SlideShare ist ein Scribd-Unternehmen logo
1 von 14
JOB costing & PROCESS Costing



            Presented By:- Nikita Khemani
                           Roshni Gupta
                           Seema Pandey
                           Vinod Rajput
PROCESS CYCLE
MEANING OF PROCESS COSTING

Meaning : process costing is a method of costing applied to industries
          where the material has to pass through two or more processes
          for being converted into a finish product. Each process is treated
          as a cost center. The cost of each process is accumulated and
          per unit cost is determined for this purpose the following formula
          is applied :



Cost per unit of each process= Cost of Output in the process
                              Normal no. of units in the process
JOB costing

Job costing is the method of costing used to determine the cost of
Non-standard carried out according to customer’s specification .

ADVANTAGE OF JOB COSTING

i.     Detailed Analysis of cost
ii.    Cost control
iii.   Advantage of Budgetary Control
iv.    Help in Production Planning
v.     Useful in cost Plus
CHARACTERISTICS OF PROCESS COSTING

1. The production is continuous and the end product is the result of a
   sequence of processes. Each plant is divided into separate process
   center processes a single product.

2. To complete the production work the sequence of process is clearly
   defined and activities of the process are also clearly identified.

3. Production is done in large scale.

4. It is also possible to obtain joint product or by-product from the
   of raw material or production technology.
DISTINCTION BETWEEN JOB COSTING & PROCESS COSTING

             Job costing                     Process costing

  1. Unit is one and specific and   1. Production is divided into
     work is done by specific          several units and the unit s are
     order.                            uniform . Production is
                                       continuous .
  2. One job is not related to or   2. The succeeding process is
     dependent on each other.          dependent on the preceding
                                       one.
  3. The cost of a job is not       3. The cost of a process is
     transferred to the others.        transferred to the next process.
Q: A product passes through three process , process A, process B,
Process C, to completion. The production of the commodity was 1,000
tone.
The cost were as follows :
                                   process A     process B     process C
Material                            3000           1500           1500
Labour                              1500           3000           5250
Manufacturing Expenses              1500           4500           5250

Assume that there was no work-in progress either at the beginning or at
the end . Show the process cost for each process and the total cost of the
finished product.
Solution
                           Process A account
      particular    Cost     Total      particular    Cost   Total
                    per      cost                     per    cost
                   tonne                             tonne
To Material         3.00     3000 By process B A/c    6.00   6000
                                         (output
To Labour           1.50     1500 transferred)

To Manufacturing    1.50     1500
Expenses

                    6.00     6000                     6.00   6000
process B account
     particular     Cost     Total       particular    Cost   Total
                    per      cost                      per    cost
                   tonne                              tonne
To process A A/c    6.00     6000 By process C A/c    15.00   15000
                                         (output
To Material         1.50     1500 transferred)

To Labour           3.50     3000

To Manufacturing    4.50     4500
Expenses

                   15.00 15000                        15.00   15000
process C Account
     particular     Cost     Total      particular    Cost   Total
                    per      cost                     per    cost
                   tonne                             tonne
To process B A/c   15.00 15000 By Finished Stock     27.00   27000
                               A/c
To Material         1.50 1500         (output
                               transferred)
To Labour           5.25 5250

To Manufacturing    5.25     5250
Expenses

                   27.00 27000                       27.00   27000
Q:   The following three jobs were completed in the week ending 7th oct.,
     2010.compute the total cost by preparing a statement of cost with
     the information given below :

                                        job No.1    job No.2 job No.3
                                            Rs.        Rs.      Rs.
Direct Material                           2000        2400     6400
Direct Labour                             1600        1800     2400
Direct Expenses                            400         600      600

Charges work over head @50% on direct Labour and office over head @10%
On work cost .What shall be the job price of 10% profit is desired on the
Supply price.
Solution:
                                  Statement of cost
                         For the week ending 7.10.2010
                    Particular                      Job no.1     Job no.2    Job
                                                                            no.3
  Direct Material                                         2000      2400     6400

  Direct Labour                                           1600      1800     2400

  Direct Expenses                                          400       600      600

   Work overhead                      prime cost         4000      4800      9400
  (50% on Direct Labour)                                  800       900      1200
  Office over head                    work cost          4800      5700     10600
  (10% on works cost)                                     480       570      1060
  Profit 10% on supply price or        total cost        5280      6270     11660
  1/9 on total cost                                       587       697      1296
                                       job price         5867      6967     12956
Reasons for use
Companies need to allocate total product costs to units of product
for the following reasons:

•A company may manufacture thousands or millions of units of
product in a given period of time.

