SlideShare ist ein Scribd-Unternehmen logo
1 von 24
How to Perform Project
Risk Management for Oil
and Gas Projects
Intaver Institute Inc.
303, 6707, Elbow Drive S.W, Calgary, AB, Canada
Tel: +1(403)692-2252
Fax: +1(403)459-4533
www.intaver.com
Introduction
• Intaver Institute Timeline
– 2002: Established
– 2004: V.1 RiskyProject
– 2009: v 3 Integrated Risk Register
– 2012: v 5
• RiskyProject
– Full Project Risk Management
Lifecycle
– Integrated Risk Register
– Risk Matrix, Risk Planning
+
– Quantitative Monte Carlo Cost and
Schedule Risk Analysis
05/07/14 2013 Intaver Institute 2
Clients
Gorgon Natural Gas Project
05/07/14 2013 Intaver Institute 3
Project Cost Estimate in Billions A$
Date of cost estimate
A three-train liquefied natural gas (LNG) facility on Barrow Island
(Australia) that will produce 15.6 million metric tons of LNG per year.
Corporate Portfolio Management Process
05/07/14 2013 Intaver Institute 4
Project Cost and
Schedule risks and
uncertainties
Geological and other
Uncertainties affecting
production
Price Uncertainties
Other Risks and
Uncertainties:
-Political risks
-Uncertainties in
Royalties regimes
-….
Economic
Analysis of the
Projects
Corporate
Portfolio
Management
Strategic
Decision
Quantitative cost and schedule risk analysis is an
important component of portfolio management
Risk Management Affects Project Profitability
05/07/14 2013 Intaver Institute 5
Full circle cost of gas
$/Mcf
Quantitative risk analysis provides realistic risk adjusted and risk mitigated cost estimates
Identifying and Managing Critical Risks is Key
05/07/14 2013 Intaver Institute 6
Risk
Quantitative risk analysis identifies and prioritizes critical risks
Which risks are critical?
05/07/14 2013 Intaver Institute 7
Risk 3Risk 3
Risk 4Risk 4
Risk 1Risk 1
Risk 5Risk 5
Risk 2Risk 2
Risk 1Risk 1
Risk 2Risk 2
Risk 3Risk 3
Risk 4Risk 4
Risk 5Risk 5
Schedule
risk
CostRisk
SafetyRisk
LegalRisk
Quality
Risk
……………..
Risk
Enviromen
talRisk
Tim
e
DependentCosts
CostRisk
Time is Money: Cost and Schedule Risks
05/07/14 2013 Intaver Institute 8
• Schedule risk drives
Costs due to time
dependent resource
costs
• 40% -70% cost risk is
schedule driven
Schedule
risk
Input 1: Project Schedule
Input 2: List of Risks (Risk Register)
Assign Risks to Project
Tasks and Resources
Perform
Analysis
Risk Events Approach
Schedule
05/07/14 2013 Intaver Institute 10
Import project schedule from project management tool
(Primavera, MS Project, etc..
Costs
05/07/14 2013 Intaver Institute 11
Schedules can include cost data for quantitative risk analysis of fixed costs
Resources
05/07/14 2013 Intaver Institute 12
Resources with rates are loaded with the project schedule to allow for risk
analysis of time dependent costs
Risk Register
05/07/14 2013 Intaver Institute 13
Project risk register is integrated to the project schedule and
cost
Risk Assignment
05/07/14 2013 Intaver Institute 14
Task R1 R2 R3 R4 R5 R6
Installing Microsoft Seismic
monitoring
x x
Deliver frac fleet and install
equipment
x
Deliver rig and equipment x
Well 1,2,3 (share common risks) x
Rig Mobilization x
Drilling x x x x
Installing Service Rig x
Completion (8 stages fracing) x x
Risks are assigned to project activities
Risk Assignment Interface
05/07/14 2013 Intaver Institute 15
30 % chance that risk
causes a delay and
increase in cost of drilling
Risk Assigned to task
‘Drilling’
Risk probability and cost and schedule impact are assigned to
activities
Run Monte Carlo Simulation
05/07/14 2013 Intaver Institute 16
Monte Carlo simulation prioritizes risk based on impact on cost, schedule or
other parameters
Results of Analysis
05/07/14 2013 Intaver Institute 17
Monte Carlo simulation results for cost and schedule can be viewed as
histograms or cumulative probability
Risk Adjusted Project Schedule
05/07/14 2013 Intaver Institute 18
Schedule with
risks
Schedule without
risks
Arrows show risk
assignments
Project Cost
05/07/14 2013 Intaver Institute 19
Schedule with
risks
Schedule without
risks
Results of quantitative cost risk analysis are shown on the Cost view
Risk Planning – Mitigation Plan
05/07/14 2013 Intaver Institute 20
Risk response plans can be plotted on a Risk Mitigation Waterfall chart
Pre and Post Mitigation Risk Scores
05/07/14 2013 Intaver Institute 21
Pre-
mitigation
Post-
mitigation
Risk Planning
Risk: Mechanical Problem with instrument
05/07/14 2013 Intaver Institute 22
Post Mitigation $16, 734, 906Pre-Mitigation Cost 17, 178, 397
Risk response plans can reduce the expected cost of the project
RiskyProject Enterprise
05/07/14 2013 Intaver Institute 23
Enterprise Risk
Database:
Schedules,
Risks,
Mitigation Plans
RiskyProject Professional
RiskyProject Lite
RiskyProject Web
Future Reading
• Virine, L. and M. Trumper. 2007 Project Decisions: The Art and Science. VA: Management
Concepts
• Virine, L. and M. Trumper. 2013. Project Think: Why Good Managers Make Poor Project
Choices. England: Gower Publishing
• P. Leach. 2005. Late and Over Budget: Why Projects Always Seem to Take Longer and
Cost More Than Planned. Projects & Profits, Vol. V Issue - XI, November 2005
• http://www.project decisions.org
• http://www.intaver.com/index-whitepapers.html
• http://www.risk-doctor.com/
• http://www.projectrisk.com
Contact
Michael Trumper
mtrumper@intaver.com
403.692.2252
Intaver Institute Inc.
www.intaver.com
05/07/14 2013 Intaver Institute 24

