SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
BACHELOR OF QUANTITY SURVEYING (HONOURS)
QSB60203 VALUE MANAGEMENT
AUGUST 2018 SEMESTER
VALUE MANAGEMENT CASE STUDY REPORT
GROUP MEMBERS:
NO. NAME STUDENT ID
1. OOI YIN JI 0319962
2. PANG KAI YUN 0319802
3. SAM WEI YIN 0320364
4. WAH YUN CHEN 0319115
5. YEO KAI WEN 0319844
6. ABD'ALLAH SAEI-UL-HAQQ 0324556
7. LEONG YU XUAN 0325102
LECTURERS : ​SR. LOO SEONG KING
PUAN HABIZAH BINTI SHEIKH ILMI
SUBMISSION DATE : ​26 NOVEMBER 2018
TABLE OF CONTENTS
NO. TITLE PAGE NO.
1.0 Introduction 3
1.1 Primary purpose of VM study 3
1.2 Benefits of VM study 5
2.0 Executive Study of Project 6
2.1 Brief Description 6
2.2 Summary of Problems 8
2.2.1 Objective 1: Consider Life Cycle Cost 9
2.2.2 Objective 2: Increasing Building Efficiency 9
2.2.3 Objective 3: Eliminating Unnecessary Function 9
2.3 Value Management Study undertaken 10
2.3.1 Design of the Study 10
3.0 Value Management Tools and Techniques 12
3.1 Function Analysis System Technique (FAST) 12
3.2 Compound Approach 14
3.2.1 Precast hollow-core slab floor construction 14
3.3 Cost Reduction Approach 14
3.3.1 Eliminate glass skylights in roof covering 14
3.4 Space Functional Analysis 15
3.4.1 Function Analysis of Project Concept 16
3.4.2 Space Functional Analysis by Floors 16
3.5 Priority Setting Matrix 18
4.0 Proposed Change in the Design 23
1
TABLE OF CONTENTS
NO. TITLE PAGE NO.
5.0 Technical Data 24
5.1 Sound Insulated Solid Wood Doors in Guest Rooms 24
5.2 Use of Precast Hollow Core Slabs 24
5.3 Eliminate glass skylights in roof covering 26
5.4 Change corridor lightning from Fluorescent Light to LED
light
27
5.5 Change wall finishes from wallpaper to plaster & paint 29
6.0 Cost Analysis 30
6.1 Change to sound insulated solid wood doors in guest rooms 30
6.2 Use of Precast Hollow Core Slabs 31
6.3 Eliminate glass skylights in roof covering 32
6.4 Enlarge the dining lounge area 33
6.5 Change corridor lightning from Fluorescent Light to LED
light
34
6.6 Change wall finishes from wallpaper to plaster & paint 35
6.7 Cost Summary 36
7.0 Action Plan 37
8.0 Conclusion and Recommendation 39
9.0 Reference 40
2
1.0 Introduction
1.1 Primary purpose of VM study
Value Engineering and Value Management techniques are systematic team-based
approach to achieve better value and cost optimization of projects without affecting the
required performance level. In the 1980’s, the term Value Engineering was further developed
to Value Management by the UK’s construction industry. However, Value Engineering is
actually the preferred term and most usually used in the US.
Value Management is an important technique throughout the entire construction
process, which is from the inception stage to completion stage. A Value Management study
that is implemented adequately is able to reduce the unnecessary cost of a project which is
different from traditional cost cutting tools such as omission of certain elements to reduce the
cost of a project. Value Management study is a systematic process to enhance the initial
project cost by eliminating unnecessary cost of elements in the project. Moreover, it can
provide better value for money to the client in terms of cost, time, quality and performance of
the project. The Value Management technique is also used to reduce risks such as late
delivery of project, cost overrun and poor quality buildings.
3
Figure 1.1:​​ Construction Cost Relationship
Figure 1.1 demonstrates the relationship between project development process and
cost implication. According to the figure below, it shows that for a greater potential savings,
value management technique must be applied during early stage of development.
4
1.2 Benefits of VM study
Value Management study contributes in identifying unnecessary cost which are not
essential for a good project. The benefits of value management study are shown below:
❖ Value Management study identifies and removes unnecessary cost with alternative
design solutions while maintaining performance and quality.
❖ Value Management provides better value and better quality buildings.
❖ Value management provides better focus on the projects and also to the client’s
objectives.
❖ Value Management cultivates and improves relationships.
❖ Value Management tends to work more on effective design.
❖ Precise and clear project brief and decision making.
❖ Value Management improves efficiency in a project.
❖ Value Management study can promote communication and common knowledge.
❖ Decisions are made with great confidence and knowledge as it can be supported by
data and performance criteria.
❖ Value Management enhances competitiveness.
5
2.0 Executive Study of Project
2.1 Brief Description
A Value Management study is carried out on the proposed project which is situated in
the Golden Triangle district, located on a 1,500 square metre site. The site itself is a relatively
small piece of land for commercial use which is located in the area of high building floor
ratio. Taken this commercial consideration, our client wishes to construct a hotel with a
vision to deliver a unique product to the market. This project, S Hotel is an 11 storeys
development project. There are a total 126 guest rooms in S Hotel. There is one floor of the
podium which houses facilities such as swimming pool, BBQ area, spa etc.
Table 2.1: Summary of Project Details
Element Description
Project Name S Hotel
Project Status A new development project which is in 35% of the design stage
No. of Floors
11- storeys of the hotel consists of:
- 7 storeys of typical floor guest rooms
- One storey of the mechanical level
- First floor of hotel lobby
- Ground floor and one floor of basement parking
6
Ground Floor Plan (left) First Floor Plan (middle) Typical Floor Plan for guest rooms (right)
Podium Roof (left) Front Elevation (right)
Render drawings of the S Hotel
7
Render drawings of the S Hotel
2.2 Summary of Problems
During the briefing, our client has highlighted several key issues and the outcome that
he wished he could obtain at the end of the Value Management study. The key driver for the
execution of value management is due to the project design was found that over budget. A
contingency approach must be adopted to resolve this issue. Achieving savings could not be
possibly done by a normal cost-cutting exercise while maintaining the function of the
building which would lead to a less satisfactory external appearance of the building. An
essential investigation of the value of the project is required in order to reach that level of
budget saving. Therefore, the aim and objectives of this study are derived to match with the
client’s concern.
Aim: Increase Value for Money (VFM)
In order to compete with other major hotels in KL City, our client aims to have the
highest value for money so that he could provide the highest quality of experience at the least
cost. Generally, the value can be increased by either adding extra functions that match the
travellers’ needs or by reducing the overall whole life costing of the building. It is crucial to
achieving an optimal balance between the advantages expected from the project and the
resources required to achieve the goals in order to obtain the highest value for money. A
8
sound and creative design is definitely a key element in contributing value for money.
Therefore, a detailed assessment of the proposed design is required if any alternative design
with the same function but the lower cost can be made.
2.2.1 Objective 1: Consider Life Cycle Cost
To serve the purpose in achieving maximum value for money, all costs incurred
during the whole lifespan of the building must be evaluated and examined. The life cycle cost
includes the initial cost, maintenance and repair cost, energy, water and replacement cost as
well as its salvage value. By taking consideration of life-cycle cost, a more accurate ROI can
be calculated as all factors of cost in both long and short terms are observed. Also, since the
client wishes to run this hotel on their own, this step is important to greatly reduce the cost
needed during the operation of the hotel. For example, window walls are used in hotel rooms
to reduce the needs of artificial lighting.
2.2.2 Objective 2: Increasing Building Efficiency
Building efficiency refers to the proportion of the building’s rentable area which is
not occupied by the services and circulation area. If there is more rentable area which are
referring to the hotel rooms, the client is able to receive more revenue from his business.
Typically, the increasing rentable area can be done by eliminating unnecessary spaces which
do not contribute to the function of the building and transform such spaces into rentable
areas. Sufficient circulation area must be provided to ensure a comfortable experience in the
hotel.
2.2.3 Objective 3: Eliminating Unnecessary Function
Unnecessary function refers to the elements which do not add any value to the
project’s fundamental requirement. The project’s unnecessary cost may be caused by the poor
9
layout of the building, wastage of materials, incorrect construction methodology, outdated
technology, costly materials and others. This unnecessary cost can be eliminated with smart
design decisions and effective project management. Potential cost savings can be gained
through the removal of unnecessary costs. The resources saved can be allocated to their most
valuable uses after careful examination.
2.3 Value Management Study undertaken
2.3.1 Design of the Study
The value study was designed in three phases which are information phase, value
management workshop and implementation phase. Implementation phase involved a 2-weeks
information gathering and analysis period while the second phase took 5 days of the
workshop period. Finally, the implementation phase involved one week long report
production period. This value study team consists of 9 personnel which were independently
appointed specifically for this value study. Importantly, none of the members of the original
consultant team participated in this value study except initial interviews and final presentation
of recommendations during the end of the workshop. The independent team includes three
value study leaders, one architect, one structural engineer, two quantity surveyors, one M&E
engineer and one specialist space planning consultant.
Information Phase
Design and other crucial information were obtained from the client and the existing
project design team through interviews. The value study leaders analyzed the information
obtained and prepare a 5-days workshop agenda as follows:
● Examination of key issues of the project
● Creation of FAST Diagram
● Sorting strategic ideas for change through brainstorming
● Carry out functional analysis of elements
● Examine spatial arrangements
10
40-hour Value Management Workshop
This is an investigation on the design which has been progressed to 35% at the design
stage. The 40-hour workshop stretches over a period of 5 days which follows the stages in job
plan which includes the phases of information, creativity, evaluation, development and
presentation.
Day 1: Examine the issues affecting the project.
Day 2: Study on spatial configuration to assess the proposed design. Ideas for change to the
spatial arrangement were created.
Day 3: Study the element and components for the design of the project. Ideas for change are
created.
Day 4: Transformed the sorted ideas that previously created into a number of value proposals
for change.
Day 5: Finalized the proposal development. Conduct a presentation of value proposals to
client and members of the original design team for their consideration to implement the
suggestions made.
Implementation Phase
A comprehensive value study report must be produced within 1 week from the date of
the workshop ends. The description of value proposals will be included in terms of
consideration for implementation by the project design team.
11
3.0 Value Management Tools and Techniques
The outcome of the value management workshop is produced by the utilization of
various VM tools and techniques to propose changes in relation to spatial arrangement,
alternative materials, change to the elements and components of the hotel. The objectives of
the study is to ensure the client’s project reach the maximum value for money through the
design, that the project could be built for the budget set.
3.1 Function Analysis System Technique (FAST)
FAST Diagram is used as one of the VM techniques adopted to develop a graphical
representation to show the relationships between the functions of a project. In this project, the
FAST diagram for the hotel is illustrated in Figure 3.1.
