SlideShare ist ein Scribd-Unternehmen logo
1 von 33
Project Management Professional
PMP® Exam Prep – Week 3
Cost Management
Muzette Charles, PMP | mcharles2@pace.edu
Cost Management
Chapter 7
“… includes the processes involved in planning, estimating, budgeting, financing, funding,
managing & controlling costs so that the project can be completed within the approved
budget.”
Process Process Group Key Deliverables
7.1 Plan Cost Management Planning Cost Management Plan
7.2 Estimate Costs Planning Activity cost estimates
7.3 Determine Budget Planning Cost Baseline (budget)
7.4 Control Costs Monitoring & Controlling Change Requests
Cost Management
Chapter 7
Plan Cost Management
Process 1
Key Points
 Provides guidance on how costs aka budget, will be managed throughout the project
 Aligns with Schedule baseline estimates, units of measure, level of accuracy (+/- %)
 Funding decisions: existing funds, equity or debt
Chapter 7, Topic 1
Units of Measure
• Currency, exchange rates
Level of Precision
• Rounding
Level of Accuracy
• Acceptable estimate ranges, inclusion
of contingency funds
Organizational Procedure Links
• Alignment with WBS control accounts
Control Thresholds
•When alarms will go off
Measurement Rules
•When and how to make what
types of measurements
Record and Report
•What to record, who gets a report,
when and at what level
Cost Management
Chapter 7
Plan Cost Management
Process 1
Cost Management
Chapter 7
Estimate Costs
Process 2
Key Points
 Developing the monetary cost each activity needed to complete the project
 Cost estimates are a prediction based on info known at a given point in time & is constantly reviewed
 Expected accuracy: initially ROM -25% to +75% , Budget -10% to +25%, Definitive -5% to +10%
 Usually expressed in currency: dollars, euros, yen, etc
Early Planning
Level of Precision
 What level of variance from estimates will trigger the need for further
investigation and possible action?
 Only rough order of magnitude (ROM) has a standard range. The
others are typical of that stage in a project for that organization.
Chapter 7, Topic 2
Rough order of
magnitude
(ROM)
–25% to +75%
Conceptual
–10% to +25%
Definitive
–5% to +10%
Initiating
Final Planning and
into Executing
Cost Management
Chapter 7
Estimate Costs
Process 2
In the project charter, costs were estimated at
US$2,000,000. What is the upper threshold to
which costs might extend by the time the
project reaches Executing?
A. US$2,500,000
B. US$3,000,000
C. US$3,500,000
D. US$3,750,000
Discussion Question
Answer: C
The project charter typically uses a ROM, which means the
estimation could increase by up to 75%, or US$3,500,000.
Chapter 7, Topic 2
Cost Estimates
Key Output
 Estimate costs by activity.
 Consider all costs:
 Direct expenses
(e.g., labor, materials, services)
 Special costs
(e.g., currency exchange rates)
 Indirect costs
(e.g., space and services provided)
Chapter 7, Topic 2
Cost Management
Chapter 7
Estimate Costs
Process 2
Cost Management
Chapter 7
Determine Budget
Process 3
Key Points
 Budget: all the calculated funds authorized to execute the project, includes reserves
 Cost baseline: the approved version of the budget, less Management Reserves, used as a
benchmark for variance analysis to measure project’s success.
 Reserve Analysis: Contingency Reserve & Management Reserve
 Funding Limit Reconciliation: PM is responsible to not exceed funding limits
Cost Management
Chapter 7
Determine Budget
Process 3
Cost Aggregation
Chapter 7, Topic 2
Activity
Cost
Estimates
Work
Package
Cost
Estimates
Contingency
Reserves for
Activities
General
Contingency
Reserve
Cost
Baseline
(All
Control
Accounts)
Management
Reserve
Project
Budget
+
+
+
=
=
=
Contingency Reserve
Budget within the cost
baseline allocated for
managing identified
risks
Management Reserve
Amount of project budget
withheld by management to
respond to unforeseen needs
Source: Adapted from Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2017,
Figure 7-8, Page 255. Material from this publication has been reproduced with the permission of PMI.
Cost Management
Chapter 7
Determine Budget
