POWER SYSTEMS
PROJECT FEATURES
Customer: Delta Electricity
Notice to Proceed:July 2007
Main fuel: natural gas
PROJECT HIGHLIGHTS
- The most innovative & efficient solution to meet Australia’s growing power needs
- Alstom’s fifth contract in Australia for the supply of GT13E2-based plant after
Kwinana (under construction), Braemar, Cockburn and Pelican Point, which have
been in operation since 2006, 2003 and 2001 respectively
- Continuation of Alstom’s experience at Colongra site (Alstom supplied the
original 4 x 300 MW steam turbines for this station back in the 1960’s)
CUSTOMER BENEFITS
- Quick starting gas turbine peaking plant
- High flexibility & reliability
- Optimal response to peak demand requirements
- Low gas emission per unit of electricity produced
The Colongra power plant is located at
Munmorah, on the New South Wales central
coast, 120 km north of Sydney, Australia
Perth
Hobart
Launceston
Burnie
Bairnsdale
Sale
Geelong
Ballarat
Portland
Kingston Ararat
Bendigo
Mildura
Peterborough
Port Augusta
Ceduna
Penong
Eucla
Forrest
Tarcoola Woomera
Roxby Downs
Marree
Oodnadatta
Whyalla
Port Lincoln
Port
Pirie
Broken Hill
Cobar
Bourke
Cunnamulla
Dirranbandi
Charleville
Quilpie
Birdsville
Alice Springs
Roma
Bundaberg
Gladstone
Mackay
Clermont
Longreach
Winton
Cloncurry
Normanton
Forsayth
Herberton Cairns
Cooktown
Laura
Weipa
Samarai
Mount Isa
Tennant Creek
Barrow Creek
Newcastle Waters
Daly Waters
Birdum
Katherine
Pine Creek
Rum
Jungle
Wyndham
Kununurra
Fitzroy
Crossing
Derby
Wave Hill
The Granites
Ord River
Halls Creek
Nhulunbuy
Croydon
Charters
Towers
Hughenden
Blackall
Mount
Morgan
Dalby
Gympie
Toowoomba
Warwick
Ipswich
Lismore
Grafton
Coffs Harbour
Port Macquarie
Tamworth
Armidale
Moree
Nyngan
Dubbo
Orange
Hay
Wagga Wagga
Albury
Devonport
Newcastle
Gold Coast
Rockhampton
Townsville
Darwin
Broome
Port Hedland
Dampier
Preston
Onslow
Carnarvon
Dongara
Geraldton
Wiluna
Laverton
Leonora
Menzies
Coolgardie
Kalgoorlie
Northam
Narrogin
AlbanyAugusta
Collie
Bunbury
Kambalda
Norseman
Esperance
Sandstone
Meekatharra
Roebourne
Mount
Goldsworthy
Pilbara
Mount
Tom Price
Mount
Newman
Mount
Magnet
Wollongong
Elizabeth
Sydney
Brisbane
Adelaide
Melbourne
CANBERRA
Kupang
Dili
Ende
Raba
Mu
rra
y
Lachlan
Da
rlin
g
Pa
roo
B
arwon
Thom
son
Diamanti
na
Daly
Victo
ria
Fitzroy
Fortescue
A
shburton
Gascoyn
Murchison
Lake
Eyre
Lake Torrens
Lake Frome
Lake
Gairdner
Lake
Everard
Timor
Melville
Island
Groote
Eylandt
Wellesley
Islands
FloresSumbawa
Kangaroo
Island
King Island
Furneaux Group
Tasmania
Fraser Island
A u s t r a l i a
S e a
Gulf of
Carpentaria
C O R
T i m o r
S e a
T A
South East Cape
Cape Leeuwin
Geographe Bay
Hood
Point
Shark
Bay
Cape Leveque
Cape York
Cape Arnhem
G r e a t
A u s t r a l i a n
B i g h t
INDIAN
OCEAN
COLONGRA - Australia
660 MW – GT13E2
Simple Cycle Power Plant
An environmentally responsible way to meet
Australia’s growing power needs
Plant Integrator™
Levers Customer benefits
INVESTMENT
Optimised investment, integrating Operating &
Maintenance costs
LEAD-TIME Shorter lead times to produce electricity faster
Higher Plant efficiency for increased power output
PERFORMANCE at a wide range of operational modes
Lower emissions to meet environmental concerns
AVAILABILITY & FLEXIBILITY Better reliability, availability and flexibility
RETROFIT
Better Plant economics through Integrated Retrofit
Solutions
LIFE EXTENSION Extended plant life options
More value for customers with
Plant Integrator™
Plant Integrator™ is Alstom’s unique
way of creating more value for
customers. We combine outstanding
expertise at the component and plant
level, as we are both an equipment
designer and manufacturer and an
EPC contractor with extensive proven
worldwide references. We ensure our
customers meet their business
objectives and serve their market
better by collaborating with them.
There are six Plant Integrator™
levers to increase the net present
value for the Customer.
PT-PE/BPROS/SCSMNM07/eng/PPS/12.07/FR/6214-allready-500385489RCSLyon
POWER SYSTEMS
Colongra plant arrangement
COLONGRA - Australia
660MW–GT13E2-SimpleCyclePowerPlant
ALSTOM’s SCOPE
- Design, supply, installation and commissioning of the entire power plant
- Turnkey delivery of:
● Turbine island
● Step-up transformers
● ALSPA Power Automation system
● Balance of Plant
SUPERIOR INTEGRATION THROUGH ALSTOM’S PROJECT
MANAGEMENT SKILLS, EPC CAPABILITIES AND STATE-OF-THE–ART
KEY COMPONENTS
Alstom’s proven and advanced technology is based on:
- four modern, flexible & environmentally-friendly GT13E2 gas turbines
- four high-efficiency air-cooled TOPAIR® turbogenerators
Meeting Delta Electricity’s requirements
Additional power was required to meet peak demand. Delta Electricity’s power
generation portfolio consists of four coal-fired power plants totalling 4240 MW
of capacity. Alstom’s turnkey delivery of the 660 MW gas fired peaking power
plant will expand Delta Electricity’s capabilities in providing power during peak
demand periods and will be an important complement to their existing portfolio
of base load generation assets, serving the electricity needs of the future.
This project confirms Alstom’s ability to deliver
clean integrated power solutions

