SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN
BACHELOR OF QUANTITY SURVEYING
MARCH 2017 INTAKE
​SOFTWARE APPLICATION FOR QUANTITY SURVEYING
[CSC 60603]
ASSIGNMENT 1
GROUP MEMBERS:
NO. NAME STUDENT ID
1. NG SIEW QING 0325750
2. NGIENG TIEN YUNG 0320221
3. NGO JIA HAUR 0320144
4. OOI YIN JI 0319962
5. PANG KAI YUN 0319802
6. SAM WEI YIN 0320364
7. SANDRABROOKE GOH 0329884
LECTURER : SR. YEAP SOON KIAT
SUBMISSION DATE : 5TH MAY 2017
TABLE OF CONTENT
No. Content Page No.
1. Introduction 3
2. Part A
2.1 Buildsoft
2.2 Glodon
2.3 CostX
2.4 Vico Software
2.5 Summary
2.6 Recommendation
4 - 16
3. Part B
3.0 Preparation / Briefing Stage
3.1 BIM
3.1.1 BIM Benefits
3.1.2 BIM Constraints
3.2 CAD Measurement
3.2.1 CAD Benefits
3.2.2 CAD Constraints
3.3 Manual Measurement
3.3.1 Manual Measurement Benefits
3.3.2 Manual Measurement Constraints
17 - 18
4. 4.0 Design Stage
4.1 BIM
4.1.1 BIM Benefits
4.1.2 BIM Constraints
4.2 CAD Measurement
4.2.1 CAD Benefits
4.2.2 CAD Constraints
4.3 Manual Measurement
4.3.1 Manual Measurement Benefits
4.3.2 Manual Measurement Constraints
19 - 21
1
TABLE OF CONTENT
No. Content Page No.
5. 5.0 Pre-construction Stage
5.1 BIM
5.1.1 BIM Benefits
5.1.2 BIM Constraints
5.2 CAD Measurement
5.2.1 CAD Benefits
5.2.2 CAD Constraints
5.3 Manual Measurement
5.3.1 Manual Measurement Benefits
5.3.2 Manual Measurement Constraints
22 - 24
6. 6.0 Construction Stage
6.1 BIM
6.1.1 BIM Benefits
6.1.2 BIM Constraints
6.2 CAD Measurement
6.2.1 CAD Benefits
6.2.2 CAD Constraints
6.3 Manual Measurement
6.3.1 Manual Measurement Benefits
6.3.2 Manual Measurement Constraints
25 - 27
7. 7.0 Post-construction Stage
7.1 BIM
7.1.1 BIM Benefits
7.1.2 BIM Constraints
7.2 CAD Measurement
7.2.1 CAD Benefits
7.2.2 CAD Constraints
7.3 Manual Measurement
7.3.1 Manual Measurement Benefits
7.3.2 Manual Measurement Constraints
28 - 29
8. Reference 30
2
1.0 Introduction
This report is a summarised research on various types of software programs that are
accessible in the construction field. It is divided into two parts which Part A will be focus on the
functions and limitation of different BIM QS software programs while the benefits and
constraints of BIM, CAD Measurement and Manual Measurement will be further discuss in Part
B. The best BIM QS software has also been discussed based on the our justifications and data
in the report.
BIM is rapidly becoming a fundamental tool which works best in managing building
information in recent construction market. A project receives information from various sources
such as engineer, architect, M&E engineer, quantity surveyor etc which often makes the
information management more complicated. Therefore, BIM is a reliable process that works to
gather the inputs from different sources to turn the information into a 3D model for a better
visualisation. It is a way to change and improve the traditional data sharing among the parties
which the communication can be greatly enhanced. Application of BIM covers all construction
project stages including pre-construction phase, construction phase and post-construction
phase. It improves the communication between the construction players by facilitating the
design decision in a faster process. Besides, BIM ensures a quicker project completion time as
it helps in organizing the project during its initial planning stage of the construction.
On the other hand, due to it’s significant impact on construction field, major industry
professionals tend to shift towards to the use of BIM. It is said that the industrialisation,
automation and computerisation of BIM would eventually diminish the role of Quantity Surveyor
in the construction industry. In fact, according to RICS report, the ability of BIM to automate
measurement is the key advantage for Quantity Surveyors in terms of improvement in efficiency
and accuracy in cost estimating. Quantity Surveyors still have to analyse the design, consult the
clients, interpret and extract the quantities as well as aligning the measurement according to
SMM2 where all these works could not be done by BIM itself only.
Despite of the benefits that BIM brings to construction sector in Malaysia, its application
remains at infancy stage. BIM is perceived as new in Malaysia and a costly tool to be widely
practiced among the parties. However, it is expected that BIM will be in high priority in future
with the assistance of government’s efforts.
3
PART A
2.1 Buildsoft
Buildsoft is a software that provide the construction and building industry with standard
estimating software where ​it offers few different types of products such as global estimating,
offsider estimating, subbies comparison, digitizer boards and so on. The buildsoft product that
will be emphasized in this report is Buildsoft Global Estimating System. This software comprises
of items such as price book, take-off system, screenshots, project analysis, bill of quantities and
four level estimating, takeoff schedules, BETS, system requirements. Buildsoft is a very easy
hands on software that every builder or subcontractor or even design team such as quantity
surveyor to use and also it can be used by people with little or no experience in terms of using
personal computers. In a nutshell, Buildsoft will not dissapoint the user as it offers complete
features that will meet the user's needs.
2.1.1 Function of Software
2.1.1.1 Bill of Quantities
Global Estimating is to produce bills of quantities. Bills of quantities are an important aspect that
required for acknowledging the quantities of materials, rate for each materials and the total sum
for all the material uses in the project. This enable user to do cost estimating, producing cost
data and cost plan. By using global estimating, bills of quantities are able being produce in 4-
level estimating which are job summary, trade breakup, calculation sheet and also rate breakup.
In a more detailed explanation, level one is job summary where user can key in the elements
that will have in the project. This sheet is where the subtotal elements of the estimate cost will
be shown. So in each different element or job, different job can be set under different trade
4
name. Each of the job can be marked up or some other extra contingency factor be applied
differently and individually according to the element. In another hand, percentage of cost
distribution will also be shown in this level as well as for labour and material summary will be
separated for user easy references.
Level two is trade breakup level where this level will contain the bill of quantity item for each
element which each of the element has its own trade break-up sheet. In this level, user are able
to put in specification that required for the project and user are able to key in the details of each
element as detail as possible to produce bills of quantities. Quantities for each element can be
typed in, calculated in detail or derived from digitizer and rated can be typed in as well or either
being linked to price list or produced in a break up sheets.
Level three is calculation sheet level. In this level, user are allow to put in the dimension of each
elements to calculate the quantity where in the end, the total of the calculation will be returned
to quantity column in Trade breakup level. Deduction for the calculation also can be key in
during this level where this provide a very convenient measurement for the user. Lineal, area
and volume calculation are allowed in this level as it will mostly depend on the description of the
elements.
Level four is rate breakup sheet where user can build up a composite rate that includes
materials, labour, sub-contract, and equipment components for item rate. In rate breakup sheet
level, rates can be key in or linked to the price list and also mathematical formula can be used in
this level.
2.1.1.2 Composite rates
Rates are considered as a very significant element which client and contractor will be focus on
when looking into the bills of quantities. Client would wish to get the best rates from contractor
and contractor will not want to over price the rate in order to get the tender of the project. This
software could help user to clearly state out the price and rates for all the elements neatly and
hence this could give user an easy review of rates for the project. In global estimating system,
the rates can be built up and it can be composite the rate for each item. Nevertheless, it can be
saved in price list or library so that user of this software can refer to the price list saved. Since
the rates are kept in the price list or library, they can be transferred from pricelist into a new job
5
if there is a new tender. This gives the user an easier and faster way which can help user to cut
off the time consuming period of user preparing bills of quantities.
2.1.1.3 Multi-level mark up function
In every project, preparation of markup price rate is a compulsory step for a quantity surveyor to
do in all of the projects. This is because the rate of the materials or any other stuff might be
different compare to the price when tenderer tendering the project and after contractor starts to
commencing the work in which economics will affect the rates of everything. This could help all
parties to prevent themselve facing financial loss. The markup rate is to revise the job or
element or item total. Usually, the item that will be marked up is profit, overhead and also
wastage. This is considered as easily adjusting the tender sum.
2.1.1.4 Analysis
In Global estimating, analysis of cost, job and quantity can be analysed. For cost analysis, the
software can analysing the overall materials and labours cost in particular job and this can
provide the overall quantities for all types of materials in particular job. In another hand, for job
analysis can be abstracting part of the building quantities item out from a job and it will be
converted into trades bill. This can enable to prepare sub contractor bill of quantities more easy.
Last but not least, quantities analysis are being analysed and being differentiate the item's
quantity into stages or level.
2.1.2 Limitation of Software
2.1.2.1 Permanently deleted
The job file that had been created in buildsoft global estimating system will be permanently
deleted when any amendment are being done on the existing data. In another meaning, there is
no undo button to undo the action. The amendment that had been done cannot be called back
so user have to be careful when doing any amendment work.
2.1.2.2 Virus Attack
Whenever using the internet, virus attack is very common problem that user will face. To own
safe purposes, user should have licensed anti-virus software so that the virus definition can be
update daily. If there is no anti virus software, the virus can attack the computer system and
also all the content in the computer and hence that will cause the loss of data in the software
system and may be can not be recovered by any means.
6
2.1.2.3 Unable of reviewing of Building Modeling
Buildsoft Global Estimating system does not offer user to see the project building model neither
in two dimensional view nor three dimensional view. This software is only able to produce a
good and nice bills of quantities, however, user will still need to refer to architectural and
structural drawing in hard copies.
7
2.2 Glodon
Glodon is founded in 1998. Cubicost is a new brand of Glodon in international market. Cubicost
BIM suite is comprised of four individual BIM-based software products which are Cubicost
Takeoff for Architecture and Structure (TAS), Cubicost Takeoff for Rebar (TRB), Cubicost
Takeoff for Mechanical and Electrical (TME), and Cubicost TBQ. All these four products
together virtually cover all general requirements in construction cost estimation business.
Moreover, BIM model and related data can be easily transferred between four products,
bringing you the most professional, efficient and accurate BIM cost estimation experience.
2.2.1 Function of Software
2.2.1.1 Cubicost Takeoff for Architecture and Structure (TAS)
TAS is embedded with Commonwealth of England calculation rules. It enables the users to
create a 3D model for better visualization effect. Thus, the result can be more accurate. By
using TAS, the users can import directly the electronic drawings such as IFC, DWG and PDF
drawings, thus the 3D model can be built efficiently. Changes or variations can be done quickly
by adjusting the model information and the calculation will be modified accordingly. It is a
quantity calculation software which is simple, helpful and accurate with just one click to
complete all the measurement work. TAS also owns Built-in Localized calculation rules as in
different markets such as SMM2, SMM4, SMM7 and etc. Besides, it is compatible with Autodesk
Revit format. (RVT) and popular 2x3 IFC format. TAS also support import and export of IFC
format.
2.2.1.2 Cubicost Takeoff for Rebar (TRB)
TRB is embedded with groundbreaking 3-dimensional measurement and calculation rules,
including British Standards and Uniform Building By-Law. Built-in calculation setting based on
British Standards and Uniform Building Bye-Law. Interchangeable calculation mode between
8
Tendering Mode and Prefabrication Mode to 5 address different requirements. TRB allows 3D
model to be imported from TAS to calculate rebar quantities. The deduction calculation can be
done more precise as the elements are linked automatically for deduction as well as anchorage
calculation integrally. Then, it can produce Rebar Schedule for fabrication on site. By using
TRB, the calculation result will be with detail breakdown which helps to provide convenience in
auditing results. Besides, it is also advantageous in variation with synchronization between
models and quantities. Various reporting format is also available.
2.2.1.3 Cubicost Takeoff for Mechanical and Electrical (TME)
TME allows quantity surveyors to do taking-off quickly for CAD and other drawings. For
examples, TME is fast in calculating all equipment in a drawing with one click to auto identify
pipes, wires, cables and ducts, resolving issues such as cumbersome manual measurement,
difficulties in auditing and low efficiency in quantity takeoff for construction, quantity checks for
settlement and the stage of tender. TME is having the built-in customizable calculation rules.
Therefore, the calculation rules of different disciplines are provided and support customization.
Besides, quantity surveyors can perform reverse checking easily to analyze quantity difference
if there is any by discovering entity from the report. Next, TME can provide a summarised
quantity reports which can be fully used in the whole process of tendering. These reports are
classified according to different sectors such as elements, location etc. By mastering TME, a
visualized MEP can be viewed clearly through a 3D model. TAS project can be imported to
enable the team members to have a more detailed and interesting experience of visualisation.
All the effects such as 360 degree viewing allows us to understand the details of the building
better.
2.2.2 Limitations of Software
2.2.2.1 Cost
License of Glodon software is costly thus there are only small number of QS firms afford to
implement Glodon in their companies especially those smaller firms. Hence, those QS firms
would rather use other BIM-based taking off softwares such as CostX and Vico since it is much
more affordable although having less functions as compared to Cubicost.
9
2.2.2.2 Newly introduced in the industry
In fact, Glodon is still a relatively new BIM-based product which offers the function of taking off
in the construction market. There are limited countries which practice this software. As for a new
software, it is constantly experiencing software updates and improvement thus it is not a
completely stable product yet. There may be some flaws or constraints that affect the
performance of this product. Moreover, there are not much users who are familiar with the
usage of GLODON as it requires training to ensure the staffs are familiar with the functions to
make good use of the software.
2.2.2.3 Lack of experts
Since, Glodon is considered as one of the new software in the industrial, hence, there are lack
of experts who are working in the field. An additional investment in training and education is
required during software implementation.
2.2.2.4 Incompatibility with partners
Currently, GLODON is not yet commonly practiced by construction professionals in Malaysia as
it is that one of the partners or subcontractors may not be using Glodon. Therefore, they may
