Extension of Time (EOT) and Related Costs
in Construction
www.cspk.org
Presented at the
FIDIC Middle East Contract Users’ Conference
February 2013 – Dubai, UAE
By
Khalil T. Hasan
Construction Solutions (www.cspk.org)
www.cspk.org
•Time is of Essence
•Delays are inevitable on construction projects
•The only project to have completed on time is a Mosque. Divine
intervention (or God’s help) was understood to be the force behind the
timely completion of this Mosque.
•Time and Money go hand-in-hand. When projects get late, additional
costs are incurred.
•This makes it imperative to take control of project delays; timely and
effectively.
www.cspk.org
•Majority of construction projects worldwide are administered by the
FIDIC forms of contract.
•FIDIC recognises delay and related costs and has provisions related
thereto. For example;
 Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition)
 Clauses 44 & 53 (FIDIC 1987 Edition)
FIDIC
FIDIC
FIDIC
FIDIC
FIDIC
www.cspk.org
The FIDIC Provisions define the conditions where delay may be
claimed as the basis for an Extension of Time (EOT). Some examples are;
 Late provision of design or drawings
 Unforeseeable Physical Conditions encountered on Site
 Inclement Weather
 Variations instructed by the Engineer (Additional Works etc.)
www.cspk.org
Meanwhile the principles of how delay and related
costs should be calculated are not defined by FIDIC.
This leads to issues; issues which are usually
contentious due to various 'schools of thoughts' and
varied interpretations existing worldwide.
Disputes are the usual outcome.
Contentious Issues in Delay Analysis
resulting in Disputes
– Critical Path
– Who owns the Float?
– Concurrent (or Contractor) Delays and how these effect
Entitlement
– EOT and its relation with Compensation for Delay
– Which is the best Method of Delay Analysis?
» As-Planned Vs. As-Built Comparison
» Impacted As-Planned
» Collapsed As-Built / But-For
» Time Slice / Sub-Networks / Time-Impact
» Etc.
www.cspk.org
www.cspk.org
In order to eliminate disputes or facilitate settlement of
disputes, there are now certain standards used worldwide.
The leading standards are;
 Society of Construction Law’s
Delay and Disruption Protocol (SCL Protocol)
 AACE 29R-03 (Forensic Schedule Analysis)
www.cspk.org
The SCL Protocol was
finalized in October 2002 after
several years of deliberations
and considerable debate and
agreement between experts
from different backgrounds
www.cspk.org
The objective of the SCL Protocol
was to bring reasonableness and
fairness into the delay assessment
process and to eliminate
widespread manipulation of
complex delay issues
www.cspk.org
The SCL Protocol tried to standardize
the issues such that disputes would be
reduced or eliminated
www.cspk.org
It is recommended that;
should be adopted as a Standard
and should be, where possible,
incorporated in the Construction
Contracts
www.cspk.org
The SCL Protocol can be downloaded from:
www.eotprotocol.com
www.cspk.org
The remaining slides of this lecture will
review and discuss the basic Principles
suggested and recommended by the
SCL Protocol
www.cspk.org
Basic Principles
suggested and recommended by
the SCL Protocol
www.cspk.org
The Principles suggested by the
SCL Protocol are simple.
Some of the key principles suggested
by the Protocol are;
www.cspk.org
RULE NO. 1
If there is an Employer’s delay, which is beyond the Contractor’s
control, and if this delay impacts the Completion Date of the Works,
the Contractor should be entitled to receive an
Extension of Time (EOT).
[This will effectively result in an extended Time for Completion and will
relieve the Contractor from having to pay penalties for delay (or
Delay Damages under FIDIC)]
www.cspk.org
RULE NO. 2
For the case of recovery of delay (or prolongation) costs incurred due to
the Employer delays, the Contractor must be able to prove that there has
been no other delay, which is in his own control, and which is equally
(or partly) contributing for delaying the Time for Completion.
This category of delay is called a ‘Concurrent’
(or Contractor’s) Delay
[In order to win a Delay Costs Claim, the Contractor must be able to
prove that he has not been responsible for Concurrent Delays to
the Time for Completion]
www.cspk.org
RULE NO. 3
Where Contractor’s Delay to Completion
occurs concurrently with Employer’s Delay
to Completion, the Contractor’s concurrent
delay should NOT reduce any
Extension of Time (EOT), which is due.
[Result of Rule No. 1 will not change and is irrespective of the result
of Rule No. 2]
www.cspk.org
The foregoing Rules proposed by the SCL Protocol are
meant to bring fairness and reasonableness into the
delay assessment process.
[The emphasis of the SCL Protocol is that no one Party
should benefit from default of the other Party]
www.cspk.org
The Illustrations demonstrating the principles of the SCL
Protocol are contained in the following Figures A to G
www.cspk.org
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Path 1 Float = 3.5 Weeks
Path 2 Float = 5.5 Weeks
Path 2
Figure A - Accepted Contract Programme
Weeks
Path 1
Contract Start
Date
Contract
Completion Date
www.cspk.org
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1 Float = 3.0 Weeks
Path 2 Float = 5.5 Weeks
AFTER EXCUSABLE DELAY
Excusable Delay
Path 1 Float = 1.0 Week
Path 2 Float = 5.5 Weeks
(a) 2.0 Weeks (a) 5.5 Weeks
(b) 1.0 Weeks (b) 0 Weeks
(c) 0 Weeks (c) 1.0 Weeks
(d) 5.5 Weeks (d) 2.0 Weeks
(a) 2.0 Weeks (a) 0.1% of Contract Price
(b) 1.0 Weeks (b) Direct Costs of Excusable Delay
(c) 0 Weeks (c) NIL
(d) 5.5 Weeks (d) (a) plus (b)
<=Date of Excusable Delay
Figure B - Delay Impact 1
Weeks
Path 1
Contract Start
Date
Contract
Completion Date