•Products are manufactured in large quantities, but products may
be sold in small quantities, sometimes one at a time (automobiles,
loaves of bread), a dozen or two at a time (eggs, cookies), etc.

•Product costs must be transferred from Finished Goods to Cost
of Goods Sold as sales are made. This requires a correct and
accurate accounting of product costs per unit, to have a proper
matching of product costs against related sales revenue.
Presentation1

Weitere ähnliche Inhalte

Was ist angesagt?

| Managerial Accounting | Chapter 4 | Systems Design: Process Costing | Intro...
| Managerial Accounting | Chapter 4 | Systems Design: Process Costing | Intro...| Managerial Accounting | Chapter 4 | Systems Design: Process Costing | Intro...
| Managerial Accounting | Chapter 4 | Systems Design: Process Costing | Intro...Ahmad Hassan
 
Cost Sheet , Tender and quotation
Cost Sheet , Tender and quotationCost Sheet , Tender and quotation
Cost Sheet , Tender and quotationRajaKrishnan M
 
Costing system job costing
Costing system job costingCosting system job costing
Costing system job costingOnline
 
Process costing manipal jaipur bba 3 semester
Process costing manipal jaipur bba 3 semesterProcess costing manipal jaipur bba 3 semester
Process costing manipal jaipur bba 3 semestersachin kumar sharma
 
Cost Revision
Cost RevisionCost Revision
Cost Revisionppkg
 
Process costing
Process costingProcess costing
Process costingPrem Chand
 
Acc mgt noreen04 systems design process costing
Acc mgt noreen04 systems design process costingAcc mgt noreen04 systems design process costing
Acc mgt noreen04 systems design process costingJudianto Nugroho
 
Manufacturinf overhead variance
Manufacturinf overhead varianceManufacturinf overhead variance
Manufacturinf overhead varianceemployee goverment
 
Management and Cost Accounting 7th Edition Drury Solutions Manual
Management and Cost Accounting 7th Edition Drury Solutions ManualManagement and Cost Accounting 7th Edition Drury Solutions Manual
Management and Cost Accounting 7th Edition Drury Solutions ManualVelmaWallace
 

Was ist angesagt? (16)

| Managerial Accounting | Chapter 4 | Systems Design: Process Costing | Intro...
| Managerial Accounting | Chapter 4 | Systems Design: Process Costing | Intro...| Managerial Accounting | Chapter 4 | Systems Design: Process Costing | Intro...
| Managerial Accounting | Chapter 4 | Systems Design: Process Costing | Intro...
 
Cost Sheet , Tender and quotation
Cost Sheet , Tender and quotationCost Sheet , Tender and quotation
Cost Sheet , Tender and quotation
 
Topic 11(short)
Topic 11(short)Topic 11(short)
Topic 11(short)
 
Costing system job costing
Costing system job costingCosting system job costing
Costing system job costing
 
Costsheet final
Costsheet finalCostsheet final
Costsheet final
 
Financial statement of Manufacturing Company
Financial statement of Manufacturing CompanyFinancial statement of Manufacturing Company
Financial statement of Manufacturing Company
 
Process costing manipal jaipur bba 3 semester
Process costing manipal jaipur bba 3 semesterProcess costing manipal jaipur bba 3 semester
Process costing manipal jaipur bba 3 semester
 
Chapter 12 var
Chapter 12 varChapter 12 var
Chapter 12 var
 
Job order costing
Job order costingJob order costing
Job order costing
 
Cost Revision
Cost RevisionCost Revision
Cost Revision
 
Process costing
Process costingProcess costing
Process costing
 
5. process cost systems
5. process cost systems5. process cost systems
5. process cost systems
 
Acc mgt noreen04 systems design process costing
Acc mgt noreen04 systems design process costingAcc mgt noreen04 systems design process costing
Acc mgt noreen04 systems design process costing
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Manufacturinf overhead variance
Manufacturinf overhead varianceManufacturinf overhead variance
Manufacturinf overhead variance
 
Management and Cost Accounting 7th Edition Drury Solutions Manual
Management and Cost Accounting 7th Edition Drury Solutions ManualManagement and Cost Accounting 7th Edition Drury Solutions Manual
Management and Cost Accounting 7th Edition Drury Solutions Manual
 

