SlideShare ist ein Scribd-Unternehmen logo
1 von 59
www.GLOBALSKILLUP.com
PMP® Certification Training!
www.GLOBALSKILLUP.com
2
CONNECT WITH US
www.GLOBALSKILLUP.com
Time Management
Chapter 6
www.GLOBALSKILLUP.com
Chapter 6
Objectives
Understand the different Time Management
Processes
Their Inputs, Tools and Techniques,
Outputs
This chapter entails one to
understand the various Time
Management aspects
required to understand the
customer delivery timeline
needs.
Also, how the timeline will
be approached, managed
and finally honored –
making the project
successful!
www.GLOBALSKILLUP.com
Project Time Management includes processes to ensure the schedule is defined, managed,
controlled and has updated schedule baseline to meet project timeline.
Establishing a Project schedule involves using the Project Information, Project Scheduling
Methods & Tools.
Most common scheduling methods include Critical Path Method (CPM) & Critical Chain
Method (CCM).
Schedule may be represented in many a ways including the Bar Chart, Network Diagram
and/or Activity List.
Knowledge Area: Time Management
www.GLOBALSKILLUP.com
There are 7 Time Management processes:
1. Plan Schedule Management
Establishing Project Schedule in Schedule
Management Plan Document which will be used
across project to control timelines as project
evolves and changes occur.
2. Define Activities
Breaking down the larger chunks of scope into
actionable small activities using the WBS by
defining project activities
3. Sequence Activities
Establishing the relationships between the
defined project activities to ensure the sequence
of activities are done in rightful manner
4. Estimate Activity Resources
What type and amount of estimated resources
are required to accomplish sequenced activity
5. Estimate Activity Durations
How long will it take to ensure the estimated
resources perform the activity assigned
6. Develop Schedule
Based on all the available information from
defined activities to sequence activities to
estimate resource & durations will aid to arrive at
develop schedule
7. Control Schedule
Monitoring and Controlling the project schedule
across the project duration w.r.t schedule
baseline and achieve the project objectives
Knowledge Area: Time Management
www.GLOBALSKILLUP.com
6.1 Plan Schedule Management
Inputs
• Project
Management
Plan
• Project Charter
• Requirements
Documentation
• Organizational
Process Assets
Tools &
Techniques
• Expert
Judgment
• Analytical
Techniques
• Meetings
Outputs
• Schedule
Management
Plan
•Integration
•Develop Project Management Plan
•Scope
•Plan Scope Management
•Collect Requirements
•Define Scope
•Create WBS
•Time
•Plan Schedule Management
•Define Activities
•Sequence Activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
•Cost
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Quality
•Plan Quality Management
•Human Resource
•Plan HR Management
•Communications
•Plan Communications Management
•Risk
•Plan Risk Management
•Identify Risks
•Perform Qualitative Risk Analysis
•Perform Quantitative Risk Analysis
•Plan Risk Responses
•Procurement
•Plan Procurement Management
•Stakeholder
•Plan Stakeholder Management
Planning Process
Is the process to ensure project schedule is managed from
beginning of the project to the end of the project with a defined
approach.
Key benefit of this means to provide a guidance and oversight
on how the project schedule is to be managed with an upfront
defined schedule thresholds.
The schedule management plan also defines how schedule
contingencies will be reported and assessed over the course of
the project delivery.
www.GLOBALSKILLUP.com
This may involve options to estimate and schedule the project using
the Scheduling methodology, scheduling Tools and techniques,
estimation approaches, formats and project management software.
Approaches are defined to ensure speedy delivery while ensuring
the project risk is managed well.
Crashing or Fast Tracking are common schedule compression
techniques using which the work is parallelized. While delivery of
the work in parallel is beneficial this may also increase the risk on
the project. These decisions are to be well explained to the relevant
stakeholders as the case may be.
In some cases, organizations with well established frameworks
ensure to have organization policies and procedures with defined
techniques to employ such as:
Rolling wave planning
Leads and lags
Alternative analysis
Methods for reviewing schedule performance
Analytical Techniques
www.GLOBALSKILLUP.com
Schedule Management Plan defines the criteria
and activities for developing, monitoring and
controlling project schedule. It establishes the
following:
Project Schedule Model Development →
Scheduling Methodology & Scheduling Tool to be
used
Level of Accuracy → Extent of the estimates
supposed to be accurate. Include any contingency
for estimation gaps
Units of Measure → What units will be applied,
staff hours, staff days, weeks, meters, liters,
kilometers and so on
Organizational Procedure Links → Links to the
phases, activities from the WBS to ensure
consistency and resulting schedules
Project Schedule Model Maintenance → Define
the updates and changes to the schedule during
the execution phase of the project
Control Thresholds → Percentage deviations
which ensure that the actions are taken for any
threshold value deviations
Rules of Performance Management
EVM (Earned Value Management) rules or
similar performance management rules are
set
How the percentage completion will be
established?