Figure 3.1: FAST diagram
12
Change to solid wood door in guest rooms
The original design for the guest room doors is without timber hollow door without
the sound insulation, however, by using the FAST diagram, noise reduction is the main
element that should be taken into consideration to improve the hotel stay experience. The
client is concerned about the external noise as it is located at the noisy street of KL city, LRT
sounds, nearby ongoing construction works and etc. Therefore, he wishes to keep the noise
from penetrating into the guest rooms to provide a quiet and peaceful sanctuary of the rooms.
However, the original design team did not take this issue into consideration.
Therefore, the function of sound reduction is required to reduce the noise in the guest
rooms in order to minimize disturbance. As a result, solid wood doors are installed as the
main doors of the guest rooms as shown in Figure 3.2.
Figure 3.2: Location of the solid wood doors
13
3.2 Compound Approach
3.2.1 Precast hollow-core slab floor construction
The original design team proposes the typical floor construction is cast-in-place
concrete slab spanning between the concrete beams. Although cast-in-situ concrete slab is
incredibly versatile, it is costly and more labour intensive.
By using compound approach, we propose precast hollow core concrete slabs to
replace the cast-in-place slabs as it generates significant savings in construction cost and
time. Hollow core slabs serve the primary function to reduce the loading of the building
which in turn decrease the foundation required. Also, it is suitable for this project as hollow
core slabs can satisfy the larger spans and loadings of a hotel.
3.3 Cost Reduction Approach
3.3.1 Eliminate glass skylights in roof covering
There are skylights located in the roof in the original design with the purpose of
providing daylighting and ventilation. The basic function of a roof is to protect the building.
Therefore, the function of a skylight to penetrate sunlight is not essential to establish the basic
function of a roof. It costs more to install skylights in the roof as compared to constructing a
complete concrete flat roof.
14
Moreover, with the concern of too much heat gain in Malaysia during the day through
the skylight, we decided to omit this element. Also, removing the skylight can reduce the
potential risks of glass breaking and injured the hotel guests due to strong wind and storm
damage since it is the weakest part of the roof.
3.4 Space Functional Analysis
Function analysis (FA) is considered to be at the core of value management (VM).
Miles (1972) always emphasized that VM has one specific purpose – the identification and
elimination of unnecessary cost. FA, or value method as it is sometimes called, is the
systematic process of identifying functions and their associated costs, and assessing the
necessity of those functions based on established criteria for the product or service.
FA is a technique which uses for identifying and describing the functions of an item
in a general so that some of the functions can be eliminated and other functions can be
combined. The purpose of function analysis is to simplify the design, operation, plan or
schedule of the item that can be less expensive to make or to use it. Functions are the
characteristics of an item which meet the desire of the needs of the user. It can be an element,
a characteristic or an action which makes the item “work” or “sell”. Function analysis
involves thinking such as why the item is important and necessary. This represents a higher
level of abstraction than when it focused on the item only. It begins with a listing of the
15
functions of the item being studied, and it provides concise and a clear description of the
functions available.
There are six steps of function analysis when comes in functional approach, the steps
are as below:
1. Investigate the function of the total system
2. Investigate the function of the system components
3. Break the system down into quantifiable parts
4. Consider what each part does
5. Place a worth on each part
6. Evaluate and make comparisons
3.4.1 Function Analysis of Project Concept
Table 3.1: Functional Analysis at Project Concept Level
Item Project
Function
Types of Function
Verb Noun
1. Hotel Accommodate Guests Basic Function
3.4.2 Space functional analysis by floors
Table 3.2 demonstrates the analysis of the function of each space in the hotel based on
the layout plan. The function of space, type of the functions, designed area, proposed area is
analyzed to identify any unnecessary function and space in the previous design which bring
no essential contribution to the basic function of the hotel.
16
Table 3.2: Space Functional Analysis at Ground Floor, First Floor, Podium and Typical Floors
17
Based on the space functional analysis carried out, the lift lobby area and the open
area in the podium floor are found to occupy a large space only for circulation purpose.
Therefore, our VM team proposes the lift lobby area and the open area to be reduced by 20%
for lift lobby and removed the open space. Thus, such spaces are used to enlarge the dining
and lounge area. The increment of the dining area can possibly increase the revenue of the
hotel as the space can be rented out for event purpose. However, the circulation area at lift
lobby is maintained at the acceptable size to prevent cramped space.
3.5 Priority Setting Matrix
The Priority Matrix helps participants rank actions based on their time to complete,
cost, importance to quality, and availability of resources. This tool can be used to prioritize
strategies and actions as part of developing an action plan. It assumes that participants have
completed a root cause analysis first, so that the selected actions address the root causes of
the problem and not just the symptoms.
3.5.1 Change corridor lightning
Priority setting matrix table
The criteria for the selection of suitable lightning have been established as follows:
A - Cost
B - Durability
C - Maintenance
D - Ease of Installation
E - Color Rendering
Figure 3.1: Priority Setting Matrix of Lighting
18
Weighted Scoring Matrix
Ratings: Excellent (5), Very Good (4), Good (3), Fair (2), Poor (1)
Figure 3.2: Weighted Scoring Matrix of Lighting
3.5.1.1 Recommendation on Selection
According to the result of Priority Setting Matrix and Weighted Scoring Matrix, it can
be seen that light emitting diodes (LED) obtained the highest score among the other available
options due to the cost effectiveness and longest lifespan. Besides that, compact fluorescent
light (CFLs) comes close with a score of 37 which took place in the second. The capital cost
of CFLs is the lowest but its lifespan is short compared to LED. The incandescent light bulb
had the lowest scoring among the three options. Although the score of durability and color
rendering given by the VM team is slightly higher than the fluorescents light but the scoring
weighted mark for maintenance is low.
In conclusion, light emitting diodes (LED) is recommended for use for the corridor of
the hotel.
19
3.5.2 Wall Finishes
Priority setting matrix table
The criteria for the selection of suitable lightning have been established as follows:
A - Capital Cost
B - Durability
C - Maintenance
D - Attractive Finish
E - Cleanliness
F - Ease of Installation
G - Variety
H - Reliability of Supply
Figure 3.3: Priority Setting Matrix of Wall Finishes
20
Weighted Scoring Matrix
Ratings: Excellent (5), Very Good (4), Good (3), Fair (2), Poor (1)
Figure 3.3: Weighted Scoring Matrix of Wall Finishes
21
3.5.2.1 Recommendation on Selection
Based on the weighted scoring matrix above, it is analyzed that plaster and paint is the
best option with tiles cladding a close second.
The team gave a high weightage to cleanliness against some of the proprietary
partitions scored poorly which are wallpaper, tiles cladding, flake finishes, wooden panelling
and lamination. Also, they scored poorly in attractive finishes. Although they scored well in
durability, maintenance and ease of installation, the team considered these attributes as lower
priority of importance. Therefore, the plaster and paint and tiles cladding scored well in
cleanliness and durability in addition maintenance and ease of installation. Hence, plaster and
paint is chosen as the wall finishes for the guest rooms.
22
4.0 Proposed change in Design
In this case, the change in layout plan is the enlargement of the dining area through
the reduction of lift lobby area.
Figure 4.1: Proposed change in design for podium area
Table 4.1: Proposed change in design for Podium Floor
From the Figure 4.1 and Table 4.1 above, the open area shall be removed and change
to lounge and dining area. Thus, the area of the lift lobby shall be reduced in how many 20%
and the remaining area shall change to dining and lounge area to serve the guest. Therefore,
the floor efficiency is increased from 2.76% to 5.01%. Thus, the circulation area at lift lobby
is maintained at the acceptable size to prevent cramped space. It shows that the usable area
for the dining and lounge area is increased and more revenue can be generated.
23
5.0 Technical data
5.1 Sound insulated solid wood doors in guest rooms
Solid wood door prevents the transmission of sound waves into the guest rooms by
incorporating into the door. Figure 5.1 shows how the sound waves are reduced after passing
through the door. If there is no sound insulation function in the door, the sound will pass
through and enter the guest rooms without reducing the amplitude. Therefore, sound insulated
doors guarantee the guests a perfect room acoustics.
Figure 5.1: Noise reduction through sound insulated door
5.2 Use of Precast Hollow Core Slabs
The advantages of precast hollow core concrete slab over the cast-in-situ slab is
shown in Table 5.1. On the other hand, Table 5.2 demonstrates the cost analysis between
cast-in-situ concrete slab and precast hollow core slab. According to the study conducted by
Asamoah, Ankrah, Offei-nyako, & Tutu (2016), the precast concrete slabs are 23.22%
cheaper than cast-in-place concrete. Therefore, the precast hollow core concrete slab is
perceived to bring cost savings with extra function which is derived by using the compound
approach.
24
According to (Nitterhouse, 2018), the comparison of hollow core slabs and
cast-in-situ concrete slabs are shown as follows.
Table 5.1: Comparison of usage between precast hollow core concrete slab and cast-in-situ slab
PRECAST CONCRETE SLAB CRITERIA CAST-IN-SITU SLAB
Mixed, poured and cured in a
factory while ideal conditions and
exacting measurements can be
maintained throughout the process
Quality Control Subject to humidity and
temperature of the day doing the
casting.
Labour efficient as work is done in
a factory
Labor Efficiency Work that can be done by
machines has to be do instead by
hand which is much more labour
intensive, therefore increasing
labour costs.
Can withstand raining as it is
already casted, can be lifted into
place during sunny day.
Weather Will affect by unexpected
rainstorm
Due to prefabrication, insulation
element can be incorporated within
the concrete which can save labour
and architectural design space.
Insulation Can only lining the interior of
the building with insulation
instead of the insulating power
from the slabs
Can do the casting of materials
ahead of time, holding them until
they are needed
Cast ahead of
time
Overlapping tasks and
improving efficiency is
impossible due to the amount of
space and labour required for
on-site casting.
25
Table 5.2: Cost comparison between cast-in-place and precast floor slabs; Sources: Asamoah,
Ankrah, Offei-nyako, & Tutu (2016)
5.3 Eliminate glass skylights in roof covering
The concrete flat roof is replaced instead of skylights in roof covering in the proposed
project. The reason that the skylights is eliminated is because ​the amount of light and heat
cannot be controlled that comes through the skylights. And due to the direct sunlight
penetration into the rooms, it produces an unpleasant glare to the surface, and therefore
making it uncomfortable to do activities in the podium. For concrete flat roof, it is easy to
clean. For example, ​when cleaning a roof of stains, molds and algae, pressure washing is
often the fastest and most effective method. Pressure washing on a flat concrete roof is less
likely to damage the surface of the roof. Unlike skylights, cleaning of the skylight becomes a
hectic job as the placement of skylight is in the roof. One of the most important reasons the
26
concrete flat roof is because the installation cost is cheap. The installation cost and
