A Primer of Commonly Overlooked
Issues in Construction Projects
Presentation for
Introduction
Presentation Goal:
This session will address some commonly overlooked critical items in
the planning and execution of construction projects which could
improve the overall performance of the project and reduce the risk of
disputes and claims.
Presenters:
Jake Ortego, PE, CCA, CCP, CCE
President – JA Cost Engineers and Advisors, Inc.
BS – Mechanical Engineering, Boston University
15+ Years in Engineering, Construction and Consulting
www.ja-cea.com
j@ja-cea.com
David Anderson
School Board Member –Kiski Area SD
BS – Chemical Engineering, The Pennsylvania State University
MBA – Robert Morris University
12+ Years in Engineering and Consulting
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 2 of 28
Construction Goals
Construction Projects follow the principle of the triple constraint of
Quality (or Scope), Cost and Schedule.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 3 of 28
Quality/Scope
CostSchedule
An emphasis on any one of the constraints will have an effect on
the other two.
Who’s Who?
There are many parties involved in a construction project that have
different skill sets and knowledge. Below is a quick guide to the
major groups beyond the Owner and Contractors. The focus of this
guide is related to advocating the Owner’s Interest.
Architect (and Engineer) – AKA “A/E” – They are responsible for
the artistic and technical design of the building. The design quality
from the A/E firms can greatly influence the total cost of the project.
A/E firms typically have limited hands on field experience and limited
knowledge of contract language.
Solicitor (Legal Council) – This is the main advocate for the
Owner’s legal interests. The Solicitors should have a detailed
knowledge of local, state and federal codes, mandates and
precedence regarding construction law. Although many solicitors
have knowledge of the law, very few have experience in the execution
of a construction project.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 4 of 28
Who’s Who? (cont.)
Construction Manager – If used on a project, the CM should protect
the Owner’s interest while coordinating all of the contractors,
vendors, consultants, etc. to bring the project to a successful
completion. In today’s construction market, many CM’s are general
contractors who are expanding their capabilities.
Clerk of the Works – The intent is for the COTW to protect the
interests of the Owner in regard to ensuring the quality of both
materials and workmanship are in accordance with the design
information such as specification and engineering drawings. Many
COTW’s have construction experience, but limited design or contract
training and/or experience.
Owners Representative – This role could include duties ranging
from a CM to a COTW to a advisory consultant. An Owner's Rep
services is not a substitute for an architect, contractor, legal counsel,
or Owner themselves. There is no clear standard for this role.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 5 of 28
Ability to Influence Costs
The ability to influence project goals diminishes with time.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 6 of 28
What is the Cost of Work?
Cost of Work (“COW”) is an term which can have multiple meanings
and interpretations.
• Typical Contracts define the COW as all costs except for the
Contractors Fee.
• Many insurance companies define the COW as all costs except for
the insurance.
• Some parties see the COW as the total cost of the contract
including fees and insurances.
The difference can be seem trivial, but become material when
calculating Fees, Insurances and Tax (where applicable) for change
orders.
It is important to clearly understand and define COW on every
project.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 7 of 28
What Causes Overruns
A common perception is that the primary driver to project overruns is
due to the contractors.
This is only part of the story
Owners are a major source of change due to
• Undefined Scope
• Modifications made during construction
Architects are also a major source of change due to
• Incomplete designs
• Overdesigning
• Performance to the Standard of Care
Depending on the state, it is accepted that the an Architects standard
of care is between 3% to 5% of the construction costs.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 8 of 28
Avoiding Disputes and Claims
Disputes and claims are often the result of:
• Miscommunication
• Unclear Expectations
• Unrealistic Expectations
• Poorly defined scope
• Different interpretations of the Contract
Avoiding disputes and claims can often be done with:
• Open Communication
• Explicit Definitions
• Mutual Understanding
What follows are areas that are commonly overlooked by owners while
planning, designing and executing a construction project.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 9 of 28
Define the Expectations (part 1)
As an Owner, you have responsibilities to the project.
During the project you will need to clearly establish the expectations
of your team regarding:
• Clear lines of authority for providing direction and approval for
project decisions
• Time to review and approve design/drawings
• Time limits on responding to Requests for Information (“RFI”)
• Time limits on responding to Change Orders
• Time limits on reviewing and approving Applications for
Payment (“Pay Apps”)
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 10 of 28
Define the Expectations (part 2)
Architects and Engineers (“A/E”) are design professionals. Most have
limited to no experience actually managing a construction project.
