Cold Eyed Reviews — June 2016
Cold Eyed Reviews – a powerful tool for good
governance and effective board supervision of projects
The acquisition of new assets through
project development is a high risk
activity, particularly as capital
investments are increasing in
technological complexity, cost, time
criticality and strategic importance.
When an organisation embarks on a
new program or critical project, a
competent board will want to have
the appropriate level of assurance at
each stage of the project’s
development to confirm that the
project is ready to progress
successfully to the next stage.
Directors or project sponsors often
request independent reviews and
validations of the accuracy and
adequacy of a project’s business case
(or feasibility study) as it is being
developed and before granting final
sanction to the investment. Once this
occurs, further periodic independent
reviews are prudent to assess the
project’s ongoing health and to
determine if there are any corrective
interventions needed to bring the
project back on track. These types of
independent reviews are often
referred to as Cold Eyed Reviews
(CERs)1
and are sometimes called
Independent Reviews or Due
Diligence Reviews.
Using appropriately qualified and
highly experienced reviewers, who
are independent of the organisation
with no ties to the project team, adds
profound value to the review. The
CER can reveal any optimism-bias2
and can introduce fresh ideas
through challenging any vertical
thinking processes which
conventionally are applied by a
project team after considering and
eliminating multiple options. The
independent thinking of the external
reviewers can highlight any inherent
weaknesses that are likely to
undermine the value realisation and
technical outcomes expected by the
board and the investors.
Board Perspective:
A CER provides a board with
assurance of the robustness of
the investment decision and that
there is good governance of the
project risks and hedging against
potential downsides. It enables
the board to regularly stress-test
the investment’s risk profile as
changes can unexpectedly occur
over the life of an investment.
The CER can provide the board
with the appropriate readiness for
the purpose of equity and debt
fund raising.
Investor Perspective:
A CER provides project investors
with an impartial assessment
of the merits of the project and
its likely potential to realise
a return on their investment.
It independently evaluates
the adequacy of the project
definition, regulatory compliance,
the cost estimate and financial
modelling, the execution
planning, the project risks and
delivery timeframes.
1	Cold Eyed Review specifically refers to independent and objective review with the review team emotionally detached from the opinions provided. However, Cold Eyes Review refers
to the team being independent in not having had previous involvement or sighting of the material being reviewed, a subtle but significant difference is highlighted in the use of these
two expressions.
2	Mott MacDonald (2002), Review of Large Public Procurement in the UK, Mott MacDonald (2002), available at www.hm-treasury.gov.uk/greenbook
	Other research in the field of Optimism Bias is referenced in Professor Flyvbjerg the founding Chair of Major Programme Management at Oxford University. Professor Flyvbjerg is
a leading international expert in the field of programme management and planning.
A board of directors is responsible for supervising the management and
overall business performance of an organisation. During the acquisition
of assets through project development, a board requires a high level
of confidence that management is applying prudence in doing the right
things and doing things right. This paper focuses on how a board and
its investor stakeholders can gain this assurance through Cold Eyed
Reviews (CERs). It discusses why an effective CER creates significant
value and effective risk hedging to an organisation.
2
Cold Eyed Reviews — June 2016
The second strategic question is –
Are we doing things right?
The CER process will further consider
how the project has been progressed
through the project development gates
in terms of its definition, risk
mitigation, and accuracy of the capital
and operating cost estimates, work
breakdown structure, execution
methodology, contracting strategy and
project organisation.
The CER will also assess other
elements of the foundation for controls
and how these controls will be applied
throughout the life of the project.
The initial scoping study and
prefeasibility study phases consider a
range of options of what the project
could be, and determines if there is
sufficient opportunity for the project to
be justified on the basis of economic,
strategic, and environmental grounds.
The business case or feasibility study
phase focuses on defining the selected
optimal option to allow an informed
investment decision.
Two critical strategic questions are
applied as part of a CER during these
development phases.
The first strategic question is –
Are we doing the right things?
The CER will assess the justification
for the selected option, including how
well it will deliver on the required
outcomes for the assets and whether it
will overcome economic hurdles.
Focusing the development study
process on the strategic question – Are
we doing the right things?– and having
that rigorously reviewed can
significantly enhance the quality of the
project definition and its associated
budget.
The review will also evaluate and
confirm if all potential operating
scenarios were considered, including
trade-off between capital and
operating expenditure. The
confirmation that the right decisions
were made by the project team on
the operating philosophies and
performance requirements of the final
assets will create an environment for
lasting decisions4
, preventing rework,
delays and ultimately, additional costs.
Strategic review questions to improve the project’s effectiveness and efficiency
prior to the final investment decision
3	Note: Different terminologies have purposely been used in each of Figures 1  2, with the knowledge and awareness that different business sectors and domains use specific industry
language to represent the various phases in the project development and execution lifecycle.
4	 Lasting decisions means that these decisions are not altered later in the project lifecycle.
Figure 1: Below shows the typical project lifecycle phases.3
Scoping study
(shaping)
What could it be?
Prefeasibility study
(PFS)
What should it be?
Feasibility study
(DFS/FEED/FEL)
What will it be?
Project commitment
(BFS)
Preparation and
investment decision
Project execution