maintenance of the skylight is more when compared to concrete flat roof. In the conclusion,
concrete flat roof is considered a more affordable option than skylights.
5.4 Change corridor lightning from Fluorescent Light to LED light
Light Emitting Diodes (LED) light is chosen for corridor lighting for the proposed
project rather than fluorescent light because ​they last longer than compact fluorescent lamp
(CFL) which is energy saver bulbs,and the consumption of energy is less. The long average
lifespan of LED light is 50,000 hours, whereas for the fluorescent light, it is 8,000 hours.
Fluorescent light will emit infrared radiation which will lead to ​eyesight loss, and in some
cases it can even cause blindness. ​LEDs do not produce infrared radiation and contain heat
sinks to help them remove unwanted heat, thus making them cooler to touch. ​By replacing
fluorescent light bulbs with energy efficient LEDs will lower the lighting costs, since they
consume far lesser energy. However, LEDs must be supplied with the voltage above the
threshold and a current below the rating. Current and lifetime change greatly with a small
change in applied voltage.Also, the efficiency of LEDs reduces as the electric current
increases. Heating also increases with higher currents which compromises the lifetime of the
LED. However, according to all the reasons above, LED light is used for this project due to
its efficiency and long lifetime.
27
Table 5.3: Life cycle cost comparison of LED, Halogen, CFL
Halogen CFL LED
Hardware Costs
Cost per bulb RM 3.50 RM 12.50 RM 13.00
Average lifespan
(hours)
1,500 8,000 25,000
Bulbs needed for
25,000 hours of use
21 2.5 1
Cost to replace bulbs
over 25,000 hours
RM 58.33 RM 39.06 RM 13
Energy Costs
Watts 53 18 12
Energy usage for 1
month at 4 hours a
day (kWh/month)
6.36 2.16 1.44
Energy costs for
25,000 hours of use
48.13 16.63 10.90
Total Costs
Hardware + energy
costs over 25,000
hours
RM 106.46 RM 55.69 RM 23.90
28
5.5 Change wall finishes from wallpaper to plaster & paint
For wall finishes, we use the plaster and paint instead of wallpaper ​because paint is a
very affordable option when you need to transform the outlook of your home. There are a few
advantages of painting over wallpaper shown in Table 5.3. To restore the uniformity of this
part of the wall, you need to repair and repaint it. Thus, despites the pros and cons of the paint
and wallpaper, plaster and paint is chosen to improve the value of the proposed project.
Table 5.3: Advantages of plaster and paint over wallpaper
Criteria Description
Inexpensive Affordable option
Ease of application In a case where you are painting over a damaged wall, you can
apply primer paint in advance to applying paint over a darker
colour. This shortens your preparation time and makes the
process easier.
Universally applicable It is applicable to any rooms in hotel, unlike wallpapers can
only be applied in high moisture rooms.
Correcting mistakes A painting mistake can easily be painted over creatively. In the
case of wallpapers, rectifying mistakes is tougher and requires
more scrapping.
29
6.0 Cost Analysis
6.1 Change to sound insulated solid wood doors in guest rooms
V.M RECOMMENDATION
ITEM: CHANGE TO SOUND INSULATED SOLID WOOD DOOR IN GUEST
ROOMS
ORIGINAL DESIGN PROPOSED DESIGN
Hollow core timber door Sound insulated solid wood door
COST BREAKDOWN
Total number of door = 126 door
Cost per door = RM 300
Total cost = RM 37,800
Total number of door = 126 door
Cost per door = RM 750
Total cost = RM 94,500
COST SUMMARY
RM 37,800 RM 94,500
Cost Savings​​ / Extra Cost RM 56,700 (150%)
By changing the guest room door from the hollow core timber door to sound insulated
solid wood door, the client need to spend an additional cost of RM 56,700.00, which is 150%
higher than the original cost.
30
6.2 Use of Precast Hollow Core Slabs
V.M RECOMMENDATION
ITEM: USE OF PRECAST HOLLOW CORE SLABS
ORIGINAL DESIGN PROPOSED DESIGN
Cast-in-situ floor slabs Precast hollow core slabs
COST BREAKDOWN
Total Area = 36,113m2
Cost per m2 = RM60/m2
Total Cost = RM 2,166,780
Total Area = 36,113m2
Cost per m2 = RM 48/m2
Total Cost = RM 1,733,424
COST SUMMARY
RM 2,166,780 RM 1,733,424
Cost Savings / ​​Extra Cost RM 433,356 (20%)
By changing all the suspended slab from cast-in-situ floor slabs to precast hollow core
slabs, the client can save an additional cost of RM 433,356.00, which is 20% less than the
original cost.
31
6.3 Eliminate glass skylights in roof covering
V.M RECOMMENDATION
ITEM: ELIMINATE SKYLIGHTS IN ROOF COVERING
ORIGINAL DESIGN PROPOSED DESIGN
Glass Skylights Concrete flat roof
COST BREAKDOWN
Size = 8.2m x 2m = 16.4m2
Total unit = 2 unit
Cost per m2 = RM 495/m2
Total cost = RM 16,236
Size = 8.2m x 2m = 16.4m2
Total unit = 2 unit
Cost per m2 = RM60/m2
Total Cost = RM 1,968
COST SUMMARY
RM 16,236 RM 1,968
Cost Savings / ​​Extra Cost RM 14,268 (88%)
By eliminating the skylight in the roof covering and change it to the concrete slab
roof, the client can save an additional cost of RM 14,268.00, which is 88% less than the
original cost.
32
6.4 Enlarge the dining lounge area
V.M RECOMMENDATION
ITEM: ENLARGE THE DINING LOUNGE AREA
ORIGINAL DESIGN PROPOSED DESIGN
Small dining area Enlargement of dining area
COST BREAKDOWN
Number of seat = 74 seat
Open Hour = 10hr
Spending per guest = RM 110
Turnover rate = 2hr per guest
Total earning per year = 5 guest x RM110 x
74 seat x 7 days x 4 weeks x 12mth
= RM 13,675,200
Worker = 15 worker
Salary per month = RM 7,000
Ingredients per people = RM 50
Total expenses per year = (15 x RM 7,000)
+ (74 seat x RM 50) = RM 108,700
Profit = RM 13,566,500
Number of seat = 142 seat
Open Hour = 10hr
Spending per guest = RM 110
Turnover rate = 2hr per guest
Total earning per year = 5 guest x RM110 x
142 seat x 7 days x 4 weeks x 12mth
= RM 26,241,600
Worker = 30 worker
Salary per month = RM 7,000
Ingredients per people = RM 50
Total expenses per year = (30 x RM 7,000)
+ (142 seat x RM 50) = RM 217,100
Profit = RM 26,024,500
COST SUMMARY
RM 13,566,500 RM 26,024,500
Loss profit​​ / Earn Profit RM 12,458,000 (92%)
By having the larger space of the dining area, client can increase group bookings by
hosting business conferences, special events, reunions, family gatherings and weddings.
These can help to fill in the rooms during normal slow seasons. The dining is taken as a profit
generator as well instead of an amenity to the hotel.
33
6.5 Change corridor lightning from Fluorescent Light to LED light
V.M RECOMMENDATION
ITEM: CHANGE CORRIDOR LIGHTNING FROM FLUORESCENT LIGHT TO
LED LIGHT
ORIGINAL DESIGN PROPOSED DESIGN
Fluorescent light LED light
COST BREAKDOWN
Total number of bulb = 133
Cost per bulb = RM 12.50
Energy Cost = RM 16.63
Total cost = RM 55.69 x 133
= RM 7,406.77
Total number of bulb = 133
Cost per bulb = RM 25
Energy Cost = RM 10.90
Total cost = RM 35.90 x 133
= RM 4,774.70
COST SUMMARY
RM 7,406.77 RM 4,774.70
Cost Savings / ​​Extra Cost RM 2,632.07 (36%)
By changing all the lightning at corridor from fluorescent light to LED light, the client
can save an additional cost of RM 2,632.07 which is 36% less than the original cost.
34
6.6 Change wall finishes from wallpaper to plaster & paint
V.M RECOMMENDATION
ITEM: CHANGE WALL FINISHES FROM WALLPAPER TO PLASTER &
PAINT
ORIGINAL DESIGN PROPOSED DESIGN
Wallpaper Plaster and Paint
COST BREAKDOWN
Total area = 6471.36m2
Cost per m2 = RM 77/m2
Total Cost = RM 498,294.72
Total area = 6471.36m2
Cost per m2 = RM 36/m2
Total Cost = RM 232,968.96
COST SUMMARY
RM 498,294.72 RM 232,968.96
Cost Savings / ​​Extra Cost RM 265,325.76 (53%)
By changing all the wall finishes of the guest rooms from wallpaper to plaster and
paint, the client can save an additional cost of RM 265,325.76.00, which is 53% less than the
original cost.
35
6.7 Cost Summary
Cost savings from specification changes:
ELEMENT ORIGINAL REVISED
Total (RM) Total (RM)
Arhitectural
Wall finishes 498,294.72 232,968.96
Roof finishes 16,236.00 1,968.00
Door 37,800.00 94,500.00
Structural
Floor construction 2,166,780.00 1,733,424.00
M&E
Lighting 7,406.77 4,774.70
TOTAL 2,726,517.49 2,067,635.66
TOTAL SAVINGS 658,881.83 (24%)
In conclusion, the client is able to save up to RM 658,881.83 which is 24% less than
the original cost by applying these changes as mentioned in the previous sections. At the
same time, the value of the resort is also increased.
36
7.0 Action plan
An action plan is prepared to implement the accepted recommendations during the
value management workshop. The action plan shows the actions need to be carried out by the
design team during the implementation. It is used to monitor the progress of the
implementation.
Table 7.1: Action Plan
CATEGORY RECOMMENDATIONS TASK ACTION TIMELINE
Architectural
Doors (typical
guest rooms)
Change to sound
insulation solid wood door
Amendment of
specification in
drawings
Architect Detailed
Design Stage
Revise cost plan Quantity
Surveyor
Roof finishes Eliminate skylights in roof
covering
Revised drawing by
changing the
skylight into flat
roof
Architect Detailed
Design Stage
Revise cost plan Quantity
Surveyor
Wall finishes
(typical guest
rooms)
Change wall finishes in
guest rooms
Change wall
finishes
specification in
drawings
Architect Detailed
Design Stage
Revise cost plan Quantity
Surveyor
Podium Enlarge the dining lounge
area
Enlarge the dining
lounge area in
drawings
Architect Detailed
Design Stage
Revise cost plan Quantity
Surveyors
37
CATEGORY RECOMMENDATIONS TASK ACTION TIMELINE
Structural
Superstructure Change floor construction
to precast hollow core
slabs
Amendment of
C&S drawings
Civil &
Structural
Engineer
Detailed
Design Stage
Revise cost plan Quantity
Surveyor
M&E
Corridor
lightning
Change from fluorescent
light to LED light
Propose changes of
lighting
Architect Detailed
Design Stage
Revise cost plan Quantity
Surveyor
Amendment of
M&E drawings
M&E
Engineer
38
8.0 Conclusion and recommendation
In a nutshell, the Value Management study carried out by our consultant team
successfully produced the value report that listed proposals for change in relation to material
changes, spatial change, elimination of elements and components of the hotel. This study
aims to assure the client can achieve the highest value for money in the design so that the
project can be built within the budget. A number of significant savings resulted from the
proposals made. Approximate 24% of cost saving is achieved through the value proposals for
this project which resolve the client’s key problem - over budgeting. Besides, the client’s aim
to achieve the value for money is achieved during the end of the value management
workshop.
It is strongly recommended that the Value Management study to be implemented for
all construction projects, especially during early design stage. Identification of client’s
requirements is made through function analysis was the main benefit and justification of the
value proposals to the client and project design team. Without the value analysis technique,
the value proposals would have little influence on the client and project design team’s
thinking. According to the cost analysis, the project is confirmed that it could be completed
within the budget as opposed to the original design which would exceed the budget.
39
9.0 References
Asamoah, R. O., Ankrah, J. S., Offei-nyako, K., & Tutu, E. O. (2016). Cost Analysis of
Precast and Cast-in-Place Concrete Construction for Selected Public Buildings in
Ghana, ​2016​. ​https://doi.org/10.1155/2016/8785129
BG_Property_Maintenance. (2018, January 17). Incandescent Bulb vs CFL Bulb vs
LED Bulb Part II • B&G Property Maintenance. Retrieved November 14, 2018,
from http://bgpmaintenance.com/incandescent-cfl-led-part-ii/
Biobaku, S. (2018, June 21). Wallpaper Vs Paint: Which is Better For Your Home? |
Private Property. Retrieved November 12, 2018, from
https://www.privateproperty.com.ng/news/wallpaper-vs-paint/
Compare Wallpapering vs Painting Costs. (n.d.). Retrieved November 12, 2018, from
https://www.kompareit.com/homeandgarden/painting-compare-paint-vs-wallpaper.
html
Comparing LED vs CFL vs Incandescent Light Bulbs. (2018, March 30). Retrieved
November 14, 2018, from
https://www.viribright.com/lumen-output-comparing-led-vs-cfl-vs-incandescent-wa
ttage/
Kang, Y. J. (2018, September 06). Will you actually save more with LED lights?
Retrieved November 13, 2018, from
https://www.recommend.my/blog/will-you-actually-save-more-with-led-lights/
LED vs. CF vs. Incandescent. (n.d.). Retrieved November 14, 2018, from
https://www.homepower.com/articles/home-efficiency/electricity/led-vs-cf-vs-inca
ndescent
Nitterhouse. (2018). Precast Concrete VS Site Cast Concrete, 1–7.
40

