SlideShare ist ein Scribd-Unternehmen logo
1 von 53
Downloaden Sie, um offline zu lesen
Executing
Process Group
Project Management
Processes PMBOK 5th edition
Hossam Maghrabi,PMP
Executing Process Group
& Project Boundaries
Executing Process Group
& Knowledge Areas
This Process Group involves Coordinating People & Resources, Managing Stakeholder Expectations, as
well as Integrating & Performing the Project’s Activities accordance with the project management plan.
The results may require Planning Updates & Re-Baselining.
A large portion of the Project’s Budget will be expended in performing the processes of this Process Group.
Direct and Manage Project work:
Data Flow Diagram
The process of Leading &
Performing Project’s Work
that defined in the project
management plan
&
Implementing Approved
Changes
To
Achieve the Project’s
Objectives.
Direct and Manage Project work:
General Note:
- The project manager, along with the project management team,
- Directs the Performance of the planned project activities and Manages the various technical &
organizational interfaces that exist within the project.
- Manage any unplanned activities and determine the appropriate course of action.
- During project execution, The Work Performance Data is collected and appropriately actioned and
communicated. It includes information about the completion status of deliverables and other relevant details
about project performance. Which used as an input to the Monitoring and Controlling Process Group.
- All Project Changes & the Implementation of Approved Changes & its impacts
Require to be reviewed for taking the proper actions,
• Corrective action - An intentional activity that realigns the performance of the project work with the project
management plan.
• Preventive action - An intentional activity that ensures the future performance of the project work is aligned with
the project management plan.
• Defect repair - An intentional activity to modify a nonconforming product or product component.
• Updates - Changes to formally controlled project documents, plans, etc.,.
- Direct and Manage Project Work Activities include,
1. Create project deliverables,
2. Manage & Train the Project’s team members,
3. Obtain, Manage & Use Resources -Materials, Tools, Equipment, & Facilities-,
4. Implement the planned Methods & Standards,
5. Establish and Manage Project Communication Channels, both External & Internal,
6. Generate Work Performance Data to facilitate Forecasting -Cost, Schedule, Technical & Quality
Progress & Status-
7. Issue change requests and implement approved changes,
8. Manage risks and implement risk response activities,
9. Manage sellers and suppliers,
10. Manage Stakeholders & their Engagement,
11. Collect & document Lessons Learned,
12. Implement Approved Process Improvement Activities, , , , ,
Direct and Manage Project work:
General Note:
Direct and Manage Project work:
Inputs
1. Project Management Plan -
2. Approved Change Requests -
The output of Perform Integrated Change Control process, and include those requests reviewed and
approved for implementation by the change control board (CCB).
3. Enterprise Environmental Factors -
– Structure & Culture of Organizations, Customer & Sponsor,
– Infrastructure & Personnel administration,
– Stakeholder risk tolerances - For example allowable cost overrun percentage -,
– Project management information system , , ,
4. Organizational Process Assets -
– Standardized Guidelines & Work Instructions,
– Communication media, record retention, and security requirements,
– Issue and defect management procedures,
– Project files from previous projects,
– Issue and defect management database(s) containing historical
Direct and Manage Project work:
Tools & Techniques (T&T)
1. Expert Judgment,
Used to assess the inputs needed to direct and manage execution of the project management plan.
2. Project Management Information System,
It is part of the environmental factors, provides access to tools, such as a scheduling tool, a work authorization
system, a configuration management system, an information collection and distribution system, or interfaces to other
online automated systems. Automated gathering and reporting on key performance indicators (KPI) can be part of
this system.
3. Meetings,
– Meetings tend to be one of three types - Information exchange; Brainstorming, option evaluation, or design;
Decision making –
– Meetings should be prepared with a well-defined agenda, purpose, objective, and time frame and should be
appropriately documented with meeting minutes and action items.
– Meeting Minutes should be stored as defined in the project management plan.
– Meetings are most effective when all participants can be face-to-face in the same location.
– Virtual Meetings generally require additional preparation and organization to achieve the same effectiveness of a
face-to-face meeting.
Direct and Manage Project work:
Outputs
1. Deliverables,
2. Work Performance Data,
Examples of work performance data include work completed, key performance indicators, technical performance
measures, start and finish dates of schedule activities, number of change requests, number of defects, actual costs,
and actual durations, etc.
3. Change Requests,
Include Corrective action, Preventive action, Defect repair & Updates.
4. Project Management Plan Updates,
5. Project Documents Updates,
Ex. Requirements documentation, Project logs, Risk register, and Stakeholder register
Perform Quality Assurance:
Data Flow Diagram
The process of Auditing the
Quality Requirements & the
results from Quality Control
Measurements
To ensure that appropriate
Quality Standards &
Operational Definitions are
used.
It Facilitates the Improvement of
quality processes
Perform Quality Assurance:
General Note:
Perform Quality Assurance is an execution process that,
- Uses Data Created During Plan Quality Management & Control Quality processes.
- Implements a Set of Planned & Systematic Acts & Processes
for,
I. Being certain about quality by preventing defects through the planning processes or by inspecting out
defects during the work-in-progress stage of implementation.
II. Building a confidence that A Future Output or an Unfinished Output - Work in Progress - will be
completed in a manner that meets the specified requirements and expectations.
III. Providing an umbrella for Continuous Process Improvement for improving the quality of all
processes to Reduces Waste & Eliminates Activities that do Not Add Value which increase levels of
Efficiency & Effectiveness.
The Prevention & Inspection aspects of quality assurance should have a demonstrable influence on the
Project Management.
Quality Assurance work will fall under the Conformance Work Category in the Cost Of Quality framework.
Perform Quality Assurance:
Inputs
1. Quality Management Plan - Describes the quality assurance and continuous
process improvement approaches for the project.
2. Process Improvement Plan.
3. Quality Metrics -Provide The Attributes That Should Be Measured & The
Allowable Variations.
4. Quality Control Measurements - The Results of Control Quality Activities.
They are used to analyze and evaluate the quality of the processes of the project against the
standards of the performing organization or the requirements specified.
5. Project Documents - Project documents may influence quality assurance work
and should be monitored within the context of a system for configuration management.
Perform Quality Assurance:
Tools & Techniques (T&T)
1. Quality Management and Control Tools - Plan Quality Management &
Control Quality processes Tools and Techniques plus other tool like as the following,
I. Affinity diagrams - Is similar to mind-mapping techniques in that they are used to
generate ideas that can be linked to form organized patterns of thought about a problem. For
example, The creation of the WBS may be enhanced by using the affinity diagram to give structure to the
decomposition of scope.
II. Process decision program charts (PDPC). Used to understand a goal in relation to the
steps for getting to the goal. It’s useful as a method for contingency planning because it aids teams in
anticipating intermediate steps that could derail achievement of the goal.
Perform Quality Assurance:
Tools & Techniques (T&T)
1. Quality Management and Control Tools –
III. Interrelationship digraphs - An adaptation of relationship diagrams - Provide a
process for creative problem solving in moderately complex scenarios that possess
intertwined logical relationships for up to 50 relevant items. It may be developed from data
generated in other tools such as the affinity diagram, the tree diagram, or the fishbone diagram.
IV. Tree diagrams - Systematic diagrams - Are useful in visualizing the parent-to-child
relationships in any decomposition hierarchy that uses a systematic set of rules that define a
nesting relationship, such as the WBS, RBS , and OBS.
V. Prioritization matrices - Identify the key issues and the suitable alternatives to be
prioritized as a set of decisions for implementation.
Perform Quality Assurance:
Tools & Techniques (T&T)
1. Quality Management and Control Tools -
VI. Activity network diagrams - Previously known as arrow diagrams - They include both the
AOA (Activity on Arrow) and, most commonly used, AON (Activity on Node) formats of a
network diagram. Activity network diagrams are used with project scheduling methodologies such as
program evaluation and review technique (PERT), critical path method (CPM), and precedence diagramming
method (PDM).
VII. Matrix diagrams - A quality management and control tool used to perform data analysis
within the organizational structure created in the matrix. The diagram show the strength of
relationships between factors, causes, and objectives that exist between the rows and columns that form the
matrix.
Perform Quality Assurance:
Tools & Techniques (T&T)
2. Quality Audits - A structured, independent process to determine if project activities
comply with organizational and project policies, processes, and procedures.
– The objectives of a quality audit may include:
- Identify all good and best practices being implemented;
- Identify all nonconformity, gaps, and shortcomings;
- Share good practices introduced or implemented in similar projects in the organization and/or industry;
- Proactively offer assistance in a positive manner to improve implementation of processes to help the team
raise productivity;
- Highlight contributions of each audit in the lessons learned repository of the organization.
Quality audits may be Scheduled or Random, and may be conducted by Internal or External auditors.
3. Process Analysis – Follows the steps outlined in the process improvement plan to
identify needed improvements. It includes root cause analysis—a specific technique used to
identify a problem, discover the underlying causes that lead to it, and develop preventive actions.
Perform Quality Assurance:
Outputs
1. Change Requests - used to take corrective action ,preventive action, or to
perform defect repair to allow full consideration of the recommended improvements.
2. Project Management Plan Updates.
3. Project Documents Updates - Quality audit reports, Training plans.....
4. Organizational Process Assets Updates - The organization’s Quality
Standards & the Quality Management System….
Manage Communications:
Data Flow Diagram
The process of creating, collecting,
distributing, storing, retrieving,
and the ultimate disposition of
project information in accordance
to the communications
management plan.
It enables an efficient and effective
communications flow between
project stakeholders.
Manage Communications:
Inputs
1. Communications Management Plan -
Describes how project communications will be planned, structured, monitored, and
controlled.
2. Work Performance Reports -
A collection of project performance and status information that may be used to
facilitate discussion and to create communications.
It is important that reports be comprehensive, accurate, and available in a timely manner.
3. Enterprise Environmental Factors.
4. Organizational Process Assets.
1. Communication Technology - Choosing of Communication Technology -.
Technology is nothing more than a tool, and depending upon the project need, it might be the use of
the email, teleconferencing, blog, website, forums etc.
All communication tools should be tailored to suit the requirements of each project.
2. Communication Models - Choosing of Communication Models -.
To ensure that the choice of the communication model is appropriate for the project & any barriers
(noise) are identified and managed in order to an effective and efficient communications process.
3. Communication Methods - Oral , Written , Body Language -
To ensure that the information that has been created & distributed has been received and understood
to enable response and feedback.
4. Information Management Systems - IMS -
5. Performance Reporting - Include,
Analysis of past performance, Analysis of project forecasts, Current status of risks and issues, Work
completed during the period, Work to be completed in the next period, Summary of changes
approved in the period, and Other relevant information, which is reviewed and discussed.
Manage Communications:
Tools & Techniques (T&T)
Manage Communications:
Outputs
1. Project Communications - may include, performance reports, deliverables status,
schedule progress, and cost incurred. They can influenced by factors such as, the urgency and
impact of the message, its method of delivery, and level of confidentiality.
2. Project Management Plan Updates - Provides information on project baselines,
communications management, and stakeholder management. Each of these areas may require
updates based upon the current performance of the project against the Performance measurement
Baseline (PMB).
Performance measurement Baseline (PMB) is an approved plan for the project work to which the
project execution is compared, and deviations are measured for management control. It integrates
scope, schedule, and cost parameters of a project, & may also include technical and quality
parameters.
3. Project Documents Updates - Issue log, Project schedule, Project funding requirements -.
4. Organizational Process Assets Updates - Stakeholder notifications, Project reports,
Project records, Feedback from stakeholders, Lessons learned documentation.
Acquire Project Team:
Data Flow Diagram
The process of Confirming
Human Resource
Availability & Obtaining
the Team Necessary to
Complete Project
Activities.
Consists of
Outlining & Guiding the
Team Selection &
Responsibility Assignment
to obtain a successful
team.
Acquire Project Team:
General Note:
The following factors should be Considered during the process of Acquiring The Project
Team & Planned for in The Planning Stages of the Project:
1. The Project Manager or Project Management Team should Effectively Negotiate & Influence
Others who are in a position To Provide the Required Human Resources for the project.
2. Failure to Acquire the Necessary Human Resources for the project may affect Project Schedules,
Budgets, Customer Satisfaction, Quality, & Risks. The project manager or project management team
will be required to reflect the impact of any unavailability of required human resources in the project
schedule , , , , , , & the other project management plans.
3. Insufficient Human Resources or Capabilities Decrease the Probability of Success and, in a worst
case scenario, Could Result in Project Cancellation.
4. If the Human Resources are Not Available due to constraints, such as economic factors or previous
assignments to other projects, the project manager or project team may be required to assign
alternative resources, perhaps with lower competencies, Provided there is No Violation of legal,
regulatory, mandatory, or other specific criteria.
Acquire Project Team:
Inputs
1. Human Resource Management Plan - Provides guidance for Identifying ,
Staffing, Managing, & Releasing the Project Team members. It includes,
I. Roles and responsibilities that define the positions, skills, and competencies that the project
demands.
II. Project organization charts that indicate the number of people needed for the project.
III. Staffing management plan that delineate the time periods each project team member will be
needed & other information important to engage the project team.
2. Enterprise Environmental Factors.
I. Existing information on human resources including availability, competency levels, prior
experience, interest in working on the project and their cost rate;
II. Personnel Administration Policies, Organizational Structure & Locations.
3. Organizational Process Assets - That influence the Acquire Project Team process.
Acquire Project Team:
Tools & Techniques (T&T)
1. Pre-assignment - The project team members are selected in advance.
This situation can occur if
– Some staff assignments are defined within the project charter.
– The project is dependent upon the expertise of particular persons.
– The project is the result of specific people being identified as part of a competitive proposal.
2. Negotiation
Negotiate the Project Staff Assignments with Functional managers, Other project management
teams within the performing organization, External organizations, vendors, suppliers, contractors.
3. Acquisition When the performing organization is unable to provide the staff needed to
complete a project, the required services may be Acquired From Outside Sources.
Acquire Project Team:
Tools & Techniques (T&T)
4. Virtual Teams -A Groups of people with a shared goal who fulfill their roles with little or
no time spent meeting face to face.
5. Multi-Criteria Decision Analysis - A valuable tool that we can apply to many
complex decisions. It is most applicable to solving problems that are characterized as a choice
among alternatives.
– Examples of selection criteria that can be used to score team members:
 Availability, Cost , Experience, , Knowledge, Skills.
 Ability - The Team Member has the competencies needed by the project. -.
 Attitude - The ability to work with others as a cohesive team -.
 International factors - Consider team member location, time zone & communication capabilities.
Acquire Project Team:
Outputs
1. Project Staff Assignments -
– The project is staffed When Appropriate People have been Assigned to the Team.
The Documentation of Project Staff Assignments can include a Project Team Directory, Memos
to Team Members, & names inserted into other parts of the project management plan, such as Project
Organization Charts & Schedules.
2. Resource Calendars - Document the time periods that each project team member
is available to work on the project.
Creating a Reliable Schedule depends on having a good understanding of each person’s availability
& schedule constraints, including time zones, work hours, vacation time, local holidays, and
commitments to other projects.
3. Project Management Plan Updates -
– When gaps occur, The Project Management Plan needs to be updated to change the team
structure, roles, or responsibilities.
Ex. The person assigned to a predefined role may not fulfill all staffing requirements outlined in the
human resource management plan.
Develop Project Team:
Data Flow Diagram
The process of Improving
Competencies, Team Member
Interaction, & Overall Team
Environment to Enhance
Project Performance.
It results in
Improve Teamwork, Enhance
People Skills & Competencies,
Motivate Employees, Reduce
Staff Turnover Rates, &
Improve Overall Project
Performance.
Develop Project Team:
General Note:
1. Project Manager -
– Should Acquire Skills To Identify, Build, Maintain, Motivate, Lead, & Inspire Project Teams To
Achieve High Team Performance & Meet the Project’s Objectives.
– Should Continually Motivate Their Team By Providing Challenges & Opportunities, Providing
Timely Feedback & Support as needed, plus Recognizing & Rewarding Good Performance.
– Should Request Management Support and/or Influence the Appropriate Stakeholders To
Acquire the Resources needed to Develop Effective Project Teams.
– Responsible for Create an Environment that Facilitates Teamwork & Developing an Effective
Project Teams.
– Should Capitalize on Cultural Differences Creating a Dynamic, Cohesive, & Collaborative
Team Culture To Improve Individual & Team productivity, Team Spirit, & Cooperation Plus
Allow Cross Training & Mentoring Between Team Members to Share Knowledge & Expertise.
2. Project Communication -
High team performance can be achieved by using open and effective communication, creating
team building opportunities, developing trust among team members, managing conflicts in a
constructive manner, and encouraging collaborative problem solving and decision making.
Develop Project Team:
Inputs
1. Human Resource Management Plan - Provides guidance on how project human
resources should be identified, staffed, managed, and eventually released.
2. Project Staff Assignments - Identify the people who are on the team / List of project
team members.
3. Resource Calendars - Identify times when the project team members can participate in
team development activities.
Develop Project Team:
Tools & Techniques (T&T)
1. Interpersonal Skills -soft skills - A behavioral competencies that include proficiencies
such as communication skills, emotional intelligence, conflict resolution, negotiation, influence, team
building, and group facilitation.
Ex. the project management team can use emotional intelligence to reduce tension and increase cooperation by
identifying, assessing, and controlling the sentiments of project team members, anticipating their actions,
acknowledging their concerns, and following up on their issues.
2. Training (in-house or external trainers) - Scheduled training takes place in the
human resource management plan. Unplanned training takes place as a result of observation,
conversation, and project performance appraisals conducted during the controlling process of
managing the project team.
Training costs could be included in the project budget, or supported by performing organization if the
added skills may be useful for future projects.
3. Ground Rules - A clear expectations regarding acceptable behavior by project team members.
All project team members share responsibility for enforcing the rules once they are established.
Discuss ground rules in areas such as code of conduct, communication, working together, or meeting
etiquette allows team members to discover values that are important to one another.
4. Team-Building Activities
5. Colocation -Tight Matrix-Involves placing many or all of the most active project
team members in the same physical location to enhance their ability to perform as a team.
While colocation is considered a good strategy, the use of virtual teams can bring benefits such as the use of more skilled
resources, reduced costs, less travel, and relocation expenses and the proximity of team members to suppliers, customers, or
other key stakeholders.
Develop Project Team:
Tools & Techniques (T&T)
6. Recognition and Rewards - Part of the team development process involves
recognizing and rewarding desirable behavior.
People are motivated if they feel they are valued in the organization and this value is demonstrated by the
rewards given to them.
A good strategy for project managers is to give the team recognition throughout the life cycle of the
project rather than waiting until the project is completed.
Develop Project Team:
Tools & Techniques (T&T)
7. Personnel Assessment Tools - Give the project manager and the project team an
insight into areas of strength and weakness.
– Tools such as attitudinal surveys, specific assessments, structured interviews, ability tests, and
focus groups.
– These tools help project managers assess the team preferences, aspirations, behavior and attitude.
Develop Project Team:
Tools & Techniques (T&T)
Develop Project Team:
Outputs
1. Team Performance Assessments - The project management team makes formal or
informal assessments of the project team’s effectiveness.
– Team performance assessment criteria should be determined by all appropriate parties and
incorporated in the Develop Project Team inputs.
– The performance of a successful team is measured in terms of technical success according to
agreed-upon project objectives (including quality levels), performance on project schedule
(finished on time), and performance on budget (finished within financial constraints).
– The evaluation of a team’s effectiveness may include indicators such as ( Improvements in
skills, Improvements in competencies, Reduced staff turnover rate, Increase team cohesiveness)
– As a result of Team performance assessment, the resources and recommendations for team
improvement should be well documented and forwarded to the relevant parties.
2. Enterprise Environmental Factors Updates - Personnel administration,
Employee training records, and skill assessments.
Manage Project Team:
Data Flow Diagram
The process of influences team
behavior, manages conflict, resolves
issues, tracking team member
performance, providing feedback,
& managing team changes to
optimize project performance.
As a result of managing the project
team, change requests are
submitted, issues are resolved, input
is provided for performance
appraisals, & lessons learned are
added to the organization’s
database.
Manage Project Team:
Inputs
1. Human Resource Management Plan.
2. Project Staff Assignments.
3. Team Performance Assessments - By continually assessing the project team’s
performance, actions can be taken to resolve issues, modify communication, address conflict, and
improve team interaction.
4. Issue Log - Issues arise in the course of managing the project team. An issue log can be used to
document and monitor who is responsible for resolving specific issues by a target date.
5. Work Performance Reports - Provide documentation about the current project status
compared to project forecasts. It include results from schedule control, cost control, quality control,
and scope validation.
The information from performance reports and related forecasts assists in determining future human
resource requirements, recognition and rewards, and updates to the staffing management plan.
6. Organizational Process Assets - Ex. Certificates of appreciation, Newsletters,
Websites, Bonus structures, Corporate clothes, & Other organizational perquisites.
Manage Project Team:
Tools & Techniques (T&T)
1. Observation and Conversation -Used to stay in touch with the work & attitudes of
project team members.