Process 3
Cost Baseline
S-curve chart
provides a time-
phased view of the
cost baseline—how
activities may have to
be reconciled with
funding infusion and
when reserves may
have to be tapped.
Chapter 7, Topic 3
Cumulative
Values
Time
Project Budget
Management
Reserve
Budget at
Completion
(BAC)
Funding
Requirements
Cost
Baseline
Expenditures
Source: Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2017,
Figure 7-9, Page 255. Material from this publication has been reproduced with the permission of PMI.
Cost Management
Chapter 7
Determine Budget
Process 3
Cost Baseline
Key Points
 The project manager is responsible for controlling spending and releasing
funds within the cost baseline.
 Funds are usually released over time, and funding schedules must be
reconciled with work schedules.
 The cost baseline includes both contingency and reserves and work package
cost estimates.
 It is the benchmark for project cost performance.
 All changes must be made through the integrated change control process.
Chapter 7, Topic 3
Cost Management
Chapter 7
Determine Budget
Process 3
During project execution, a contractor defaults.
How will the resulting increases in costs be
funded?
A. Contingency reserves
B. Management reserves
C. Change request to increase cost baseline
Discussion Question
Answer: B
This is probably an unexpected risk, since if there
was serious risk of default, the contractor, in most
cases, wouldn’t have been selected. Management
reserves are earmarked for these unforeseen risks.
Chapter 7, Topic 3
Cost Management
Chapter 7
Key Points
 Earned Value Mgmt (EVM):
 Assessing both schedule & cost performance through the concept of earned value; the monetary value of work
actually completed
 Tracks how is your project is performing against the plan
 Variances & forecast future performance, cost & completion date
 Performance Measurement Baseline: integrates cost, time & scope to predict variance, correct & minimize risk
Control Costs
Process 4
Match each EVM term with the correct definition.
Discussion Question
Answers: 1—b; 2—a; 3—c
Chapter 7, Topic 4
1. Earned value
2. Planned value
3. Actual cost
a. Authorized budget for
scheduled work
b. Budgeted cost of
completed work to the
reference point
c. Amount of money spent
by the reference point
EVM Variances
A variance uses subtraction to compare baseline
and actual performance. The first term is always EV.
Chapter 7, Topic 4
Schedule Variance
How does the work done
compare with the work that was
scheduled to be done?
SV = EV − PV
Cost Variance
How does the amount of work
done compare with the budget
dollars spent?
CV = EV − AC
A positive result is good.
The project is ahead of schedule.
A positive result is good.
The project is under budget.
Control Costs
Process 4
Cost Management
Chapter 7
EVM Performance Indices
A performance index is a ratio that uses division.
The numerator is always EV.
Chapter 7, Topic 4
Schedule Performance Index
How well is the project
performing against the schedule?
Cost Performance Index
How is the project performing
against the budget?
Above ONE is good.
(Project is ahead of schedule.)
Above ONE is good.
(Project is under budget.)
SPI =
EV
PV
CPI =
EV
AC
Cost Management
Chapter 7Control Costs
Process 4
How much will this project cost us when we’re done?
EAC = Actual Costs (AC) +
Estimate at Completion (EAC)
Chapter 7, Topic 4
Estimated Cost to
Finish All Remaining
Work (ETC)
 An early warning signal that a threshold may be violated
 A tool to determine proactive behavior (e.g., changes in staffing, less
expensive materials)
Control Costs
Process 4
Cost Management
Chapter 7
EACNew
 Prior estimates are no
longer reliable.
 Remaining activity
costs are re-estimated
and aggregated.
 Common approach but
time-consuming and
expensive.
Chapter 7, Topic 4
EACNew = AC + Bottom-Up ETC
Example:
US$197K + (US$53K + US$42K +
US$68K) = US$360K
Cost Management
Chapter 7Control Costs
Process 4
EACCPI
 CPI is reliable indicator
of future performance.
 If future is likely to
follow past perfor-
mance, this method is
used.
Chapter 7, Topic 4
EACCPI
=
BAC
CPI
Example:
