SlideShare ist ein Scribd-Unternehmen logo
1 von 26
GOVT. WOMEN ENGINEERING COLLEGE, AJMER
Presentation On:
NATIONAL AND REGIONAL PLANNING
PRESENTED TO: PRESENTED BY:
Mr. Anant Gupta Jyoti Garg
Khushi Lohia
Monika Tailor
Nisha Dangi
CONTENT:
 INTRODUCTION
 POWER SYSTEM PLANNING
 TRANSMISSION VERSUS DISTRIBUTION PLANNING
 LONG TERM VERSUS SHORT TERM PLANNING
 ISSUES IN TRANSMISSION PLANNING
 GENERATION PLANNING
 CAPACITY RESOURCE PLANNING
 TRANSMISSION PLANNING
 NATIONAL AND REGIONAL PLANNING
INTRODUCTION:
 Planning is the process of selecting vision, values, mission and objectives and
deciding what should be done to attain them.
 The elements may be:
 • Generation facilities
 • Substations
 • Transmission lines and/or cables
 • Capacitors/Reactors
 Planning is the process of taking a careful decision.
The decision should be:
 Where to allocate the element (for instance, thesending and receiving end
of a line).
 When to install the element (for instance, 2018).
 What to select, in terms of the element specifications (for instance, number
of bundles and conductor type).
Transmission Versus Distribution Planning :
 Three main levels for a power system structure, namely, transmission, sub-
transmission and distribution.
 Distribution level is often planned or at least operated, radially.
Long-term Versus Short-term Planning:
Power system planning issues may cover a period of 1–10 years, or even more.
For the peak loading condition of the coming year, a power system utility
expert notices that from the two lines, feeding a substation, one would be
overloaded by 10% of its rating, while, the other would be loaded by 60% of its
rating.
If a control device is installed on one line, the load distribution may be
balanced on both lines.
Once decided, the installation process of this device can be performed in such
a way that no problem arises for the coming year.
This is a typical short term transmission planning decision.
The load forecasting for the coming years shows that with all already available and
planned generations, there would be a shortfall of generation in 9 years from now,
onward.
After a careful study, the planner decides on adding a new 500 MW steam power
plant at a specific bus in that year.
Its construction should start well in advance so that it would be available at the
required time.
His or her decision is a typical long-term (9-year) transmission planning decision.
Basic Issues in Transmission Planning:
 Load Forecasting
The first crucial step for any planning study is to predict the consumption for the study
period (say 2015–2020), as all subsequent studies will be based on that.
However, it is understood that a short-term load forecasting, used for operational studies,
is significantly different from the long-term one used in planning studies.
In a short-term load forecasting, for predicting the load for instance, of the next week,
we come across predicting the load for each hour of the coming week.
It is obvious that the determining factors may be weather conditions, special TV programs
and similar.
Obviously, the determining factors are different here i.e. Population rate increase, GDP
(Gross Domestic Product) and similar terms have dominant effects.
 Generation Expansion Planning:
After predicting the load, the next step is to determine the generation
requirements to satisfy the load.
An obvious simple solution is to assume a generation increase equal to load
increase.
If, for instance, in year 2015, the peak load would be 40,000 MW and at that
time, the available generation is 35,000 MW, an extra generation of 5,000 MW
would be required.
 Substation Expansion Planning:
Once the load is predicted and the generation requirements are known, the next step is to determine
the substation requirements, both, in terms of
Expanding the existing ones
Installing some new ones
This is referred to as Substation Expansion Planning (SEP).
SEP is a difficult task as many factors are involved such as
Those constraints due to the upward grid, feeding the substations,
Those constraints due to the downward grid, through which the substation supplies the loads,
Those constraints due to the factors to be observed for the substation itself.
 Network Expansion Planning:
Network Expansion Planning (NEP) is a process in which the network
(transmission lines, cables, etc.) specifications are determined.
In fact, the network is a media for transmitting the power, efficiently and in
a reliable manner from generation resources to the load centers.
Generator planning:
Load Forecasting
In the short term, load can be forecast with great accuracy, and this is
performed daily to determine generation units’ commitment.
Load forecasting for the purpose of generation planning, however, requires a
substantially longer time horizon, because system expansion projects require
long lead times, often between 2 and 10 years.
The outputs from a load forecast are a forecast of annual energy sales (in
kilowatt-hours), and the annual peak demand (in kilowatts).
There are two widely used methods in energy sales forecasting, econometric
regression analysis, and end- use electricity models.
 The usefulness of each method depends on data availability, customer
segmentation, and the degree of detail required.