Path 2
(3) Compensation for Delay to
Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
Contract
Completion Date
Impact on Path 1
= 2.0 Weeks
Path 2
Path 1
www.cspk.org
Principles & Provisions of the SCL Protocol
relevant to Figure B
Core Principle No. 7 - Float as it relates to time
Unless there is express provision to the contrary in the contract, where there is remaining
float in the programme at the time of an Employer Risk Event, an EOT should only be
granted to the extent that the Employer Delay is predicted to reduce to below zero the total
float on the activity paths affected by the Employer Delay.
Guidance Section 1.12.1
If as a result of an Employer Delay, the Contractor is prevented from completing the works
by the Contractor’s planned completion date (being a date earlier than the contract
completion date), the Contractor should in principle be entitled to be paid the costs
directly caused by the Employer Delay, notwithstanding that there is no delay to the
contract completion date (and therefore no entitlement to an EOT), provided also that at
the time they enter into the contract, the Employer is aware of the Contractor’s intention to
complete the works prior to the contract completion date, and that intention is realistic and
achievable.
www.cspk.org
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1 Float = 3.0 Weeks
Path 2 Float = 5.5 Weeks
AFTER EXCUSABLE DELAY
Excusable Delay
Float = -0.5 Week
(a) 0.5 Weeks (a) 5.5 Weeks
(b) 3.5 Weeks (b) 0.5 Weeks
(c) 0 Weeks (c) 3.5 Weeks
(d) 5.5 Weeks (d) 0 Weeks
(a) 3.5 Weeks (a) 0.15% of Contract Price
(b) 0.5 Weeks (b) Direct Costs of Excusable Delay
(c) 0 Weeks (c) (a) plus (b)
(d) 3.0 Weeks (d) NIL
Contract
Completion Date
Impact on Path 1
= 3.5 Weeks
Path 2
Path 1
Path 2
(3) Compensation for Delay to
Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
<=Date of Excusable Delay
Figure C - Delay Impact 2
Weeks
Path 1
Contract Start
Date
Contract
Completion Date
www.cspk.org
Core Principle No. 4 - Procedure for granting extension of time
The EOT should be granted to the extent that the Employer Risk Event is
reasonably predicted to prevent the works being completed by the then
prevailing contract completion date…..The goal of the EOT procedure is
the ascertainment of the appropriate contractual entitlement to an EOT; the
procedure is not to be based on whether or not the Contractor needs an
EOT in order not to be liable for liquidated damages.
Core Principle No. 5 – Effect of delay
For an EOT to be granted, it is not necessary for the Employer Risk Event
already to have begun to affect the Contractor’s progress with the works,
or for the effect of the Employer Risk Event to have ended.
Principles & Provisions of the SCL Protocol
relevant to Figure C
www.cspk.org
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Path 1 Float = 3.0 Weeks
Path 2 Float = 5.5 Weeks
AFTER EXCUSABLE DELAY
Float = -0.5 Week
Excusable Delay
Impact on Path 2 = 6.0 Weeks
(a) 0 Weeks (a) 5.5 Weeks
(b) 6.0 Weeks (b) 0 Weeks
(c) 0.5 Weeks (c) 6.0 Weeks
(d) 5.5 Weeks (d) 0.5 Weeks
(a) 3.5 Weeks (a) (d) minus (c)
(b) 0.5 Weeks (b) Direct Costs of Excusable Delay
NIL
(c) 6.0 Weeks (c) Direct Costs of Excusable Delay
(d) 3.0 Weeks (d) 0.2% of Contract Price
<=Date of Excusable Delay
Figure D - Delay Impact 3
Weeks
Path 1
Contract Start
Date
Contract
Completion Date
Path 2
Path 1
Contract
Completion Date
Path 2
(3) Compensation for Delay to
Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
www.cspk.org
Core Principle No. 4 - Procedure for granting extension of time
The EOT should be granted to the extent that the Employer Risk Event is
reasonably predicted to prevent the works being completed by the then
prevailing contract completion date…..The goal of the EOT procedure is
the ascertainment of the appropriate contractual entitlement to an EOT; the
procedure is not to be based on whether or not the Contractor needs an
EOT in order not to be liable for liquidated damages.
Core Principle No. 5 – Effect of delay
For an EOT to be granted, it is not necessary for the Employer Risk Event
already to have begun to affect the Contractor’s progress with the works,
or for the effect of the Employer Risk Event to have ended.
Principles & Provisions of the SCL Protocol
relevant to Figure D
www.cspk.org
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
Contract Completion Date
Float = -1.5 Weeks
AFTER EXCUSABLE DELAY
Contract Completion Date
Excusable Delay
Impact on Path 1 = 2.0 Weeks
Float = -3.5 Weeks
(a) 3.5 Weeks (a) 2.0 Weeks
(b) 2.0 Weeks (b) 0 Weeks
(c) 1.5 Weeks (c) 3.5 Weeks
(d) 0 Weeks (d) 1.5 Weeks
(a) 3.5 Weeks (a) (c) plus (d)
(b) 2.0 Weeks (b) Direct Costs of Excusable Delay
NIL
(c) 3.0 Weeks (c) Direct Costs of Excusable Delay
(d) 0 Weeks (d) 0.1% of Contract Price
Figure E - Delay Impact 4
Weeks
Path 1
Contract Start
Date
<=Date of Excusable Delay
Path 2
Path 1
Path 2
(3) Compensation for Delay to
Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
www.cspk.org
Guidance Section 1.2.11
…an EOT should be granted to the extent that the Employer Risk Event is
predicted to prevent the works being completed by the then prevailing
contract completion date. This process requires consideration of the
available float…
Guidance Section 1.4.12
…Where there has been Employer Delay, this may prevent the Employer
charging the Contractor with LDs for failure to achieve a contract
completion date…
Principles & Provisions of the SCL Protocol
relevant to Figure E
www.cspk.org
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
<=Date of Excusable Delay
Contract Completion Date
Float = -1.5 Weeks
AFTER EXCUSABLE DELAY
Contract Completion Date