Deliver the project
Operations
Extract the value
Recommended CER points
Recommended CER for funding investment decision
Business Case (Feasibility Study)
Governance Clarity and maturity
of project definition
Risk Management
Procurement
The review determines if the selected
procurement strategy is appropriate and
aligned with the project risk profile and
the supply market’s potential, including
possible funding options and scenarios.
The review will confirm if the
formal governance structures are
established to integrate the various
project functions, particularly for
the transition from development
mode to implementation.
The review will consider the context and the clarity of
the organisation’s strategic framework, including the
objectives, internal policies and business plans, as these
establish the foundation for the project’s business case.
Significant value comes from understanding the
business’s strategic objectives, and having clarity
around definition of the needs of the business and the
quantification of the outcomes against benchmarks.
Key elements of a CER
A CER can, and should be, structured to suit
a project’s characteristics, risk-profile, timing
within the lifecycle, governance review
requirements and readiness for the funding
investment decision (FID). The reviews are often
carried out under strict time constraints, given
the tight timeframes for approval to proceed to
the next development stage and for the final
funding investment decision.
An assessment is made
as to whether the project is
sufficiently well-defined for
its stage of development and
the likely influence on the
accuracy of the cost and
time estimates and level of
contingency applied.
The review will assess the completeness of
the risk register, including whether risk
controls and planned mitigation measures
have been included in the cost estimate and
residual risks included in the contingency
assessment. It will also confirm that risk
management processes are in place for the
implementation phase.
The business case is reviewed against the organisation’s
strategic framework to confirm alignment. In particular,
the risk-adjusted economic value of the project is compared
against the organisation’s strategic investment strategy.
An analysis can also be completed on whether the strategic
objectives are placing any unnecessary constraints on the
project which, if corrected, may unlock additional value in
the pursued option.
Foundation for
control
Strategy
Other elements where value is added by
having an independent assessment include:
• the capabilities and capacities of the project team
• team culture and behaviours
• organisational improvement
• fiscal management and discipline
• economic benefit and value add
• sensitivity analysis
• systems management
• monitoring, control and reporting
• change management
• document and information management, and
• market, corporate and commercial functions.
3
Cold Eyed Reviews — June 2016
4
Cold Eyed Reviews — June 2016
The CER process has been applied to
a large number of projects across
major infrastructure, chemical, oil
and gas and mining sectors. In the
reviews conducted for various
organisations, the outcomes have led
to better risk focus, improvements to
the business value chain, reductions
in program and project costs and
improved returns on investment. On
one multibillion dollar pit to port
mining project the CER assisted the
owner to focus its efforts on
improving certain aspects of the
project definition, to successfully
negotiate a major engineering
procurement and construction
contract and to provide greater
confidence to secure the required
debt funding for the project to
proceed. For a major chemical
manufacturing plant, the CER
flagged the need for improvement of
the owner’s governance and risk
management processes and
improvement in budget certainty.
The project proceeded to execution
and successful completion, meeting
all of its objectives.
The CER methodologies applied to
the establishment of new assets has
beenadaptedtoprovidetransactional
due diligence for the merger and
acquisition of operating assets,
utilising third party reliance
agreements. It has been used in
contractual disputes, in alternative
dispute resolutions and forensic
analyses for the purpose of mediating
between two disputing parties. When
applied in these situations, time
constraints typically applied in a
CER will need to be varied to suit the
project requirements.
At the conclusion of the CER a
comprehensive traffic light matrix
(see image below) can be provided as
part of the report, outlining the
critical issues and providing
recommendations for improvement.
The process is focused on advice that
can be actioned to produce improved
results.
Outcome of recent reviews
About the Author
Magued Moftah is an Executive
Advisor with E3 Advisory Pty
Ltd. He has a proven track
record in leadership and
management spanning 40 years in
engineering projects and business
management. He has extensive
experience managing contracts in
the infrastructure, rail, oil and gas,
mining, water and waste water
and power sectors.
Magued has been responsible
for leading and managing Cold
Eyed Reviews, asset acquisitions,
technical and commercial due
diligence and contract resolution
mediation and disputation
activities.
Advisian		/	1
SUB-ELEMENT MINIMUM	 REQUIREMENT NOTE
• Key	supply	and	demand	drivers Detailed	assessment and	
evaluation.• Revenue	growth	factors
• Industry	structures
• Diversity	of	suppliers	and	customers
• Forecast	project	position	– when	operational
• Price	assumption
• Historical	and	forecast	margins
• Value	adding	sources,	historically	and	forecast Demonstrated	position
• Project’s	ability	to	exploit	these	opportunities
• Fits	with	overall	strategy Demonstrated	position
• Review	of	the	relationship	between	the	project	and	business	strategy
• Strategic	alternatives	including	exit	/no	go	option Detailedwithin	available	
envelope of data• Basis	of	potential	project	being	best	option
• Potential	of	phased	development
• Scenario	development	process Basedon	recommended	
project
• Driver	to	execute	exit	strategy Fullydeveloped	strategy
• Triggers	for	exit	decision
Strategy CRITICAL	AND	URGENT
Immediate	action	on	identified	shortcomings	and	recommendations	
is	required	to	achieve	success	of	the	project
IMPORTANT	AND	URGENT
The	project	should	go	forward	with	action	on	recommendations
IMPORTANT	AND	OF	BENEFIT
The	program	or	project	may	benefit	from	implementation	
or	recommendations
Industry	
Attractiveness
Strategic	
Rationale
Strategic	Fit
Strategic	
Alternatives
Scen ario	An alysis
Exit	Strategy
Comprehensive traffic light matrix (example)