Most people expect that the Architects will be involved in nearly every
aspect of the project and will represent the Owner’s Interest.
It is recommended that open discussion are held with the Architect to
discuss each of the following:
• Establishing a budget that the A/E is to design to
• The level and detail that the A/E will review the Pay Applications
• The level and detail that the A/E will review the Change Orders
• The frequency and expectations of site visits
• The basis of the fee and what will constitute a change
• The schedule expectations
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 11 of 28
Understand your Accuracy
Misunderstanding an Estimate can set a project up to fail.
Construction costs can vary greatly due to time, location and resource
availability. As a result Construction estimates are only 100% when
the project is complete and final costs are submitted.
It is important to understand the accuracy of your estimates to help
plan for the potential costs of a project.
The following is an example of the accuracy to expect from estimates.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 12 of 28
Estimate from SQF Est 75% Dwgs 90% Dwgs*
Architect ± 30% ± 25% ± 20%
Independent Estimator ± 25% ± 20% ± 10%
CM or GC ± 20% ± 15% ± 5%
*Note: for this example, 90% are considered “Issued for Construction”
Contingency vs. Allowance
Allowances and contingencies are used to plan for items that are not
clearly defined or for unknown circumstances.
Allowances are for “Known Unknowns”.
Example: Landscaping will be performed at the conclusion of the
project, but the exact configuration and selections have not been
finalized.
Contingencies are for “Unknown Unknowns”.
This should be reserved for items that cannot be clearly identified
at the planning, design and bidding of the project.
A common mistake is to use contingency for items that should be an
allowance. This can exhaust the contingency before it has a chance
to be used for truly unforeseen events.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 13 of 28
Plan for Unexpected
In addition to accuracy of the estimate, owners should add costs to their
budgets for the following:
• Quality of the drawings
• Price Escalation and Inflation for projects over 1 year
• Increase labor rates for projects over 1 year
• Potential changes requested within the school district.
Most projects should carry a 10% contingency on top of any estimate.
In the rare cases where the drawings are complete and the scope is well
defined, contingency should not be any lower than 5%.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 14 of 28
Value Eng. Vs Scope Reduction
Value Engineering and Scope Reduction are different!
Value Engineering is the practice of altering the scope to achieve the
same performance goals at a lower installation or operating cost.
Example: Replacing Wood Framed Windows with Vinyl Framed
windows could result in a savings in material while still achieving
the desired lighting.
Scope Reduction is the practice of removing items from the scope of
work to lower costs.
Example: Removing windows in lieu of a wall will save material and
installation cost, but also not achieve the desired lighting.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 15 of 28
Independent Estimates
Having an independent estimate performed on the Construction
Drawings prior to sending them out for bid can be valuable in
identifying the possible ambiguity in the drawings. The independent
estimate should be configured to cleanly match the A/E’s estimate.
Major variances exist between the A/E Estimate and the Independent
Estimate can be addressed in the following way:
• Require the Architect to review the basis of bid to determine the
cause of the differences. If it is an issue of interpretation, the
A/E should update their drawings to alleviate any ambiguity.
• Isolate the major differences and ask that bidders provide a
breakout price for this area.
• Remove any major difference from the bidding documents (or
place them on hold) until the drawings are further developed.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 16 of 28
Details in the Bids
It is easier to ask questions and state expectations during bidding
than it is after the award. The words “Lowest Responsive Bidder”
does not prevent the Owner from requiring bid details.
Examples include:
• Requiring Bidders to acknowledge that all change orders will have
no more than a 15% markup for the prime with a total mark up
not to exceed 20% of the base cost of work
• Requiring Bidders to acknowledge that all change orders will be
submitted with complete supporting information for cost, labor,
subcontractors, fees and insurances
• Requesting bidders to provide add and deducts for any areas of
the scope that may not be well defined.
• Requesting the bidders to identify any areas of the bid documents
which are unclear or unbuildable.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 17 of 28
Define the Expectations (part 3)
As with the project team and architect, it is prudent to define your
expectations for the Construction Manager, General Contractor or
and/or Prime Contractors including:
• Change Management
• Change Multipliers (or Markups)
• Reporting Requirements
• Scheduling Requirements
• Substantial Completion
• Invoicing Requirements
• Incentives or Liquidated Damages
• How Contingency is to be Spent
Any agreements to these types of discussions
should be included as part of the contract.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 18 of 28
Modify the Contract
The contract is the place where all of the agreements governing the
execution of the project are captured.
Consider the following:
• AIA Contracts are written by Architects
• ACG are written by Contractors
• There are no standard contract templates that advocate the
owner
The standard templates are meant to be flexible. But in doing so,
they often are ambiguous.
Ambiguity leads to the possibility of different interpretations which
can lead to claims.
Ambiguity is typically construed against the drafter.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 19 of 28
Modify the Contract (cont.)
Recommended areas to focus on that are typically ambiguous include:
• Mark ups for changes and for pay applications
• Rates for additional work
• Pay Applications being percent complete or substantiated (Cost
Plus)
• Basis of Allowances
• Expectations and Agreements they may have been verbally
discussed.
• Any part of the contract that uses the word “reasonable” should be
explicitly defined.
All contracts can be modified, but not all modifications are legal. Discuss
any modifications with your legal council before implementing.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 20 of 28
Fast Track vs. Fast Pace
The two terms are often confused and interchanged.
“Fast Track” is a method of staggering the sequence of a project to
achieve a shorter total design – construct duration. Construction
Starts as the drawings per discipline are issued.
The inherent risk is that the items typically designed last (MEP)
have more stringent constraints due to the physical completion of
the earlier items such as Civil and Structural.
“Fast Pace” or “Accelerated” is the method of compressing
components of the schedule to achieve a shorter duration for any
part(s) of the project.
The risks lie in over congested project sites, overtime, shift work
and lowered quality.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 21 of 28
Expect Change
Change is a normal and expected part of every project!
No design is perfect and changes help all parties adjust the design to
meet the physical expectations of construction. A well planned
project is designed to absorb a certain level of change.
When evaluating and approving changes,
consider each of the following:
• Was it in the base scope?
• Is it needed or wanted?
• Are the costs supported and
reasonable?
• Is there any impact to the duration of the project?
Always get a change in writing and never authorize a blanket change
order without costs and/or limits.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 22 of 28
No News can be Bad News
One of the methods to manage the risk of overruns and delays is to
proactively identify potential issues before they escalate.
Here are some recommended methods to do this:
• Question the contractors and their subs to identify unknowns
and possible risks on a weekly basis.
• Encourage the contractors and their subcontractors to submit
their invoices on the regular cycle.
Work the Construction Manager and Prime Contractors to
forecast the project’s workload and cash flow.
• Encourage Requests for Information (“RFI”) to be submitted for
all design and specification questions.
• Keep the contractors informed about any owner related items
that will affect their schedule or activities.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 23 of 28
Errors and Omissions
The is one of the most commonly misunderstood aspects of increased
costs to a project.
It is expected that A/E firms have up to a 3% error and omission
rate. In some states, this value may be as high as 5%.
Errors are items that are incorrectly designed and require rework to
correct if construction on this item has started.
Example: A set of stairs ends 2 ft under the landing. To correct,
the stairs may have to be re-fabricated.
The price of fixing an error is made up of costs directly related to
fixing this issue. This could involve other ancillary work that may be
affected by the corrections
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 24 of 28
Errors and Omissions (cont.)
Omissions are items that have been either unintentionally omitted
from the design. They may require rework to incorporate the
omission.
Example: A set of stairs does not have any hand railing in the
design. To correct, the handrail will have to be fabricated and
installed.
The Owner must still pay for the base item regardless if it was not in
the base design and estimates.
The cost of the omission is considered to be any additional costs
required to include the omitted scope that is greater than what would
have been paid if the scope was included in the design.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 25 of 28
Errors and Omissions (cont.)
From a contractors perspective, the Owner is required to pay for the
entire amount to fix an error or omission.
As long as the item is not included in the scope of work to the
contractor, then this assumption is correct.
The owner may attempt to pass the cost on to their A/E Firms.
Most A/E firms have insurance for errors and omissions. The
insurance is only intended to cover the added costs for correction.
It is rare for claims to be awarded if the total cost of errors and
omissions is under 3% of the construction costs.
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 26 of 28
Conclusion
It is reasonable to discuss any and all items in this report with your
Architect, Solicitor and Construction Firms.
In general, you can increase you chances
of a successful project by:
• Good Planning
• Defining Expectations
• Clarify Assumptions
• Communicating with the Team
Another equally good way of
executing project is to:
• Be Definite
• Be Clear
• Be Fair
• Be Careful
A Primer of Commonly Overlooked Issues in Construction Projects
School Design and Construction Conference
Slide 27 of 28
QUESTIONS