Control Accounts on which the management
review to be performed
EVM techniques applied
SV (Schedule Variance) & SPI (Schedule
Performance Indicator) against the Schedule
baseline
Reporting formats → What reports are required,
Which format and at What frequency
Process descriptions → Any processes which will
administer the schedule performance and
management across the project course
Schedule Management Plan
www.GLOBALSKILLUP.com
6.2 Define Activities
Inputs
• Schedule
Management
Plan
• Scope Baseline
• Enterprise
Environmental
Factors
• Organizational
Process Assets
Tools & Techniques
• Decomposition
• Rolling Wave
Planning
• Expert Judgment
Outputs
• Activity List
• Activity
Attributes
• Milestone List
•Integration
•Develop Project Management Plan
•Scope
•Plan Scope Management
•Collect Requirements
•Define Scope
•Create WBS
•Time
•Plan Schedule Management
•Define Activities
•Sequence Activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
•Cost
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Quality
•Plan Quality Management
•Human Resource
•Plan HR Management
•Communications
•Plan Communications Management
•Risk
•Plan Risk Management
•Identify Risks
•Perform Qualitative Risk Analysis
•Perform Quantitative Risk Analysis
•Plan Risk Responses
•Procurement
•Plan Procurement Management
•Stakeholder
•Plan Stakeholder Management
Planning Process
Define Activities process is performed to ensure the actions are identified
and documented to produce end project deliverables.
Key benefit of this process is to provide an understanding of breaking
down the work packages into activities that can be easily estimated,
scheduled, executed, monitored and controlled.
The purpose of this process is to identify the specific tasks needed to be
done in order to produce the project’s deliverables.
Scope Baseline is used as a starting point to breakdown documented
deliverables even further, as well as a guide to assure that entire scope
of Project is covered, but not extend beyond boundaries of Project.
www.GLOBALSKILLUP.com
Rolling Wave Planning
Rolling wave planning is the iterative planning
technique to plan the immediate work in detail
and subsequent work at higher levels in at
progressive elaboration manner.
As an example, in the early stages of the project
work packages are defined at a higher level for
different phases. However, as we enter the phase
more clarity is available and the work packages
are made granular.
Understand it this way, waves closer to us give
better clarity on what they bring along with them.
Similar to the immediate work at hand, we know
more detailed view of them to accomplish, than
the far away waves or work.
This is a comprehensive list of all activities to be
performed as part of the project.
Each activity is supplemented with an activity
identifier and sufficient detailed scope of work so
as that could be accomplished.
Is Activity List same as WBS?
An activity list is a list of “What we are doing” in
the project to accomplish deliverables.
Whereas a WBS is a list of “What we are
making” in the project as deliverables.
Imagine this as WBS is a high level view of
deliverables and Activity list as a low level view of
the deliverables.
Activity List
www.GLOBALSKILLUP.com
Activity Attributes
Often the activity has just more than
the activity identifier like WBS ID,
Activity label, Activity code, successor
activity code, predecessor activity
code, logical relationship definition,
leads, lags, resource associated, cost
associated, geographic tag, the
project calendar the activity is
assigned, effort type(level of effort,
apportioned effort, discrete effort) and
so on.
All these attributes help bring more
organized and clarity in the
accomplishment of each activity.
A Milestone is an important event of
accomplishment of major work.
These milestone activities are simply
put, the zero duration activities.
They could be either internal to the
organization or external market
commitment requirements.
Milestone List
www.GLOBALSKILLUP.com
6.3 Sequence Activities
Inputs
•Schedule
Management Plan
•Activity List
•Activity Attributes
•Milestone List.
•Scope Statement
•Enterprise
Environmental
Factors
•Organizational
Process Assets
Tools & Techniques
•Precedence
Diagramming
Method (PDM)
•Dependency
Determination
•Leads And Lags
Outputs
•Project Schedule
Network Diagrams
•Project Document
Updates
•Integration
•Develop Project Management Plan
•Scope
•Plan Scope Management
•Collect Requirements
•Define Scope
•Create WBS
•Time
•Plan Schedule Management
•Define Activities
•Sequence Activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
•Cost
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Quality
•Plan Quality Management
•Human Resource
•Plan HR Management
•Communications
•Plan Communications Management
•Risk
•Plan Risk Management
•Identify Risks
•Perform Qualitative Risk Analysis
•Perform Quantitative Risk Analysis
•Plan Risk Responses
•Procurement
•Plan Procurement Management
•Stakeholder
•Plan Stakeholder Management
Planning Process
Activities need to be sequenced or connected with each other
by a relation and dependencies to ensure the proper flow and
completion of the project work considering all the constraints.
This also ensures realistic schedules and efficiency in delivery
of project work since the appropriate leads and lags are added.
All activities other than the very first and very last
activity/milestone, rest all of them need to be connected with
each other.
www.GLOBALSKILLUP.com
PDM is one of the activity sequencing techniques in practice; in which activities are represented in a graphical
manner to show precedence of activities to be accomplished in sequence.
In this technique, activities are represented as Nodes. Also known as AON (Activity on Node).
Most software packages use this type of representation including Microsoft Project.
PDM (Precedence Diagramming Method)
Start
A
B
C
D
E G
H
Finish
www.GLOBALSKILLUP.com
PDM (Precedence Diagramming Method)
Finish to Finish RelationshipStart to Start Relationship
Research Data
Started
Produce Report
Started
Data Transfer
Finished
Migration
Finished
Start to Finish Relationship
Most Rarely Used
Server Installation Started
Vendor Job Finished
Finish to Start Relationship
Most Commonly Used
Draft Manual
Finished
Print Manual
Started
PDM also used logical relationships between activity to activity. Four types of relationships:
www.GLOBALSKILLUP.com
Dependencies can be of different nature.
Mandatory → These are the legally or contractually required or inherent in the nature of work being done.
Hard logic which has to be met at any cost.
Discretionary → These dependencies are at discretion of Project Team. And are the preferred
dependencies based on the best practices of work done in the past or as defined by the SME(Subject
Matter Experts) for an alternate option. Also know as Soft logic which can undergo an alternate option.