not be able to access and take information from the models. Hence, inconvenience would be
caused in terms of communication between the partners.
10
2.3 CostX
CostX is one of the BIM software which was published on the year of 2014. It is a software that
enables a quantity surveyor to do taking off from 2D drawings quickly and accurately. Besides,
costX owns a most advanced electronic taker off system that can automatically generate
quantities from 3D models. Through costX, we can prepare estimates, bills of quantities and
tenders in a quicker way.
2.3.1 Function of Software
2.3.1.1 Support 2D taking off
CostX enables quantity surveyor to prepare 2D taking off accurately and quickly because it
supports various types of file including PDF and CAD. Quantity surveyor does not need to open
CAD or PDF while doing taking off. Unlike other software, you will need to take few step before
u can take measurement of a specific area or length. CostX could measure area, length with
only a click. All this could save a lot of time for professions who are involved in construction.
2.3.1.2​ ​Support 3D taking off
CostX also supports a 3D file or BIM file such as Revit, archiCAD, sketchup and other bim file.
Through costX, we can navigate around the mode. For example, we can rotate around the
model via rear, front, side or other perspectives with only using a mouse. In addition, by utilising
costX we can explore the properties of the building easily. Also, they can add user defined
model properties into the schedule to supplement the existing model data. Next, it can extracts
quantities and create a customized estimate by using the function of object based dimension
groups. Lastly, it could also allow us to measure manually in this software.
11
2.3.1.3 Workbook
The workbook sides of costX includes live-link, rates, codes, phraseology and constant plus the
standard and custom report writer. Existing rate libraries can be imported from excel and the
data will live- link to estimate. It will auto update the quantity and estimate if there are any
changes.
2.3.1.4 Auto-revisioning
The function of this auto revisioning is to help us to identify amendments and changes of the 2D
and 3D drawings and update the quantity when necessary. Quantity surveyors can compare the
dimension of old and new drawing and display them for adjustment easily. One of the
advantages of this auto-revisioning is the old version of drawings and workbook will be locked
and the users are unable to do any measurement on it.
2.3.1.5 Sub-contractor Comparison
In CostX, there is this function called subcontractor comparison. The quantity surveyor could
compare the subcontractors in terms of their trades. They can generate workbook which allow
subcontractor details to be entered and compared. It eases quantity surveyors as they do not
need to key in the information of subcontractors in each time.
2.3.2 Limitation of Software
2.3.2.1 Cost and license
The initial cost to install this software is high in terms of hardware and license. In addition, there
are few type of license for this software which is ​standalone, network and portable. Each of this
option carry different price.
2.3.2.2 Rebar detection
CostX could not detect the reinforcement bar in the column. Quantity surveyor need to measure
it separately. This might cause overmeasure of BRC.
12
2.4 Vico Software
Vico software established different types of construction software and services which
contributes to the construction industry. The construction software are Vico Takeoff Manager,
Vico Cost Manager, Vico LBS Manager, etc. These software are generally used by contractors
and construction managers to minimize the risk, improve schedules for large scale projects and
manage construction costs. Besides, Vico’s 5D Virtual Construction solutions which launched by
Vico software remain the construction industry’s integrated approach to quantity takeoff, project
scheduling, coordination and cost estimation. Also, the file formats which are related with BIM
such as ArchiCAD, Tekla, Revit and etc are applicable to the new Vico Office products.
2.4.1 Function of Software
2.4.1.1 Vico Takeoff Manager
Vico Takeoff Manager is using a unique geometry analysis algorithm to produce quick and high
accuracy of quantity takeoff by scanning 3D model which created from authorized BIM tools.
The user has to visually verifies the elements in the 3D model included in the quantities. For the
quantity calculations, user has to adjust the changes manually by adding or subtracting the
model elements in the 3D model. Besides, Vico Cost Planner and Schedule Planner modules
can takeoff data by location automatically. Hence, it does not require to export and import data.
As a result, the accuracy for cost planning and schedules are increased.
2.4.1.2 Vico Cost Planner
Vico Cost Planner allows cost calculation, cost estimating, and value engineering module. It can
use the quantities generated from Takeoff Manager to produce a highly accurate amount in
estimation within a short period of time. Besides, Cost Planner provides cost feedback at
different project phases starting from design phase to close out phase. Nevertheless, Cost
Planner also allows the users to keep and store the important and reusable projects data for
further usage.
13
2.4.1.3 Vico Constructability Manager
Vico Constructability Manager able to detect constructability issues for the published models.
With Constructability Manager, users can do a comparison on the models in terms of layer by
layer or different types of element. The user can easily make amendment on the model and
rerun the comparisons to produce a new model. Besides, Constructability Manager able to
generate a constructability report that included all constructability issues for any current status
of a project.
2.4.1.4 Vico LBS Manager
Vico LBS Manager help the user to differentiate the location structure which is the combination
of floors or zones in a building. The location structure defined in the LBS Manager able to
maintain a uniform location structure for all project information published to the Vico Office
Project. Besides, LBS Manager can recalculate the quantities and update the result at the end
of the editing process whenever the changes on floors or zones are made without going back
for the BIM application. Therefore, it can produce a best project schedule as the phasing and
zoning of a project are optimized.
2.4.1.5 Vico Schedule Planner
Vico Schedule Planner combines the function of Vico Takeoff Manager, Vico Cost Planner and
Vico LBS Manager which can produce a highly optimized project schedule. Vico Schedule
Planner ensures a smooth project flows by adding the size of crew, productivity rates and
geography specific pricing. With this, users can compress the work schedule without increasing
the risk as they can control task buffers and identify conflicts easily. As a result, the productivity
and predictability are increased to deliver the projects within a short period.
2.4.2 Limitation of Software
2.4.2.1 Inefficient
By using Vico Software software, each time only can operate one model file. Hence, it is
inefficient as it takes a longer time to produce project’s document compared to other BIM
software.
14
2.5 Summary
Software
Feature
Buildsoft Glodon CostX Vico
Simplicity Yes Yes Yes No
Taking-off Yes Yes Yes Yes
Application for
Architect and Engineer
No No No No
Able to read different
type of drawing
No Yes Yes Yes
Able to export into
other formats
No Yes No Yes
15
2.6 Recommendation
Nowadays, there are various types of BIM QS software available in the industry. Each
and every software would definitely has its own leading features as well as the limitations.
Therefore, the best BIM QS software does not necessarily means to have the most features but
having the most appropriate and functional feature that meet the user’s requirements to
effectively ease their job.
Based on our study and understanding on the 4 BIM QS software that we had chosen,
we would like to recommend Cubicost by Glodon as the best software among these four
softwares. Firstly, Cubicost by Glodon is easy to operate. Most of the things could be done with
just a click. For example, changes and variation could be quickly made with just a click by
adjusting the model information and the calculation will be modified accordingly. This could
definitely gives the user a more accurate result as they do not need to make changes or
variation for each part and so, all those human errors such as careless mistake could be
avoided.
Secondly, Cubicost by Glodon able to provide the user a better visualisation as a 3D
model will be created as they key in all the related information or data accordingly. TME can
auto identify the pipes, wires, cables and ducts. Hence, a visualized MEP can be viewed clearly
through a 3D model. The users will have better understanding on the details of the building
through these unique features such as 360 degree viewing.
Last but not least, the user can save a significant sum of time by using Cubicost by
Glodon due to the special features like on-screen taking off, 3D visualisation and paperless
estimating. Traditional way of doing measurement is totally not needed if using this software.
The quantity surveyor could no longer spend such a long period of time for scaling and taking
off the data from the drawing. As a result, the workload could be ease and the process of
preparing a BQ could be speed up. The time saved could then turns into profit.
16
PART B
3.0 Briefing/ Preparation Stage
3.1 Building Information Model (BIM)
3.1.1 BIM Benefits
a. Visualization improved by 3D Model - Better visualization enables the contractor to
understand the site planning of the project easily even at the preparation stage. 3D
modeling services also creating a virtual environment, which help to convince the project
team and contractor present their rough idea of design to their client.
b. Improve the communication and the coordination among different parties - As a result of
BIM provide a visualization services as an entry services, therefore BIM acts a platform
that show all the progress of the project at any given moment from different party who
access to the model. It allows the project members to communicate their idea to each
other. Besides, it is able to identify any potential risk of delay or error before hand-in the
project thus avoiding extra expenses incurred.
3.1.2 BIM Constraints
a. High cost for software and training - The cost of the BIM software is very expensive.
Secondly, it also requires staff training because it involves a lot of complication during
implementation.
3.2 CAD Measurement
3.2.1 CAD Benefits
a. Database for manufacturing - Designers will include the data such as material,
dimension and shapes of the components etc in CAD when creating the documentation
for designing purpose. These data can be used for manufacturing as well.
b. Increase value to client - CAD software enables designers to explore and produce
conceptual proposals in a shorter time frame. For instance, designers can produce and
evaluate alternative designs for a proposed housing area to the client. Hence, a higher
level of service has been proposed to the client which differentiate us from potential
competitors.
c. Visualisation - Client is able to look at virtual reality simulations of the layout of the
proposed buildings. It is cheaper to make any amendment at briefing stage rather than
17
when the building is in construction stage. It ensures a higher quality of the end product
which matches the specification and expectation of the client more.
3.2.2 CAD Constraints
a. High initial cost - High expenses incurred to implement CAD which includes the cost of
software itself, cost of computer hardware, software updates as well as training cost for
the workers.
b. Software Complexity - CAD becomes more versatile and adaptable as it advances.
However, the software itself becomes more complicated which makes it difficult for the
first-time users to practice the software.
3.3 Manual Measurement
3.3.1 Manual Measurement Benefits
a. Cost Effective - Manual measurement is very cost effective compared to BIM and CAD
measurement as it does not require to purchase any software which is very costly. It
would only cost mainly on the printing hence it saves a lot of money.
b. No Training Is Required - Every quantity surveyor know how to do manual measurement
while not every quantity surveyor know how to do BIM and CAD measurement because
it requires technical skills to use the software to do measurement. Therefore, extra
training is required for them to master the software.
3.3.2 Manual Measurement Constraints
a. Errors - There is a risk of human errors as quantity surveyor is rushing to complete the
cost estimates. They have to use a well-organized systematic method of takeoff to avoid
overmeasure or under measure. Besides, scale of the drawings is not as accurate as
software thus leading to measurement discrepancies.
b. Time consuming - Manual measurement consumes more time than BIM and CAD
measurement because manual measurement is practiced by using measurement tools
such as scale rule and calculator. The quantity surveyor need to measure and scale
everything manually so it takes longer time as manpower has its limits. This will delay
the time of task completion.
18
4.0 Design Stage
4.1 Building Information Model (BIM)
4.1.1 BIM Benefits
a. High graphic perspective of 3D modeling that everyone can easily understand - BIM is
created for the purpose of designing building. It creates the drawing that everyone can
understand because this application provide a 360-degree rotation of a 3D model.
Moreover, every view or component for a building in interconnected. For example, if the
users do any adjustment on window in a building. All of the windows’ dimension will be
adjusted and updated automatically.
b. Improve efficiency - Clash detection is the one advantage that would improve the
efficiency during design phase. All the error or clash that will impact the construction
process will be mentioned so the potential issue can be settle before the construction
start.
c. Reduce the material usage - Compared to the traditional method such as CAD
measurement or manual measurement, the use of BIM can reduce the material cost
because BIM has potential to eliminate construction waste sources. We can use the BIM
drawings and calculations to show the reduction of material use through the building
design.
4.1.2 BIM Constraints
a. Require trained or experienced technical staff - BIM is unfamiliar and tedious, so it
requires the technician who owns the skills and knowledge on how a project designed
and documented. However, it is more time consuming due to the training programme for
the staff to learn how to operate it.
4.2 CAD Measurement
4.2.1 CAD Benefits
a. Accurate design - CAD enables the designers to produce very accurate and precise
designs with minimum errors. For example, designers can draw the model at 1:1 scale
which ensures its accuracy of measurement for the advantage of quantity surveyors. On
the contrary, there is high risk of human errors on manual drafting as scale is involved in
the drawings. Dimensions of the model have to be manually verified and established
19
which human errors tend to occur frequently at this stage. An error-free design enhances
an accurate and correct measurement prepared by quantity surveyors.
b. Cost modelling - Cost modelling can be done by utilising CAD in the initial stage of
design phase. Quantity surveyors are able to identify the specifications in the design and
thus propose to cut down of the cost to the client if necessary. They are able to show the
implications of cost upon the design produced to the client immediately which helps to
improve the communication between quantity surveyors and client. Without CAD, they
might face some difficulties in analysing the result of design and cost since the
production of the drawings is time consuming thus affect the time taken for cost estimate
as well.
4.2.2 CAD Constraints
a. Lack of standardisation in design - There are a few methods of drawing the plans which
are depends on the architect preferences. For example, some architects will use
‘polyline’ to draw in CAD drawings but some may not. Objects drawn by using polyline
makes measurement process easier as quantity surveyors can take the total area
without returning to the manual taking-off to calculate the length and width of the area.
This would diminish the purpose of using CAD in measurement. However, it is difficult to
standardize all architects to use the same method to draw as they would not be aware of