Weitere ähnliche Inhalte

Was ist angesagt?

Session W1 - Reliable Risk Quantification For Project Cost and Schedule
Session W1 - Reliable Risk Quantification For Project Cost and ScheduleSession W1 - Reliable Risk Quantification For Project Cost and Schedule
Session W1 - Reliable Risk Quantification For Project Cost and ScheduleProject Controls Expo
 
Introduction to primavera risk analysis ppt
Introduction to primavera risk analysis pptIntroduction to primavera risk analysis ppt
Introduction to primavera risk analysis pptp6academy
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14p6academy
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisp6academy
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaPankaj K Sinha
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...p6academy
 
Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Anakinzs
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementMike Tulkoff
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14p6academy
 
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...p6academy
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisjisothomas
 
Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...
Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...
Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...Project Controls Expo
 
Thesis Presentation_LocNguyen
Thesis Presentation_LocNguyenThesis Presentation_LocNguyen
Thesis Presentation_LocNguyenLoc Nguyen
 
Project Controls Expo - 31st Oct 2012 - Improving Professionalism in Project ...
Project Controls Expo - 31st Oct 2012 - Improving Professionalism in Project ...Project Controls Expo - 31st Oct 2012 - Improving Professionalism in Project ...
Project Controls Expo - 31st Oct 2012 - Improving Professionalism in Project ...Project Controls Expo
 
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Terry Johns: Uncertainty - understanding the impact and the importance of rec...Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Terry Johns: Uncertainty - understanding the impact and the importance of rec...Association for Project Management
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisBECM, RUET, Bangladesh
 
Blog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk AnalysisBlog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk AnalysisAsaman Patnaik
 

Was ist angesagt? (20)

Session W1 - Reliable Risk Quantification For Project Cost and Schedule
Session W1 - Reliable Risk Quantification For Project Cost and ScheduleSession W1 - Reliable Risk Quantification For Project Cost and Schedule
Session W1 - Reliable Risk Quantification For Project Cost and Schedule
 
Introduction to primavera risk analysis ppt
Introduction to primavera risk analysis pptIntroduction to primavera risk analysis ppt
Introduction to primavera risk analysis ppt
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysis
 
Project Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K SinhaProject Risk Management-Pankaj K Sinha
Project Risk Management-Pankaj K Sinha
 
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
Mitigating cost and schedule risk with oracle primavera risk analysis - Oracl...
 
Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)Cis 500 assignment 6 vo ip part 4 (risk register)
Cis 500 assignment 6 vo ip part 4 (risk register)
 
Session B2 - Project Cost Control
Session B2 - Project Cost ControlSession B2 - Project Cost Control
Session B2 - Project Cost Control
 
Using Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project ManagementUsing Risk Analysis and Simulation in Project Management
Using Risk Analysis and Simulation in Project Management
 
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14An introduction to primavera risk analysis  - Oracle Primavera P6 Collaborate 14
An introduction to primavera risk analysis - Oracle Primavera P6 Collaborate 14
 
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...Schedule analysis what could possibly go wrong  - Oracle Primavera Collaborat...
Schedule analysis what could possibly go wrong - Oracle Primavera Collaborat...
 
Pert master risk analysis tool
Pert master   risk analysis toolPert master   risk analysis tool
Pert master risk analysis tool
 
Concepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysisConcepts and best practices for the risk register in primavera risk analysis
Concepts and best practices for the risk register in primavera risk analysis
 
Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...
Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...
Project Controls Expo - 31st Oct 2012 - Data Integration Throughout the Proje...
 
Thesis Presentation_LocNguyen
Thesis Presentation_LocNguyenThesis Presentation_LocNguyen
Thesis Presentation_LocNguyen
 
Project Controls Expo - 31st Oct 2012 - Improving Professionalism in Project ...
Project Controls Expo - 31st Oct 2012 - Improving Professionalism in Project ...Project Controls Expo - 31st Oct 2012 - Improving Professionalism in Project ...
Project Controls Expo - 31st Oct 2012 - Improving Professionalism in Project ...
 
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Terry Johns: Uncertainty - understanding the impact and the importance of rec...Terry Johns: Uncertainty - understanding the impact and the importance of rec...
Terry Johns: Uncertainty - understanding the impact and the importance of rec...
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Blog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk AnalysisBlog Cost and Schedule Risk Analysis
Blog Cost and Schedule Risk Analysis
 
project risk analysis
project risk analysisproject risk analysis
project risk analysis
 

Andere mochten auch

Challenges in the oil and gas sector overview and outlook
Challenges in the oil and gas sector  overview and outlookChallenges in the oil and gas sector  overview and outlook
Challenges in the oil and gas sector overview and outlookdammygee
 
Decision making in the oil and gas industry
Decision making in the oil and gas industryDecision making in the oil and gas industry
Decision making in the oil and gas industryPalantir_Solutions
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisIntaver Insititute
 
Connected Project Management in the Oil, Gas & Chemicals Industry
Connected Project Management in the Oil, Gas & Chemicals Industry Connected Project Management in the Oil, Gas & Chemicals Industry
Connected Project Management in the Oil, Gas & Chemicals Industry Ashwin Menon
 
Why risk management services are vital to the oil and gas industry
Why risk management services are vital to the oil and gas industryWhy risk management services are vital to the oil and gas industry
Why risk management services are vital to the oil and gas industryLloyd's Register Energy
 
Case study solving technique
Case study solving techniqueCase study solving technique
Case study solving techniqueTriptisahu
 
Risk modelling in the Exploration and Production Industry
Risk modelling in the Exploration and Production IndustryRisk modelling in the Exploration and Production Industry
Risk modelling in the Exploration and Production IndustryPalantir_Solutions
 
Subsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the futureSubsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the futureStatoil
 