External → Dependencies where the project team has to consider the external work done beyond the
project team’s control. This is more rampant in case of Contractual Projects. This is beyond control of
project team.
Internal → Dependencies where project team has to lookup to internal precedence to ensure the previous
work is accomplished. This is in the control of the Project team.
These 4 dependencies can be clubbed in combination:
Mandatory External Dependencies
Mandatory Internal Dependencies
Discretionary External Dependencies
Discretionary Internal Dependencies
Dependency Determination
www.GLOBALSKILLUP.com
Lead Time
Let us understand what a lead is with an example.
For a movie, Activity A(movie shooting) takes 5 Days.
Post the movie shooting, Activity B(mass production)
takes another 10 Days for release. The movie in such a
scenario is produced for release at 5+10=15 days.
Let us now consider a little smart situation. Activity A
takes 5 days. Activity B takes another 10 days for mass
production. However, as the movie is been shot, the
production activities can be started with 3 days in
advance(lead) to completion of movie shooting.
This would mean the new release date of the movie can
be as early as 12 days instead of 15 days with a lead
time of 3 days for production.
Let us understand what a lag is with an example.
For a wooden house construction, Activity A(Procurement
of wood) takes 4 days. Activity B(Construction of house)
takes 6 days. The schedule for the house construction in
such an ideal scenario is 4+6=10 days.
Let us now consider a little practicality, After the wood is
procured, we would want to ideally have the wood
seasoned for 3 days(Lag) during which time, neither the
procurement can be done nor the construction can begin.
This would mean the practical end to end of construction
of wooden house is 4+3+6=13 days. More realistic
sense.
Lag Time
A – 5 Days
B – 10 Days
Lead of 3 Days
Total Duration 2+10=12 Days
A – 4 Days
B – 6 Days
Lag of 3 Days
Total Duration 4+3+6=13 Days
www.GLOBALSKILLUP.com
Pay attention to Tasks where convergence and divergence occurs.
These are critical tasks. Any defects introduced in these tasks or delays
will lead to major quality deficit.
Activity Convergence – Many outputs of
activities converge into one activity making
it critical activity
Activity Divergence – Many outputs will
diverge from this activity making it critical
activity
Activity Activity
Output
Many
Outputs
Input
Many
Inputs
A project is termed highly complex with many activities with convergences and
divergences, not just the many number of tasks on the Project schedule
network.
www.GLOBALSKILLUP.com
As the name suggests it is a graphical representation of the Project Schedule in
a Network format. Though it is usually represented in graphical manner, it is
also accompanied by descriptions for any exceptions represented in the
graphic.
A
B
D
I
C
E
K
J
F
L
G
Start End
H
Exceptions
-----------
-----------
-----------
-----------
Project Schedule Network Diagram
www.GLOBALSKILLUP.com
6.4 Estimate Activity Resources
Inputs
•Schedule
Management Plan
•Activity List
•Activity Attributes
•Resource Calendars
•Risk Register
•Activity Cost
Estimates
•Enterprise
Environmental
Factors
•Organizational
Process Assets
Tools & Techniques
•Expert Judgment
•Alternative Analysis
•Published
Estimating Data
•Bottom Up
Estimating
•Project
Management
Software
Outputs
•Activity Resource
Requirements
•Resource
Breakdown
Structure
•Project Document
Updates
•Integration
•Develop Project Management Plan
•Scope
•Plan Scope Management
•Collect Requirements
•Define Scope
•Create WBS
•Time
•Plan Schedule Management
•Define Activities
•Sequence Activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
•Cost
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Quality
•Plan Quality Management
•Human Resource
•Plan HR Management
•Communications
•Plan Communications Management
•Risk
•Plan Risk Management
•Identify Risks
•Perform Qualitative Risk Analysis
•Perform Quantitative Risk Analysis
•Plan Risk Responses
•Procurement
•Plan Procurement Management
•Stakeholder
•Plan Stakeholder Management
Planning Process
This is the process of estimating based on the type, quantity,
quality of human resources, material resources to arrive at
more accurate estimate(key benefit).
Estimate Activity Resources and Estimate Costs are closely
linked to each other.
For example, a high rise tower construction needs
specialized government approvals and specialized skilled
workers to execute tasks at such a high rise tower. This
means additional cost incurred to procure these resources.
www.GLOBALSKILLUP.com
Activity Cost Estimates are the probable
costs which may be incurred on the
particular activities and summed to arrive at
the project completion cost.
The cost of resources may impact resource
selection to keep the project cost optimal to
respect the triple constraints.
Activity Costs may be direct or indirect :
Direct:
Labor Cost, Materials, Equipment,
Services
Interest Charges, Exchange Rates, Cost
Contingency Reserve
Indirect:
Depends on the performing business
unit and/or Organization
Activity Cost Estimates
www.GLOBALSKILLUP.com
Alternative Analysis
Many activities can be accomplished in more
than one way. Alternative Analysis is the ways of
finding the best optimal manner to accomplish
the activities and project completion.
This includes various skill levels of the resources,
type of resources used, size and performance of
the machines used, manual or automated tools,
make-rent-or-buy decisions and so on.
A make-or-buy analysis results whether work can
best be accomplished by project team or
purchased from contracted sources.
In Practice, these type of decisions are some
times best defined by the organizational culture
and project manager’s decision is limited in
nature. Some organizations prefer to always buy
a new tool instead of development of one. And
some other prefer to develop their own tool
instead of buy. A few also venture out to sell their
own use tools to the market.
