Activity ID Activity Name Original
Duration
Start Finish
14234-3 Eg14234-3 Egbaoma Gas Processing Plant - New 586 05-Aug-14 A 04-Apr-16
14234-3.Co14234-3.Contract About Contract 459 05-Aug-14 A 04-Apr-16
A21270 Kick Off Meeting 0 05-Aug-14 A
A21280 Commencement of Project Work 0 05-Aug-14 A
A21790 HAZOP 8 17-Dec-14 A 24-Dec-14 A
A21800 Engineering Completion 0 21-Sep-15
A21810 Procurement Completion 0 26-Oct-15
A21820 Site Modification, Construction & Erection Works Completion 0 24-Feb-16
A21830 Pre-Commissioning & Commissioning Works Completion 0 29-Feb-16
A21840 First Gas In & Successful Test Run 0 29-Feb-16
A21940 Performance Test 3 29-Feb-16 03-Mar-16
A21950 Reliability Test 30 03-Mar-16 04-Apr-16
A21960 Project Closing 0 04-Apr-16
14234-3.En14234-3.Engineering Engineering 398 18-Aug-14 A 02-Oct-15
14234-3.En14234-3.Engineering.1 Process 341 18-Aug-14 A 19-Apr-15 A
A21350 Process Design Completion 0 19-Apr-15 A
14234-3.E14234-3.Engineering.1.1 Documents and Reports 341 18-Aug-14 A 19-Apr-15 A
14234-3.E14234-3.Engineering.1.2 Drawings 326 27-Aug-14 A 25-Mar-15 A
14234-3.En14234-3.Engineering.2 Mechanical Static 377 21-Aug-14 A 15-Apr-15 A
A21360 Mechanical Static Design Completion 0 15-Apr-15 A
14234-3.E14234-3.Engineering.2.2 Design Calculation Book 286 17-Sep-14 A 15-Apr-15 A
14234-3.E14234-3.Engineering.2.3 Drawings 367 21-Aug-14 A 09-Apr-15 A
14234-3.E14234-3.Engineering.2.4 Datasheet 295 17-Sep-14 A 09-Apr-15 A
14234-3.E14234-3.Engineering.2.1 Documents 277 11-Sep-14 A 10-Mar-15 A
14234-3.En14234-3.Engineering.4 Piping 366 11-Sep-14 A 04-May-15 A
A21380 Piping Design Start 0 11-Sep-14 A
A21670 Piping Design Completion 0 30-Mar-15 A
14234-3.E14234-3.Engineering.4.3 Skid General Arrangement Drawing 366 02-Oct-14 A 30-Mar-15 A
14234-3.E14234-3.Engineering.4.1 Documents 81 03-Nov-14 A 04-Feb-15 A
14234-3.E14234-3.Engineering.4.2 General Drawings 292 11-Sep-14 A 04-May-15 A
14234-3.En14234-3.Engineering.3 Mechanical Rotating 177 06-Jan-15 A 19-Apr-15 A
A21370 Mechanical Rotating Design Completion 0 19-Apr-15 A
14234-3.E14234-3.Engineering.3.1 Datasheets 177 06-Jan-15 A 19-Apr-15 A
14234-3.En14234-3.Engineering.5 Electrical 202 02-Oct-14 A 02-Oct-15 A
A21390 Electrical System Design Completion 0 14-Apr-15 A
14234-3.E14234-3.Engineering.5.2 Documents 194 02-Oct-14 A 02-Oct-15 A
14234-3.E14234-3.Engineering.5.1 Data Sheets 101 07-Jan-15 A 03-Feb-15 A
14234-3.E14234-3.Engineering.5.3 Drawings 103 26-Jan-15 A 14-Apr-15 A
14234-3.En14234-3.Engineering.6 Instrumentation 314 05-Nov-14 A 09-Jul-15 A
A21400 Instrumentation System Design Completion 0 15-Apr-15 A
14234-3.E14234-3.Engineering.6.2 Documents 186 05-Nov-14 A 09-Jul-15 A
14234-3.E14234-3.Engineering.6.1 Data Sheets 176 07-Jan-15 A 12-May-15 A
14234-3.E14234-3.Engineering.6.30 Layouts & Drawings 183 25-Feb-15 A 22-Apr-15 A
14234-3.En14234-3.Engineering.7 Civil & Structure 360 21-Aug-14 A 12-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
04-Apr-16,
04-Apr-16,
Kick Off Meeting, 05-Aug-14 A
Commencement of Project Work, 05-Aug-14 A
HAZOP
Engineering Completion,
Procurement Completion,
Site Modification
Pre-Commissio
First Gas In &
Performance T
Reliability T
Project Clo
02-Oct-15, 14234-3.Engineering
19-Apr-15 A, 14234-3.Engineering.1 Process
Process Design Completion,
19-Apr-15 A, 14234-3.Engineering.1.1 Documents a
25-Mar-15 A, 14234-3.Engineering.1.2 Drawings
15-Apr-15 A, 14234-3.Engineering.2 Mechanical Stat
Mechanical Static Design Completion,
15-Apr-15 A, 14234-3.Engineering.2.2 Design Calcul
09-Apr-15 A, 14234-3.Engineering.2.3 Drawings
09-Apr-15 A, 14234-3.Engineering.2.4 Datasheet
10-Mar-15 A, 14234-3.Engineering.2.1 Documents
04-May-15 A, 14234-3.Engineering.4 Piping
Piping Design Start, 11-Sep-14 A
Piping Design Completion,
30-Mar-15 A, 14234-3.Engineering.4.3 Skid General Ar
04-Feb-15 A, 14234-3.Engineering.4.1 Documents
04-May-15 A, 14234-3.Engineering.4.2 General Dr
19-Apr-15 A, 14234-3.Engineering.3 Mechanical Rot
Mechanical Rotating Design Completion,
19-Apr-15 A, 14234-3.Engineering.3.1 Datasheets
02-Oct-15 A, 14234-3.Engineerin
Electrical System Design Completion,
02-Oct-15 A, 14234-3.Engineerin
03-Feb-15 A, 14234-3.Engineering.5.1 Data Sheets
14-Apr-15 A, 14234-3.Engineering.5.3 Drawings
09-Jul-15 A, 14234-3.Engineering.6 Instrum
Instrumentation System Design Completion,
09-Jul-15 A, 14234-3.Engineering.6.2 Docu
12-May-15 A, 14234-3.Engineering.6.1 Data Shee
22-Apr-15 A, 14234-3.Engineering.6.30 Layouts & D
12-Aug-15, 14234-3.Engineering.7 Civ
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 1 of 7 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish
A21410 Civil & Structure Design Completion 0 12-Aug-15
14234-3.E14234-3.Engineering.7.2 Drawings 360 21-Aug-14 A 12-Aug-15
14234-3.E14234-3.Engineering.7.1 Document 78 03-Nov-14 A 29-Jan-15 A
14234-3.En14234-3.Engineering.8 HSE 306 20-Aug-14 A 22-Jun-15 A
A21420 HSE Documentation Completion 0 22-Jun-15 A
14234-3.E14234-3.Engineering.8.1 Document 306 20-Aug-14 A 22-Jun-15 A
14234-3.En14234-3.Engineering.9 QAQC 147 20-Aug-14 A 10-Mar-15 A
A21430 QAQC Documentation Completion 0 10-Mar-15 A
14234-3.E14234-3.Engineering.9.1 Document 59 20-Aug-14 A 10-Mar-15 A
14234-3.En14234-3.Engineering.10 Commissioning 244 05-Nov-14 A 21-Sep-15
A21440 Commissioning Documentation Completion 0 21-Sep-15
14234-3.E14234-3.Engineering.10.1 Documents 244 05-Nov-14 A 21-Sep-15
14234-3.En14234-3.Engineering.11 General 194 15-Sep-14 A 25-Mar-15 A
A21450 General Documentation Completion 0 25-Mar-15 A
14234-3.E14234-3.Engineering.11.1 Documents 107 15-Sep-14 A 25-Mar-15 A
14234-3.Pr14234-3.Procourment Procurement 310 19-Oct-14 A 26-Oct-15
A21460 Procurement Completion 0 26-Oct-15
14234-3.Pr14234-3.Procourment.1 Issuance of PO for major buyout Items 216 19-Oct-14 A 22-Jan-15 A
A21570 PO Placed for all Major Items 0 22-Jan-15 A
14234-3.P14234-3.Procourment.1.2 Deethanizer OH Condenser E-401 71 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.3 Condensate Stabilization Column C-3001 7 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.6 Gas/Gas Exchanger E-300A 7 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.7 Gas/Gas Exchanger E-300B 7 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.8 Gas/Liquid Exchanger E-302A 54 19-Oct-14 A 08-Dec-14 A
14234-3.P14234-3.Procourment.1.10 Regeneration Gas Cooler E-303 54 19-Oct-14 A 04-Jan-15 A
14234-3.P14234-3.Procourment.1.11 Water Degassing Boot V-3401 7 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.12 CPI Separator V-3402 7 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.13 On Spec Condensate Storage Tank T-3301 7 21-Jan-15 A 22-Jan-15 A
14234-3.P14234-3.Procourment.1.14 Off Spec Condensate Storage Tank T-3302 7 21-Jan-15 A 22-Jan-15 A
14234-3.P14234-3.Procourment.1.15 Bulk Materials 17 08-Dec-14 A 08-Dec-14 A
14234-3.P14234-3.Procourment.1.9 Gas/Liquid Exchanger E-302B 54 19-Oct-14 A 08-Dec-14 A
14234-3.P14234-3.Procourment.1.1 Chiller E-301 46 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.5 Condensate Reboiler E-3001 7 19-Oct-14 A 19-Oct-14 A
14234-3.P14234-3.Procourment.1.4 Propane Receiver V-706 7 19-Oct-14 A 19-Oct-14 A
14234-3.Pr14234-3.Procourment.2 Receipt of Head & Shell Materials at SPEC Facility 253 19-Oct-14 A 22-Feb-15 A
A21560 Fabrication Material Received @ SPEC Fabrication Facility 0 22-Feb-15 A
14234-3.P14234-3.Procourment.2.1 Chiller E-301 17 19-Oct-14 A 02-Dec-14 A
14234-3.P14234-3.Procourment.2.2 Deethanizer OH Condenser E-401 17 19-Oct-14 A 02-Dec-14 A
14234-3.P14234-3.Procourment.2.3 Condensate Stabilization Column C-3001 17 19-Oct-14 A 02-Dec-14 A
14234-3.P14234-3.Procourment.2.4 Propane Receiver V-706 17 19-Oct-14 A 02-Dec-14 A
14234-3.P14234-3.Procourment.2.5 Condensate Reboiler E-3001 17 19-Oct-14 A 02-Nov-14 A
14234-3.P14234-3.Procourment.2.6 Gas/Gas Exchanger E-300A 40 19-Oct-14 A 02-Dec-14 A
14234-3.P14234-3.Procourment.2.7 Gas/Gas Exchanger E-300B 40 19-Oct-14 A 02-Dec-14 A
14234-3.P14234-3.Procourment.2.8 Gas/Liquid Exchanger E-302A 47 19-Oct-14 A 30-Dec-14 A
14234-3.P14234-3.Procourment.2.9 Gas/Liquid Exchanger E-302B 47 19-Oct-14 A 30-Dec-14 A
14234-3.P14234-3.Procourment.2.10 Regeneration Gas Cooler E-303 47 19-Oct-14 A 05-Jan-15 A
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
Civil & Structure Design Completion,
12-Aug-15, 14234-3.Engineering.7.2 D
29-Jan-15 A, 14234-3.Engineering.7.1 Document
22-Jun-15 A, 14234-3.Engineering.8 HSE
HSE Documentation Completion,
22-Jun-15 A, 14234-3.Engineering.8.1 Docum
10-Mar-15 A, 14234-3.Engineering.9 QAQC
QAQC Documentation Completion,
10-Mar-15 A, 14234-3.Engineering.9.1 Document
21-Sep-15, 14234-3.Engineering.1
Commissioning Documentation Co
21-Sep-15, 14234-3.Engineering.1
25-Mar-15 A, 14234-3.Engineering.11 General
General Documentation Completion,
25-Mar-15 A, 14234-3.Engineering.11.1 Documents
26-Oct-15, 14234-3.Procourm
Procurement Completion,
22-Jan-15 A, 14234-3.Procourment.1 Issuance of PO for majo
PO Placed for all Major Items,
19-Oct-14 A, 14234-3.Procourment.1.2 Deethanizer OH Condenser E-40
19-Oct-14 A, 14234-3.Procourment.1.3 Condensate Stabilization Column
19-Oct-14 A, 14234-3.Procourment.1.6 Gas/Gas Exchanger E-300A
19-Oct-14 A, 14234-3.Procourment.1.7 Gas/Gas Exchanger E-300B
08-Dec-14 A, 14234-3.Procourment.1.8 Gas/Liquid Exchanger E-30
04-Jan-15 A, 14234-3.Procourment.1.10 Regeneration Gas Coo
19-Oct-14 A, 14234-3.Procourment.1.11 Water Degassing Boot V-3401
19-Oct-14 A, 14234-3.Procourment.1.12 CPI Separator V-3402
22-Jan-15 A, 14234-3.Procourment.1.13 On Spec Condensate
22-Jan-15 A, 14234-3.Procourment.1.14 Off Spec Condensate
08-Dec-14 A, 14234-3.Procourment.1.15 Bulk Materials
08-Dec-14 A, 14234-3.Procourment.1.9 Gas/Liquid Exchanger E-30
19-Oct-14 A, 14234-3.Procourment.1.1 Chiller E-301
19-Oct-14 A, 14234-3.Procourment.1.5 Condensate Reboiler E-3001
19-Oct-14 A, 14234-3.Procourment.1.4 Propane Receiver V-706
22-Feb-15 A, 14234-3.Procourment.2 Receipt of Head & S
Fabrication Material Received @ SPEC Fabrication Facility,
02-Dec-14 A, 14234-3.Procourment.2.1 Chiller E-301
02-Dec-14 A, 14234-3.Procourment.2.2 Deethanizer OH Condenser
02-Dec-14 A, 14234-3.Procourment.2.3 Condensate Stabilization Co
02-Dec-14 A, 14234-3.Procourment.2.4 Propane Receiver V-706
02-Nov-14 A, 14234-3.Procourment.2.5 Condensate Reboiler E-3001
02-Dec-14 A, 14234-3.Procourment.2.6 Gas/Gas Exchanger E-300A
02-Dec-14 A, 14234-3.Procourment.2.7 Gas/Gas Exchanger E-300B
30-Dec-14 A, 14234-3.Procourment.2.8 Gas/Liquid Exchanger E
30-Dec-14 A, 14234-3.Procourment.2.9 Gas/Liquid Exchanger E
05-Jan-15 A, 14234-3.Procourment.2.10 Regeneration Gas Coo
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 2 of 7 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish
14234-3.P14234-3.Procourment.2.11 Water Degassing Boot V-3401 21 19-Oct-14 A 07-Dec-14 A
14234-3.P14234-3.Procourment.2.12 CPI Separator V-3402 21 19-Oct-14 A 07-Dec-14 A
14234-3.P14234-3.Procourment.2.13 On Spec Condensate Storage Tank T-3301 49 22-Jan-15 A 22-Feb-15 A
14234-3.P14234-3.Procourment.2.14 Off Spec Condensate Storage Tank T-3302 49 22-Jan-15 A 22-Feb-15 A