US$325,000/0.85 = US$382,353
Note that the CPI is below 1; the
project is over budget.
For ETC work performed at present CPI (typical variances)
Control Costs
Process 4
Cost Management
Chapter 7
EACBAC
 When variances were
due to identifiable events
that are now in the past
(i.e., the increased costs
are in the past).
 When future estimates
are probably accurate.
Chapter 7, Topic 4
EACBAC = AC + (BAC – EV)
Example:
US$197K + (US$325K – US$150K)
= US$197K + US$175K
= US$372K
For ETC work performed at budgeted rate (atypical variances)
Cost Management
Chapter 7Control Costs
Process 4
EACCPI * SPI
 CPI is considered accurate.
 There is a milestone or deadline
constraint (e.g., “We have to
finish the project on schedule!
What will it take?”).
Chapter 7, Topic 4
Example:
$197K +
= $197K +
= $197K + $217K = $414K
EACCPI ∗ SPI = AC +
(BAC – EV)
(CPI × SPI)
($325K – $150K)
(.85 × .95)
$175K
.807
Control Costs
Process 4
Cost Management
Chapter 7
A bridge must be in operation by a certain date. At
the data date, half of the work has been completed.
 BAC = US$15M
 CPI = .8
 SPI = .7
Calculate EAC.
Discussion Question
Answer:
Use the EACCPI ∗ SPI formula because of the schedule
constraint. EV is US$7.5M (half of scheduled work).
Calculate AC based on CPI formula to determine that
AC is US$9.375M. EAC will be US$22.768M.
Chapter 7, Topic 4
Estimate to Complete (ETC)
Once the EAC is known, we can
calculate the estimate to complete
by subtracting the budget already
spent (AC) from the estimated cost
of the project at completion.
Chapter 7, Topic 4
ETC = EAC – AC
Example:
US$22.768M – US$9.375M =
US$13.393M
Cost Management
Chapter 7Control Costs
Process 4
Variance at Completion (VAC)
 A projection of the probable
budget deficit or surplus
Chapter 7, Topic 4
VAC = BAC – EAC
Example:
US$15M – US$22.8M = <US$7.8M> BAC
EAC
Control Costs
Process 4
Cost Management
Chapter 7
TCPI Scenarios
Budget is achievable.
Use BAC.
Chapter 7, Topic 4
NOTE!
Unlike CPI and SPI, a TCPI above 1 is bad and below 1 is good.
A TCPI above 1 indicates that CPI must improve, which may be hard to achieve.
TCPIBAC =
(BAC – EV)
(BAC – AC)
Budget is clearly not viable.
Use EAC.
TCPIEAC =
(BAC – EV)
(EAC – AC)
Control Costs
Process 4
Cost Management
Chapter 7
The BAC is US$10M. EV is US$4M, and AC is
US$5M. What should the project manager do?
A. Take no action. The budget is achievable.
B. Prepare a change request to change the
schedule or cost baseline.
C. Motivate the team to work harder.
D. Add team members.
Discussion Question
Answer: B
Using the TCPIBAC formula, we find that the needed
future CPI is 1.2 (US$6M/US$5M). If we solve for the
historic CPI, we find that it is .8. The CPI is unlikely to
improve to more than .88, so a change request is in order.
Chapter 7, Topic 4
Discussion Question
Answer:
The project is behind
schedule (EV less than
PV) and above budget
(AC more than EV).
Chapter 7, Topic 4
Cumulative
Cost
Time
Project Budget
Management
Reserve
BAC
Actual Cost
(AC)
Data Date
Planned Value
(PV)
Earned Value
(EV)
Source: Adapted from Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management
Institute, Inc., 2017, Figure 7-12, Page 264. Material from this publication has been reproduced with the permission of PMI.
S-curve charts can be used to
visualize current and forecast
project performance.
What does this S-curve show?
S-curve charts can be used to
visualize current and forecast
project performance.
What does this S-curve show?
Discussion Question
Answer:
The project is behind
schedule (EV less than
PV) and above budget
(AC more than EV).
Chapter 7, Topic 4
Source: Adapted from Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management
Institute, Inc., 2017, Figure 7-12, Page 264. Material from this publication has been reproduced with the permission of PMI.
Cumulative
Cost
Time
Project Budget
Management
Reserve
BAC
Actual Cost
(AC)
Data Date
EAC
ETC
Planned Value
(PV)
Earned Value
(EV)
Cost Management
Chapter 7
Control Costs
Process 4
Project is on Track: .95 < CPI or SPI < 1.10 (Industry Rule)
Cost Management
Chapter 7
PMP Exam Prep
Group Exercise – PDM Critical Path