 End-use electricity models are physical, engineering based methods that
often are used in forecasting the residential load, and sometimes for
commercial and industrial loads.
 Forecasting the peak demand is done based on forecasted energy sales
by multiplying forecasted energy with an empirically determined load factor
coefficient.
 Peak load is extremely sensitive to weather, and both the historic data
and the forecast must be adjusted consistently to normalize them relative to
the weather.
 Peak load forecasting is important because it directly influences the
required generation capacity—on every day of the year there must be enough
available generation to feed the peak load.
Reactive Power Planning:
In running NEP, the voltages are assumed to be flat (i.e. 1 p.u.) and reactive power flows
are ignored.
The main reason is the fact that constructing a line is not considered as a main tool for
voltage improvement.
Moreover, the running time of NEP can be exceptionally high or even the solution may
not be possible if AC Load Flow (ACLF) is employed. That is why in practice, NEP is
normally based on using Direct Current Load Flow (DCLF).
Upon running GEP, SEP and NEP, the network topology is determined.
However, it may perform unsatisfactorily, if a detailed AC Load Flow (ACLF) is
performed, based on existing algorithms.
To solve such a difficulty, static reactive power compensators, such as capacitors and
reactors may be used. Moreover, some more flexible reactive power resources are
required. The problem is, however
Where to install these devices?
What capacities do we have to employ?
What types do we have to use?
Capacity Resource Planning:
The question of what type of generating station (hydroelectric, nuclear, coal,
gas turbine, or other) would be the most economical addition to the system is
answered by combining a production cost analysis with an investment cost
analysis.
The evaluation begins by preparing a set of expansion scenarios.
An expansion scenario includes additions of multiple units and the planners are
required to hypothesize the type and the number of units that should be
considered.
The scenarios then are evaluated one at a time, beginning with a multiyear
reliability simulation to determine the LOLP index for each year of study.
If the reliability requirements are not met they often can be improved either
by advancing the installation dates of some units, or by delaying retirement
dates of others.
Transmission Planning:
• A transmission system makes it possible to supply loads from the most
economical sources of power, and operate generating stations flexibly and thus
improve overall system reliability.
• Transmission planning therefore ensures that the transmission infrastructure
can deliver power from the generators to the loads, and that all the equipment
will remain within its operating limits in both normal operation and during
system contingencies.
• Contingencies in this context mean unexpected failures of any system element;
for example a generator or a transmission line could have an unexpected outage,
which would force the remainder of the system to transition to a new operating
point.
NATIONAL AND REGIONAL PLANNING:
 There is a lot of diversity in the country in topography, daily peak due
to date and difference in annual peak load timing( winter or summer)
and resources in various regions.
 Hence, the five electricity regions have been established.
 The economic Arguments in support of regional coordination are:
A. Such coordination allow join planning and operation of facilities.
B. It makes exchange of economical energy easier.
C. It prevents construction of unneccessary facilities by isolated
system.
 More specifically, as a result of transmission, coordination offers distinct
economic and the none –coincidental occurrence of the peaks of participation
system.
 It might be possible to reduce the total generating capacity requirements
capacity that would otherwise applied if each utility system were fully meet
its need.
 By combining the existing capacity of different utility, it is possible to reduce
the required reserve capacity of generation in the region and to make
economic use of the generation resources such as hydro and fossil fuel.
 One of the problems in regional planning relates to coordination among the
various utility in the region with respect to tariff and backing down of
generating units in merit order.
 HVDC links for transfer of power between various regions is desirable in order
to utilize surplus power in some regions and for stable grid operation.
FIVE ELECTRICITY REGIONS ARE:
 A. Northern Region
 B. Western Region
 C. Southern Region
 D. Eastern Region
 E. North Eastern Region
ELECTRICITY REGIONS OF INDIA
 Integrated resources planning:
 Least cost utility planning:
 There are two fundamental problems inherent in traditional planning.
 The first is – the demand forecasting and investment planning are treated as
sequential steps in planning.
 The second is – that planning efforts are inadequately directed at the main
constraints facing the sector like the serious shortage of resources.
 Least cost planning is least cost utility planning strategy to provide reliable
electrical services at the lowest overall cost with a mix of supply side and
demand side resources.
POWER SYSTEM PLANNING