14234-3.P14234-3.Procourment.2.15 Bulk Materials 21 08-Dec-14 A 30-Dec-14 A
14234-3.Pr14234-3.Procourment.3 Successful Vessel Hydro Test 22 02-Apr-15 A 16-Aug-15
A21550 Hydrotesting of Vessels Completion 0 16-Aug-15
14234-3.P14234-3.Procourment.3.1 Chiller E-301 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.2 Deethanizer OH Condenser E-401 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.3 Condensate Stabilization Column C-3001 1 03-Apr-15 A 03-Apr-15 A
14234-3.P14234-3.Procourment.3.4 Propane Receiver V-706 1 03-Apr-15 A 03-Apr-15 A
14234-3.P14234-3.Procourment.3.5 Condensate Reboiler E-3001 1 03-Apr-15 A 03-Apr-15 A
14234-3.P14234-3.Procourment.3.6 Gas/Gas Exchanger E-300A 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.7 Gas/Gas Exchanger E-300B 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.8 Gas/Liquid Exchanger E-302A 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.9 Gas/Liquid Exchanger E-302B 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.10 Regeneration Gas Cooler E-303 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.3.11 Water Degassing Boot V-3401 1 02-Apr-15 A 02-Apr-15 A
14234-3.P14234-3.Procourment.3.12 CPI Separator V-3402 1 02-Apr-15 A 02-Apr-15 A
14234-3.Pr14234-3.Procourment.4 Equipment FAT at SPEC Facility 41 16-Aug-15 25-Oct-15
A21540 Equipment FAT Completion 0 25-Oct-15
14234-3.P14234-3.Procourment.4.1 Gas/Gas Exchanger (E-300A/B) Skid 1 10-Sep-15 13-Sep-15
14234-3.P14234-3.Procourment.4.2 Gas Liquid Exchanger (E-302A/B) Skid 1 27-Aug-15 30-Aug-15
14234-3.P14234-3.Procourment.4.3 Regeneration Gas Cooler (E-303) Skid 1 10-Sep-15 13-Sep-15
14234-3.P14234-3.Procourment.4.4 Gas Metering Package 1 25-Oct-15 25-Oct-15
14234-3.P14234-3.Procourment.4.5 NGL Stabilization Package 1 25-Oct-15 25-Oct-15
14234-3.P14234-3.Procourment.4.6 NGL Loading Pump Package 1 30-Aug-15 30-Aug-15
14234-3.P14234-3.Procourment.4.7 Water Degassing Boot & CPI Separator Package 1 16-Aug-15 16-Aug-15
14234-3.P14234-3.Procourment.4.8 ESD/FGS Panel 2 27-Sep-15 28-Sep-15
14234-3.Pr14234-3.Procourment.5 Shipping Readiness of Materials from SPEC Facility 41 17-Aug-15 26-Oct-15
A21530 Shipping Readiness of Materials @ SPEC Facility 0 26-Oct-15
14234-3.P14234-3.Procourment.5.1 Gas/Gas & Gas/Liquid Exchangers Package 2 13-Sep-15 16-Sep-15
14234-3.P14234-3.Procourment.5.2 Gas Metering Package 1 26-Oct-15 26-Oct-15
14234-3.P14234-3.Procourment.5.3 Condensate Stabilization Package 1 26-Oct-15 26-Oct-15
14234-3.P14234-3.Procourment.5.4 Condensate Loading Pump Package 1 31-Aug-15 31-Aug-15
14234-3.P14234-3.Procourment.5.5 Water Degassing Boot & CPI Separator Package 1 17-Aug-15 17-Aug-15
14234-3.P14234-3.Procourment.5.6 ESD/FGS Panel 1 29-Sep-15 29-Sep-15
14234-3.Pr14234-3.Project Constraints Project Constraints 137 09-Jul-15 27-Nov-15
A23989 Project Activities Resumed 0 09-Jul-15
A23990 First Shipment Despatch from HFZ 5 15-Aug-15* 20-Aug-15
A24000 First Shipment Receiving on Site 65 20-Aug-15 27-Oct-15
A24040 Overhaul of Compressors & Generators 80 15-Aug-15* 06-Nov-15
A24050 Procurement of MCC Enclosure & Component 5 15-Jul-15* 20-Jul-15
A24060 Material Deliveries, Assembly, & FAT 65 20-Jul-15 25-Sep-15
A24080 Procurement of Synchornization Controller + Delivery to HFZ 25 15-Aug-15* 10-Sep-15
A24100 Pumps Receiving in HFZ 45 09-Jul-15 24-Aug-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
07-Dec-14 A, 14234-3.Procourment.2.11 Water Degassing Boot V-3
07-Dec-14 A, 14234-3.Procourment.2.12 CPI Separator V-3402
22-Feb-15 A, 14234-3.Procourment.2.13 On Spec Conden
22-Feb-15 A, 14234-3.Procourment.2.14 Off Spec Conden
30-Dec-14 A, 14234-3.Procourment.2.15 Bulk Materials
16-Aug-15, 14234-3.Procourment.3 S
Hydrotesting of Vessels Completion,
16-Aug-15, 14234-3.Procourment.3.1
16-Aug-15, 14234-3.Procourment.3.2
03-Apr-15 A, 14234-3.Procourment.3.3 Condensate S
03-Apr-15 A, 14234-3.Procourment.3.4 Propane Rece
03-Apr-15 A, 14234-3.Procourment.3.5 Condensate R
16-Aug-15, 14234-3.Procourment.3.6
16-Aug-15, 14234-3.Procourment.3.7
16-Aug-15, 14234-3.Procourment.3.8
16-Aug-15, 14234-3.Procourment.3.9
16-Aug-15, 14234-3.Procourment.3.10
02-Apr-15 A, 14234-3.Procourment.3.11 Water Degas
02-Apr-15 A, 14234-3.Procourment.3.12 CPI Separato
25-Oct-15, 14234-3.Procourm
Equipment FAT Completion,
13-Sep-15, 14234-3.Procourment.4
30-Aug-15, 14234-3.Procourment.4.2
13-Sep-15, 14234-3.Procourment.4
25-Oct-15, 14234-3.Procourm
25-Oct-15, 14234-3.Procourm
30-Aug-15, 14234-3.Procourment.4.6
16-Aug-15, 14234-3.Procourment.4.7
28-Sep-15, 14234-3.Procourmen
26-Oct-15, 14234-3.Procourm
Shipping Readiness of Materia
16-Sep-15, 14234-3.Procourment.
26-Oct-15, 14234-3.Procourm
26-Oct-15, 14234-3.Procourm
31-Aug-15, 14234-3.Procourment.5.
17-Aug-15, 14234-3.Procourment.5.5
29-Sep-15, 14234-3.Procourmen
27-Nov-15, 14234-3.Proje
Project Activities Resumed, 09-Jul-15
First Shipment Despatch from HFZ
First Shipment Receiving on S
Overhaul of Compressors &
Procurement of MCC Enclosure & Compo
Material Deliveries, Assembly, & F
Procurement of Synchornization Co
Pumps Receiving in HFZ
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 3 of 7 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish
A24101 Procurement of Commissioning Spare 5 01-Sep-15* 05-Sep-15
A24102 Commissioning Spares Receiving In HFZ 25 05-Sep-15 01-Oct-15
A24150 Procurement of Electrical & Instrumentation Cables 5 30-Jul-15* 04-Aug-15
A24160 Electrical & Instrumentation Cables Ex. Works Readiness & Receiving on Site 92 04-Aug-15 07-Nov-15
A24161 DPR Visit - Hydro for 2nd Lot of Vessels and FAT for 1st lot Skid Packages 14 25-Aug-15* 08-Sep-15
A24162 Punch List Close Out + Shipping Readiness 3 08-Sep-15 11-Sep-15
A24170 2nd Shipment Dispatch from UAE 5 11-Sep-15 16-Sep-15
A24180 2nd Shipment Receiving on Site 50 16-Sep-15 06-Nov-15
A24181 DPR Visit - FAT for 2nd Lot of Skid Packages 13 15-Sep-15* 28-Sep-15
A24182 Punch List Close Out + Shipping Readiness 3 28-Sep-15 01-Oct-15
A24190 3rd Shipment Dispatch from UAE 5 01-Oct-15 07-Oct-15
A24200 3rd Shipment Receiving on Site 50 07-Oct-15 27-Nov-15
14234-3.Co14234-3.Construction Site Modification, Construction & Erection W 222 21-Jan-15 A 24-Feb-16
A21880 Site Modification, Construction & Erection Completion 0 24-Feb-16
14234-3.C14234-3.Construction.2 Site Construction & Erection Works 222 21-Jan-15 A 24-Feb-16
A21510 Site Construction & Erection Works Completion 0 24-Feb-16
14234-3.C14234-3.Construction.2.1 Foundation for Gas Metering Package 56 12-Aug-15 09-Oct-15
14234-3.C14234-3.Construction.2.2 Foundation for Water Degassing Boot & CPI Separator Sk 56 12-Aug-15 09-Oct-15
14234-3.C14234-3.Construction.2.3 Foundation for NGL Storage Tank T-3101 56 21-Jan-15 A 05-Sep-15
14234-3.C14234-3.Construction.2.4 Foundation for Condensate Stabilization Skid 56 12-Aug-15 09-Oct-15
14234-3.C14234-3.Construction.2.5 Foundation for Condensate Transfer Pump Skid 56 12-Aug-15 09-Oct-15
14234-3.C14234-3.Construction.2.6 Foundation for Gas/Gas Exchanger (E-300A/B) Skid 42 21-Sep-15 03-Nov-15
14234-3.C14234-3.Construction.2.7 Foundation for Gas Liquid Exchanger (E-302(A/B Skid 56 12-Aug-15 09-Oct-15
14234-3.C14234-3.Construction.2.8 Foundation for Regeneration Gas Cooler (E-303) Skid 42 21-Sep-15 04-Nov-15
14234-3.C14234-3.Construction.2.9 Foundation for Lighting Poles 56 12-Aug-15 09-Oct-15
14234-3.C14234-3.Construction.2.26 Erection of Gas Metering Skid 5 14-Nov-15 20-Nov-15
14234-3.C14234-3.Construction.2.10 Foundation for NGL Storage Tank T-3102 56 09-Jul-15 05-Sep-15
14234-3.C14234-3.Construction.2.28 Erection of NGL Storage Tank T-3101 126 09-Jul-15 16-Nov-15
14234-3.C14234-3.Construction.2.27 Erection of NGL Storage Tank T-3102 126 09-Jul-15 16-Nov-15
14234-3.C14234-3.Construction.2.11 Erection of Water Degassing Boot & CPI Separator Skid 7 14-Nov-15 23-Nov-15
14234-3.C14234-3.Construction.2.12 Erection of Condensate Stabilization Skid 14 27-Nov-15 11-Dec-15
14234-3.C14234-3.Construction.2.13 Erection of NGL Transfer Pump Skid 7 27-Nov-15 04-Dec-15
14234-3.C14234-3.Construction.2.14 Erection of Gas/Gas Exchanger (E-300A/B) Skid 7 09-Dec-15 17-Dec-15
14234-3.C14234-3.Construction.2.15 Erection of Gas Liquid Exchanger (E-302(A/B Skid 7 27-Nov-15 04-Dec-15
14234-3.C14234-3.Construction.2.16 Erection of Regeneration Gas Cooler (E-303) Skid 7 10-Dec-15 17-Dec-15
14234-3.C14234-3.Construction.2.17 Erection of Lighting Poles 7 14-Nov-15 23-Nov-15
14234-3.C14234-3.Construction.2.18 Cable Pulling - Instrument Cables 21 07-Nov-15 28-Nov-15
14234-3.C14234-3.Construction.2.19 Cable Pulling - Electrical Cables 21 07-Nov-15 28-Nov-15
14234-3.C14234-3.Construction.2.20 Electrical Cables Termination in MCC 14 19-Jan-16 02-Feb-16
14234-3.C14234-3.Construction.2.21 Erection of ESD/FGS Panel 7 27-Nov-15 04-Dec-15
14234-3.C14234-3.Construction.2.22 Instruments Cable Termination in DCS Panel 14 04-Dec-15 19-Dec-15
14234-3.C14234-3.Construction.2.23 Instruments Cable Termination in ESD/FGS Panel 14 07-Nov-15 21-Nov-15
14234-3.C14234-3.Construction.2.24 Interconnecting Cables - DCS to ESD/FGS Panel 14 19-Dec-15 02-Jan-16
14234-3.C14234-3.Construction.2.25 Interconnecting Piping Works 64 19-Dec-15 24-Feb-16
14234-3.C14234-3.Construction.1 Site Modification Works 103 04-Sep-15 19-Dec-15
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
Procurement of Commissioning Spa
Commissioning Spares Receiving
Procurement of Electrical & Instrumenta
Electrical & Instrumentation C
DPR Visit - Hydro for 2nd Lot of Ves
Punch List Close Out + Shipping Re
2nd Shipment Dispatch from UAE
2nd Shipment Receiving on S
DPR Visit - FAT for 2nd Lot of Ski
Punch List Close Out + Shipping
3rd Shipment Dispatch from UAE
3rd Shipment Receiving on
24-Feb-16, 142
Site Modification
24-Feb-16, 142
Site Constructio
09-Oct-15, 14234-3.Constructio
09-Oct-15, 14234-3.Constructio
05-Sep-15, 14234-3.Construction.2
09-Oct-15, 14234-3.Constructio
09-Oct-15, 14234-3.Constructio
03-Nov-15, 14234-3.Constru
09-Oct-15, 14234-3.Constructio
04-Nov-15, 14234-3.Constru
09-Oct-15, 14234-3.Constructio
20-Nov-15, 14234-3.Const
05-Sep-15, 14234-3.Construction.2
16-Nov-15, 14234-3.Constr
16-Nov-15, 14234-3.Constr
23-Nov-15, 14234-3.Cons
11-Dec-15, 14234-3.Con
04-Dec-15, 14234-3.Con
17-Dec-15, 14234-3.Co
04-Dec-15, 14234-3.Con
17-Dec-15, 14234-3.Co
23-Nov-15, 14234-3.Cons
28-Nov-15, 14234-3.Cons
28-Nov-15, 14234-3.Cons
02-Feb-16, 14234
04-Dec-15, 14234-3.Con
19-Dec-15, 14234-3.Co
21-Nov-15, 14234-3.Const
02-Jan-16, 14234-3.C
24-Feb-16, 142
19-Dec-15, 14234-3.Co
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 4 of 7 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish
A21520 Site Modification Works Completion 0 19-Dec-15
14234-3.C14234-3.Construction.1.1 Three Phase Separator Package 18 27-Nov-15 16-Dec-15
14234-3.C14234-3.Construction.1.14 Heat Medium Expansion Tank/Pumps Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.19 LPG Bullets Control Station Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.26 LPG Loading Arm Skid 18 27-Nov-15 16-Dec-15
14234-3.C14234-3.Construction.1.27 Distributed Control System (DCS) 35 27-Oct-15 02-Dec-15
14234-3.C14234-3.Construction.1.28 Power Generators 19 06-Nov-15 25-Nov-15