Weitere ähnliche Inhalte

Was ist angesagt?

Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examManish Purwar
 
Pm deep dive cost management
Pm deep dive   cost managementPm deep dive   cost management
Pm deep dive cost managementNiraj Agarwal
 
Earned value
Earned valueEarned value
Earned valueOliver
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis trainingPaul King
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementProPM Academy
 
Project cost & control
Project cost & controlProject cost & control
Project cost & controlAMARAYYA
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsIftikhar Anjum
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction projectIAEME Publication
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management EssentialsGlen Alleman
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementHayat Denzi
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value AnalysisSaqib Raza
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentationProPM Academy
 

Was ist angesagt? (19)

Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned value for pmp and pmi acp exam
Earned value for pmp and pmi acp examEarned value for pmp and pmi acp exam
Earned value for pmp and pmi acp exam
 
Project Control Process
Project Control ProcessProject Control Process
Project Control Process
 
Pm deep dive cost management
Pm deep dive   cost managementPm deep dive   cost management
Pm deep dive cost management
 
Earned value
Earned valueEarned value
Earned value
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Earned value analysis training
Earned value analysis trainingEarned value analysis training
Earned value analysis training
 
DPPM1
DPPM1DPPM1
DPPM1
 
A simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value ManagementA simple approach to understanding Earned Value Management
A simple approach to understanding Earned Value Management
 
The Benefits of using Earned Value Management
The Benefits of using Earned Value ManagementThe Benefits of using Earned Value Management
The Benefits of using Earned Value Management
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
Earned Value Management (EVM) Limitations
Earned Value Management (EVM) LimitationsEarned Value Management (EVM) Limitations
Earned Value Management (EVM) Limitations
 
Earned value analysis for a construction project
Earned value analysis for a construction projectEarned value analysis for a construction project
Earned value analysis for a construction project
 
Earned Value Management Essentials
Earned Value Management EssentialsEarned Value Management Essentials
Earned Value Management Essentials
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value analysis - presentation
Earned value analysis  -  presentationEarned value analysis  -  presentation
Earned value analysis - presentation
 

Ähnlich wie PMP M Charles_Spring2019_Week3_Chapter7

Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentationCDN_Irony
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdfzohir khellouf
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updatedShraddha PMP
 
Cost unit 2013 part 2. 24 jan
Cost unit 2013 part 2. 24 janCost unit 2013 part 2. 24 jan
Cost unit 2013 part 2. 24 janSkript
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost managementImran Jamil
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Cert iv cost part 2
Cert iv  cost part 2Cert iv  cost part 2
Cert iv cost part 2Skript
 
Basic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdfBasic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdfElyes ELEBRI
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationRicardo Viana Vargas
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfDr Mohamed Elfarran
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptadabotor7
 

Ähnlich wie PMP M Charles_Spring2019_Week3_Chapter7 (20)

Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentation
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
CAPM Week 3 Chapter 7
CAPM Week 3 Chapter 7CAPM Week 3 Chapter 7
CAPM Week 3 Chapter 7
 
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSISPROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
PROJECT HEALTH MONITORING BY EARNED VALUE ANALYSIS
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf03costestimation-140930114902-phpapp01.pdf
03costestimation-140930114902-phpapp01.pdf
 
07.cost management updated
07.cost management updated07.cost management updated
07.cost management updated
 
