US clarification
Int. demo
attends
Portfolio management
US clarification
Implementation & testing Stabilizing
DeliveryAnalysis & design Int. demo
presents
Int. demo
attends
User demo
attends
User demo
attends
User demo
attends
- Let’s focus on sprint n timeline
- Schedule of activities seems easily achievable, right?
Pr. Leader
BA
Tests Coord.
EM
DM
Developer
Key-User
www.outsystems.com© OutSystems. All Rights Reserved
4. Sprint as an assembly line
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10
Sprint n n+1n-1
User demo
presents
n+1 Settl.
Priorities
Int. demo
attends
n-1 Acceptance testing Acceptance testing
Delivery Demo, testing & stabilizing
n+1 Settlement
US drill-down & sizing
n+1 Settl.
n+1 Settl.
Test plan
n+1
A&D
n+1 Settlement
US drill-down & sizing
n+1
designDesign
n and n+1 US clarification
n-1 Acceptance testing
Int. demo
attends
Portfolio management
n+1 Analysis (Processes, US)
US clarification n+1 Settlement
US, Acc. criteria
Implementation & testing Stabilizing
DeliveryAnalysis & design Int. demo
presents
Int. demo
attends
User demo
attends
n-1 Acc. testing
User demo
attends
User demo
attends
- Well, this view makes the challenge very clear: during a sprint you also need to manage activities related to previous and following ones
- The acknowledgement and understanding of this reality from all team members is crucial to have a strict and methodical following of a
fully enabling schedule such as the one here presented: otherwise, the risk of not fulfilling all activities and breaking the chain is too high
Pr. Leader
BA
Tests Coord.
EM
DM
Developer
Key-User
www.outsystems.com© OutSystems. All Rights Reserved
5. Keep it moving!
How not to break the chain
in such a tight schedule scenario
(recommendations focusing on sprint preparation and planning)
www.outsystems.com© OutSystems. All Rights Reserved
5. Keep it moving!
Analysis
• The first scope prioritization done during project
Initiation stage provides the candidate US to be
addressed in a given sprint
• Analysis must make sure that those US are well
detailed: this includes crucial aspects such as
following the INVEST principles and, often,
producing screen mockups or activity diagrams
• Results of analysis should be shared in order to
start the sprint settlement step
• More details are available in the Requirements
Gathering sections of the OutSystems Delivery
Method, which are part of the practices for
Initiation and Sprint Development stages
Tips
• To avoid impact on other sprint activities and,
therefore, causing a break on the chain, it is very
important that the schedules – such as the one
presented above (and in chapter 4) – are respected
• Considering the potential need of several iterations with
key-users that it involves, analysis phase is especially
prone to delays and must be carefully planned with
key-users
www.outsystems.com© OutSystems. All Rights Reserved
5. Keep it moving!
Settlement
• On the opening session of this sprint preparation
step, the candidate US are presented by the BA
to the EM / DM for solution design, sizing and
sprint planning and to the Tests Coordinator for
the creation of a test plan and scenarios based
on the acceptance criteria defined
• Besides implementation also unit testing,
integration testing and handling feedback
(defects and minor changes) need to be part of
the US estimation and completed within the
sprint – the US must be fully demonstrable and
testable by business by sprint end
• Sizing must be aligned with sprint planning
(following slide presents a method to achieve
this)
• Resulting sizing should be compared to the initial
sizing of the release so that relevant differences,
its causes and any impact on backlog coverage
by the timebox can be aligned with the customer
• On the closing session, EM and DM present the
understanding of US by the dev team and all
team agrees on what will be committed to deliver
in the sprint
• This understanding should also be used as the
basis for distinguishing defects from changes
www.outsystems.com© OutSystems. All Rights Reserved
5. Keep it moving!
Planning
• Define an intermediate delivery / internal demo
point, allowing full implementation and testing to
occur until then but also a stabilization period to
occur after it until the sprint demo to users
• In the stabilization period team should be fully
dedicated to handling first feedback from the
internal demo and to defect fixing (should not be
used for finishing developments)
Given good sprint preparations and sizings, this method should provide
a significant help to achieve success on most sprint deliveries
(without the need to regularly resort to unsustainable effort peaks)
Tips
• Correctly balance weight of implementation vs sprint
stabilization according to above objectives
• Rule of thumb would be having the internal demo point
around 70% of the sprint, leaving 30% for stabilization
(the example presented above and in chapter 4)
• To align sizing with sprint planning these factors should
also be used when estimating US
• Although normally stable, the factors could be tuned as
result of sprint retrospective
www.outsystems.com© OutSystems. All Rights Reserved
5. Keep it moving!
After sprint end
• Development team must focus on the topics of the new sprint
• Exception should only be made when an issue needs to be addressed to unblock the acceptance
tests
www.outsystems.com
Thank you!
Nuno Fernandes