14234-3.C14234-3.Construction.1.29 LV Switchgear & MCC 15 27-Nov-15 12-Dec-15
14234-3.C14234-3.Construction.1.23 Heat Medium Heater Skid 12Mmbtu 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.24 Flare KO Drum Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.25 Propane Loading Arm Skid 18 27-Nov-15 16-Dec-15
14234-3.C14234-3.Construction.1.15 Fuel Gas Conditioning Skid 25 27-Oct-15 21-Nov-15
14234-3.C14234-3.Construction.1.16 Instrument Air Package 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.17 Depropanizer Reboiler Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.18 Debutanizer Reboiler Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.30 Synchronization Panel 15 07-Nov-15 23-Nov-15
14234-3.C14234-3.Construction.1.13 Deethanizer Reboiler Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.3 Inlet Compressor Package - A 26 06-Nov-15 03-Dec-15
14234-3.C14234-3.Construction.1.5 Inlet Compressor Package - C 26 06-Nov-15 03-Dec-15
14234-3.C14234-3.Construction.1.7 Regeneration Heater Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.8 Deethanizer Reflux Accumulator Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.9 Depropanizer Reflux Accumulator Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.10 Debutanizer Reflux Accumulator Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.11 Condensate Flash Tank Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.12 Cold & LP Separator Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.20 Propane Bullets Control Staion Skid 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.21 LPG Loading Pumps Skid 18 27-Nov-15 16-Dec-15
14234-3.C14234-3.Construction.1.22 Heat Medium Heater Skid 6Mmbtu 26 27-Oct-15 23-Nov-15
14234-3.C14234-3.Construction.1.4 Inlet Compressor Package - B 26 06-Nov-15 03-Dec-15
14234-3.C14234-3.Construction.1.6 Molecular Sieve Filters Package 26 20-Oct-15 16-Nov-15
14234-3.C14234-3.Construction.1.2 Booster Compressor Package 42 06-Nov-15 19-Dec-15
14234-3.C14234-3.Construction.1.31 UPS System 67 04-Sep-15 12-Nov-15
14234-3.Co14234-3.Commissioning Precommissioning & Commissioning Wo 105 12-Nov-15 29-Feb-16
A21480 Precommissioning & Commissioning Completion 0 29-Feb-16
14234-3.C14234-3.Commissioning.1 Pre-Commissioning Works 57 12-Nov-15 09-Jan-16
A21500 Pre-Commissioning Completion 0 09-Jan-16
14234-3.C14234-3.Commissioning.1.1 Three Phase Separator Package 7 11-Dec-15 18-Dec-15
14234-3.C14234-3.Commissioning.1.2 Booster Compressor Package 7 19-Dec-15 26-Dec-15
14234-3.C14234-3.Commissioning.1.3 Inlet Compressor Package - A 7 03-Dec-15 10-Dec-15
14234-3.C14234-3.Commissioning.1.4 Inlet Compressor Package - B 7 03-Dec-15 10-Dec-15
14234-3.C14234-3.Commissioning.1.5 Inlet Compressor Package - C 7 03-Dec-15 10-Dec-15
14234-3.C14234-3.Commissioning.1.6 Molecular Sieve Filters Package 7 19-Dec-15 26-Dec-15
14234-3.C14234-3.Commissioning.1.7 Regeneration Heater Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.8 Deethanizer Reflux Accumulator Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.9 Depropanizer Reflux Accumulator Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.10 Debutanizer Reflux Accumulator Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.11 Condensate Flash Tank Skid 7 02-Jan-16 09-Jan-16
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
Site Modification Works
16-Dec-15, 14234-3.Co
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
16-Dec-15, 14234-3.Co
02-Dec-15, 14234-3.Cons
25-Nov-15, 14234-3.Cons
12-Dec-15, 14234-3.Con
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
16-Dec-15, 14234-3.Co
21-Nov-15, 14234-3.Const
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
03-Dec-15, 14234-3.Cons
03-Dec-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
23-Nov-15, 14234-3.Cons
16-Dec-15, 14234-3.Co
23-Nov-15, 14234-3.Cons
03-Dec-15, 14234-3.Cons
16-Nov-15, 14234-3.Constr
19-Dec-15, 14234-3.Co
12-Nov-15, 14234-3.Constr
29-Feb-16, 142
Precommission
09-Jan-16, 14234-3.C
Pre-Commissioning C
18-Dec-15, 14234-3.Co
26-Dec-15, 14234-3.C
10-Dec-15, 14234-3.Com
10-Dec-15, 14234-3.Com
10-Dec-15, 14234-3.Com
26-Dec-15, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 5 of 7 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish
14234-3.C14234-3.Commissioning.1.12 Cold & LP Separator Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.13 Deethanizer Reboiler Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.14 Heat Medium Expansion Tank/Pumps Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.15 Fuel Gas Conditioning Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.16 Instrument Air Package 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.17 Depropanizer Reboiler Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.18 Debutanizer Reboiler Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.19 LPG Bullets Control Station Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.20 Propane Bullets Control Staion Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.21 LPG Loading Pumps Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.22 Heat Medium Heater Skid 6Mmbtu 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.23 Heat Medium Heater Skid 12Mmbtu 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.24 Flare KO Drum Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.25 Propane Loading Arm Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.26 LPG Loading Arm Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.27 Gas Metering Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.28 Water Degassing Boot & CPI Separator Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.29 Condensate Stabilization Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.30 Condensate Transfer Pump Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.31 Gas/Gas Exchanger (E-300A/B) Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.36 Distributed Control System (DCS) 7 19-Dec-15 26-Dec-15
14234-3.C14234-3.Commissioning.1.37 Synchronization Panel 7 23-Nov-15 30-Nov-15
14234-3.C14234-3.Commissioning.1.32 Gas Liquid Exchanger (E-302(A/B Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.33 Regeneration Gas Cooler (E-303) Skid 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.34 F&G System 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.35 ESD/FGS System 7 02-Jan-16 09-Jan-16
14234-3.C14234-3.Commissioning.1.38 LV Switchgear & MCC 7 12-Dec-15 21-Dec-15
14234-3.C14234-3.Commissioning.1.39 UPS System 7 12-Nov-15 19-Nov-15
14234-3.C14234-3.Commissioning.1.40 Power Generators 7 26-Nov-15 03-Dec-15
14234-3.C14234-3.Commissioning.2 Commissioning Works 48 09-Jan-16 29-Feb-16
A21490 Commissioning Completion 0 29-Feb-16
14234-3.C14234-3.Commissioning.2.1 Three Phase Separator Package 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.2 Booster Compressor Package 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.3 Inlet Compressor Package - A 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.4 Inlet Compressor Package - B 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.5 Inlet Compressor Package - C 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.6 Molecular Sieve Filters Package 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.7 Regeneration Heater Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.8 Deethanizer Reflux Accumulator Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.9 Depropanizer Reflux Accumulator Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.10 Debutanizer Reflux Accumulator Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.11 Condensate Flash Tank Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.12 Cold & LP Separator Skid 5 09-Jan-16 15-Jan-16
14234-3.C14234-3.Commissioning.2.13 Deethanizer Reboiler Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.14 Heat Medium Expansion Tank/Pumps Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.15 Fuel Gas Conditioning Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.16 Instrument Air Package 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.17 Depropanizer Reboiler Skid 5 24-Feb-16 29-Feb-16
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
26-Dec-15, 14234-3.C
30-Nov-15, 14234-3.Com
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
09-Jan-16, 14234-3.C
21-Dec-15, 14234-3.Co
19-Nov-15, 14234-3.Comm
03-Dec-15, 14234-3.Com
29-Feb-16, 142
Commissioning
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
15-Jan-16, 14234-3
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 6 of 7 TASK filter: All Activities
© Oracle Corporation
Activity ID Activity Name Original
Duration
Start Finish
14234-3.C14234-3.Commissioning.2.18 Debutanizer Reboiler Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.19 LPG Bullets Control Station Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.20 Propane Bullets Control Staion Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.21 LPG Loading Pumps Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.22 Heat Medium Heater Skid 6Mmbtu 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.23 Heat Medium Heater Skid 12Mmbtu 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.24 Flare KO Drum Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.25 Propane Loading Arm Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.26 LPG Loading Arm Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.27 Gas Metering Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.28 Water Degassing Boot & CPI Separator Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.29 Condensate Stabilization Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.30 Condensate Transfer Pump Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.31 Gas/Gas Exchanger (E-300A/B) Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.32 Gas Liquid Exchanger (E-302(A/B Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.33 Regeneration Gas Cooler (E-303) Skid 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.34 F&G System 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.35 ESD/FGS System 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.36 Distributed Control System (DCS) 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.37 Synchronization Panel 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.38 LV Switchgear & MCC 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.39 Power Generators 5 24-Feb-16 29-Feb-16
14234-3.C14234-3.Commissioning.2.40 UPS System 5 24-Feb-16 29-Feb-16
14234-3.Pe14234-3.Perf & Rel Test Performance and Reliability Test 33 29-Feb-16 04-Apr-16
14234-3.Pe14234-3.Perf & Rel Test.Perf Test Performance Test 3 29-Feb-16 03-Mar-16
A24210 Performance Test 3 29-Feb-16 03-Mar-16
14234-3.Pe14234-3.Perf & Rel Test.Rel. Test Reliability Test 30 03-Mar-16 04-Apr-16
A24220 Reliability Test 30 03-Mar-16 04-Apr-16
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
2014 2015 2016
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
29-Feb-16, 142
04-Apr-16,
03-Mar-16, 142
Performance T
04-Apr-16,
Reliability T
Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaini...
Page 7 of 7 TASK filter: All Activities
© Oracle Corporation