The project management team monitors progress toward project deliverables, accomplishments that are a
source of pride for team members, and interpersonal issues.
2. Project Performance Appraisals
– Objectives for conducting performance appraisals during the course of a project can include
clarification of roles and responsibilities, constructive feedback to team members, discovery of
unknown or unresolved issues, development of individual training plans, & the establishment of
specific goals for future time periods.
– The need for formal or informal project performance appraisals depends on the length of
the project, complexity of the project, organizational policy, labor contract requirements, and the
amount and quality of regular communication.
Manage Project Team:
Tools & Techniques (T&T)
3. Conflict Management.
Manage Project Team:
Tools & Techniques (T&T)
4. Interpersonal Skills.
It is important to communicate the vision and inspire the
project team to achieve high performance.
Manage Project Team:
Outputs
1. Change Requests - Following is an examples,
I. Staffing Changes, whether by choice or by uncontrollable events, may include moving people
to different assignments, outsourcing some of the work, and replacing team members who
leave. This will affect the project management plan(Schedule , Budget ……) through
integration change control process.
II. Preventive actions like Cross training to reduce problems during project team member
absences and additional role clarification to ensure all responsibilities are fulfilled.
2. Project Management Plan Updates -Human Resource Management plan,,,,,,.
3. Project Documents Updates - Issue log, Roles description, Project staff
assignments,,,,,.
4. Enterprise Environmental Factors Updates -Input to organizational
performance appraisals, & Personnel skill updates.
5. Organizational Process Assets Updates - Historical information and lessons
learned documentation, Templates, and Organizational standard processes.
Manage Stakeholder Engagement:
Data Flow Diagram
Communicating & working
with stakeholders
To
Meet their needs/expectations,
address issues as they occur,
& foster appropriate
stakeholder engagement in
project activities throughout
the project life cycle.
It allows the project manager
to increase support and
minimize resistance from
stakeholders for increasing
the chances to achieve project
success.
Manage Stakeholder Engagement:
General Note:
The ability of Stakeholders to Influence the project is typically highest during the initial
stages and gets progressively lower as the project progresses.
- Managing Stakeholder Engagement helps to increase the probability of project success by ensuring
that stakeholders clearly understand the project goals, objectives, benefits, and risks. Which enables
stakeholder to be active supporters of the project and to help guide activities and project decisions.
- By Anticipating People’s Reactions to the project, proactive actions can be taken to win support or
minimize negative impacts and Decreases the risk of the project failing to meet its goals and
objectives.
- The project manager is responsible for Managing Stakeholder Engagement which involves
activities such as,
1. Engaging Stakeholders at appropriate project stages to obtain or confirm their continued commitment to the
success of the project,
2. Managing Stakeholder Expectations through negotiation and communication, Ensuring Project Goals are
Achieved,
3. Addressing Potential Concerns that have not yet become issues & Anticipating Future Problems that may be
raised by stakeholders,
4. Clarifying and Resolving Issues that have been identified.
Manage Stakeholder Engagement:
Inputs
1. Stakeholder Management Plan - Provides guidance on how the various stakeholders
can be best involved in the project.
2. Communications Management Plan - Provides guidance and information on
managing stakeholder expectations. Ex. Stakeholder communications requirements, Information to be
communicated, including language, format, content, and level of detail, Reason for distribution of information, Person
or groups who will receive information, and Escalation process.
3. Change Log - Used to document changes that occur during a project. These changes - & their
impact on the project in terms of time, cost, and risk - are communicated to the appropriate
stakeholders.
4. Organizational Process Assets.
Manage Stakeholder Engagement:
Tools & Techniques (T&T)
1. Communication Methods - Oral , Written , Body Language / Formal , Unformal -.
- Based on the stakeholders’ communication requirements, the project manager decides
how, when, and which of these communication methods are to be used in the project.
- The methods of communication identified for each stakeholder in the communications
management plan are utilized during stakeholder engagement management.
2. Interpersonal Skills -
- Apply interpersonal skills to manage stakeholders’ expectations, Building trust, Resolving
conflict, Active listening, Overcoming resistance to change.
3. Management Skills -
- Apply management skills to Coordinate and Harmonize the group toward accomplishing
the project objectives through the following activities,
Facilitate consensus, Influence people to support the project, Negotiate agreements to satisfy the
project needs, Modify organizational behavior to accept the project outcomes.
Manage Stakeholder Engagement:
Outputs
1. Issue Log - This log is updated as new issues are identified and current issues are resolved.
2. Change Requests - Managing stakeholder engagement may result in a change request
to the product or the project, corrective or preventive actions to the project itself or to the
interaction with the impacted stakeholders.
3. Project Management Plan Updates
Ex. Some communications may no longer be necessary, an ineffective communication method may
be replaced by another method, or a new communication requirement may be identified.
Ex. It may be determined that a stakeholder has additional informational needs.
4. Project Documents Updates
Ex. The stakeholder register.
5. Organizational Process Assets Updates -
Ex. Stakeholder notifications, Project reports, Project presentations, Project records, Feedback from
stakeholders, Lessons learned documentation.
Conduct Procurements:
Data Flow Diagram
The process of Obtaining
Seller Responses, Selecting
a Seller, & Awarding a
Contract.
It provides alignment of
internal and external
stakeholder expectations
through established
agreements.
Conduct Procurements:
General Note:
The effort of the buyer & seller in this process is to Collectively Prepare a
Procurement Statement of Work that will satisfy the requirements of the project.
The parties will then negotiate a final contract for award.
During the Conduct Procurements process,
1. The team will Receive Bids or Proposals & will Apply Previously Defined Selection
Criteria to Select One or more Sellers who are qualified to perform the work &
acceptable as a seller.
2. On major procurement items, the overall process of requesting responses from sellers
and evaluating those responses can be repeated.
3. A short list of qualified sellers can be established based on a preliminary proposal.
4. A more detailed evaluation can then be conducted based on a more specific and
comprehensive requirements document requested from the sellers on the short list.
Conduct Procurements:
Inputs
1. Procurement Management Plan - Describes how the procurement processes will be
managed from developing procurement documentation through contract closure.
2. Procurement Documents - Provide an audit trail for contracts and other agreements.
3. Source Selection Criteria - Include information on the supplier’s required capabilities,
capacity, delivery dates, product cost, life-cycle cost, technical expertise, and the approach to the contract.
4. Seller proposals - Prepared in response to a procurement document package. They form the
basic information that will be used by an evaluation body to select one or more successful bidders (sellers).
5. Project Documents - Ex. The risk-related contract decisions included within the risk register.
6. Make-or-Buy Decisions.
7. Procurement Statement of Work - It is a critical component of the procurement
process and can be modified as needed through this process until a final agreement is in place
(Specifications, Quantity desired, Quality levels…..). It Provides suppliers with a clearly stated set of
goals, requirements, and outcomes from which they can provide a quantifiable response.
8. Organizational Process Assets.
Conduct Procurements:
Tools & Techniques (T&T)
The Tools and Techniques described here may be used alone or in combination with select sellers.
1. Bidder Conferences - Contractor Conferences, Vendor Conferences, & Pre-Bid Conferences -
They are meetings between the buyer and all prospective sellers, Prior to submittal of a Bid or
Proposal, To Ensure That all prospective sellers have a clear and common understanding of the
procurement requirements, & that no bidders receive preferential treatment.
To be fair, buyers should take great care to ensure that all prospective sellers hear every question
from any individual prospective seller and every answer from the buyer. Responses to questions can
be incorporated into the procurement documents as amendments.
2. Proposal Evaluation Techniques - A formal evaluation review process will be
defined by the buyer’s procurement policies.
3. Independent Estimates - The procuring organization may elect to either prepare its
own independent estimate, or have an estimate of costs prepared by an outside professional
estimator, To Serve As a Benchmark on proposed responses.
Significant differences in cost estimates can be an indication that the procurement statement of
work was deficient, ambiguous, and/or that the prospective sellers either misunderstood or failed to
respond fully to the procurement statement of work.
Conduct Procurements:
Tools & Techniques (T&T)
4. Expert Judgment - The evaluation of proposals may be accomplished by a multi-
discipline review team with expertise in each of the areas covered by the procurement documents
and proposed contract. Such as contracting, legal, finance, accounting, engineering, design, research,
development, sales, and manufacturing.
5. Advertising - Placing advertisements for procurement to expand the lists of potential sellers
or because the government jurisdictions require public advertising.
6. Analytical Techniques - Help organizations identify the readiness of a vendor to
provide the desired end state, determine the cost expected to support budgeting, and avoid cost
overruns due to changes.
Ex. By Examining Past Performance Information, teams may Identify Areas that may have more
risk & that need to be monitored closely to ensure success of the project.
7. Procurement Negotiations -Help in Clarify the structure, Requirements, & other
terms of the purchases so that mutual agreement can be reached prior to signing the contract. The
Project Manager & other Project Management Team may not be the lead negotiator on procurements. They may
be present during negotiations to provide assistance & clarification.
For Complex Procurement Items, contract negotiation can be an independent process with inputs (e.g., issues or an open
items listing) and outputs (e.g., documented decisions) of its own. For Simple Procurement Items, the terms and
conditions of the contract can be previously set and nonnegotiable, and only need to be accepted by the seller.
Conduct Procurements:
Outputs
1. Selected Sellers - Those who have been judged to be in a competitive range based upon
the outcome of the proposal or bid evaluation, & who have negotiated a draft contract that will
become the actual contract when an award is made.
Final approval of all complex, high-value, high-risk procurements will generally require organizational
senior management approval prior to award.
2. Agreements - A Procurement Agreement includes terms and conditions, and may
incorporate other items that the buyer specifies regarding what the seller is to perform or provide.
Include, Statement of work or deliverables, Schedule baseline, Performance reporting, Period of
performance, Roles and responsibilities, Seller’s place of performance, Pricing, Payment terms, Place of
delivery, Inspection and acceptance criteria, Warranty, Product support, Limitation of liability, Fees and
retainer, Penalties, Incentives, Insurance and performance bonds, Subordinate subcontractor approvals,
Change request handling, & Termination clause and alternative dispute resolution (ADR) mechanisms.
The project management team is responsible for making sure that all agreements meet the
specific needs of the project while adhering to organizational procurement policies.
The ADR method can be decided in advance as a part of the procurement award.
Conduct Procurements:
Outputs
3. Resource Calendars - The quantity and availability of contracted resources and those
dates on which each specific resource or resource group can be active or idle are documented.
4. Change Requests.
5. Project Management Plan Updates - Any impacted baseline plans.
6. Project Documents Updates - Requirements documentation, Requirements
traceability documentation, Risk register, Stakeholder register