Weitere ähnliche Inhalte

Was ist angesagt?

Introduction to Scrum.ppt
Introduction to Scrum.pptIntroduction to Scrum.ppt
Introduction to Scrum.ppt
Mohan Late
 
IIBA and Solvera May Event - Testing w Agile slides
IIBA and Solvera May Event - Testing w Agile slidesIIBA and Solvera May Event - Testing w Agile slides
IIBA and Solvera May Event - Testing w Agile slides
SaskatchewanIIBA
 

Was ist angesagt? (19)

Agile - Scrum Presentation
Agile - Scrum PresentationAgile - Scrum Presentation
Agile - Scrum Presentation
 
Five Key Numbers to Gauge your Agile Engineering Efforts
Five Key Numbers to Gauge your Agile Engineering EffortsFive Key Numbers to Gauge your Agile Engineering Efforts
Five Key Numbers to Gauge your Agile Engineering Efforts
 
Waterfall vs Agile : A Beginner's Guide in Project Management
Waterfall vs Agile : A Beginner's Guide in Project ManagementWaterfall vs Agile : A Beginner's Guide in Project Management
Waterfall vs Agile : A Beginner's Guide in Project Management
 
Scrum artifacts
Scrum artifactsScrum artifacts
Scrum artifacts
 
SAFe: An Introduction to the Scaled Agile Framework
SAFe: An Introduction to the Scaled Agile FrameworkSAFe: An Introduction to the Scaled Agile Framework
SAFe: An Introduction to the Scaled Agile Framework
 
Best Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project ManagementBest Practices When Moving To Agile Project Management
Best Practices When Moving To Agile Project Management
 
Gwc agile and scrum
Gwc agile and scrumGwc agile and scrum
Gwc agile and scrum
 
Agile project management with scrum
Agile project management with scrumAgile project management with scrum
Agile project management with scrum
 
Between Scrum and Kanban - define test process for Agile methodologies
Between Scrum and Kanban - define test process for Agile methodologiesBetween Scrum and Kanban - define test process for Agile methodologies
Between Scrum and Kanban - define test process for Agile methodologies
 
Waterfall vs agile approach scrum framework and best practices in software d...
Waterfall vs agile approach  scrum framework and best practices in software d...Waterfall vs agile approach  scrum framework and best practices in software d...
Waterfall vs agile approach scrum framework and best practices in software d...
 
Introduction to Scrum.ppt
Introduction to Scrum.pptIntroduction to Scrum.ppt
Introduction to Scrum.ppt
 
Testing in Agile Development
Testing in Agile DevelopmentTesting in Agile Development
Testing in Agile Development
 
Methodology Patterns (Agile Cambridge 2014)
Methodology Patterns (Agile Cambridge 2014)Methodology Patterns (Agile Cambridge 2014)
Methodology Patterns (Agile Cambridge 2014)
 
IIBA and Solvera May Event - Testing w Agile slides
IIBA and Solvera May Event - Testing w Agile slidesIIBA and Solvera May Event - Testing w Agile slides
IIBA and Solvera May Event - Testing w Agile slides
 