Weitere ähnliche Inhalte

Was ist angesagt?

Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoignitetribes
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoignitetribes
 
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01Philippe Porta
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendationsubk1411
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement ignitetribes
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technipignitetribes
 
Piping Design Course in Hyderabad
Piping Design Course in HyderabadPiping Design Course in Hyderabad
Piping Design Course in HyderabadSanjary Edu
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draftignitetribes
 
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)MAHESH PANDIT
 
Study 2: Front-End Engineering Design and Project Definition
Study 2: Front-End Engineering Design and Project DefinitionStudy 2: Front-End Engineering Design and Project Definition
Study 2: Front-End Engineering Design and Project DefinitionGerard B. Hawkins
 
AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdfMy own
 
Gas Liquid Engineering - Presentation Brazil
Gas Liquid Engineering - Presentation BrazilGas Liquid Engineering - Presentation Brazil
Gas Liquid Engineering - Presentation BrazilSistema FIEB
 

Was ist angesagt? (20)

Pid.pdf
Pid.pdfPid.pdf
Pid.pdf
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
Oil and-gas-facilities-and-pipelines-110906055120-phpapp01
 
Epc issues and recommendations
Epc issues and recommendationsEpc issues and recommendations
Epc issues and recommendations
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technip
 
Piping Design Course in Hyderabad
Piping Design Course in HyderabadPiping Design Course in Hyderabad
Piping Design Course in Hyderabad
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
6 71-0051 rev. 4 standard specification for pipeline construction (onshore)
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Planning For Engineering
Planning For EngineeringPlanning For Engineering
Planning For Engineering
 
Study 2: Front-End Engineering Design and Project Definition
Study 2: Front-End Engineering Design and Project DefinitionStudy 2: Front-End Engineering Design and Project Definition
Study 2: Front-End Engineering Design and Project Definition
 
EPC Business Model
EPC Business ModelEPC Business Model
EPC Business Model
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdf
 
Basic engineering_Checklist
Basic engineering_ChecklistBasic engineering_Checklist
Basic engineering_Checklist
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Piping basics knowledge
Piping basics knowledgePiping basics knowledge
Piping basics knowledge
 
Gas Liquid Engineering - Presentation Brazil
Gas Liquid Engineering - Presentation BrazilGas Liquid Engineering - Presentation Brazil
Gas Liquid Engineering - Presentation Brazil
 

Ähnlich wie Project Schedule - Level IV Schedule

Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nixzalis Bourdier
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityRoumik Mukherjee
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...yang lu
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0Ahmed Khaled
 
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Arun Bharadwaj
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfAhmed Mehrem
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Ahmed Mehrem
 
GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015William Irving
 
Equipment Arrival Status.pptx
Equipment Arrival Status.pptxEquipment Arrival Status.pptx
Equipment Arrival Status.pptxMehmanNasibov1
 
C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)Baig Ali
 
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalSeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalAhmed Mehrem
 

Ähnlich wie Project Schedule - Level IV Schedule (20)

01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-Nbourdier-lab2-gantt chart with activities-
Nbourdier-lab2-gantt chart with activities-
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
 
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...-The PERT Chart-The tendering time schedule for Adar Produced  Water Re-injec...
-The PERT Chart-The tendering time schedule for Adar Produced Water Re-injec...
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
ADIB Time Schedule V4.0
ADIB Time Schedule V4.0ADIB Time Schedule V4.0
ADIB Time Schedule V4.0
 