Weitere ähnliche Inhalte

Was ist angesagt?

Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupTùng Trần Thanh
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Editionpankajsh10
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management DetailsAnand Bobade
 
Project communication management
Project communication managementProject communication management
Project communication managementPreshan Pradeepa
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Agus Suhanto
 
Common causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsCommon causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsSANJEEV Wazir
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures Ian Cammack
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk ManagementKelvin Fredson
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniquesShivangi Saini
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelyChetan Khanzode
 
Project communications management
Project communications managementProject communications management
Project communications managementPrabudh Dhingra
 
Presentation project management
Presentation project managementPresentation project management
Presentation project managementFlobz Caloy
 

Was ist angesagt? (20)

Project Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP WorkgroupProject Schedule Management - Sequence Activities - PMP Workgroup
Project Schedule Management - Sequence Activities - PMP Workgroup
 
Project Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th EditionProject Scope Management - PMBOK 5th Edition
Project Scope Management - PMBOK 5th Edition
 
PMP Chap 10 - Project Communication Management Details
PMP  Chap 10 - Project Communication Management DetailsPMP  Chap 10 - Project Communication Management Details
PMP Chap 10 - Project Communication Management Details
 
Project communication management
Project communication managementProject communication management
Project communication management
 
Project communications management PMBOK Sixth Edition
Project communications management  PMBOK Sixth EditionProject communications management  PMBOK Sixth Edition
Project communications management PMBOK Sixth Edition
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
PMP_Project Cost Management
PMP_Project Cost ManagementPMP_Project Cost Management
PMP_Project Cost Management
 
Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6Project Schedule Management - PMBOK6
Project Schedule Management - PMBOK6
 
Common causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsCommon causes of cost overruns in construction projects
Common causes of cost overruns in construction projects
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures
 
9.6 Control Resources
9.6 Control Resources9.6 Control Resources
9.6 Control Resources
 
PMP_Project Communication Management
PMP_Project Communication ManagementPMP_Project Communication Management
PMP_Project Communication Management
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk Management
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Establishing an effective epmo
Establishing an effective epmoEstablishing an effective epmo
Establishing an effective epmo
 
Smart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectivelySmart project management - Best Practices to Manage Project effectively
Smart project management - Best Practices to Manage Project effectively
 
Project communications management
Project communications managementProject communications management
Project communications management
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Presentation project management
Presentation project managementPresentation project management
Presentation project management
 

Andere mochten auch

PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -Hossam Maghrabi
 
PMBOK_5th_Project Management Framework
PMBOK_5th_Project Management FrameworkPMBOK_5th_Project Management Framework
PMBOK_5th_Project Management FrameworkHossam Maghrabi
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part twoHossam Maghrabi
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part twoHossam Maghrabi
 
Monitor and Control Process Group - Part One
Monitor and Control Process Group - Part OneMonitor and Control Process Group - Part One
Monitor and Control Process Group - Part OneHossam Maghrabi
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OneHossam Maghrabi
 
Risk management overview
Risk management overviewRisk management overview
Risk management overviewHossam Maghrabi
 
Pmbok 5th planning process group part three
Pmbok 5th planning process group part threePmbok 5th planning process group part three
Pmbok 5th planning process group part threeHossam Maghrabi
 
Pmbok 5th planning process group part four _ Project Risk Management
Pmbok 5th planning process group part four _ Project Risk ManagementPmbok 5th planning process group part four _ Project Risk Management
Pmbok 5th planning process group part four _ Project Risk ManagementHossam Maghrabi
 
PMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in EnglishPMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in EnglishRicardo Viana Vargas
 
Project Management Communications – Virtual and Global Teams
Project Management Communications – Virtual and Global TeamsProject Management Communications – Virtual and Global Teams
Project Management Communications – Virtual and Global TeamsDimitris Litsikakis
 
PMP success - Preparation to Passing the Certification.
PMP success - Preparation to Passing the Certification.PMP success - Preparation to Passing the Certification.
PMP success - Preparation to Passing the Certification.sandeep sonkusale
 
Project Management: Executing process group - Lesson 3
Project Management: Executing process group - Lesson 3Project Management: Executing process group - Lesson 3
Project Management: Executing process group - Lesson 3JMBOKAcademy
 
01 3 day elearning executing process v2
01 3 day elearning executing process v201 3 day elearning executing process v2
01 3 day elearning executing process v2Joyce Wong
 
Executing and Managing a Project
Executing and Managing a ProjectExecuting and Managing a Project
Executing and Managing a ProjectNishant Munjal
 
PMP PMBok 5th Project management processes
PMP PMBok 5th Project management processesPMP PMBok 5th Project management processes
PMP PMBok 5th Project management processesAbdullah Ahmed, PMP, RMP
 
Introduction to pmp
Introduction to pmpIntroduction to pmp
Introduction to pmpshkadry
 

Andere mochten auch (20)

PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -PMBOK_5th_Initiating Process Group -
PMBOK_5th_Initiating Process Group -
 
PMBOK_5th_Project Management Framework
PMBOK_5th_Project Management FrameworkPMBOK_5th_Project Management Framework
PMBOK_5th_Project Management Framework
 
Pmbok 5th planning process group part two
Pmbok 5th planning process group part twoPmbok 5th planning process group part two
Pmbok 5th planning process group part two
 
Monitor and control process group part two
Monitor and control process group part twoMonitor and control process group part two
Monitor and control process group part two
 
Monitor and Control Process Group - Part One
Monitor and Control Process Group - Part OneMonitor and Control Process Group - Part One
Monitor and Control Process Group - Part One
 
PMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part OnePMBOK 5th Planning Process Group Part One
PMBOK 5th Planning Process Group Part One
 
Risk management overview
Risk management overviewRisk management overview
Risk management overview
 
Pmbok 5th planning process group part three
Pmbok 5th planning process group part threePmbok 5th planning process group part three
Pmbok 5th planning process group part three
 
Pmbok 5th planning process group part four _ Project Risk Management
Pmbok 5th planning process group part four _ Project Risk ManagementPmbok 5th planning process group part four _ Project Risk Management
Pmbok 5th planning process group part four _ Project Risk Management
 
PMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in EnglishPMBOK® Guide 5th edition Processes Flow in English
PMBOK® Guide 5th edition Processes Flow in English
 
PMO OUTSOURCING
PMO OUTSOURCINGPMO OUTSOURCING
PMO OUTSOURCING
 
Project Management Communications – Virtual and Global Teams
Project Management Communications – Virtual and Global TeamsProject Management Communications – Virtual and Global Teams
Project Management Communications – Virtual and Global Teams
 
PMP success - Preparation to Passing the Certification.
PMP success - Preparation to Passing the Certification.PMP success - Preparation to Passing the Certification.
PMP success - Preparation to Passing the Certification.
 
