Appendix 14.1
PERT and PERT simulation
PERT—PROGRAM EVALUATION AND REVIEW TECHNIQUE
In 1958 the Special Office of the Navy and the Booze, Allen and Hamilton consulting firm developed
PERT (program evaluation and review technique) to schedule the more than 3300 contractors of the
Polaris submarine project and to cover uncertainty of activity time estimates.
PERT is almost identical to the critical path method (CPM) technique except it assumes each
activity duration has a range that follows a statistical distribution. PERT uses three time estimates
for each activity. Basically, this means each activity duration can range from an optimistic time to a
pessimistic time, and a weighted average can be computed for each activity. Because project activities
usually represent work, and because work tends to stay behind once it gets behind, the PERT
developers chose an approximation of the beta distribution to represent activity durations. This
distribution is known to be flexible and can accommodate empirical data that do not follow a normal
distribution. The activity durations can be skewed more toward the high or low end of the data
range. Figure A14.1A depicts a beta distribution for activity durations that is skewed toward the
right and is representative of work that tends to stay late once it is behind. The distribution for the
project duration is represented by a normal (symmetrical) distribution shown in Figure A14.1B. The
project distribution represents the sum of the weighted averages of the activities on the critical
path(s).
FIGURE A14.1 Activity and project frequency distributions
Knowing the weighted average and variances for each activity allows the project planner to
compute the probability of meeting different project durations. Follow the steps described in the
hypothetical example given next. (The jargon is difficult for those not familiar with statistics, but the
process is relatively simple after working through a couple of examples.)
The weighted average activity time is computed by the following formula:
6
4 bma
te
++
= (14.1)
where:
te = weighted average activity time
a = optimistic activity time (1 chance in 100 of completing the activity earlier under normal
Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray
Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 1
conditions)
b = pessimistic activity time (1 chance in 100 of completing the activity later under normal
conditions)
m = most likely activity time.
When the three time estimates have been specified, this equation is used to compute the
weighted average duration for each activity. The average (deterministic) value is placed on the
project network as in the CPM method and the early, late, slack and project completion times are
computed as they are in the CPM method.
The variability in the activity time estimates is approximated by the following equations:
Equation 14.2 represents the standard deviation for the activity. Equation 14.3 represents the
standard deviation for the project. Note the standard deviation of the activity is squared in this
equation; this is also called variance. This sum includes only activities on the critical path(s) or path
being reviewed.