Agile Software Development Overview
Agile Software Development OverviewAgile Software Development Overview
Agile Software Development Overview
 
Scrum Methodology well elucidated
Scrum Methodology well elucidatedScrum Methodology well elucidated
Scrum Methodology well elucidated
 
Scrum referencecard
Scrum referencecardScrum referencecard
Scrum referencecard
 
Agile Scrum CMMI
Agile Scrum CMMIAgile Scrum CMMI
Agile Scrum CMMI
 
What Is Agile Scrum
What Is Agile ScrumWhat Is Agile Scrum
What Is Agile Scrum
 

Andere mochten auch

Andere mochten auch (11)

How to plan sprints in agile
How to plan sprints in agileHow to plan sprints in agile
How to plan sprints in agile
 
Agile Software Development - Learn It Yourself
Agile Software Development - Learn It YourselfAgile Software Development - Learn It Yourself
Agile Software Development - Learn It Yourself
 
Mental models for human centric leadership
Mental models for human centric leadershipMental models for human centric leadership
Mental models for human centric leadership
 
The Business Analyst And The Sdlc
The Business Analyst And The SdlcThe Business Analyst And The Sdlc
The Business Analyst And The Sdlc
 
Agile and Lean Software Development
Agile and Lean Software DevelopmentAgile and Lean Software Development
Agile and Lean Software Development
 
Conducting An Agile Retrospective
Conducting An Agile RetrospectiveConducting An Agile Retrospective
Conducting An Agile Retrospective
 
Agile Roles & responsibilities
Agile Roles & responsibilitiesAgile Roles & responsibilities
Agile Roles & responsibilities
 
Agile Product Owner in Wonderland!
Agile Product Owner in Wonderland!Agile Product Owner in Wonderland!
Agile Product Owner in Wonderland!
 
Understanding the Agile Release and Sprint Planning Process
Understanding the Agile Release and Sprint Planning Process Understanding the Agile Release and Sprint Planning Process
Understanding the Agile Release and Sprint Planning Process
 
Product Development Using Agile and Lean Principles
Product Development Using Agile and Lean PrinciplesProduct Development Using Agile and Lean Principles
Product Development Using Agile and Lean Principles
 
Creating A Product Backlog
Creating A Product BacklogCreating A Product Backlog
Creating A Product Backlog
 

Ähnlich wie Putting sprint development into operation

Deepti Debnath_Citi Corp-2015
Deepti Debnath_Citi Corp-2015 Deepti Debnath_Citi Corp-2015
Deepti Debnath_Citi Corp-2015
deepti Debnath
 
The Agile Readiness Assessment Tool Essay
The Agile Readiness Assessment Tool EssayThe Agile Readiness Assessment Tool Essay
The Agile Readiness Assessment Tool Essay
Heidi Owens
 
Presentation by saurabh chandra
Presentation by saurabh chandraPresentation by saurabh chandra
Presentation by saurabh chandra
PMI_IREP_TP
 
aw_survivalguide_r2opt
aw_survivalguide_r2optaw_survivalguide_r2opt
aw_survivalguide_r2opt
Reza Abed
 

Ähnlich wie Putting sprint development into operation (20)

Kristian Fischer - Put Test in the Driver's Seat
Kristian Fischer - Put Test in the Driver's SeatKristian Fischer - Put Test in the Driver's Seat
Kristian Fischer - Put Test in the Driver's Seat
 
Scaled agile implementation
Scaled agile implementationScaled agile implementation
Scaled agile implementation
 
Is Test Planning a lost art in Agile? by Michelle Williams
Is Test Planning a lost art in Agile? by Michelle WilliamsIs Test Planning a lost art in Agile? by Michelle Williams
Is Test Planning a lost art in Agile? by Michelle Williams
 
Deepti Debnath_Citi Corp-2015
Deepti Debnath_Citi Corp-2015 Deepti Debnath_Citi Corp-2015
Deepti Debnath_Citi Corp-2015
 