Weitere ähnliche Inhalte

Was ist angesagt?

Infrastrcture project management
Infrastrcture project managementInfrastrcture project management
Infrastrcture project managementSanjeev Deshmukh
 
Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Glen Alleman
 
Project and project management
Project and project managementProject and project management
Project and project managementwodato
 
Project Analysis and Methods of project evaluation
Project Analysis and Methods of project evaluationProject Analysis and Methods of project evaluation
Project Analysis and Methods of project evaluationYousuf Razzaq
 
Principles of IT Governance
Principles of IT GovernancePrinciples of IT Governance
Principles of IT GovernanceGlen Alleman
 
33720055
3372005533720055
33720055dkr786
 
Notes on IT programmatic risk in 5 not so easy pieces
Notes on IT programmatic risk in 5 not so easy piecesNotes on IT programmatic risk in 5 not so easy pieces
Notes on IT programmatic risk in 5 not so easy piecesGlen Alleman
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as OpportunityGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
PROJECT CLASSIFICATION, IDENTIFICATION, FORMULATION
PROJECT CLASSIFICATION, IDENTIFICATION, FORMULATIONPROJECT CLASSIFICATION, IDENTIFICATION, FORMULATION
PROJECT CLASSIFICATION, IDENTIFICATION, FORMULATIONDr. RICHA SINGHAL
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
Module 1 project planning and appraisal
Module 1 project planning and appraisalModule 1 project planning and appraisal
Module 1 project planning and appraisaldmkanchepalya
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
project planning
project planningproject planning
project planningOmid Minooee
 
Project Management Notes 1
Project Management Notes 1Project Management Notes 1
Project Management Notes 1Golam Bitonsir
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 
Risk Management Guidance
Risk Management GuidanceRisk Management Guidance
Risk Management GuidanceGlen Alleman
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk ManagementGlen Alleman
 

Was ist angesagt? (19)

Infrastrcture project management
Infrastrcture project managementInfrastrcture project management
Infrastrcture project management
 
Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)Cpm500 d _alleman__tpm lesson 3 (v1)
Cpm500 d _alleman__tpm lesson 3 (v1)
 
Project and project management
Project and project managementProject and project management
Project and project management
 
Project Analysis and Methods of project evaluation
Project Analysis and Methods of project evaluationProject Analysis and Methods of project evaluation
Project Analysis and Methods of project evaluation
 
Principles of IT Governance
Principles of IT GovernancePrinciples of IT Governance
Principles of IT Governance
 
33720055
3372005533720055
33720055
 
Notes on IT programmatic risk in 5 not so easy pieces
Notes on IT programmatic risk in 5 not so easy piecesNotes on IT programmatic risk in 5 not so easy pieces
Notes on IT programmatic risk in 5 not so easy pieces
 