Weitere ähnliche Inhalte

Was ist angesagt?

tuas-ccp5-singapore-ka26-gas-combined-cycle-plant
tuas-ccp5-singapore-ka26-gas-combined-cycle-planttuas-ccp5-singapore-ka26-gas-combined-cycle-plant
tuas-ccp5-singapore-ka26-gas-combined-cycle-plantDaniel ANG
 
Kinetic energy recovery system ppt
Kinetic energy recovery system pptKinetic energy recovery system ppt
Kinetic energy recovery system pptgautam khillare
 
Hybrid pneumatic engine with exhaust heat recovery
Hybrid pneumatic engine with exhaust heat recoveryHybrid pneumatic engine with exhaust heat recovery
Hybrid pneumatic engine with exhaust heat recoveryLiviu Giurca
 
ENERGY EFFICIENT MOTORS
ENERGY EFFICIENT MOTORSENERGY EFFICIENT MOTORS
ENERGY EFFICIENT MOTORSArigela Harika
 
KERS ( Kinetic Energy Recovery system)
KERS ( Kinetic Energy Recovery system)KERS ( Kinetic Energy Recovery system)
KERS ( Kinetic Energy Recovery system)ThusharPs1
 
Energy conservation in electric drives
Energy conservation in electric drives Energy conservation in electric drives
Energy conservation in electric drives VIVEK KUMAR SHARMA
 
Energy recovery systems in automobile
Energy recovery systems in automobileEnergy recovery systems in automobile
Energy recovery systems in automobileIsaac Durocher
 
Presentation innovative hybrid_heavy_vehicle
Presentation innovative hybrid_heavy_vehiclePresentation innovative hybrid_heavy_vehicle
Presentation innovative hybrid_heavy_vehicleLiviu Giurca
 
Drive retrofit for synchronous motor
Drive retrofit for synchronous motorDrive retrofit for synchronous motor
Drive retrofit for synchronous motorVacon Plc
 
