SlideShare ist ein Scribd-Unternehmen logo
1 von 3
Downloaden Sie, um offline zu lesen
STEPS OF DETERMINING THE MOST ECONOMIC PIPE SIZE:
1 | P a g e
1. Knowing the required process flow rate, the allowable head loss in the pipe using Darcy
Weisbach equation.
2. Using the available fluid properties, required flow rate, pipe length and pipe material,
calculate the required Reynolds number, relative roughness, friction factor and head loss
due to friction.
3. Assume appropriate equipment operating efficiency.
For pumps, use 60 %.
For electric motors, use 90 %.
Determine the required energy input to overcome system fluid friction losses.
𝑃𝑜𝑤𝑒𝑟 =
𝑄 × ℎ 𝑓 × 𝐺
367 × 𝜂 𝑝 × 𝜂 𝑚
𝑄: 𝑉𝑜𝑙𝑢𝑚𝑒𝑡𝑟𝑖𝑐 𝑓𝑙𝑜𝑤 𝑟𝑎𝑡𝑒 ( 𝑚3
ℎ𝑟⁄ )
ℎ 𝑓: 𝐹𝑟𝑖𝑐𝑡𝑖𝑜𝑛𝑎𝑙 ℎ𝑒𝑎𝑑 𝑙𝑜𝑠𝑠 (𝑓𝑡)
𝐺: 𝑠𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝑔𝑟𝑎𝑣𝑖𝑡𝑦
𝑃𝑜𝑤𝑒𝑟 (𝑘𝑤)
𝜂 𝑚, 𝜂 𝑝: 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 𝑜𝑓 𝑚𝑜𝑡𝑜𝑟, 𝑝𝑢𝑚𝑝
4. Based on the stated running hours, compute the system’s annual operating energy cost.
5. Find out the manufacture’s price quotation for the pump and driver based on the required
flow rate and the calculated head.
6. Find out the maintenance cost. Assume that the annual maintenance costs will be 4% of
the price.
7. Calculate the present value of each pipe size and select the lowest present value cost.
Example:
A water would be pumped from a a tank as shown in the following diamgram.
The fluid properties are as fellow:
ρ = 998 Kg/m3, µ = 9.82E-04 Pa.S,
ɛ = 0.0003 m,
Q = 100 m3
/hr,
Pv @ 25 o
C = 0.0316 Bara
Solution
1. Preliminary sizing of suction pipe line
Vapor pressure of water at 25 o
C = 0.0316 Bara.
Hmax= 9.8 m
D, in A, m2
V m/s Re F H_Major H_Minor H_total
2 0.00196 14.26 7.25E+05 8.35E-02 173.08 1.55 174.63
3 0.00442 6.3379 4.83E+05 1.32E-02 3.6 0.3 3.9
4 0.00785 3.56 3.62E+05 1.39E-02 0.9 0.097 0.997
5 0.01227 2.28 2.90E+05 1.45E-02 0.31 0.039 0.35
10 m 20 m
4 m
10 m
STEPS OF DETERMINING THE MOST ECONOMIC PIPE SIZE:
2 | P a g e
Liquid velocities in straight pipe in excess of 4.6 m/s will generally produce
objectionable noise. Where there are numerous bends, valves, the velocity limit for noise
may be in the order of 3 m/s.
The preliminary pipe diameter should be 4 in.
Assume that the discharge pipe diameter is like the suction.
D, in H_Major H_minor H_total
4 11.8 0.097 11.9
5 10.61 0.039 10.65
So, we would select 4, 5 in to enter to the economic analysis of the pipe
The pump should be selected according to the following criteria:
Flow rate = 100 m3
/h
Required flow head = 12,8 m
2. Economic analysis of suction pipeline
Note: The prices assumed here are only for illustration
• Calculate the pump power:
D, in Power, KW
4 6.49
5 5.5
Assume the energy power 1 $/KWh
Thus, the annual energy cost based on 8000 hrs yearly:
D, in Cost, $
4 51,920
5 44,000
• Here, I assume the capital cost of the pump is 13,000 $.
• The maintenance cost = 520 $
Thus, the annual cost:
D, in Annual cost, $
4 52,440
5 44,520
• Estimate the total capital cost
D, in Labor cost, $
4 30,000
5 50,000
• Break-even analysis:
𝑛 𝑒 =
50,000 − 30,000
52,440 − 44,520
= 2.5 𝑦𝑟
STEPS OF DETERMINING THE MOST ECONOMIC PIPE SIZE:
3 | P a g e
• Estimate the total life cycle cost:
D, in Present value, $
4 574,309
5 512,102
So, the optimum economic pipe diameter is 5 in.
Summary of Economic variables for two pipe systems
Parameter 4 in 5 in
Fluid velocity m/s 3.56 2.28
Reynolds number 3.62E+5 2.9E+5
Head loss due to friction, m 11.9 10.65
Power, KW 6.49 5.5
Annual cost, $ 52,440 44,520
Initial capital cost, $ 30,000 50,000
Life cycle present value, $ 574,309 512,102
Conclusion:
What is appeared from the first glance that the optimum diameter is the smallest diameter with
smallest initial cost, but what is appeared economically is that the 5 in pipe is optimum
economically.
Hint:
All the cost and prices are for illustration only and not actual.
Break-even analysis:
𝑛 𝑒 =
𝐷𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 𝑖𝑛 𝑐𝑎𝑝𝑖𝑡𝑎𝑙 cos𝑡
𝐷𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 𝑖𝑛 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 cos𝑡
Total life cycle cost present value:
𝐶 = 𝐶𝑖 + 𝐶0
(1 + 𝑖) 𝑛
− 1
𝑖(1 + 𝑖) 𝑛
Ci: initial capital cost, $
Co: operating cost
i: interest rate
n: total life time