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
 
ERUP WBS
ERUP WBSERUP WBS
ERUP WBS
 
Cash Flow Portfolio
Cash Flow PortfolioCash Flow Portfolio
Cash Flow Portfolio
 
Zewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdfZewail B4 Base Line Schedule All Buildings.pdf
Zewail B4 Base Line Schedule All Buildings.pdf
 
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
Zewail b4 base line schedule all buildings (detailed) completion 17 nov 2016
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015GWOS_Week_of_03-23-2015
GWOS_Week_of_03-23-2015
 
WORKING PORTFOLIO - 01
WORKING PORTFOLIO - 01WORKING PORTFOLIO - 01
WORKING PORTFOLIO - 01
 
Equipment Arrival Status.pptx
Equipment Arrival Status.pptxEquipment Arrival Status.pptx
Equipment Arrival Status.pptx
 
Leyet Colleges Schedule
Leyet Colleges ScheduleLeyet Colleges Schedule
Leyet Colleges Schedule
 
C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)C&ess presentation drm (30.10.13)
C&ess presentation drm (30.10.13)
 
IHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdfIHH Healthcare Tender Programme.pdf
IHH Healthcare Tender Programme.pdf
 
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalSeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
 

Project Schedule - Level IV Schedule

  • 1. Activity ID Activity Name Original Duration Start Finish 14234-3 Eg14234-3 Egbaoma Gas Processing Plant - New 586 05-Aug-14 A 04-Apr-16 14234-3.Co14234-3.Contract About Contract 459 05-Aug-14 A 04-Apr-16 A21270 Kick Off Meeting 0 05-Aug-14 A A21280 Commencement of Project Work 0 05-Aug-14 A A21790 HAZOP 8 17-Dec-14 A 24-Dec-14 A A21800 Engineering Completion 0 21-Sep-15 A21810 Procurement Completion 0 26-Oct-15 A21820 Site Modification, Construction & Erection Works Completion 0 24-Feb-16 A21830 Pre-Commissioning & Commissioning Works Completion 0 29-Feb-16 A21840 First Gas In & Successful Test Run 0 29-Feb-16 A21940 Performance Test 3 29-Feb-16 03-Mar-16 A21950 Reliability Test 30 03-Mar-16 04-Apr-16 A21960 Project Closing 0 04-Apr-16 14234-3.En14234-3.Engineering Engineering 398 18-Aug-14 A 02-Oct-15 14234-3.En14234-3.Engineering.1 Process 341 18-Aug-14 A 19-Apr-15 A A21350 Process Design Completion 0 19-Apr-15 A 14234-3.E14234-3.Engineering.1.1 Documents and Reports 341 18-Aug-14 A 19-Apr-15 A 14234-3.E14234-3.Engineering.1.2 Drawings 326 27-Aug-14 A 25-Mar-15 A 14234-3.En14234-3.Engineering.2 Mechanical Static 377 21-Aug-14 A 15-Apr-15 A A21360 Mechanical Static Design Completion 0 15-Apr-15 A 14234-3.E14234-3.Engineering.2.2 Design Calculation Book 286 17-Sep-14 A 15-Apr-15 A 14234-3.E14234-3.Engineering.2.3 Drawings 367 21-Aug-14 A 09-Apr-15 A 14234-3.E14234-3.Engineering.2.4 Datasheet 295 17-Sep-14 A 09-Apr-15 A 14234-3.E14234-3.Engineering.2.1 Documents 277 11-Sep-14 A 10-Mar-15 A 14234-3.En14234-3.Engineering.4 Piping 366 11-Sep-14 A 04-May-15 A A21380 Piping Design Start 0 11-Sep-14 A A21670 Piping Design Completion 0 30-Mar-15 A 14234-3.E14234-3.Engineering.4.3 Skid General Arrangement Drawing 366 02-Oct-14 A 30-Mar-15 A 14234-3.E14234-3.Engineering.4.1 Documents 81 03-Nov-14 A 04-Feb-15 A 14234-3.E14234-3.Engineering.4.2 General Drawings 292 11-Sep-14 A 04-May-15 A 14234-3.En14234-3.Engineering.3 Mechanical Rotating 177 06-Jan-15 A 19-Apr-15 A A21370 Mechanical Rotating Design Completion 0 19-Apr-15 A 14234-3.E14234-3.Engineering.3.1 Datasheets 177 06-Jan-15 A 19-Apr-15 A 14234-3.En14234-3.Engineering.5 Electrical 202 02-Oct-14 A 02-Oct-15 A A21390 Electrical System Design Completion 0 14-Apr-15 A 14234-3.E14234-3.Engineering.5.2 Documents 194 02-Oct-14 A 02-Oct-15 A 14234-3.E14234-3.Engineering.5.1 Data Sheets 101 07-Jan-15 A 03-Feb-15 A 14234-3.E14234-3.Engineering.5.3 Drawings 103 26-Jan-15 A 14-Apr-15 A 14234-3.En14234-3.Engineering.6 Instrumentation 314 05-Nov-14 A 09-Jul-15 A A21400 Instrumentation System Design Completion 0 15-Apr-15 A 14234-3.E14234-3.Engineering.6.2 Documents 186 05-Nov-14 A 09-Jul-15 A 14234-3.E14234-3.Engineering.6.1 Data Sheets 176 07-Jan-15 A 12-May-15 A 14234-3.E14234-3.Engineering.6.30 Layouts & Drawings 183 25-Feb-15 A 22-Apr-15 A 14234-3.En14234-3.Engineering.7 Civil & Structure 360 21-Aug-14 A 12-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2014 2015 2016 04-Apr-16, 04-Apr-16, Kick Off Meeting, 05-Aug-14 A Commencement of Project Work, 05-Aug-14 A HAZOP Engineering Completion, Procurement Completion, Site Modification Pre-Commissio First Gas In & Performance T Reliability T Project Clo 02-Oct-15, 14234-3.Engineering 19-Apr-15 A, 14234-3.Engineering.1 Process Process Design Completion, 19-Apr-15 A, 14234-3.Engineering.1.1 Documents a 25-Mar-15 A, 14234-3.Engineering.1.2 Drawings 15-Apr-15 A, 14234-3.Engineering.2 Mechanical Stat Mechanical Static Design Completion, 15-Apr-15 A, 14234-3.Engineering.2.2 Design Calcul 09-Apr-15 A, 14234-3.Engineering.2.3 Drawings 09-Apr-15 A, 14234-3.Engineering.2.4 Datasheet 10-Mar-15 A, 14234-3.Engineering.2.1 Documents 04-May-15 A, 14234-3.Engineering.4 Piping Piping Design Start, 11-Sep-14 A Piping Design Completion, 30-Mar-15 A, 14234-3.Engineering.4.3 Skid General Ar 04-Feb-15 A, 14234-3.Engineering.4.1 Documents 04-May-15 A, 14234-3.Engineering.4.2 General Dr 19-Apr-15 A, 14234-3.Engineering.3 Mechanical Rot Mechanical Rotating Design Completion, 19-Apr-15 A, 14234-3.Engineering.3.1 Datasheets 02-Oct-15 A, 14234-3.Engineerin Electrical System Design Completion, 02-Oct-15 A, 14234-3.Engineerin 03-Feb-15 A, 14234-3.Engineering.5.1 Data Sheets 14-Apr-15 A, 14234-3.Engineering.5.3 Drawings 09-Jul-15 A, 14234-3.Engineering.6 Instrum Instrumentation System Design Completion, 09-Jul-15 A, 14234-3.Engineering.6.2 Docu 12-May-15 A, 14234-3.Engineering.6.1 Data Shee 22-Apr-15 A, 14234-3.Engineering.6.30 Layouts & D 12-Aug-15, 14234-3.Engineering.7 Civ Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25 Actual Level of Effort Actual Work Remaining Work Critical Remaini... Page 1 of 7 TASK filter: All Activities © Oracle Corporation
  • 2. Activity ID Activity Name Original Duration Start Finish A21410 Civil & Structure Design Completion 0 12-Aug-15 14234-3.E14234-3.Engineering.7.2 Drawings 360 21-Aug-14 A 12-Aug-15 14234-3.E14234-3.Engineering.7.1 Document 78 03-Nov-14 A 29-Jan-15 A 14234-3.En14234-3.Engineering.8 HSE 306 20-Aug-14 A 22-Jun-15 A A21420 HSE Documentation Completion 0 22-Jun-15 A 14234-3.E14234-3.Engineering.8.1 Document 306 20-Aug-14 A 22-Jun-15 A 14234-3.En14234-3.Engineering.9 QAQC 147 20-Aug-14 A 10-Mar-15 A A21430 QAQC Documentation Completion 0 10-Mar-15 A 14234-3.E14234-3.Engineering.9.1 Document 59 20-Aug-14 A 10-Mar-15 A 14234-3.En14234-3.Engineering.10 Commissioning 244 05-Nov-14 A 21-Sep-15 A21440 Commissioning Documentation Completion 0 21-Sep-15 14234-3.E14234-3.Engineering.10.1 Documents 244 05-Nov-14 A 21-Sep-15 14234-3.En14234-3.Engineering.11 General 194 15-Sep-14 A 25-Mar-15 A A21450 General Documentation Completion 0 25-Mar-15 A 14234-3.E14234-3.Engineering.11.1 Documents 107 15-Sep-14 A 25-Mar-15 A 14234-3.Pr14234-3.Procourment Procurement 310 19-Oct-14 A 26-Oct-15 A21460 Procurement Completion 0 26-Oct-15 14234-3.Pr14234-3.Procourment.1 Issuance of PO for major buyout Items 216 19-Oct-14 A 22-Jan-15 A A21570 PO Placed for all Major Items 0 22-Jan-15 A 14234-3.P14234-3.Procourment.1.2 Deethanizer OH Condenser E-401 71 19-Oct-14 A 19-Oct-14 A 14234-3.P14234-3.Procourment.1.3 Condensate Stabilization Column C-3001 7 19-Oct-14 A 19-Oct-14 A 14234-3.P14234-3.Procourment.1.6 Gas/Gas Exchanger E-300A 7 19-Oct-14 A 19-Oct-14 A 14234-3.P14234-3.Procourment.1.7 Gas/Gas Exchanger E-300B 7 19-Oct-14 A 19-Oct-14 A 14234-3.P14234-3.Procourment.1.8 Gas/Liquid Exchanger E-302A 54 19-Oct-14 A 08-Dec-14 A 14234-3.P14234-3.Procourment.1.10 Regeneration Gas Cooler E-303 54 19-Oct-14 A 04-Jan-15 A 14234-3.P14234-3.Procourment.1.11 Water Degassing Boot V-3401 7 19-Oct-14 A 19-Oct-14 A 14234-3.P14234-3.Procourment.1.12 CPI Separator V-3402 7 19-Oct-14 A 19-Oct-14 A 14234-3.P14234-3.Procourment.1.13 On Spec Condensate Storage Tank T-3301 7 21-Jan-15 A 22-Jan-15 A 14234-3.P14234-3.Procourment.1.14 Off Spec Condensate Storage Tank T-3302 7 21-Jan-15 A 22-Jan-15 A 14234-3.P14234-3.Procourment.1.15 Bulk Materials 17 08-Dec-14 A 08-Dec-14 A 14234-3.P14234-3.Procourment.1.9 Gas/Liquid Exchanger E-302B 54 19-Oct-14 A 08-Dec-14 A 14234-3.P14234-3.Procourment.1.1 Chiller E-301 46 19-Oct-14 A 19-Oct-14 A 14234-3.P14234-3.Procourment.1.5 Condensate Reboiler E-3001 7 19-Oct-14 A 19-Oct-14 A 14234-3.P14234-3.Procourment.1.4 Propane Receiver V-706 7 19-Oct-14 A 19-Oct-14 A 14234-3.Pr14234-3.Procourment.2 Receipt of Head & Shell Materials at SPEC Facility 253 19-Oct-14 A 22-Feb-15 A A21560 Fabrication Material Received @ SPEC Fabrication Facility 0 22-Feb-15 A 14234-3.P14234-3.Procourment.2.1 Chiller E-301 17 19-Oct-14 A 02-Dec-14 A 14234-3.P14234-3.Procourment.2.2 Deethanizer OH Condenser E-401 