Energy efficient induction motor
Energy efficient induction motorEnergy efficient induction motor
Energy efficient induction motorkevinpatel169
 
Regenerative Braking System Report
Regenerative Braking System ReportRegenerative Braking System Report
Regenerative Braking System Reportsangeetkhule
 
design of energy efficient motor
design of energy efficient motordesign of energy efficient motor
design of energy efficient motor1241060020
 
Comprehensive Power Introduction April 2013
Comprehensive Power Introduction April 2013Comprehensive Power Introduction April 2013
Comprehensive Power Introduction April 2013Jeff Sable
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1Murugappa Group
 
Seminar report format (1)
Seminar report format (1)Seminar report format (1)
Seminar report format (1)Abhinavbh1
 

Was ist angesagt? (20)

tuas-ccp5-singapore-ka26-gas-combined-cycle-plant
tuas-ccp5-singapore-ka26-gas-combined-cycle-planttuas-ccp5-singapore-ka26-gas-combined-cycle-plant
tuas-ccp5-singapore-ka26-gas-combined-cycle-plant
 
Kinetic energy recovery system ppt
Kinetic energy recovery system pptKinetic energy recovery system ppt
Kinetic energy recovery system ppt
 
Hybrid pneumatic engine with exhaust heat recovery
Hybrid pneumatic engine with exhaust heat recoveryHybrid pneumatic engine with exhaust heat recovery
Hybrid pneumatic engine with exhaust heat recovery
 
ENERGY EFFICIENT MOTORS
ENERGY EFFICIENT MOTORSENERGY EFFICIENT MOTORS
ENERGY EFFICIENT MOTORS
 
KERS ( Kinetic Energy Recovery system)
KERS ( Kinetic Energy Recovery system)KERS ( Kinetic Energy Recovery system)
KERS ( Kinetic Energy Recovery system)
 
Energy conservation in electric drives
Energy conservation in electric drives Energy conservation in electric drives
Energy conservation in electric drives
 
This is Cummins Power Generation 2011
This is Cummins Power Generation 2011This is Cummins Power Generation 2011
This is Cummins Power Generation 2011
 
Energy recovery systems in automobile
Energy recovery systems in automobileEnergy recovery systems in automobile
Energy recovery systems in automobile
 
Presentation innovative hybrid_heavy_vehicle
Presentation innovative hybrid_heavy_vehiclePresentation innovative hybrid_heavy_vehicle
Presentation innovative hybrid_heavy_vehicle
 
Drive retrofit for synchronous motor
Drive retrofit for synchronous motorDrive retrofit for synchronous motor
Drive retrofit for synchronous motor
 
Energy efficient induction motor
Energy efficient induction motorEnergy efficient induction motor
Energy efficient induction motor
 
Regenerative Braking System Report
Regenerative Braking System ReportRegenerative Braking System Report
Regenerative Braking System Report
 
Resume Superintendent Head Electrical
Resume Superintendent Head ElectricalResume Superintendent Head Electrical
Resume Superintendent Head Electrical
 
Hybrid Drivetrain
Hybrid DrivetrainHybrid Drivetrain
Hybrid Drivetrain
 
design of energy efficient motor
design of energy efficient motordesign of energy efficient motor
design of energy efficient motor
 
Comprehensive Power Introduction April 2013
Comprehensive Power Introduction April 2013Comprehensive Power Introduction April 2013
Comprehensive Power Introduction April 2013
 
KERS
KERSKERS
KERS
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1
 
World of KERS
World of KERS World of KERS
World of KERS
 
Seminar report format (1)
Seminar report format (1)Seminar report format (1)
Seminar report format (1)
 

Andere mochten auch (10)

Magazine profile
Magazine profileMagazine profile
Magazine profile
 
VidGamDevCert
VidGamDevCertVidGamDevCert
VidGamDevCert
 
Scan0003
Scan0003Scan0003
Scan0003
 
Scan0001
Scan0001Scan0001
Scan0001
 
Fábula hábitos raros
Fábula hábitos rarosFábula hábitos raros
Fábula hábitos raros
 
Company profile KJA
Company profile KJACompany profile KJA
Company profile KJA
 
Carta.
Carta.Carta.
Carta.
 