Weitere ähnliche Inhalte

Was ist angesagt?

Selection of Heat Exchanger Types
Selection of Heat Exchanger TypesSelection of Heat Exchanger Types
Selection of Heat Exchanger Types
Gerard B. Hawkins
 
Gas Absorption & Stripping in Chemical Engineering (Part 2/4)
Gas Absorption & Stripping in Chemical Engineering (Part 2/4)Gas Absorption & Stripping in Chemical Engineering (Part 2/4)
Gas Absorption & Stripping in Chemical Engineering (Part 2/4)
Chemical Engineering Guy
 
Gas Absorption & Stripping in Chemical Engineering (Part 3/4)
Gas Absorption & Stripping in Chemical Engineering (Part 3/4)Gas Absorption & Stripping in Chemical Engineering (Part 3/4)
Gas Absorption & Stripping in Chemical Engineering (Part 3/4)
Chemical Engineering Guy
 
H2 Plant presentation-2
H2 Plant presentation-2H2 Plant presentation-2
H2 Plant presentation-2
Nageswar Rao
 
Flash Distillation in Chemical and Process Engineering (Part 2 of 3)
Flash Distillation in Chemical and Process Engineering (Part 2 of 3)Flash Distillation in Chemical and Process Engineering (Part 2 of 3)
Flash Distillation in Chemical and Process Engineering (Part 2 of 3)
Chemical Engineering Guy
 

Was ist angesagt? (20)

Flarenet
FlarenetFlarenet
Flarenet
 
01 kern's method.
01 kern's method.01 kern's method.
01 kern's method.
 
