Risk Event Modeling and Event Chains
1. Risk Event Modeling
Intaver Institute Inc.
303, 6707, Elbow Drive S.W,
Calgary, AB, Canada
Tel: +1 (403) 692-2252
Fax: +1 (403) 459-4533
www.intaver.com
4280 East Tamiami Trail, 302-M,
Naples Florida, 34112, USA
Tel: +1(510) 984 3527
2. The Project Management Problem
2009 Intaver Institute
Many projects are unsuccessful!
• Budget
• Schedule
• Quality
• Other measures
Projects
consistently
fail to meet:
3. 2009 Intaver Institute 3
Key Project Management Issues
• How to estimate project duration or cost?
• What are the most critical risks and how to handle
them?
• How to measure project performance?
• How to make an informed decision about the
future course of the project?
The Project Management Problem
4. 1/31/2018 2009 Intaver Institute 4
Reasons
• Human psychological limits
• Inadequate training
• Poor processes
• other
The Project Management Problem
5. 2009 Intaver Institute
Risk management key to project success
• Risks are events that can occur during a project
that changes to course of a project
• Risk is key source of project uncertainty and major
root cause of project failure
• Limited ability to forecast and manage project
uncertainty due to risk
The Project Management Problem
6. 2009 Intaver Institute
Chains of unfortunate events
• Risks can form event chains
• A risk occurs and causes another risk to occur,
which causes yet another
• Unexpected result of a series of events derail
projects
• Statistical sampling or Monte Carlo simulations
the best solution for modeling the effect of
related and unrelated project risks
The Project Management Problem
7. Benefits
2009 Intaver Institute
Understand impact of risk on projects
• Understand project risk and uncertainty in Cost
and Duration
• Identify critical risks and activities
• Model risk handling efforts
• Improved contingency and buffer plans
• Monitoring with risks and uncertainties provides
strong, early signals of impending issues
8. Uses common PM artifacts
• WBS
• Resources
• Costs
• Risk Register or Risk Lists developed for
qualitative risk management
Risk Event Modeling Workflow
2009 Intaver Institute
9. Risk Definition
• Risks
– Risks are “events” that have a probability of occurring
during a project
– Risks are identified and assigned to tasks or resources
– Define impact of risks by assigning:
• Chance of occurrence
• Outcome (e.g. delay, increase in cost)
• Result (percentage or fixed value of outcome)
2009 Intaver Institute
10. What is Monte Carlo
Monte Carlo simulation is a mathematical method used in
risk analysis. Monte Carlo simulations are used to
approximate the distribution of potential results based on
probabilistic inputs.
11. Monte Carlo Simulations
Input Parameters Output Parameters
Calculation
Engine
Critical Path
Scheduling
Engine
(
)
Task duration
cost, finish time,
etc.
cost, finish time,
etc.
Project duration
13. Two Approaches to Estimating Probabilities
• The relative frequency approach, where probability equals
the number of occurrences of specific outcome (or event)
divided by the total number of possible outcomes.
• The subjective approach represents an expert’s degree of
belief that a particular outcome will occur.
14. Two Approaches for Defining Uncertainties
• Distribution-based approach
• Event-based approach
17. Before Eliciting Judgment You Need to Have:
• A clearly defined problem
• An identified list of risks, or a risk breakdown
structure, for the project
• A project schedule
• A clearly defined set of questions you will ask
experts
In addition, your team of experts should be aware of
any personal interest that expert may have regarding
particular issues. It helps to mitigate motivational
biases.
18. Psychological Factors
• Availability heuristic: people judge the probability of
the occurrence of events by how easily these events
are brought to mind.
• Anchoring heuristic: refers to the human tendency
to remain close to the initial estimate.
• Wishful thinking: when we overestimate the
probabilities of opportunities and underestimate the
probabilities of risks.
19. Overestimating the Probability of Compound Events
If the probability of a defect in a component is 20% and the
device uses three redundant components, the probability of
the defective device will be (0.2 * 0.2 * 0.2) = 0.008%.
People tend to think this number is much higher.
20. Ignoring Base-Rate Frequencies
• Historically, the probability that a particular component will
be defective is 1%.
• The component is tested before installation.
• The test showed that the component is defective.
• The test usually successfully identifies defective
components 80% of the time.
• What is the probability that a component is defective?
The correct answer is close to 4%, however, most people
would think that answer is a little bit lower than 80%.