Nataraj Krishnaswamy Profile
Nataraj Krishnaswamy ProfileNataraj Krishnaswamy Profile
Nataraj Krishnaswamy Profile
 
The Agile Readiness Assessment Tool Essay
The Agile Readiness Assessment Tool EssayThe Agile Readiness Assessment Tool Essay
The Agile Readiness Assessment Tool Essay
 
Presentation by saurabh chandra
Presentation by saurabh chandraPresentation by saurabh chandra
Presentation by saurabh chandra
 
Automation Project Survival Guide.pptx
Automation Project Survival Guide.pptxAutomation Project Survival Guide.pptx
Automation Project Survival Guide.pptx
 
Test Planning and Test Estimation Techniques
Test Planning and Test Estimation TechniquesTest Planning and Test Estimation Techniques
Test Planning and Test Estimation Techniques
 
Six sigma.ppt
Six sigma.pptSix sigma.ppt
Six sigma.ppt
 
Management of time uncertainty in agile
Management of time uncertainty in agileManagement of time uncertainty in agile
Management of time uncertainty in agile
 
AgileTestStrategy.pptx
AgileTestStrategy.pptxAgileTestStrategy.pptx
AgileTestStrategy.pptx
 
aw_survivalguide_r2opt
aw_survivalguide_r2optaw_survivalguide_r2opt
aw_survivalguide_r2opt
 
Quality Testing and Agile at Salesforce
Quality Testing and Agile at Salesforce Quality Testing and Agile at Salesforce
Quality Testing and Agile at Salesforce
 
Applying both of waterfall and iterative development
Applying both of waterfall and iterative developmentApplying both of waterfall and iterative development
Applying both of waterfall and iterative development
 
Scrum Process Overview
Scrum Process OverviewScrum Process Overview
Scrum Process Overview
 
Neil Potter Presentation
Neil Potter Presentation Neil Potter Presentation
Neil Potter Presentation
 
The Case for Agile testing
The Case for Agile testingThe Case for Agile testing
The Case for Agile testing
 
5020
50205020
5020
 
Agile Model & Methodology
Agile Model & MethodologyAgile Model & Methodology
Agile Model & Methodology
 

Kürzlich hochgeladen

Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
VictoriaMetrics
 
AI Mastery 201: Elevating Your Workflow with Advanced LLM Techniques
AI Mastery 201: Elevating Your Workflow with Advanced LLM TechniquesAI Mastery 201: Elevating Your Workflow with Advanced LLM Techniques
AI Mastery 201: Elevating Your Workflow with Advanced LLM Techniques
VictorSzoltysek
 
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
masabamasaba
 
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
masabamasaba
 

Kürzlich hochgeladen (20)

AI & Machine Learning Presentation Template
AI & Machine Learning Presentation TemplateAI & Machine Learning Presentation Template
AI & Machine Learning Presentation Template
 
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
MarTech Trend 2024 Book : Marketing Technology Trends (2024 Edition) How Data...
 
%in Bahrain+277-882-255-28 abortion pills for sale in Bahrain
%in Bahrain+277-882-255-28 abortion pills for sale in Bahrain%in Bahrain+277-882-255-28 abortion pills for sale in Bahrain
%in Bahrain+277-882-255-28 abortion pills for sale in Bahrain
 
%in kempton park+277-882-255-28 abortion pills for sale in kempton park
%in kempton park+277-882-255-28 abortion pills for sale in kempton park %in kempton park+277-882-255-28 abortion pills for sale in kempton park
%in kempton park+277-882-255-28 abortion pills for sale in kempton park
 
Shapes for Sharing between Graph Data Spaces - and Epistemic Querying of RDF-...
Shapes for Sharing between Graph Data Spaces - and Epistemic Querying of RDF-...Shapes for Sharing between Graph Data Spaces - and Epistemic Querying of RDF-...
Shapes for Sharing between Graph Data Spaces - and Epistemic Querying of RDF-...
 