Impact on Path 1 = 2.0 Weeks
Excusable Delay
Float = -3.5 Weeks
(a) 2.0 Weeks (a) 0 Weeks
(b) 3.5 Weeks (b) 2.0 Weeks
(c) 1.5 Weeks (c) 3.5 Weeks
(d) 0 Weeks (d) 1.5 Weeks
(a) 3.5 Weeks (a) (c) plus (d)
(b) 2.0 Weeks (b) Direct Costs of Excusable Delay
NIL
(c) 3.0 Weeks (c) Direct Costs of Excusable Delay
(d) 0 Weeks (d) 0.1% of Contract Price
Figure F - Delay Impact 5
Weeks
Path 1
Contract Start
Date
Path 2
Path 1
Path 2
(3) Compensation for Delay to
Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
www.cspk.org
Guidance Section 1.4.8
Where an Employer Risk Event occurs after the contract completion date, in a
situation where failure to complete by the contract completion date has been caused
by Contractor Delays, the principle set out in Section 1.4.7 above should apply,
except where the Employer Risk Event is a non-compensable Employer Risk Event.
In such an event, no EOT (or compensation) should be due. Where an EOT is due
after the contract completion date, the Employer Risk Event does not exonerate the
Contractor for all its delays prior to the Employer Risk Event occurring. The effect
of the Employer Risk Event should be assessed as described above and any EOT
found due should simply be added to the contract completion date.
Principles & Provisions of the SCL Protocol
relevant to Figure F
www.cspk.org
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS)
<=Date of Excusable Delay
Contract Completion Date
Float = -1.5 Weeks
Path 2 Float = 2.5 Weeks
AFTER EXCUSABLE DELAY
Contract Completion Date
Float = -1.5 Weeks
Excusable Delay = 3.5 Weeks
(a) 2.5 Weeks (a) 0 Weeks
(b) 3.5 Weeks (b) 2.5 Weeks
(c) 1.0 Weeks (c) 3.5 Weeks
(d) 1.5 Weeks (d) 1.5 Weeks
(a) 0 Weeks (a) (b) plus (d)
(b) 2.0 Weeks (b) Direct Costs of Excusable Delay
(c) 3.0 Weeks (c) NIL
(d) 3.5 Weeks (d) 0.2% of Contract Price
Path 1
Path 2
(3) Compensation for Delay to
Progress
(1) EOT Entitlement (2) Period of Prolongation Costs
(4) Other Compensation
Figure G - Delay Impact 6
Weeks
Path 1
Contract Start
Date
Path 2
www.cspk.org
Guidance Section 1.4.1
Where Contractor Delay to Completion occurs concurrently with Employer Delay to
Completion, the Contractor’s concurrent delay should not reduce any EOT due.
Guidance Section 1.4.7
Where Employer Risk Events and Contractor Risk Events occur sequentially but
have concurrent effects, here again any Contractor Delay should not reduce the
amount of EOT due to the Contractor as a result of the Employer Delay.
Concurrency (Appendix A – Definations and Glossary)
True concurrent delay is the occurrence of two or more delay events at the same
time, one an Employer Risk Event, the other a Contractor Risk Event and the effects
of which are felt at the same time. The term ‘concurrent delay’ is often used to
describe the situation where two or more delay events arise at different times, but
the effects of them are felt (in whole or in part) at the same time. To avoid
confusion, this is more correctly termed the ‘concurrent effect’ of sequential delay
events.
Principles & Provisions of the SCL Protocol
relevant to Figure G – Slide 1/2
www.cspk.org
Core Principle No. 9 - Concurrent delay – its effect on entitlement to extension of time
Where Contractor Delay to Completion occurs or has effect concurrently with Employer
Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT
due.
Core Principle No. 14 - Link between extension of time and compensation
Entitlement to an EOT does not automatically lead to entitlement to compensation (and
vice versa).
Core Principle No. 10 - Concurrent delay – its effect on entitlement to compensation for
prolongation
If the Contractor incurs additional costs that are caused both by Employer Delay and
concurrent Contractor Delay, then the Contractor should only recover compensation to
the extent it is able to separately identify the additional costs caused by the Employer
Delay from those caused by the Contractor Delay. If it would have incurred the
additional costs in any event as a result of Contractor Delays, the Contractor will not be
entitled to recover those additional costs.
Principles & Provisions of the SCL Protocol
relevant to Figure G – Slide 2/2
www.cspk.org
Guidance Section 3.2.13
Although the programme should be the primary tool for guiding the
CA in his determination of EOT, it should be used in conjunction
with the contemporary evidence to ensure that the resulting EOT is
fair and reasonable. It will also be necessary for the parties to apply
common sense and experience to the process to ensure that all
relevant factors are taken into account, and that any anomalous
results generated by the programme analysis are managed properly.
Key Guideline, Suggestion and Advice of the
SCL Protocol
www.cspk.org
Figure No. Question 1 Question 2 Question 3 Question 4
B (c) (b) (a) (b)
C (a) (b) (d) (b)
D (c) (d) (d) (c)
E (b) (a) (d) (c)
F (a) (b) (d) (c)
G (c) (a) (a) (b)
Correct Responses for Figures B to G
Congratulations we
have come to the end of
the Lecture.
You are now a
Qualified and Certified
Delay Claims Analyst
and Expert.
www.cspk.org
FIDIC and Construction Solutions
thank you for your attendance and contribution.
We wish you all Good Luck.
www.cspk.org
We urge all participants to review the SCL Protocol on their own.
Construction Solutions’ Claims Management Division
(www.cspk.org) will remain available for further discussions on the
foregoing and any other relevant issue.
This Lecture was delivered by the Managing Partner of Construction Solutions,
Mr. Khalil Tayab Hasan. For any queries and clarifications, please feel free to
contact Mr. Hasan at;
khalilhasan@cspk.org
khalilhasan@hotmail.com
+971 50 8861709
+92 345 8500195
www.cspk.org