Cost unit 2013 part 2. 24 jan
Cost unit 2013 part 2. 24 janCost unit 2013 part 2. 24 jan
Cost unit 2013 part 2. 24 jan
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
A brief on project cost management
A brief on project cost managementA brief on project cost management
A brief on project cost management
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Cert iv cost part 2
Cert iv  cost part 2Cert iv  cost part 2
Cert iv cost part 2
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 
Basic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdfBasic Concepts of Earned Value Management.pdf
Basic Concepts of Earned Value Management.pdf
 
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo SimulationEarned Value Probabilistic Forecasting Using Monte Carlo Simulation
Earned Value Probabilistic Forecasting Using Monte Carlo Simulation
 
07 pmp cost management exam
07 pmp cost management exam07 pmp cost management exam
07 pmp cost management exam
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Project Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.pptProject Planning and Excution chapter 4.ppt
Project Planning and Excution chapter 4.ppt
 

Mehr von Muzette Charles, PMP

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderMuzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskMuzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8Muzette Charles, PMP
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5Muzette Charles, PMP
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3Muzette Charles, PMP
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewMuzette Charles, PMP
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10Muzette Charles, PMP
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8Muzette Charles, PMP
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2Muzette Charles, PMP
 

Mehr von Muzette Charles, PMP (20)

PMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics ReviewPMP Muzette Charles_Sp19_Week6_Ethics Review
PMP Muzette Charles_Sp19_Week6_Ethics Review
 
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_StakeholderPMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
PMP Muzette Charles_Sp2019_Chapter12_13 Procurement_Stakeholder
 
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_RiskPMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
PMP Muzette Charles_Sp2019_Week5_Chapter11_Risk
 
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10PMP Muzette Charles_Spring2019_Week4_Chapter9_10
PMP Muzette Charles_Spring2019_Week4_Chapter9_10
 
PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8PMP Muzette Charles_Spring2019_Week4_Chapter8
PMP Muzette Charles_Spring2019_Week4_Chapter8
 
PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6PMP Muzette Charles_Spring2019_Week3_Chapter6
PMP Muzette Charles_Spring2019_Week3_Chapter6
 
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5PMP Muzette Charles_Sp2019_Week2_Chapter4_5
PMP Muzette Charles_Sp2019_Week2_Chapter4_5
 
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
PMP Muzette Charles_Sp2019_Week1_chapter1_2_3
 
CAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_ReviewCAPM Muzette Charles Ethics_Review
CAPM Muzette Charles Ethics_Review
 
CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13CAPM Muzette Charles Chapter11-13
CAPM Muzette Charles Chapter11-13
 
CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10CAPM Muzette Charles Week5 Chapter9-10
CAPM Muzette Charles Week5 Chapter9-10
 
CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8CAPM Muzette Charles_Week4_Chapter7-8
CAPM Muzette Charles_Week4_Chapter7-8
 
CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4CAPM Muzette Charles Chapter3-4
CAPM Muzette Charles Chapter3-4
 
CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6CAPM M Charles Week3 Chapter5-6
CAPM M Charles Week3 Chapter5-6
 
CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2CAPM Muzette Charles_Week1_Chapter1-2
CAPM Muzette Charles_Week1_Chapter1-2
 
CAPM Week 6 Final Review
CAPM Week 6 Final ReviewCAPM Week 6 Final Review
CAPM Week 6 Final Review
 
CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13CAPM Week 5 Chapter 13
CAPM Week 5 Chapter 13
 
CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12CAPM Week 5 Chapter 12
CAPM Week 5 Chapter 12
 
CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11CAPM Week 4 Chapter 11
CAPM Week 4 Chapter 11
 
CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10CAPM Week 4 Chapter 10
CAPM Week 4 Chapter 10
 

Kürzlich hochgeladen

TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxnegromaestrong
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docxPoojaSen20
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.pptRamjanShidvankar
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxdhanalakshmis0310
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentationcamerronhm
 

Kürzlich hochgeladen (20)

TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
Asian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptxAsian American Pacific Islander Month DDSD 2024.pptx
Asian American Pacific Islander Month DDSD 2024.pptx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptx
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 