Value engineering Short Over view ppt
Value engineering Short Over view pptValue engineering Short Over view ppt
Value engineering Short Over view pptMashfiq Albartross
 
Cost Estimating for Offshore Oil & Gas Facility Decommissioning
Cost Estimating for Offshore Oil & Gas Facility DecommissioningCost Estimating for Offshore Oil & Gas Facility Decommissioning
Cost Estimating for Offshore Oil & Gas Facility DecommissioningDonnie Miller
 
Petroleum economics and risk analysis
Petroleum economics and risk analysisPetroleum economics and risk analysis
Petroleum economics and risk analysisMohammad Alfian
 
10 Well Abandonment Presentation Jan 29
10 Well Abandonment Presentation Jan 2910 Well Abandonment Presentation Jan 29
10 Well Abandonment Presentation Jan 29Will Butler, P.Eng
 
Value analysis and value engineering
Value analysis and value engineeringValue analysis and value engineering
Value analysis and value engineeringAyush dixit
 
Case study analysis format
Case study analysis formatCase study analysis format
Case study analysis formatRon Simeral
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Jeremy Jay Lim
 
Case study solving technique
Case study solving techniqueCase study solving technique
Case study solving techniqueTriptisahu
 

Andere mochten auch (18)

Challenges in the oil and gas sector overview and outlook
Challenges in the oil and gas sector  overview and outlookChallenges in the oil and gas sector  overview and outlook
Challenges in the oil and gas sector overview and outlook
 
Decision making in the oil and gas industry
Decision making in the oil and gas industryDecision making in the oil and gas industry
Decision making in the oil and gas industry
 
Introduction to project economics in oil and gas upstream industry
Introduction to project economics in oil and gas upstream industryIntroduction to project economics in oil and gas upstream industry
Introduction to project economics in oil and gas upstream industry
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk Analysis
 
Connected Project Management in the Oil, Gas & Chemicals Industry
Connected Project Management in the Oil, Gas & Chemicals Industry Connected Project Management in the Oil, Gas & Chemicals Industry
Connected Project Management in the Oil, Gas & Chemicals Industry
 
Collaborative Value Engineering
Collaborative Value EngineeringCollaborative Value Engineering
Collaborative Value Engineering
 
Why risk management services are vital to the oil and gas industry
Why risk management services are vital to the oil and gas industryWhy risk management services are vital to the oil and gas industry
Why risk management services are vital to the oil and gas industry
 
Case study solving technique
Case study solving techniqueCase study solving technique
Case study solving technique
 
Risk modelling in the Exploration and Production Industry
Risk modelling in the Exploration and Production IndustryRisk modelling in the Exploration and Production Industry
Risk modelling in the Exploration and Production Industry
 
Subsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the futureSubsea well intervention: Learning from the past - planning for the future
Subsea well intervention: Learning from the past - planning for the future
 
Value engineering Short Over view ppt
Value engineering Short Over view pptValue engineering Short Over view ppt
Value engineering Short Over view ppt
 
Cost Estimating for Offshore Oil & Gas Facility Decommissioning
Cost Estimating for Offshore Oil & Gas Facility DecommissioningCost Estimating for Offshore Oil & Gas Facility Decommissioning
Cost Estimating for Offshore Oil & Gas Facility Decommissioning
 
Petroleum economics and risk analysis
Petroleum economics and risk analysisPetroleum economics and risk analysis
Petroleum economics and risk analysis
 
10 Well Abandonment Presentation Jan 29
10 Well Abandonment Presentation Jan 2910 Well Abandonment Presentation Jan 29
10 Well Abandonment Presentation Jan 29
 
Value analysis and value engineering
Value analysis and value engineeringValue analysis and value engineering
Value analysis and value engineering
 
Case study analysis format
Case study analysis formatCase study analysis format
Case study analysis format
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
Case study solving technique
Case study solving techniqueCase study solving technique
Case study solving technique
 