Project Quality Management
Project Quality ManagementProject Quality Management
Project Quality Management
 
Managing Risk as Opportunity
Managing Risk as OpportunityManaging Risk as Opportunity
Managing Risk as Opportunity
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
PROJECT CLASSIFICATION, IDENTIFICATION, FORMULATION
PROJECT CLASSIFICATION, IDENTIFICATION, FORMULATIONPROJECT CLASSIFICATION, IDENTIFICATION, FORMULATION
PROJECT CLASSIFICATION, IDENTIFICATION, FORMULATION
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
Module 1 project planning and appraisal
Module 1 project planning and appraisalModule 1 project planning and appraisal
Module 1 project planning and appraisal
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
project planning
project planningproject planning
project planning
 
Project Management Notes 1
Project Management Notes 1Project Management Notes 1
Project Management Notes 1
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 
Risk Management Guidance
Risk Management GuidanceRisk Management Guidance
Risk Management Guidance
 
Continuous Risk Management
Continuous Risk ManagementContinuous Risk Management
Continuous Risk Management
 

Andere mochten auch

সৃজনশীল চিন্তন দক্ষতা
সৃজনশীল চিন্তন দক্ষতাসৃজনশীল চিন্তন দক্ষতা
সৃজনশীল চিন্তন দক্ষতাbasharosd
 
E3 CER A Powerful tool for Governance
E3 CER A Powerful tool for GovernanceE3 CER A Powerful tool for Governance
E3 CER A Powerful tool for GovernanceMagued Moftah
 
The Tao of Badass Attraction Guide
The Tao of Badass Attraction GuideThe Tao of Badass Attraction Guide
The Tao of Badass Attraction GuideDavid Wabasse
 
চাপ মোকাবেলার দক্ষতা
চাপ মোকাবেলার দক্ষতা চাপ মোকাবেলার দক্ষতা
চাপ মোকাবেলার দক্ষতা basharosd
 
Premier league
Premier leaguePremier league
Premier leaguewiffen7
 
যোগাযোগ দক্ষতা. অর্জনের সূত্র Ppt
যোগাযোগ দক্ষতা. অর্জনের সূত্র Pptযোগাযোগ দক্ষতা. অর্জনের সূত্র Ppt
যোগাযোগ দক্ষতা. অর্জনের সূত্র Pptbasharosd
 
Bon jovi
Bon joviBon jovi
Bon joviKarost
 
Projekt HiLASE – Ing. Tomáš Mocek, Ph.D.
Projekt HiLASE – Ing. Tomáš Mocek, Ph.D.Projekt HiLASE – Ing. Tomáš Mocek, Ph.D.
Projekt HiLASE – Ing. Tomáš Mocek, Ph.D.SpinUp-Univerzita-Pardubice
 
যোগাযোগ দক্ষতা. অর্জনের সূত্র Ppsx
যোগাযোগ দক্ষতা. অর্জনের সূত্র Ppsxযোগাযোগ দক্ষতা. অর্জনের সূত্র Ppsx
যোগাযোগ দক্ষতা. অর্জনের সূত্র Ppsxbasharosd
 
Les verbes en er (prĂŠsent)
Les verbes en  er (prĂŠsent)Les verbes en  er (prĂŠsent)
Les verbes en er (prĂŠsent)belge21
 
GuĂ­a Brand Rain para potenciar tu reputaciĂłn personal cuando viajas
GuĂ­a Brand Rain para potenciar tu reputaciĂłn personal cuando viajasGuĂ­a Brand Rain para potenciar tu reputaciĂłn personal cuando viajas
GuĂ­a Brand Rain para potenciar tu reputaciĂłn personal cuando viajasanpro21
 
Les verbes en er (prĂŠsent)
Les verbes en er (prĂŠsent)Les verbes en er (prĂŠsent)
Les verbes en er (prĂŠsent)belge21
 

Andere mochten auch (12)

সৃজনশীল চিন্তন দক্ষতা
সৃজনশীল চিন্তন দক্ষতাসৃজনশীল চিন্তন দক্ষতা
সৃজনশীল চিন্তন দক্ষতা
 
E3 CER A Powerful tool for Governance
E3 CER A Powerful tool for GovernanceE3 CER A Powerful tool for Governance
E3 CER A Powerful tool for Governance
 
The Tao of Badass Attraction Guide
The Tao of Badass Attraction GuideThe Tao of Badass Attraction Guide
The Tao of Badass Attraction Guide
 