Andere mochten auch

In Touch Overview 1 April 06
In Touch Overview 1 April 06In Touch Overview 1 April 06
In Touch Overview 1 April 06telemedicina
 
The Benefits of Using a Biometric Timeclock in Workforce Management
The Benefits of Using a Biometric Timeclock in Workforce ManagementThe Benefits of Using a Biometric Timeclock in Workforce Management
The Benefits of Using a Biometric Timeclock in Workforce ManagementM2SYS Technology
 
Five key themes in enterprise cloud computing migration
Five key themes in enterprise cloud computing migrationFive key themes in enterprise cloud computing migration
Five key themes in enterprise cloud computing migrationWinn Technology Group
 
Solution Chapter 3 l Cost Accounting Planning and Control by Matz.Hammer an...
Solution Chapter 3   l Cost Accounting Planning and Control by Matz.Hammer an...Solution Chapter 3   l Cost Accounting Planning and Control by Matz.Hammer an...
Solution Chapter 3 l Cost Accounting Planning and Control by Matz.Hammer an...Bushra Sultana Malik
 
Cloud Computing for the Enterprise
Cloud Computing for the EnterpriseCloud Computing for the Enterprise
Cloud Computing for the EnterpriseAmazon Web Services
 
Solution Manual Cost Accounting Planning and Control by Matz.Hammer and Usry ...
Solution Manual Cost Accounting Planning and Control by Matz.Hammer and Usry ...Solution Manual Cost Accounting Planning and Control by Matz.Hammer and Usry ...
Solution Manual Cost Accounting Planning and Control by Matz.Hammer and Usry ...Bushra Sultana Malik
 

Andere mochten auch (11)

Franchise Time Clock
Franchise Time ClockFranchise Time Clock
Franchise Time Clock
 
In Touch Overview 1 April 06
In Touch Overview 1 April 06In Touch Overview 1 April 06
In Touch Overview 1 April 06
 
Final powerpoint
Final powerpointFinal powerpoint
Final powerpoint
 
Zend PHP Solutions for IBM i
Zend PHP Solutions for IBM iZend PHP Solutions for IBM i
Zend PHP Solutions for IBM i
 
Franchise Accounting Software
Franchise Accounting SoftwareFranchise Accounting Software
Franchise Accounting Software
 
The Benefits of Using a Biometric Timeclock in Workforce Management
The Benefits of Using a Biometric Timeclock in Workforce ManagementThe Benefits of Using a Biometric Timeclock in Workforce Management
The Benefits of Using a Biometric Timeclock in Workforce Management
 
Five key themes in enterprise cloud computing migration
Five key themes in enterprise cloud computing migrationFive key themes in enterprise cloud computing migration
Five key themes in enterprise cloud computing migration
 
Chapter no 2 CGS
Chapter no 2 CGSChapter no 2 CGS
Chapter no 2 CGS
 
Solution Chapter 3 l Cost Accounting Planning and Control by Matz.Hammer an...
Solution Chapter 3   l Cost Accounting Planning and Control by Matz.Hammer an...Solution Chapter 3   l Cost Accounting Planning and Control by Matz.Hammer an...
Solution Chapter 3 l Cost Accounting Planning and Control by Matz.Hammer an...
 
Cloud Computing for the Enterprise
Cloud Computing for the EnterpriseCloud Computing for the Enterprise
Cloud Computing for the Enterprise
 
Solution Manual Cost Accounting Planning and Control by Matz.Hammer and Usry ...
Solution Manual Cost Accounting Planning and Control by Matz.Hammer and Usry ...Solution Manual Cost Accounting Planning and Control by Matz.Hammer and Usry ...
Solution Manual Cost Accounting Planning and Control by Matz.Hammer and Usry ...
 