Ähnlich wie RiskyProject for Oil and Gas Industry

Risky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagementRisky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagementIntaver Insititute
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
Enterprise Risk Management and Analysis with RiskyProject
Enterprise Risk Management and Analysis with RiskyProjectEnterprise Risk Management and Analysis with RiskyProject
Enterprise Risk Management and Analysis with RiskyProjectIntaver Insititute
 
IRJET - Risk Allocation in Public Private Partnership Projects in Kerala
IRJET - Risk Allocation in Public Private Partnership Projects in KeralaIRJET - Risk Allocation in Public Private Partnership Projects in Kerala
IRJET - Risk Allocation in Public Private Partnership Projects in KeralaIRJET Journal
 
Risky projectcloudpresentation
Risky projectcloudpresentationRisky projectcloudpresentation
Risky projectcloudpresentationIntaver Insititute
 
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...OECD Governance
 
03-2004PDS_Technology_Isom
03-2004PDS_Technology_Isom03-2004PDS_Technology_Isom
03-2004PDS_Technology_IsomJohn Isom
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction IndustryIntaver Insititute
 
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET Journal
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...IRJET Journal
 
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET Journal
 
Perform quantitative risk analysis
Perform quantitative risk analysis Perform quantitative risk analysis
Perform quantitative risk analysis Shereef Sabri
 

Ähnlich wie RiskyProject for Oil and Gas Industry (20)

Oil and Gas Risk Analysis
Oil and Gas Risk AnalysisOil and Gas Risk Analysis
Oil and Gas Risk Analysis
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
 
Risky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagementRisky projectenterpriseriskmanagement
Risky projectenterpriseriskmanagement
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Enterprise Risk Management and Analysis with RiskyProject
Enterprise Risk Management and Analysis with RiskyProjectEnterprise Risk Management and Analysis with RiskyProject
Enterprise Risk Management and Analysis with RiskyProject
 
Risky project Enterprise
Risky project EnterpriseRisky project Enterprise
Risky project Enterprise
 
Updated CV
Updated CVUpdated CV
Updated CV
 
IRJET - Risk Allocation in Public Private Partnership Projects in Kerala
IRJET - Risk Allocation in Public Private Partnership Projects in KeralaIRJET - Risk Allocation in Public Private Partnership Projects in Kerala
IRJET - Risk Allocation in Public Private Partnership Projects in Kerala
 
Risky projectcloudpresentation
Risky projectcloudpresentationRisky projectcloudpresentation
Risky projectcloudpresentation
 
MANAGING RISKS IN IT PROJECTS ... get the complete set and others at www.gafm...
MANAGING RISKS IN IT PROJECTS ... get the complete set and others at www.gafm...MANAGING RISKS IN IT PROJECTS ... get the complete set and others at www.gafm...
MANAGING RISKS IN IT PROJECTS ... get the complete set and others at www.gafm...
 
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...Using AI led assurance to deliver projects on time and on budget - D. Amratia...
Using AI led assurance to deliver projects on time and on budget - D. Amratia...
 
03-2004PDS_Technology_Isom
03-2004PDS_Technology_Isom03-2004PDS_Technology_Isom
03-2004PDS_Technology_Isom
 
Project risk analysis in Construction Industry
Project risk analysis in Construction IndustryProject risk analysis in Construction Industry
Project risk analysis in Construction Industry
 
Enhancing performance using a programme dashboard
Enhancing performance using a programme dashboard Enhancing performance using a programme dashboard
Enhancing performance using a programme dashboard
 
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk AnalysisIRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
IRJET- Risk Management of Construction Projects by using Primavera Risk Analysis
 
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
CONSTRUCTION PROJECT MANAGEMANT BY USING M. S PROJECT FOR ATULA ELEGANCE AT V...
 
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
IRJET- Developing a Model of Risk Allocation and Risk Handling for Effective ...
 