Project Management: Executing process group - Lesson 3
Project Management: Executing process group - Lesson 3Project Management: Executing process group - Lesson 3
Project Management: Executing process group - Lesson 3
 
01 3 day elearning executing process v2
01 3 day elearning executing process v201 3 day elearning executing process v2
01 3 day elearning executing process v2
 
Executing and Managing a Project
Executing and Managing a ProjectExecuting and Managing a Project
Executing and Managing a Project
 
Executing
ExecutingExecuting
Executing
 
PMP PMBok 5th Project management processes
PMP PMBok 5th Project management processesPMP PMBok 5th Project management processes
PMP PMBok 5th Project management processes
 
Introduction to pmp
Introduction to pmpIntroduction to pmp
Introduction to pmp
 
Project Management Framework
Project Management FrameworkProject Management Framework
Project Management Framework
 

Ähnlich wie Pmbok 5th executing process group

Quality management procedures
Quality management proceduresQuality management procedures
Quality management proceduresselinasimpson1201
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
Project management
Project managementProject management
Project managementRohit Mishra
 
Project management
Project managementProject management
Project managementRohit Mishra
 
04 project integration management
04  project integration management04  project integration management
04 project integration managementAla Ibrahim
 
Product quality management
Product quality managementProduct quality management
Product quality managementSunil Meena
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptxHarsimratDeo1
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptxHarsimratDeo1
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagementDhamo daran
 
209560525-PMP-Study-Sheet.pdf
209560525-PMP-Study-Sheet.pdf209560525-PMP-Study-Sheet.pdf
209560525-PMP-Study-Sheet.pdfUmarFarooq29531
 
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...IRJET Journal
 
SPM PPT.pptx
SPM PPT.pptxSPM PPT.pptx
SPM PPT.pptxabhikde11
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfHuyNguyen657394
 
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdfprojectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdfJyotiYadav916744
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfHuyNguyen657394
 
BSBMGT517 Manage operational planPart C– Project Managing an op.docx
BSBMGT517 Manage operational planPart C– Project Managing an op.docxBSBMGT517 Manage operational planPart C– Project Managing an op.docx
BSBMGT517 Manage operational planPart C– Project Managing an op.docxAASTHA76
 

Ähnlich wie Pmbok 5th executing process group (20)

Quality management procedures
Quality management proceduresQuality management procedures
Quality management procedures
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
Project management
Project managementProject management
Project management
 
Project management
Project managementProject management
Project management
 
PMP PMBOK5 project management processes
PMP PMBOK5 project management processesPMP PMBOK5 project management processes
PMP PMBOK5 project management processes
 
04 project integration management
04  project integration management04  project integration management
04 project integration management
 
Product quality management
Product quality managementProduct quality management
Product quality management
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 
04 projectintegrationmanagement
04 projectintegrationmanagement04 projectintegrationmanagement
04 projectintegrationmanagement
 
209560525-PMP-Study-Sheet.pdf
209560525-PMP-Study-Sheet.pdf209560525-PMP-Study-Sheet.pdf
209560525-PMP-Study-Sheet.pdf
 
1. project integration management
1. project integration management1. project integration management
1. project integration management
 
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
Project Planning, Scheduling and Preparation of Quality Assurance Control Doc...
 
SPM PPT.pptx
SPM PPT.pptxSPM PPT.pptx
SPM PPT.pptx
 
Topic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdfTopic 6 - Project Integration Management.pdf
Topic 6 - Project Integration Management.pdf
 
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdfprojectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
projectplanningandprojectworkplan-130828212658-phpapp02 (1).pdf
 
Project planning and project work plan
Project planning and project work planProject planning and project work plan
Project planning and project work plan
 
8.2 Manage Quality
8.2 Manage Quality8.2 Manage Quality
8.2 Manage Quality
 
Topic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdfTopic 11 - Project Schedule Management.pdf
Topic 11 - Project Schedule Management.pdf
 
BSBMGT517 Manage operational planPart C– Project Managing an op.docx
BSBMGT517 Manage operational planPart C– Project Managing an op.docxBSBMGT517 Manage operational planPart C– Project Managing an op.docx
BSBMGT517 Manage operational planPart C– Project Managing an op.docx
 

Kürzlich hochgeladen

Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证jdkhjh
 
Motivational theories an leadership skills
Motivational theories an leadership skillsMotivational theories an leadership skills
Motivational theories an leadership skillskristinalimarenko7
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingGiuseppe De Simone
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramCIToolkit
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)jennyeacort
 
Management and managerial skills training manual.pdf
Management and managerial skills training manual.pdfManagement and managerial skills training manual.pdf
Management and managerial skills training manual.pdffillmonipdc
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchRashtriya Kisan Manch
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Giuseppe De Simone
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsCIToolkit
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionCIToolkit
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsCIToolkit
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...CIToolkit
 

Kürzlich hochgeladen (20)

sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
原版1:1复刻密西西比大学毕业证Mississippi毕业证留信学历认证
 
Motivational theories an leadership skills
Motivational theories an leadership skillsMotivational theories an leadership skills
Motivational theories an leadership skills
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
Shaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful ThinkingShaping Organizational Culture Beyond Wishful Thinking
Shaping Organizational Culture Beyond Wishful Thinking
 
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why DiagramBeyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
Beyond the Five Whys: Exploring the Hierarchical Causes with the Why-Why Diagram
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
Call Us🔝⇛+91-97111🔝47426 Call In girls Munirka (DELHI)
 
Management and managerial skills training manual.pdf
Management and managerial skills training manual.pdfManagement and managerial skills training manual.pdf
Management and managerial skills training manual.pdf
 
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan ManchFarmer Representative Organization in Lucknow | Rashtriya Kisan Manch
Farmer Representative Organization in Lucknow | Rashtriya Kisan Manch
 
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
Effective learning in the Age of Hybrid Work - Agile Saturday Tallinn 2024
 
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement RoadmapsFrom Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
From Goals to Actions: Uncovering the Key Components of Improvement Roadmaps
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
How-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem ResolutionHow-How Diagram: A Practical Approach to Problem Resolution
How-How Diagram: A Practical Approach to Problem Resolution
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Measuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield MetricsMeasuring True Process Yield using Robust Yield Metrics
Measuring True Process Yield using Robust Yield Metrics
 
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
Paired Comparison Analysis: A Practical Tool for Evaluating Options and Prior...
 