Flow through pipes ppt
Flow through pipes pptFlow through pipes ppt
Flow through pipes ppt
 
Absorption and Stripping - mass transfer
Absorption and Stripping - mass transferAbsorption and Stripping - mass transfer
Absorption and Stripping - mass transfer
 
Design Calculation of Venting for Atmospheric & Low Pressure Storage Tanks
Design Calculation of Venting for Atmospheric & Low Pressure Storage TanksDesign Calculation of Venting for Atmospheric & Low Pressure Storage Tanks
Design Calculation of Venting for Atmospheric & Low Pressure Storage Tanks
 
FR MULTIPLE EFFECT EVAPORATION
FR MULTIPLE EFFECT EVAPORATIONFR MULTIPLE EFFECT EVAPORATION
FR MULTIPLE EFFECT EVAPORATION
 
AFD7 Agitation and Mixing
AFD7 Agitation and MixingAFD7 Agitation and Mixing
AFD7 Agitation and Mixing
 
flare system design.pdf
flare system design.pdfflare system design.pdf
flare system design.pdf
 
Selection of Heat Exchanger Types
Selection of Heat Exchanger TypesSelection of Heat Exchanger Types
Selection of Heat Exchanger Types
 
Gas Absorption & Stripping in Chemical Engineering (Part 2/4)
Gas Absorption & Stripping in Chemical Engineering (Part 2/4)Gas Absorption & Stripping in Chemical Engineering (Part 2/4)
Gas Absorption & Stripping in Chemical Engineering (Part 2/4)
 
Gas Absorption & Stripping in Chemical Engineering (Part 3/4)
Gas Absorption & Stripping in Chemical Engineering (Part 3/4)Gas Absorption & Stripping in Chemical Engineering (Part 3/4)
Gas Absorption & Stripping in Chemical Engineering (Part 3/4)
 
Understanding npsh and cavitation
Understanding npsh and cavitationUnderstanding npsh and cavitation
Understanding npsh and cavitation
 
Dimensionless number
Dimensionless numberDimensionless number
Dimensionless number
 
Single phase flow line sizing
Single phase flow line sizingSingle phase flow line sizing
Single phase flow line sizing
 
Aspen HYSYS - Basic Course (SS)
Aspen HYSYS - Basic Course (SS)Aspen HYSYS - Basic Course (SS)
Aspen HYSYS - Basic Course (SS)
 
H2 Plant presentation-2
H2 Plant presentation-2H2 Plant presentation-2
H2 Plant presentation-2
 
Flash Distillation in Chemical and Process Engineering (Part 2 of 3)
Flash Distillation in Chemical and Process Engineering (Part 2 of 3)Flash Distillation in Chemical and Process Engineering (Part 2 of 3)
Flash Distillation in Chemical and Process Engineering (Part 2 of 3)
 
Selection and Design of Condensers
Selection and Design of CondensersSelection and Design of Condensers
Selection and Design of Condensers
 
CENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIAL
CENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIALCENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIAL
CENTRIFUGAL COMPRESSOR SETTLE OUT CONDITIONS TUTORIAL
 
Agitated vessel Design
Agitated vessel Design Agitated vessel Design
Agitated vessel Design
 

Ähnlich wie Economic pipe size

Energy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans pptEnergy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans ppt
D.Pawan Kumar
 
Boiler doc 04 flowmetering
Boiler doc 04   flowmeteringBoiler doc 04   flowmetering
Boiler doc 04 flowmetering
Mars Tsani
 
Flow measurement basics
Flow measurement basicsFlow measurement basics
Flow measurement basics
Salman1011
 
H&MProject_TylerLenzen_Spring2014
H&MProject_TylerLenzen_Spring2014H&MProject_TylerLenzen_Spring2014
H&MProject_TylerLenzen_Spring2014
Tyler Lenzen
 

Ähnlich wie Economic pipe size (20)

MATHEMATICAL MODELLING FOR ANALYSIS OF CHANGE IN SHAPE OF SUCTION MANIFOLD TO...
MATHEMATICAL MODELLING FOR ANALYSIS OF CHANGE IN SHAPE OF SUCTION MANIFOLD TO...MATHEMATICAL MODELLING FOR ANALYSIS OF CHANGE IN SHAPE OF SUCTION MANIFOLD TO...
MATHEMATICAL MODELLING FOR ANALYSIS OF CHANGE IN SHAPE OF SUCTION MANIFOLD TO...
 