Weitere ähnliche Inhalte

Was ist angesagt?

Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projectsPALLA NARASIMHUDU
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...IJMER
 
6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery MethodsMcCarthy Holdings, Inc.
 
Evaluation of the factors influencing time and cost overruns in telecom tower...
Evaluation of the factors influencing time and cost overruns in telecom tower...Evaluation of the factors influencing time and cost overruns in telecom tower...
Evaluation of the factors influencing time and cost overruns in telecom tower...Alexander Decker
 
Design-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful OutcomesDesign-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful OutcomesMcCarthy Holdings, Inc.
 
Nuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting ModelsNuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting ModelsThis account is closed
 
Stakeholder management In Construction Industry
Stakeholder management In  Construction IndustryStakeholder management In  Construction Industry
Stakeholder management In Construction IndustryGirish Singh
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims EffectivelySHAZEBALIKHAN1
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...marcus evans Network
 
ConstructionFlow
ConstructionFlowConstructionFlow
ConstructionFlowJeff Dixon
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1Charles S. Maggio
 
The role of an Architect
The role of an ArchitectThe role of an Architect
The role of an ArchitectClara Lee
 
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...Alberto Sanchez
 
Project management risks for rail projects
Project management risks for rail projectsProject management risks for rail projects
Project management risks for rail projectsEdgilis
 

Was ist angesagt? (20)

Project Delivery Method Selection Tool
Project Delivery Method Selection ToolProject Delivery Method Selection Tool
Project Delivery Method Selection Tool
 
Risk analysis and managements large epc projects
Risk analysis and managements  large epc projectsRisk analysis and managements  large epc projects
Risk analysis and managements large epc projects
 
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
Stakeholders’ Perception of the Causes and Effect of Construction Delays on P...
 
DESIGN & BUILD
DESIGN & BUILDDESIGN & BUILD
DESIGN & BUILD
 
6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods
 
Evaluation of the factors influencing time and cost overruns in telecom tower...
Evaluation of the factors influencing time and cost overruns in telecom tower...Evaluation of the factors influencing time and cost overruns in telecom tower...
Evaluation of the factors influencing time and cost overruns in telecom tower...
 
Design-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful OutcomesDesign-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful Outcomes
 
Nuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting ModelsNuclear Supply Chain Symposium - Canadian Contracting Models
Nuclear Supply Chain Symposium - Canadian Contracting Models
 
Stakeholder management In Construction Industry
Stakeholder management In  Construction IndustryStakeholder management In  Construction Industry
Stakeholder management In Construction Industry
 
Managing the Construction Claims Effectively
Managing the Construction Claims EffectivelyManaging the Construction Claims Effectively
Managing the Construction Claims Effectively
 
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
Construction Projects Delivery Methods - Nilaksh Kothari, Manitowoc Public Ut...
 
Chapter 1
Chapter 1Chapter 1
Chapter 1
 
ConstructionFlow
ConstructionFlowConstructionFlow
ConstructionFlow
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Akinjiyan_Olufemi_DRP14-15 Submitted
Akinjiyan_Olufemi_DRP14-15 SubmittedAkinjiyan_Olufemi_DRP14-15 Submitted
Akinjiyan_Olufemi_DRP14-15 Submitted
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
GENERIC - Comparing Different Construction Delivery Methods - Aug 2014_r1
 
The role of an Architect
The role of an ArchitectThe role of an Architect
The role of an Architect
 
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
 
Project management risks for rail projects
Project management risks for rail projectsProject management risks for rail projects
Project management risks for rail projects
 

Ähnlich wie PASBA 2010 presentation

CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdfCCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdfChassyTesoro1
 
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfLec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfGhulamQadirWaqar1
 
Capital Project Risk Survey
Capital Project Risk SurveyCapital Project Risk Survey
Capital Project Risk SurveyEric Ho
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slidesDoreen Yeo
 
The Design Assist Method of Project Delivery
The Design Assist Method of Project DeliveryThe Design Assist Method of Project Delivery
The Design Assist Method of Project DeliverySHKLaw
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryMECandPMV
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Construction Contracts Common Interest Developments
Construction Contracts Common Interest DevelopmentsConstruction Contracts Common Interest Developments
Construction Contracts Common Interest DevelopmentsConstruction Cicerone
 
Construction Compliance Consultants
Construction Compliance ConsultantsConstruction Compliance Consultants
Construction Compliance Consultantsbfitzsimons1974
 