Weitere ähnliche Inhalte

Ähnlich wie FIDIC Lecture - EOT & Related Costs in Construction.pptx

Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Antonio Coladarce
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3 Rae Davies
 
Understanding Carbon Credits Business
Understanding Carbon Credits BusinessUnderstanding Carbon Credits Business
Understanding Carbon Credits BusinessAmit Chauhan
 
Matrix of responsibility
Matrix of responsibilityMatrix of responsibility
Matrix of responsibilityFarzana Amin
 
I0313048051
I0313048051I0313048051
I0313048051theijes
 
Psscoc 2008 db contract
Psscoc 2008 db contractPsscoc 2008 db contract
Psscoc 2008 db contractVance Ang
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
Improvement of the model of minimization of the costs in a time overrun conte...
Improvement of the model of minimization of the costs in a time overrun conte...Improvement of the model of minimization of the costs in a time overrun conte...
Improvement of the model of minimization of the costs in a time overrun conte...IAEME Publication
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Rae Davies
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice IIseenyeeyong
 
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfLec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfGhulamQadirWaqar1
 

Ähnlich wie FIDIC Lecture - EOT & Related Costs in Construction.pptx (20)

Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
Advanced Training for Construction Management: CONTRACTS MANAGEMENT part1
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
CFW NEC Management of change under the NEC3
CFW NEC  Management of change under the NEC3 CFW NEC  Management of change under the NEC3
CFW NEC Management of change under the NEC3
 