 −
=
6
ab
etσ (14.2)
2
eE tT σσ Σ= (14.3)
Finally, the average project duration (TE) is the sum of all the average activity times along the
critical path (sum of te), and it follows a normal distribution.
Knowing the average project duration and the variances of activities allows the probability of
completing the project (or segment of the project) by a specific time to be computed using standard
statistical tables. The equation below (Equation 14.4) is used to compute the ‘Z’ value found in
statistical tables (Z = number of standard deviations from the mean), which, in turn, tells the
probability of completing the project in the time specified.
2
et
ES TT
Z
σΣ
−
=
(14.4)
where:
TE = critical path duration
TS = scheduled project duration
Z = probability (of meeting scheduled duration) found in statistical Table A14.2
A hypothetical example using the PERT technique
The activity times and variances are given in Table A14.1. The project network is presented in Figure
A14.2. This figure shows the project network as AOA and AON. The AON network is presented as a
reminder that PERT can use AON networks as well as AOA.
Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray
Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 2
TABLE A14.1 Activity times and variances
FIGURE A14.2 Hypothetical network
The expected project duration (TE) is 64 time units; the critical path is 1-2-3-5-6. With this
information, the probability of completing the project by a specific date can easily be computed using
standard statistical methods. For example, what is the probability the project will be completed
before a scheduled time (TS) of 67? The normal curve for the project would appear as shown in
Figure A14.3.
Using the formula for the Z value, the probability can be computed as follows:
Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray
Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 3
69.0
50.0
36
3
11925
6467
2
=
+=
+
=
+++
−
=
Σ
−
=
P
TT
Z
et
ES
σ
FIGURE A14.3 Possible project durations
Reading from Table A14.2, a Z value of +0.5 gives a probability of 0.69, which is interpreted to
mean there is a 69 per cent chance of completing the project on or before 67 time units.
Conversely, the probability of completing the project by time period 60 is computed as follows:
26.0
67.0
36
4
11925
6460
≈
−=
−
=
+++
−
=
P
Z
From Table A14.2, a Z value of –0.67 gives an approximate probability of 0.26, which is
interpreted to mean there is about a 26 per cent chance of completing the project on or before 60
time units. Note that this same type of calculation can be made for any path or segment of a path in
the network.
Table A14.2 Z Values and probabilities
Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray
Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 4
When such probabilities are available to management, trade-off decisions can be made to accept
or reduce the risk associated with a particular project duration. For example, if the project manager
wishes to improve the chances of completing the project by 64 time units, at least two choices are
available. First, management can spend money up front to change conditions that will reduce the
duration of one or more activities on the critical path. A more prudent, second alternative would be
to allocate money to a contingency fund and wait to see how the project is progressing as it is
implemented.
APPENDIX 14.1 EXERCISES
1. Given the project information below, what is the probability of completing the National Holiday
Toy project in 93 time units?
Act.
ID
Description Predece
ssor
Optm
. (a)
Most
likely (m)
Pess.
(b)
Act time te Variance
[(b 2 a)/6]2
Critical
1 Design
package
None  6 12 24
2 Design
product
1 16 19 28
3 Build package 1  4  7 10
4 Secure patent 2 21 30 39
5 Build product 2 17 29 47
6 Paint 3, 4, 5  4  7 10
7 Test market 6 13 16 19
2. The Global Tea and Organic Juice companies have merged.
The following information has been collected for the ‘Consolidation Project.’
Activity Description Predecessor a opt m ml b pess
1 Codify accounts None 16 19 28
2 File articles of unification None 30 30  30
3 Unify price and credit policy None 60 72  90
Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray
Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 5
4 Unify personnel policies None 18 27  30
5 Unify data processing 1 17 29  47
6 Train accounting staff 1  4  7  10
7 Pilot run data processing 5 12 15  18
8 Calculate P&L and balance sheet 6, 7  6 12  24
9 Transfer real property 2 18 27  30
10 Train sales force 3 20 35  50
11 Negotiate with unions 4 40 55 100
12 Determine capital needs 8 11 20  29
13 Explain personnel policies 11 14 23  26
14 Secure line of credit 9, 12 13 16  19
15 End 10, 12, 14  0  0   0
a) Compute the expected time for each activity.
b) Compute the variance for each activity.
c) Compute the expected project duration.
d) What is the probability of completing the project by day 112? Within 116 days?
e) What is the probability of completing ‘Negotiate with Unions’ by day 90?
Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray
Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 6
3. The expected times and variances for the project activities are given below. What is the
probability of completing the project in 25 periods?
Variance
ID
Description Predecessor te [(b 2 a)/6]2
1 Pilot production None 6 3
2 Select channels of distrib. None 7 4
3 Develop mktg. program None 4 2
4 Test market 1 4 2
5 Patent 1 10 5
6 Full production 4 16 10
7 Ad promotion 3 3 2
8 Release 2, 5, 6, 7 2 1
Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray
Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 7

Weitere ähnliche Inhalte

Was ist angesagt?

Chronological Decomposition Heuristic: A Temporal Divide-and-Conquer Strateg...
Chronological Decomposition Heuristic:  A Temporal Divide-and-Conquer Strateg...Chronological Decomposition Heuristic:  A Temporal Divide-and-Conquer Strateg...
Chronological Decomposition Heuristic: A Temporal Divide-and-Conquer Strateg...
Alkis Vazacopoulos
 

Was ist angesagt? (18)

Ieeepro techno solutions 2014 ieee java project - a hyper-heuristic scheduling
Ieeepro techno solutions   2014 ieee java project - a hyper-heuristic schedulingIeeepro techno solutions   2014 ieee java project - a hyper-heuristic scheduling
Ieeepro techno solutions 2014 ieee java project - a hyper-heuristic scheduling
 
Deep Learning and Optimization Methods
Deep Learning and Optimization MethodsDeep Learning and Optimization Methods
Deep Learning and Optimization Methods
 
352735340 rsh-qam11-tif-12-doc
352735340 rsh-qam11-tif-12-doc352735340 rsh-qam11-tif-12-doc
352735340 rsh-qam11-tif-12-doc
 
Chronological Decomposition Heuristic: A Temporal Divide-and-Conquer Strateg...
Chronological Decomposition Heuristic:  A Temporal Divide-and-Conquer Strateg...Chronological Decomposition Heuristic:  A Temporal Divide-and-Conquer Strateg...
Chronological Decomposition Heuristic: A Temporal Divide-and-Conquer Strateg...
 
