Annual maintenance of industrial and energy plants requires good preparation. Over the years, we have carried out hundreds of annual maintenance shutdowns and learned how to succeed.
This info package guides you through the most important items – from preparation to activities during the actual maintenance procedure.
2. Maintpartner helps you to succeed
Annual maintenance of industrial and energy plants
requires good preparation. Over the years, we have
carried out hundreds of annual maintenance shutdowns
and learned how to succeed.
This info package guides you through the most important
items – from preparation to activities during the actual
maintenance procedure.
Maintpartner is a leading industrial operation and maintenance company in Northern Europe
and the leading actor in the energy sector in the Nordic countries. We help our customers
improve the productivity of their production facilities and minimize process disruptions.
In addition to long-term operation and maintenance agreements we offer development,
installation and engineering services. Our digital solutions represent the best-in-class
development in the field.
Maintpartner Group employs approximately 1,900 people. Our net sales in 2016 amounted to
some EUR 160 million. The Group has offices in Finland, Sweden, Poland and Estonia. More
information at www.maintpartner.com
Copyright Maintpartner Oy 20182
3. Successful shutdown planning is a significant
competitive advantage – and saves costs
COSTS: Downtime in production
represents typically some 10–30%
of the annual maintenance costs.
PRODUCTION LOSSES:
On average, annual production in
process industry is reduced by 2%
due to planned shutdowns.
Bad shutdown management may lead to losses of 5–10% of the total annual
production when, for example, schedule and budget are exceeded. Necessary
tasks may also remain undone which causes machine breakages and failures
when back in operation.
4. Typical failures in shutdowns and their
effects
Source data
The maintenance system is not
up-to-date
No predictive maintenance
program
Condition of the machines and
equipment has not been
monitored
Shutdown planning
Work objects and the various
work stages have not been
clarified with sufficient precision
The overall management
stumbles
There are work on the agenda
that need not be done during
the shutdown
Preparing
The required safety and other
inductions have not been made
Access permits have not been
arranged
Locking procedures and
process isolations have not
been defined
Execution
Project plan is not available
Deficient communication
Start-up plan has not been
finalized in time
Copyright Maintpartner Oy 20184
• It is not known which
equipment would require
maintenance
• Surprises during or after
the downtime (malfunctions
during operation and
production disturbances)
• Spare parts are missing,
and they can’t be delivered
quickly due to the suppliers'
holidays
• There is not enough
workforce, and during the
high season it is difficult to
get more
• Express deliveries,
overtime, and schedule
overruns increase costs
• Work cannot be started on
time
• Overtime and schedule
overruns increase the costs
• Unnecessary hurry poses
safety risks
• Personnel do not know
their work tasks
• Spare parts and tools are
not ready at the work
objects
• Hassle, trouble and safety
risks
• Shutdown costs may rise
5. 5 Copyright Maintpartner Oy 2018
Preparing
Lessons from the previous shutdown
Financing of investments
Condition monitoring of the plant
6. Lessons from previous maintenance
shutdown
Think about the previous annual maintenance, how did it
go considering e.g.
Safety at the site
Quality; claims, positive feedback
Investments and refurbishment work
Maintenance-related repairs
Spare parts, subcontractors, suppliers
Copyright Maintpartner Oy 20186
YOU HAVE TAKEN CARE OF
THE FINANCING OF THE
INVESTMENTS ALREADY IN
THE AUTUMN OF THE
PREVIOUS YEAR, HAVEN’T
YOU?
• Find out as early as possible
those changes to the
investment program that
shall be implemented in the
annual maintenance.
• Ensure that their funding is
budgeted.
Did you stay within the schedule and budget, did
you meet the quality requirements?
Always register the repairs, alterations and new parts
etc. in the maintenance management system or site
diary without delay.
7. Continuous and proactive monitoring of the
plant
• By sensory evaluation find out whether there are oil leaks,
noise, abnormal heating, abnormal smell?
• Take care of condition monitoring and analyses during
operation (e.g. vibration, temperature, compressed air
leaks).
• Go through the fault logs in automation systems and those
of the operators.
• Check what topical regulatory liabilities there are and what
kind of statutory work needs to be done in the annual
maintenance.