Understanding Carbon Credits Business
Understanding Carbon Credits BusinessUnderstanding Carbon Credits Business
Understanding Carbon Credits Business
 
Matrix of responsibility
Matrix of responsibilityMatrix of responsibility
Matrix of responsibility
 
I0313048051
I0313048051I0313048051
I0313048051
 
Psscoc 2008 db contract
Psscoc 2008 db contractPsscoc 2008 db contract
Psscoc 2008 db contract
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
Newsletter TE&A
Newsletter TE&ANewsletter TE&A
Newsletter TE&A
 
Improvement of the model of minimization of the costs in a time overrun conte...
Improvement of the model of minimization of the costs in a time overrun conte...Improvement of the model of minimization of the costs in a time overrun conte...
Improvement of the model of minimization of the costs in a time overrun conte...
 
AWI20202 commercial
AWI20202 commercialAWI20202 commercial
AWI20202 commercial
 
D012522433
D012522433D012522433
D012522433
 
Contractual brief
Contractual briefContractual brief
Contractual brief
 
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
Construction Futures Wales - NEC Workshop - Importance of Program Control & M...
 
Pp2 asignment-1
Pp2 asignment-1Pp2 asignment-1
Pp2 asignment-1
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfLec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdf
 

Kürzlich hochgeladen

An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 

Kürzlich hochgeladen (20)