friction loss along a pipe
friction loss along a pipefriction loss along a pipe
friction loss along a pipe
 
Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014Optimum overhaul of pumps 2014
Optimum overhaul of pumps 2014
 
Energy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans pptEnergy efficiency in pumps and fans ppt
Energy efficiency in pumps and fans ppt
 
Improving Energy Efficiency of Pumps and Fans
Improving Energy Efficiency of Pumps and FansImproving Energy Efficiency of Pumps and Fans
Improving Energy Efficiency of Pumps and Fans
 
Steam Header Design in Fluid (Steam) System
Steam Header Design in Fluid (Steam) SystemSteam Header Design in Fluid (Steam) System
Steam Header Design in Fluid (Steam) System
 
Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)Be project - PRDS (Pressure Reducing And Desuperheater Station)
Be project - PRDS (Pressure Reducing And Desuperheater Station)
 
IRJET- Computational Fluid Dynamic Analysis of Performance of Centrifugal Pum...
IRJET- Computational Fluid Dynamic Analysis of Performance of Centrifugal Pum...IRJET- Computational Fluid Dynamic Analysis of Performance of Centrifugal Pum...
IRJET- Computational Fluid Dynamic Analysis of Performance of Centrifugal Pum...
 
Mech CE6461 FMM lab_manual
Mech CE6461 FMM lab_manualMech CE6461 FMM lab_manual
Mech CE6461 FMM lab_manual
 
Boiler doc 04 flowmetering
Boiler doc 04   flowmeteringBoiler doc 04   flowmetering
Boiler doc 04 flowmetering
 
Centrifugal pump sizing tutorial
Centrifugal pump sizing   tutorialCentrifugal pump sizing   tutorial
Centrifugal pump sizing tutorial
 
Flow measurement basics
Flow measurement basicsFlow measurement basics
Flow measurement basics
 
H&MProject_TylerLenzen_Spring2014
H&MProject_TylerLenzen_Spring2014H&MProject_TylerLenzen_Spring2014
H&MProject_TylerLenzen_Spring2014
 
Design Considerations for Antisurge Valve Sizing
Design Considerations for Antisurge Valve SizingDesign Considerations for Antisurge Valve Sizing
Design Considerations for Antisurge Valve Sizing
 
Section 7 multistage separation processes
Section 7   multistage separation processesSection 7   multistage separation processes
Section 7 multistage separation processes
 
Experimental Study and Investigation of Helical Pipe Heat Exchanger with Vary...
Experimental Study and Investigation of Helical Pipe Heat Exchanger with Vary...Experimental Study and Investigation of Helical Pipe Heat Exchanger with Vary...
Experimental Study and Investigation of Helical Pipe Heat Exchanger with Vary...
 
Design of Sprinkler System and CO2 Total Flooding System of Given Plan I Gaur...
Design of Sprinkler System and CO2 Total Flooding System of Given Plan I Gaur...Design of Sprinkler System and CO2 Total Flooding System of Given Plan I Gaur...
Design of Sprinkler System and CO2 Total Flooding System of Given Plan I Gaur...
 
Fluid mechanics lab manual
Fluid mechanics lab manualFluid mechanics lab manual
Fluid mechanics lab manual
 
Quishpe mireya practica6
Quishpe mireya practica6Quishpe mireya practica6
Quishpe mireya practica6
 
Be project final_project_first_stage_presentation
Be project final_project_first_stage_presentationBe project final_project_first_stage_presentation
Be project final_project_first_stage_presentation
 

Mehr von Mohamed A. Hassan, CEng MIChemE

Mehr von Mohamed A. Hassan, CEng MIChemE (13)

Mohmed Abdel Salam Hasan - CEng Certificate.pdf
Mohmed Abdel Salam Hasan - CEng Certificate.pdfMohmed Abdel Salam Hasan - CEng Certificate.pdf
Mohmed Abdel Salam Hasan - CEng Certificate.pdf
 
