Project Costs
Management
Sections of this presentation were adapted from A Guide to
the Project Management Body of Knowledge 6th Edition,
Dr. M.K. Mlela
Cost Management Overview
•Key Concepts & Terms
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Control Costs
Key Concepts & Terms
•Project Cost Management
•Project Cost Management Processes
•Key Terms
•Trends & Emerging Practices
•Tailoring Considerations
•Considerations for Adaptive Environment
Project Cost Management
Project cost management is the processes
involved in planning, estimating, budgeting,
financing, funding, managing, and controlling
costs so that the project can be completed
within the approved budget.
Project Cost Management Processes
• Plan Cost Management
• Estimate Costs
• Determine Budget
• Control Costs
Estimate
Costs
Determine
Budget
Cost Control
Plan Cost
Management
Key Terms
• Earned value management (EVM): a project
management technique for measuring project
performance and progress based on the
comparison of work performed and work planned.
• Life cycle costing: the concept of looking at cost
over the entire life of the product, not just the cost of
the project to create the product.
• Value analysis (value engineering): the concept
that focuses on finding a less costly way to do the
same work.
• Cost risk: cost-related risks.
Key Terms (continued)
• Types of costs:
o Variable costs: costs that change with the amount of
work.
o Fixed costs: costs that do not change with the amount
of work.
o Direct costs: costs directly attributable to the work on
the project
o Indirect costs: overhead items or costs incurred for
the benefit of more than one projects.
Key Terms (continued)
• Cost estimate ranges:
o Rough order of magnitude (ROM): used during project
initiating; typical range -25 to +75 percent.
o Budget estimate: when starting the plan iteration; typical
range -10 to +25 percent.
o Definitive estimate: as progress planning progresses;
typical range Âą 10 percent or -5 to +10 percent.
Trends & Emerging Practices
•Expansion of EVM to include the concept of earned
schedule (ES)
 The common practice is to use EVM to evaluate the status of project
cost and forecast the project's cost at completion while using CPM to
evaluate the status of project schedule and forecast the project's
completion time.
 The Earned Schedule (ES) allows EVM metrics to be transformed to
time or duration metrics to enhance the evaluation of project
schedule performance and to forecast the duration needed to
complete the project.
•The Earned Value Management (EVM) and the
Critical Path Method (CPM) are widely accepted
methods and are often used simultaneously to
evaluate project performance.
Tailoring Considerations
• Knowledge management
Knowledge management is the process by which an enterprise gathers, organizes,
shares and analyzes its knowledge in a way that is easily accessible to
Client/stakeholders.
Knowledge management involves data mining and some method of operation to
push information to users to make it easily accessible.
Does the organization have a formal knowledge management and financial
database repository that a project manager is required to use and that is readily
accessible?
• Estimating and budgeting
process of approximating the total expenditure of the project.
Does the organization have existing formal or informal cost estimating and
budgeting-related policies, procedures, and guidelines?
• Earned value management
Earned Value Management (EVM) is a project performance
management methodology that integrates cost, schedule,
technical scope, and risk to assess progress against a baseline, use
that information to identify problems, and forecast cost (and, to a
certain extent, schedule) at completion.
Does the organization use earned value management in managing
projects?
Use of agile approach. Does the organization use agile methodologies in
managing projects? How does this impact cost estimating?
Governance. Does the organization have formal or informal audit and
governance policies, procedures, and guidelines?
Tailoring Considerations
Plan Cost Management
Plan Cost Management is the process of defining how the project costs
will be estimated, budgeted, managed, monitored, and controlled.
Estimate
Costs
Determine
Budget
Cost Control
Plan Cost
Management
Plan Cost Management: Data Flow Diagram
Plan Cost Management
Estimate Costs
Process of developing an approximation of the cost of resources needed to complete
project work. The key benefit of this process is that it determines the monetary
resources required for the project. This process is performed periodically throughout
the project as needed.
Estimate
Costs
Determine
Budget
Cost Control
Plan Cost
Management
Estimate Costs: Data Flow Diagram
Estimate Costs
Determine Budget
Estimate
Costs
Determine
Budget
Cost Control
Plan Cost
Management
Process of aggregating the estimated costs of individual activities or work
packages to establish an authorized cost baseline.
A
a
Determine Budget
Determine Budget: Data Flow Diagram
Control Costs
Estimate
Costs
Determine
Budget
Cost Control
Plan Cost
Management
Control Costs is the process of monitoring the status of the project to update the project costs
and managing changes to the cost baseline. The key benefit of this process is that the cost
baseline is maintained throughout the project.
Control Costs
Control Costs: Data Flow Diagram
L4_Cost Management.ppt