17 19-Oct-14 A 02-Dec-14 A 14234-3.P14234-3.Procourment.2.3 Condensate Stabilization Column C-3001 17 19-Oct-14 A 02-Dec-14 A 14234-3.P14234-3.Procourment.2.4 Propane Receiver V-706 17 19-Oct-14 A 02-Dec-14 A 14234-3.P14234-3.Procourment.2.5 Condensate Reboiler E-3001 17 19-Oct-14 A 02-Nov-14 A 14234-3.P14234-3.Procourment.2.6 Gas/Gas Exchanger E-300A 40 19-Oct-14 A 02-Dec-14 A 14234-3.P14234-3.Procourment.2.7 Gas/Gas Exchanger E-300B 40 19-Oct-14 A 02-Dec-14 A 14234-3.P14234-3.Procourment.2.8 Gas/Liquid Exchanger E-302A 47 19-Oct-14 A 30-Dec-14 A 14234-3.P14234-3.Procourment.2.9 Gas/Liquid Exchanger E-302B 47 19-Oct-14 A 30-Dec-14 A 14234-3.P14234-3.Procourment.2.10 Regeneration Gas Cooler E-303 47 19-Oct-14 A 05-Jan-15 A Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2014 2015 2016 Civil & Structure Design Completion, 12-Aug-15, 14234-3.Engineering.7.2 D 29-Jan-15 A, 14234-3.Engineering.7.1 Document 22-Jun-15 A, 14234-3.Engineering.8 HSE HSE Documentation Completion, 22-Jun-15 A, 14234-3.Engineering.8.1 Docum 10-Mar-15 A, 14234-3.Engineering.9 QAQC QAQC Documentation Completion, 10-Mar-15 A, 14234-3.Engineering.9.1 Document 21-Sep-15, 14234-3.Engineering.1 Commissioning Documentation Co 21-Sep-15, 14234-3.Engineering.1 25-Mar-15 A, 14234-3.Engineering.11 General General Documentation Completion, 25-Mar-15 A, 14234-3.Engineering.11.1 Documents 26-Oct-15, 14234-3.Procourm Procurement Completion, 22-Jan-15 A, 14234-3.Procourment.1 Issuance of PO for majo PO Placed for all Major Items, 19-Oct-14 A, 14234-3.Procourment.1.2 Deethanizer OH Condenser E-40 19-Oct-14 A, 14234-3.Procourment.1.3 Condensate Stabilization Column 19-Oct-14 A, 14234-3.Procourment.1.6 Gas/Gas Exchanger E-300A 19-Oct-14 A, 14234-3.Procourment.1.7 Gas/Gas Exchanger E-300B 08-Dec-14 A, 14234-3.Procourment.1.8 Gas/Liquid Exchanger E-30 04-Jan-15 A, 14234-3.Procourment.1.10 Regeneration Gas Coo 19-Oct-14 A, 14234-3.Procourment.1.11 Water Degassing Boot V-3401 19-Oct-14 A, 14234-3.Procourment.1.12 CPI Separator V-3402 22-Jan-15 A, 14234-3.Procourment.1.13 On Spec Condensate 22-Jan-15 A, 14234-3.Procourment.1.14 Off Spec Condensate 08-Dec-14 A, 14234-3.Procourment.1.15 Bulk Materials 08-Dec-14 A, 14234-3.Procourment.1.9 Gas/Liquid Exchanger E-30 19-Oct-14 A, 14234-3.Procourment.1.1 Chiller E-301 19-Oct-14 A, 14234-3.Procourment.1.5 Condensate Reboiler E-3001 19-Oct-14 A, 14234-3.Procourment.1.4 Propane Receiver V-706 22-Feb-15 A, 14234-3.Procourment.2 Receipt of Head & S Fabrication Material Received @ SPEC Fabrication Facility, 02-Dec-14 A, 14234-3.Procourment.2.1 Chiller E-301 02-Dec-14 A, 14234-3.Procourment.2.2 Deethanizer OH Condenser 02-Dec-14 A, 14234-3.Procourment.2.3 Condensate Stabilization Co 02-Dec-14 A, 14234-3.Procourment.2.4 Propane Receiver V-706 02-Nov-14 A, 14234-3.Procourment.2.5 Condensate Reboiler E-3001 02-Dec-14 A, 14234-3.Procourment.2.6 Gas/Gas Exchanger E-300A 02-Dec-14 A, 14234-3.Procourment.2.7 Gas/Gas Exchanger E-300B 30-Dec-14 A, 14234-3.Procourment.2.8 Gas/Liquid Exchanger E 30-Dec-14 A, 14234-3.Procourment.2.9 Gas/Liquid Exchanger E 05-Jan-15 A, 14234-3.Procourment.2.10 Regeneration Gas Coo Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25 Actual Level of Effort Actual Work Remaining Work Critical Remaini... Page 2 of 7 TASK filter: All Activities © Oracle Corporation
  • 3. Activity ID Activity Name Original Duration Start Finish 14234-3.P14234-3.Procourment.2.11 Water Degassing Boot V-3401 21 19-Oct-14 A 07-Dec-14 A 14234-3.P14234-3.Procourment.2.12 CPI Separator V-3402 21 19-Oct-14 A 07-Dec-14 A 14234-3.P14234-3.Procourment.2.13 On Spec Condensate Storage Tank T-3301 49 22-Jan-15 A 22-Feb-15 A 14234-3.P14234-3.Procourment.2.14 Off Spec Condensate Storage Tank T-3302 49 22-Jan-15 A 22-Feb-15 A 14234-3.P14234-3.Procourment.2.15 Bulk Materials 21 08-Dec-14 A 30-Dec-14 A 14234-3.Pr14234-3.Procourment.3 Successful Vessel Hydro Test 22 02-Apr-15 A 16-Aug-15 A21550 Hydrotesting of Vessels Completion 0 16-Aug-15 14234-3.P14234-3.Procourment.3.1 Chiller E-301 1 16-Aug-15 16-Aug-15 14234-3.P14234-3.Procourment.3.2 Deethanizer OH Condenser E-401 1 16-Aug-15 16-Aug-15 14234-3.P14234-3.Procourment.3.3 Condensate Stabilization Column C-3001 1 03-Apr-15 A 03-Apr-15 A 14234-3.P14234-3.Procourment.3.4 Propane Receiver V-706 1 03-Apr-15 A 03-Apr-15 A 14234-3.P14234-3.Procourment.3.5 Condensate Reboiler E-3001 1 03-Apr-15 A 03-Apr-15 A 14234-3.P14234-3.Procourment.3.6 Gas/Gas Exchanger E-300A 1 16-Aug-15 16-Aug-15 14234-3.P14234-3.Procourment.3.7 Gas/Gas Exchanger E-300B 1 16-Aug-15 16-Aug-15 14234-3.P14234-3.Procourment.3.8 Gas/Liquid Exchanger E-302A 1 16-Aug-15 16-Aug-15 14234-3.P14234-3.Procourment.3.9 Gas/Liquid Exchanger E-302B 1 16-Aug-15 16-Aug-15 14234-3.P14234-3.Procourment.3.10 Regeneration Gas Cooler E-303 1 16-Aug-15 16-Aug-15 14234-3.P14234-3.Procourment.3.11 Water Degassing Boot V-3401 1 02-Apr-15 A 02-Apr-15 A 14234-3.P14234-3.Procourment.3.12 CPI Separator V-3402 1 02-Apr-15 A 02-Apr-15 A 14234-3.Pr14234-3.Procourment.4 Equipment FAT at SPEC Facility 41 16-Aug-15 25-Oct-15 A21540 Equipment FAT Completion 0 25-Oct-15 14234-3.P14234-3.Procourment.4.1 Gas/Gas Exchanger (E-300A/B) Skid 1 10-Sep-15 13-Sep-15 14234-3.P14234-3.Procourment.4.2 Gas Liquid Exchanger (E-302A/B) Skid 1 27-Aug-15 30-Aug-15 14234-3.P14234-3.Procourment.4.3 Regeneration Gas Cooler (E-303) Skid 1 10-Sep-15 13-Sep-15 14234-3.P14234-3.Procourment.4.4 Gas Metering Package 1 25-Oct-15 25-Oct-15 14234-3.P14234-3.Procourment.4.5 NGL Stabilization Package 1 25-Oct-15 25-Oct-15 14234-3.P14234-3.Procourment.4.6 NGL Loading Pump Package 1 30-Aug-15 30-Aug-15 14234-3.P14234-3.Procourment.4.7 Water Degassing Boot & CPI Separator Package 1 16-Aug-15 16-Aug-15 14234-3.P14234-3.Procourment.4.8 ESD/FGS Panel 2 27-Sep-15 28-Sep-15 14234-3.Pr14234-3.Procourment.5 Shipping Readiness of Materials from SPEC Facility 41 17-Aug-15 26-Oct-15 A21530 Shipping Readiness of Materials @ SPEC Facility 0 26-Oct-15 14234-3.P14234-3.Procourment.5.1 Gas/Gas & Gas/Liquid Exchangers Package 2 13-Sep-15 16-Sep-15 14234-3.P14234-3.Procourment.5.2 Gas Metering Package 1 26-Oct-15 26-Oct-15 14234-3.P14234-3.Procourment.5.3 Condensate Stabilization Package 1 26-Oct-15 26-Oct-15 14234-3.P14234-3.Procourment.5.4 Condensate Loading Pump Package 1 31-Aug-15 31-Aug-15 14234-3.P14234-3.Procourment.5.5 Water Degassing Boot & CPI Separator Package 1 17-Aug-15 17-Aug-15 14234-3.P14234-3.Procourment.5.6 ESD/FGS Panel 1 29-Sep-15 29-Sep-15 14234-3.Pr14234-3.Project Constraints Project Constraints 137 09-Jul-15 27-Nov-15 A23989 Project Activities Resumed 0 09-Jul-15 A23990 First Shipment Despatch from HFZ 5 15-Aug-15* 20-Aug-15 A24000 First Shipment Receiving on Site 65 20-Aug-15 27-Oct-15 A24040 Overhaul of Compressors & Generators 80 15-Aug-15* 06-Nov-15 A24050 Procurement of MCC Enclosure & Component 5 15-Jul-15* 20-Jul-15 A24060 Material Deliveries, Assembly, & FAT 65 20-Jul-15 25-Sep-15 A24080 Procurement of Synchornization Controller + Delivery to HFZ 25 15-Aug-15* 10-Sep-15 A24100 Pumps Receiving in HFZ 45 09-Jul-15 24-Aug-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2014 2015 2016 07-Dec-14 A, 14234-3.Procourment.2.11 Water Degassing Boot V-3 07-Dec-14 A, 14234-3.Procourment.2.12 CPI Separator V-3402 22-Feb-15 A, 14234-3.Procourment.2.13 On Spec Conden 22-Feb-15 A, 14234-3.Procourment.2.14 Off Spec Conden 30-Dec-14 A, 14234-3.Procourment.2.15 Bulk Materials 16-Aug-15, 14234-3.Procourment.3 S Hydrotesting of Vessels Completion, 16-Aug-15, 14234-3.Procourment.3.1 16-Aug-15, 14234-3.Procourment.3.2 03-Apr-15 A, 14234-3.Procourment.3.3 Condensate S 03-Apr-15 A, 14234-3.Procourment.3.4 Propane Rece 03-Apr-15 A, 14234-3.Procourment.3.5 Condensate R 16-Aug-15, 14234-3.Procourment.3.6 16-Aug-15, 14234-3.Procourment.3.7 16-Aug-15, 14234-3.Procourment.3.8 16-Aug-15, 14234-3.Procourment.3.9 16-Aug-15, 14234-3.Procourment.3.10 02-Apr-15 A, 14234-3.Procourment.3.11 Water Degas 02-Apr-15 A, 14234-3.Procourment.3.12 CPI Separato 25-Oct-15, 14234-3.Procourm Equipment FAT Completion, 13-Sep-15, 14234-3.Procourment.4 30-Aug-15, 14234-3.Procourment.4.2 13-Sep-15, 14234-3.Procourment.4 25-Oct-15, 14234-3.Procourm 25-Oct-15, 14234-3.Procourm 30-Aug-15, 14234-3.Procourment.4.6 16-Aug-15, 14234-3.Procourment.4.7 28-Sep-15, 14234-3.Procourmen 26-Oct-15, 14234-3.Procourm Shipping Readiness of Materia 16-Sep-15, 14234-3.Procourment. 26-Oct-15, 14234-3.Procourm 26-Oct-15, 14234-3.Procourm 31-Aug-15, 14234-3.Procourment.5. 17-Aug-15, 14234-3.Procourment.5.5 29-Sep-15, 14234-3.Procourmen 27-Nov-15, 14234-3.Proje Project Activities Resumed, 09-Jul-15 First Shipment Despatch from HFZ First Shipment Receiving on S Overhaul of Compressors & Procurement of MCC Enclosure & Compo Material Deliveries, Assembly, & F Procurement of Synchornization Co Pumps Receiving in HFZ Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25 Actual Level of Effort Actual Work Remaining Work Critical Remaini... Page 3 of 7 TASK filter: All Activities © Oracle Corporation