RiskyProject Enterprise
RiskyProject EnterpriseRiskyProject Enterprise
RiskyProject Enterprise
 
Perform quantitative risk analysis
Perform quantitative risk analysis Perform quantitative risk analysis
Perform quantitative risk analysis
 

Mehr von Intaver Insititute

RiskyProject Software Version 7.2
RiskyProject  Software Version 7.2RiskyProject  Software Version 7.2
RiskyProject Software Version 7.2Intaver Insititute
 
How Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectHow Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectIntaver Insititute
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear ProjectsIntaver Insititute
 
Project Cost Risk Analysis - Reporting
Project Cost Risk Analysis - ReportingProject Cost Risk Analysis - Reporting
Project Cost Risk Analysis - ReportingIntaver Insititute
 
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Intaver Insititute
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear ProjectsIntaver Insititute
 
Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.Intaver Insititute
 
Risk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project PortfoliosRisk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project PortfoliosIntaver Insititute
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesIntaver Insititute
 
Risk Event Modeling and Event Chains
Risk Event Modeling and Event ChainsRisk Event Modeling and Event Chains
Risk Event Modeling and Event ChainsIntaver Insititute
 
Quantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryQuantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryIntaver Insititute
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisIntaver Insititute
 
Estimates in Project Management
Estimates in Project ManagementEstimates in Project Management
Estimates in Project ManagementIntaver Insititute
 
Project Management: Adaptive management
Project Management: Adaptive managementProject Management: Adaptive management
Project Management: Adaptive managementIntaver Insititute
 
Decision framing in Project Management
Decision framing in Project ManagementDecision framing in Project Management
Decision framing in Project ManagementIntaver Insititute
 
Risky project Cloud presentation rus
Risky project Cloud presentation rusRisky project Cloud presentation rus
Risky project Cloud presentation rusIntaver Insititute
 

Mehr von Intaver Insititute (20)

RiskyProject Software Version 7.2
RiskyProject  Software Version 7.2RiskyProject  Software Version 7.2
RiskyProject Software Version 7.2
 
How Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your projectHow Risk Events and Uncertainties can affect your project
How Risk Events and Uncertainties can affect your project
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Project Cost Risk Analysis - Reporting
Project Cost Risk Analysis - ReportingProject Cost Risk Analysis - Reporting
Project Cost Risk Analysis - Reporting
 
Project Cost Analysis
Project Cost AnalysisProject Cost Analysis
Project Cost Analysis
 
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1Project Risk Analysis and Risk Management Software RiskyProject version 7.1
Project Risk Analysis and Risk Management Software RiskyProject version 7.1
 
Risk Analysis of Linear Projects
Risk Analysis of Linear ProjectsRisk Analysis of Linear Projects
Risk Analysis of Linear Projects
 
Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.Smart Monte Carlo: Tricks for schedule risk analysis.
Smart Monte Carlo: Tricks for schedule risk analysis.
 
Risk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project PortfoliosRisk Resilient Projects and Project Portfolios
Risk Resilient Projects and Project Portfolios
 
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project SchedulesProject Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
Project Risk Analysis: Creating and Managing Risk Adjusted Project Schedules
 
RiskyProject 7
RiskyProject 7RiskyProject 7
RiskyProject 7
 
RiskyProject Software
RiskyProject SoftwareRiskyProject Software
RiskyProject Software
 
Risk Event Modeling and Event Chains
Risk Event Modeling and Event ChainsRisk Event Modeling and Event Chains
Risk Event Modeling and Event Chains
 
Quantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace IndustryQuantiative Risk Analysis for the Aerospace Industry
Quantiative Risk Analysis for the Aerospace Industry
 
Monte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk AnalysisMonte Carlo and Schedule Risk Analysis
Monte Carlo and Schedule Risk Analysis
 
Estimates in Project Management
Estimates in Project ManagementEstimates in Project Management
Estimates in Project Management
 
Project Management: Adaptive management
Project Management: Adaptive managementProject Management: Adaptive management
Project Management: Adaptive management
 
Decision framing in Project Management
Decision framing in Project ManagementDecision framing in Project Management
Decision framing in Project Management
 
Risky projectpresentation rus
Risky projectpresentation rusRisky projectpresentation rus
Risky projectpresentation rus
 
Risky project Cloud presentation rus
Risky project Cloud presentation rusRisky project Cloud presentation rus
Risky project Cloud presentation rus
 