চাপ মোকাবেলার দক্ষতা
চাপ মোকাবেলার দক্ষতা চাপ মোকাবেলার দক্ষতা
চাপ মোকাবেলার দক্ষতা
 
Premier league
Premier leaguePremier league
Premier league
 
যোগাযোগ দক্ষতা. অর্জনের সূত্র Ppt
যোগাযোগ দক্ষতা. অর্জনের সূত্র Pptযোগাযোগ দক্ষতা. অর্জনের সূত্র Ppt
যোগাযোগ দক্ষতা. অর্জনের সূত্র Ppt
 
Bon jovi
Bon joviBon jovi
Bon jovi
 
Projekt HiLASE – Ing. Tomáš Mocek, Ph.D.
Projekt HiLASE – Ing. Tomáš Mocek, Ph.D.Projekt HiLASE – Ing. Tomáš Mocek, Ph.D.
Projekt HiLASE – Ing. Tomáš Mocek, Ph.D.
 
যোগাযোগ দক্ষতা. অর্জনের সূত্র Ppsx
যোগাযোগ দক্ষতা. অর্জনের সূত্র Ppsxযোগাযোগ দক্ষতা. অর্জনের সূত্র Ppsx
যোগাযোগ দক্ষতা. অর্জনের সূত্র Ppsx
 
Les verbes en er (prĂŠsent)
Les verbes en  er (prĂŠsent)Les verbes en  er (prĂŠsent)
Les verbes en er (prĂŠsent)
 
GuĂ­a Brand Rain para potenciar tu reputaciĂłn personal cuando viajas
GuĂ­a Brand Rain para potenciar tu reputaciĂłn personal cuando viajasGuĂ­a Brand Rain para potenciar tu reputaciĂłn personal cuando viajas
GuĂ­a Brand Rain para potenciar tu reputaciĂłn personal cuando viajas
 
Les verbes en er (prĂŠsent)
Les verbes en er (prĂŠsent)Les verbes en er (prĂŠsent)
Les verbes en er (prĂŠsent)
 

Ähnlich wie E3 cer a powerful tool for governance

PMO and Tollgate Process
PMO and Tollgate Process PMO and Tollgate Process
PMO and Tollgate Process Bob Prieto
 
L2 PM Project Feasibility study.pptx
L2 PM Project Feasibility study.pptxL2 PM Project Feasibility study.pptx
L2 PM Project Feasibility study.pptxbettymakuve1
 
Choosing Innovation Projects
Choosing Innovation ProjectsChoosing Innovation Projects
Choosing Innovation ProjectsFadli Luthfi
 
Angga efriansyah chapter 8[1]
Angga efriansyah chapter 8[1]Angga efriansyah chapter 8[1]
Angga efriansyah chapter 8[1]anggaefriansyah
 
Schilling (2017pp.129 151) choosing innovation projects (chapter 7)
Schilling (2017pp.129 151) choosing innovation projects (chapter 7)Schilling (2017pp.129 151) choosing innovation projects (chapter 7)
Schilling (2017pp.129 151) choosing innovation projects (chapter 7)NandiNoprita
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAddisu15
 
Introduction Termination of a project is inevitable, but how it .pdf
Introduction Termination of a project is inevitable, but how it .pdfIntroduction Termination of a project is inevitable, but how it .pdf
Introduction Termination of a project is inevitable, but how it .pdfanuragperipheral
 
Module 2.pdf
Module 2.pdfModule 2.pdf
Module 2.pdfSaffanAhmed1
 
Strategic Management.pptx
Strategic Management.pptxStrategic Management.pptx
Strategic Management.pptxGermelynPea1
 
Project appraisal part 1
Project appraisal part  1Project appraisal part  1
Project appraisal part 1danappadharwad
 
Using the Analytic Hierarchy Process (AHP) to Select and Prioritize Project...
Using the Analytic Hierarchy Process  (AHP) to Select and Prioritize  Project...Using the Analytic Hierarchy Process  (AHP) to Select and Prioritize  Project...
Using the Analytic Hierarchy Process (AHP) to Select and Prioritize Project...Ricardo Viana Vargas
 
Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Amr Miqdadi
 
Ch 13
Ch 13Ch 13
Ch 13kpserver
 

Ähnlich wie E3 cer a powerful tool for governance (20)

PMO and Tollgate Process
PMO and Tollgate Process PMO and Tollgate Process
PMO and Tollgate Process
 
L2 PM Project Feasibility study.pptx
L2 PM Project Feasibility study.pptxL2 PM Project Feasibility study.pptx
L2 PM Project Feasibility study.pptx
 
2.pptx
2.pptx2.pptx
2.pptx
 
Components of FS,Th&BP.pptx
Components of FS,Th&BP.pptxComponents of FS,Th&BP.pptx
Components of FS,Th&BP.pptx
 
Choosing Innovation Projects
Choosing Innovation ProjectsChoosing Innovation Projects
Choosing Innovation Projects
 
Chapter 8 .
Chapter 8 .Chapter 8 .
Chapter 8 .
 