Weitere ähnliche Inhalte

Was ist angesagt?

Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)
Pang Khai Shuen
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
Lee Pei Gie
 
Presentation ibs
Presentation ibsPresentation ibs
Presentation ibs
UTHM
 
Project management project 1 report (pr architects)
Project management project 1 report (pr architects)Project management project 1 report (pr architects)
Project management project 1 report (pr architects)
Jannah Jailani
 

Was ist angesagt? (20)

Procurement types
Procurement typesProcurement types
Procurement types
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
 
Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)
 
Building Economics Cost Plan Report
Building Economics Cost Plan ReportBuilding Economics Cost Plan Report
Building Economics Cost Plan Report
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
GBI: Role of BS
GBI: Role of BSGBI: Role of BS
GBI: Role of BS
 
Building Services Case Study
Building Services Case StudyBuilding Services Case Study
Building Services Case Study
 
Ibs part1
Ibs part1Ibs part1
Ibs part1
 
Site possession
Site possessionSite possession
Site possession
 
Project management report project 1
Project management report project 1Project management report project 1
Project management report project 1
 
Pm assignment-2-report
Pm assignment-2-reportPm assignment-2-report
Pm assignment-2-report
 
Presentation ibs
Presentation ibsPresentation ibs
Presentation ibs
 
Project management project 1 report (pr architects)
Project management project 1 report (pr architects)Project management project 1 report (pr architects)
Project management project 1 report (pr architects)
 
Project Management Group Assignment Final Report
Project Management Group Assignment Final ReportProject Management Group Assignment Final Report
Project Management Group Assignment Final Report
 
Vm report
Vm reportVm report
Vm report
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATION
 

Ähnlich wie Assignment - S Hotel

CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_Report
Muhammad Daniyal
 

Ähnlich wie Assignment - S Hotel (20)

Value Management Group Assignment
Value Management Group AssignmentValue Management Group Assignment
Value Management Group Assignment
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)
 
Vm assignment (5)
Vm assignment (5)Vm assignment (5)
Vm assignment (5)
 