Weitere ähnliche Inhalte

Ähnlich wie L4_Cost Management.ppt

Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfVarunSubramanyam
 
project management f.pptx
project management f.pptxproject management f.pptx
project management f.pptxJoshKoros
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaGlobalSkillup
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting EngagementSaumya Ganguly
 
PMP Module 4 - Cost
PMP Module 4 - CostPMP Module 4 - Cost
PMP Module 4 - CostCybrary
 
project cost management.pptx
project cost management.pptxproject cost management.pptx
project cost management.pptxInayatSheikh1
 
New Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program AssuranceNew Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program AssuranceSusan Schanta
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfHuyNguyen657394
 
Project Execution and Project management (GT IV batch) 2.pptx
Project Execution and Project management (GT IV batch) 2.pptxProject Execution and Project management (GT IV batch) 2.pptx
Project Execution and Project management (GT IV batch) 2.pptxbhanu852126
 
project control.pptx
project control.pptxproject control.pptx
project control.pptxAlkaPandya5
 
AI in Project Management.pdf
AI in Project Management.pdfAI in Project Management.pdf
AI in Project Management.pdfJamieDornan2
 
1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx gggggggggggggggggadabotor7
 
Beyond PMP: Integration Management
Beyond PMP: Integration ManagementBeyond PMP: Integration Management
Beyond PMP: Integration Managementabhinayverma
 

Ähnlich wie L4_Cost Management.ppt (20)

Chap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdfChap05_Project Monitoring and Control.pdf
Chap05_Project Monitoring and Control.pdf
 
project management f.pptx
project management f.pptxproject management f.pptx
project management f.pptx
 
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge AreaOnline PMP Training Material for PMP Exam - Cost Management Knowledge Area
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
 
Managing the Consulting Engagement
Managing the Consulting EngagementManaging the Consulting Engagement
Managing the Consulting Engagement
 
PMP Module 4 - Cost
PMP Module 4 - CostPMP Module 4 - Cost
PMP Module 4 - Cost
 
Cost
CostCost
Cost
 
Cost
CostCost
Cost
 
project cost management.pptx
project cost management.pptxproject cost management.pptx
project cost management.pptx
 
New Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program AssuranceNew Techniques to Elevate QA to Program Assurance
New Techniques to Elevate QA to Program Assurance
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 
Project Execution and Project management (GT IV batch) 2.pptx
Project Execution and Project management (GT IV batch) 2.pptxProject Execution and Project management (GT IV batch) 2.pptx
Project Execution and Project management (GT IV batch) 2.pptx
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
project control.pptx
project control.pptxproject control.pptx
project control.pptx
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
 
AI in Project Management.pdf
AI in Project Management.pdfAI in Project Management.pdf
AI in Project Management.pdf
 
1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg1 ch 1 Project CM.pptx ggggggggggggggggg
1 ch 1 Project CM.pptx ggggggggggggggggg
 
Beyond PMP: Integration Management
Beyond PMP: Integration ManagementBeyond PMP: Integration Management
Beyond PMP: Integration Management
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
2) PMT & PIM.pptx
2) PMT & PIM.pptx2) PMT & PIM.pptx
2) PMT & PIM.pptx
 
P ex cost management-1
P ex cost management-1P ex cost management-1
P ex cost management-1
 

Mehr von MUST

Lecture 4-ELECTRIC MOTORS-ACTUATION SYSTEMS2.ppt
Lecture 4-ELECTRIC MOTORS-ACTUATION SYSTEMS2.pptLecture 4-ELECTRIC MOTORS-ACTUATION SYSTEMS2.ppt
Lecture 4-ELECTRIC MOTORS-ACTUATION SYSTEMS2.pptMUST
 