Weitere ähnliche Inhalte

Was ist angesagt?

Load Forecasting
Load ForecastingLoad Forecasting
Load Forecastinglinsstalex
 
Voltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridVoltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridLeonardo ENERGY
 
Generation shift factor and line outage factor
Generation shift factor and line outage factorGeneration shift factor and line outage factor
Generation shift factor and line outage factorViren Pandya
 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal schedulingASHIRBAD BARIK
 
TRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIATRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIAArun Muraleedharan
 
Control of hvdc system
Control of hvdc systemControl of hvdc system
Control of hvdc systemAazim Rasool
 
Wide Area Monitoring System WAMS & Applications
Wide Area Monitoring System WAMS & ApplicationsWide Area Monitoring System WAMS & Applications
Wide Area Monitoring System WAMS & ApplicationsPower System Operation
 
Automatic Generation Control
Automatic Generation ControlAutomatic Generation Control
Automatic Generation ControlBirju Besra
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Deviceskhemraj298
 
Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)Asha Anu Kurian
 
Load Forecasting II
Load Forecasting IILoad Forecasting II
Load Forecasting IIlinsstalex
 
20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx
20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx
20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptxthanigaivelraja1
 
Lecture 1_Introduction to power system planning.pdf
Lecture 1_Introduction to power system planning.pdfLecture 1_Introduction to power system planning.pdf
Lecture 1_Introduction to power system planning.pdfssuser5feb82
 
3 reactive power and voltage control
3 reactive power and voltage control3 reactive power and voltage control
3 reactive power and voltage control8141245710
 

Was ist angesagt? (20)

Load Forecasting
Load ForecastingLoad Forecasting
Load Forecasting
 
Voltage and Frequency Control of the Grid
Voltage and Frequency Control of the GridVoltage and Frequency Control of the Grid
Voltage and Frequency Control of the Grid
 
Spinning reserve
Spinning reserveSpinning reserve
Spinning reserve
 
Generation shift factor and line outage factor
Generation shift factor and line outage factorGeneration shift factor and line outage factor
Generation shift factor and line outage factor
 
Hydrothermal scheduling
Hydrothermal schedulingHydrothermal scheduling
Hydrothermal scheduling
 
TRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIATRANSMISSION PLANNING CRITERIA
TRANSMISSION PLANNING CRITERIA
 
CHAPTER- 4.ppt
CHAPTER- 4.pptCHAPTER- 4.ppt
CHAPTER- 4.ppt
 
Control of hvdc system
Control of hvdc systemControl of hvdc system
Control of hvdc system
 
Wide Area Monitoring System WAMS & Applications
Wide Area Monitoring System WAMS & ApplicationsWide Area Monitoring System WAMS & Applications
Wide Area Monitoring System WAMS & Applications
 
Reactive power compensation
Reactive power compensationReactive power compensation
Reactive power compensation
 
Solar pv connected to grid
Solar pv connected to gridSolar pv connected to grid
Solar pv connected to grid
 
Automatic Generation Control
Automatic Generation ControlAutomatic Generation Control
Automatic Generation Control
 
Series & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs DevicesSeries & shunt compensation and FACTs Devices
Series & shunt compensation and FACTs Devices
 
Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)Economic load dispatch(with and without losses)
Economic load dispatch(with and without losses)
 