Fler klockor behövs i Älvsjö centrum
Fler klockor behövs i Älvsjö centrumFler klockor behövs i Älvsjö centrum
Fler klockor behövs i Älvsjö centrum
 
Indicadores tercer periodo tecnologia
Indicadores tercer periodo tecnologiaIndicadores tercer periodo tecnologia
Indicadores tercer periodo tecnologia
 
Glaubwürdigkeit und Effizienz sind planbar: Anregungen zur Kommunikationspla...
Glaubwürdigkeit und Effizienz  sind planbar: Anregungen zur Kommunikationspla...Glaubwürdigkeit und Effizienz  sind planbar: Anregungen zur Kommunikationspla...
Glaubwürdigkeit und Effizienz sind planbar: Anregungen zur Kommunikationspla...
 

Ähnlich wie Colongra fact sheet

Enmas o_&_m_presentation
Enmas  o_&_m_presentationEnmas  o_&_m_presentation
Enmas o_&_m_presentationlvsamy
 
Comprehensive Power Introduction Nov2013
Comprehensive Power Introduction Nov2013Comprehensive Power Introduction Nov2013
Comprehensive Power Introduction Nov2013Jeff Sable
 
Chris dowe-synergy’s-renewable-energy-integration
Chris dowe-synergy’s-renewable-energy-integrationChris dowe-synergy’s-renewable-energy-integration
Chris dowe-synergy’s-renewable-energy-integrationjames hamilton
 
Nidec asi corporate energy efficient power solutions
Nidec asi corporate energy   efficient power solutionsNidec asi corporate energy   efficient power solutions
Nidec asi corporate energy efficient power solutionsNidec Corporation
 
GE ADGT Products
GE ADGT ProductsGE ADGT Products
GE ADGT ProductsGE코리아
 
Se management presentation november 2010
Se management presentation november 2010Se management presentation november 2010
Se management presentation november 2010kmccarthy1981
 
Forenergy Project_Sylvain Martin_Biella conference
Forenergy Project_Sylvain Martin_Biella conferenceForenergy Project_Sylvain Martin_Biella conference
Forenergy Project_Sylvain Martin_Biella conferenceSylvain Martin
 
Comprehensive Power Introduction May 2013
Comprehensive Power Introduction May 2013Comprehensive Power Introduction May 2013
Comprehensive Power Introduction May 2013Jeff Sable
 
Biomass heat and power , Volter CHP, Cogeneration 40 kWe + 100 kWth
Biomass heat and power , Volter CHP, Cogeneration 40 kWe + 100 kWthBiomass heat and power , Volter CHP, Cogeneration 40 kWe + 100 kWth
Biomass heat and power , Volter CHP, Cogeneration 40 kWe + 100 kWthRado Irgl
 
GE ADGT Application CHP-Cogen-CC
GE ADGT Application CHP-Cogen-CCGE ADGT Application CHP-Cogen-CC
GE ADGT Application CHP-Cogen-CCGE코리아
 
Eaton ups energoefektivitate
Eaton ups energoefektivitateEaton ups energoefektivitate
Eaton ups energoefektivitateElektrumlv
 
Battery Storage Can Work in Every Level from Large to Small Companies to SMEs
Battery Storage Can Work in Every Level from Large to Small Companies to SMEsBattery Storage Can Work in Every Level from Large to Small Companies to SMEs
Battery Storage Can Work in Every Level from Large to Small Companies to SMEsEMEX
 

Ähnlich wie Colongra fact sheet (20)

Carrington
CarringtonCarrington
Carrington
 
Enmas o_&_m_presentation
Enmas  o_&_m_presentationEnmas  o_&_m_presentation
Enmas o_&_m_presentation
 
Gas power-plants
Gas power-plantsGas power-plants
Gas power-plants
 
Az-Zour
Az-ZourAz-Zour
Az-Zour
 
Comprehensive Power Introduction Nov2013
Comprehensive Power Introduction Nov2013Comprehensive Power Introduction Nov2013
Comprehensive Power Introduction Nov2013
 