Kürzlich hochgeladen

Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyKhushali Kathiriya
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodJuan lago vázquez
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingEdi Saputra
 
Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfOverkill Security
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...DianaGray10
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024The Digital Insurer
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamUiPathCommunity
 
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKSpring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKJago de Vreede
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Victor Rentea
 
Cyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdfCyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdfOverkill Security
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Zilliz
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businesspanagenda
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FMESafe Software
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Jeffrey Haguewood
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 

Kürzlich hochgeladen (20)

Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin WoodPolkadot JAM Slides - Token2049 - By Dr. Gavin Wood
Polkadot JAM Slides - Token2049 - By Dr. Gavin Wood
 
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost SavingRepurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
Repurposing LNG terminals for Hydrogen Ammonia: Feasibility and Cost Saving
 
Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdf
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024FWD Group - Insurer Innovation Award 2024
FWD Group - Insurer Innovation Award 2024
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 AmsterdamDEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
DEV meet-up UiPath Document Understanding May 7 2024 Amsterdam
 
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKSpring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024Finding Java's Hidden Performance Traps @ DevoxxUK 2024
Finding Java's Hidden Performance Traps @ DevoxxUK 2024
 
Cyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdfCyberprint. Dark Pink Apt Group [EN].pdf
Cyberprint. Dark Pink Apt Group [EN].pdf
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
 
Why Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire businessWhy Teams call analytics are critical to your entire business
Why Teams call analytics are critical to your entire business
 
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers:  A Deep Dive into Serverless Spatial Data and FMECloud Frontiers:  A Deep Dive into Serverless Spatial Data and FME
Cloud Frontiers: A Deep Dive into Serverless Spatial Data and FME
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 