PMP M Charles_Spring2019_Week3_Chapter7

  • 1. Project Management Professional PMP® Exam Prep – Week 3 Cost Management Muzette Charles, PMP | mcharles2@pace.edu
  • 2. Cost Management Chapter 7 “… includes the processes involved in planning, estimating, budgeting, financing, funding, managing & controlling costs so that the project can be completed within the approved budget.” Process Process Group Key Deliverables 7.1 Plan Cost Management Planning Cost Management Plan 7.2 Estimate Costs Planning Activity cost estimates 7.3 Determine Budget Planning Cost Baseline (budget) 7.4 Control Costs Monitoring & Controlling Change Requests
  • 3. Cost Management Chapter 7 Plan Cost Management Process 1 Key Points  Provides guidance on how costs aka budget, will be managed throughout the project  Aligns with Schedule baseline estimates, units of measure, level of accuracy (+/- %)  Funding decisions: existing funds, equity or debt
  • 4. Chapter 7, Topic 1 Units of Measure • Currency, exchange rates Level of Precision • Rounding Level of Accuracy • Acceptable estimate ranges, inclusion of contingency funds Organizational Procedure Links • Alignment with WBS control accounts Control Thresholds •When alarms will go off Measurement Rules •When and how to make what types of measurements Record and Report •What to record, who gets a report, when and at what level Cost Management Chapter 7 Plan Cost Management Process 1
  • 5. Cost Management Chapter 7 Estimate Costs Process 2 Key Points  Developing the monetary cost each activity needed to complete the project  Cost estimates are a prediction based on info known at a given point in time & is constantly reviewed  Expected accuracy: initially ROM -25% to +75% , Budget -10% to +25%, Definitive -5% to +10%  Usually expressed in currency: dollars, euros, yen, etc
  • 6. Early Planning Level of Precision  What level of variance from estimates will trigger the need for further investigation and possible action?  Only rough order of magnitude (ROM) has a standard range. The others are typical of that stage in a project for that organization. Chapter 7, Topic 2 Rough order of magnitude (ROM) –25% to +75% Conceptual –10% to +25% Definitive –5% to +10% Initiating Final Planning and into Executing Cost Management Chapter 7 Estimate Costs Process 2
  • 7. In the project charter, costs were estimated at US$2,000,000. What is the upper threshold to which costs might extend by the time the project reaches Executing? A. US$2,500,000 B. US$3,000,000 C. US$3,500,000 D. US$3,750,000 Discussion Question Answer: C The project charter typically uses a ROM, which means the estimation could increase by up to 75%, or US$3,500,000. Chapter 7, Topic 2
  • 8. Cost Estimates Key Output  Estimate costs by activity.  Consider all costs:  Direct expenses (e.g., labor, materials, services)  Special costs (e.g., currency exchange rates)  Indirect costs (e.g., space and services provided) Chapter 7, Topic 2 Cost Management Chapter 7 Estimate Costs Process 2
  • 9. Cost Management Chapter 7 Determine Budget Process 3 Key Points  Budget: all the calculated funds authorized to execute the project, includes reserves  Cost baseline: the approved version of the budget, less Management Reserves, used as a benchmark for variance analysis to measure project’s success.  Reserve Analysis: Contingency Reserve & Management Reserve  Funding Limit Reconciliation: PM is responsible to not exceed funding limits
  • 10. Cost Management Chapter 7 Determine Budget Process 3 Cost Aggregation
  • 11. Chapter 7, Topic 2 Activity Cost Estimates Work Package Cost Estimates Contingency Reserves for Activities General Contingency Reserve Cost Baseline (All Control Accounts) Management Reserve Project Budget + + + = = = Contingency Reserve Budget within the cost baseline allocated for managing identified risks Management Reserve Amount of project budget withheld by management to respond to unforeseen needs Source: Adapted from Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2017, Figure 7-8, Page 255. Material from this publication has been reproduced with the permission of PMI. Cost Management Chapter 7 Determine Budget Process 3