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate IndustryIRJET- Value Engineering-An Approach to Enhance Real Estate Industry
IRJET- Value Engineering-An Approach to Enhance Real Estate Industry
 
Value engineering in residential house construction
Value engineering in residential house constructionValue engineering in residential house construction
Value engineering in residential house construction
 
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTIONVALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION
VALUE ENGINEERING IN RESIDENTIAL HOUSE CONSTRUCTION
 
Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725Application of-value-engineering-in-residential-building-ijertv9 is050725
Application of-value-engineering-in-residential-building-ijertv9 is050725
 
Compiled report
Compiled reportCompiled report
Compiled report
 
Compiled report
Compiled reportCompiled report
Compiled report
 
Cost studies model_answers_2014_jan
Cost studies model_answers_2014_janCost studies model_answers_2014_jan
Cost studies model_answers_2014_jan
 
CE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_ReportCE-545_Fall 2015_TPG_03_Final_Report
CE-545_Fall 2015_TPG_03_Final_Report
 
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
 
Value Management Tutorial - VM Application in Cost Planning
Value Management Tutorial - VM Application in Cost PlanningValue Management Tutorial - VM Application in Cost Planning
Value Management Tutorial - VM Application in Cost Planning
 
The role of time, cost and quality in project management
The role of time, cost and quality in project managementThe role of time, cost and quality in project management
The role of time, cost and quality in project management
 
Review Application of value engineering in construction project.
Review Application of value engineering in construction project.Review Application of value engineering in construction project.
Review Application of value engineering in construction project.
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
 
Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800Minor project by priyanshu kumar, 9608684800
Minor project by priyanshu kumar, 9608684800
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
IIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction ProjectIIRJET-Cost Control Techniques for Construction Project
IIRJET-Cost Control Techniques for Construction Project
 
ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIA...
ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIA...ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIA...
ARC 3612 PROJECT MANAGEMENT- PROJECT 1- DEFINING AND DOCUMENTING A RESIDENTIA...
 

Mehr von Kai Yun Pang

Mehr von Kai Yun Pang (20)

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau Langkawi
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - Report
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump Station
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft Project
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - Financial Appraisal
Assignment - Financial Appraisal Assignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study Report
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - Journal
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK Land
 
Assignment - Financial Analysis
Assignment - Financial AnalysisAssignment - Financial Analysis
Assignment - Financial Analysis
 
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)
 
Assignment - Cost Plan
Assignment - Cost PlanAssignment - Cost Plan
Assignment - Cost Plan
 
Assignment 2 - Buildsoft Software
Assignment 2 - Buildsoft SoftwareAssignment 2 - Buildsoft Software
Assignment 2 - Buildsoft Software
 

Kürzlich hochgeladen

Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 

Kürzlich hochgeladen (20)

Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptxOn_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
On_Translating_a_Tamil_Poem_by_A_K_Ramanujan.pptx
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
How to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptxHow to setup Pycharm environment for Odoo 17.pptx
How to setup Pycharm environment for Odoo 17.pptx
 