• Find out the scheduled maintenances that have been
defined in the preventive maintenance program and,
where necessary, those defined by the equipment
manufacturer.
• Estimate, how much the plant has been in operation
compared with the average; is the wear and tear higher or
lower than in the previous years, based on the present
operation? Consider also the load of the coming year.
Copyright Maintpartner Oy 20187
8. 8 Copyright Maintpartner Oy 2018
Planning
Planning process
Establishing a shutdown in the system
Ordering and reserving resources
Freezing a shutdown
Communication and regulatory requirements
9. Starting shutdown planning
Name a responsible project manager.
Run the selected work from the maintenance management system to the shutdown plan.
Note that it is not necessary to perform all upcoming maintenance work during the
shutdown. They can be made outside the shutdown and thus make the downtime
shorter.
Draw up the total budget for the shutdown when each individual work has its own budget
taking into account the work duration, resources, and spare parts.
Safety matters must be given serious consideration already at this stage.
Identify risks and establish measures for risk management; it is advisable to make risk
assessments well in advance.
At sites, which require work permits, production needs to start preparing for work permits well
in advance before the shutdown starts.
Communicate in time the upcoming changes also to the maintenance personnel at the plant
and other persons participating in the project to ensure timely work planning and to avoid
quality deviations due to surprises.
Copyright Maintpartner Oy 20189
10. Setting up a shutdown project in a common
system
• A shutdown project shall include all the work that is known to be
done during the shutdown:
Projects
Preventive maintenance
Planned repair work
• The projects usually run independently but it is good to have them
in the overall plan as well.
• It is advisable to set up an ”open shutdown” in the system as
well. There you can add work that needs to be done during a
shutdown, but you do not know yet, which one.
When starting to plan the annual maintenance shutdown,
the ”open shutdown” is checked for work that will be done
during it.
Copyright Maintpartner Oy 201810
DOCUMENTING THE
ANNUAL SHUTDOWN
• When planning, set up a
document folder where
you put all the
documents gathered
during the shutdown.
• Pictures/drawings,
meeting memos, risk
assessments,
protocols on
measurements, tests
etc.
• Ask the supplier for
necessary documents,
e.g. material and
classification certificates
11. Work-specific planning
Determine for each work
Time
Duration
Resources
Spare parts
Work-related tasks (electricity,
automation, machine installation,
construction work)
Locking procedures and process
isolations
Budget
Locate necessary drawings/pictures.
Set up all work stages as individual work
so that the complete scope is shown in
the shutdown plan.
Copyright Maintpartner Oy 201811
12. Ordering and delivery of spare parts,
machines and equipment
Define the needed spare parts and order them
in good time.
Apply the defined procurement channels and
written order contracts with their terms and
conditions.
PRO TIP: Let independent consultants help you:
when acquiring systems and equipment it is
advisable to consult an expert in electricity and
automation to ensure that
spare parts are commonly used types and
automation system can be accessed also
by other than the representatives of the
manufacturer or importer.
Before the shutdown, the warehouse staff puts
together the spare parts for each individual work
in one pile, together with the shutdown work slip.
This helps in collecting the parts to the
workshop or from the warehouse during the
shutdown.
Copyright Maintpartner Oy 201812
13. Reserving human resources on the basis of
the annual maintenance shutdown plan
Reserve enough workforce – during the most busy season it is
difficult to get more workers.
Utilize the experience of the employees when defining the time
taken up by various work tasks:
How many persons can simultaneously work at the same
object?
In which order is the work performed?
In detail, how many persons are needed for each specific
work?
This gives you the total need for workforce.
Try to arrange inductions, access permits etc. in advance.
Copyright Maintpartner Oy 201813
IN GENERAL,
WORKFORCE INCLUDES
E.G.
• Persons who write work
permits
• Machine fitters
• Welders
• Electricians
• Automation technicians
• Project management,
persons responsible for
the annual maintenance
• Supervisors for various
technical work
• Safety coordinator
14. Freezing the shutdown and communicating
responsibilities
Define at what stage the shutdown is
”frozen”, i.e. no new work is added to the
shutdown (unless there is an extremely good
reason for it).