Pmbok 5th executing process group

  • 1. Executing Process Group Project Management Processes PMBOK 5th edition Hossam Maghrabi,PMP
  • 2. Executing Process Group & Project Boundaries
  • 3. Executing Process Group & Knowledge Areas This Process Group involves Coordinating People & Resources, Managing Stakeholder Expectations, as well as Integrating & Performing the Project’s Activities accordance with the project management plan. The results may require Planning Updates & Re-Baselining. A large portion of the Project’s Budget will be expended in performing the processes of this Process Group.
  • 4. Direct and Manage Project work: Data Flow Diagram The process of Leading & Performing Project’s Work that defined in the project management plan & Implementing Approved Changes To Achieve the Project’s Objectives.
  • 5. Direct and Manage Project work: General Note: - The project manager, along with the project management team, - Directs the Performance of the planned project activities and Manages the various technical & organizational interfaces that exist within the project. - Manage any unplanned activities and determine the appropriate course of action. - During project execution, The Work Performance Data is collected and appropriately actioned and communicated. It includes information about the completion status of deliverables and other relevant details about project performance. Which used as an input to the Monitoring and Controlling Process Group. - All Project Changes & the Implementation of Approved Changes & its impacts Require to be reviewed for taking the proper actions, • Corrective action - An intentional activity that realigns the performance of the project work with the project management plan. • Preventive action - An intentional activity that ensures the future performance of the project work is aligned with the project management plan. • Defect repair - An intentional activity to modify a nonconforming product or product component. • Updates - Changes to formally controlled project documents, plans, etc.,.
  • 6. - Direct and Manage Project Work Activities include, 1. Create project deliverables, 2. Manage & Train the Project’s team members, 3. Obtain, Manage & Use Resources -Materials, Tools, Equipment, & Facilities-, 4. Implement the planned Methods & Standards, 5. Establish and Manage Project Communication Channels, both External & Internal, 6. Generate Work Performance Data to facilitate Forecasting -Cost, Schedule, Technical & Quality Progress & Status- 7. Issue change requests and implement approved changes, 8. Manage risks and implement risk response activities, 9. Manage sellers and suppliers, 10. Manage Stakeholders & their Engagement, 11. Collect & document Lessons Learned, 12. Implement Approved Process Improvement Activities, , , , , Direct and Manage Project work: General Note:
  • 7. Direct and Manage Project work: Inputs 1. Project Management Plan - 2. Approved Change Requests - The output of Perform Integrated Change Control process, and include those requests reviewed and approved for implementation by the change control board (CCB). 3. Enterprise Environmental Factors - – Structure & Culture of Organizations, Customer & Sponsor, – Infrastructure & Personnel administration, – Stakeholder risk tolerances - For example allowable cost overrun percentage -, – Project management information system , , , 4. Organizational Process Assets - – Standardized Guidelines & Work Instructions, – Communication media, record retention, and security requirements, – Issue and defect management procedures, – Project files from previous projects, – Issue and defect management database(s) containing historical
  • 8. Direct and Manage Project work: Tools & Techniques (T&T) 1. Expert Judgment, Used to assess the inputs needed to direct and manage execution of the project management plan. 2. Project Management Information System, It is part of the environmental factors, provides access to tools, such as a scheduling tool, a work authorization system, a configuration management system, an information collection and distribution system, or interfaces to other online automated systems. Automated gathering and reporting on key performance indicators (KPI) can be part of this system. 3. Meetings, – Meetings tend to be one of three types - Information exchange; Brainstorming, option evaluation, or design; Decision making – – Meetings should be prepared with a well-defined agenda, purpose, objective, and time frame and should be appropriately documented with meeting minutes and action items. – Meeting Minutes should be stored as defined in the project management plan. – Meetings are most effective when all participants can be face-to-face in the same location. – Virtual Meetings generally require additional preparation and organization to achieve the same effectiveness of a face-to-face meeting.
  • 9. Direct and Manage Project work: Outputs 1. Deliverables, 2. Work Performance Data, Examples of work performance data include work completed, key performance indicators, technical performance measures, start and finish dates of schedule activities, number of change requests, number of defects, actual costs, and actual durations, etc. 3. Change Requests, Include Corrective action, Preventive action, Defect repair & Updates. 4. Project Management Plan Updates, 5. Project Documents Updates, Ex. Requirements documentation, Project logs, Risk register, and Stakeholder register
  • 10. Perform Quality Assurance: Data Flow Diagram The process of Auditing the Quality Requirements & the results from Quality Control Measurements To ensure that appropriate Quality Standards & Operational Definitions are used. It Facilitates the Improvement of quality processes
  • 11. Perform Quality Assurance: General Note: Perform Quality Assurance is an execution process that, - Uses Data Created During Plan Quality Management & Control Quality processes. - Implements a Set of Planned & Systematic Acts & Processes for, I. Being certain about quality by preventing defects through the planning processes or by inspecting out defects during the work-in-progress stage of implementation. II. Building a confidence that A Future Output or an Unfinished Output - Work in Progress - will be completed in a manner that meets the specified requirements and expectations. III. Providing an umbrella for Continuous Process Improvement for improving the quality of all processes to Reduces Waste & Eliminates Activities that do Not Add Value which increase levels of Efficiency & Effectiveness. The Prevention & Inspection aspects of quality assurance should have a demonstrable influence on the Project Management. Quality Assurance work will fall under the Conformance Work Category in the Cost Of Quality framework.
  • 12. Perform Quality Assurance: Inputs 1. Quality Management Plan - Describes the quality assurance and continuous process improvement approaches for the project. 2. Process Improvement Plan. 3. Quality Metrics -Provide The Attributes That Should Be Measured & The Allowable Variations. 4. Quality Control Measurements - The Results of Control Quality Activities. They are used to analyze and evaluate the quality of the processes of the project against the standards of the performing organization or the requirements specified. 5. Project Documents - Project documents may influence quality assurance work and should be monitored within the context of a system for configuration management.
  • 13. Perform Quality Assurance: Tools & Techniques (T&T) 1. Quality Management and Control Tools - Plan Quality Management & Control Quality processes Tools and Techniques plus other tool like as the following, I. Affinity diagrams - Is similar to mind-mapping techniques in that they are used to generate ideas that can be linked to form organized patterns of thought about a problem. For example, The creation of the WBS may be enhanced by using the affinity diagram to give structure to the decomposition of scope. II. Process decision program charts (PDPC). Used to understand a goal in relation to the steps for getting to the goal. It’s useful as a method for contingency planning because it aids teams in anticipating intermediate steps that could derail achievement of the goal.
  • 14. Perform Quality Assurance: Tools & Techniques (T&T) 1. Quality Management and Control Tools – III. Interrelationship digraphs - An adaptation of relationship diagrams - Provide a process for creative problem solving in moderately complex scenarios that possess intertwined logical relationships for up to 50 relevant items. It may be developed from data generated in other tools such as the affinity diagram, the tree diagram, or the fishbone diagram. IV. Tree diagrams - Systematic diagrams - Are useful in visualizing the parent-to-child relationships in any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship, such as the WBS, RBS , and OBS. V. Prioritization matrices - Identify the key issues and the suitable alternatives to be prioritized as a set of decisions for implementation.
  • 15. Perform Quality Assurance: Tools & Techniques (T&T) 1. Quality Management and Control Tools - VI. Activity network diagrams - Previously known as arrow diagrams - They include both the AOA (Activity on Arrow) and, most commonly used, AON (Activity on Node) formats of a network diagram. Activity network diagrams are used with project scheduling methodologies such as program evaluation and review technique (PERT), critical path method (CPM), and precedence diagramming method (PDM). VII. Matrix diagrams - A quality management and control tool used to perform data analysis within the organizational structure created in the matrix. The diagram show the strength of relationships between factors, causes, and objectives that exist between the rows and columns that form the matrix.
  • 16. Perform Quality Assurance: Tools & Techniques (T&T) 2. Quality Audits - A structured, independent process to determine if project activities comply with organizational and project policies, processes, and procedures. – The objectives of a quality audit may include: - Identify all good and best practices being implemented; - Identify all nonconformity, gaps, and shortcomings; - Share good practices introduced or implemented in similar projects in the organization and/or industry; - Proactively offer assistance in a positive manner to improve implementation of processes to help the team raise productivity; - Highlight contributions of each audit in the lessons learned repository of the organization. Quality audits may be Scheduled or Random, and may be conducted by Internal or External auditors. 3. Process Analysis – Follows the steps outlined in the process improvement plan to identify needed improvements. It includes root cause analysis—a specific technique used to identify a problem, discover the underlying causes that lead to it, and develop preventive actions.
  • 17. Perform Quality Assurance: Outputs 1. Change Requests - used to take corrective action ,preventive action, or to perform defect repair to allow full consideration of the recommended improvements. 2. Project Management Plan Updates. 3. Project Documents Updates - Quality audit reports, Training plans..... 4. Organizational Process Assets Updates - The organization’s Quality Standards & the Quality Management System….
  • 18. Manage Communications: Data Flow Diagram The process of creating, collecting, distributing, storing, retrieving, and the ultimate disposition of project information in accordance to the communications management plan. It enables an efficient and effective communications flow between project stakeholders.
  • 19. Manage Communications: Inputs 1. Communications Management Plan - Describes how project communications will be planned, structured, monitored, and controlled. 2. Work Performance Reports - A collection of project performance and status information that may be used to facilitate discussion and to create communications. It is important that reports be comprehensive, accurate, and available in a timely manner. 3. Enterprise Environmental Factors. 4. Organizational Process Assets.
  • 20. 1. Communication Technology - Choosing of Communication Technology -. Technology is nothing more than a tool, and depending upon the project need, it might be the use of the email, teleconferencing, blog, website, forums etc. All communication tools should be tailored to suit the requirements of each project. 2. Communication Models - Choosing of Communication Models -. To ensure that the choice of the communication model is appropriate for the project & any barriers (noise) are identified and managed in order to an effective and efficient communications process. 3. Communication Methods - Oral , Written , Body Language - To ensure that the information that has been created & distributed has been received and understood to enable response and feedback. 4. Information Management Systems - IMS - 5. Performance Reporting - Include, Analysis of past performance, Analysis of project forecasts, Current status of risks and issues, Work completed during the period, Work to be completed in the next period, Summary of changes approved in the period, and Other relevant information, which is reviewed and discussed. Manage Communications: Tools & Techniques (T&T)