  • 4. Activity ID Activity Name Original Duration Start Finish A24101 Procurement of Commissioning Spare 5 01-Sep-15* 05-Sep-15 A24102 Commissioning Spares Receiving In HFZ 25 05-Sep-15 01-Oct-15 A24150 Procurement of Electrical & Instrumentation Cables 5 30-Jul-15* 04-Aug-15 A24160 Electrical & Instrumentation Cables Ex. Works Readiness & Receiving on Site 92 04-Aug-15 07-Nov-15 A24161 DPR Visit - Hydro for 2nd Lot of Vessels and FAT for 1st lot Skid Packages 14 25-Aug-15* 08-Sep-15 A24162 Punch List Close Out + Shipping Readiness 3 08-Sep-15 11-Sep-15 A24170 2nd Shipment Dispatch from UAE 5 11-Sep-15 16-Sep-15 A24180 2nd Shipment Receiving on Site 50 16-Sep-15 06-Nov-15 A24181 DPR Visit - FAT for 2nd Lot of Skid Packages 13 15-Sep-15* 28-Sep-15 A24182 Punch List Close Out + Shipping Readiness 3 28-Sep-15 01-Oct-15 A24190 3rd Shipment Dispatch from UAE 5 01-Oct-15 07-Oct-15 A24200 3rd Shipment Receiving on Site 50 07-Oct-15 27-Nov-15 14234-3.Co14234-3.Construction Site Modification, Construction & Erection W 222 21-Jan-15 A 24-Feb-16 A21880 Site Modification, Construction & Erection Completion 0 24-Feb-16 14234-3.C14234-3.Construction.2 Site Construction & Erection Works 222 21-Jan-15 A 24-Feb-16 A21510 Site Construction & Erection Works Completion 0 24-Feb-16 14234-3.C14234-3.Construction.2.1 Foundation for Gas Metering Package 56 12-Aug-15 09-Oct-15 14234-3.C14234-3.Construction.2.2 Foundation for Water Degassing Boot & CPI Separator Sk 56 12-Aug-15 09-Oct-15 14234-3.C14234-3.Construction.2.3 Foundation for NGL Storage Tank T-3101 56 21-Jan-15 A 05-Sep-15 14234-3.C14234-3.Construction.2.4 Foundation for Condensate Stabilization Skid 56 12-Aug-15 09-Oct-15 14234-3.C14234-3.Construction.2.5 Foundation for Condensate Transfer Pump Skid 56 12-Aug-15 09-Oct-15 14234-3.C14234-3.Construction.2.6 Foundation for Gas/Gas Exchanger (E-300A/B) Skid 42 21-Sep-15 03-Nov-15 14234-3.C14234-3.Construction.2.7 Foundation for Gas Liquid Exchanger (E-302(A/B Skid 56 12-Aug-15 09-Oct-15 14234-3.C14234-3.Construction.2.8 Foundation for Regeneration Gas Cooler (E-303) Skid 42 21-Sep-15 04-Nov-15 14234-3.C14234-3.Construction.2.9 Foundation for Lighting Poles 56 12-Aug-15 09-Oct-15 14234-3.C14234-3.Construction.2.26 Erection of Gas Metering Skid 5 14-Nov-15 20-Nov-15 14234-3.C14234-3.Construction.2.10 Foundation for NGL Storage Tank T-3102 56 09-Jul-15 05-Sep-15 14234-3.C14234-3.Construction.2.28 Erection of NGL Storage Tank T-3101 126 09-Jul-15 16-Nov-15 14234-3.C14234-3.Construction.2.27 Erection of NGL Storage Tank T-3102 126 09-Jul-15 16-Nov-15 14234-3.C14234-3.Construction.2.11 Erection of Water Degassing Boot & CPI Separator Skid 7 14-Nov-15 23-Nov-15 14234-3.C14234-3.Construction.2.12 Erection of Condensate Stabilization Skid 14 27-Nov-15 11-Dec-15 14234-3.C14234-3.Construction.2.13 Erection of NGL Transfer Pump Skid 7 27-Nov-15 04-Dec-15 14234-3.C14234-3.Construction.2.14 Erection of Gas/Gas Exchanger (E-300A/B) Skid 7 09-Dec-15 17-Dec-15 14234-3.C14234-3.Construction.2.15 Erection of Gas Liquid Exchanger (E-302(A/B Skid 7 27-Nov-15 04-Dec-15 14234-3.C14234-3.Construction.2.16 Erection of Regeneration Gas Cooler (E-303) Skid 7 10-Dec-15 17-Dec-15 14234-3.C14234-3.Construction.2.17 Erection of Lighting Poles 7 14-Nov-15 23-Nov-15 14234-3.C14234-3.Construction.2.18 Cable Pulling - Instrument Cables 21 07-Nov-15 28-Nov-15 14234-3.C14234-3.Construction.2.19 Cable Pulling - Electrical Cables 21 07-Nov-15 28-Nov-15 14234-3.C14234-3.Construction.2.20 Electrical Cables Termination in MCC 14 19-Jan-16 02-Feb-16 14234-3.C14234-3.Construction.2.21 Erection of ESD/FGS Panel 7 27-Nov-15 04-Dec-15 14234-3.C14234-3.Construction.2.22 Instruments Cable Termination in DCS Panel 14 04-Dec-15 19-Dec-15 14234-3.C14234-3.Construction.2.23 Instruments Cable Termination in ESD/FGS Panel 14 07-Nov-15 21-Nov-15 14234-3.C14234-3.Construction.2.24 Interconnecting Cables - DCS to ESD/FGS Panel 14 19-Dec-15 02-Jan-16 14234-3.C14234-3.Construction.2.25 Interconnecting Piping Works 64 19-Dec-15 24-Feb-16 14234-3.C14234-3.Construction.1 Site Modification Works 103 04-Sep-15 19-Dec-15 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2014 2015 2016 Procurement of Commissioning Spa Commissioning Spares Receiving Procurement of Electrical & Instrumenta Electrical & Instrumentation C DPR Visit - Hydro for 2nd Lot of Ves Punch List Close Out + Shipping Re 2nd Shipment Dispatch from UAE 2nd Shipment Receiving on S DPR Visit - FAT for 2nd Lot of Ski Punch List Close Out + Shipping 3rd Shipment Dispatch from UAE 3rd Shipment Receiving on 24-Feb-16, 142 Site Modification 24-Feb-16, 142 Site Constructio 09-Oct-15, 14234-3.Constructio 09-Oct-15, 14234-3.Constructio 05-Sep-15, 14234-3.Construction.2 09-Oct-15, 14234-3.Constructio 09-Oct-15, 14234-3.Constructio 03-Nov-15, 14234-3.Constru 09-Oct-15, 14234-3.Constructio 04-Nov-15, 14234-3.Constru 09-Oct-15, 14234-3.Constructio 20-Nov-15, 14234-3.Const 05-Sep-15, 14234-3.Construction.2 16-Nov-15, 14234-3.Constr 16-Nov-15, 14234-3.Constr 23-Nov-15, 14234-3.Cons 11-Dec-15, 14234-3.Con 04-Dec-15, 14234-3.Con 17-Dec-15, 14234-3.Co 04-Dec-15, 14234-3.Con 17-Dec-15, 14234-3.Co 23-Nov-15, 14234-3.Cons 28-Nov-15, 14234-3.Cons 28-Nov-15, 14234-3.Cons 02-Feb-16, 14234 04-Dec-15, 14234-3.Con 19-Dec-15, 14234-3.Co 21-Nov-15, 14234-3.Const 02-Jan-16, 14234-3.C 24-Feb-16, 142 19-Dec-15, 14234-3.Co Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25 Actual Level of Effort Actual Work Remaining Work Critical Remaini... Page 4 of 7 TASK filter: All Activities © Oracle Corporation
  • 5. Activity ID Activity Name Original Duration Start Finish A21520 Site Modification Works Completion 0 19-Dec-15 14234-3.C14234-3.Construction.1.1 Three Phase Separator Package 18 27-Nov-15 16-Dec-15 14234-3.C14234-3.Construction.1.14 Heat Medium Expansion Tank/Pumps Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.19 LPG Bullets Control Station Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.26 LPG Loading Arm Skid 18 27-Nov-15 16-Dec-15 14234-3.C14234-3.Construction.1.27 Distributed Control System (DCS) 35 27-Oct-15 02-Dec-15 14234-3.C14234-3.Construction.1.28 Power Generators 19 06-Nov-15 25-Nov-15 14234-3.C14234-3.Construction.1.29 LV Switchgear & MCC 15 27-Nov-15 12-Dec-15 14234-3.C14234-3.Construction.1.23 Heat Medium Heater Skid 12Mmbtu 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.24 Flare KO Drum Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.25 Propane Loading Arm Skid 18 27-Nov-15 16-Dec-15 14234-3.C14234-3.Construction.1.15 Fuel Gas Conditioning Skid 25 27-Oct-15 21-Nov-15 14234-3.C14234-3.Construction.1.16 Instrument Air Package 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.17 Depropanizer Reboiler Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.18 Debutanizer Reboiler Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.30 Synchronization Panel 15 07-Nov-15 23-Nov-15 14234-3.C14234-3.Construction.1.13 Deethanizer Reboiler Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.3 Inlet Compressor Package - A 26 06-Nov-15 03-Dec-15 14234-3.C14234-3.Construction.1.5 Inlet Compressor Package - C 26 06-Nov-15 03-Dec-15 14234-3.C14234-3.Construction.1.7 Regeneration Heater Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.8 Deethanizer Reflux Accumulator Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.9 Depropanizer Reflux Accumulator Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.10 Debutanizer Reflux Accumulator Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.11 Condensate Flash Tank Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.12 Cold & LP Separator Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.20 Propane Bullets Control Staion Skid 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.21 LPG Loading Pumps Skid 18 27-Nov-15 16-Dec-15 14234-3.C14234-3.Construction.1.22 Heat Medium Heater Skid 6Mmbtu 26 27-Oct-15 23-Nov-15 14234-3.C14234-3.Construction.1.4 Inlet Compressor Package - B 26 06-Nov-15 03-Dec-15 14234-3.C14234-3.Construction.1.6 Molecular Sieve Filters Package 26 20-Oct-15 16-Nov-15 14234-3.C14234-3.Construction.1.2 Booster Compressor Package 42 06-Nov-15 19-Dec-15 14234-3.C14234-3.Construction.1.31 UPS System 67 04-Sep-15 12-Nov-15 14234-3.Co14234-3.Commissioning Precommissioning & Commissioning Wo 105 12-Nov-15 29-Feb-16 A21480 Precommissioning & Commissioning Completion 0 29-Feb-16 14234-3.C14234-3.Commissioning.1 Pre-Commissioning Works 57 12-Nov-15 09-Jan-16 A21500 Pre-Commissioning Completion 0 09-Jan-16 14234-3.C14234-3.Commissioning.1.1 Three Phase Separator Package 7 11-Dec-15 18-Dec-15 14234-3.C14234-3.Commissioning.1.2 Booster Compressor Package 7 19-Dec-15 26-Dec-15 14234-3.C14234-3.Commissioning.1.3 Inlet Compressor Package - A 7 03-Dec-15 10-Dec-15 14234-3.C14234-3.Commissioning.1.4 