Resource Leveling Considering Float Consumption Impact
Resource Leveling Considering Float Consumption ImpactResource Leveling Considering Float Consumption Impact
Resource Leveling Considering Float Consumption Impact
 
ملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريعملاحظات مهمة عن تعجيل المشاريع
ملاحظات مهمة عن تعجيل المشاريع
 
50120130406040
5012013040604050120130406040
50120130406040
 
Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...Optimization of Time Restriction in Construction Project Management Using Lin...
Optimization of Time Restriction in Construction Project Management Using Lin...
 
Grasp approach to rcpsp with min max robustness objective
Grasp approach to rcpsp with min max robustness objectiveGrasp approach to rcpsp with min max robustness objective
Grasp approach to rcpsp with min max robustness objective
 
Evolutionary Multi-Goal Workflow Progress in Shade
Evolutionary  Multi-Goal Workflow Progress in ShadeEvolutionary  Multi-Goal Workflow Progress in Shade
Evolutionary Multi-Goal Workflow Progress in Shade
 
Project scope preparation
Project scope preparationProject scope preparation
Project scope preparation
 
Probabilistic project sizing using Randomized Branch Sampling (RBS)
Probabilistic project sizing using Randomized Branch Sampling (RBS)Probabilistic project sizing using Randomized Branch Sampling (RBS)
Probabilistic project sizing using Randomized Branch Sampling (RBS)
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
PERT
PERTPERT
PERT
 
Paper18
Paper18Paper18
Paper18
 
Ieeepro techno solutions ieee java project - budget-driven scheduling algor...
Ieeepro techno solutions   ieee java project - budget-driven scheduling algor...Ieeepro techno solutions   ieee java project - budget-driven scheduling algor...
Ieeepro techno solutions ieee java project - budget-driven scheduling algor...
 
A New Approach for Job Scheduling Using Hybrid GA-ST Optimization-Crimson Pub...
A New Approach for Job Scheduling Using Hybrid GA-ST Optimization-Crimson Pub...A New Approach for Job Scheduling Using Hybrid GA-ST Optimization-Crimson Pub...
A New Approach for Job Scheduling Using Hybrid GA-ST Optimization-Crimson Pub...
 
RTS
RTSRTS
RTS
 

Ähnlich wie Pearson1e ch14 appendix_14_1

PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
Snehal Athawale
 
CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx
CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docxCASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx
CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx
troutmanboris
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
hannahpepino1
 

Ähnlich wie Pearson1e ch14 appendix_14_1 (20)

PERT.pptx
PERT.pptxPERT.pptx
PERT.pptx
 
CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx
CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docxCASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx
CASeexAMPlegeneRAlAvIATIOnhAngARReSTORATIOnI n t r.docx
 
Cpm module iii reference
Cpm module iii referenceCpm module iii reference
Cpm module iii reference
 
Ii. pert cpm
Ii. pert cpmIi. pert cpm
Ii. pert cpm
 
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)(PROGRAM EVALUATION AND REVIE TECHNIQUE)
(PROGRAM EVALUATION AND REVIE TECHNIQUE)
 
Pert Analysis
Pert AnalysisPert Analysis
Pert Analysis
 
Programme Evaluation and Review Technique
Programme Evaluation and Review TechniqueProgramme Evaluation and Review Technique
Programme Evaluation and Review Technique
 
Basics CPM&PERT.ppt
Basics CPM&PERT.pptBasics CPM&PERT.ppt
Basics CPM&PERT.ppt
 
CPM-PERT.ppt
CPM-PERT.pptCPM-PERT.ppt
CPM-PERT.ppt
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
 