Certified PHA-HAZOP Leader
Certified PHA-HAZOP Leader Certified PHA-HAZOP Leader
Certified PHA-HAZOP Leader
 
TechnipFMC spyro
TechnipFMC spyroTechnipFMC spyro
TechnipFMC spyro
 
Everyday pipeline engineering calculations
Everyday pipeline engineering calculationsEveryday pipeline engineering calculations
Everyday pipeline engineering calculations
 
Vertical vapor liquid separator
Vertical vapor liquid separatorVertical vapor liquid separator
Vertical vapor liquid separator
 
Separator feed characteristics
Separator feed characteristicsSeparator feed characteristics
Separator feed characteristics
 
Preliminary selection of centrifugal compressor
Preliminary selection of centrifugal compressorPreliminary selection of centrifugal compressor
Preliminary selection of centrifugal compressor
 
Hydrate formation temperature prediction
Hydrate formation temperature predictionHydrate formation temperature prediction
Hydrate formation temperature prediction
 
Heat exchanger effecctiveness
Heat exchanger effecctivenessHeat exchanger effecctiveness
Heat exchanger effecctiveness
 
Flow regime and droplets diameter calculations
Flow regime and droplets diameter calculationsFlow regime and droplets diameter calculations
Flow regime and droplets diameter calculations
 
Flow measurement through orifice
Flow measurement through orificeFlow measurement through orifice
Flow measurement through orifice
 
Azeotropic distillation 1
Azeotropic distillation 1Azeotropic distillation 1
Azeotropic distillation 1
 
Azeotropic distillation 2
Azeotropic distillation 2Azeotropic distillation 2
Azeotropic distillation 2
 

Kürzlich hochgeladen

Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
amitlee9823
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
dharasingh5698
 

Kürzlich hochgeladen (20)

Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night StandCall Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
Call Girls In Bangalore ☎ 7737669865 🥵 Book Your One night Stand
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
DC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equationDC MACHINE-Motoring and generation, Armature circuit equation
DC MACHINE-Motoring and generation, Armature circuit equation
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 