Inlet Compressor Package - B 7 03-Dec-15 10-Dec-15 14234-3.C14234-3.Commissioning.1.5 Inlet Compressor Package - C 7 03-Dec-15 10-Dec-15 14234-3.C14234-3.Commissioning.1.6 Molecular Sieve Filters Package 7 19-Dec-15 26-Dec-15 14234-3.C14234-3.Commissioning.1.7 Regeneration Heater Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.8 Deethanizer Reflux Accumulator Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.9 Depropanizer Reflux Accumulator Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.10 Debutanizer Reflux Accumulator Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.11 Condensate Flash Tank Skid 7 02-Jan-16 09-Jan-16 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2014 2015 2016 Site Modification Works 16-Dec-15, 14234-3.Co 23-Nov-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 16-Dec-15, 14234-3.Co 02-Dec-15, 14234-3.Cons 25-Nov-15, 14234-3.Cons 12-Dec-15, 14234-3.Con 23-Nov-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 16-Dec-15, 14234-3.Co 21-Nov-15, 14234-3.Const 23-Nov-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 03-Dec-15, 14234-3.Cons 03-Dec-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 23-Nov-15, 14234-3.Cons 16-Dec-15, 14234-3.Co 23-Nov-15, 14234-3.Cons 03-Dec-15, 14234-3.Cons 16-Nov-15, 14234-3.Constr 19-Dec-15, 14234-3.Co 12-Nov-15, 14234-3.Constr 29-Feb-16, 142 Precommission 09-Jan-16, 14234-3.C Pre-Commissioning C 18-Dec-15, 14234-3.Co 26-Dec-15, 14234-3.C 10-Dec-15, 14234-3.Com 10-Dec-15, 14234-3.Com 10-Dec-15, 14234-3.Com 26-Dec-15, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25 Actual Level of Effort Actual Work Remaining Work Critical Remaini... Page 5 of 7 TASK filter: All Activities © Oracle Corporation
  • 6. Activity ID Activity Name Original Duration Start Finish 14234-3.C14234-3.Commissioning.1.12 Cold & LP Separator Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.13 Deethanizer Reboiler Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.14 Heat Medium Expansion Tank/Pumps Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.15 Fuel Gas Conditioning Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.16 Instrument Air Package 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.17 Depropanizer Reboiler Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.18 Debutanizer Reboiler Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.19 LPG Bullets Control Station Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.20 Propane Bullets Control Staion Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.21 LPG Loading Pumps Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.22 Heat Medium Heater Skid 6Mmbtu 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.23 Heat Medium Heater Skid 12Mmbtu 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.24 Flare KO Drum Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.25 Propane Loading Arm Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.26 LPG Loading Arm Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.27 Gas Metering Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.28 Water Degassing Boot & CPI Separator Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.29 Condensate Stabilization Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.30 Condensate Transfer Pump Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.31 Gas/Gas Exchanger (E-300A/B) Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.36 Distributed Control System (DCS) 7 19-Dec-15 26-Dec-15 14234-3.C14234-3.Commissioning.1.37 Synchronization Panel 7 23-Nov-15 30-Nov-15 14234-3.C14234-3.Commissioning.1.32 Gas Liquid Exchanger (E-302(A/B Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.33 Regeneration Gas Cooler (E-303) Skid 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.34 F&G System 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.35 ESD/FGS System 7 02-Jan-16 09-Jan-16 14234-3.C14234-3.Commissioning.1.38 LV Switchgear & MCC 7 12-Dec-15 21-Dec-15 14234-3.C14234-3.Commissioning.1.39 UPS System 7 12-Nov-15 19-Nov-15 14234-3.C14234-3.Commissioning.1.40 Power Generators 7 26-Nov-15 03-Dec-15 14234-3.C14234-3.Commissioning.2 Commissioning Works 48 09-Jan-16 29-Feb-16 A21490 Commissioning Completion 0 29-Feb-16 14234-3.C14234-3.Commissioning.2.1 Three Phase Separator Package 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.2 Booster Compressor Package 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.3 Inlet Compressor Package - A 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.4 Inlet Compressor Package - B 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.5 Inlet Compressor Package - C 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.6 Molecular Sieve Filters Package 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.7 Regeneration Heater Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.8 Deethanizer Reflux Accumulator Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.9 Depropanizer Reflux Accumulator Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.10 Debutanizer Reflux Accumulator Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.11 Condensate Flash Tank Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.12 Cold & LP Separator Skid 5 09-Jan-16 15-Jan-16 14234-3.C14234-3.Commissioning.2.13 Deethanizer Reboiler Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.14 Heat Medium Expansion Tank/Pumps Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.15 Fuel Gas Conditioning Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.16 Instrument Air Package 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.17 Depropanizer Reboiler Skid 5 24-Feb-16 29-Feb-16 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2014 2015 2016 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 26-Dec-15, 14234-3.C 30-Nov-15, 14234-3.Com 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 09-Jan-16, 14234-3.C 21-Dec-15, 14234-3.Co 19-Nov-15, 14234-3.Comm 03-Dec-15, 14234-3.Com 29-Feb-16, 142 Commissioning 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 15-Jan-16, 14234-3 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25 Actual Level of Effort Actual Work Remaining Work Critical Remaini... Page 6 of 7 TASK filter: All Activities © Oracle Corporation
  • 7. Activity ID Activity Name Original Duration Start Finish 14234-3.C14234-3.Commissioning.2.18 Debutanizer Reboiler Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.19 LPG Bullets Control Station Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.20 Propane Bullets Control Staion Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.21 LPG Loading Pumps Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.22 Heat Medium Heater Skid 6Mmbtu 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.23 Heat Medium Heater Skid 12Mmbtu 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.24 Flare KO Drum Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.25 Propane Loading Arm Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.26 LPG Loading Arm Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.27 Gas Metering Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.28 Water Degassing Boot & CPI Separator Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.29 Condensate Stabilization Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.30 Condensate Transfer Pump Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.31 Gas/Gas Exchanger (E-300A/B) Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.32 Gas Liquid Exchanger (E-302(A/B Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.33 Regeneration Gas Cooler (E-303) Skid 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.34 F&G System 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.35 ESD/FGS System 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.36 Distributed Control System (DCS) 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.37 Synchronization Panel 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.38 LV Switchgear & MCC 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.39 Power Generators 5 24-Feb-16 29-Feb-16 14234-3.C14234-3.Commissioning.2.40 UPS System 5 24-Feb-16 29-Feb-16 14234-3.Pe14234-3.Perf & Rel Test Performance and Reliability Test 33 29-Feb-16 04-Apr-16 14234-3.Pe14234-3.Perf & Rel Test.Perf Test Performance Test 3 29-Feb-16 03-Mar-16 A24210 Performance Test 3 29-Feb-16 03-Mar-16 14234-3.Pe14234-3.Perf & Rel Test.Rel. Test Reliability Test 30 03-Mar-16 04-Apr-16 A24220 Reliability Test 30 03-Mar-16 04-Apr-16 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 2014 2015 2016 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 29-Feb-16, 142 04-Apr-16, 03-Mar-16, 142 Performance T 04-Apr-16, Reliability T Egbaoma Gas Processing Plant - New Level IV Schedule-latest 16-Jul-15 15:25 Actual Level of Effort Actual Work Remaining Work Critical Remaini... Page 7 of 7 TASK filter: All Activities © Oracle Corporation