Per tand project crashing
Per tand project crashingPer tand project crashing
Per tand project crashing
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
13 project management
13 project management13 project management
13 project management
 
Project management
Project managementProject management
Project management
 
Lec 10 pert estimating techniques
Lec 10 pert estimating techniquesLec 10 pert estimating techniques
Lec 10 pert estimating techniques
 
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...IRJET- 	  Comparative Analysis between Critical Path Method and Monte Carlo S...
IRJET- Comparative Analysis between Critical Path Method and Monte Carlo S...
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing Algorithm
 
Pert and CPM
Pert and CPMPert and CPM
Pert and CPM
 
Cpm n pert
Cpm n pertCpm n pert
Cpm n pert
 
PERT
PERTPERT
PERT
 

Kürzlich hochgeladen

Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
AnaAcapella
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
ssuserdda66b
 

Kürzlich hochgeladen (20)

Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdfVishram Singh - Textbook of Anatomy  Upper Limb and Thorax.. Volume 1 (1).pdf
Vishram Singh - Textbook of Anatomy Upper Limb and Thorax.. Volume 1 (1).pdf
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 

Pearson1e ch14 appendix_14_1

  • 1. Appendix 14.1 PERT and PERT simulation PERT—PROGRAM EVALUATION AND REVIEW TECHNIQUE In 1958 the Special Office of the Navy and the Booze, Allen and Hamilton consulting firm developed PERT (program evaluation and review technique) to schedule the more than 3300 contractors of the Polaris submarine project and to cover uncertainty of activity time estimates. PERT is almost identical to the critical path method (CPM) technique except it assumes each activity duration has a range that follows a statistical distribution. PERT uses three time estimates for each activity. Basically, this means each activity duration can range from an optimistic time to a pessimistic time, and a weighted average can be computed for each activity. Because project activities usually represent work, and because work tends to stay behind once it gets behind, the PERT developers chose an approximation of the beta distribution to represent activity durations. This distribution is known to be flexible and can accommodate empirical data that do not follow a normal distribution. The activity durations can be skewed more toward the high or low end of the data range. Figure A14.1A depicts a beta distribution for activity durations that is skewed toward the right and is representative of work that tends to stay late once it is behind. The distribution for the project duration is represented by a normal (symmetrical) distribution shown in Figure A14.1B. The project distribution represents the sum of the weighted averages of the activities on the critical path(s). FIGURE A14.1 Activity and project frequency distributions Knowing the weighted average and variances for each activity allows the project planner to compute the probability of meeting different project durations. Follow the steps described in the hypothetical example given next. (The jargon is difficult for those not familiar with statistics, but the process is relatively simple after working through a couple of examples.) The weighted average activity time is computed by the following formula: 6 4 bma te ++ = (14.1) where: te = weighted average activity time a = optimistic activity time (1 chance in 100 of completing the activity earlier under normal Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 1
  • 2. conditions) b = pessimistic activity time (1 chance in 100 of completing the activity later under normal conditions) m = most likely activity time. When the three time estimates have been specified, this equation is used to compute the weighted average duration for each activity. The average (deterministic) value is placed on the project network as in the CPM method and the early, late, slack and project completion times are computed as they are in the CPM method. The variability in the activity time estimates is approximated by the following equations: Equation 14.2 represents the standard deviation for the activity. Equation 14.3 represents the standard deviation for the project. Note the standard deviation of the activity is squared in this equation; this is also called variance. This sum includes only activities on the critical path(s) or path being reviewed.       − = 6 ab etσ (14.2) 2 eE tT σσ Σ= (14.3) Finally, the average project duration (TE) is the sum of all the average activity times along the critical path (sum of te), and it follows a normal distribution. Knowing the average project duration and the variances of activities allows the probability of completing the project (or segment of the project) by a specific time to be computed using standard statistical tables. The equation below (Equation 14.4) is used to compute the ‘Z’ value found in statistical tables (Z = number of standard deviations from the mean), which, in turn, tells the probability of completing the project in the time specified. 2 et ES TT Z σΣ − = (14.4) where: TE = critical path duration TS = scheduled project duration Z = probability (of meeting scheduled duration) found in statistical Table A14.2 A hypothetical example using the PERT technique The activity times and variances are given in Table A14.1. The project network is presented in Figure A14.2. This figure shows the project network as AOA and AON. The AON network is presented as a reminder that PERT can use AON networks as well as AOA. Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 2