NYQUIST_PLOTS.pdf
NYQUIST_PLOTS.pdfNYQUIST_PLOTS.pdf
NYQUIST_PLOTS.pdfMUST
 
ME451_L10_RouthHurwitz.pdf
ME451_L10_RouthHurwitz.pdfME451_L10_RouthHurwitz.pdf
ME451_L10_RouthHurwitz.pdfMUST
 
LECTURE 1. Control Systems Engineering_MEB 4101.pdf
LECTURE 1. Control Systems Engineering_MEB 4101.pdfLECTURE 1. Control Systems Engineering_MEB 4101.pdf
LECTURE 1. Control Systems Engineering_MEB 4101.pdfMUST
 
Stability criteria and Analysis_Control Systems Engineering_MEB 4101.pdf
Stability criteria and Analysis_Control Systems Engineering_MEB 4101.pdfStability criteria and Analysis_Control Systems Engineering_MEB 4101.pdf
Stability criteria and Analysis_Control Systems Engineering_MEB 4101.pdfMUST
 
LECTURE 3_On-off_Control Systems Engineering_MEB 4101.pptx
LECTURE 3_On-off_Control Systems Engineering_MEB 4101.pptxLECTURE 3_On-off_Control Systems Engineering_MEB 4101.pptx
LECTURE 3_On-off_Control Systems Engineering_MEB 4101.pptxMUST
 
LECTURE 4. Stability criteria and Analysis_Control Systems Engineering_MEB 41...
LECTURE 4. Stability criteria and Analysis_Control Systems Engineering_MEB 41...LECTURE 4. Stability criteria and Analysis_Control Systems Engineering_MEB 41...
LECTURE 4. Stability criteria and Analysis_Control Systems Engineering_MEB 41...MUST
 
2 Robot Actuators and drive systems.ppt
2 Robot Actuators and drive systems.ppt2 Robot Actuators and drive systems.ppt
2 Robot Actuators and drive systems.pptMUST
 
ON-OFF CONTROL (2).ppt
ON-OFF CONTROL (2).pptON-OFF CONTROL (2).ppt
ON-OFF CONTROL (2).pptMUST
 
L7_PROJECT PROCUREMENT Management.pdf
L7_PROJECT PROCUREMENT Management.pdfL7_PROJECT PROCUREMENT Management.pdf
L7_PROJECT PROCUREMENT Management.pdfMUST
 
L8_PROJECT CONTRACT Management.ppt
L8_PROJECT CONTRACT Management.pptL8_PROJECT CONTRACT Management.ppt
L8_PROJECT CONTRACT Management.pptMUST
 
Project procurement Management.ppt
Project procurement Management.pptProject procurement Management.ppt
Project procurement Management.pptMUST
 
PROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfPROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfMUST
 
pmp11-risk-180412035349-2.pdf
pmp11-risk-180412035349-2.pdfpmp11-risk-180412035349-2.pdf
pmp11-risk-180412035349-2.pdfMUST
 
2nd_order.pdf
2nd_order.pdf2nd_order.pdf
2nd_order.pdfMUST
 
History of Robotics.ppt
History of Robotics.pptHistory of Robotics.ppt
History of Robotics.pptMUST
 
Machine Vision Systems.pptx
Machine Vision Systems.pptxMachine Vision Systems.pptx
Machine Vision Systems.pptxMUST
 
Project Human Resources Management.ppt
Project Human Resources Management.pptProject Human Resources Management.ppt
Project Human Resources Management.pptMUST
 
Robot actuation and feedback components.pptx
Robot actuation and feedback components.pptxRobot actuation and feedback components.pptx
Robot actuation and feedback components.pptxMUST
 
Contract management.ppt
Contract management.pptContract management.ppt
Contract management.pptMUST
 

Mehr von MUST (20)

Lecture 4-ELECTRIC MOTORS-ACTUATION SYSTEMS2.ppt
Lecture 4-ELECTRIC MOTORS-ACTUATION SYSTEMS2.pptLecture 4-ELECTRIC MOTORS-ACTUATION SYSTEMS2.ppt
Lecture 4-ELECTRIC MOTORS-ACTUATION SYSTEMS2.ppt
 