Many Organizations have a predefined rate lists,
estimation production chart data, per unit costs
defined for geographies, countries, time zones,
special work days and so on. This type of data is
readily usable to arrive at the estimation.
In this technique, the activity is compared to the
activities for which data exists and the actual cost
or durations of the closest comparable activity is
selected from the data and used as the estimate.
The advantage of this technique is that it is very
accurate when the project conditions match the
conditions under which the published data was
generated.
The disadvantages are that data does not exist
for many activities and that the published data
that does exist is based upon the characteristics
of the organizations who compiled and published
the data.
Published Estimating Data
www.GLOBALSKILLUP.com
Bottom up Estimating
Aggregation of all the bottom most
elements which can be individually
estimated to sum up for estimate is known
as bottom up estimate.
All WBS elements broken down into work
packages and further granular elements
are used to arrive at the bottom up
estimating.
Advantage of such estimate analysis is
that it is highly accurate form of estimate
as the work is better understood.
Disadvantage of such estimate analysis is
that it is time consuming and also may not
be practical at the beginning of the project
since it may not have a decomposed WBS.
Advance in technology has led us to utilize
the software tools to ensure we have more
accurate and reliable estimates based on
the input collaboration of various project
management aspects like scheduling,
risks, optimized resource utilization,
breakdown structures and so on.
Project Management Software
Source Acknowledged: http://www.tenrox.com/
www.GLOBALSKILLUP.com
Defines the list of resources to be applied for any given activity on the project.
Identification of Set of Responsibilities for a Role. Pooling all different roles into
Resource requirements for meeting the Project objectives.
Activity Resource Requirements
It is a structural illustration of resources based on category and type. This is useful
for organizing and reporting project schedule data with resource utilization
information.
Resource Breakdown Structure
Project
Resources
Management
Leads
Analysts
Design
Development
Project
Manager
Sr.
Management
Materials
Notepads Sketch Boards
Marketing
Brochures
Equipment
Computers
Photo Copiers
Project Staff
Architects &
Designers
Developers Quality
Assurance
Control
www.GLOBALSKILLUP.com
6.5 Estimate Activity Duration
Inputs
•Schedule Management Plan
•Activity List
•Activity Attributes
•Activity Resource
Requirements
•Resource Calendars
•Project Scope Statement
•Risk Register
•Resource Breakdown
Structure
•Enterprise Environmental
Factors
•Organizational Process
Assets
Tools & Techniques
•Expert Judgment
•Analogous Estimating
•Parametric Estimating
•Three-Point Estimating
•Group-Decision Making
•Reserve Analysis
Outputs
•Activity Duration
Estimates
•Project Document
Updates
•Integration
•Develop Project Management Plan
•Scope
•Plan Scope Management
•Collect Requirements
•Define Scope
•Create WBS
•Time
•Plan Schedule Management
•Define Activities
•Sequence Activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
•Cost
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Quality
•Plan Quality Management
•Human Resource
•Plan HR Management
•Communications
•Plan Communications Management
•Risk
•Plan Risk Management
•Identify Risks
•Perform Qualitative Risk Analysis
•Perform Quantitative Risk Analysis
•Plan Risk Responses
•Procurement
•Plan Procurement Management
•Stakeholder
•Plan Stakeholder Management
Planning Process
This is one of the most important
process which aids in the overall
estimation of the project size in
terms of duration.
It is the process of estimating the
period taken for each activity to
complete with estimated resources.
May not be possible to estimate
completely at the beginning and may
be progressively elaborated for
accurate estimations.
Assumptions should be called out to
the reviewer. Estimates usually
originate from the person or group
with the most familiarity about the
task at hand. This minimizes
estimation gaps upfront due to
ambiguity of task.
Estimation activity uses multiple
information including activity scope
of work, required resource types,
estimated resource quantities and
resource calendars.
www.GLOBALSKILLUP.com
Example.
For your new bungalow, installing an artificial lawn will take 80 hours of effort.
With one worker who can work 40 hours a week(8 hours a day for 5days) will take 10 work days of duration which is 2 weeks
of elapsed time to complete 80 hours of effort.
With two workers who can work 40 hours a week(8 hours a day for 5days) will take 5 work days of duration which is 1 week
of elapsed time to complete 80 hours of effort.
With four workers who can work 40 hours a week(8 hours a day for 5days) will take 2.5 work days of duration which is 1/2
week of elapsed time to complete 80 hours of effort.
With two workers who can work 80 hours a week(16 hours a day for 5days) will take 2.5 work days of duration which is 1
week of elapsed time to complete 80 hours of effort.
Effort ↔ Duration ↔ Elapsed Time
www.GLOBALSKILLUP.com
Analogous Estimating
(Cost or Duration)
Based on the previous experiences or historical
information, one may readily come up with the
duration or cost estimate for a similar work.
This is known as Analogous(equivalent)
estimating also sometimes knows as Gross value
estimating.
Most easily and commonly used form of
estimation, costless form of estimation. However,
it is also less accurate.
Example:
Two years back I spent 4 months for this
Based on my past experience of such a,
I believe the new
would cost us the same 4 months.
Based on the estimating technique in which an
algorithm is used to calculate cost or duration
using the historical information or project
parameters(statistical relationship).
Example:
For a 1 square foot of construction, it took
INR 3500 in the previous construction project.
For the construction of the 50 square foot of new
construction project,
The estimate will be 50*3500 = INR 175000.