  • 3. TABLE A14.1 Activity times and variances FIGURE A14.2 Hypothetical network The expected project duration (TE) is 64 time units; the critical path is 1-2-3-5-6. With this information, the probability of completing the project by a specific date can easily be computed using standard statistical methods. For example, what is the probability the project will be completed before a scheduled time (TS) of 67? The normal curve for the project would appear as shown in Figure A14.3. Using the formula for the Z value, the probability can be computed as follows: Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 3
  • 4. 69.0 50.0 36 3 11925 6467 2 = += + = +++ − = Σ − = P TT Z et ES σ FIGURE A14.3 Possible project durations Reading from Table A14.2, a Z value of +0.5 gives a probability of 0.69, which is interpreted to mean there is a 69 per cent chance of completing the project on or before 67 time units. Conversely, the probability of completing the project by time period 60 is computed as follows: 26.0 67.0 36 4 11925 6460 ≈ −= − = +++ − = P Z From Table A14.2, a Z value of –0.67 gives an approximate probability of 0.26, which is interpreted to mean there is about a 26 per cent chance of completing the project on or before 60 time units. Note that this same type of calculation can be made for any path or segment of a path in the network. Table A14.2 Z Values and probabilities Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 4
  • 5. When such probabilities are available to management, trade-off decisions can be made to accept or reduce the risk associated with a particular project duration. For example, if the project manager wishes to improve the chances of completing the project by 64 time units, at least two choices are available. First, management can spend money up front to change conditions that will reduce the duration of one or more activities on the critical path. A more prudent, second alternative would be to allocate money to a contingency fund and wait to see how the project is progressing as it is implemented. APPENDIX 14.1 EXERCISES 1. Given the project information below, what is the probability of completing the National Holiday Toy project in 93 time units? Act. ID Description Predece ssor Optm . (a) Most likely (m) Pess. (b) Act time te Variance [(b 2 a)/6]2 Critical 1 Design package None  6 12 24 2 Design product 1 16 19 28 3 Build package 1  4  7 10 4 Secure patent 2 21 30 39 5 Build product 2 17 29 47 6 Paint 3, 4, 5  4  7 10 7 Test market 6 13 16 19 2. The Global Tea and Organic Juice companies have merged. The following information has been collected for the ‘Consolidation Project.’ Activity Description Predecessor a opt m ml b pess 1 Codify accounts None 16 19 28 2 File articles of unification None 30 30  30 3 Unify price and credit policy None 60 72  90 Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 5
  • 6. 4 Unify personnel policies None 18 27  30 5 Unify data processing 1 17 29  47 6 Train accounting staff 1  4  7  10 7 Pilot run data processing 5 12 15  18 8 Calculate P&L and balance sheet 6, 7  6 12  24 9 Transfer real property 2 18 27  30 10 Train sales force 3 20 35  50 11 Negotiate with unions 4 40 55 100 12 Determine capital needs 8 11 20  29 13 Explain personnel policies 11 14 23  26 14 Secure line of credit 9, 12 13 16  19 15 End 10, 12, 14  0  0   0 a) Compute the expected time for each activity. b) Compute the variance for each activity. c) Compute the expected project duration. d) What is the probability of completing the project by day 112? Within 116 days? e) What is the probability of completing ‘Negotiate with Unions’ by day 90? Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 6
  • 7. 3. The expected times and variances for the project activities are given below. What is the probability of completing the project in 25 periods? Variance ID Description Predecessor te [(b 2 a)/6]2 1 Pilot production None 6 3 2 Select channels of distrib. None 7 4 3 Develop mktg. program None 4 2 4 Test market 1 4 2 5 Patent 1 10 5 6 Full production 4 16 10 7 Ad promotion 3 3 2 8 Release 2, 5, 6, 7 2 1 Appendix t/a Project Management in Practice by N Pearson, EW Larson, CF Gray Copyright ©2013 McGraw-Hill Education (Australia) Pty Ltd Page 7