Assignment - S Hotel

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING (HONOURS) QSB60203 VALUE MANAGEMENT AUGUST 2018 SEMESTER VALUE MANAGEMENT CASE STUDY REPORT GROUP MEMBERS: NO. NAME STUDENT ID 1. OOI YIN JI 0319962 2. PANG KAI YUN 0319802 3. SAM WEI YIN 0320364 4. WAH YUN CHEN 0319115 5. YEO KAI WEN 0319844 6. ABD'ALLAH SAEI-UL-HAQQ 0324556 7. LEONG YU XUAN 0325102 LECTURERS : ​SR. LOO SEONG KING PUAN HABIZAH BINTI SHEIKH ILMI SUBMISSION DATE : ​26 NOVEMBER 2018
  • 2. TABLE OF CONTENTS NO. TITLE PAGE NO. 1.0 Introduction 3 1.1 Primary purpose of VM study 3 1.2 Benefits of VM study 5 2.0 Executive Study of Project 6 2.1 Brief Description 6 2.2 Summary of Problems 8 2.2.1 Objective 1: Consider Life Cycle Cost 9 2.2.2 Objective 2: Increasing Building Efficiency 9 2.2.3 Objective 3: Eliminating Unnecessary Function 9 2.3 Value Management Study undertaken 10 2.3.1 Design of the Study 10 3.0 Value Management Tools and Techniques 12 3.1 Function Analysis System Technique (FAST) 12 3.2 Compound Approach 14 3.2.1 Precast hollow-core slab floor construction 14 3.3 Cost Reduction Approach 14 3.3.1 Eliminate glass skylights in roof covering 14 3.4 Space Functional Analysis 15 3.4.1 Function Analysis of Project Concept 16 3.4.2 Space Functional Analysis by Floors 16 3.5 Priority Setting Matrix 18 4.0 Proposed Change in the Design 23 1
  • 3. TABLE OF CONTENTS NO. TITLE PAGE NO. 5.0 Technical Data 24 5.1 Sound Insulated Solid Wood Doors in Guest Rooms 24 5.2 Use of Precast Hollow Core Slabs 24 5.3 Eliminate glass skylights in roof covering 26 5.4 Change corridor lightning from Fluorescent Light to LED light 27 5.5 Change wall finishes from wallpaper to plaster & paint 29 6.0 Cost Analysis 30 6.1 Change to sound insulated solid wood doors in guest rooms 30 6.2 Use of Precast Hollow Core Slabs 31 6.3 Eliminate glass skylights in roof covering 32 6.4 Enlarge the dining lounge area 33 6.5 Change corridor lightning from Fluorescent Light to LED light 34 6.6 Change wall finishes from wallpaper to plaster & paint 35 6.7 Cost Summary 36 7.0 Action Plan 37 8.0 Conclusion and Recommendation 39 9.0 Reference 40 2
  • 4. 1.0 Introduction 1.1 Primary purpose of VM study Value Engineering and Value Management techniques are systematic team-based approach to achieve better value and cost optimization of projects without affecting the required performance level. In the 1980’s, the term Value Engineering was further developed to Value Management by the UK’s construction industry. However, Value Engineering is actually the preferred term and most usually used in the US. Value Management is an important technique throughout the entire construction process, which is from the inception stage to completion stage. A Value Management study that is implemented adequately is able to reduce the unnecessary cost of a project which is different from traditional cost cutting tools such as omission of certain elements to reduce the cost of a project. Value Management study is a systematic process to enhance the initial project cost by eliminating unnecessary cost of elements in the project. Moreover, it can provide better value for money to the client in terms of cost, time, quality and performance of the project. The Value Management technique is also used to reduce risks such as late delivery of project, cost overrun and poor quality buildings. 3
  • 5. Figure 1.1:​​ Construction Cost Relationship Figure 1.1 demonstrates the relationship between project development process and cost implication. According to the figure below, it shows that for a greater potential savings, value management technique must be applied during early stage of development. 4
  • 6. 1.2 Benefits of VM study Value Management study contributes in identifying unnecessary cost which are not essential for a good project. The benefits of value management study are shown below: ❖ Value Management study identifies and removes unnecessary cost with alternative design solutions while maintaining performance and quality. ❖ Value Management provides better value and better quality buildings. ❖ Value management provides better focus on the projects and also to the client’s objectives. ❖ Value Management cultivates and improves relationships. ❖ Value Management tends to work more on effective design. ❖ Precise and clear project brief and decision making. ❖ Value Management improves efficiency in a project. ❖ Value Management study can promote communication and common knowledge. ❖ Decisions are made with great confidence and knowledge as it can be supported by data and performance criteria. ❖ Value Management enhances competitiveness. 5
  • 7. 2.0 Executive Study of Project 2.1 Brief Description A Value Management study is carried out on the proposed project which is situated in the Golden Triangle district, located on a 1,500 square metre site. The site itself is a relatively small piece of land for commercial use which is located in the area of high building floor ratio. Taken this commercial consideration, our client wishes to construct a hotel with a vision to deliver a unique product to the market. This project, S Hotel is an 11 storeys development project. There are a total 126 guest rooms in S Hotel. There is one floor of the podium which houses facilities such as swimming pool, BBQ area, spa etc. Table 2.1: Summary of Project Details Element Description Project Name S Hotel Project Status A new development project which is in 35% of the design stage No. of Floors 11- storeys of the hotel consists of: - 7 storeys of typical floor guest rooms - One storey of the mechanical level - First floor of hotel lobby - Ground floor and one floor of basement parking 6
  • 8. Ground Floor Plan (left) First Floor Plan (middle) Typical Floor Plan for guest rooms (right) Podium Roof (left) Front Elevation (right) Render drawings of the S Hotel 7
  • 9. Render drawings of the S Hotel 2.2 Summary of Problems During the briefing, our client has highlighted several key issues and the outcome that he wished he could obtain at the end of the Value Management study. The key driver for the execution of value management is due to the project design was found that over budget. A contingency approach must be adopted to resolve this issue. Achieving savings could not be possibly done by a normal cost-cutting exercise while maintaining the function of the building which would lead to a less satisfactory external appearance of the building. An essential investigation of the value of the project is required in order to reach that level of budget saving. Therefore, the aim and objectives of this study are derived to match with the client’s concern. Aim: Increase Value for Money (VFM) In order to compete with other major hotels in KL City, our client aims to have the highest value for money so that he could provide the highest quality of experience at the least cost. Generally, the value can be increased by either adding extra functions that match the travellers’ needs or by reducing the overall whole life costing of the building. It is crucial to achieving an optimal balance between the advantages expected from the project and the resources required to achieve the goals in order to obtain the highest value for money. A 8
  • 10. sound and creative design is definitely a key element in contributing value for money. Therefore, a detailed assessment of the proposed design is required if any alternative design with the same function but the lower cost can be made. 2.2.1 Objective 1: Consider Life Cycle Cost To serve the purpose in achieving maximum value for money, all costs incurred during the whole lifespan of the building must be evaluated and examined. The life cycle cost includes the initial cost, maintenance and repair cost, energy, water and replacement cost as well as its salvage value. By taking consideration of life-cycle cost, a more accurate ROI can be calculated as all factors of cost in both long and short terms are observed. Also, since the client wishes to run this hotel on their own, this step is important to greatly reduce the cost needed during the operation of the hotel. For example, window walls are used in hotel rooms to reduce the needs of artificial lighting. 2.2.2 Objective 2: Increasing Building Efficiency Building efficiency refers to the proportion of the building’s rentable area which is not occupied by the services and circulation area. If there is more rentable area which are referring to the hotel rooms, the client is able to receive more revenue from his business. Typically, the increasing rentable area can be done by eliminating unnecessary spaces which do not contribute to the function of the building and transform such spaces into rentable areas. Sufficient circulation area must be provided to ensure a comfortable experience in the hotel. 2.2.3 Objective 3: Eliminating Unnecessary Function Unnecessary function refers to the elements which do not add any value to the project’s fundamental requirement. The project’s unnecessary cost may be caused by the poor 9
  • 11. layout of the building, wastage of materials, incorrect construction methodology, outdated technology, costly materials and others. This unnecessary cost can be eliminated with smart design decisions and effective project management. Potential cost savings can be gained through the removal of unnecessary costs. The resources saved can be allocated to their most valuable uses after careful examination. 2.3 Value Management Study undertaken 2.3.1 Design of the Study The value study was designed in three phases which are information phase, value management workshop and implementation phase. Implementation phase involved a 2-weeks information gathering and analysis period while the second phase took 5 days of the workshop period. Finally, the implementation phase involved one week long report production period. This value study team consists of 9 personnel which were independently appointed specifically for this value study. Importantly, none of the members of the original consultant team participated in this value study except initial interviews and final presentation of recommendations during the end of the workshop. The independent team includes three value study leaders, one architect, one structural engineer, two quantity surveyors, one M&E engineer and one specialist space planning consultant. Information Phase Design and other crucial information were obtained from the client and the existing project design team through interviews. The value study leaders analyzed the information obtained and prepare a 5-days workshop agenda as follows: ● Examination of key issues of the project ● Creation of FAST Diagram ● Sorting strategic ideas for change through brainstorming ● Carry out functional analysis of elements ● Examine spatial arrangements 10
  • 12. 40-hour Value Management Workshop This is an investigation on the design which has been progressed to 35% at the design stage. The 40-hour workshop stretches over a period of 5 days which follows the stages in job plan which includes the phases of information, creativity, evaluation, development and presentation. Day 1: Examine the issues affecting the project. Day 2: Study on spatial configuration to assess the proposed design. Ideas for change to the spatial arrangement were created. Day 3: Study the element and components for the design of the project. Ideas for change are created. Day 4: Transformed the sorted ideas that previously created into a number of value proposals for change. Day 5: Finalized the proposal development. Conduct a presentation of value proposals to client and members of the original design team for their consideration to implement the suggestions made. Implementation Phase A comprehensive value study report must be produced within 1 week from the date of the workshop ends. The description of value proposals will be included in terms of consideration for implementation by the project design team. 11
  • 13. 3.0 Value Management Tools and Techniques The outcome of the value management workshop is produced by the utilization of various VM tools and techniques to propose changes in relation to spatial arrangement, alternative materials, change to the elements and components of the hotel. The objectives of the study is to ensure the client’s project reach the maximum value for money through the design, that the project could be built for the budget set. 3.1 Function Analysis System Technique (FAST) FAST Diagram is used as one of the VM techniques adopted to develop a graphical representation to show the relationships between the functions of a project. In this project, the FAST diagram for the hotel is illustrated in Figure 3.1. Figure 3.1: FAST diagram 12