Five Key Considerations for Design Build Projects
Five Key Considerations for Design Build ProjectsFive Key Considerations for Design Build Projects
Five Key Considerations for Design Build ProjectsSuzanne Cody
 
COST EFFECIENT CHAP 2 ppt.pptx
COST EFFECIENT CHAP 2 ppt.pptxCOST EFFECIENT CHAP 2 ppt.pptx
COST EFFECIENT CHAP 2 ppt.pptxabedamtie
 
092811 Updated Contech Brochure
092811 Updated Contech Brochure092811 Updated Contech Brochure
092811 Updated Contech BrochurePaul Smith
 
Professional_practice_coa
Professional_practice_coaProfessional_practice_coa
Professional_practice_coaYogesh Bhardwaj
 
Professional_practice_I.pptx
Professional_practice_I.pptxProfessional_practice_I.pptx
Professional_practice_I.pptxYogesh Bhardwaj
 
Architecture Professional practice
Architecture Professional  practice Architecture Professional  practice
Architecture Professional practice Ar. Mukunda K.S
 
Leed green associate vi. stakeholder involvement in innovation answer
Leed green associate vi. stakeholder involvement in innovation   answer Leed green associate vi. stakeholder involvement in innovation   answer
Leed green associate vi. stakeholder involvement in innovation answer Bilal Mohamed
 

Ähnlich wie PASBA 2010 presentation (20)

CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdfCCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
 
Lec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdfLec-01 Project Planning & Management (Th.).pdf
Lec-01 Project Planning & Management (Th.).pdf
 
Capital Project Risk Survey
Capital Project Risk SurveyCapital Project Risk Survey
Capital Project Risk Survey
 
Chapter 3- Contract Management
Chapter 3- Contract ManagementChapter 3- Contract Management
Chapter 3- Contract Management
 
Standard forms lgtf
Standard forms lgtfStandard forms lgtf
Standard forms lgtf
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slides
 
The Design Assist Method of Project Delivery
The Design Assist Method of Project DeliveryThe Design Assist Method of Project Delivery
The Design Assist Method of Project Delivery
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Construction Contracts Common Interest Developments
Construction Contracts Common Interest DevelopmentsConstruction Contracts Common Interest Developments
Construction Contracts Common Interest Developments
 
Construction Compliance Consultants
Construction Compliance ConsultantsConstruction Compliance Consultants
Construction Compliance Consultants
 
Five Key Considerations for Design Build Projects
Five Key Considerations for Design Build ProjectsFive Key Considerations for Design Build Projects
Five Key Considerations for Design Build Projects
 
COST EFFECIENT CHAP 2 ppt.pptx
COST EFFECIENT CHAP 2 ppt.pptxCOST EFFECIENT CHAP 2 ppt.pptx
COST EFFECIENT CHAP 2 ppt.pptx
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
Contracting strategies for_terminal_construction
Contracting strategies for_terminal_constructionContracting strategies for_terminal_construction
Contracting strategies for_terminal_construction
 
092811 Updated Contech Brochure
092811 Updated Contech Brochure092811 Updated Contech Brochure
092811 Updated Contech Brochure
 
Professional_practice_coa
Professional_practice_coaProfessional_practice_coa
Professional_practice_coa
 
Professional_practice_I.pptx
Professional_practice_I.pptxProfessional_practice_I.pptx
Professional_practice_I.pptx
 
Architecture Professional practice
Architecture Professional  practice Architecture Professional  practice
Architecture Professional practice
 
Leed green associate vi. stakeholder involvement in innovation answer
Leed green associate vi. stakeholder involvement in innovation   answer Leed green associate vi. stakeholder involvement in innovation   answer
Leed green associate vi. stakeholder involvement in innovation answer
 

Kürzlich hochgeladen

1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingTeacherCyreneCayanan
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdfQucHHunhnh
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024Janet Corral
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3JemimahLaneBuaron
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphThiyagu K
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...fonyou31
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 

Kürzlich hochgeladen (20)

1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
fourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writingfourth grading exam for kindergarten in writing
fourth grading exam for kindergarten in writing
 
1029-Danh muc Sach Giao Khoa khoi 6.pdf
1029-Danh muc Sach Giao Khoa khoi  6.pdf1029-Danh muc Sach Giao Khoa khoi  6.pdf
1029-Danh muc Sach Giao Khoa khoi 6.pdf
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
General AI for Medical Educators April 2024
General AI for Medical Educators April 2024General AI for Medical Educators April 2024
General AI for Medical Educators April 2024
 
Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3Q4-W6-Restating Informational Text Grade 3
Q4-W6-Restating Informational Text Grade 3
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
Ecosystem Interactions Class Discussion Presentation in Blue Green Lined Styl...
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 

PASBA 2010 presentation

  • 1. A Primer of Commonly Overlooked Issues in Construction Projects Presentation for
  • 2. Introduction Presentation Goal: This session will address some commonly overlooked critical items in the planning and execution of construction projects which could improve the overall performance of the project and reduce the risk of disputes and claims. Presenters: Jake Ortego, PE, CCA, CCP, CCE President – JA Cost Engineers and Advisors, Inc. BS – Mechanical Engineering, Boston University 15+ Years in Engineering, Construction and Consulting www.ja-cea.com j@ja-cea.com David Anderson School Board Member –Kiski Area SD BS – Chemical Engineering, The Pennsylvania State University MBA – Robert Morris University 12+ Years in Engineering and Consulting A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 2 of 28
  • 3. Construction Goals Construction Projects follow the principle of the triple constraint of Quality (or Scope), Cost and Schedule. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 3 of 28 Quality/Scope CostSchedule An emphasis on any one of the constraints will have an effect on the other two.
  • 4. Who’s Who? There are many parties involved in a construction project that have different skill sets and knowledge. Below is a quick guide to the major groups beyond the Owner and Contractors. The focus of this guide is related to advocating the Owner’s Interest. Architect (and Engineer) – AKA “A/E” – They are responsible for the artistic and technical design of the building. The design quality from the A/E firms can greatly influence the total cost of the project. A/E firms typically have limited hands on field experience and limited knowledge of contract language. Solicitor (Legal Council) – This is the main advocate for the Owner’s legal interests. The Solicitors should have a detailed knowledge of local, state and federal codes, mandates and precedence regarding construction law. Although many solicitors have knowledge of the law, very few have experience in the execution of a construction project. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 4 of 28
  • 5. Who’s Who? (cont.) Construction Manager – If used on a project, the CM should protect the Owner’s interest while coordinating all of the contractors, vendors, consultants, etc. to bring the project to a successful completion. In today’s construction market, many CM’s are general contractors who are expanding their capabilities. Clerk of the Works – The intent is for the COTW to protect the interests of the Owner in regard to ensuring the quality of both materials and workmanship are in accordance with the design information such as specification and engineering drawings. Many COTW’s have construction experience, but limited design or contract training and/or experience. Owners Representative – This role could include duties ranging from a CM to a COTW to a advisory consultant. An Owner's Rep services is not a substitute for an architect, contractor, legal counsel, or Owner themselves. There is no clear standard for this role. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 5 of 28
  • 6. Ability to Influence Costs The ability to influence project goals diminishes with time. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 6 of 28
  • 7. What is the Cost of Work? Cost of Work (“COW”) is an term which can have multiple meanings and interpretations. • Typical Contracts define the COW as all costs except for the Contractors Fee. • Many insurance companies define the COW as all costs except for the insurance. • Some parties see the COW as the total cost of the contract including fees and insurances. The difference can be seem trivial, but become material when calculating Fees, Insurances and Tax (where applicable) for change orders. It is important to clearly understand and define COW on every project. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 7 of 28
  • 8. What Causes Overruns A common perception is that the primary driver to project overruns is due to the contractors. This is only part of the story Owners are a major source of change due to • Undefined Scope • Modifications made during construction Architects are also a major source of change due to • Incomplete designs • Overdesigning • Performance to the Standard of Care Depending on the state, it is accepted that the an Architects standard of care is between 3% to 5% of the construction costs. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 8 of 28
  • 9. Avoiding Disputes and Claims Disputes and claims are often the result of: • Miscommunication • Unclear Expectations • Unrealistic Expectations • Poorly defined scope • Different interpretations of the Contract Avoiding disputes and claims can often be done with: • Open Communication • Explicit Definitions • Mutual Understanding What follows are areas that are commonly overlooked by owners while planning, designing and executing a construction project. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 9 of 28
  • 10. Define the Expectations (part 1) As an Owner, you have responsibilities to the project. During the project you will need to clearly establish the expectations of your team regarding: • Clear lines of authority for providing direction and approval for project decisions • Time to review and approve design/drawings • Time limits on responding to Requests for Information (“RFI”) • Time limits on responding to Change Orders • Time limits on reviewing and approving Applications for Payment (“Pay Apps”) A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 10 of 28