RiskyProject for Oil and Gas Industry

  • 1. How to Perform Project Risk Management for Oil and Gas Projects Intaver Institute Inc. 303, 6707, Elbow Drive S.W, Calgary, AB, Canada Tel: +1(403)692-2252 Fax: +1(403)459-4533 www.intaver.com
  • 2. Introduction • Intaver Institute Timeline – 2002: Established – 2004: V.1 RiskyProject – 2009: v 3 Integrated Risk Register – 2012: v 5 • RiskyProject – Full Project Risk Management Lifecycle – Integrated Risk Register – Risk Matrix, Risk Planning + – Quantitative Monte Carlo Cost and Schedule Risk Analysis 05/07/14 2013 Intaver Institute 2 Clients
  • 3. Gorgon Natural Gas Project 05/07/14 2013 Intaver Institute 3 Project Cost Estimate in Billions A$ Date of cost estimate A three-train liquefied natural gas (LNG) facility on Barrow Island (Australia) that will produce 15.6 million metric tons of LNG per year.
  • 4. Corporate Portfolio Management Process 05/07/14 2013 Intaver Institute 4 Project Cost and Schedule risks and uncertainties Geological and other Uncertainties affecting production Price Uncertainties Other Risks and Uncertainties: -Political risks -Uncertainties in Royalties regimes -…. Economic Analysis of the Projects Corporate Portfolio Management Strategic Decision Quantitative cost and schedule risk analysis is an important component of portfolio management
  • 5. Risk Management Affects Project Profitability 05/07/14 2013 Intaver Institute 5 Full circle cost of gas $/Mcf Quantitative risk analysis provides realistic risk adjusted and risk mitigated cost estimates
  • 6. Identifying and Managing Critical Risks is Key 05/07/14 2013 Intaver Institute 6 Risk Quantitative risk analysis identifies and prioritizes critical risks
  • 7. Which risks are critical? 05/07/14 2013 Intaver Institute 7 Risk 3Risk 3 Risk 4Risk 4 Risk 1Risk 1 Risk 5Risk 5 Risk 2Risk 2 Risk 1Risk 1 Risk 2Risk 2 Risk 3Risk 3 Risk 4Risk 4 Risk 5Risk 5 Schedule risk CostRisk SafetyRisk LegalRisk Quality Risk …………….. Risk Enviromen talRisk
  • 8. Tim e DependentCosts CostRisk Time is Money: Cost and Schedule Risks 05/07/14 2013 Intaver Institute 8 • Schedule risk drives Costs due to time dependent resource costs • 40% -70% cost risk is schedule driven Schedule risk
  • 9. Input 1: Project Schedule Input 2: List of Risks (Risk Register) Assign Risks to Project Tasks and Resources Perform Analysis Risk Events Approach
  • 10. Schedule 05/07/14 2013 Intaver Institute 10 Import project schedule from project management tool (Primavera, MS Project, etc..
  • 11. Costs 05/07/14 2013 Intaver Institute 11 Schedules can include cost data for quantitative risk analysis of fixed costs
  • 12. Resources 05/07/14 2013 Intaver Institute 12 Resources with rates are loaded with the project schedule to allow for risk analysis of time dependent costs
  • 13. Risk Register 05/07/14 2013 Intaver Institute 13 Project risk register is integrated to the project schedule and cost
  • 14. Risk Assignment 05/07/14 2013 Intaver Institute 14 Task R1 R2 R3 R4 R5 R6 Installing Microsoft Seismic monitoring x x Deliver frac fleet and install equipment x Deliver rig and equipment x Well 1,2,3 (share common risks) x Rig Mobilization x Drilling x x x x Installing Service Rig x Completion (8 stages fracing) x x Risks are assigned to project activities
  • 15. Risk Assignment Interface 05/07/14 2013 Intaver Institute 15 30 % chance that risk causes a delay and increase in cost of drilling Risk Assigned to task ‘Drilling’ Risk probability and cost and schedule impact are assigned to activities
  • 16. Run Monte Carlo Simulation 05/07/14 2013 Intaver Institute 16 Monte Carlo simulation prioritizes risk based on impact on cost, schedule or other parameters
  • 17. Results of Analysis 05/07/14 2013 Intaver Institute 17 Monte Carlo simulation results for cost and schedule can be viewed as histograms or cumulative probability
  • 18. Risk Adjusted Project Schedule 05/07/14 2013 Intaver Institute 18 Schedule with risks Schedule without risks Arrows show risk assignments
  • 19. Project Cost 05/07/14 2013 Intaver Institute 19 Schedule with risks Schedule without risks Results of quantitative cost risk analysis are shown on the Cost view
  • 20. Risk Planning – Mitigation Plan 05/07/14 2013 Intaver Institute 20 Risk response plans can be plotted on a Risk Mitigation Waterfall chart
  • 21. Pre and Post Mitigation Risk Scores 05/07/14 2013 Intaver Institute 21 Pre- mitigation Post- mitigation
  • 22. Risk Planning Risk: Mechanical Problem with instrument 05/07/14 2013 Intaver Institute 22 Post Mitigation $16, 734, 906Pre-Mitigation Cost 17, 178, 397 Risk response plans can reduce the expected cost of the project
  • 23. RiskyProject Enterprise 05/07/14 2013 Intaver Institute 23 Enterprise Risk Database: Schedules, Risks, Mitigation Plans RiskyProject Professional RiskyProject Lite RiskyProject Web
  • 24. Future Reading • Virine, L. and M. Trumper. 2007 Project Decisions: The Art and Science. VA: Management Concepts • Virine, L. and M. Trumper. 2013. Project Think: Why Good Managers Make Poor Project Choices. England: Gower Publishing • P. Leach. 2005. Late and Over Budget: Why Projects Always Seem to Take Longer and Cost More Than Planned. Projects & Profits, Vol. V Issue - XI, November 2005 • http://www.project decisions.org • http://www.intaver.com/index-whitepapers.html • http://www.risk-doctor.com/ • http://www.projectrisk.com Contact Michael Trumper mtrumper@intaver.com 403.692.2252 Intaver Institute Inc. www.intaver.com 05/07/14 2013 Intaver Institute 24

Hinweis der Redaktion

  1. To model schedule driven cost, we have included high level resources that have been assigned to specific tasks.