its effect towards quantity surveyors.
b. Loss of work due to not saving - CAD drawings will be lost as a results of not saving
them during the drafting process. CAD users are not able to auto save the projects as it
does not own a backup system.
4.3 Manual Measurement
4.3.1 Manual Measurement Benefits
a. Cost Effective - Manual measurement is very cost effective compare to BIM and CAD
measurement as it does not require to purchase any software which is very costly. It
would only cost mainly on the printing hence it safe a lot of money.
b. No Training Is Required - Every quantity surveyor know how to do manual measurement
while not every quantity surveyor know how to do BIM and CAD measurement because
it required trained skill to use the software to do measurement. Therefore, extra training
is required for them to master the software.
20
c. Client’s satisfaction - Client may find it easier to understand the measurements as they
are more used to the traditional method. The client might also not familiar with BIM and
CAD measurement.
4.3.2 Manual Measurement Constraints
a. Errors - There is a risk of human errors as quantity surveyor is rushing to complete the
cost estimates. The quantity surveyor must use a well-organized systematic method of
takeoff to avoid missing or double counting items. Besides that, the scale of the
drawings might not be as accurate compare to software so it might be a little difference.
b. Can’t provide better visualization - Unlike BIM and CAD measurement that can provide
3D model using the software, in manual measurement, the quantity surveyor are using
2D drawing. The quantity surveyor has to take many days to visualize the whole
construction from the 2D drawing. Therefore, manual measurement consume more time
than BIM and CAD measurement.
c. Sharing of information - Since there will only be one original copy of the drawings, if
there is any changes to the drawings, it is difficult to share the updated information to the
other department of the project.
21
5.0 Pre-construction Stage
5.1 Building Information Model (BIM)
5.1.1 BIM Benefits
a. Scheduling by 4D BIM - 4D BIM, is used to plan construction related activities on site.
The progress of the activities on site throughout this project can be extracted and
visualised by those who are involved. BIM elements such as columns, floor slabs and
others can be attached to find out its proper start and end time. The capabilities of BIM
to facilitate the mapping of time, cost resources and transportation analysis can improve
logistics performance. Therefore, it allows a better understanding on how the process
will proceed in a particular point of time and help in scheduling the construction progress.
b. Improve safety - BIM technology can easily identify the traffic condition and hazards
around the site that can cause accident before the construction starts. This is to ensure
that the task can be completed safely and efficiently as when the risk or hazards are
identified, the person in charge will bring up solution to overcome before hand.
c. Cost estimating by 5D BIM - 5D BIM, provide all the cost advices and estimates on
various design proposals in real time during construction. 5D BIM will automatically
estimate the material costs of the project even there are changes in between the project,
thus the estimators can manage the budget of construction.
5.1.2 BIM Constraints
a. Defective of 4D BIM - 4D BIM has been proved that it is very effective to the overall
schedule of communication even though the schedule is complex. However, there is a
contrast between the final results of a schedule in 4D-animation after communicating
and while working with the fundamental schedule. For example, it will be hard to analysis
and overview work in progress of the project when there are several thousand activities
in the schedule.
5.2 CAD Measurement
5.2.1 CAD Benefits
a. Enhance communication - Since CAD drawings can be easily sent to quantity surveyors
within minutes through email, so they can react to the necessary changes and make
22
amendment in cost estimate as soon as possible. Quantity surveyors receive the
drawings from architect in a short period of time after the design stage is completed.
b. Quick measurement - By utilising CAD software such as CostX, the measurement
process of unique shapes in the drawings takes short time and easier. Quantity
surveyors do not need to divide it into a few regular shapes to get the total area of a
whole irregular shapes with the help of CAD. The total area of the irregular shape of the
proposed building can be get within a minute by just clicking on the boundary of the
shape.
c. Accurate taking-off - Measurement done by quantity surveyors is more precise and
accurate in reality compared to manual measurement. It is due to CAD drawings are
produced in scale 1:1 and it helps to eliminate the risk of human errors in quantities and
scales.
5.2.2 CAD Constraints
a. Unable to produce BQ - CAD software is limited to taking-off only but not production of
Bills of Quantities. Obtaining the quantities do not automatically produced a bill of
quantities which makes the work become tedious. It is because the quantities extracted
need to be exported to another software to produce bills of quantities or the quantity
surveyors have to transfer the quantities into BQ format manually. Mistakes tend to
occur in this process.
5.3 Manual Measurement
5.3.1 Manual Measurement Benefits
a. Cost Effective - Manual measurement is very cost effective compare to BIM and CAD
measurement as it does not require to purchase any software which is very costly. It
would only cost mainly on the printing hence it safe a lot of money.
b. No Training Is Required - Every quantity surveyor know how to do manual measurement
while not every quantity surveyor know how to do BIM and CAD measurement because
it required trained skill to use the software to do measurement. Therefore, extra training
is required for them to master the software.
c. Flexibility in workflow - Manual measurement allows quantity surveyors to work in a
workflow that they are comfortable thus making it more fluent within the company. While
BIM and CAD measurement is made in such a way where they need to follow certain
23
steps to get things done. Therefore, manual measurement is more suitable to situations
that are unable to gained by the software because of its flexibility as well as changing or
working according to rules and regulation of region.
5.3.2 Manual Measurement Constraints
a. Errors - Manual measurement might cause human errors and lower down the accuracy.
The quantity surveyor must use a well-organized systematic method of takeoff to avoid
missing or double counting items. Besides that, the scale of the drawings might not be
as accurate compare to software so it might be a little difference. This might cause
differences in the final cost of the project.
b. Unable to make changes quickly - If there are changes of any dimension or quantity,
recalculation of the work will be required. The quantity surveyor needed more time to
calculate the changes as man power has limits. Work will be very troublesome and
tedious if there is changes in design. The quantity surveyor may need to redo everything.
6.0 Construction Stage
24
6.1 Building Information Model (BIM)
6.1.1 BIM Benefits
a. Save time - During the construction phase, BIM have the ability and convince the
resolution of complex tasks and identify changes or clashes because it is a digital
representation that provides the real-time information in three dimensions. In addition,
everyone that involves in the collaboration can access to the digital document anywhere
and anytime, as the documents are delivered to cloud. It also allows controlling the
schedules and minimizing rework, so the construction could be complete in time.
b. Reduce wastage - Material schedule, the method of construction has been selected and
planned during the design phase and pre-construction phase. Therefore, wastage is
reduced during construction phase.
c. Promotes prefabrication - Construction team provides all information as early as possible
also facilitates on-site prefabrication, ensuring cost savings for higher quality and also
error-free components. Therefore, it can benefits the real-time delivery and mitigates
storage problems.
6.1.2 BIM Constraints
a. Price Fluctuations - Although the BIM model is a very useful tool that can help us to
collect information across the entire construction project. However, we still need to
employ the external manual method due to the price fluctuations as BIM model do not
consider the price fluctuation of the materials in the market.
6.2 CAD Measurement
6.2.1 CAD Benefits
a. Reduce wastage - Greater accuracy of the design can be achieved by using CAD thus
leading to a better design with reduced errors. Better designs help to carry out the
manufacturing process faster as well as reducing the wastage drastically caused by
faulty design.
b. Reduce confusion - Ability of CAD to show design information clearly and persistently to
avoid misinterpretations during construction. The design information can be viewed
clearly through efficient plotting. Also, dimensions of the complex shapes of the layout
can be accurately defined without error.
25
c. Detect interferences - CAD users are capable to detect any clashes of the drawings by
keying in the information into the system which manual drafted drawings may be looked
correct.
6.2.1 CAD Constraints
a. Limited to 2D - Since the CAD drawings are in two-dimensional, the measurement done
by quantity surveyors are also based on two-dimensional designs only. Quantities that
require volume which is in three-dimensions could not be measured. Therefore, it may
affect the comprehensiveness of the final quantities.
6.3 Manual Measurement
6.3.1 M​anual Measurement Benefits
a. Cost Effective - Manual measurement is very cost effective compare to BIM and CAD
measurement as it does not require to purchase any software which is very costly. It
would only cost mainly on the printing hence it safe a lot of money.
b. No Training Is Required - Every quantity surveyor know how to do manual measurement
while not every quantity surveyor know how to do BIM and CAD measurement because
it required trained skill to use the software to do measurement. Therefore, extra training
is required for them to master the software.
c. Safe and secured - Manual measurement reduce the risk of information loss as all the
measurement is in hardcopy. While BIM and CAD measurement have a higher risk in
loss of information because the computer might suddenly spoil and all the information
will be gone or the files might not be saved properly. Furthermore, manual measurement
has no restriction such as power failure. The quantity surveyor will not be affected due to
power down or computer system clashed as it is totally based on paper works.
6.3.2 Manual Measurement Constraints
a. Project time extended - Project time will be extended because there are some factors
that affect project duration negatively. Occurring of design errors, reworks and changing
client demands can affect project duration and lack of understanding of the project by
the clients. 2D drawings can lead to variation orders and consequently cause extension
in the duration of project and may increase the project cost.
26
b. Reduce accuracy of data - Humans are slower in identifying error compare to software.
When error is identified during the construction stage, this will have incurred cost to
reconstruct the certain part which leads to other additional cost. Reconstructing will also
lead to the change in measurement and BQ and hence more time is needed to
re-estimate the cost plan.
7.0 Post construction stage
7.1 Building Information Model (BIM)
27
7.1.1 BIM Benefits
a. Model data recorded - The construction management can provide an accurate model or
record of the building, and all the information about the components to their client at the
end of the project.
b. Sustainability and facility management - 7D BIM, mainly contributes to facilities
management departments that can utilize BIM technology for coordinated, computable
building information and knowledge management. In addition, BIM technology providing
more precise control systems, and consistently delivering cost effective services for the
occupants of the building.
7.1.2 BIM Constraints
a. Cultural barrier toward a new technology - Once the building construction completed, the
maintenance team who hired by the project management separately do not have the skill
and knowledge to manage the building by using BIM. Thus, this could be a barrier to
implement BIM for facilities management.
7.2 CAD Measurement
7.2.1 CAD Benefits
a. Data Management - CAD software is able to store and manage both graphic data and
non-graphic data effectively. Graphic data refers to drawings of a project while
non-graphic data refer to quantities, cost, specifications etc. These data is crucial to
serve the purpose of cost analysis after the project is completed. Also, the data stored is
used as a reference guide in future so that the repetitive components do not have to be
designed repeatedly. In CAD, these data are grouped orderly which ensures an easy
access for quantity surveyors.
b. Easy to reproduce - After the construction is completed, CAD drawings can be easily
reproduced in a short period of time for future reference or other purpose.
7.2.1 CAD Constraints
28
a. Limited information - There is little to no information of some components in CAD files in
terms of softscape of the buildings. Lack of information leads to an inadequate of
visualisation of the designated space usage.
7.3 Manual Measurement
7.3.1 Manual Mea​surement Benefits
a. Easy to obtain information - All the information is in hardcopy, a person does not need to
master any software in order to locate and extract the specific information needed.
b. Reduce the risk of loss of information - All the information is in hardcopy so it will
reduced the risk of loss of information. The use of software will have a higher risk in loss
of information because if the files are not kept properly, all the information will be gone.
7.3.2 Manual Measurement Constraints
a. Require place to store the drawing - Storage facilities is required to keep all the manual
drawings.
b. Time needed after commissioning - Significant time is needed to collect and validate
data needed to form the manual, as the information often consists of 2D drawings and
PDF documents
c. Limited information - A hardcopy manual does not provide some crucial information for
the Facility Maintenance team that extends beyond the 2D drawings such as
maintenance planning and space planning.
29
8.0 Reference
● Ocheja, A. (2017). ​Computer Aided Design (CAD) System For Quantity Surveyors In
Malaysia​. ​Academia.edu​. Retrieved 19 April 2017, from
http://www.academia.edu/2168124/Computer_Aided_Design_CAD_System_For_Quantit
y_Surveyors_In_Malaysia
● Stonecypher, L. (2017). ​Benefits of using the CAD Software: Advantages of the CAD
Software​. ​Brighthub Engineering​. Retrieved 19 April 2017, from
http://www.brighthubengineering.com/cad-autocad-reviews-tips/17593-benefits-of-using-t
he-cad-software/
● James, T. (2017). ​The Advantages and Disadvantages of CAD.CAM | Synonym​.
Classroom.synonym.com​. Retrieved 21 April 2017, from
http://classroom.synonym.com/advantages-disadvantages-cadcam-10002481.html
● Advantages of BIM-Based Management Model. Retrieved 9 February 2015 , from
http://www.glodon.com/en/journals_articles.aspx?id=25
● Harris, V. (2016, June 25). The end of manual take-off for Estimators. Retrieved April 21,
2017, from​ ​http://www.biminstitute.org.za/end-manual-take-off-estimators/
● Dalcı, A. (2014). ​An Investigation on Some Benefits of BIM Application (Doctoral
dissertation, Eastern Mediterranean University (EMU)-Doğu Akdeniz Üniversitesi
(DAÜ)).
● Alder, M. A. (2006). Comparing Time and Accuracy of Building Information Modeling to
On-Screen Takeoff for a Quantity Takeoff of a Conceptual Estimate.
● Bečvarovská, R., & Matějka, P. COMPARATIVE ANALYSIS OF CREATING
TRADITIONAL QUANTITY TAKEOFF METHOD AND USING A BIM TOOL.
● Group, T. (2017). ​5D BIM Construction Software | Virtual Construction | Vico Software​.
Vicosoftware.com​. Retrieved 2 May 2017, from ​http://www.vicosoftware.com​.
● Vico Office R3.0 Help User guide​. (2017). ​http://www.vicosoftware.com​. Retrieved 2 May
2017, from
http://www.vicosoftware.com/hs-fs/hub/658/file-13189303-pdf/docs/vico_office_release_
3_help_file.pdf
30