  • 11. Define the Expectations (part 2) Architects and Engineers (“A/E”) are design professionals. Most have limited to no experience actually managing a construction project. Most people expect that the Architects will be involved in nearly every aspect of the project and will represent the Owner’s Interest. It is recommended that open discussion are held with the Architect to discuss each of the following: • Establishing a budget that the A/E is to design to • The level and detail that the A/E will review the Pay Applications • The level and detail that the A/E will review the Change Orders • The frequency and expectations of site visits • The basis of the fee and what will constitute a change • The schedule expectations A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 11 of 28
  • 12. Understand your Accuracy Misunderstanding an Estimate can set a project up to fail. Construction costs can vary greatly due to time, location and resource availability. As a result Construction estimates are only 100% when the project is complete and final costs are submitted. It is important to understand the accuracy of your estimates to help plan for the potential costs of a project. The following is an example of the accuracy to expect from estimates. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 12 of 28 Estimate from SQF Est 75% Dwgs 90% Dwgs* Architect ± 30% ± 25% ± 20% Independent Estimator ± 25% ± 20% ± 10% CM or GC ± 20% ± 15% ± 5% *Note: for this example, 90% are considered “Issued for Construction”
  • 13. Contingency vs. Allowance Allowances and contingencies are used to plan for items that are not clearly defined or for unknown circumstances. Allowances are for “Known Unknowns”. Example: Landscaping will be performed at the conclusion of the project, but the exact configuration and selections have not been finalized. Contingencies are for “Unknown Unknowns”. This should be reserved for items that cannot be clearly identified at the planning, design and bidding of the project. A common mistake is to use contingency for items that should be an allowance. This can exhaust the contingency before it has a chance to be used for truly unforeseen events. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 13 of 28
  • 14. Plan for Unexpected In addition to accuracy of the estimate, owners should add costs to their budgets for the following: • Quality of the drawings • Price Escalation and Inflation for projects over 1 year • Increase labor rates for projects over 1 year • Potential changes requested within the school district. Most projects should carry a 10% contingency on top of any estimate. In the rare cases where the drawings are complete and the scope is well defined, contingency should not be any lower than 5%. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 14 of 28
  • 15. Value Eng. Vs Scope Reduction Value Engineering and Scope Reduction are different! Value Engineering is the practice of altering the scope to achieve the same performance goals at a lower installation or operating cost. Example: Replacing Wood Framed Windows with Vinyl Framed windows could result in a savings in material while still achieving the desired lighting. Scope Reduction is the practice of removing items from the scope of work to lower costs. Example: Removing windows in lieu of a wall will save material and installation cost, but also not achieve the desired lighting. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 15 of 28
  • 16. Independent Estimates Having an independent estimate performed on the Construction Drawings prior to sending them out for bid can be valuable in identifying the possible ambiguity in the drawings. The independent estimate should be configured to cleanly match the A/E’s estimate. Major variances exist between the A/E Estimate and the Independent Estimate can be addressed in the following way: • Require the Architect to review the basis of bid to determine the cause of the differences. If it is an issue of interpretation, the A/E should update their drawings to alleviate any ambiguity. • Isolate the major differences and ask that bidders provide a breakout price for this area. • Remove any major difference from the bidding documents (or place them on hold) until the drawings are further developed. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 16 of 28
  • 17. Details in the Bids It is easier to ask questions and state expectations during bidding than it is after the award. The words “Lowest Responsive Bidder” does not prevent the Owner from requiring bid details. Examples include: • Requiring Bidders to acknowledge that all change orders will have no more than a 15% markup for the prime with a total mark up not to exceed 20% of the base cost of work • Requiring Bidders to acknowledge that all change orders will be submitted with complete supporting information for cost, labor, subcontractors, fees and insurances • Requesting bidders to provide add and deducts for any areas of the scope that may not be well defined. • Requesting the bidders to identify any areas of the bid documents which are unclear or unbuildable. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 17 of 28
  • 18. Define the Expectations (part 3) As with the project team and architect, it is prudent to define your expectations for the Construction Manager, General Contractor or and/or Prime Contractors including: • Change Management • Change Multipliers (or Markups) • Reporting Requirements • Scheduling Requirements • Substantial Completion • Invoicing Requirements • Incentives or Liquidated Damages • How Contingency is to be Spent Any agreements to these types of discussions should be included as part of the contract. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 18 of 28