Parametric Estimating
(Cost or Duration)
project
project
www.GLOBALSKILLUP.com
Accuracy of the estimates may be significantly improved considering the risk and uncertainty
of every estimate. This can be achieved by using the PERT(Program Evaluation and Review
Techniques) values.
PERT uses 3 different estimates to define an approximate range for an activity’s duration.
Most Likely (M) – This is the most likely estimate
Optimistic (O) – based on thinking best case scenario
Pessimistic (P) – based on thinking worst case scenario
Considering the range of risk and uncertainty, the 3 different estimates can be either:
Triangular Distribution (simple average). Estimate =(O+M+P) / 3
Beta Distribution (weighted average). Estimate = (O+4M+P) / 6
Three Point Estimating
Example: For development of an e-commerce website:
• It will take 3 days to complete (optimistic) – Best case scenario
• It will take 5 days to complete (most likely)
• It will take 13 days to complete (pessimistic) – Worst case scenario
Realistic Estimate = (3+4*5+13)/6 = 3+20+13 /6 = 36/ 6 = 6 Days
Realistic Estimate will always be closer to Most Likely Estimate.
www.GLOBALSKILLUP.com
Learning Curve
Estimation
A common learning curve on Project
depicts that the cumulative average
time to complete a manual task which
involves learning will decrease 20%
whenever volume doubles. This is
referred to as an 80% learning curve.
Let's illustrate the 80% learning curve with a person
learning to design and code websites of similar size and
complexity. If the first website takes 100 hours, then after
the second website the cumulative average time will be 80
hours (80% of 100 hours).
The cumulative average of 80 hours consists of 100 hours
for the first website plus only 60 hours for the second
website resulting in a total of 160 hours divided by 2
websites.
After the fourth website the cumulative average time will be
64 hours (80% of 80 hours).
After the eighth website the cumulative average will be 51.2
hours (80% of 64 hours). In other words, total time to
complete all eight websites will be 409.6 hours (8 websites
times an average time of 51.2 hours).
Improvements in technology can mean time and cost
reductions beyond those in the learning curve.
For example, software may become available to assist in
the design and coding, computer processing speeds might
increase, there may be lower costs of processing and
storage, etc.
The learning curve is important for setting standards,
estimating costs, and establishing selling prices.
www.GLOBALSKILLUP.com
Estimates may sometimes include the Contingency Reserve (Time reserves or
Money buffers) which is included for estimates considering the “known-
unknowns” of the estimates. However, these are different from Management
Reserve, which are kept for any “unknown unknowns” scope additions by
management.
Contingency Reserve is used by Project Manager.
Management Reserve is used by Stakeholders(Management).
ReserveAnalysis
www.GLOBALSKILLUP.com
6.6 Develop Schedule
Inputs
•Schedule Management
Plan
•Activity List
•Activity Attributes
•Activity Resource
Requirements
•Resource Calendars
•Project Scope Statement
•Risk Register
•Risk Breakdown Structure
•Enterprise Environmental
Factors
•Organizational Process
Assets
Tools & Techniques
•Schedule Network
Analysis
•Critical Path Method
•Critical Chain Method
•Resource Optimization
Technique
•Modeling Techniques
•Leads And Lags
•Schedule Compression
•Scheduling Tool
Outputs
•Schedule Baseline
•Project Schedule
•Schedule Data
•Project Calendars
•Project
Management Plan
Updates
•Project Document
Updates
•Integration
•Develop Project Management Plan
•Scope
•Plan Scope Management
•Collect Requirements
•Define Scope
•Create WBS
•Time
•Plan Schedule Management
•Define Activities
•Sequence Activities
•Estimate Activity Resources
•Estimate Activity Duration
•Develop Schedule
•Cost
•Plan Cost Management
•Estimate Costs
•Determine Budget
•Quality
•Plan Quality Management
•Human Resource
•Plan HR Management
•Communications
•Plan Communications Management
•Risk
•Plan Risk Management
•Identify Risks
•Perform Qualitative Risk Analysis
•Perform Quantitative Risk Analysis
•Plan Risk Responses
•Procurement
•Plan Procurement Management
•Stakeholder
•Plan Stakeholder Management
Planning Process
It is the process of analyzing activity sequences, durations, resource
requirements, and schedule constraints to create project schedule
model.
Key benefit is that by entering schedule activities, durations, resources,
resource availabilities, and logical relationships into the scheduling tool,
it generates a schedule model with planned dates for completing project
activities.
As the project evolves, it is a continuous process to ensure the schedule
is updated for changes.
www.GLOBALSKILLUP.com
It is a technique that generates the project schedule model. More importantly the analysis will help you
identify the points of path convergence and divergence.
This helps in schedule compression analysis and ensuring the key points and paths are given due diligence.
Schedule Network Analysis
www.GLOBALSKILLUP.com
The longest duration path
of the project is known as
the critical path. The
duration of the project is
determined by activities
listed on critical path.
Critical Path Method
Technique is to identify the
minimum longest duration
path of project. Any activity
on this critical path is called
a critical path activity.
Any activity other than the
critical path activity with
total float gives the
schedule flexibility without
altering the Project end
dates.
Critical Path Method
S F
5 3 6
4 9
8
S F
5+3+6=14
4+9=13
8
Longest Path is
Critical Path
This path of
activities would
have a Float of 6
(14-8)
This path of
activities
would have a
Float of 1
(14-13)
www.GLOBALSKILLUP.com
End
D 5
F 9
E 8
C 6
Start
Early
Start(ES)
Early
Finish(EF)
Total
Float
Task name & Duration
Late
Start(LS)
Late
Finish(LF)
Branch1:
Non Critical Path: ABCF(3+4+6+9= 22)
Branch2:
Critical Path: ADEF(3+5+8+9=25)
– The longest duration path on the project is identified also
known as Critical Path.