Weitere ähnliche Inhalte

Was ist angesagt?

Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)
Pang Khai Shuen
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final account
ahmong4
 
Value Management Assignment (Slides)
Value Management Assignment (Slides)Value Management Assignment (Slides)
Value Management Assignment (Slides)
Pang Khai Shuen
 
Eca presentation slides
Eca presentation slidesEca presentation slides
Eca presentation slides
ahmong4
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
Lee Pei Gie
 

Was ist angesagt? (20)

Vm report
Vm reportVm report
Vm report
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Software Report
Software ReportSoftware Report
Software Report
 
Vm assignment (5)
Vm assignment (5)Vm assignment (5)
Vm assignment (5)
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
Elemental cost analysis Presentation Slides
Elemental cost analysis Presentation SlidesElemental cost analysis Presentation Slides
Elemental cost analysis Presentation Slides
 
Value Management Assignment (Report)
Value Management Assignment (Report)Value Management Assignment (Report)
Value Management Assignment (Report)
 
pp2 Final account-1
pp2 Final account-1pp2 Final account-1
pp2 Final account-1
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Elemental Cost Analysis
Elemental Cost AnalysisElemental Cost Analysis
Elemental Cost Analysis
 
Assignmenr for pp2 final account
Assignmenr for pp2 final accountAssignmenr for pp2 final account
Assignmenr for pp2 final account
 
Value Management Assignment (Slides)
Value Management Assignment (Slides)Value Management Assignment (Slides)
Value Management Assignment (Slides)
 
Eca presentation slides
Eca presentation slidesEca presentation slides
Eca presentation slides
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Pp2 final report
Pp2 final reportPp2 final report
Pp2 final report
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)
 
BIM Introduction
BIM IntroductionBIM Introduction
BIM Introduction
 
Assignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost AppraisalAssignment - Preliminary Cost Appraisal
Assignment - Preliminary Cost Appraisal
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 

Ähnlich wie Assignment 1 - Software

Material Quotation System Functional Requirements Document V6
Material Quotation System  Functional Requirements Document V6Material Quotation System  Functional Requirements Document V6
Material Quotation System Functional Requirements Document V6
Semon Wu
 

Ähnlich wie Assignment 1 - Software (20)

Software Application Group Assignment
Software Application Group AssignmentSoftware Application Group Assignment
Software Application Group Assignment
 
Software Development: Fixed Price Model Features
Software Development: Fixed Price Model FeaturesSoftware Development: Fixed Price Model Features
Software Development: Fixed Price Model Features
 
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
IRJET- A Study on Use of Building Information Modelling for Cost Estimation P...
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation Slides
 
Software
Software Software
Software
 
Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...Application of Building Information Modelling Software’s for Planning and Sch...
Application of Building Information Modelling Software’s for Planning and Sch...
 
Software Application Report
Software Application ReportSoftware Application Report
Software Application Report
 
Software Application report
Software Application reportSoftware Application report
Software Application report
 
Drive Business Excellence with Outcomes-Based Contracting: The OBC Toolkit
Drive Business Excellence with Outcomes-Based Contracting: The OBC ToolkitDrive Business Excellence with Outcomes-Based Contracting: The OBC Toolkit
Drive Business Excellence with Outcomes-Based Contracting: The OBC Toolkit
 
Are Function Points Still Relevant?
Are Function Points Still Relevant?Are Function Points Still Relevant?
Are Function Points Still Relevant?
 
Are Function Points Still Relevant?
Are Function Points Still Relevant?Are Function Points Still Relevant?
Are Function Points Still Relevant?
 
Software assignment
Software assignmentSoftware assignment
Software assignment
 
ME8793 PPCE QB-1.pdf
ME8793 PPCE QB-1.pdfME8793 PPCE QB-1.pdf
ME8793 PPCE QB-1.pdf
 
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...Cost Analysis of ComFrame: A Communication Framework for  Data Management in ...
Cost Analysis of ComFrame: A Communication Framework for Data Management in ...
 