NYQUIST_PLOTS.pdf
NYQUIST_PLOTS.pdfNYQUIST_PLOTS.pdf
NYQUIST_PLOTS.pdf
 
ME451_L10_RouthHurwitz.pdf
ME451_L10_RouthHurwitz.pdfME451_L10_RouthHurwitz.pdf
ME451_L10_RouthHurwitz.pdf
 
LECTURE 1. Control Systems Engineering_MEB 4101.pdf
LECTURE 1. Control Systems Engineering_MEB 4101.pdfLECTURE 1. Control Systems Engineering_MEB 4101.pdf
LECTURE 1. Control Systems Engineering_MEB 4101.pdf
 
Stability criteria and Analysis_Control Systems Engineering_MEB 4101.pdf
Stability criteria and Analysis_Control Systems Engineering_MEB 4101.pdfStability criteria and Analysis_Control Systems Engineering_MEB 4101.pdf
Stability criteria and Analysis_Control Systems Engineering_MEB 4101.pdf
 
LECTURE 3_On-off_Control Systems Engineering_MEB 4101.pptx
LECTURE 3_On-off_Control Systems Engineering_MEB 4101.pptxLECTURE 3_On-off_Control Systems Engineering_MEB 4101.pptx
LECTURE 3_On-off_Control Systems Engineering_MEB 4101.pptx
 
LECTURE 4. Stability criteria and Analysis_Control Systems Engineering_MEB 41...
LECTURE 4. Stability criteria and Analysis_Control Systems Engineering_MEB 41...LECTURE 4. Stability criteria and Analysis_Control Systems Engineering_MEB 41...
LECTURE 4. Stability criteria and Analysis_Control Systems Engineering_MEB 41...
 
2 Robot Actuators and drive systems.ppt
2 Robot Actuators and drive systems.ppt2 Robot Actuators and drive systems.ppt
2 Robot Actuators and drive systems.ppt
 
ON-OFF CONTROL (2).ppt
ON-OFF CONTROL (2).pptON-OFF CONTROL (2).ppt
ON-OFF CONTROL (2).ppt
 
L7_PROJECT PROCUREMENT Management.pdf
L7_PROJECT PROCUREMENT Management.pdfL7_PROJECT PROCUREMENT Management.pdf
L7_PROJECT PROCUREMENT Management.pdf
 
L8_PROJECT CONTRACT Management.ppt
L8_PROJECT CONTRACT Management.pptL8_PROJECT CONTRACT Management.ppt
L8_PROJECT CONTRACT Management.ppt
 
Project procurement Management.ppt
Project procurement Management.pptProject procurement Management.ppt
Project procurement Management.ppt
 
PROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdfPROJECT RISK MANAGEMENT.pdf
PROJECT RISK MANAGEMENT.pdf
 
pmp11-risk-180412035349-2.pdf
pmp11-risk-180412035349-2.pdfpmp11-risk-180412035349-2.pdf
pmp11-risk-180412035349-2.pdf
 
2nd_order.pdf
2nd_order.pdf2nd_order.pdf
2nd_order.pdf
 
History of Robotics.ppt
History of Robotics.pptHistory of Robotics.ppt
History of Robotics.ppt
 
Machine Vision Systems.pptx
Machine Vision Systems.pptxMachine Vision Systems.pptx
Machine Vision Systems.pptx
 
Project Human Resources Management.ppt
Project Human Resources Management.pptProject Human Resources Management.ppt
Project Human Resources Management.ppt
 
Robot actuation and feedback components.pptx
Robot actuation and feedback components.pptxRobot actuation and feedback components.pptx
Robot actuation and feedback components.pptx
 
Contract management.ppt
Contract management.pptContract management.ppt
Contract management.ppt
 

KĂźrzlich hochgeladen

GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningCIToolkit
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Smisbafathima9940
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxSaqib Mansoor Ahmed
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementTulsiDhidhi1
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 

KĂźrzlich hochgeladen (20)

GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima S
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Does Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptxDoes Leadership Possible Without a Vision.pptx
Does Leadership Possible Without a Vision.pptx
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 
operational plan ppt.pptx nursing management
operational plan ppt.pptx nursing managementoperational plan ppt.pptx nursing management
operational plan ppt.pptx nursing management
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote SpeakerLeadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
Leadership in Crisis - Helio Vogas, Risk & Leadership Keynote Speaker
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 