Samra
SamraSamra
Samra
 
Chris dowe-synergy’s-renewable-energy-integration
Chris dowe-synergy’s-renewable-energy-integrationChris dowe-synergy’s-renewable-energy-integration
Chris dowe-synergy’s-renewable-energy-integration
 
Nidec asi corporate energy efficient power solutions
Nidec asi corporate energy   efficient power solutionsNidec asi corporate energy   efficient power solutions
Nidec asi corporate energy efficient power solutions
 
GE ADGT Products
GE ADGT ProductsGE ADGT Products
GE ADGT Products
 
Se management presentation november 2010
Se management presentation november 2010Se management presentation november 2010
Se management presentation november 2010
 
Forenergy Project_Sylvain Martin_Biella conference
Forenergy Project_Sylvain Martin_Biella conferenceForenergy Project_Sylvain Martin_Biella conference
Forenergy Project_Sylvain Martin_Biella conference
 
Comprehensive Power Introduction May 2013
Comprehensive Power Introduction May 2013Comprehensive Power Introduction May 2013
Comprehensive Power Introduction May 2013
 
Biomass heat and power , Volter CHP, Cogeneration 40 kWe + 100 kWth
Biomass heat and power , Volter CHP, Cogeneration 40 kWe + 100 kWthBiomass heat and power , Volter CHP, Cogeneration 40 kWe + 100 kWth
Biomass heat and power , Volter CHP, Cogeneration 40 kWe + 100 kWth
 
Heat exchangers
Heat exchangersHeat exchangers
Heat exchangers
 
Tzafit
TzafitTzafit
Tzafit
 
GE ADGT Application CHP-Cogen-CC
GE ADGT Application CHP-Cogen-CCGE ADGT Application CHP-Cogen-CC
GE ADGT Application CHP-Cogen-CC
 
Eaton ups energoefektivitate
Eaton ups energoefektivitateEaton ups energoefektivitate
Eaton ups energoefektivitate
 
09.02.2012 Modern coking coal technology, Peter Long
09.02.2012 Modern coking coal technology, Peter Long09.02.2012 Modern coking coal technology, Peter Long
09.02.2012 Modern coking coal technology, Peter Long
 
Battery Storage Can Work in Every Level from Large to Small Companies to SMEs
Battery Storage Can Work in Every Level from Large to Small Companies to SMEsBattery Storage Can Work in Every Level from Large to Small Companies to SMEs
Battery Storage Can Work in Every Level from Large to Small Companies to SMEs
 