%in Harare+277-882-255-28 abortion pills for sale in Harare
%in Harare+277-882-255-28 abortion pills for sale in Harare%in Harare+277-882-255-28 abortion pills for sale in Harare
%in Harare+277-882-255-28 abortion pills for sale in Harare
 
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
Large-scale Logging Made Easy: Meetup at Deutsche Bank 2024
 
Introducing Microsoft’s new Enterprise Work Management (EWM) Solution
Introducing Microsoft’s new Enterprise Work Management (EWM) SolutionIntroducing Microsoft’s new Enterprise Work Management (EWM) Solution
Introducing Microsoft’s new Enterprise Work Management (EWM) Solution
 
WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...
WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...
WSO2Con2024 - From Code To Cloud: Fast Track Your Cloud Native Journey with C...
 
8257 interfacing 2 in microprocessor for btech students
8257 interfacing 2 in microprocessor for btech students8257 interfacing 2 in microprocessor for btech students
8257 interfacing 2 in microprocessor for btech students
 
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital TransformationWSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
WSO2Con2024 - WSO2's IAM Vision: Identity-Led Digital Transformation
 
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
WSO2CON 2024 - Cloud Native Middleware: Domain-Driven Design, Cell-Based Arch...
 
Define the academic and professional writing..pdf
Define the academic and professional writing..pdfDefine the academic and professional writing..pdf
Define the academic and professional writing..pdf
 
AI Mastery 201: Elevating Your Workflow with Advanced LLM Techniques
AI Mastery 201: Elevating Your Workflow with Advanced LLM TechniquesAI Mastery 201: Elevating Your Workflow with Advanced LLM Techniques
AI Mastery 201: Elevating Your Workflow with Advanced LLM Techniques
 
Direct Style Effect Systems - The Print[A] Example - A Comprehension Aid
Direct Style Effect Systems -The Print[A] Example- A Comprehension AidDirect Style Effect Systems -The Print[A] Example- A Comprehension Aid
Direct Style Effect Systems - The Print[A] Example - A Comprehension Aid
 
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
%+27788225528 love spells in Huntington Beach Psychic Readings, Attraction sp...
 
Microsoft AI Transformation Partner Playbook.pdf
Microsoft AI Transformation Partner Playbook.pdfMicrosoft AI Transformation Partner Playbook.pdf
Microsoft AI Transformation Partner Playbook.pdf
 
WSO2CON2024 - It's time to go Platformless
WSO2CON2024 - It's time to go PlatformlessWSO2CON2024 - It's time to go Platformless
WSO2CON2024 - It's time to go Platformless
 
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
%+27788225528 love spells in Colorado Springs Psychic Readings, Attraction sp...
 
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
Devoxx UK 2024 - Going serverless with Quarkus, GraalVM native images and AWS...
 