Critical Path Method using Forward Pass & Backward Pass
B 4
A 3
Representation
of the task in the
Project Schedule
This method helps the project manager identify the critical activities on the entire project by identification of the Critical Path and
also to understand how much delays on tasks is acceptable without impacting the project.
In forward pass, each of the activities, Early Start & Early Finish can be arrived for entire project.
In backward pass, each of the activities, Late Start & Late Finish can be arrived for entire project duration.
After both forward pass & back ward pass, once we have identified ES, EF & LS, LF, one can easily come up with the total float on
each of the activities for entire project duration.
www.GLOBALSKILLUP.com
End
3 8
D 5
16 25
F 9
8 16
E 8
7 13
C 6
Start
Early
Start(ES)
Early
Finish(EF)
Total
Float
Activity name &
Duration
Late
Start(LS)
Late
Finish(LF)
Forward Pass (EF = ES + Duration)
3 7
B 4
0 3
A 3
Branch1(ABCF) the last EF is 13.
Branch2(ADEF) the last EF is 16.
In forward pass, pick the largest previous EF number
from the branches, which will also become the ES for
merging activity F. Hence, ES(Task F) will be 16.
On Activity F
ES(Task F) = 16
EF(Task F) = ES(Task F) + Duration(Task F)
= 16 + 9 = 25 days
On Activity A
ES(Task A) = 0. Start the first activity as soon as possible, 0.
EF(Task A) = ES(Task A) + Duration(Task A) = 0 + 3 = 3 days
Let us calculate ES & EF of all branches first.
Branch 1(ABCF)
On Activity B
EF(Task A) = 3, This value is assigned to ES(Task B)
EF(Task B) = ES(Task B) + Duration(Task B) = 3 + 4 = 7 days
On Activity C
EF(Task B) = 7, This value is assigned to ES(Task C)
EF(Task C) = ES(Task C) + Duration(Task C) = 7 + 6 = 13 days
Branch2(ADEF)
On Activity D
EF(Task A) = 3, This value is assigned to ES(Task D)
EF(Task D) = ES(Task D) + Duration(Task D) = 3 + 5 = 8 days
On Activity E
EF(Task D) = 8, This value is assigned to ES(Task E)
EF(Task E) = ES(Task E) + Duration(Task E) = 8 + 8 = 16 days Task representation legend
www.GLOBALSKILLUP.com
End
3 8
D 5
3 8
16 25
F 9
16 258 16
E 8
8 16
7 13
C 6
10 16
Start
Early
Start(ES)
Early
Finish(EF)
Total
Float
Activity name &
Duration
Late
Start(LS)
Late
Finish(LF)
Backward Pass (LF – DURATION = LS)
3 7
B 4
6 100 3
A 3
0 3
Branch1(ABCF) the first LS is 6.
Branch2(ADEF) the first LS is 3.
In backward pass, pick the smallest LS number from the
branches(6 or 3?) which will also become the LF for
activity A. Hence, LF(Task A) will be 3.
On Activity A
LS(Task A) = LF(Task A) – Duration(Task A) = 3 – 3 = 0.
When ES & LS are ‘0’, that would mean all calculations
so far are correct.
On Activity F
EF(Task F) = 25, This value is assigned to LF(Task F)
ES(Task F) = EF(Task F) – Duration(Task F) = 25 – 9 = 16 days
Let us calculate LS & LF of all branches now.
Branch 1(ABCF)
On Activity C
LF(Task F) = 16, This value is assigned to LF(Task C)
LS(Task C) = LF(Task C) – Duration(Task C) = 16 – 6 = 10 days
On Activity B
LS(Task C) = 10, This value is assigned to LF(Task B)
LS(Task B) = LF(Task B) – Duration(Task B) = 10 – 4 = 6 days
Branch2(ADEF)
On Activity E
LS(Task F) = 16, This value is assigned to LF(Task E)
LS(Task E) = LF(Task E) – Duration(Task E) = 16 – 8 = 8 days
On Activity D
LS(Task E) = 8, This value is assigned to LF(Task D)
LS(Task D) = LF(Task D) – Duration(Task D) = 8 – 5 = 3 days Task representation legend
www.GLOBALSKILLUP.com
A Float (also known as Slack) is the amount of time an activity may be delayed without having any further impact.
Free Float is known as the delay on the activity without impacting the subsequent tasks.
Total Float is known as the delay on the activity without impacting overall project completion itself.
With Floats, Project Manager has little comfort to realign the activity priorities and reschedule for any constraints.
Floats on a Project
A B C D E F
X Y
7 4 9 3 8 1
9
Alternate
Path of
Activities
Critical
Path of
Activities
Free Float of X
8
Free Float of Y
9 + 8 = 17
Total Float of X
8
Total Float of Y
All Critical Path Activities (A, B, C, D, E, F) will have Zero Free Float Duration & Zero Total Float Duration
End
Start
www.GLOBALSKILLUP.com
End
3 8
0 D 5
3 8
16 25
0 F 9
16 258 16
0 E 8
8 16
7 13
3 C 6
10 16
Start
Early
Start(ES)
Early
Finish(EF)
Total
Float
Activity name &
Duration
Late
Start(LS)
Late
Finish(LF)
Let us calculate “Float/Slack” now!