Angga efriansyah chapter 8[1]
Angga efriansyah chapter 8[1]Angga efriansyah chapter 8[1]
Angga efriansyah chapter 8[1]
 
Schilling (2017pp.129 151) choosing innovation projects (chapter 7)
Schilling (2017pp.129 151) choosing innovation projects (chapter 7)Schilling (2017pp.129 151) choosing innovation projects (chapter 7)
Schilling (2017pp.129 151) choosing innovation projects (chapter 7)
 
Auditing projects in the early stages.pdf
Auditing projects in the early stages.pdfAuditing projects in the early stages.pdf
Auditing projects in the early stages.pdf
 
Introduction Termination of a project is inevitable, but how it .pdf
Introduction Termination of a project is inevitable, but how it .pdfIntroduction Termination of a project is inevitable, but how it .pdf
Introduction Termination of a project is inevitable, but how it .pdf
 
Module 2.pdf
Module 2.pdfModule 2.pdf
Module 2.pdf
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
 
Publishable article
Publishable articlePublishable article
Publishable article
 
Strategic Management.pptx
Strategic Management.pptxStrategic Management.pptx
Strategic Management.pptx
 
Project appraisal part 1
Project appraisal part  1Project appraisal part  1
Project appraisal part 1
 
Using the Analytic Hierarchy Process (AHP) to Select and Prioritize Project...
Using the Analytic Hierarchy Process  (AHP) to Select and Prioritize  Project...Using the Analytic Hierarchy Process  (AHP) to Select and Prioritize  Project...
Using the Analytic Hierarchy Process (AHP) to Select and Prioritize Project...
 
Pm chapter 2...
Pm chapter 2...Pm chapter 2...
Pm chapter 2...
 
Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1Pmp Exam Prep PDF-1
Pmp Exam Prep PDF-1
 
Ch 13
Ch 13Ch 13
Ch 13
 
Pm chapter 2
Pm chapter 2Pm chapter 2
Pm chapter 2
 

KĂźrzlich hochgeladen

B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableSeo
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture conceptP&CO
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...amitlee9823
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLkapoorjyoti4444
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperityhemanthkumar470700
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentationuneakwhite
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfAmzadHosen3
 

KĂźrzlich hochgeladen (20)

B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service AvailableCall Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
Call Girls Ludhiana Just Call 98765-12871 Top Class Call Girl Service Available
 
Business Model Canvas (BMC)- A new venture concept
Business Model Canvas (BMC)-  A new venture conceptBusiness Model Canvas (BMC)-  A new venture concept
Business Model Canvas (BMC)- A new venture concept
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
Call Girls Electronic City Just Call 👗 7737669865 👗 Top Class Call Girl Servi...
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRLBAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
BAGALUR CALL GIRL IN 98274*61493 ❤CALL GIRLS IN ESCORT SERVICE❤CALL GIRL
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Falcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to ProsperityFalcon's Invoice Discounting: Your Path to Prosperity
Falcon's Invoice Discounting: Your Path to Prosperity
 
Uneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration PresentationUneak White's Personal Brand Exploration Presentation
Uneak White's Personal Brand Exploration Presentation
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
John Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdfJohn Halpern sued for sexual assault.pdf
John Halpern sued for sexual assault.pdf
 