Bill of quantities
Bill of quantitiesBill of quantities
Bill of quantities
 
EFFICIENT AND RELIABLE PERFORMANCE OF A GOAL QUESTION METRICS APPROACH FOR RE...
EFFICIENT AND RELIABLE PERFORMANCE OF A GOAL QUESTION METRICS APPROACH FOR RE...EFFICIENT AND RELIABLE PERFORMANCE OF A GOAL QUESTION METRICS APPROACH FOR RE...
EFFICIENT AND RELIABLE PERFORMANCE OF A GOAL QUESTION METRICS APPROACH FOR RE...
 
EFFICIENT AND RELIABLE PERFORMANCE OF A GOAL QUESTION METRICS APPROACH FOR RE...
EFFICIENT AND RELIABLE PERFORMANCE OF A GOAL QUESTION METRICS APPROACH FOR RE...EFFICIENT AND RELIABLE PERFORMANCE OF A GOAL QUESTION METRICS APPROACH FOR RE...
EFFICIENT AND RELIABLE PERFORMANCE OF A GOAL QUESTION METRICS APPROACH FOR RE...
 
Lec.1 Introduction to Estimation
Lec.1   Introduction to EstimationLec.1   Introduction to Estimation
Lec.1 Introduction to Estimation
 
Material Quotation System Functional Requirements Document V6
Material Quotation System  Functional Requirements Document V6Material Quotation System  Functional Requirements Document V6
Material Quotation System Functional Requirements Document V6
 
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 

Mehr von Kai Yun Pang

Mehr von Kai Yun Pang (20)

Assignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau LangkawiAssignment 2 - Resort Proposal at Pulau Langkawi
Assignment 2 - Resort Proposal at Pulau Langkawi
 
Assignment 2 - Report
Assignment 2 - ReportAssignment 2 - Report
Assignment 2 - Report
 
Assignment 1 - Water Pump Station
Assignment 1 - Water Pump StationAssignment 1 - Water Pump Station
Assignment 1 - Water Pump Station
 
Assignment 1 - Microsoft Project
Assignment 1 - Microsoft ProjectAssignment 1 - Microsoft Project
Assignment 1 - Microsoft Project
 
Assignment - Financial Appraisal
Assignment - Financial AppraisalAssignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - Financial Appraisal
Assignment - Financial Appraisal Assignment - Financial Appraisal
Assignment - Financial Appraisal
 
Assignment - FIDIC Contract
Assignment - FIDIC ContractAssignment - FIDIC Contract
Assignment - FIDIC Contract
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - CIPAA 2012
Seminar - CIPAA 2012Seminar - CIPAA 2012
Seminar - CIPAA 2012
 
Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)Assignment - S Hotel (Presentation Slide)
Assignment - S Hotel (Presentation Slide)
 
Assignment - S Hotel
Assignment - S HotelAssignment - S Hotel
Assignment - S Hotel
 
Assignment - Case Study Report
Assignment - Case Study ReportAssignment - Case Study Report
Assignment - Case Study Report
 
Assignment - Journal
Assignment - JournalAssignment - Journal
Assignment - Journal
 
Assignment - Community Service
Assignment - Community Service Assignment - Community Service
Assignment - Community Service
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Seminar - Question
Seminar - QuestionSeminar - Question
Seminar - Question
 
Assignment - MK Land
Assignment - MK LandAssignment - MK Land
Assignment - MK Land
 
Assignment - Financial Analysis
Assignment - Financial AnalysisAssignment - Financial Analysis
Assignment - Financial Analysis
 
Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)Assignment - Preliminary Cost Appraisal (Presentation Slide)
Assignment - Preliminary Cost Appraisal (Presentation Slide)
 

Kürzlich hochgeladen

Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
KarakKing
 

Kürzlich hochgeladen (20)

Philosophy of china and it's charactistics
Philosophy of china and it's charactisticsPhilosophy of china and it's charactistics
Philosophy of china and it's charactistics
 
21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx21st_Century_Skills_Framework_Final_Presentation_2.pptx
21st_Century_Skills_Framework_Final_Presentation_2.pptx
 
Interdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptxInterdisciplinary_Insights_Data_Collection_Methods.pptx
Interdisciplinary_Insights_Data_Collection_Methods.pptx
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Salient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functionsSalient Features of India constitution especially power and functions
Salient Features of India constitution especially power and functions
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
REMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptxREMIFENTANIL: An Ultra short acting opioid.pptx
REMIFENTANIL: An Ultra short acting opioid.pptx
 
Google Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptxGoogle Gemini An AI Revolution in Education.pptx
Google Gemini An AI Revolution in Education.pptx
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17How to Add New Custom Addons Path in Odoo 17
How to Add New Custom Addons Path in Odoo 17
 
General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
latest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answerslatest AZ-104 Exam Questions and Answers
latest AZ-104 Exam Questions and Answers
 
Plant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptxPlant propagation: Sexual and Asexual propapagation.pptx
Plant propagation: Sexual and Asexual propapagation.pptx
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Basic Intentional Injuries Health Education
Basic Intentional Injuries Health EducationBasic Intentional Injuries Health Education
Basic Intentional Injuries Health Education
 
Tatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf artsTatlong Kwento ni Lola basyang-1.pdf arts
Tatlong Kwento ni Lola basyang-1.pdf arts
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 