  • 19. Modify the Contract The contract is the place where all of the agreements governing the execution of the project are captured. Consider the following: • AIA Contracts are written by Architects • ACG are written by Contractors • There are no standard contract templates that advocate the owner The standard templates are meant to be flexible. But in doing so, they often are ambiguous. Ambiguity leads to the possibility of different interpretations which can lead to claims. Ambiguity is typically construed against the drafter. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 19 of 28
  • 20. Modify the Contract (cont.) Recommended areas to focus on that are typically ambiguous include: • Mark ups for changes and for pay applications • Rates for additional work • Pay Applications being percent complete or substantiated (Cost Plus) • Basis of Allowances • Expectations and Agreements they may have been verbally discussed. • Any part of the contract that uses the word “reasonable” should be explicitly defined. All contracts can be modified, but not all modifications are legal. Discuss any modifications with your legal council before implementing. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 20 of 28
  • 21. Fast Track vs. Fast Pace The two terms are often confused and interchanged. “Fast Track” is a method of staggering the sequence of a project to achieve a shorter total design – construct duration. Construction Starts as the drawings per discipline are issued. The inherent risk is that the items typically designed last (MEP) have more stringent constraints due to the physical completion of the earlier items such as Civil and Structural. “Fast Pace” or “Accelerated” is the method of compressing components of the schedule to achieve a shorter duration for any part(s) of the project. The risks lie in over congested project sites, overtime, shift work and lowered quality. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 21 of 28
  • 22. Expect Change Change is a normal and expected part of every project! No design is perfect and changes help all parties adjust the design to meet the physical expectations of construction. A well planned project is designed to absorb a certain level of change. When evaluating and approving changes, consider each of the following: • Was it in the base scope? • Is it needed or wanted? • Are the costs supported and reasonable? • Is there any impact to the duration of the project? Always get a change in writing and never authorize a blanket change order without costs and/or limits. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 22 of 28
  • 23. No News can be Bad News One of the methods to manage the risk of overruns and delays is to proactively identify potential issues before they escalate. Here are some recommended methods to do this: • Question the contractors and their subs to identify unknowns and possible risks on a weekly basis. • Encourage the contractors and their subcontractors to submit their invoices on the regular cycle. Work the Construction Manager and Prime Contractors to forecast the project’s workload and cash flow. • Encourage Requests for Information (“RFI”) to be submitted for all design and specification questions. • Keep the contractors informed about any owner related items that will affect their schedule or activities. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 23 of 28
  • 24. Errors and Omissions The is one of the most commonly misunderstood aspects of increased costs to a project. It is expected that A/E firms have up to a 3% error and omission rate. In some states, this value may be as high as 5%. Errors are items that are incorrectly designed and require rework to correct if construction on this item has started. Example: A set of stairs ends 2 ft under the landing. To correct, the stairs may have to be re-fabricated. The price of fixing an error is made up of costs directly related to fixing this issue. This could involve other ancillary work that may be affected by the corrections A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 24 of 28
  • 25. Errors and Omissions (cont.) Omissions are items that have been either unintentionally omitted from the design. They may require rework to incorporate the omission. Example: A set of stairs does not have any hand railing in the design. To correct, the handrail will have to be fabricated and installed. The Owner must still pay for the base item regardless if it was not in the base design and estimates. The cost of the omission is considered to be any additional costs required to include the omitted scope that is greater than what would have been paid if the scope was included in the design. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 25 of 28
  • 26. Errors and Omissions (cont.) From a contractors perspective, the Owner is required to pay for the entire amount to fix an error or omission. As long as the item is not included in the scope of work to the contractor, then this assumption is correct. The owner may attempt to pass the cost on to their A/E Firms. Most A/E firms have insurance for errors and omissions. The insurance is only intended to cover the added costs for correction. It is rare for claims to be awarded if the total cost of errors and omissions is under 3% of the construction costs. A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 26 of 28
  • 27. Conclusion It is reasonable to discuss any and all items in this report with your Architect, Solicitor and Construction Firms. In general, you can increase you chances of a successful project by: • Good Planning • Defining Expectations • Clarify Assumptions • Communicating with the Team Another equally good way of executing project is to: • Be Definite • Be Clear • Be Fair • Be Careful A Primer of Commonly Overlooked Issues in Construction Projects School Design and Construction Conference Slide 27 of 28