Putting sprint development into operation

  • 1. www.outsystems.com Putting Sprint Development Into Operation Ensuring the delivery of a sprint Jan-2015
  • 2. www.outsystems.com© OutSystems. All Rights Reserved Index 1. Goal of this document 2. Challenges of sprint development 3. Team roles 4. Sprint as an assembly line 5. Keep it moving!
  • 3. www.outsystems.com© OutSystems. All Rights Reserved 1. Goal of this document This is a practical guide for sprint development. It helps you focus on the main challenges found when using Agile in the field. Chapter 2 presents you key points for project success – along with the recommendations to address them Chapter 4 has a visual diagram with the schedule for sprint activities, following three core principles: 1. sprint starts fully prepared (“ready”) 2. complete delivery with quality within a sprint (“done”) 3. sprint as an assembly line: how sprint activities impact next ones on the chain Chapter 5 completes the recommendations, focusing on sprint preparation and planning. In conclusion, the practices here proposed promote a stable, predictable and productive team pace, resulting in quality and timely deliveries and avoiding unsustainable peaks close to delivery milestones. This document uses, as basis, the OutSystems Delivery Method. Target audience: Agile Project Managers (including EMs and DMs)
  • 4. www.outsystems.com© OutSystems. All Rights Reserved 2. Challenges of sprint development Focusing on the key points for success
  • 5. www.outsystems.com© OutSystems. All Rights Reserved 2. Challenges of sprint development Getting business involved and keeping up with the pace • Especially in companies with little experience on Agile methodologies, ensuring availability of users and their direct involvement in specific sprint stages can be as difficult as it is crucial for project success: key-users must, definitely, be part of the team Tips • Key to guarantee business involvement is an early alignment of expectations: at project kick-off it must be clear why Agile emphasizes communication and collaboration and all expected points of interaction with key-users must be presented – and scheduled – along with what regular activities are expected from them and the effort those will take • Scheduling regular status update meetings with business stakeholders is also highly advised to ensure full alignment Symptoms These emerge very soon when key-user availability is not verified: unclear priorities, difficulties preparing a sprint to start, User Story descriptions full of unverified assumptions, demos not meeting expectations, delivered User Stories are not accepted by business, key-users feel “not keeping up with the pace of the dev team” … including quality issues The sprint diagrams provided in chapters 3 and 4 can well be used for this alignment
  • 6. www.outsystems.com© OutSystems. All Rights Reserved 2. Challenges of sprint development Preparing a sprint to start • Which is the same as saying “Meeting the definition of READY before sprint start” • It must be clear to all team that only US that are prioritized, well defined, estimated and unblocked from dependencies can be allowed into a sprint • Definition of DONE for US is also part of sprint preparation: consider that a poor definition of done means poor value for business in the end Tips • Planning is key to, consistently, being able to fill a sprint on time while respecting definition of READY Symptoms Failing at sprint preparation invariably results in failing estimations and/or quality issues as side-effect (for example when not knowing well the acceptance criteria to meet, or when incomplete definitions and/or poor estimations result in more effort to deliver, stealing time away from testing...) About the activities involved in sprint preparation: - Chapter 4 presents a recommended schedule - Chapter 5 presents tips and best practices
  • 7. www.outsystems.com© OutSystems. All Rights Reserved 2. Challenges of sprint development Delivering with quality all User Stories of a sprint (and surviving it) • Which is the same as saying “Meeting the definition of DONE at sprint end” and, we might add, “without constantly having to resort to unsustainable peaks” • First of all, this is tighly related with success on the previous challenge: only with good sprint preparation can the team commit to the US definitions and completion be correctly evaluated Tips • Proper US estimation and sprint planning are at focus here: besides implementation, estimate and plan time so that testing and handling feedback (defects but also minor changes) also occur within the sprint Symptoms When a sprint leaves unfinished work, affecting the delivery capacity of next sprints is hardly avoidable: beware of “snow-ball” effects here resulting on big impacts on the full scope delivery within the available timebox Chapters 4 and 5 propose a sizing and planning method in order to, given good sprint preparations, consistently achieve success on sprint delivery