Assignment 1 - Software

  • 1. SCHOOL OF ARCHITECTURE, BUILDING AND DESIGN BACHELOR OF QUANTITY SURVEYING MARCH 2017 INTAKE ​SOFTWARE APPLICATION FOR QUANTITY SURVEYING [CSC 60603] ASSIGNMENT 1 GROUP MEMBERS: NO. NAME STUDENT ID 1. NG SIEW QING 0325750 2. NGIENG TIEN YUNG 0320221 3. NGO JIA HAUR 0320144 4. OOI YIN JI 0319962 5. PANG KAI YUN 0319802 6. SAM WEI YIN 0320364 7. SANDRABROOKE GOH 0329884 LECTURER : SR. YEAP SOON KIAT SUBMISSION DATE : 5TH MAY 2017
  • 2. TABLE OF CONTENT No. Content Page No. 1. Introduction 3 2. Part A 2.1 Buildsoft 2.2 Glodon 2.3 CostX 2.4 Vico Software 2.5 Summary 2.6 Recommendation 4 - 16 3. Part B 3.0 Preparation / Briefing Stage 3.1 BIM 3.1.1 BIM Benefits 3.1.2 BIM Constraints 3.2 CAD Measurement 3.2.1 CAD Benefits 3.2.2 CAD Constraints 3.3 Manual Measurement 3.3.1 Manual Measurement Benefits 3.3.2 Manual Measurement Constraints 17 - 18 4. 4.0 Design Stage 4.1 BIM 4.1.1 BIM Benefits 4.1.2 BIM Constraints 4.2 CAD Measurement 4.2.1 CAD Benefits 4.2.2 CAD Constraints 4.3 Manual Measurement 4.3.1 Manual Measurement Benefits 4.3.2 Manual Measurement Constraints 19 - 21 1
  • 3. TABLE OF CONTENT No. Content Page No. 5. 5.0 Pre-construction Stage 5.1 BIM 5.1.1 BIM Benefits 5.1.2 BIM Constraints 5.2 CAD Measurement 5.2.1 CAD Benefits 5.2.2 CAD Constraints 5.3 Manual Measurement 5.3.1 Manual Measurement Benefits 5.3.2 Manual Measurement Constraints 22 - 24 6. 6.0 Construction Stage 6.1 BIM 6.1.1 BIM Benefits 6.1.2 BIM Constraints 6.2 CAD Measurement 6.2.1 CAD Benefits 6.2.2 CAD Constraints 6.3 Manual Measurement 6.3.1 Manual Measurement Benefits 6.3.2 Manual Measurement Constraints 25 - 27 7. 7.0 Post-construction Stage 7.1 BIM 7.1.1 BIM Benefits 7.1.2 BIM Constraints 7.2 CAD Measurement 7.2.1 CAD Benefits 7.2.2 CAD Constraints 7.3 Manual Measurement 7.3.1 Manual Measurement Benefits 7.3.2 Manual Measurement Constraints 28 - 29 8. Reference 30 2
  • 4. 1.0 Introduction This report is a summarised research on various types of software programs that are accessible in the construction field. It is divided into two parts which Part A will be focus on the functions and limitation of different BIM QS software programs while the benefits and constraints of BIM, CAD Measurement and Manual Measurement will be further discuss in Part B. The best BIM QS software has also been discussed based on the our justifications and data in the report. BIM is rapidly becoming a fundamental tool which works best in managing building information in recent construction market. A project receives information from various sources such as engineer, architect, M&E engineer, quantity surveyor etc which often makes the information management more complicated. Therefore, BIM is a reliable process that works to gather the inputs from different sources to turn the information into a 3D model for a better visualisation. It is a way to change and improve the traditional data sharing among the parties which the communication can be greatly enhanced. Application of BIM covers all construction project stages including pre-construction phase, construction phase and post-construction phase. It improves the communication between the construction players by facilitating the design decision in a faster process. Besides, BIM ensures a quicker project completion time as it helps in organizing the project during its initial planning stage of the construction. On the other hand, due to it’s significant impact on construction field, major industry professionals tend to shift towards to the use of BIM. It is said that the industrialisation, automation and computerisation of BIM would eventually diminish the role of Quantity Surveyor in the construction industry. In fact, according to RICS report, the ability of BIM to automate measurement is the key advantage for Quantity Surveyors in terms of improvement in efficiency and accuracy in cost estimating. Quantity Surveyors still have to analyse the design, consult the clients, interpret and extract the quantities as well as aligning the measurement according to SMM2 where all these works could not be done by BIM itself only. Despite of the benefits that BIM brings to construction sector in Malaysia, its application remains at infancy stage. BIM is perceived as new in Malaysia and a costly tool to be widely practiced among the parties. However, it is expected that BIM will be in high priority in future with the assistance of government’s efforts. 3
  • 5. PART A 2.1 Buildsoft Buildsoft is a software that provide the construction and building industry with standard estimating software where ​it offers few different types of products such as global estimating, offsider estimating, subbies comparison, digitizer boards and so on. The buildsoft product that will be emphasized in this report is Buildsoft Global Estimating System. This software comprises of items such as price book, take-off system, screenshots, project analysis, bill of quantities and four level estimating, takeoff schedules, BETS, system requirements. Buildsoft is a very easy hands on software that every builder or subcontractor or even design team such as quantity surveyor to use and also it can be used by people with little or no experience in terms of using personal computers. In a nutshell, Buildsoft will not dissapoint the user as it offers complete features that will meet the user's needs. 2.1.1 Function of Software 2.1.1.1 Bill of Quantities Global Estimating is to produce bills of quantities. Bills of quantities are an important aspect that required for acknowledging the quantities of materials, rate for each materials and the total sum for all the material uses in the project. This enable user to do cost estimating, producing cost data and cost plan. By using global estimating, bills of quantities are able being produce in 4- level estimating which are job summary, trade breakup, calculation sheet and also rate breakup. In a more detailed explanation, level one is job summary where user can key in the elements that will have in the project. This sheet is where the subtotal elements of the estimate cost will be shown. So in each different element or job, different job can be set under different trade 4
  • 6. name. Each of the job can be marked up or some other extra contingency factor be applied differently and individually according to the element. In another hand, percentage of cost distribution will also be shown in this level as well as for labour and material summary will be separated for user easy references. Level two is trade breakup level where this level will contain the bill of quantity item for each element which each of the element has its own trade break-up sheet. In this level, user are able to put in specification that required for the project and user are able to key in the details of each element as detail as possible to produce bills of quantities. Quantities for each element can be typed in, calculated in detail or derived from digitizer and rated can be typed in as well or either being linked to price list or produced in a break up sheets. Level three is calculation sheet level. In this level, user are allow to put in the dimension of each elements to calculate the quantity where in the end, the total of the calculation will be returned to quantity column in Trade breakup level. Deduction for the calculation also can be key in during this level where this provide a very convenient measurement for the user. Lineal, area and volume calculation are allowed in this level as it will mostly depend on the description of the elements. Level four is rate breakup sheet where user can build up a composite rate that includes materials, labour, sub-contract, and equipment components for item rate. In rate breakup sheet level, rates can be key in or linked to the price list and also mathematical formula can be used in this level. 2.1.1.2 Composite rates Rates are considered as a very significant element which client and contractor will be focus on when looking into the bills of quantities. Client would wish to get the best rates from contractor and contractor will not want to over price the rate in order to get the tender of the project. This software could help user to clearly state out the price and rates for all the elements neatly and hence this could give user an easy review of rates for the project. In global estimating system, the rates can be built up and it can be composite the rate for each item. Nevertheless, it can be saved in price list or library so that user of this software can refer to the price list saved. Since the rates are kept in the price list or library, they can be transferred from pricelist into a new job 5
  • 7. if there is a new tender. This gives the user an easier and faster way which can help user to cut off the time consuming period of user preparing bills of quantities. 2.1.1.3 Multi-level mark up function In every project, preparation of markup price rate is a compulsory step for a quantity surveyor to do in all of the projects. This is because the rate of the materials or any other stuff might be different compare to the price when tenderer tendering the project and after contractor starts to commencing the work in which economics will affect the rates of everything. This could help all parties to prevent themselve facing financial loss. The markup rate is to revise the job or element or item total. Usually, the item that will be marked up is profit, overhead and also wastage. This is considered as easily adjusting the tender sum. 2.1.1.4 Analysis In Global estimating, analysis of cost, job and quantity can be analysed. For cost analysis, the software can analysing the overall materials and labours cost in particular job and this can provide the overall quantities for all types of materials in particular job. In another hand, for job analysis can be abstracting part of the building quantities item out from a job and it will be converted into trades bill. This can enable to prepare sub contractor bill of quantities more easy. Last but not least, quantities analysis are being analysed and being differentiate the item's quantity into stages or level. 2.1.2 Limitation of Software 2.1.2.1 Permanently deleted The job file that had been created in buildsoft global estimating system will be permanently deleted when any amendment are being done on the existing data. In another meaning, there is no undo button to undo the action. The amendment that had been done cannot be called back so user have to be careful when doing any amendment work. 2.1.2.2 Virus Attack Whenever using the internet, virus attack is very common problem that user will face. To own safe purposes, user should have licensed anti-virus software so that the virus definition can be update daily. If there is no anti virus software, the virus can attack the computer system and also all the content in the computer and hence that will cause the loss of data in the software system and may be can not be recovered by any means. 6
  • 8. 2.1.2.3 Unable of reviewing of Building Modeling Buildsoft Global Estimating system does not offer user to see the project building model neither in two dimensional view nor three dimensional view. This software is only able to produce a good and nice bills of quantities, however, user will still need to refer to architectural and structural drawing in hard copies. 7
  • 9. 2.2 Glodon Glodon is founded in 1998. Cubicost is a new brand of Glodon in international market. Cubicost BIM suite is comprised of four individual BIM-based software products which are Cubicost Takeoff for Architecture and Structure (TAS), Cubicost Takeoff for Rebar (TRB), Cubicost Takeoff for Mechanical and Electrical (TME), and Cubicost TBQ. All these four products together virtually cover all general requirements in construction cost estimation business. Moreover, BIM model and related data can be easily transferred between four products, bringing you the most professional, efficient and accurate BIM cost estimation experience. 2.2.1 Function of Software 2.2.1.1 Cubicost Takeoff for Architecture and Structure (TAS) TAS is embedded with Commonwealth of England calculation rules. It enables the users to create a 3D model for better visualization effect. Thus, the result can be more accurate. By using TAS, the users can import directly the electronic drawings such as IFC, DWG and PDF drawings, thus the 3D model can be built efficiently. Changes or variations can be done quickly by adjusting the model information and the calculation will be modified accordingly. It is a quantity calculation software which is simple, helpful and accurate with just one click to complete all the measurement work. TAS also owns Built-in Localized calculation rules as in different markets such as SMM2, SMM4, SMM7 and etc. Besides, it is compatible with Autodesk Revit format. (RVT) and popular 2x3 IFC format. TAS also support import and export of IFC format. 2.2.1.2 Cubicost Takeoff for Rebar (TRB) TRB is embedded with groundbreaking 3-dimensional measurement and calculation rules, including British Standards and Uniform Building By-Law. Built-in calculation setting based on British Standards and Uniform Building Bye-Law. Interchangeable calculation mode between 8
  • 10. Tendering Mode and Prefabrication Mode to 5 address different requirements. TRB allows 3D model to be imported from TAS to calculate rebar quantities. The deduction calculation can be done more precise as the elements are linked automatically for deduction as well as anchorage calculation integrally. Then, it can produce Rebar Schedule for fabrication on site. By using TRB, the calculation result will be with detail breakdown which helps to provide convenience in auditing results. Besides, it is also advantageous in variation with synchronization between models and quantities. Various reporting format is also available. 2.2.1.3 Cubicost Takeoff for Mechanical and Electrical (TME) TME allows quantity surveyors to do taking-off quickly for CAD and other drawings. For examples, TME is fast in calculating all equipment in a drawing with one click to auto identify pipes, wires, cables and ducts, resolving issues such as cumbersome manual measurement, difficulties in auditing and low efficiency in quantity takeoff for construction, quantity checks for settlement and the stage of tender. TME is having the built-in customizable calculation rules. Therefore, the calculation rules of different disciplines are provided and support customization. Besides, quantity surveyors can perform reverse checking easily to analyze quantity difference if there is any by discovering entity from the report. Next, TME can provide a summarised quantity reports which can be fully used in the whole process of tendering. These reports are classified according to different sectors such as elements, location etc. By mastering TME, a visualized MEP can be viewed clearly through a 3D model. TAS project can be imported to enable the team members to have a more detailed and interesting experience of visualisation. All the effects such as 360 degree viewing allows us to understand the details of the building better. 2.2.2 Limitations of Software 2.2.2.1 Cost License of Glodon software is costly thus there are only small number of QS firms afford to implement Glodon in their companies especially those smaller firms. Hence, those QS firms would rather use other BIM-based taking off softwares such as CostX and Vico since it is much more affordable although having less functions as compared to Cubicost. 9
  • 11. 2.2.2.2 Newly introduced in the industry In fact, Glodon is still a relatively new BIM-based product which offers the function of taking off in the construction market. There are limited countries which practice this software. As for a new software, it is constantly experiencing software updates and improvement thus it is not a completely stable product yet. There may be some flaws or constraints that affect the performance of this product. Moreover, there are not much users who are familiar with the usage of GLODON as it requires training to ensure the staffs are familiar with the functions to make good use of the software. 2.2.2.3 Lack of experts Since, Glodon is considered as one of the new software in the industrial, hence, there are lack of experts who are working in the field. An additional investment in training and education is required during software implementation. 2.2.2.4 Incompatibility with partners Currently, GLODON is not yet commonly practiced by construction professionals in Malaysia as it is that one of the partners or subcontractors may not be using Glodon. Therefore, they may not be able to access and take information from the models. Hence, inconvenience would be caused in terms of communication between the partners. 10