Demand side management: Demand response
Demand side management: Demand response Demand side management: Demand response
Demand side management: Demand response
 
Load Forecasting II
Load Forecasting IILoad Forecasting II
Load Forecasting II
 
Statcom
StatcomStatcom
Statcom
 
20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx
20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx
20EEE659T - UNIT - 2 - POWER SYSTEM PLANNING AND RELIABILITY.pptx
 
Lecture 1_Introduction to power system planning.pdf
Lecture 1_Introduction to power system planning.pdfLecture 1_Introduction to power system planning.pdf
Lecture 1_Introduction to power system planning.pdf
 
3 reactive power and voltage control
3 reactive power and voltage control3 reactive power and voltage control
3 reactive power and voltage control
 

Ähnlich wie POWER SYSTEM PLANNING

The 5 core tools are recognized as standard quality tools for the automotive ...
The 5 core tools are recognized as standard quality tools for the automotive ...The 5 core tools are recognized as standard quality tools for the automotive ...
The 5 core tools are recognized as standard quality tools for the automotive ...arvindsinghrathore6
 
Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Sifan Welisa
 
Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...
Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...
Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...swapnamansani123
 
Power system Planning - Basic Techniques
Power system Planning - Basic TechniquesPower system Planning - Basic Techniques
Power system Planning - Basic TechniquesChithraM26
 
Load types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curvesLoad types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curvesAzfar Rasool
 
Renewable energy integration and energy storage
Renewable energy integration and energy storage Renewable energy integration and energy storage
Renewable energy integration and energy storage Bushveld Energy
 
Uncertainty model for rate of change of frequency analysis with high renewab...
Uncertainty model for rate of change of frequency analysis with  high renewab...Uncertainty model for rate of change of frequency analysis with  high renewab...
Uncertainty model for rate of change of frequency analysis with high renewab...IJECEIAES
 
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...Resurgent India
 
Two-way Load Flow Analysis using Newton-Raphson and Neural Network Methods
Two-way Load Flow Analysis using Newton-Raphson and Neural Network MethodsTwo-way Load Flow Analysis using Newton-Raphson and Neural Network Methods
Two-way Load Flow Analysis using Newton-Raphson and Neural Network MethodsIRJET Journal
 
Load forecasting,Megger,Earthing ELCB
Load forecasting,Megger,Earthing ELCBLoad forecasting,Megger,Earthing ELCB
Load forecasting,Megger,Earthing ELCBSuryakant Morey
 
Load forcasting in rajasthan
Load forcasting in rajasthanLoad forcasting in rajasthan
Load forcasting in rajasthanShubhamKashyap125
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
ghods-A-10-257-3-30dc0c6
ghods-A-10-257-3-30dc0c6ghods-A-10-257-3-30dc0c6
ghods-A-10-257-3-30dc0c6ladan ghods
 
Alemante research method presentation ppt
Alemante research method presentation pptAlemante research method presentation ppt
Alemante research method presentation pptGetahunShankoKefeni
 
Economical and Reliable Expansion Alternative of Composite Power System under...
Economical and Reliable Expansion Alternative of Composite Power System under...Economical and Reliable Expansion Alternative of Composite Power System under...
Economical and Reliable Expansion Alternative of Composite Power System under...IJECEIAES
 
Grid Integration and Application of Solar Energy; A Technological Review
Grid Integration and Application of Solar Energy; A Technological ReviewGrid Integration and Application of Solar Energy; A Technological Review
Grid Integration and Application of Solar Energy; A Technological ReviewIRJET Journal
 

Ähnlich wie POWER SYSTEM PLANNING (20)

The 5 core tools are recognized as standard quality tools for the automotive ...
The 5 core tools are recognized as standard quality tools for the automotive ...The 5 core tools are recognized as standard quality tools for the automotive ...
The 5 core tools are recognized as standard quality tools for the automotive ...
 
Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]Power system planning & operation [eceg 4410]
Power system planning & operation [eceg 4410]
 
Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...
Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...
Research_on_distribution_system_planning_theoryunder_the_trend_of_load-supply...
 