E3 cer a powerful tool for governance

  • 1. 1 Cold Eyed Reviews — June 2016 Cold Eyed Reviews – a powerful tool for good governance and effective board supervision of projects The acquisition of new assets through project development is a high risk activity, particularly as capital investments are increasing in technological complexity, cost, time criticality and strategic importance. When an organisation embarks on a new program or critical project, a competent board will want to have the appropriate level of assurance at each stage of the project’s development to confirm that the project is ready to progress successfully to the next stage. Directors or project sponsors often request independent reviews and validations of the accuracy and adequacy of a project’s business case (or feasibility study) as it is being developed and before granting final sanction to the investment. Once this occurs, further periodic independent reviews are prudent to assess the project’s ongoing health and to determine if there are any corrective interventions needed to bring the project back on track. These types of independent reviews are often referred to as Cold Eyed Reviews (CERs)1 and are sometimes called Independent Reviews or Due Diligence Reviews. Using appropriately qualified and highly experienced reviewers, who are independent of the organisation with no ties to the project team, adds profound value to the review. The CER can reveal any optimism-bias2 and can introduce fresh ideas through challenging any vertical thinking processes which conventionally are applied by a project team after considering and eliminating multiple options. The independent thinking of the external reviewers can highlight any inherent weaknesses that are likely to undermine the value realisation and technical outcomes expected by the board and the investors. Board Perspective: A CER provides a board with assurance of the robustness of the investment decision and that there is good governance of the project risks and hedging against potential downsides. It enables the board to regularly stress-test the investment’s risk profile as changes can unexpectedly occur over the life of an investment. The CER can provide the board with the appropriate readiness for the purpose of equity and debt fund raising. Investor Perspective: A CER provides project investors with an impartial assessment of the merits of the project and its likely potential to realise a return on their investment. It independently evaluates the adequacy of the project definition, regulatory compliance, the cost estimate and financial modelling, the execution planning, the project risks and delivery timeframes. 1 Cold Eyed Review specifically refers to independent and objective review with the review team emotionally detached from the opinions provided. However, Cold Eyes Review refers to the team being independent in not having had previous involvement or sighting of the material being reviewed, a subtle but significant difference is highlighted in the use of these two expressions. 2 Mott MacDonald (2002), Review of Large Public Procurement in the UK, Mott MacDonald (2002), available at www.hm-treasury.gov.uk/greenbook Other research in the field of Optimism Bias is referenced in Professor Flyvbjerg the founding Chair of Major Programme Management at Oxford University. Professor Flyvbjerg is a leading international expert in the field of programme management and planning. A board of directors is responsible for supervising the management and overall business performance of an organisation. During the acquisition of assets through project development, a board requires a high level of confidence that management is applying prudence in doing the right things and doing things right. This paper focuses on how a board and its investor stakeholders can gain this assurance through Cold Eyed Reviews (CERs). It discusses why an effective CER creates significant value and effective risk hedging to an organisation.
  • 2. 2 Cold Eyed Reviews — June 2016 The second strategic question is – Are we doing things right? The CER process will further consider how the project has been progressed through the project development gates in terms of its definition, risk mitigation, and accuracy of the capital and operating cost estimates, work breakdown structure, execution methodology, contracting strategy and project organisation. The CER will also assess other elements of the foundation for controls and how these controls will be applied throughout the life of the project. The initial scoping study and prefeasibility study phases consider a range of options of what the project could be, and determines if there is sufficient opportunity for the project to be justified on the basis of economic, strategic, and environmental grounds. The business case or feasibility study phase focuses on defining the selected optimal option to allow an informed investment decision. Two critical strategic questions are applied as part of a CER during these development phases. The first strategic question is – Are we doing the right things? The CER will assess the justification for the selected option, including how well it will deliver on the required outcomes for the assets and whether it will overcome economic hurdles. Focusing the development study process on the strategic question – Are we doing the right things?– and having that rigorously reviewed can significantly enhance the quality of the project definition and its associated budget. The review will also evaluate and confirm if all potential operating scenarios were considered, including trade-off between capital and operating expenditure. The confirmation that the right decisions were made by the project team on the operating philosophies and performance requirements of the final assets will create an environment for lasting decisions4 , preventing rework, delays and ultimately, additional costs. Strategic review questions to improve the project’s effectiveness and efficiency prior to the final investment decision 3 Note: Different terminologies have purposely been used in each of Figures 1 2, with the knowledge and awareness that different business sectors and domains use specific industry language to represent the various phases in the project development and execution lifecycle. 4 Lasting decisions means that these decisions are not altered later in the project lifecycle. Figure 1: Below shows the typical project lifecycle phases.3 Scoping study (shaping) What could it be? Prefeasibility study (PFS) What should it be? Feasibility study (DFS/FEED/FEL) What will it be? Project commitment (BFS) Preparation and investment decision Project execution Deliver the project Operations Extract the value Recommended CER points Recommended CER for funding investment decision