Plan together with the project promoter to
make all needs clear and allow
subcontractors to recruit suitable seasonal
workforce – demanding work requires
experienced workforce.
Communicate clearly to all parties their
responsibilities.
Draw up a visual project plan which you can
deliver to participants and workshops /
coffee rooms.
Copyright Maintpartner Oy 201814
15. Getting out of silos –communicating
outwardly
Ensure that regulatory requirements are
being taken care of, such as
Obligation to inform, for example
possible emissions when shutting
down the facility.
Inspections required by the
authorities when working e.g. with
pressure vessels, electrical drives and
hazardous chemicals.
Safety coordinator, where necessary,
etc.
Inform relevant stakeholder about the
impact of the annual maintenance shutdown:
Canteen
Access restrictions
Possible interruptions in deliveries or
other impact on the neighboring
inhabitants, customers etc.
Copyright Maintpartner Oy 201815
16. 16 Copyright Maintpartner Oy 2018
During the annual
maintenance
Occupational safety
Meeting practices, monitoring and
documentation
Production startup and end of the project
17. Safety comes first
Safety is the first priority in every job.
Everyone is responsible for
compliance with the safety regulations
and is obliged to address the
deficiencies / offenses.
Perform work-specific risk
assessments and project risk surveys.
Safety issues are dealt with at each
meeting.
Each team leader, work planner and
project manager will undertake daily site
inspections during the standstill and make
a written memorandum.
It is also possible to ask other staff
members in the area to make observation
walks and to check work permits and use
of protective equipment.
Copyright Maintpartner Oy 201817
18. Monitoring, additional work, documents
Close co-operation and communication with partners are
indispensable.
Have meetings related to the shutdown 1–2 times/day:
Go through the completed, ongoing and upcoming work,
are you on schedule and whether changes have
occurred. Production is responsible for its part.
Agree on add-on and stand-alone work daily in writing
through a site diary, write them down in the meeting
memos.
Also consider first whether the work in question is
necessary to be dealt with during this maintenance
shutdown.
Follow-up costs regularly.
Finalize in good time the startup plan / detailed plan for test
runs.
Make a separate risk assessment for the startup phase.
Copyright Maintpartner Oy 201818
19. Preparing and executing production startup
Complete a startup plan where you ensure that:
Functional testing is defined and guidelines are available
Checklist for critical items: During the startup, leaks or
other minor repairs may occur and need to be quickly
handled to allow the production to run up
Responsibilities of operators and production are clear
All activities during the startup are scheduled
Good interaction and tacit knowledge shared by different
coordinators
Make a thorough final cleaning and organizing, and take care
of defects before starting up.
Ensure that there are adequate resources for the production
startup.
20. Ending the annual maintenance project
When the production is running normally, it is time to look at
how the shutdown succeeded.
Go through the shutdown plan; was all work done, what was left
undone and why. What kind of problems were encountered and
where did you succeed.
Stakeholders prepare a comprehensive final report.
Updating documents, final report, financial report, report
on spare parts, maintenance reports, device registry
update, safety issues documentation.
Closing meeting:
Go through step-by-step successful things and things to
develop + safety issues, schedules, technical changes,
etc.
Minutes of the acceptance inspection and memorandum
of the closing meeting.
Put together all documents related to the shutdown.
Register the
work carried
out as well
as learnings
Plan next
annual
maintenance
Carry out
annual
maintenance
21. 21
Contact us. We'll be pleased to tell you more.
Markku Leinonen, President, Project, Installation & Engineering Services Finland
Tel. +358 (0)46 851 6195
Hannu Leskelä, President, Industrial Service Agreements Finland & Estonia
Tel. +358 (0)40 546 8580
Timo Partanen, President (act.), Energy, Operation and Maintenance Finland & Poland
Tel. +358 (0)50 454 7200
Jukka Kallioniemi, President, Maintpartner Sweden
Tel. +358 (0)50 453 2727
Wojciech Serafin, President, Maintpartner Industry Poland
Tel. + 48 32 231 3265
Emails in the format firstname.lastname@maintpartner.com
Copyright Maintpartner Oy 2018
22. We keep the industry in operation
and in good condition.