  • 8. www.outsystems.com© OutSystems. All Rights Reserved 2. Challenges of sprint development Fitting demo feedback into the timebox • Agile highlights the need of good US definitions but also the need to adapt and tune, which comes naturally from the promoted collaboration during demos • Pre-reserve, in US estimations, effort for handling feedback related to minor changes • Major changes must result in new US: do check if the initial sizing of the release reserved some capacity for these (which can occur, depending on the available information and maturity of requirements at the time of project budgeting) Tips • Know your timebox! Sometimes it doesn’t fit and timebox control must be strict to quickly show it: “something goes in, something goes out” • In these situations backlog negotiation is mandatory to keep it healthy
  • 9. www.outsystems.com© OutSystems. All Rights Reserved 2. Challenges of sprint development Improving team performance • Learning from the experience and immediately applying any resulting lessons to the way that team is working should not be as hard as changing a tire while driving • More details are available in the OutSystems Delivery Method, Sprint Development stage checklist and practices Tips • Do not underestimate the value of sprint retrospectives: do it regularly within the development team but sometimes also involving the customer (eventually on a dedicated session), as a way of ensuring full alignment and allowing improvement also on this side
  • 10. www.outsystems.com© OutSystems. All Rights Reserved 3. Team roles Before further analyzing sprint activities let’s have a quick overview of their executors: - their main responsibilities - and recommended availability pattern
  • 11. www.outsystems.com© OutSystems. All Rights Reserved 3. Team roles: main responsibilities Key-User • Clarifies processes and prioritizes requirements • Attends demos and performs acceptance testing • At least one key-user should have the responsibility to gather peer consensus and be their representative Project Leader • Portfolio, budget and project management • Prioritizes requirements Business Analyst • Promotes the complete definition of business processes next to key-users • Clarifies processes and prioritizes requirements towards dev team • Performs acceptance testing and demos to business Tests Coordinator • Defines test plan for each User Story • Performs acceptance testing • Coordinates all tests executed on customer side (including ones done by key-users and BA) Engagement Manager • Maps business vision to a workable solution design and architecture • Maintains stakeholders and team aligned with the business case and with what users really need • Fufills the role of Business Analyst or Tests Coordinator when these are are not available Delivery Manager • Leads and controls the development team • Responsible for delivery and for the implemented technical solution Developer • Implements the technical solution
  • 12. www.outsystems.com© OutSystems. All Rights Reserved 3. Team roles: recommended availability pattern Sprint 1 Sprint 2 ... Sprint n Sol. Release Pr. Leader BA Tests Coord. EM DM Developer Release X Key-User 2 x full time full time half time half to full time full time half to 2 x full time 1 to 2 x full time 10 to 14h / week 5 to 10h / week 8 to 14h / week Go Live scenario with an OutSystems Team “Core” with 2 Dev up to full time if no BA and/or no Tests Coordinator
  • 13. www.outsystems.com© OutSystems. All Rights Reserved 4. Sprint as an assembly line An assembly line provides a very good analogy to sprint development: A stage incorrectly or untimely executed results in less productivity or quality issues for following stages
  • 14. www.outsystems.com© OutSystems. All Rights Reserved 4. Sprint as an assembly line Analysis Sprint n Sprint n+1Sprint n-1 Int. demo User demo Delivery Stabilizing Analysis & Design Int. demo Settle ment Test plan Settl., A&D Design Settl., A&D US clarification Acceptance testing Acceptance testing Portfolio management Settle ment US clarification Implementation & Testing Stabilizing Delivery US clarification User demo Acc. testing Settle ment User demo M T W T F M T W T F M T W T F M T W T F M T W T F M T W T F User demo Int. demo Int. demo - Activities related to sprint n start on sprint n-1 and finish on sprint n+1 - For a sprint to be fully delivered until its last day all prior activities in the chain must have been successfully and timely executed - Take special attention also to the recommended schedule for completing the preparation of a sprint before its start Pr. Leader BA Tests Coord. EM DM Developer Key-User
  • 15. www.outsystems.com© OutSystems. All Rights Reserved 4. Sprint as an assembly line Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Sprint n n+1n-1 User demo presents Int. demo attends Acceptance testing Delivery Demo, testing & stabilizingDesign US clarification Int. demo attends Portfolio management US clarification Implementation & testing Stabilizing DeliveryAnalysis & design Int. demo presents Int. demo attends User demo attends User demo attends User demo attends - Let’s focus on sprint n timeline - Schedule of activities seems easily achievable, right? Pr. Leader BA Tests Coord. EM DM Developer Key-User