An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 

FIDIC Lecture - EOT & Related Costs in Construction.pptx

  • 1. Extension of Time (EOT) and Related Costs in Construction www.cspk.org Presented at the FIDIC Middle East Contract Users’ Conference February 2013 – Dubai, UAE By Khalil T. Hasan Construction Solutions (www.cspk.org)
  • 2. www.cspk.org •Time is of Essence •Delays are inevitable on construction projects •The only project to have completed on time is a Mosque. Divine intervention (or God’s help) was understood to be the force behind the timely completion of this Mosque. •Time and Money go hand-in-hand. When projects get late, additional costs are incurred. •This makes it imperative to take control of project delays; timely and effectively.
  • 3. www.cspk.org •Majority of construction projects worldwide are administered by the FIDIC forms of contract. •FIDIC recognises delay and related costs and has provisions related thereto. For example;  Sub-Clauses 8.4 & 20.1 (FIDIC 1999 Edition)  Clauses 44 & 53 (FIDIC 1987 Edition) FIDIC FIDIC FIDIC FIDIC FIDIC
  • 4. www.cspk.org The FIDIC Provisions define the conditions where delay may be claimed as the basis for an Extension of Time (EOT). Some examples are;  Late provision of design or drawings  Unforeseeable Physical Conditions encountered on Site  Inclement Weather  Variations instructed by the Engineer (Additional Works etc.)
  • 5. www.cspk.org Meanwhile the principles of how delay and related costs should be calculated are not defined by FIDIC. This leads to issues; issues which are usually contentious due to various 'schools of thoughts' and varied interpretations existing worldwide. Disputes are the usual outcome.
  • 6. Contentious Issues in Delay Analysis resulting in Disputes – Critical Path – Who owns the Float? – Concurrent (or Contractor) Delays and how these effect Entitlement – EOT and its relation with Compensation for Delay – Which is the best Method of Delay Analysis? » As-Planned Vs. As-Built Comparison » Impacted As-Planned » Collapsed As-Built / But-For » Time Slice / Sub-Networks / Time-Impact » Etc. www.cspk.org
  • 7. www.cspk.org In order to eliminate disputes or facilitate settlement of disputes, there are now certain standards used worldwide. The leading standards are;  Society of Construction Law’s Delay and Disruption Protocol (SCL Protocol)  AACE 29R-03 (Forensic Schedule Analysis)
  • 8. www.cspk.org The SCL Protocol was finalized in October 2002 after several years of deliberations and considerable debate and agreement between experts from different backgrounds
  • 9. www.cspk.org The objective of the SCL Protocol was to bring reasonableness and fairness into the delay assessment process and to eliminate widespread manipulation of complex delay issues
  • 10. www.cspk.org The SCL Protocol tried to standardize the issues such that disputes would be reduced or eliminated
  • 11. www.cspk.org It is recommended that; should be adopted as a Standard and should be, where possible, incorporated in the Construction Contracts
  • 12. www.cspk.org The SCL Protocol can be downloaded from: www.eotprotocol.com
  • 13. www.cspk.org The remaining slides of this lecture will review and discuss the basic Principles suggested and recommended by the SCL Protocol
  • 14. www.cspk.org Basic Principles suggested and recommended by the SCL Protocol
  • 15. www.cspk.org The Principles suggested by the SCL Protocol are simple. Some of the key principles suggested by the Protocol are;
  • 16. www.cspk.org RULE NO. 1 If there is an Employer’s delay, which is beyond the Contractor’s control, and if this delay impacts the Completion Date of the Works, the Contractor should be entitled to receive an Extension of Time (EOT). [This will effectively result in an extended Time for Completion and will relieve the Contractor from having to pay penalties for delay (or Delay Damages under FIDIC)]
  • 17. www.cspk.org RULE NO. 2 For the case of recovery of delay (or prolongation) costs incurred due to the Employer delays, the Contractor must be able to prove that there has been no other delay, which is in his own control, and which is equally (or partly) contributing for delaying the Time for Completion. This category of delay is called a ‘Concurrent’ (or Contractor’s) Delay [In order to win a Delay Costs Claim, the Contractor must be able to prove that he has not been responsible for Concurrent Delays to the Time for Completion]
  • 18. www.cspk.org RULE NO. 3 Where Contractor’s Delay to Completion occurs concurrently with Employer’s Delay to Completion, the Contractor’s concurrent delay should NOT reduce any Extension of Time (EOT), which is due. [Result of Rule No. 1 will not change and is irrespective of the result of Rule No. 2]
  • 19. www.cspk.org The foregoing Rules proposed by the SCL Protocol are meant to bring fairness and reasonableness into the delay assessment process. [The emphasis of the SCL Protocol is that no one Party should benefit from default of the other Party]
  • 20. www.cspk.org The Illustrations demonstrating the principles of the SCL Protocol are contained in the following Figures A to G
  • 21. www.cspk.org 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 Path 1 Float = 3.5 Weeks Path 2 Float = 5.5 Weeks Path 2 Figure A - Accepted Contract Programme Weeks Path 1 Contract Start Date Contract Completion Date
  • 22. www.cspk.org 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1 Float = 3.0 Weeks Path 2 Float = 5.5 Weeks AFTER EXCUSABLE DELAY Excusable Delay Path 1 Float = 1.0 Week Path 2 Float = 5.5 Weeks (a) 2.0 Weeks (a) 5.5 Weeks (b) 1.0 Weeks (b) 0 Weeks (c) 0 Weeks (c) 1.0 Weeks (d) 5.5 Weeks (d) 2.0 Weeks (a) 2.0 Weeks (a) 0.1% of Contract Price (b) 1.0 Weeks (b) Direct Costs of Excusable Delay (c) 0 Weeks (c) NIL (d) 5.5 Weeks (d) (a) plus (b) <=Date of Excusable Delay Figure B - Delay Impact 1 Weeks Path 1 Contract Start Date Contract Completion Date Path 2 (3) Compensation for Delay to Progress (1) EOT Entitlement (2) Period of Prolongation Costs (4) Other Compensation Contract Completion Date Impact on Path 1 = 2.0 Weeks Path 2 Path 1