Ähnlich wie Presentation1

Process costing
Process costingProcess costing
Process costingsigh_baba
 
ACG 2071 Managerial Accounting Process Costing Systems .docx
ACG 2071 Managerial Accounting Process Costing Systems .docxACG 2071 Managerial Accounting Process Costing Systems .docx
ACG 2071 Managerial Accounting Process Costing Systems .docxbobbywlane695641
 
Manufacturing cost accounting ppt @ mba finance
Manufacturing cost accounting ppt @ mba financeManufacturing cost accounting ppt @ mba finance
Manufacturing cost accounting ppt @ mba financeBabasab Patil
 
Process costing explained
Process costing explainedProcess costing explained
Process costing explainedSam zain
 
Bus 7800 week 6 absorption costing
Bus 7800 week 6 absorption costingBus 7800 week 6 absorption costing
Bus 7800 week 6 absorption costingOUHainesM
 
Fundamentals of accounting - cost value profit (cvp)
Fundamentals of accounting - cost value profit (cvp)Fundamentals of accounting - cost value profit (cvp)
Fundamentals of accounting - cost value profit (cvp)John Paul Espino
 
CA Ch.18-Process Costing-part 1-Nureni.pdf
CA Ch.18-Process Costing-part 1-Nureni.pdfCA Ch.18-Process Costing-part 1-Nureni.pdf
CA Ch.18-Process Costing-part 1-Nureni.pdfsandiibrahim3
 
Cost concepts
Cost conceptsCost concepts
Cost conceptswolfaze
 
| Managerial Accounting | Chapter 7 | Systems Design: Activity-Based Costing ...
| Managerial Accounting | Chapter 7 | Systems Design: Activity-Based Costing ...| Managerial Accounting | Chapter 7 | Systems Design: Activity-Based Costing ...
| Managerial Accounting | Chapter 7 | Systems Design: Activity-Based Costing ...Ahmad Hassan
 

Ähnlich wie Presentation1 (20)

Job costing slides
Job costing slidesJob costing slides
Job costing slides
 
Process costing
Process costingProcess costing
Process costing
 
Cost accounting
Cost accountingCost accounting
Cost accounting
 
ACG 2071 Managerial Accounting Process Costing Systems .docx
ACG 2071 Managerial Accounting Process Costing Systems .docxACG 2071 Managerial Accounting Process Costing Systems .docx
ACG 2071 Managerial Accounting Process Costing Systems .docx
 
Product costing
Product costingProduct costing
Product costing
 
Process Costing
Process CostingProcess Costing
Process Costing
 
ACN3101 TOPIC 9 211224.ppt
ACN3101 TOPIC 9 211224.pptACN3101 TOPIC 9 211224.ppt
ACN3101 TOPIC 9 211224.ppt
 
Job costing 3 a
Job costing 3 aJob costing 3 a
Job costing 3 a
 
Bsr3 a unit 1 2016
Bsr3 a unit 1   2016Bsr3 a unit 1   2016
Bsr3 a unit 1 2016
 
Manufacturing cost accounting ppt @ mba finance
Manufacturing cost accounting ppt @ mba financeManufacturing cost accounting ppt @ mba finance
Manufacturing cost accounting ppt @ mba finance
 
Process costing explained
Process costing explainedProcess costing explained
Process costing explained
 
Accounting problems 2
Accounting problems 2Accounting problems 2
Accounting problems 2
 
Bus 7800 week 6 absorption costing
Bus 7800 week 6 absorption costingBus 7800 week 6 absorption costing
Bus 7800 week 6 absorption costing
 
Mojakoe ab-uts-20111
Mojakoe ab-uts-20111Mojakoe ab-uts-20111
Mojakoe ab-uts-20111
 
Uts ab 2011 2012 gasal
Uts ab 2011 2012 gasalUts ab 2011 2012 gasal
Uts ab 2011 2012 gasal
 
Fundamentals of accounting - cost value profit (cvp)
Fundamentals of accounting - cost value profit (cvp)Fundamentals of accounting - cost value profit (cvp)
Fundamentals of accounting - cost value profit (cvp)
 
CA Ch.18-Process Costing-part 1-Nureni.pdf
CA Ch.18-Process Costing-part 1-Nureni.pdfCA Ch.18-Process Costing-part 1-Nureni.pdf
CA Ch.18-Process Costing-part 1-Nureni.pdf
 
yitu
yituyitu
yitu
 
Cost concepts
Cost conceptsCost concepts
Cost concepts
 
| Managerial Accounting | Chapter 7 | Systems Design: Activity-Based Costing ...
| Managerial Accounting | Chapter 7 | Systems Design: Activity-Based Costing ...| Managerial Accounting | Chapter 7 | Systems Design: Activity-Based Costing ...
| Managerial Accounting | Chapter 7 | Systems Design: Activity-Based Costing ...
 