  • 12. 2.3 CostX CostX is one of the BIM software which was published on the year of 2014. It is a software that enables a quantity surveyor to do taking off from 2D drawings quickly and accurately. Besides, costX owns a most advanced electronic taker off system that can automatically generate quantities from 3D models. Through costX, we can prepare estimates, bills of quantities and tenders in a quicker way. 2.3.1 Function of Software 2.3.1.1 Support 2D taking off CostX enables quantity surveyor to prepare 2D taking off accurately and quickly because it supports various types of file including PDF and CAD. Quantity surveyor does not need to open CAD or PDF while doing taking off. Unlike other software, you will need to take few step before u can take measurement of a specific area or length. CostX could measure area, length with only a click. All this could save a lot of time for professions who are involved in construction. 2.3.1.2​ ​Support 3D taking off CostX also supports a 3D file or BIM file such as Revit, archiCAD, sketchup and other bim file. Through costX, we can navigate around the mode. For example, we can rotate around the model via rear, front, side or other perspectives with only using a mouse. In addition, by utilising costX we can explore the properties of the building easily. Also, they can add user defined model properties into the schedule to supplement the existing model data. Next, it can extracts quantities and create a customized estimate by using the function of object based dimension groups. Lastly, it could also allow us to measure manually in this software. 11
  • 13. 2.3.1.3 Workbook The workbook sides of costX includes live-link, rates, codes, phraseology and constant plus the standard and custom report writer. Existing rate libraries can be imported from excel and the data will live- link to estimate. It will auto update the quantity and estimate if there are any changes. 2.3.1.4 Auto-revisioning The function of this auto revisioning is to help us to identify amendments and changes of the 2D and 3D drawings and update the quantity when necessary. Quantity surveyors can compare the dimension of old and new drawing and display them for adjustment easily. One of the advantages of this auto-revisioning is the old version of drawings and workbook will be locked and the users are unable to do any measurement on it. 2.3.1.5 Sub-contractor Comparison In CostX, there is this function called subcontractor comparison. The quantity surveyor could compare the subcontractors in terms of their trades. They can generate workbook which allow subcontractor details to be entered and compared. It eases quantity surveyors as they do not need to key in the information of subcontractors in each time. 2.3.2 Limitation of Software 2.3.2.1 Cost and license The initial cost to install this software is high in terms of hardware and license. In addition, there are few type of license for this software which is ​standalone, network and portable. Each of this option carry different price. 2.3.2.2 Rebar detection CostX could not detect the reinforcement bar in the column. Quantity surveyor need to measure it separately. This might cause overmeasure of BRC. 12
  • 14. 2.4 Vico Software Vico software established different types of construction software and services which contributes to the construction industry. The construction software are Vico Takeoff Manager, Vico Cost Manager, Vico LBS Manager, etc. These software are generally used by contractors and construction managers to minimize the risk, improve schedules for large scale projects and manage construction costs. Besides, Vico’s 5D Virtual Construction solutions which launched by Vico software remain the construction industry’s integrated approach to quantity takeoff, project scheduling, coordination and cost estimation. Also, the file formats which are related with BIM such as ArchiCAD, Tekla, Revit and etc are applicable to the new Vico Office products. 2.4.1 Function of Software 2.4.1.1 Vico Takeoff Manager Vico Takeoff Manager is using a unique geometry analysis algorithm to produce quick and high accuracy of quantity takeoff by scanning 3D model which created from authorized BIM tools. The user has to visually verifies the elements in the 3D model included in the quantities. For the quantity calculations, user has to adjust the changes manually by adding or subtracting the model elements in the 3D model. Besides, Vico Cost Planner and Schedule Planner modules can takeoff data by location automatically. Hence, it does not require to export and import data. As a result, the accuracy for cost planning and schedules are increased. 2.4.1.2 Vico Cost Planner Vico Cost Planner allows cost calculation, cost estimating, and value engineering module. It can use the quantities generated from Takeoff Manager to produce a highly accurate amount in estimation within a short period of time. Besides, Cost Planner provides cost feedback at different project phases starting from design phase to close out phase. Nevertheless, Cost Planner also allows the users to keep and store the important and reusable projects data for further usage. 13
  • 15. 2.4.1.3 Vico Constructability Manager Vico Constructability Manager able to detect constructability issues for the published models. With Constructability Manager, users can do a comparison on the models in terms of layer by layer or different types of element. The user can easily make amendment on the model and rerun the comparisons to produce a new model. Besides, Constructability Manager able to generate a constructability report that included all constructability issues for any current status of a project. 2.4.1.4 Vico LBS Manager Vico LBS Manager help the user to differentiate the location structure which is the combination of floors or zones in a building. The location structure defined in the LBS Manager able to maintain a uniform location structure for all project information published to the Vico Office Project. Besides, LBS Manager can recalculate the quantities and update the result at the end of the editing process whenever the changes on floors or zones are made without going back for the BIM application. Therefore, it can produce a best project schedule as the phasing and zoning of a project are optimized. 2.4.1.5 Vico Schedule Planner Vico Schedule Planner combines the function of Vico Takeoff Manager, Vico Cost Planner and Vico LBS Manager which can produce a highly optimized project schedule. Vico Schedule Planner ensures a smooth project flows by adding the size of crew, productivity rates and geography specific pricing. With this, users can compress the work schedule without increasing the risk as they can control task buffers and identify conflicts easily. As a result, the productivity and predictability are increased to deliver the projects within a short period. 2.4.2 Limitation of Software 2.4.2.1 Inefficient By using Vico Software software, each time only can operate one model file. Hence, it is inefficient as it takes a longer time to produce project’s document compared to other BIM software. 14
  • 16. 2.5 Summary Software Feature Buildsoft Glodon CostX Vico Simplicity Yes Yes Yes No Taking-off Yes Yes Yes Yes Application for Architect and Engineer No No No No Able to read different type of drawing No Yes Yes Yes Able to export into other formats No Yes No Yes 15
  • 17. 2.6 Recommendation Nowadays, there are various types of BIM QS software available in the industry. Each and every software would definitely has its own leading features as well as the limitations. Therefore, the best BIM QS software does not necessarily means to have the most features but having the most appropriate and functional feature that meet the user’s requirements to effectively ease their job. Based on our study and understanding on the 4 BIM QS software that we had chosen, we would like to recommend Cubicost by Glodon as the best software among these four softwares. Firstly, Cubicost by Glodon is easy to operate. Most of the things could be done with just a click. For example, changes and variation could be quickly made with just a click by adjusting the model information and the calculation will be modified accordingly. This could definitely gives the user a more accurate result as they do not need to make changes or variation for each part and so, all those human errors such as careless mistake could be avoided. Secondly, Cubicost by Glodon able to provide the user a better visualisation as a 3D model will be created as they key in all the related information or data accordingly. TME can auto identify the pipes, wires, cables and ducts. Hence, a visualized MEP can be viewed clearly through a 3D model. The users will have better understanding on the details of the building through these unique features such as 360 degree viewing. Last but not least, the user can save a significant sum of time by using Cubicost by Glodon due to the special features like on-screen taking off, 3D visualisation and paperless estimating. Traditional way of doing measurement is totally not needed if using this software. The quantity surveyor could no longer spend such a long period of time for scaling and taking off the data from the drawing. As a result, the workload could be ease and the process of preparing a BQ could be speed up. The time saved could then turns into profit. 16
  • 18. PART B 3.0 Briefing/ Preparation Stage 3.1 Building Information Model (BIM) 3.1.1 BIM Benefits a. Visualization improved by 3D Model - Better visualization enables the contractor to understand the site planning of the project easily even at the preparation stage. 3D modeling services also creating a virtual environment, which help to convince the project team and contractor present their rough idea of design to their client. b. Improve the communication and the coordination among different parties - As a result of BIM provide a visualization services as an entry services, therefore BIM acts a platform that show all the progress of the project at any given moment from different party who access to the model. It allows the project members to communicate their idea to each other. Besides, it is able to identify any potential risk of delay or error before hand-in the project thus avoiding extra expenses incurred. 3.1.2 BIM Constraints a. High cost for software and training - The cost of the BIM software is very expensive. Secondly, it also requires staff training because it involves a lot of complication during implementation. 3.2 CAD Measurement 3.2.1 CAD Benefits a. Database for manufacturing - Designers will include the data such as material, dimension and shapes of the components etc in CAD when creating the documentation for designing purpose. These data can be used for manufacturing as well. b. Increase value to client - CAD software enables designers to explore and produce conceptual proposals in a shorter time frame. For instance, designers can produce and evaluate alternative designs for a proposed housing area to the client. Hence, a higher level of service has been proposed to the client which differentiate us from potential competitors. c. Visualisation - Client is able to look at virtual reality simulations of the layout of the proposed buildings. It is cheaper to make any amendment at briefing stage rather than 17
  • 19. when the building is in construction stage. It ensures a higher quality of the end product which matches the specification and expectation of the client more. 3.2.2 CAD Constraints a. High initial cost - High expenses incurred to implement CAD which includes the cost of software itself, cost of computer hardware, software updates as well as training cost for the workers. b. Software Complexity - CAD becomes more versatile and adaptable as it advances. However, the software itself becomes more complicated which makes it difficult for the first-time users to practice the software. 3.3 Manual Measurement 3.3.1 Manual Measurement Benefits a. Cost Effective - Manual measurement is very cost effective compared to BIM and CAD measurement as it does not require to purchase any software which is very costly. It would only cost mainly on the printing hence it saves a lot of money. b. No Training Is Required - Every quantity surveyor know how to do manual measurement while not every quantity surveyor know how to do BIM and CAD measurement because it requires technical skills to use the software to do measurement. Therefore, extra training is required for them to master the software. 3.3.2 Manual Measurement Constraints a. Errors - There is a risk of human errors as quantity surveyor is rushing to complete the cost estimates. They have to use a well-organized systematic method of takeoff to avoid overmeasure or under measure. Besides, scale of the drawings is not as accurate as software thus leading to measurement discrepancies. b. Time consuming - Manual measurement consumes more time than BIM and CAD measurement because manual measurement is practiced by using measurement tools such as scale rule and calculator. The quantity surveyor need to measure and scale everything manually so it takes longer time as manpower has its limits. This will delay the time of task completion. 18
  • 20. 4.0 Design Stage 4.1 Building Information Model (BIM) 4.1.1 BIM Benefits a. High graphic perspective of 3D modeling that everyone can easily understand - BIM is created for the purpose of designing building. It creates the drawing that everyone can understand because this application provide a 360-degree rotation of a 3D model. Moreover, every view or component for a building in interconnected. For example, if the users do any adjustment on window in a building. All of the windows’ dimension will be adjusted and updated automatically. b. Improve efficiency - Clash detection is the one advantage that would improve the efficiency during design phase. All the error or clash that will impact the construction process will be mentioned so the potential issue can be settle before the construction start. c. Reduce the material usage - Compared to the traditional method such as CAD measurement or manual measurement, the use of BIM can reduce the material cost because BIM has potential to eliminate construction waste sources. We can use the BIM drawings and calculations to show the reduction of material use through the building design. 4.1.2 BIM Constraints a. Require trained or experienced technical staff - BIM is unfamiliar and tedious, so it requires the technician who owns the skills and knowledge on how a project designed and documented. However, it is more time consuming due to the training programme for the staff to learn how to operate it. 4.2 CAD Measurement 4.2.1 CAD Benefits a. Accurate design - CAD enables the designers to produce very accurate and precise designs with minimum errors. For example, designers can draw the model at 1:1 scale which ensures its accuracy of measurement for the advantage of quantity surveyors. On the contrary, there is high risk of human errors on manual drafting as scale is involved in the drawings. Dimensions of the model have to be manually verified and established 19
  • 21. which human errors tend to occur frequently at this stage. An error-free design enhances an accurate and correct measurement prepared by quantity surveyors. b. Cost modelling - Cost modelling can be done by utilising CAD in the initial stage of design phase. Quantity surveyors are able to identify the specifications in the design and thus propose to cut down of the cost to the client if necessary. They are able to show the implications of cost upon the design produced to the client immediately which helps to improve the communication between quantity surveyors and client. Without CAD, they might face some difficulties in analysing the result of design and cost since the production of the drawings is time consuming thus affect the time taken for cost estimate as well. 4.2.2 CAD Constraints a. Lack of standardisation in design - There are a few methods of drawing the plans which are depends on the architect preferences. For example, some architects will use ‘polyline’ to draw in CAD drawings but some may not. Objects drawn by using polyline makes measurement process easier as quantity surveyors can take the total area without returning to the manual taking-off to calculate the length and width of the area. This would diminish the purpose of using CAD in measurement. However, it is difficult to standardize all architects to use the same method to draw as they would not be aware of its effect towards quantity surveyors. b. Loss of work due to not saving - CAD drawings will be lost as a results of not saving them during the drafting process. CAD users are not able to auto save the projects as it does not own a backup system. 4.3 Manual Measurement 4.3.1 Manual Measurement Benefits a. Cost Effective - Manual measurement is very cost effective compare to BIM and CAD measurement as it does not require to purchase any software which is very costly. It would only cost mainly on the printing hence it safe a lot of money. b. No Training Is Required - Every quantity surveyor know how to do manual measurement while not every quantity surveyor know how to do BIM and CAD measurement because it required trained skill to use the software to do measurement. Therefore, extra training is required for them to master the software. 20