  • 23. www.cspk.org Principles & Provisions of the SCL Protocol relevant to Figure B Core Principle No. 7 - Float as it relates to time Unless there is express provision to the contrary in the contract, where there is remaining float in the programme at the time of an Employer Risk Event, an EOT should only be granted to the extent that the Employer Delay is predicted to reduce to below zero the total float on the activity paths affected by the Employer Delay. Guidance Section 1.12.1 If as a result of an Employer Delay, the Contractor is prevented from completing the works by the Contractor’s planned completion date (being a date earlier than the contract completion date), the Contractor should in principle be entitled to be paid the costs directly caused by the Employer Delay, notwithstanding that there is no delay to the contract completion date (and therefore no entitlement to an EOT), provided also that at the time they enter into the contract, the Employer is aware of the Contractor’s intention to complete the works prior to the contract completion date, and that intention is realistic and achievable.
  • 24. www.cspk.org 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1 Float = 3.0 Weeks Path 2 Float = 5.5 Weeks AFTER EXCUSABLE DELAY Excusable Delay Float = -0.5 Week (a) 0.5 Weeks (a) 5.5 Weeks (b) 3.5 Weeks (b) 0.5 Weeks (c) 0 Weeks (c) 3.5 Weeks (d) 5.5 Weeks (d) 0 Weeks (a) 3.5 Weeks (a) 0.15% of Contract Price (b) 0.5 Weeks (b) Direct Costs of Excusable Delay (c) 0 Weeks (c) (a) plus (b) (d) 3.0 Weeks (d) NIL Contract Completion Date Impact on Path 1 = 3.5 Weeks Path 2 Path 1 Path 2 (3) Compensation for Delay to Progress (1) EOT Entitlement (2) Period of Prolongation Costs (4) Other Compensation <=Date of Excusable Delay Figure C - Delay Impact 2 Weeks Path 1 Contract Start Date Contract Completion Date
  • 25. www.cspk.org Core Principle No. 4 - Procedure for granting extension of time The EOT should be granted to the extent that the Employer Risk Event is reasonably predicted to prevent the works being completed by the then prevailing contract completion date…..The goal of the EOT procedure is the ascertainment of the appropriate contractual entitlement to an EOT; the procedure is not to be based on whether or not the Contractor needs an EOT in order not to be liable for liquidated damages. Core Principle No. 5 – Effect of delay For an EOT to be granted, it is not necessary for the Employer Risk Event already to have begun to affect the Contractor’s progress with the works, or for the effect of the Employer Risk Event to have ended. Principles & Provisions of the SCL Protocol relevant to Figure C
  • 26. www.cspk.org 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Path 1 Float = 3.0 Weeks Path 2 Float = 5.5 Weeks AFTER EXCUSABLE DELAY Float = -0.5 Week Excusable Delay Impact on Path 2 = 6.0 Weeks (a) 0 Weeks (a) 5.5 Weeks (b) 6.0 Weeks (b) 0 Weeks (c) 0.5 Weeks (c) 6.0 Weeks (d) 5.5 Weeks (d) 0.5 Weeks (a) 3.5 Weeks (a) (d) minus (c) (b) 0.5 Weeks (b) Direct Costs of Excusable Delay NIL (c) 6.0 Weeks (c) Direct Costs of Excusable Delay (d) 3.0 Weeks (d) 0.2% of Contract Price <=Date of Excusable Delay Figure D - Delay Impact 3 Weeks Path 1 Contract Start Date Contract Completion Date Path 2 Path 1 Contract Completion Date Path 2 (3) Compensation for Delay to Progress (1) EOT Entitlement (2) Period of Prolongation Costs (4) Other Compensation
  • 27. www.cspk.org Core Principle No. 4 - Procedure for granting extension of time The EOT should be granted to the extent that the Employer Risk Event is reasonably predicted to prevent the works being completed by the then prevailing contract completion date…..The goal of the EOT procedure is the ascertainment of the appropriate contractual entitlement to an EOT; the procedure is not to be based on whether or not the Contractor needs an EOT in order not to be liable for liquidated damages. Core Principle No. 5 – Effect of delay For an EOT to be granted, it is not necessary for the Employer Risk Event already to have begun to affect the Contractor’s progress with the works, or for the effect of the Employer Risk Event to have ended. Principles & Provisions of the SCL Protocol relevant to Figure D
  • 28. www.cspk.org 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) Contract Completion Date Float = -1.5 Weeks AFTER EXCUSABLE DELAY Contract Completion Date Excusable Delay Impact on Path 1 = 2.0 Weeks Float = -3.5 Weeks (a) 3.5 Weeks (a) 2.0 Weeks (b) 2.0 Weeks (b) 0 Weeks (c) 1.5 Weeks (c) 3.5 Weeks (d) 0 Weeks (d) 1.5 Weeks (a) 3.5 Weeks (a) (c) plus (d) (b) 2.0 Weeks (b) Direct Costs of Excusable Delay NIL (c) 3.0 Weeks (c) Direct Costs of Excusable Delay (d) 0 Weeks (d) 0.1% of Contract Price Figure E - Delay Impact 4 Weeks Path 1 Contract Start Date <=Date of Excusable Delay Path 2 Path 1 Path 2 (3) Compensation for Delay to Progress (1) EOT Entitlement (2) Period of Prolongation Costs (4) Other Compensation
  • 29. www.cspk.org Guidance Section 1.2.11 …an EOT should be granted to the extent that the Employer Risk Event is predicted to prevent the works being completed by the then prevailing contract completion date. This process requires consideration of the available float… Guidance Section 1.4.12 …Where there has been Employer Delay, this may prevent the Employer charging the Contractor with LDs for failure to achieve a contract completion date… Principles & Provisions of the SCL Protocol relevant to Figure E