Power system Planning - Basic Techniques
Power system Planning - Basic TechniquesPower system Planning - Basic Techniques
Power system Planning - Basic Techniques
 
Load types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curvesLoad types, estimation, grwoth, forecasting and duration curves
Load types, estimation, grwoth, forecasting and duration curves
 
Renewable energy integration and energy storage
Renewable energy integration and energy storage Renewable energy integration and energy storage
Renewable energy integration and energy storage
 
PP_lect1.pptx
PP_lect1.pptxPP_lect1.pptx
PP_lect1.pptx
 
EE6603 - Power System Operation & Control
EE6603 - Power System Operation & ControlEE6603 - Power System Operation & Control
EE6603 - Power System Operation & Control
 
Uncertainty model for rate of change of frequency analysis with high renewab...
Uncertainty model for rate of change of frequency analysis with  high renewab...Uncertainty model for rate of change of frequency analysis with  high renewab...
Uncertainty model for rate of change of frequency analysis with high renewab...
 
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
Affordable 24x7 Power To All @2019- Fuel Security & Distribution Reforms - Ke...
 
Dr.pptx1
Dr.pptx1Dr.pptx1
Dr.pptx1
 
Two-way Load Flow Analysis using Newton-Raphson and Neural Network Methods
Two-way Load Flow Analysis using Newton-Raphson and Neural Network MethodsTwo-way Load Flow Analysis using Newton-Raphson and Neural Network Methods
Two-way Load Flow Analysis using Newton-Raphson and Neural Network Methods
 
Load forecasting,Megger,Earthing ELCB
Load forecasting,Megger,Earthing ELCBLoad forecasting,Megger,Earthing ELCB
Load forecasting,Megger,Earthing ELCB
 
Eskom - Grid Connectivity
Eskom - Grid ConnectivityEskom - Grid Connectivity
Eskom - Grid Connectivity
 
Load forcasting in rajasthan
Load forcasting in rajasthanLoad forcasting in rajasthan
Load forcasting in rajasthan
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
ghods-A-10-257-3-30dc0c6
ghods-A-10-257-3-30dc0c6ghods-A-10-257-3-30dc0c6
ghods-A-10-257-3-30dc0c6
 
Alemante research method presentation ppt
Alemante research method presentation pptAlemante research method presentation ppt
Alemante research method presentation ppt
 
Economical and Reliable Expansion Alternative of Composite Power System under...
Economical and Reliable Expansion Alternative of Composite Power System under...Economical and Reliable Expansion Alternative of Composite Power System under...
Economical and Reliable Expansion Alternative of Composite Power System under...
 
Grid Integration and Application of Solar Energy; A Technological Review
Grid Integration and Application of Solar Energy; A Technological ReviewGrid Integration and Application of Solar Energy; A Technological Review
Grid Integration and Application of Solar Energy; A Technological Review
 

Kürzlich hochgeladen

Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxmaisarahman1
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationBhangaleSonal
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxNadaHaitham1
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdfKamal Acharya
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Call Girls Mumbai
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxMuhammadAsimMuhammad6
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARKOUSTAV SARKAR
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdfKamal Acharya
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...Amil baba
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdfKamal Acharya
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilVinayVitekari
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 

Kürzlich hochgeladen (20)

Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptxOrlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
Orlando’s Arnold Palmer Hospital Layout Strategy-1.pptx
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Online electricity billing project report..pdf
Online electricity billing project report..pdfOnline electricity billing project report..pdf
Online electricity billing project report..pdf
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 