Kürzlich hochgeladen

Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 

Kürzlich hochgeladen (20)

Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 

Presentation1

  • 1. JOB costing & PROCESS Costing Presented By:- Nikita Khemani Roshni Gupta Seema Pandey Vinod Rajput
  • 3. MEANING OF PROCESS COSTING Meaning : process costing is a method of costing applied to industries where the material has to pass through two or more processes for being converted into a finish product. Each process is treated as a cost center. The cost of each process is accumulated and per unit cost is determined for this purpose the following formula is applied : Cost per unit of each process= Cost of Output in the process Normal no. of units in the process
  • 4. JOB costing Job costing is the method of costing used to determine the cost of Non-standard carried out according to customer’s specification . ADVANTAGE OF JOB COSTING i. Detailed Analysis of cost ii. Cost control iii. Advantage of Budgetary Control iv. Help in Production Planning v. Useful in cost Plus
  • 5. CHARACTERISTICS OF PROCESS COSTING 1. The production is continuous and the end product is the result of a sequence of processes. Each plant is divided into separate process center processes a single product. 2. To complete the production work the sequence of process is clearly defined and activities of the process are also clearly identified. 3. Production is done in large scale. 4. It is also possible to obtain joint product or by-product from the of raw material or production technology.
  • 6. DISTINCTION BETWEEN JOB COSTING & PROCESS COSTING Job costing Process costing 1. Unit is one and specific and 1. Production is divided into work is done by specific several units and the unit s are order. uniform . Production is continuous . 2. One job is not related to or 2. The succeeding process is dependent on each other. dependent on the preceding one. 3. The cost of a job is not 3. The cost of a process is transferred to the others. transferred to the next process.
  • 7. Q: A product passes through three process , process A, process B, Process C, to completion. The production of the commodity was 1,000 tone. The cost were as follows : process A process B process C Material 3000 1500 1500 Labour 1500 3000 5250 Manufacturing Expenses 1500 4500 5250 Assume that there was no work-in progress either at the beginning or at the end . Show the process cost for each process and the total cost of the finished product.
  • 8. Solution Process A account particular Cost Total particular Cost Total per cost per cost tonne tonne To Material 3.00 3000 By process B A/c 6.00 6000 (output To Labour 1.50 1500 transferred) To Manufacturing 1.50 1500 Expenses 6.00 6000 6.00 6000
  • 9. process B account particular Cost Total particular Cost Total per cost per cost tonne tonne To process A A/c 6.00 6000 By process C A/c 15.00 15000 (output To Material 1.50 1500 transferred) To Labour 3.50 3000 To Manufacturing 4.50 4500 Expenses 15.00 15000 15.00 15000
  • 10. process C Account particular Cost Total particular Cost Total per cost per cost tonne tonne To process B A/c 15.00 15000 By Finished Stock 27.00 27000 A/c To Material 1.50 1500 (output transferred) To Labour 5.25 5250 To Manufacturing 5.25 5250 Expenses 27.00 27000 27.00 27000
  • 11. Q: The following three jobs were completed in the week ending 7th oct., 2010.compute the total cost by preparing a statement of cost with the information given below : job No.1 job No.2 job No.3 Rs. Rs. Rs. Direct Material 2000 2400 6400 Direct Labour 1600 1800 2400 Direct Expenses 400 600 600 Charges work over head @50% on direct Labour and office over head @10% On work cost .What shall be the job price of 10% profit is desired on the Supply price.
  • 12. Solution: Statement of cost For the week ending 7.10.2010 Particular Job no.1 Job no.2 Job no.3 Direct Material 2000 2400 6400 Direct Labour 1600 1800 2400 Direct Expenses 400 600 600 Work overhead prime cost 4000 4800 9400 (50% on Direct Labour) 800 900 1200 Office over head work cost 4800 5700 10600 (10% on works cost) 480 570 1060 Profit 10% on supply price or total cost 5280 6270 11660 1/9 on total cost 587 697 1296 job price 5867 6967 12956
  • 13. Reasons for use Companies need to allocate total product costs to units of product for the following reasons: •A company may manufacture thousands or millions of units of product in a given period of time. •Products are manufactured in large quantities, but products may be sold in small quantities, sometimes one at a time (automobiles, loaves of bread), a dozen or two at a time (eggs, cookies), etc. •Product costs must be transferred from Finished Goods to Cost of Goods Sold as sales are made. This requires a correct and accurate accounting of product costs per unit, to have a proper matching of product costs against related sales revenue.