  • 14. Change to solid wood door in guest rooms The original design for the guest room doors is without timber hollow door without the sound insulation, however, by using the FAST diagram, noise reduction is the main element that should be taken into consideration to improve the hotel stay experience. The client is concerned about the external noise as it is located at the noisy street of KL city, LRT sounds, nearby ongoing construction works and etc. Therefore, he wishes to keep the noise from penetrating into the guest rooms to provide a quiet and peaceful sanctuary of the rooms. However, the original design team did not take this issue into consideration. Therefore, the function of sound reduction is required to reduce the noise in the guest rooms in order to minimize disturbance. As a result, solid wood doors are installed as the main doors of the guest rooms as shown in Figure 3.2. Figure 3.2: Location of the solid wood doors 13
  • 15. 3.2 Compound Approach 3.2.1 Precast hollow-core slab floor construction The original design team proposes the typical floor construction is cast-in-place concrete slab spanning between the concrete beams. Although cast-in-situ concrete slab is incredibly versatile, it is costly and more labour intensive. By using compound approach, we propose precast hollow core concrete slabs to replace the cast-in-place slabs as it generates significant savings in construction cost and time. Hollow core slabs serve the primary function to reduce the loading of the building which in turn decrease the foundation required. Also, it is suitable for this project as hollow core slabs can satisfy the larger spans and loadings of a hotel. 3.3 Cost Reduction Approach 3.3.1 Eliminate glass skylights in roof covering There are skylights located in the roof in the original design with the purpose of providing daylighting and ventilation. The basic function of a roof is to protect the building. Therefore, the function of a skylight to penetrate sunlight is not essential to establish the basic function of a roof. It costs more to install skylights in the roof as compared to constructing a complete concrete flat roof. 14
  • 16. Moreover, with the concern of too much heat gain in Malaysia during the day through the skylight, we decided to omit this element. Also, removing the skylight can reduce the potential risks of glass breaking and injured the hotel guests due to strong wind and storm damage since it is the weakest part of the roof. 3.4 Space Functional Analysis Function analysis (FA) is considered to be at the core of value management (VM). Miles (1972) always emphasized that VM has one specific purpose – the identification and elimination of unnecessary cost. FA, or value method as it is sometimes called, is the systematic process of identifying functions and their associated costs, and assessing the necessity of those functions based on established criteria for the product or service. FA is a technique which uses for identifying and describing the functions of an item in a general so that some of the functions can be eliminated and other functions can be combined. The purpose of function analysis is to simplify the design, operation, plan or schedule of the item that can be less expensive to make or to use it. Functions are the characteristics of an item which meet the desire of the needs of the user. It can be an element, a characteristic or an action which makes the item “work” or “sell”. Function analysis involves thinking such as why the item is important and necessary. This represents a higher level of abstraction than when it focused on the item only. It begins with a listing of the 15
  • 17. functions of the item being studied, and it provides concise and a clear description of the functions available. There are six steps of function analysis when comes in functional approach, the steps are as below: 1. Investigate the function of the total system 2. Investigate the function of the system components 3. Break the system down into quantifiable parts 4. Consider what each part does 5. Place a worth on each part 6. Evaluate and make comparisons 3.4.1 Function Analysis of Project Concept Table 3.1: Functional Analysis at Project Concept Level Item Project Function Types of Function Verb Noun 1. Hotel Accommodate Guests Basic Function 3.4.2 Space functional analysis by floors Table 3.2 demonstrates the analysis of the function of each space in the hotel based on the layout plan. The function of space, type of the functions, designed area, proposed area is analyzed to identify any unnecessary function and space in the previous design which bring no essential contribution to the basic function of the hotel. 16
  • 18. Table 3.2: Space Functional Analysis at Ground Floor, First Floor, Podium and Typical Floors 17
  • 19. Based on the space functional analysis carried out, the lift lobby area and the open area in the podium floor are found to occupy a large space only for circulation purpose. Therefore, our VM team proposes the lift lobby area and the open area to be reduced by 20% for lift lobby and removed the open space. Thus, such spaces are used to enlarge the dining and lounge area. The increment of the dining area can possibly increase the revenue of the hotel as the space can be rented out for event purpose. However, the circulation area at lift lobby is maintained at the acceptable size to prevent cramped space. 3.5 Priority Setting Matrix The Priority Matrix helps participants rank actions based on their time to complete, cost, importance to quality, and availability of resources. This tool can be used to prioritize strategies and actions as part of developing an action plan. It assumes that participants have completed a root cause analysis first, so that the selected actions address the root causes of the problem and not just the symptoms. 3.5.1 Change corridor lightning Priority setting matrix table The criteria for the selection of suitable lightning have been established as follows: A - Cost B - Durability C - Maintenance D - Ease of Installation E - Color Rendering Figure 3.1: Priority Setting Matrix of Lighting 18
  • 20. Weighted Scoring Matrix Ratings: Excellent (5), Very Good (4), Good (3), Fair (2), Poor (1) Figure 3.2: Weighted Scoring Matrix of Lighting 3.5.1.1 Recommendation on Selection According to the result of Priority Setting Matrix and Weighted Scoring Matrix, it can be seen that light emitting diodes (LED) obtained the highest score among the other available options due to the cost effectiveness and longest lifespan. Besides that, compact fluorescent light (CFLs) comes close with a score of 37 which took place in the second. The capital cost of CFLs is the lowest but its lifespan is short compared to LED. The incandescent light bulb had the lowest scoring among the three options. Although the score of durability and color rendering given by the VM team is slightly higher than the fluorescents light but the scoring weighted mark for maintenance is low. In conclusion, light emitting diodes (LED) is recommended for use for the corridor of the hotel. 19
  • 21. 3.5.2 Wall Finishes Priority setting matrix table The criteria for the selection of suitable lightning have been established as follows: A - Capital Cost B - Durability C - Maintenance D - Attractive Finish E - Cleanliness F - Ease of Installation G - Variety H - Reliability of Supply Figure 3.3: Priority Setting Matrix of Wall Finishes 20
  • 22. Weighted Scoring Matrix Ratings: Excellent (5), Very Good (4), Good (3), Fair (2), Poor (1) Figure 3.3: Weighted Scoring Matrix of Wall Finishes 21
  • 23. 3.5.2.1 Recommendation on Selection Based on the weighted scoring matrix above, it is analyzed that plaster and paint is the best option with tiles cladding a close second. The team gave a high weightage to cleanliness against some of the proprietary partitions scored poorly which are wallpaper, tiles cladding, flake finishes, wooden panelling and lamination. Also, they scored poorly in attractive finishes. Although they scored well in durability, maintenance and ease of installation, the team considered these attributes as lower priority of importance. Therefore, the plaster and paint and tiles cladding scored well in cleanliness and durability in addition maintenance and ease of installation. Hence, plaster and paint is chosen as the wall finishes for the guest rooms. 22
  • 24. 4.0 Proposed change in Design In this case, the change in layout plan is the enlargement of the dining area through the reduction of lift lobby area. Figure 4.1: Proposed change in design for podium area Table 4.1: Proposed change in design for Podium Floor From the Figure 4.1 and Table 4.1 above, the open area shall be removed and change to lounge and dining area. Thus, the area of the lift lobby shall be reduced in how many 20% and the remaining area shall change to dining and lounge area to serve the guest. Therefore, the floor efficiency is increased from 2.76% to 5.01%. Thus, the circulation area at lift lobby is maintained at the acceptable size to prevent cramped space. It shows that the usable area for the dining and lounge area is increased and more revenue can be generated. 23
  • 25. 5.0 Technical data 5.1 Sound insulated solid wood doors in guest rooms Solid wood door prevents the transmission of sound waves into the guest rooms by incorporating into the door. Figure 5.1 shows how the sound waves are reduced after passing through the door. If there is no sound insulation function in the door, the sound will pass through and enter the guest rooms without reducing the amplitude. Therefore, sound insulated doors guarantee the guests a perfect room acoustics. Figure 5.1: Noise reduction through sound insulated door 5.2 Use of Precast Hollow Core Slabs The advantages of precast hollow core concrete slab over the cast-in-situ slab is shown in Table 5.1. On the other hand, Table 5.2 demonstrates the cost analysis between cast-in-situ concrete slab and precast hollow core slab. According to the study conducted by Asamoah, Ankrah, Offei-nyako, & Tutu (2016), the precast concrete slabs are 23.22% cheaper than cast-in-place concrete. Therefore, the precast hollow core concrete slab is perceived to bring cost savings with extra function which is derived by using the compound approach. 24
  • 26. According to (Nitterhouse, 2018), the comparison of hollow core slabs and cast-in-situ concrete slabs are shown as follows. Table 5.1: Comparison of usage between precast hollow core concrete slab and cast-in-situ slab PRECAST CONCRETE SLAB CRITERIA CAST-IN-SITU SLAB Mixed, poured and cured in a factory while ideal conditions and exacting measurements can be maintained throughout the process Quality Control Subject to humidity and temperature of the day doing the casting. Labour efficient as work is done in a factory Labor Efficiency Work that can be done by machines has to be do instead by hand which is much more labour intensive, therefore increasing labour costs. Can withstand raining as it is already casted, can be lifted into place during sunny day. Weather Will affect by unexpected rainstorm Due to prefabrication, insulation element can be incorporated within the concrete which can save labour and architectural design space. Insulation Can only lining the interior of the building with insulation instead of the insulating power from the slabs Can do the casting of materials ahead of time, holding them until they are needed Cast ahead of time Overlapping tasks and improving efficiency is impossible due to the amount of space and labour required for on-site casting. 25
  • 27. Table 5.2: Cost comparison between cast-in-place and precast floor slabs; Sources: Asamoah, Ankrah, Offei-nyako, & Tutu (2016) 5.3 Eliminate glass skylights in roof covering The concrete flat roof is replaced instead of skylights in roof covering in the proposed project. The reason that the skylights is eliminated is because ​the amount of light and heat cannot be controlled that comes through the skylights. And due to the direct sunlight penetration into the rooms, it produces an unpleasant glare to the surface, and therefore making it uncomfortable to do activities in the podium. For concrete flat roof, it is easy to clean. For example, ​when cleaning a roof of stains, molds and algae, pressure washing is often the fastest and most effective method. Pressure washing on a flat concrete roof is less likely to damage the surface of the roof. Unlike skylights, cleaning of the skylight becomes a hectic job as the placement of skylight is in the roof. One of the most important reasons the 26