3 7
3 B 4
6 100 3
0 A 3
0 3
Did you notice all activities falling on the critical path?
All activities on this critical path by default have Zero
Slack or Zero Float.
In order to calculate Float on all activities,
simply use the LS – ES otherwise LF – EF.
On Activity A
0 – 0 = 0. Float on Activity A is 0.
On Activity B
6 -3 = 3. Float on Activity B is 3 days
On Activity C
10 – 7 = 3. Float on Activity C is 3 days.
Please observe, either Activity B or Activity C can be delayed by 3 days, with
out impacting the project. This does not mean you can delay both B and C
together by 3 & 3 days.
On Activity D
3 – 3 = 0. Float on Activity D is 0.
On Activity E
8 – 8 = 0. Float on Activity E is 0.
On Activity F
16 – 16 = 0. Float on Activity F is 0. Task representation legend
www.GLOBALSKILLUP.com
Activity: Please perform
A4
B6
D9
C7
E4
F5
G6 FinishStart
Q1. Identify the Critical path of the project?
Q2. How early can we finish the project itself?
Q3. How late can we finish the project without impacting Client?
Q4. What is the float on the task C?
Q5. What would be the new critical path duration if C7 become C14?
www.GLOBALSKILLUP.com
Activity: Answers
A4
B6
D9
C7
E4
F5
G6 FinishStart
Q1. Identify the Critical path of the project? A4-D9-F5-G6
Q2. How early can we finish the project itself? 24 Days
Q3. How late can we finish the project without impacting Client? On 24th Day
Q4. What is the float on the task C? 2 Days
Q5. What would be the new critical path duration if C7 become C14? 29 Days
0 4
0 4
18 24
18 24
10 14
14 18
13 18
13 18
4 10
8 14
4 11
6 13
4 13
4 13
www.GLOBALSKILLUP.com
Project Buffer
A B C Project
Buffer
In reality, Project
Completion with
no Project Buffer
may derail the
end market
commitments
and cause major
business
reputation loss
Ideal
Project
Completion
Ideally,
1 Task is assigned to
1 Project Resource
at any given point in
time.
No multitasking by
same resources.
G H
X Y
Project
Start
Project
End
Critical Path of Project with Project Buffer
makes the project more realistic towards end
result.
Start-A-B-C-End is the Critical Path.
Start-G-H-B-C-End is alternate path.
Start-X-Y-B-C-End is alternate path.
Many a times, in order to suppress the ambiguity on
projects and overcome the uncertainty, Project
buffer’s are used.
This is simply sometimes an extra timeline after the
anticipated Ideal Project Completion.
Project Buffers should not be planned thinking
resources on the project will not be productive!
www.GLOBALSKILLUP.com
Feeding Buffer
Critical Path of Project with Project Buffer makes the project more realistic towards end result.
In addition, all alternate paths collision to critical path activities need to be buffered(feeding buffer) to stop
derailment of critical path activities. This will protect the Project timeline by not cascading on each individual
critical path activity.
Each feeding buffer size must account for uncertainty/ambiguity in the duration of the chain of dependent
activities leading up to that buffer.
A B C Project
Buffer
Ideal
Project
Completion
Ideally,
1 Task is assigned to
1 Project Resource
at any given point in
time.
No multitasking by
same resources.
G H
X Y
Project
Start
Project
End
Feeding
Buffer
Feeding
Buffer
Real
Project
Completion
www.GLOBALSKILLUP.com
Critical Chain Method
In a typical project to calculate the project duration, we would
look into Sequencing of Activities through critical path. And this
critical path can be considered as the actual project duration, if
the assumption of 1 Task Per Resource Per Project is true.
However, in reality – we would want to achieve some
benefit(including resource optimization) by applying same
resource(SME’s sometimes) to work on some activities, such as
in the case depicted above. This application of resource over
multiple places on the project alters the critical chain of the
project.
This optimized resource constrained critical path is sometimes
known as Critical Chain.
Look at task H & Y to be performed by the same resource
Person 1 after task A. This would mean that automatically the
project critical path which was earlier
Start-A-B-C-End
this has now altered to become Start-A-H-Y-B-C-End
As new Critical Chain path emerges, feeding buffers will change
so that critical path activities are not cascaded further.
A
Person1
B
Person1
C
Person 4
Project
Buffer
Ideal
Project
Completion
G
Person2
H
Person1
X
Person 3
Y
Person1
Project
Start
Project
End
Real
Project
Completion
Feeding Buffer
Feeding Buffer
www.GLOBALSKILLUP.com
Resource Leveling
Resource allocation on particular activities may require critical resources which are in high
demand. This may impose these critical resources to be over allocated on parallel activities
and/or multiple projects.
Resource leveling ensures these critical resources are optimally spread across parallel
activities and multiple projects so that they don’t need to work 16 hours a day!
Resource Smoothing
Activities with free float are re-adjusted so that the resources work is evened out.
Readjustment of these activities should not cause changes to the project schedule duration.
Resource Optimization Techniques
0
10
20
30
40
50
60
70
W1 W2 W3 W4 W5 W6 W7 W8 W9
0
10
20
30
40
50
60
70
W1 W2 W3 W4 W5 W6 W7 W8 W9
40WorkHours
40WorkHours
Leveling
www.GLOBALSKILLUP.com
What-IF Scenario Analysis
Process to evaluate the scenarios and their
anticipated outcomes which may be either
Positive, Negative or Unknown.