  • 30. www.cspk.org 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) <=Date of Excusable Delay Contract Completion Date Float = -1.5 Weeks AFTER EXCUSABLE DELAY Contract Completion Date Impact on Path 1 = 2.0 Weeks Excusable Delay Float = -3.5 Weeks (a) 2.0 Weeks (a) 0 Weeks (b) 3.5 Weeks (b) 2.0 Weeks (c) 1.5 Weeks (c) 3.5 Weeks (d) 0 Weeks (d) 1.5 Weeks (a) 3.5 Weeks (a) (c) plus (d) (b) 2.0 Weeks (b) Direct Costs of Excusable Delay NIL (c) 3.0 Weeks (c) Direct Costs of Excusable Delay (d) 0 Weeks (d) 0.1% of Contract Price Figure F - Delay Impact 5 Weeks Path 1 Contract Start Date Path 2 Path 1 Path 2 (3) Compensation for Delay to Progress (1) EOT Entitlement (2) Period of Prolongation Costs (4) Other Compensation
  • 31. www.cspk.org Guidance Section 1.4.8 Where an Employer Risk Event occurs after the contract completion date, in a situation where failure to complete by the contract completion date has been caused by Contractor Delays, the principle set out in Section 1.4.7 above should apply, except where the Employer Risk Event is a non-compensable Employer Risk Event. In such an event, no EOT (or compensation) should be due. Where an EOT is due after the contract completion date, the Employer Risk Event does not exonerate the Contractor for all its delays prior to the Employer Risk Event occurring. The effect of the Employer Risk Event should be assessed as described above and any EOT found due should simply be added to the contract completion date. Principles & Provisions of the SCL Protocol relevant to Figure F
  • 32. www.cspk.org 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 PRIOR TO EXCUSABLE DELAY (UPDATE WITH ACTUAL PROGRESS) <=Date of Excusable Delay Contract Completion Date Float = -1.5 Weeks Path 2 Float = 2.5 Weeks AFTER EXCUSABLE DELAY Contract Completion Date Float = -1.5 Weeks Excusable Delay = 3.5 Weeks (a) 2.5 Weeks (a) 0 Weeks (b) 3.5 Weeks (b) 2.5 Weeks (c) 1.0 Weeks (c) 3.5 Weeks (d) 1.5 Weeks (d) 1.5 Weeks (a) 0 Weeks (a) (b) plus (d) (b) 2.0 Weeks (b) Direct Costs of Excusable Delay (c) 3.0 Weeks (c) NIL (d) 3.5 Weeks (d) 0.2% of Contract Price Path 1 Path 2 (3) Compensation for Delay to Progress (1) EOT Entitlement (2) Period of Prolongation Costs (4) Other Compensation Figure G - Delay Impact 6 Weeks Path 1 Contract Start Date Path 2
  • 33. www.cspk.org Guidance Section 1.4.1 Where Contractor Delay to Completion occurs concurrently with Employer Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT due. Guidance Section 1.4.7 Where Employer Risk Events and Contractor Risk Events occur sequentially but have concurrent effects, here again any Contractor Delay should not reduce the amount of EOT due to the Contractor as a result of the Employer Delay. Concurrency (Appendix A – Definations and Glossary) True concurrent delay is the occurrence of two or more delay events at the same time, one an Employer Risk Event, the other a Contractor Risk Event and the effects of which are felt at the same time. The term ‘concurrent delay’ is often used to describe the situation where two or more delay events arise at different times, but the effects of them are felt (in whole or in part) at the same time. To avoid confusion, this is more correctly termed the ‘concurrent effect’ of sequential delay events. Principles & Provisions of the SCL Protocol relevant to Figure G – Slide 1/2
  • 34. www.cspk.org Core Principle No. 9 - Concurrent delay – its effect on entitlement to extension of time Where Contractor Delay to Completion occurs or has effect concurrently with Employer Delay to Completion, the Contractor’s concurrent delay should not reduce any EOT due. Core Principle No. 14 - Link between extension of time and compensation Entitlement to an EOT does not automatically lead to entitlement to compensation (and vice versa). Core Principle No. 10 - Concurrent delay – its effect on entitlement to compensation for prolongation If the Contractor incurs additional costs that are caused both by Employer Delay and concurrent Contractor Delay, then the Contractor should only recover compensation to the extent it is able to separately identify the additional costs caused by the Employer Delay from those caused by the Contractor Delay. If it would have incurred the additional costs in any event as a result of Contractor Delays, the Contractor will not be entitled to recover those additional costs. Principles & Provisions of the SCL Protocol relevant to Figure G – Slide 2/2
  • 35. www.cspk.org Guidance Section 3.2.13 Although the programme should be the primary tool for guiding the CA in his determination of EOT, it should be used in conjunction with the contemporary evidence to ensure that the resulting EOT is fair and reasonable. It will also be necessary for the parties to apply common sense and experience to the process to ensure that all relevant factors are taken into account, and that any anomalous results generated by the programme analysis are managed properly. Key Guideline, Suggestion and Advice of the SCL Protocol
  • 36. www.cspk.org Figure No. Question 1 Question 2 Question 3 Question 4 B (c) (b) (a) (b) C (a) (b) (d) (b) D (c) (d) (d) (c) E (b) (a) (d) (c) F (a) (b) (d) (c) G (c) (a) (a) (b) Correct Responses for Figures B to G
  • 37. Congratulations we have come to the end of the Lecture. You are now a Qualified and Certified Delay Claims Analyst and Expert. www.cspk.org
  • 38. FIDIC and Construction Solutions thank you for your attendance and contribution. We wish you all Good Luck. www.cspk.org
  • 39. We urge all participants to review the SCL Protocol on their own. Construction Solutions’ Claims Management Division (www.cspk.org) will remain available for further discussions on the foregoing and any other relevant issue. This Lecture was delivered by the Managing Partner of Construction Solutions, Mr. Khalil Tayab Hasan. For any queries and clarifications, please feel free to contact Mr. Hasan at; khalilhasan@cspk.org khalilhasan@hotmail.com +971 50 8861709 +92 345 8500195 www.cspk.org