4. Scope Management plan
Process for preparing a project scope
statement
Process that enables the creation of
the WBS from the detailed project
scope statement
Process that establishes how the
scope baseline will be approved and
maintained
Process that specifies how formal
acceptance of the completed project
deliverables will be obtained
Requirement Management plan
How requirements activities will be
planned, tracked and reported
Requirements prioritization process
Metrics that will be used and the
rationale for using them
19. Plan Schedule Management
• Project schedule model development
• Release and iteration length.
• Level of accuracy
• Units of measure
• Control thresholds
• Rules of performance measurement
• Reporting formats.
30. Cost Management Plan
Units of measure
Level of precision
Level of accuracy
Control thresholds
Rules of performance measurement
Reporting formats