  • 12. Cost Baseline S-curve chart provides a time- phased view of the cost baseline—how activities may have to be reconciled with funding infusion and when reserves may have to be tapped. Chapter 7, Topic 3 Cumulative Values Time Project Budget Management Reserve Budget at Completion (BAC) Funding Requirements Cost Baseline Expenditures Source: Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2017, Figure 7-9, Page 255. Material from this publication has been reproduced with the permission of PMI. Cost Management Chapter 7 Determine Budget Process 3
  • 13. Cost Baseline Key Points  The project manager is responsible for controlling spending and releasing funds within the cost baseline.  Funds are usually released over time, and funding schedules must be reconciled with work schedules.  The cost baseline includes both contingency and reserves and work package cost estimates.  It is the benchmark for project cost performance.  All changes must be made through the integrated change control process. Chapter 7, Topic 3 Cost Management Chapter 7 Determine Budget Process 3
  • 14. During project execution, a contractor defaults. How will the resulting increases in costs be funded? A. Contingency reserves B. Management reserves C. Change request to increase cost baseline Discussion Question Answer: B This is probably an unexpected risk, since if there was serious risk of default, the contractor, in most cases, wouldn’t have been selected. Management reserves are earmarked for these unforeseen risks. Chapter 7, Topic 3
  • 15. Cost Management Chapter 7 Key Points  Earned Value Mgmt (EVM):  Assessing both schedule & cost performance through the concept of earned value; the monetary value of work actually completed  Tracks how is your project is performing against the plan  Variances & forecast future performance, cost & completion date  Performance Measurement Baseline: integrates cost, time & scope to predict variance, correct & minimize risk Control Costs Process 4
  • 16. Match each EVM term with the correct definition. Discussion Question Answers: 1—b; 2—a; 3—c Chapter 7, Topic 4 1. Earned value 2. Planned value 3. Actual cost a. Authorized budget for scheduled work b. Budgeted cost of completed work to the reference point c. Amount of money spent by the reference point
  • 17. EVM Variances A variance uses subtraction to compare baseline and actual performance. The first term is always EV. Chapter 7, Topic 4 Schedule Variance How does the work done compare with the work that was scheduled to be done? SV = EV − PV Cost Variance How does the amount of work done compare with the budget dollars spent? CV = EV − AC A positive result is good. The project is ahead of schedule. A positive result is good. The project is under budget. Control Costs Process 4 Cost Management Chapter 7
  • 18. EVM Performance Indices A performance index is a ratio that uses division. The numerator is always EV. Chapter 7, Topic 4 Schedule Performance Index How well is the project performing against the schedule? Cost Performance Index How is the project performing against the budget? Above ONE is good. (Project is ahead of schedule.) Above ONE is good. (Project is under budget.) SPI = EV PV CPI = EV AC Cost Management Chapter 7Control Costs Process 4
  • 19. How much will this project cost us when we’re done? EAC = Actual Costs (AC) + Estimate at Completion (EAC) Chapter 7, Topic 4 Estimated Cost to Finish All Remaining Work (ETC)  An early warning signal that a threshold may be violated  A tool to determine proactive behavior (e.g., changes in staffing, less expensive materials) Control Costs Process 4 Cost Management Chapter 7
  • 20. EACNew  Prior estimates are no longer reliable.  Remaining activity costs are re-estimated and aggregated.  Common approach but time-consuming and expensive. Chapter 7, Topic 4 EACNew = AC + Bottom-Up ETC Example: US$197K + (US$53K + US$42K + US$68K) = US$360K Cost Management Chapter 7Control Costs Process 4
  • 21. EACCPI  CPI is reliable indicator of future performance.  If future is likely to follow past perfor- mance, this method is used. Chapter 7, Topic 4 EACCPI = BAC CPI Example: US$325,000/0.85 = US$382,353 Note that the CPI is below 1; the project is over budget. For ETC work performed at present CPI (typical variances) Control Costs Process 4 Cost Management Chapter 7