L4_Cost Management.ppt

  • 1. Project Costs Management Sections of this presentation were adapted from A Guide to the Project Management Body of Knowledge 6th Edition, Dr. M.K. Mlela
  • 2. Cost Management Overview •Key Concepts & Terms •Plan Cost Management •Estimate Costs •Determine Budget •Control Costs
  • 3. Key Concepts & Terms •Project Cost Management •Project Cost Management Processes •Key Terms •Trends & Emerging Practices •Tailoring Considerations •Considerations for Adaptive Environment
  • 4. Project Cost Management Project cost management is the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget.
  • 5. Project Cost Management Processes • Plan Cost Management • Estimate Costs • Determine Budget • Control Costs Estimate Costs Determine Budget Cost Control Plan Cost Management
  • 6. Key Terms • Earned value management (EVM): a project management technique for measuring project performance and progress based on the comparison of work performed and work planned. • Life cycle costing: the concept of looking at cost over the entire life of the product, not just the cost of the project to create the product. • Value analysis (value engineering): the concept that focuses on finding a less costly way to do the same work. • Cost risk: cost-related risks.
  • 7. Key Terms (continued) • Types of costs: o Variable costs: costs that change with the amount of work. o Fixed costs: costs that do not change with the amount of work. o Direct costs: costs directly attributable to the work on the project o Indirect costs: overhead items or costs incurred for the benefit of more than one projects.
  • 8. Key Terms (continued) • Cost estimate ranges: o Rough order of magnitude (ROM): used during project initiating; typical range -25 to +75 percent. o Budget estimate: when starting the plan iteration; typical range -10 to +25 percent. o Definitive estimate: as progress planning progresses; typical range Âą 10 percent or -5 to +10 percent.
  • 9. Trends & Emerging Practices •Expansion of EVM to include the concept of earned schedule (ES)  The common practice is to use EVM to evaluate the status of project cost and forecast the project's cost at completion while using CPM to evaluate the status of project schedule and forecast the project's completion time.  The Earned Schedule (ES) allows EVM metrics to be transformed to time or duration metrics to enhance the evaluation of project schedule performance and to forecast the duration needed to complete the project. •The Earned Value Management (EVM) and the Critical Path Method (CPM) are widely accepted methods and are often used simultaneously to evaluate project performance.
  • 10. Tailoring Considerations • Knowledge management Knowledge management is the process by which an enterprise gathers, organizes, shares and analyzes its knowledge in a way that is easily accessible to Client/stakeholders. Knowledge management involves data mining and some method of operation to push information to users to make it easily accessible. Does the organization have a formal knowledge management and financial database repository that a project manager is required to use and that is readily accessible? • Estimating and budgeting process of approximating the total expenditure of the project. Does the organization have existing formal or informal cost estimating and budgeting-related policies, procedures, and guidelines?
  • 11. • Earned value management Earned Value Management (EVM) is a project performance management methodology that integrates cost, schedule, technical scope, and risk to assess progress against a baseline, use that information to identify problems, and forecast cost (and, to a certain extent, schedule) at completion. Does the organization use earned value management in managing projects? Use of agile approach. Does the organization use agile methodologies in managing projects? How does this impact cost estimating? Governance. Does the organization have formal or informal audit and governance policies, procedures, and guidelines? Tailoring Considerations
  • 12. Plan Cost Management Plan Cost Management is the process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled. Estimate Costs Determine Budget Cost Control Plan Cost Management
  • 13. Plan Cost Management: Data Flow Diagram Plan Cost Management
  • 14. Estimate Costs Process of developing an approximation of the cost of resources needed to complete project work. The key benefit of this process is that it determines the monetary resources required for the project. This process is performed periodically throughout the project as needed. Estimate Costs Determine Budget Cost Control Plan Cost Management
  • 15. Estimate Costs: Data Flow Diagram Estimate Costs
  • 16. Determine Budget Estimate Costs Determine Budget Cost Control Plan Cost Management Process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. A a
  • 18. Control Costs Estimate Costs Determine Budget Cost Control Plan Cost Management Control Costs is the process of monitoring the status of the project to update the project costs and managing changes to the cost baseline. The key benefit of this process is that the cost baseline is maintained throughout the project.
  • 19. Control Costs Control Costs: Data Flow Diagram