  • 21. Manage Communications: Outputs 1. Project Communications - may include, performance reports, deliverables status, schedule progress, and cost incurred. They can influenced by factors such as, the urgency and impact of the message, its method of delivery, and level of confidentiality. 2. Project Management Plan Updates - Provides information on project baselines, communications management, and stakeholder management. Each of these areas may require updates based upon the current performance of the project against the Performance measurement Baseline (PMB). Performance measurement Baseline (PMB) is an approved plan for the project work to which the project execution is compared, and deviations are measured for management control. It integrates scope, schedule, and cost parameters of a project, & may also include technical and quality parameters. 3. Project Documents Updates - Issue log, Project schedule, Project funding requirements -. 4. Organizational Process Assets Updates - Stakeholder notifications, Project reports, Project records, Feedback from stakeholders, Lessons learned documentation.
  • 22. Acquire Project Team: Data Flow Diagram The process of Confirming Human Resource Availability & Obtaining the Team Necessary to Complete Project Activities. Consists of Outlining & Guiding the Team Selection & Responsibility Assignment to obtain a successful team.
  • 23. Acquire Project Team: General Note: The following factors should be Considered during the process of Acquiring The Project Team & Planned for in The Planning Stages of the Project: 1. The Project Manager or Project Management Team should Effectively Negotiate & Influence Others who are in a position To Provide the Required Human Resources for the project. 2. Failure to Acquire the Necessary Human Resources for the project may affect Project Schedules, Budgets, Customer Satisfaction, Quality, & Risks. The project manager or project management team will be required to reflect the impact of any unavailability of required human resources in the project schedule , , , , , , & the other project management plans. 3. Insufficient Human Resources or Capabilities Decrease the Probability of Success and, in a worst case scenario, Could Result in Project Cancellation. 4. If the Human Resources are Not Available due to constraints, such as economic factors or previous assignments to other projects, the project manager or project team may be required to assign alternative resources, perhaps with lower competencies, Provided there is No Violation of legal, regulatory, mandatory, or other specific criteria.
  • 24. Acquire Project Team: Inputs 1. Human Resource Management Plan - Provides guidance for Identifying , Staffing, Managing, & Releasing the Project Team members. It includes, I. Roles and responsibilities that define the positions, skills, and competencies that the project demands. II. Project organization charts that indicate the number of people needed for the project. III. Staffing management plan that delineate the time periods each project team member will be needed & other information important to engage the project team. 2. Enterprise Environmental Factors. I. Existing information on human resources including availability, competency levels, prior experience, interest in working on the project and their cost rate; II. Personnel Administration Policies, Organizational Structure & Locations. 3. Organizational Process Assets - That influence the Acquire Project Team process.
  • 25. Acquire Project Team: Tools & Techniques (T&T) 1. Pre-assignment - The project team members are selected in advance. This situation can occur if – Some staff assignments are defined within the project charter. – The project is dependent upon the expertise of particular persons. – The project is the result of specific people being identified as part of a competitive proposal. 2. Negotiation Negotiate the Project Staff Assignments with Functional managers, Other project management teams within the performing organization, External organizations, vendors, suppliers, contractors. 3. Acquisition When the performing organization is unable to provide the staff needed to complete a project, the required services may be Acquired From Outside Sources.
  • 26. Acquire Project Team: Tools & Techniques (T&T) 4. Virtual Teams -A Groups of people with a shared goal who fulfill their roles with little or no time spent meeting face to face. 5. Multi-Criteria Decision Analysis - A valuable tool that we can apply to many complex decisions. It is most applicable to solving problems that are characterized as a choice among alternatives. – Examples of selection criteria that can be used to score team members:  Availability, Cost , Experience, , Knowledge, Skills.  Ability - The Team Member has the competencies needed by the project. -.  Attitude - The ability to work with others as a cohesive team -.  International factors - Consider team member location, time zone & communication capabilities.
  • 27. Acquire Project Team: Outputs 1. Project Staff Assignments - – The project is staffed When Appropriate People have been Assigned to the Team. The Documentation of Project Staff Assignments can include a Project Team Directory, Memos to Team Members, & names inserted into other parts of the project management plan, such as Project Organization Charts & Schedules. 2. Resource Calendars - Document the time periods that each project team member is available to work on the project. Creating a Reliable Schedule depends on having a good understanding of each person’s availability & schedule constraints, including time zones, work hours, vacation time, local holidays, and commitments to other projects. 3. Project Management Plan Updates - – When gaps occur, The Project Management Plan needs to be updated to change the team structure, roles, or responsibilities. Ex. The person assigned to a predefined role may not fulfill all staffing requirements outlined in the human resource management plan.
  • 28. Develop Project Team: Data Flow Diagram The process of Improving Competencies, Team Member Interaction, & Overall Team Environment to Enhance Project Performance. It results in Improve Teamwork, Enhance People Skills & Competencies, Motivate Employees, Reduce Staff Turnover Rates, & Improve Overall Project Performance.
  • 29. Develop Project Team: General Note: 1. Project Manager - – Should Acquire Skills To Identify, Build, Maintain, Motivate, Lead, & Inspire Project Teams To Achieve High Team Performance & Meet the Project’s Objectives. – Should Continually Motivate Their Team By Providing Challenges & Opportunities, Providing Timely Feedback & Support as needed, plus Recognizing & Rewarding Good Performance. – Should Request Management Support and/or Influence the Appropriate Stakeholders To Acquire the Resources needed to Develop Effective Project Teams. – Responsible for Create an Environment that Facilitates Teamwork & Developing an Effective Project Teams. – Should Capitalize on Cultural Differences Creating a Dynamic, Cohesive, & Collaborative Team Culture To Improve Individual & Team productivity, Team Spirit, & Cooperation Plus Allow Cross Training & Mentoring Between Team Members to Share Knowledge & Expertise. 2. Project Communication - High team performance can be achieved by using open and effective communication, creating team building opportunities, developing trust among team members, managing conflicts in a constructive manner, and encouraging collaborative problem solving and decision making.
  • 30. Develop Project Team: Inputs 1. Human Resource Management Plan - Provides guidance on how project human resources should be identified, staffed, managed, and eventually released. 2. Project Staff Assignments - Identify the people who are on the team / List of project team members. 3. Resource Calendars - Identify times when the project team members can participate in team development activities.
  • 31. Develop Project Team: Tools & Techniques (T&T) 1. Interpersonal Skills -soft skills - A behavioral competencies that include proficiencies such as communication skills, emotional intelligence, conflict resolution, negotiation, influence, team building, and group facilitation. Ex. the project management team can use emotional intelligence to reduce tension and increase cooperation by identifying, assessing, and controlling the sentiments of project team members, anticipating their actions, acknowledging their concerns, and following up on their issues. 2. Training (in-house or external trainers) - Scheduled training takes place in the human resource management plan. Unplanned training takes place as a result of observation, conversation, and project performance appraisals conducted during the controlling process of managing the project team. Training costs could be included in the project budget, or supported by performing organization if the added skills may be useful for future projects. 3. Ground Rules - A clear expectations regarding acceptable behavior by project team members. All project team members share responsibility for enforcing the rules once they are established. Discuss ground rules in areas such as code of conduct, communication, working together, or meeting etiquette allows team members to discover values that are important to one another.
  • 32. 4. Team-Building Activities 5. Colocation -Tight Matrix-Involves placing many or all of the most active project team members in the same physical location to enhance their ability to perform as a team. While colocation is considered a good strategy, the use of virtual teams can bring benefits such as the use of more skilled resources, reduced costs, less travel, and relocation expenses and the proximity of team members to suppliers, customers, or other key stakeholders. Develop Project Team: Tools & Techniques (T&T)
  • 33. 6. Recognition and Rewards - Part of the team development process involves recognizing and rewarding desirable behavior. People are motivated if they feel they are valued in the organization and this value is demonstrated by the rewards given to them. A good strategy for project managers is to give the team recognition throughout the life cycle of the project rather than waiting until the project is completed. Develop Project Team: Tools & Techniques (T&T)
  • 34. 7. Personnel Assessment Tools - Give the project manager and the project team an insight into areas of strength and weakness. – Tools such as attitudinal surveys, specific assessments, structured interviews, ability tests, and focus groups. – These tools help project managers assess the team preferences, aspirations, behavior and attitude. Develop Project Team: Tools & Techniques (T&T)
  • 35. Develop Project Team: Outputs 1. Team Performance Assessments - The project management team makes formal or informal assessments of the project team’s effectiveness. – Team performance assessment criteria should be determined by all appropriate parties and incorporated in the Develop Project Team inputs. – The performance of a successful team is measured in terms of technical success according to agreed-upon project objectives (including quality levels), performance on project schedule (finished on time), and performance on budget (finished within financial constraints). – The evaluation of a team’s effectiveness may include indicators such as ( Improvements in skills, Improvements in competencies, Reduced staff turnover rate, Increase team cohesiveness) – As a result of Team performance assessment, the resources and recommendations for team improvement should be well documented and forwarded to the relevant parties. 2. Enterprise Environmental Factors Updates - Personnel administration, Employee training records, and skill assessments.
  • 36. Manage Project Team: Data Flow Diagram The process of influences team behavior, manages conflict, resolves issues, tracking team member performance, providing feedback, & managing team changes to optimize project performance. As a result of managing the project team, change requests are submitted, issues are resolved, input is provided for performance appraisals, & lessons learned are added to the organization’s database.
  • 37. Manage Project Team: Inputs 1. Human Resource Management Plan. 2. Project Staff Assignments. 3. Team Performance Assessments - By continually assessing the project team’s performance, actions can be taken to resolve issues, modify communication, address conflict, and improve team interaction. 4. Issue Log - Issues arise in the course of managing the project team. An issue log can be used to document and monitor who is responsible for resolving specific issues by a target date. 5. Work Performance Reports - Provide documentation about the current project status compared to project forecasts. It include results from schedule control, cost control, quality control, and scope validation. The information from performance reports and related forecasts assists in determining future human resource requirements, recognition and rewards, and updates to the staffing management plan. 6. Organizational Process Assets - Ex. Certificates of appreciation, Newsletters, Websites, Bonus structures, Corporate clothes, & Other organizational perquisites.