  • 22. EACBAC  When variances were due to identifiable events that are now in the past (i.e., the increased costs are in the past).  When future estimates are probably accurate. Chapter 7, Topic 4 EACBAC = AC + (BAC – EV) Example: US$197K + (US$325K – US$150K) = US$197K + US$175K = US$372K For ETC work performed at budgeted rate (atypical variances) Cost Management Chapter 7Control Costs Process 4
  • 23. EACCPI * SPI  CPI is considered accurate.  There is a milestone or deadline constraint (e.g., “We have to finish the project on schedule! What will it take?”). Chapter 7, Topic 4 Example: $197K + = $197K + = $197K + $217K = $414K EACCPI ∗ SPI = AC + (BAC – EV) (CPI × SPI) ($325K – $150K) (.85 × .95) $175K .807 Control Costs Process 4 Cost Management Chapter 7
  • 24. A bridge must be in operation by a certain date. At the data date, half of the work has been completed.  BAC = US$15M  CPI = .8  SPI = .7 Calculate EAC. Discussion Question Answer: Use the EACCPI ∗ SPI formula because of the schedule constraint. EV is US$7.5M (half of scheduled work). Calculate AC based on CPI formula to determine that AC is US$9.375M. EAC will be US$22.768M. Chapter 7, Topic 4
  • 25. Estimate to Complete (ETC) Once the EAC is known, we can calculate the estimate to complete by subtracting the budget already spent (AC) from the estimated cost of the project at completion. Chapter 7, Topic 4 ETC = EAC – AC Example: US$22.768M – US$9.375M = US$13.393M Cost Management Chapter 7Control Costs Process 4
  • 26. Variance at Completion (VAC)  A projection of the probable budget deficit or surplus Chapter 7, Topic 4 VAC = BAC – EAC Example: US$15M – US$22.8M = <US$7.8M> BAC EAC Control Costs Process 4 Cost Management Chapter 7
  • 27. TCPI Scenarios Budget is achievable. Use BAC. Chapter 7, Topic 4 NOTE! Unlike CPI and SPI, a TCPI above 1 is bad and below 1 is good. A TCPI above 1 indicates that CPI must improve, which may be hard to achieve. TCPIBAC = (BAC – EV) (BAC – AC) Budget is clearly not viable. Use EAC. TCPIEAC = (BAC – EV) (EAC – AC) Control Costs Process 4 Cost Management Chapter 7
  • 28. The BAC is US$10M. EV is US$4M, and AC is US$5M. What should the project manager do? A. Take no action. The budget is achievable. B. Prepare a change request to change the schedule or cost baseline. C. Motivate the team to work harder. D. Add team members. Discussion Question Answer: B Using the TCPIBAC formula, we find that the needed future CPI is 1.2 (US$6M/US$5M). If we solve for the historic CPI, we find that it is .8. The CPI is unlikely to improve to more than .88, so a change request is in order. Chapter 7, Topic 4
  • 29. Discussion Question Answer: The project is behind schedule (EV less than PV) and above budget (AC more than EV). Chapter 7, Topic 4 Cumulative Cost Time Project Budget Management Reserve BAC Actual Cost (AC) Data Date Planned Value (PV) Earned Value (EV) Source: Adapted from Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2017, Figure 7-12, Page 264. Material from this publication has been reproduced with the permission of PMI. S-curve charts can be used to visualize current and forecast project performance. What does this S-curve show?
  • 30. S-curve charts can be used to visualize current and forecast project performance. What does this S-curve show? Discussion Question Answer: The project is behind schedule (EV less than PV) and above budget (AC more than EV). Chapter 7, Topic 4 Source: Adapted from Project Management Institute, A Guide to the Project Management Body of Knowledge (PMBOK® Guide)—Sixth Edition, Project Management Institute, Inc., 2017, Figure 7-12, Page 264. Material from this publication has been reproduced with the permission of PMI. Cumulative Cost Time Project Budget Management Reserve BAC Actual Cost (AC) Data Date EAC ETC Planned Value (PV) Earned Value (EV)
  • 31. Cost Management Chapter 7 Control Costs Process 4 Project is on Track: .95 < CPI or SPI < 1.10 (Industry Rule)
  • 33. PMP Exam Prep Group Exercise – PDM Critical Path