POWER SYSTEM PLANNING

  • 1. GOVT. WOMEN ENGINEERING COLLEGE, AJMER Presentation On: NATIONAL AND REGIONAL PLANNING PRESENTED TO: PRESENTED BY: Mr. Anant Gupta Jyoti Garg Khushi Lohia Monika Tailor Nisha Dangi
  • 2. CONTENT:  INTRODUCTION  POWER SYSTEM PLANNING  TRANSMISSION VERSUS DISTRIBUTION PLANNING  LONG TERM VERSUS SHORT TERM PLANNING  ISSUES IN TRANSMISSION PLANNING  GENERATION PLANNING  CAPACITY RESOURCE PLANNING  TRANSMISSION PLANNING  NATIONAL AND REGIONAL PLANNING
  • 3. INTRODUCTION:  Planning is the process of selecting vision, values, mission and objectives and deciding what should be done to attain them.  The elements may be:  • Generation facilities  • Substations  • Transmission lines and/or cables  • Capacitors/Reactors  Planning is the process of taking a careful decision.
  • 4. The decision should be:  Where to allocate the element (for instance, thesending and receiving end of a line).  When to install the element (for instance, 2018).  What to select, in terms of the element specifications (for instance, number of bundles and conductor type).
  • 5. Transmission Versus Distribution Planning :  Three main levels for a power system structure, namely, transmission, sub- transmission and distribution.  Distribution level is often planned or at least operated, radially.
  • 6. Long-term Versus Short-term Planning: Power system planning issues may cover a period of 1–10 years, or even more. For the peak loading condition of the coming year, a power system utility expert notices that from the two lines, feeding a substation, one would be overloaded by 10% of its rating, while, the other would be loaded by 60% of its rating. If a control device is installed on one line, the load distribution may be balanced on both lines. Once decided, the installation process of this device can be performed in such a way that no problem arises for the coming year.
  • 7. This is a typical short term transmission planning decision. The load forecasting for the coming years shows that with all already available and planned generations, there would be a shortfall of generation in 9 years from now, onward. After a careful study, the planner decides on adding a new 500 MW steam power plant at a specific bus in that year. Its construction should start well in advance so that it would be available at the required time. His or her decision is a typical long-term (9-year) transmission planning decision.
  • 8. Basic Issues in Transmission Planning:  Load Forecasting The first crucial step for any planning study is to predict the consumption for the study period (say 2015–2020), as all subsequent studies will be based on that. However, it is understood that a short-term load forecasting, used for operational studies, is significantly different from the long-term one used in planning studies. In a short-term load forecasting, for predicting the load for instance, of the next week, we come across predicting the load for each hour of the coming week. It is obvious that the determining factors may be weather conditions, special TV programs and similar. Obviously, the determining factors are different here i.e. Population rate increase, GDP (Gross Domestic Product) and similar terms have dominant effects.
  • 9.  Generation Expansion Planning: After predicting the load, the next step is to determine the generation requirements to satisfy the load. An obvious simple solution is to assume a generation increase equal to load increase. If, for instance, in year 2015, the peak load would be 40,000 MW and at that time, the available generation is 35,000 MW, an extra generation of 5,000 MW would be required.
  • 10.  Substation Expansion Planning: Once the load is predicted and the generation requirements are known, the next step is to determine the substation requirements, both, in terms of Expanding the existing ones Installing some new ones This is referred to as Substation Expansion Planning (SEP). SEP is a difficult task as many factors are involved such as Those constraints due to the upward grid, feeding the substations, Those constraints due to the downward grid, through which the substation supplies the loads, Those constraints due to the factors to be observed for the substation itself.
  • 11.  Network Expansion Planning: Network Expansion Planning (NEP) is a process in which the network (transmission lines, cables, etc.) specifications are determined. In fact, the network is a media for transmitting the power, efficiently and in a reliable manner from generation resources to the load centers.
  • 12. Generator planning: Load Forecasting In the short term, load can be forecast with great accuracy, and this is performed daily to determine generation units’ commitment. Load forecasting for the purpose of generation planning, however, requires a substantially longer time horizon, because system expansion projects require long lead times, often between 2 and 10 years. The outputs from a load forecast are a forecast of annual energy sales (in kilowatt-hours), and the annual peak demand (in kilowatts). There are two widely used methods in energy sales forecasting, econometric regression analysis, and end- use electricity models.