  • 38. Manage Project Team: Tools & Techniques (T&T) 1. Observation and Conversation -Used to stay in touch with the work & attitudes of project team members. The project management team monitors progress toward project deliverables, accomplishments that are a source of pride for team members, and interpersonal issues. 2. Project Performance Appraisals – Objectives for conducting performance appraisals during the course of a project can include clarification of roles and responsibilities, constructive feedback to team members, discovery of unknown or unresolved issues, development of individual training plans, & the establishment of specific goals for future time periods. – The need for formal or informal project performance appraisals depends on the length of the project, complexity of the project, organizational policy, labor contract requirements, and the amount and quality of regular communication.
  • 39. Manage Project Team: Tools & Techniques (T&T) 3. Conflict Management.
  • 40. Manage Project Team: Tools & Techniques (T&T) 4. Interpersonal Skills. It is important to communicate the vision and inspire the project team to achieve high performance.
  • 41. Manage Project Team: Outputs 1. Change Requests - Following is an examples, I. Staffing Changes, whether by choice or by uncontrollable events, may include moving people to different assignments, outsourcing some of the work, and replacing team members who leave. This will affect the project management plan(Schedule , Budget ……) through integration change control process. II. Preventive actions like Cross training to reduce problems during project team member absences and additional role clarification to ensure all responsibilities are fulfilled. 2. Project Management Plan Updates -Human Resource Management plan,,,,,,. 3. Project Documents Updates - Issue log, Roles description, Project staff assignments,,,,,. 4. Enterprise Environmental Factors Updates -Input to organizational performance appraisals, & Personnel skill updates. 5. Organizational Process Assets Updates - Historical information and lessons learned documentation, Templates, and Organizational standard processes.
  • 42. Manage Stakeholder Engagement: Data Flow Diagram Communicating & working with stakeholders To Meet their needs/expectations, address issues as they occur, & foster appropriate stakeholder engagement in project activities throughout the project life cycle. It allows the project manager to increase support and minimize resistance from stakeholders for increasing the chances to achieve project success.
  • 43. Manage Stakeholder Engagement: General Note: The ability of Stakeholders to Influence the project is typically highest during the initial stages and gets progressively lower as the project progresses. - Managing Stakeholder Engagement helps to increase the probability of project success by ensuring that stakeholders clearly understand the project goals, objectives, benefits, and risks. Which enables stakeholder to be active supporters of the project and to help guide activities and project decisions. - By Anticipating People’s Reactions to the project, proactive actions can be taken to win support or minimize negative impacts and Decreases the risk of the project failing to meet its goals and objectives. - The project manager is responsible for Managing Stakeholder Engagement which involves activities such as, 1. Engaging Stakeholders at appropriate project stages to obtain or confirm their continued commitment to the success of the project, 2. Managing Stakeholder Expectations through negotiation and communication, Ensuring Project Goals are Achieved, 3. Addressing Potential Concerns that have not yet become issues & Anticipating Future Problems that may be raised by stakeholders, 4. Clarifying and Resolving Issues that have been identified.
  • 44. Manage Stakeholder Engagement: Inputs 1. Stakeholder Management Plan - Provides guidance on how the various stakeholders can be best involved in the project. 2. Communications Management Plan - Provides guidance and information on managing stakeholder expectations. Ex. Stakeholder communications requirements, Information to be communicated, including language, format, content, and level of detail, Reason for distribution of information, Person or groups who will receive information, and Escalation process. 3. Change Log - Used to document changes that occur during a project. These changes - & their impact on the project in terms of time, cost, and risk - are communicated to the appropriate stakeholders. 4. Organizational Process Assets.
  • 45. Manage Stakeholder Engagement: Tools & Techniques (T&T) 1. Communication Methods - Oral , Written , Body Language / Formal , Unformal -. - Based on the stakeholders’ communication requirements, the project manager decides how, when, and which of these communication methods are to be used in the project. - The methods of communication identified for each stakeholder in the communications management plan are utilized during stakeholder engagement management. 2. Interpersonal Skills - - Apply interpersonal skills to manage stakeholders’ expectations, Building trust, Resolving conflict, Active listening, Overcoming resistance to change. 3. Management Skills - - Apply management skills to Coordinate and Harmonize the group toward accomplishing the project objectives through the following activities, Facilitate consensus, Influence people to support the project, Negotiate agreements to satisfy the project needs, Modify organizational behavior to accept the project outcomes.
  • 46. Manage Stakeholder Engagement: Outputs 1. Issue Log - This log is updated as new issues are identified and current issues are resolved. 2. Change Requests - Managing stakeholder engagement may result in a change request to the product or the project, corrective or preventive actions to the project itself or to the interaction with the impacted stakeholders. 3. Project Management Plan Updates Ex. Some communications may no longer be necessary, an ineffective communication method may be replaced by another method, or a new communication requirement may be identified. Ex. It may be determined that a stakeholder has additional informational needs. 4. Project Documents Updates Ex. The stakeholder register. 5. Organizational Process Assets Updates - Ex. Stakeholder notifications, Project reports, Project presentations, Project records, Feedback from stakeholders, Lessons learned documentation.
  • 47. Conduct Procurements: Data Flow Diagram The process of Obtaining Seller Responses, Selecting a Seller, & Awarding a Contract. It provides alignment of internal and external stakeholder expectations through established agreements.
  • 48. Conduct Procurements: General Note: The effort of the buyer & seller in this process is to Collectively Prepare a Procurement Statement of Work that will satisfy the requirements of the project. The parties will then negotiate a final contract for award. During the Conduct Procurements process, 1. The team will Receive Bids or Proposals & will Apply Previously Defined Selection Criteria to Select One or more Sellers who are qualified to perform the work & acceptable as a seller. 2. On major procurement items, the overall process of requesting responses from sellers and evaluating those responses can be repeated. 3. A short list of qualified sellers can be established based on a preliminary proposal. 4. A more detailed evaluation can then be conducted based on a more specific and comprehensive requirements document requested from the sellers on the short list.
  • 49. Conduct Procurements: Inputs 1. Procurement Management Plan - Describes how the procurement processes will be managed from developing procurement documentation through contract closure. 2. Procurement Documents - Provide an audit trail for contracts and other agreements. 3. Source Selection Criteria - Include information on the supplier’s required capabilities, capacity, delivery dates, product cost, life-cycle cost, technical expertise, and the approach to the contract. 4. Seller proposals - Prepared in response to a procurement document package. They form the basic information that will be used by an evaluation body to select one or more successful bidders (sellers). 5. Project Documents - Ex. The risk-related contract decisions included within the risk register. 6. Make-or-Buy Decisions. 7. Procurement Statement of Work - It is a critical component of the procurement process and can be modified as needed through this process until a final agreement is in place (Specifications, Quantity desired, Quality levels…..). It Provides suppliers with a clearly stated set of goals, requirements, and outcomes from which they can provide a quantifiable response. 8. Organizational Process Assets.
  • 50. Conduct Procurements: Tools & Techniques (T&T) The Tools and Techniques described here may be used alone or in combination with select sellers. 1. Bidder Conferences - Contractor Conferences, Vendor Conferences, & Pre-Bid Conferences - They are meetings between the buyer and all prospective sellers, Prior to submittal of a Bid or Proposal, To Ensure That all prospective sellers have a clear and common understanding of the procurement requirements, & that no bidders receive preferential treatment. To be fair, buyers should take great care to ensure that all prospective sellers hear every question from any individual prospective seller and every answer from the buyer. Responses to questions can be incorporated into the procurement documents as amendments. 2. Proposal Evaluation Techniques - A formal evaluation review process will be defined by the buyer’s procurement policies. 3. Independent Estimates - The procuring organization may elect to either prepare its own independent estimate, or have an estimate of costs prepared by an outside professional estimator, To Serve As a Benchmark on proposed responses. Significant differences in cost estimates can be an indication that the procurement statement of work was deficient, ambiguous, and/or that the prospective sellers either misunderstood or failed to respond fully to the procurement statement of work.
  • 51. Conduct Procurements: Tools & Techniques (T&T) 4. Expert Judgment - The evaluation of proposals may be accomplished by a multi- discipline review team with expertise in each of the areas covered by the procurement documents and proposed contract. Such as contracting, legal, finance, accounting, engineering, design, research, development, sales, and manufacturing. 5. Advertising - Placing advertisements for procurement to expand the lists of potential sellers or because the government jurisdictions require public advertising. 6. Analytical Techniques - Help organizations identify the readiness of a vendor to provide the desired end state, determine the cost expected to support budgeting, and avoid cost overruns due to changes. Ex. By Examining Past Performance Information, teams may Identify Areas that may have more risk & that need to be monitored closely to ensure success of the project. 7. Procurement Negotiations -Help in Clarify the structure, Requirements, & other terms of the purchases so that mutual agreement can be reached prior to signing the contract. The Project Manager & other Project Management Team may not be the lead negotiator on procurements. They may be present during negotiations to provide assistance & clarification. For Complex Procurement Items, contract negotiation can be an independent process with inputs (e.g., issues or an open items listing) and outputs (e.g., documented decisions) of its own. For Simple Procurement Items, the terms and conditions of the contract can be previously set and nonnegotiable, and only need to be accepted by the seller.
  • 52. Conduct Procurements: Outputs 1. Selected Sellers - Those who have been judged to be in a competitive range based upon the outcome of the proposal or bid evaluation, & who have negotiated a draft contract that will become the actual contract when an award is made. Final approval of all complex, high-value, high-risk procurements will generally require organizational senior management approval prior to award. 2. Agreements - A Procurement Agreement includes terms and conditions, and may incorporate other items that the buyer specifies regarding what the seller is to perform or provide. Include, Statement of work or deliverables, Schedule baseline, Performance reporting, Period of performance, Roles and responsibilities, Seller’s place of performance, Pricing, Payment terms, Place of delivery, Inspection and acceptance criteria, Warranty, Product support, Limitation of liability, Fees and retainer, Penalties, Incentives, Insurance and performance bonds, Subordinate subcontractor approvals, Change request handling, & Termination clause and alternative dispute resolution (ADR) mechanisms. The project management team is responsible for making sure that all agreements meet the specific needs of the project while adhering to organizational procurement policies. The ADR method can be decided in advance as a part of the procurement award.
  • 53. Conduct Procurements: Outputs 3. Resource Calendars - The quantity and availability of contracted resources and those dates on which each specific resource or resource group can be active or idle are documented. 4. Change Requests. 5. Project Management Plan Updates - Any impacted baseline plans. 6. Project Documents Updates - Requirements documentation, Requirements traceability documentation, Risk register, Stakeholder register