21. Eliciting Probabilities of Events
• Pose a direct question: “What is the probability that the
project will be canceled due to budgetary problems?”
• Ask the experts two opposing questions: (1) “What is the
probability that the project will be canceled?” and (2) “What
is the probability the project will be completed?” The sum of
these two assessments should be 100%.
• Break compound events into simple events and review them
separately.
22. Probability Wheel
25% No delay of activity
35% 3 day delay of activity
40% 5 day delay of activity
24. Eliciting Judgment: Method of Relative Heights
Task Duration
2
4
6
8
10
2 3 4 5 6
50%
40%
30%
20%
10%Frequency
Probability
(days)
Question: How many times the duration
will be between 2 and 3 days?
25. How Many Trials Are Required?
Huge number of trials (> 1000) usually does not increase
accuracy of analysis
• Incorporate rare events
• Use convergence monitoring
26. What Is The Chance That a Project Will Be on Time
and Budget?
27. Analysis of Monte Carlo Results
• Sensitivity and Correlations
• Critical Indices
• Crucial tasks
• Critical Risks
• Probabilistic Calendars
• Deadlines
• Conditional Branching
• Probabilistic Branching
• Chance of Task Existence
28. Analyze Results
1/31/2018 2009 Intaver Institute 28
• Risk Scores
• Overview with and without risks
• Detailed results of analysis
View results
• Sensitivity
• Crucial Tasks
• Success Rate
• Risk Chart
Identify critical
risks and tasks
• Risk ScoresRisk Matrix
29. Project Gantt
1/31/2018 2009 Intaver Institute 29
When you have project
schedule and risk
breakdown structure ready
click here to perform Monte
Carlo simulations
31. Result Gantt Chart
1/31/2018 2009 Intaver Institute 31
White bars represent
original project schedule
(no risks)
Blue bars represent
project schedule with
risks
Because of risks, project duration
significantly increased
32. Results of Risk Analysis
1/31/2018 2009 Intaver Institute 32
Project Summary:
project duration, cost,
and finish time with
and without risks
Results of analysis
for project cost,
finish time, and
duration
Double click on any chart to view detailed information
33. Detailed Results of Analysis
Move the slider to determine the
chance that project will be within budget
Get detailed
statistical data
Data can be exported
as an image or text
Detailed results can be shown for each tasks
or whole project for cost, duration, start time,
finish time, and income.
34. Sensitivity
Tornado chart shows risks or other
parameters that have the most
affect on the project schedule
Critical risks need to be
mitigated first
35. Crucial Tasks
Crucial tasks have the
most affect on the
project schedule
Crucial tasks for project cost and duration
can be different
36. Success Rate
A task can be canceled if it reaches a task or a project deadline or if it is affected
by risk with a “Cancel task” outcome.
Success rate is calculated
based on number of times
the task is not canceled
37. Risk Chart
Risk chart show risks, associated with task versus duration or cost
This task has cost
and high risk
These tasks have
balanced risk versus
Cost ratio.
38. Risk Matrix
Risk matrix shows probability/impact on 5x5 matrix
Double-click on a
risk to view risk
assignments
Risk Probability,
Impact and Score for
the current schedule
39. Risk Planning
Modeling risk mitigation efforts
•Risk handling strategies
•Transfer
•Mitigate
•Eliminate
•Ignore
•Risk mitigation efforts represent their own costs etc.
which must be accounted for
•Create multiple baselines that model pre and post
mitigation risk handling efforts
•View results of risk handling efforts
•Select project alternative based on criteria (cost,
duration, start and finish time, success rate)
40. Additional Resources
40
Project Think:
Why Good
Managers
Make Poor
Project
Choices
Project
Decisions: The
Art and Science
Introduction to
Project Risk
Management
and Decision
Project Risk
Analysis Made
Ridiculously
Simple
Hinweis der Redaktion
Why is this easy
Risk register is central point of entry into risk analysis and management system
Shows calculated project risk scores – ranks and identifies critical project risks.
Add two screen shots.
Risk Register
Risk Assignment
Add slide with Risk Mitigation Waterfall diagram with descriptive names
Change to put calculated results in the Result Gantt chart
Detailed results show certainty levels or the chance that a project parameter will be a certain value. Allows you to see the values e.g. managing at 75% certainty as well as setting buffers or contingencies.
Calculates the success rates of tasks or project based upon deadlines or constraints