  • 13.  The usefulness of each method depends on data availability, customer segmentation, and the degree of detail required.  End-use electricity models are physical, engineering based methods that often are used in forecasting the residential load, and sometimes for commercial and industrial loads.  Forecasting the peak demand is done based on forecasted energy sales by multiplying forecasted energy with an empirically determined load factor coefficient.  Peak load is extremely sensitive to weather, and both the historic data and the forecast must be adjusted consistently to normalize them relative to the weather.  Peak load forecasting is important because it directly influences the required generation capacity—on every day of the year there must be enough available generation to feed the peak load.
  • 14. Reactive Power Planning: In running NEP, the voltages are assumed to be flat (i.e. 1 p.u.) and reactive power flows are ignored. The main reason is the fact that constructing a line is not considered as a main tool for voltage improvement. Moreover, the running time of NEP can be exceptionally high or even the solution may not be possible if AC Load Flow (ACLF) is employed. That is why in practice, NEP is normally based on using Direct Current Load Flow (DCLF). Upon running GEP, SEP and NEP, the network topology is determined. However, it may perform unsatisfactorily, if a detailed AC Load Flow (ACLF) is performed, based on existing algorithms.
  • 15. To solve such a difficulty, static reactive power compensators, such as capacitors and reactors may be used. Moreover, some more flexible reactive power resources are required. The problem is, however Where to install these devices? What capacities do we have to employ? What types do we have to use?
  • 16. Capacity Resource Planning: The question of what type of generating station (hydroelectric, nuclear, coal, gas turbine, or other) would be the most economical addition to the system is answered by combining a production cost analysis with an investment cost analysis. The evaluation begins by preparing a set of expansion scenarios. An expansion scenario includes additions of multiple units and the planners are required to hypothesize the type and the number of units that should be considered. The scenarios then are evaluated one at a time, beginning with a multiyear reliability simulation to determine the LOLP index for each year of study. If the reliability requirements are not met they often can be improved either by advancing the installation dates of some units, or by delaying retirement dates of others.
  • 17. Transmission Planning: • A transmission system makes it possible to supply loads from the most economical sources of power, and operate generating stations flexibly and thus improve overall system reliability. • Transmission planning therefore ensures that the transmission infrastructure can deliver power from the generators to the loads, and that all the equipment will remain within its operating limits in both normal operation and during system contingencies. • Contingencies in this context mean unexpected failures of any system element; for example a generator or a transmission line could have an unexpected outage, which would force the remainder of the system to transition to a new operating point.
  • 18. NATIONAL AND REGIONAL PLANNING:  There is a lot of diversity in the country in topography, daily peak due to date and difference in annual peak load timing( winter or summer) and resources in various regions.  Hence, the five electricity regions have been established.  The economic Arguments in support of regional coordination are: A. Such coordination allow join planning and operation of facilities. B. It makes exchange of economical energy easier. C. It prevents construction of unneccessary facilities by isolated system.
  • 19.  More specifically, as a result of transmission, coordination offers distinct economic and the none –coincidental occurrence of the peaks of participation system.  It might be possible to reduce the total generating capacity requirements capacity that would otherwise applied if each utility system were fully meet its need.  By combining the existing capacity of different utility, it is possible to reduce the required reserve capacity of generation in the region and to make economic use of the generation resources such as hydro and fossil fuel.  One of the problems in regional planning relates to coordination among the various utility in the region with respect to tariff and backing down of generating units in merit order.  HVDC links for transfer of power between various regions is desirable in order to utilize surplus power in some regions and for stable grid operation.
  • 20.
  • 21.
  • 22. FIVE ELECTRICITY REGIONS ARE:  A. Northern Region  B. Western Region  C. Southern Region  D. Eastern Region  E. North Eastern Region
  • 25.  Least cost utility planning:  There are two fundamental problems inherent in traditional planning.  The first is – the demand forecasting and investment planning are treated as sequential steps in planning.  The second is – that planning efforts are inadequately directed at the main constraints facing the sector like the serious shortage of resources.  Least cost planning is least cost utility planning strategy to provide reliable electrical services at the lowest overall cost with a mix of supply side and demand side resources.