  • 22. c. Client’s satisfaction - Client may find it easier to understand the measurements as they are more used to the traditional method. The client might also not familiar with BIM and CAD measurement. 4.3.2 Manual Measurement Constraints a. Errors - There is a risk of human errors as quantity surveyor is rushing to complete the cost estimates. The quantity surveyor must use a well-organized systematic method of takeoff to avoid missing or double counting items. Besides that, the scale of the drawings might not be as accurate compare to software so it might be a little difference. b. Can’t provide better visualization - Unlike BIM and CAD measurement that can provide 3D model using the software, in manual measurement, the quantity surveyor are using 2D drawing. The quantity surveyor has to take many days to visualize the whole construction from the 2D drawing. Therefore, manual measurement consume more time than BIM and CAD measurement. c. Sharing of information - Since there will only be one original copy of the drawings, if there is any changes to the drawings, it is difficult to share the updated information to the other department of the project. 21
  • 23. 5.0 Pre-construction Stage 5.1 Building Information Model (BIM) 5.1.1 BIM Benefits a. Scheduling by 4D BIM - 4D BIM, is used to plan construction related activities on site. The progress of the activities on site throughout this project can be extracted and visualised by those who are involved. BIM elements such as columns, floor slabs and others can be attached to find out its proper start and end time. The capabilities of BIM to facilitate the mapping of time, cost resources and transportation analysis can improve logistics performance. Therefore, it allows a better understanding on how the process will proceed in a particular point of time and help in scheduling the construction progress. b. Improve safety - BIM technology can easily identify the traffic condition and hazards around the site that can cause accident before the construction starts. This is to ensure that the task can be completed safely and efficiently as when the risk or hazards are identified, the person in charge will bring up solution to overcome before hand. c. Cost estimating by 5D BIM - 5D BIM, provide all the cost advices and estimates on various design proposals in real time during construction. 5D BIM will automatically estimate the material costs of the project even there are changes in between the project, thus the estimators can manage the budget of construction. 5.1.2 BIM Constraints a. Defective of 4D BIM - 4D BIM has been proved that it is very effective to the overall schedule of communication even though the schedule is complex. However, there is a contrast between the final results of a schedule in 4D-animation after communicating and while working with the fundamental schedule. For example, it will be hard to analysis and overview work in progress of the project when there are several thousand activities in the schedule. 5.2 CAD Measurement 5.2.1 CAD Benefits a. Enhance communication - Since CAD drawings can be easily sent to quantity surveyors within minutes through email, so they can react to the necessary changes and make 22
  • 24. amendment in cost estimate as soon as possible. Quantity surveyors receive the drawings from architect in a short period of time after the design stage is completed. b. Quick measurement - By utilising CAD software such as CostX, the measurement process of unique shapes in the drawings takes short time and easier. Quantity surveyors do not need to divide it into a few regular shapes to get the total area of a whole irregular shapes with the help of CAD. The total area of the irregular shape of the proposed building can be get within a minute by just clicking on the boundary of the shape. c. Accurate taking-off - Measurement done by quantity surveyors is more precise and accurate in reality compared to manual measurement. It is due to CAD drawings are produced in scale 1:1 and it helps to eliminate the risk of human errors in quantities and scales. 5.2.2 CAD Constraints a. Unable to produce BQ - CAD software is limited to taking-off only but not production of Bills of Quantities. Obtaining the quantities do not automatically produced a bill of quantities which makes the work become tedious. It is because the quantities extracted need to be exported to another software to produce bills of quantities or the quantity surveyors have to transfer the quantities into BQ format manually. Mistakes tend to occur in this process. 5.3 Manual Measurement 5.3.1 Manual Measurement Benefits a. Cost Effective - Manual measurement is very cost effective compare to BIM and CAD measurement as it does not require to purchase any software which is very costly. It would only cost mainly on the printing hence it safe a lot of money. b. No Training Is Required - Every quantity surveyor know how to do manual measurement while not every quantity surveyor know how to do BIM and CAD measurement because it required trained skill to use the software to do measurement. Therefore, extra training is required for them to master the software. c. Flexibility in workflow - Manual measurement allows quantity surveyors to work in a workflow that they are comfortable thus making it more fluent within the company. While BIM and CAD measurement is made in such a way where they need to follow certain 23
  • 25. steps to get things done. Therefore, manual measurement is more suitable to situations that are unable to gained by the software because of its flexibility as well as changing or working according to rules and regulation of region. 5.3.2 Manual Measurement Constraints a. Errors - Manual measurement might cause human errors and lower down the accuracy. The quantity surveyor must use a well-organized systematic method of takeoff to avoid missing or double counting items. Besides that, the scale of the drawings might not be as accurate compare to software so it might be a little difference. This might cause differences in the final cost of the project. b. Unable to make changes quickly - If there are changes of any dimension or quantity, recalculation of the work will be required. The quantity surveyor needed more time to calculate the changes as man power has limits. Work will be very troublesome and tedious if there is changes in design. The quantity surveyor may need to redo everything. 6.0 Construction Stage 24
  • 26. 6.1 Building Information Model (BIM) 6.1.1 BIM Benefits a. Save time - During the construction phase, BIM have the ability and convince the resolution of complex tasks and identify changes or clashes because it is a digital representation that provides the real-time information in three dimensions. In addition, everyone that involves in the collaboration can access to the digital document anywhere and anytime, as the documents are delivered to cloud. It also allows controlling the schedules and minimizing rework, so the construction could be complete in time. b. Reduce wastage - Material schedule, the method of construction has been selected and planned during the design phase and pre-construction phase. Therefore, wastage is reduced during construction phase. c. Promotes prefabrication - Construction team provides all information as early as possible also facilitates on-site prefabrication, ensuring cost savings for higher quality and also error-free components. Therefore, it can benefits the real-time delivery and mitigates storage problems. 6.1.2 BIM Constraints a. Price Fluctuations - Although the BIM model is a very useful tool that can help us to collect information across the entire construction project. However, we still need to employ the external manual method due to the price fluctuations as BIM model do not consider the price fluctuation of the materials in the market. 6.2 CAD Measurement 6.2.1 CAD Benefits a. Reduce wastage - Greater accuracy of the design can be achieved by using CAD thus leading to a better design with reduced errors. Better designs help to carry out the manufacturing process faster as well as reducing the wastage drastically caused by faulty design. b. Reduce confusion - Ability of CAD to show design information clearly and persistently to avoid misinterpretations during construction. The design information can be viewed clearly through efficient plotting. Also, dimensions of the complex shapes of the layout can be accurately defined without error. 25
  • 27. c. Detect interferences - CAD users are capable to detect any clashes of the drawings by keying in the information into the system which manual drafted drawings may be looked correct. 6.2.1 CAD Constraints a. Limited to 2D - Since the CAD drawings are in two-dimensional, the measurement done by quantity surveyors are also based on two-dimensional designs only. Quantities that require volume which is in three-dimensions could not be measured. Therefore, it may affect the comprehensiveness of the final quantities. 6.3 Manual Measurement 6.3.1 M​anual Measurement Benefits a. Cost Effective - Manual measurement is very cost effective compare to BIM and CAD measurement as it does not require to purchase any software which is very costly. It would only cost mainly on the printing hence it safe a lot of money. b. No Training Is Required - Every quantity surveyor know how to do manual measurement while not every quantity surveyor know how to do BIM and CAD measurement because it required trained skill to use the software to do measurement. Therefore, extra training is required for them to master the software. c. Safe and secured - Manual measurement reduce the risk of information loss as all the measurement is in hardcopy. While BIM and CAD measurement have a higher risk in loss of information because the computer might suddenly spoil and all the information will be gone or the files might not be saved properly. Furthermore, manual measurement has no restriction such as power failure. The quantity surveyor will not be affected due to power down or computer system clashed as it is totally based on paper works. 6.3.2 Manual Measurement Constraints a. Project time extended - Project time will be extended because there are some factors that affect project duration negatively. Occurring of design errors, reworks and changing client demands can affect project duration and lack of understanding of the project by the clients. 2D drawings can lead to variation orders and consequently cause extension in the duration of project and may increase the project cost. 26
  • 28. b. Reduce accuracy of data - Humans are slower in identifying error compare to software. When error is identified during the construction stage, this will have incurred cost to reconstruct the certain part which leads to other additional cost. Reconstructing will also lead to the change in measurement and BQ and hence more time is needed to re-estimate the cost plan. 7.0 Post construction stage 7.1 Building Information Model (BIM) 27
  • 29. 7.1.1 BIM Benefits a. Model data recorded - The construction management can provide an accurate model or record of the building, and all the information about the components to their client at the end of the project. b. Sustainability and facility management - 7D BIM, mainly contributes to facilities management departments that can utilize BIM technology for coordinated, computable building information and knowledge management. In addition, BIM technology providing more precise control systems, and consistently delivering cost effective services for the occupants of the building. 7.1.2 BIM Constraints a. Cultural barrier toward a new technology - Once the building construction completed, the maintenance team who hired by the project management separately do not have the skill and knowledge to manage the building by using BIM. Thus, this could be a barrier to implement BIM for facilities management. 7.2 CAD Measurement 7.2.1 CAD Benefits a. Data Management - CAD software is able to store and manage both graphic data and non-graphic data effectively. Graphic data refers to drawings of a project while non-graphic data refer to quantities, cost, specifications etc. These data is crucial to serve the purpose of cost analysis after the project is completed. Also, the data stored is used as a reference guide in future so that the repetitive components do not have to be designed repeatedly. In CAD, these data are grouped orderly which ensures an easy access for quantity surveyors. b. Easy to reproduce - After the construction is completed, CAD drawings can be easily reproduced in a short period of time for future reference or other purpose. 7.2.1 CAD Constraints 28
  • 30. a. Limited information - There is little to no information of some components in CAD files in terms of softscape of the buildings. Lack of information leads to an inadequate of visualisation of the designated space usage. 7.3 Manual Measurement 7.3.1 Manual Mea​surement Benefits a. Easy to obtain information - All the information is in hardcopy, a person does not need to master any software in order to locate and extract the specific information needed. b. Reduce the risk of loss of information - All the information is in hardcopy so it will reduced the risk of loss of information. The use of software will have a higher risk in loss of information because if the files are not kept properly, all the information will be gone. 7.3.2 Manual Measurement Constraints a. Require place to store the drawing - Storage facilities is required to keep all the manual drawings. b. Time needed after commissioning - Significant time is needed to collect and validate data needed to form the manual, as the information often consists of 2D drawings and PDF documents c. Limited information - A hardcopy manual does not provide some crucial information for the Facility Maintenance team that extends beyond the 2D drawings such as maintenance planning and space planning. 29
  • 31. 8.0 Reference ● Ocheja, A. (2017). ​Computer Aided Design (CAD) System For Quantity Surveyors In Malaysia​. ​Academia.edu​. Retrieved 19 April 2017, from http://www.academia.edu/2168124/Computer_Aided_Design_CAD_System_For_Quantit y_Surveyors_In_Malaysia ● Stonecypher, L. (2017). ​Benefits of using the CAD Software: Advantages of the CAD Software​. ​Brighthub Engineering​. Retrieved 19 April 2017, from http://www.brighthubengineering.com/cad-autocad-reviews-tips/17593-benefits-of-using-t he-cad-software/ ● James, T. (2017). ​The Advantages and Disadvantages of CAD.CAM | Synonym​. Classroom.synonym.com​. Retrieved 21 April 2017, from http://classroom.synonym.com/advantages-disadvantages-cadcam-10002481.html ● Advantages of BIM-Based Management Model. Retrieved 9 February 2015 , from http://www.glodon.com/en/journals_articles.aspx?id=25 ● Harris, V. (2016, June 25). The end of manual take-off for Estimators. Retrieved April 21, 2017, from​ ​http://www.biminstitute.org.za/end-manual-take-off-estimators/ ● Dalcı, A. (2014). ​An Investigation on Some Benefits of BIM Application (Doctoral dissertation, Eastern Mediterranean University (EMU)-Doğu Akdeniz Üniversitesi (DAÜ)). ● Alder, M. A. (2006). Comparing Time and Accuracy of Building Information Modeling to On-Screen Takeoff for a Quantity Takeoff of a Conceptual Estimate. ● Bečvarovská, R., & Matějka, P. COMPARATIVE ANALYSIS OF CREATING TRADITIONAL QUANTITY TAKEOFF METHOD AND USING A BIM TOOL. ● Group, T. (2017). ​5D BIM Construction Software | Virtual Construction | Vico Software​. Vicosoftware.com​. Retrieved 2 May 2017, from ​http://www.vicosoftware.com​. ● Vico Office R3.0 Help User guide​. (2017). ​http://www.vicosoftware.com​. Retrieved 2 May 2017, from http://www.vicosoftware.com/hs-fs/hub/658/file-13189303-pdf/docs/vico_office_release_ 3_help_file.pdf 30