Triac1
Triac1Triac1
Triac1
 

Colongra fact sheet

  • 1. POWER SYSTEMS PROJECT FEATURES Customer: Delta Electricity Notice to Proceed:July 2007 Main fuel: natural gas PROJECT HIGHLIGHTS - The most innovative & efficient solution to meet Australia’s growing power needs - Alstom’s fifth contract in Australia for the supply of GT13E2-based plant after Kwinana (under construction), Braemar, Cockburn and Pelican Point, which have been in operation since 2006, 2003 and 2001 respectively - Continuation of Alstom’s experience at Colongra site (Alstom supplied the original 4 x 300 MW steam turbines for this station back in the 1960’s) CUSTOMER BENEFITS - Quick starting gas turbine peaking plant - High flexibility & reliability - Optimal response to peak demand requirements - Low gas emission per unit of electricity produced The Colongra power plant is located at Munmorah, on the New South Wales central coast, 120 km north of Sydney, Australia Perth Hobart Launceston Burnie Bairnsdale Sale Geelong Ballarat Portland Kingston Ararat Bendigo Mildura Peterborough Port Augusta Ceduna Penong Eucla Forrest Tarcoola Woomera Roxby Downs Marree Oodnadatta Whyalla Port Lincoln Port Pirie Broken Hill Cobar Bourke Cunnamulla Dirranbandi Charleville Quilpie Birdsville Alice Springs Roma Bundaberg Gladstone Mackay Clermont Longreach Winton Cloncurry Normanton Forsayth Herberton Cairns Cooktown Laura Weipa Samarai Mount Isa Tennant Creek Barrow Creek Newcastle Waters Daly Waters Birdum Katherine Pine Creek Rum Jungle Wyndham Kununurra Fitzroy Crossing Derby Wave Hill The Granites Ord River Halls Creek Nhulunbuy Croydon Charters Towers Hughenden Blackall Mount Morgan Dalby Gympie Toowoomba Warwick Ipswich Lismore Grafton Coffs Harbour Port Macquarie Tamworth Armidale Moree Nyngan Dubbo Orange Hay Wagga Wagga Albury Devonport Newcastle Gold Coast Rockhampton Townsville Darwin Broome Port Hedland Dampier Preston Onslow Carnarvon Dongara Geraldton Wiluna Laverton Leonora Menzies Coolgardie Kalgoorlie Northam Narrogin AlbanyAugusta Collie Bunbury Kambalda Norseman Esperance Sandstone Meekatharra Roebourne Mount Goldsworthy Pilbara Mount Tom Price Mount Newman Mount Magnet Wollongong Elizabeth Sydney Brisbane Adelaide Melbourne CANBERRA Kupang Dili Ende Raba Mu rra y Lachlan Da rlin g Pa roo B arwon Thom son Diamanti na Daly Victo ria Fitzroy Fortescue A shburton Gascoyn Murchison Lake Eyre Lake Torrens Lake Frome Lake Gairdner Lake Everard Timor Melville Island Groote Eylandt Wellesley Islands FloresSumbawa Kangaroo Island King Island Furneaux Group Tasmania Fraser Island A u s t r a l i a S e a Gulf of Carpentaria C O R T i m o r S e a T A South East Cape Cape Leeuwin Geographe Bay Hood Point Shark Bay Cape Leveque Cape York Cape Arnhem G r e a t A u s t r a l i a n B i g h t INDIAN OCEAN COLONGRA - Australia 660 MW – GT13E2 Simple Cycle Power Plant An environmentally responsible way to meet Australia’s growing power needs Plant Integrator™ Levers Customer benefits INVESTMENT Optimised investment, integrating Operating & Maintenance costs LEAD-TIME Shorter lead times to produce electricity faster Higher Plant efficiency for increased power output PERFORMANCE at a wide range of operational modes Lower emissions to meet environmental concerns AVAILABILITY & FLEXIBILITY Better reliability, availability and flexibility RETROFIT Better Plant economics through Integrated Retrofit Solutions LIFE EXTENSION Extended plant life options More value for customers with Plant Integrator™ Plant Integrator™ is Alstom’s unique way of creating more value for customers. We combine outstanding expertise at the component and plant level, as we are both an equipment designer and manufacturer and an EPC contractor with extensive proven worldwide references. We ensure our customers meet their business objectives and serve their market better by collaborating with them. There are six Plant Integrator™ levers to increase the net present value for the Customer.
  • 2. PT-PE/BPROS/SCSMNM07/eng/PPS/12.07/FR/6214-allready-500385489RCSLyon POWER SYSTEMS Colongra plant arrangement COLONGRA - Australia 660MW–GT13E2-SimpleCyclePowerPlant ALSTOM’s SCOPE - Design, supply, installation and commissioning of the entire power plant - Turnkey delivery of: ● Turbine island ● Step-up transformers ● ALSPA Power Automation system ● Balance of Plant SUPERIOR INTEGRATION THROUGH ALSTOM’S PROJECT MANAGEMENT SKILLS, EPC CAPABILITIES AND STATE-OF-THE–ART KEY COMPONENTS Alstom’s proven and advanced technology is based on: - four modern, flexible & environmentally-friendly GT13E2 gas turbines - four high-efficiency air-cooled TOPAIR® turbogenerators Meeting Delta Electricity’s requirements Additional power was required to meet peak demand. Delta Electricity’s power generation portfolio consists of four coal-fired power plants totalling 4240 MW of capacity. Alstom’s turnkey delivery of the 660 MW gas fired peaking power plant will expand Delta Electricity’s capabilities in providing power during peak demand periods and will be an important complement to their existing portfolio of base load generation assets, serving the electricity needs of the future. This project confirms Alstom’s ability to deliver clean integrated power solutions