  • 28. concrete flat roof is because the installation cost is cheap. The installation cost and maintenance of the skylight is more when compared to concrete flat roof. In the conclusion, concrete flat roof is considered a more affordable option than skylights. 5.4 Change corridor lightning from Fluorescent Light to LED light Light Emitting Diodes (LED) light is chosen for corridor lighting for the proposed project rather than fluorescent light because ​they last longer than compact fluorescent lamp (CFL) which is energy saver bulbs,and the consumption of energy is less. The long average lifespan of LED light is 50,000 hours, whereas for the fluorescent light, it is 8,000 hours. Fluorescent light will emit infrared radiation which will lead to ​eyesight loss, and in some cases it can even cause blindness. ​LEDs do not produce infrared radiation and contain heat sinks to help them remove unwanted heat, thus making them cooler to touch. ​By replacing fluorescent light bulbs with energy efficient LEDs will lower the lighting costs, since they consume far lesser energy. However, LEDs must be supplied with the voltage above the threshold and a current below the rating. Current and lifetime change greatly with a small change in applied voltage.Also, the efficiency of LEDs reduces as the electric current increases. Heating also increases with higher currents which compromises the lifetime of the LED. However, according to all the reasons above, LED light is used for this project due to its efficiency and long lifetime. 27
  • 29. Table 5.3: Life cycle cost comparison of LED, Halogen, CFL Halogen CFL LED Hardware Costs Cost per bulb RM 3.50 RM 12.50 RM 13.00 Average lifespan (hours) 1,500 8,000 25,000 Bulbs needed for 25,000 hours of use 21 2.5 1 Cost to replace bulbs over 25,000 hours RM 58.33 RM 39.06 RM 13 Energy Costs Watts 53 18 12 Energy usage for 1 month at 4 hours a day (kWh/month) 6.36 2.16 1.44 Energy costs for 25,000 hours of use 48.13 16.63 10.90 Total Costs Hardware + energy costs over 25,000 hours RM 106.46 RM 55.69 RM 23.90 28
  • 30. 5.5 Change wall finishes from wallpaper to plaster & paint For wall finishes, we use the plaster and paint instead of wallpaper ​because paint is a very affordable option when you need to transform the outlook of your home. There are a few advantages of painting over wallpaper shown in Table 5.3. To restore the uniformity of this part of the wall, you need to repair and repaint it. Thus, despites the pros and cons of the paint and wallpaper, plaster and paint is chosen to improve the value of the proposed project. Table 5.3: Advantages of plaster and paint over wallpaper Criteria Description Inexpensive Affordable option Ease of application In a case where you are painting over a damaged wall, you can apply primer paint in advance to applying paint over a darker colour. This shortens your preparation time and makes the process easier. Universally applicable It is applicable to any rooms in hotel, unlike wallpapers can only be applied in high moisture rooms. Correcting mistakes A painting mistake can easily be painted over creatively. In the case of wallpapers, rectifying mistakes is tougher and requires more scrapping. 29
  • 31. 6.0 Cost Analysis 6.1 Change to sound insulated solid wood doors in guest rooms V.M RECOMMENDATION ITEM: CHANGE TO SOUND INSULATED SOLID WOOD DOOR IN GUEST ROOMS ORIGINAL DESIGN PROPOSED DESIGN Hollow core timber door Sound insulated solid wood door COST BREAKDOWN Total number of door = 126 door Cost per door = RM 300 Total cost = RM 37,800 Total number of door = 126 door Cost per door = RM 750 Total cost = RM 94,500 COST SUMMARY RM 37,800 RM 94,500 Cost Savings​​ / Extra Cost RM 56,700 (150%) By changing the guest room door from the hollow core timber door to sound insulated solid wood door, the client need to spend an additional cost of RM 56,700.00, which is 150% higher than the original cost. 30
  • 32. 6.2 Use of Precast Hollow Core Slabs V.M RECOMMENDATION ITEM: USE OF PRECAST HOLLOW CORE SLABS ORIGINAL DESIGN PROPOSED DESIGN Cast-in-situ floor slabs Precast hollow core slabs COST BREAKDOWN Total Area = 36,113m2 Cost per m2 = RM60/m2 Total Cost = RM 2,166,780 Total Area = 36,113m2 Cost per m2 = RM 48/m2 Total Cost = RM 1,733,424 COST SUMMARY RM 2,166,780 RM 1,733,424 Cost Savings / ​​Extra Cost RM 433,356 (20%) By changing all the suspended slab from cast-in-situ floor slabs to precast hollow core slabs, the client can save an additional cost of RM 433,356.00, which is 20% less than the original cost. 31
  • 33. 6.3 Eliminate glass skylights in roof covering V.M RECOMMENDATION ITEM: ELIMINATE SKYLIGHTS IN ROOF COVERING ORIGINAL DESIGN PROPOSED DESIGN Glass Skylights Concrete flat roof COST BREAKDOWN Size = 8.2m x 2m = 16.4m2 Total unit = 2 unit Cost per m2 = RM 495/m2 Total cost = RM 16,236 Size = 8.2m x 2m = 16.4m2 Total unit = 2 unit Cost per m2 = RM60/m2 Total Cost = RM 1,968 COST SUMMARY RM 16,236 RM 1,968 Cost Savings / ​​Extra Cost RM 14,268 (88%) By eliminating the skylight in the roof covering and change it to the concrete slab roof, the client can save an additional cost of RM 14,268.00, which is 88% less than the original cost. 32
  • 34. 6.4 Enlarge the dining lounge area V.M RECOMMENDATION ITEM: ENLARGE THE DINING LOUNGE AREA ORIGINAL DESIGN PROPOSED DESIGN Small dining area Enlargement of dining area COST BREAKDOWN Number of seat = 74 seat Open Hour = 10hr Spending per guest = RM 110 Turnover rate = 2hr per guest Total earning per year = 5 guest x RM110 x 74 seat x 7 days x 4 weeks x 12mth = RM 13,675,200 Worker = 15 worker Salary per month = RM 7,000 Ingredients per people = RM 50 Total expenses per year = (15 x RM 7,000) + (74 seat x RM 50) = RM 108,700 Profit = RM 13,566,500 Number of seat = 142 seat Open Hour = 10hr Spending per guest = RM 110 Turnover rate = 2hr per guest Total earning per year = 5 guest x RM110 x 142 seat x 7 days x 4 weeks x 12mth = RM 26,241,600 Worker = 30 worker Salary per month = RM 7,000 Ingredients per people = RM 50 Total expenses per year = (30 x RM 7,000) + (142 seat x RM 50) = RM 217,100 Profit = RM 26,024,500 COST SUMMARY RM 13,566,500 RM 26,024,500 Loss profit​​ / Earn Profit RM 12,458,000 (92%) By having the larger space of the dining area, client can increase group bookings by hosting business conferences, special events, reunions, family gatherings and weddings. These can help to fill in the rooms during normal slow seasons. The dining is taken as a profit generator as well instead of an amenity to the hotel. 33
  • 35. 6.5 Change corridor lightning from Fluorescent Light to LED light V.M RECOMMENDATION ITEM: CHANGE CORRIDOR LIGHTNING FROM FLUORESCENT LIGHT TO LED LIGHT ORIGINAL DESIGN PROPOSED DESIGN Fluorescent light LED light COST BREAKDOWN Total number of bulb = 133 Cost per bulb = RM 12.50 Energy Cost = RM 16.63 Total cost = RM 55.69 x 133 = RM 7,406.77 Total number of bulb = 133 Cost per bulb = RM 25 Energy Cost = RM 10.90 Total cost = RM 35.90 x 133 = RM 4,774.70 COST SUMMARY RM 7,406.77 RM 4,774.70 Cost Savings / ​​Extra Cost RM 2,632.07 (36%) By changing all the lightning at corridor from fluorescent light to LED light, the client can save an additional cost of RM 2,632.07 which is 36% less than the original cost. 34
  • 36. 6.6 Change wall finishes from wallpaper to plaster & paint V.M RECOMMENDATION ITEM: CHANGE WALL FINISHES FROM WALLPAPER TO PLASTER & PAINT ORIGINAL DESIGN PROPOSED DESIGN Wallpaper Plaster and Paint COST BREAKDOWN Total area = 6471.36m2 Cost per m2 = RM 77/m2 Total Cost = RM 498,294.72 Total area = 6471.36m2 Cost per m2 = RM 36/m2 Total Cost = RM 232,968.96 COST SUMMARY RM 498,294.72 RM 232,968.96 Cost Savings / ​​Extra Cost RM 265,325.76 (53%) By changing all the wall finishes of the guest rooms from wallpaper to plaster and paint, the client can save an additional cost of RM 265,325.76.00, which is 53% less than the original cost. 35
  • 37. 6.7 Cost Summary Cost savings from specification changes: ELEMENT ORIGINAL REVISED Total (RM) Total (RM) Arhitectural Wall finishes 498,294.72 232,968.96 Roof finishes 16,236.00 1,968.00 Door 37,800.00 94,500.00 Structural Floor construction 2,166,780.00 1,733,424.00 M&E Lighting 7,406.77 4,774.70 TOTAL 2,726,517.49 2,067,635.66 TOTAL SAVINGS 658,881.83 (24%) In conclusion, the client is able to save up to RM 658,881.83 which is 24% less than the original cost by applying these changes as mentioned in the previous sections. At the same time, the value of the resort is also increased. 36
  • 38. 7.0 Action plan An action plan is prepared to implement the accepted recommendations during the value management workshop. The action plan shows the actions need to be carried out by the design team during the implementation. It is used to monitor the progress of the implementation. Table 7.1: Action Plan CATEGORY RECOMMENDATIONS TASK ACTION TIMELINE Architectural Doors (typical guest rooms) Change to sound insulation solid wood door Amendment of specification in drawings Architect Detailed Design Stage Revise cost plan Quantity Surveyor Roof finishes Eliminate skylights in roof covering Revised drawing by changing the skylight into flat roof Architect Detailed Design Stage Revise cost plan Quantity Surveyor Wall finishes (typical guest rooms) Change wall finishes in guest rooms Change wall finishes specification in drawings Architect Detailed Design Stage Revise cost plan Quantity Surveyor Podium Enlarge the dining lounge area Enlarge the dining lounge area in drawings Architect Detailed Design Stage Revise cost plan Quantity Surveyors 37
  • 39. CATEGORY RECOMMENDATIONS TASK ACTION TIMELINE Structural Superstructure Change floor construction to precast hollow core slabs Amendment of C&S drawings Civil & Structural Engineer Detailed Design Stage Revise cost plan Quantity Surveyor M&E Corridor lightning Change from fluorescent light to LED light Propose changes of lighting Architect Detailed Design Stage Revise cost plan Quantity Surveyor Amendment of M&E drawings M&E Engineer 38
  • 40. 8.0 Conclusion and recommendation In a nutshell, the Value Management study carried out by our consultant team successfully produced the value report that listed proposals for change in relation to material changes, spatial change, elimination of elements and components of the hotel. This study aims to assure the client can achieve the highest value for money in the design so that the project can be built within the budget. A number of significant savings resulted from the proposals made. Approximate 24% of cost saving is achieved through the value proposals for this project which resolve the client’s key problem - over budgeting. Besides, the client’s aim to achieve the value for money is achieved during the end of the value management workshop. It is strongly recommended that the Value Management study to be implemented for all construction projects, especially during early design stage. Identification of client’s requirements is made through function analysis was the main benefit and justification of the value proposals to the client and project design team. Without the value analysis technique, the value proposals would have little influence on the client and project design team’s thinking. According to the cost analysis, the project is confirmed that it could be completed within the budget as opposed to the original design which would exceed the budget. 39
  • 41. 9.0 References Asamoah, R. O., Ankrah, J. S., Offei-nyako, K., & Tutu, E. O. (2016). Cost Analysis of Precast and Cast-in-Place Concrete Construction for Selected Public Buildings in Ghana, ​2016​. ​https://doi.org/10.1155/2016/8785129 BG_Property_Maintenance. (2018, January 17). Incandescent Bulb vs CFL Bulb vs LED Bulb Part II • B&G Property Maintenance. Retrieved November 14, 2018, from http://bgpmaintenance.com/incandescent-cfl-led-part-ii/ Biobaku, S. (2018, June 21). Wallpaper Vs Paint: Which is Better For Your Home? | Private Property. Retrieved November 12, 2018, from https://www.privateproperty.com.ng/news/wallpaper-vs-paint/ Compare Wallpapering vs Painting Costs. (n.d.). Retrieved November 12, 2018, from https://www.kompareit.com/homeandgarden/painting-compare-paint-vs-wallpaper. html Comparing LED vs CFL vs Incandescent Light Bulbs. (2018, March 30). Retrieved November 14, 2018, from https://www.viribright.com/lumen-output-comparing-led-vs-cfl-vs-incandescent-wa ttage/ Kang, Y. J. (2018, September 06). Will you actually save more with LED lights? Retrieved November 13, 2018, from https://www.recommend.my/blog/will-you-actually-save-more-with-led-lights/ LED vs. CF vs. Incandescent. (n.d.). Retrieved November 14, 2018, from https://www.homepower.com/articles/home-efficiency/electricity/led-vs-cf-vs-inca ndescent Nitterhouse. (2018). Precast Concrete VS Site Cast Concrete, 1–7. 40