Economic pipe size

  • 1. STEPS OF DETERMINING THE MOST ECONOMIC PIPE SIZE: 1 | P a g e 1. Knowing the required process flow rate, the allowable head loss in the pipe using Darcy Weisbach equation. 2. Using the available fluid properties, required flow rate, pipe length and pipe material, calculate the required Reynolds number, relative roughness, friction factor and head loss due to friction. 3. Assume appropriate equipment operating efficiency. For pumps, use 60 %. For electric motors, use 90 %. Determine the required energy input to overcome system fluid friction losses. 𝑃𝑜𝑤𝑒𝑟 = 𝑄 × ℎ 𝑓 × 𝐺 367 × 𝜂 𝑝 × 𝜂 𝑚 𝑄: 𝑉𝑜𝑙𝑢𝑚𝑒𝑡𝑟𝑖𝑐 𝑓𝑙𝑜𝑤 𝑟𝑎𝑡𝑒 ( 𝑚3 ℎ𝑟⁄ ) ℎ 𝑓: 𝐹𝑟𝑖𝑐𝑡𝑖𝑜𝑛𝑎𝑙 ℎ𝑒𝑎𝑑 𝑙𝑜𝑠𝑠 (𝑓𝑡) 𝐺: 𝑠𝑝𝑒𝑐𝑖𝑓𝑖𝑐 𝑔𝑟𝑎𝑣𝑖𝑡𝑦 𝑃𝑜𝑤𝑒𝑟 (𝑘𝑤) 𝜂 𝑚, 𝜂 𝑝: 𝐸𝑓𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑦 𝑜𝑓 𝑚𝑜𝑡𝑜𝑟, 𝑝𝑢𝑚𝑝 4. Based on the stated running hours, compute the system’s annual operating energy cost. 5. Find out the manufacture’s price quotation for the pump and driver based on the required flow rate and the calculated head. 6. Find out the maintenance cost. Assume that the annual maintenance costs will be 4% of the price. 7. Calculate the present value of each pipe size and select the lowest present value cost. Example: A water would be pumped from a a tank as shown in the following diamgram. The fluid properties are as fellow: ρ = 998 Kg/m3, µ = 9.82E-04 Pa.S, ɛ = 0.0003 m, Q = 100 m3 /hr, Pv @ 25 o C = 0.0316 Bara Solution 1. Preliminary sizing of suction pipe line Vapor pressure of water at 25 o C = 0.0316 Bara. Hmax= 9.8 m D, in A, m2 V m/s Re F H_Major H_Minor H_total 2 0.00196 14.26 7.25E+05 8.35E-02 173.08 1.55 174.63 3 0.00442 6.3379 4.83E+05 1.32E-02 3.6 0.3 3.9 4 0.00785 3.56 3.62E+05 1.39E-02 0.9 0.097 0.997 5 0.01227 2.28 2.90E+05 1.45E-02 0.31 0.039 0.35 10 m 20 m 4 m 10 m
  • 2. STEPS OF DETERMINING THE MOST ECONOMIC PIPE SIZE: 2 | P a g e Liquid velocities in straight pipe in excess of 4.6 m/s will generally produce objectionable noise. Where there are numerous bends, valves, the velocity limit for noise may be in the order of 3 m/s. The preliminary pipe diameter should be 4 in. Assume that the discharge pipe diameter is like the suction. D, in H_Major H_minor H_total 4 11.8 0.097 11.9 5 10.61 0.039 10.65 So, we would select 4, 5 in to enter to the economic analysis of the pipe The pump should be selected according to the following criteria: Flow rate = 100 m3 /h Required flow head = 12,8 m 2. Economic analysis of suction pipeline Note: The prices assumed here are only for illustration • Calculate the pump power: D, in Power, KW 4 6.49 5 5.5 Assume the energy power 1 $/KWh Thus, the annual energy cost based on 8000 hrs yearly: D, in Cost, $ 4 51,920 5 44,000 • Here, I assume the capital cost of the pump is 13,000 $. • The maintenance cost = 520 $ Thus, the annual cost: D, in Annual cost, $ 4 52,440 5 44,520 • Estimate the total capital cost D, in Labor cost, $ 4 30,000 5 50,000 • Break-even analysis: 𝑛 𝑒 = 50,000 − 30,000 52,440 − 44,520 = 2.5 𝑦𝑟
  • 3. STEPS OF DETERMINING THE MOST ECONOMIC PIPE SIZE: 3 | P a g e • Estimate the total life cycle cost: D, in Present value, $ 4 574,309 5 512,102 So, the optimum economic pipe diameter is 5 in. Summary of Economic variables for two pipe systems Parameter 4 in 5 in Fluid velocity m/s 3.56 2.28 Reynolds number 3.62E+5 2.9E+5 Head loss due to friction, m 11.9 10.65 Power, KW 6.49 5.5 Annual cost, $ 52,440 44,520 Initial capital cost, $ 30,000 50,000 Life cycle present value, $ 574,309 512,102 Conclusion: What is appeared from the first glance that the optimum diameter is the smallest diameter with smallest initial cost, but what is appeared economically is that the 5 in pipe is optimum economically. Hint: All the cost and prices are for illustration only and not actual. Break-even analysis: 𝑛 𝑒 = 𝐷𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 𝑖𝑛 𝑐𝑎𝑝𝑖𝑡𝑎𝑙 cos𝑡 𝐷𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 𝑖𝑛 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 cos𝑡 Total life cycle cost present value: 𝐶 = 𝐶𝑖 + 𝐶0 (1 + 𝑖) 𝑛 − 1 𝑖(1 + 𝑖) 𝑛 Ci: initial capital cost, $ Co: operating cost i: interest rate n: total life time