  • 3. Business Case (Feasibility Study) Governance Clarity and maturity of project definition Risk Management Procurement The review determines if the selected procurement strategy is appropriate and aligned with the project risk profile and the supply market’s potential, including possible funding options and scenarios. The review will confirm if the formal governance structures are established to integrate the various project functions, particularly for the transition from development mode to implementation. The review will consider the context and the clarity of the organisation’s strategic framework, including the objectives, internal policies and business plans, as these establish the foundation for the project’s business case. Significant value comes from understanding the business’s strategic objectives, and having clarity around definition of the needs of the business and the quantification of the outcomes against benchmarks. Key elements of a CER A CER can, and should be, structured to suit a project’s characteristics, risk-profile, timing within the lifecycle, governance review requirements and readiness for the funding investment decision (FID). The reviews are often carried out under strict time constraints, given the tight timeframes for approval to proceed to the next development stage and for the final funding investment decision. An assessment is made as to whether the project is sufficiently well-defined for its stage of development and the likely influence on the accuracy of the cost and time estimates and level of contingency applied. The review will assess the completeness of the risk register, including whether risk controls and planned mitigation measures have been included in the cost estimate and residual risks included in the contingency assessment. It will also confirm that risk management processes are in place for the implementation phase. The business case is reviewed against the organisation’s strategic framework to confirm alignment. In particular, the risk-adjusted economic value of the project is compared against the organisation’s strategic investment strategy. An analysis can also be completed on whether the strategic objectives are placing any unnecessary constraints on the project which, if corrected, may unlock additional value in the pursued option. Foundation for control Strategy Other elements where value is added by having an independent assessment include: • the capabilities and capacities of the project team • team culture and behaviours • organisational improvement • fiscal management and discipline • economic benefit and value add • sensitivity analysis • systems management • monitoring, control and reporting • change management • document and information management, and • market, corporate and commercial functions. 3 Cold Eyed Reviews — June 2016
  • 4. 4 Cold Eyed Reviews — June 2016 The CER process has been applied to a large number of projects across major infrastructure, chemical, oil and gas and mining sectors. In the reviews conducted for various organisations, the outcomes have led to better risk focus, improvements to the business value chain, reductions in program and project costs and improved returns on investment. On one multibillion dollar pit to port mining project the CER assisted the owner to focus its efforts on improving certain aspects of the project definition, to successfully negotiate a major engineering procurement and construction contract and to provide greater confidence to secure the required debt funding for the project to proceed. For a major chemical manufacturing plant, the CER flagged the need for improvement of the owner’s governance and risk management processes and improvement in budget certainty. The project proceeded to execution and successful completion, meeting all of its objectives. The CER methodologies applied to the establishment of new assets has beenadaptedtoprovidetransactional due diligence for the merger and acquisition of operating assets, utilising third party reliance agreements. It has been used in contractual disputes, in alternative dispute resolutions and forensic analyses for the purpose of mediating between two disputing parties. When applied in these situations, time constraints typically applied in a CER will need to be varied to suit the project requirements. At the conclusion of the CER a comprehensive traffic light matrix (see image below) can be provided as part of the report, outlining the critical issues and providing recommendations for improvement. The process is focused on advice that can be actioned to produce improved results. Outcome of recent reviews About the Author Magued Moftah is an Executive Advisor with E3 Advisory Pty Ltd. He has a proven track record in leadership and management spanning 40 years in engineering projects and business management. He has extensive experience managing contracts in the infrastructure, rail, oil and gas, mining, water and waste water and power sectors. Magued has been responsible for leading and managing Cold Eyed Reviews, asset acquisitions, technical and commercial due diligence and contract resolution mediation and disputation activities. Advisian / 1 SUB-ELEMENT MINIMUM REQUIREMENT NOTE • Key supply and demand drivers Detailed assessment and evaluation.• Revenue growth factors • Industry structures • Diversity of suppliers and customers • Forecast project position – when operational • Price assumption • Historical and forecast margins • Value adding sources, historically and forecast Demonstrated position • Project’s ability to exploit these opportunities • Fits with overall strategy Demonstrated position • Review of the relationship between the project and business strategy • Strategic alternatives including exit /no go option Detailedwithin available envelope of data• Basis of potential project being best option • Potential of phased development • Scenario development process Basedon recommended project • Driver to execute exit strategy Fullydeveloped strategy • Triggers for exit decision Strategy CRITICAL AND URGENT Immediate action on identified shortcomings and recommendations is required to achieve success of the project IMPORTANT AND URGENT The project should go forward with action on recommendations IMPORTANT AND OF BENEFIT The program or project may benefit from implementation or recommendations Industry Attractiveness Strategic Rationale Strategic Fit Strategic Alternatives Scen ario An alysis Exit Strategy Comprehensive traffic light matrix (example)