  • 16. www.outsystems.com© OutSystems. All Rights Reserved 4. Sprint as an assembly line Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10 Sprint n n+1n-1 User demo presents n+1 Settl. Priorities Int. demo attends n-1 Acceptance testing Acceptance testing Delivery Demo, testing & stabilizing n+1 Settlement US drill-down & sizing n+1 Settl. n+1 Settl. Test plan n+1 A&D n+1 Settlement US drill-down & sizing n+1 designDesign n and n+1 US clarification n-1 Acceptance testing Int. demo attends Portfolio management n+1 Analysis (Processes, US) US clarification n+1 Settlement US, Acc. criteria Implementation & testing Stabilizing DeliveryAnalysis & design Int. demo presents Int. demo attends User demo attends n-1 Acc. testing User demo attends User demo attends - Well, this view makes the challenge very clear: during a sprint you also need to manage activities related to previous and following ones - The acknowledgement and understanding of this reality from all team members is crucial to have a strict and methodical following of a fully enabling schedule such as the one here presented: otherwise, the risk of not fulfilling all activities and breaking the chain is too high Pr. Leader BA Tests Coord. EM DM Developer Key-User
  • 17. www.outsystems.com© OutSystems. All Rights Reserved 5. Keep it moving! How not to break the chain in such a tight schedule scenario (recommendations focusing on sprint preparation and planning)
  • 18. www.outsystems.com© OutSystems. All Rights Reserved 5. Keep it moving! Analysis • The first scope prioritization done during project Initiation stage provides the candidate US to be addressed in a given sprint • Analysis must make sure that those US are well detailed: this includes crucial aspects such as following the INVEST principles and, often, producing screen mockups or activity diagrams • Results of analysis should be shared in order to start the sprint settlement step • More details are available in the Requirements Gathering sections of the OutSystems Delivery Method, which are part of the practices for Initiation and Sprint Development stages Tips • To avoid impact on other sprint activities and, therefore, causing a break on the chain, it is very important that the schedules – such as the one presented above (and in chapter 4) – are respected • Considering the potential need of several iterations with key-users that it involves, analysis phase is especially prone to delays and must be carefully planned with key-users
  • 19. www.outsystems.com© OutSystems. All Rights Reserved 5. Keep it moving! Settlement • On the opening session of this sprint preparation step, the candidate US are presented by the BA to the EM / DM for solution design, sizing and sprint planning and to the Tests Coordinator for the creation of a test plan and scenarios based on the acceptance criteria defined • Besides implementation also unit testing, integration testing and handling feedback (defects and minor changes) need to be part of the US estimation and completed within the sprint – the US must be fully demonstrable and testable by business by sprint end • Sizing must be aligned with sprint planning (following slide presents a method to achieve this) • Resulting sizing should be compared to the initial sizing of the release so that relevant differences, its causes and any impact on backlog coverage by the timebox can be aligned with the customer • On the closing session, EM and DM present the understanding of US by the dev team and all team agrees on what will be committed to deliver in the sprint • This understanding should also be used as the basis for distinguishing defects from changes
  • 20. www.outsystems.com© OutSystems. All Rights Reserved 5. Keep it moving! Planning • Define an intermediate delivery / internal demo point, allowing full implementation and testing to occur until then but also a stabilization period to occur after it until the sprint demo to users • In the stabilization period team should be fully dedicated to handling first feedback from the internal demo and to defect fixing (should not be used for finishing developments) Given good sprint preparations and sizings, this method should provide a significant help to achieve success on most sprint deliveries (without the need to regularly resort to unsustainable effort peaks) Tips • Correctly balance weight of implementation vs sprint stabilization according to above objectives • Rule of thumb would be having the internal demo point around 70% of the sprint, leaving 30% for stabilization (the example presented above and in chapter 4) • To align sizing with sprint planning these factors should also be used when estimating US • Although normally stable, the factors could be tuned as result of sprint retrospective
  • 21. www.outsystems.com© OutSystems. All Rights Reserved 5. Keep it moving! After sprint end • Development team must focus on the topics of the new sprint • Exception should only be made when an issue needs to be addressed to unblock the acceptance tests

Hinweis der Redaktion