Based on the outcome of the scenarios, the
schedule network analysis is performed which
may result into actionable results such as
delayed production delivery, impacted financial
revenue from the product delivery, extended
periods of delivery so on.
The outcomes may also be used in adverse
situation planning such as in case of a labor
union unrest, what may be the contingency plan
or response to such situation.
Simulation
Simulation involves calculation of multiple project
durations based on the activity assumptions.
This may be based on the 3 point estimates
distribution(Optimistic, Most Likely, Pessimistic)
or Monte Carlo Simulation.
Monte Carlo Simulation is the most common
simulation in which a distribution of possible
activity durations (based on 3-point estimating –
Optimistic, Pessimistic, Most Likely) are defined
based on probabilistic random number ranges.
This simulation aides the project manager to come
up with variations and extremes which in turn
helps project manager to inform stakeholders and
set rightful expectations on the project schedules
and costs.
Stakeholders are in advantage situation to make a
better informed decision based on at least some
probabilistic patterns of simulation instead of
pulling numbers from thin air.
Modeling Techniques
www.GLOBALSKILLUP.com
Schedule Compression Techniques are applied to shorten schedule duration of
the entire project.
Crashing
Cost & Schedule tradeoffs are analyzed to determine how to obtain the
greatest amount of compression with least incremental cost.
As the compression is achieved, the risk and the cost on the particular
task dramatically increases. It may not be best to crash always.
Methods to apply crashing include
adding additional resources
approving overtime resources
adding incentives for finishing early
General practice is to ensure the tasks on critical path are crashed first.
Fast Tracking
Activities or Phases performed in parallel instead of sequential leading to
quick delivery, though increased cost and/or some rework.
This only works when the activities overlap on each other for some
duration.
Schedule Compression Techniques
40 Work Hours done
by 1 Person
40 Work
Hours done by
2 Person
Crashing done by addition
of resources to save time
www.GLOBALSKILLUP.com
Crashing Graphically
Terminate
(T)
Start
(S)
7M
6M
8M
7M
Critical Path: Longest Duration Path of
Project. Any delay on this path of
activity will further delay Project itself.
Alternate Path: This path if
wanted could be delayed by a
flexibility of 2M. This
flexibility is called Float.
Terminate
(T)
Start
(S)
7M
6M
8M
7M
Months
www.GLOBALSKILLUP.com
Crashing Graphically
Terminate
(T)
Start
(S)
7M
6M
8M
7M
Instead of 1 Person
working for 8M, let
us say 2 people work
on this task to
complete in 2M
1 Person
1 Person 1 Person
1 Person
Terminate
(T)
Start
(S)
7M
6M
2M
7M
With 2 Person working now, duration of
task reduced to 2M from 8M, incurring
an extra cost of maybe 1 extra machine
/extra salary for new person
1 Person
1 Person 1 Person
2 Person
New Critical Path is
13M with an Extra
Cost of 1 Person
This is the new
Alternate Path with a
Float of 13M-9M = 4M
www.GLOBALSKILLUP.com
Crashing Exam Example
What activities can be crashed?
• All Critical Path Activities with Zero Float Activity can be crashed.
• Non-Critical Path Activities need not be crashed as they don’t generate
any additional benefit to the project schedule compression.
Which will be most beneficial activity that can be crashed from the list?
• Activity F will be the most beneficial from the activities among B, C, F, H, J
since it has Cost per Month of 433 which is the least.
Activity
Critical
Path
Activity
Activity
Float
(Slack)
Project
Float
Duration
(month)
Crash
Duration
Time
Savings
Cost
(month)
Crash
Cost
Extra
Cost
Cost
Per
Month
A 1 5 9 1 8 9300 12000 2700 338
B √ 0 5 4 3 1 6800 9000 2200 2200
C √ 0 5 3 2 1 8000 14000 6000 6000
D 2 5 4 3 1 13700 18000 4300 4300
E √ 3 5 6 1 5 6600 10000 3400 680
F √ 0 5 5 2 3 9700 11000 1300 433
G 2 5 8 2 6 7400 8500 1100 183
H √ 0 5 7 3 4 10100 12500 2400 600
I 2 5 10 3 7 12200 17500 5300 757
J √ 0 5 8 4 4 5800 9500 3700 925
Project has a float of 5 months, what
would be the best possible crash activity
to ensure the 5 months float is saved?
• Zero slack critical path activities B, C,
F, H, J.
• Combining them together to achieve 5
months, looking into Time savings
B+C+F, B+J, C+J, B+H, C+H which will
be 2200+6000+433, 2200+925,
6000+925, 2200+600, 6000+600
• The best option is to pick the lowest
crash cost per month combination
which is B+H.
What is the cost incurred to crash this
Project?
• Cost incurred to crash any project
would be to crash all the critical path
zero slack activities and utilize the
complete Project float value(in this case
5 Months) to pick the lowest crash cost
per month combination as calculated
earlier.
• So the combination is B+H which is
2200+600 = 2800 (Crash cost of the
project)
www.GLOBALSKILLUP.com
Fast Tracking Example
Days -> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
"A" Task of 6 days A A A A A A
"B" Task of 9 days B B B B B B B B B
"C" Task of 12 days C C C C C C C C C C C C
"D" Task of 5 days D D D D D
Days -> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
"A" Task of 6 days A A A A A A
If "B" can be fast tracked by 4d
"B" Task of 9 days B B B B B B B B B
If "C" can be fast tracked by 8d
"C" Task of 12 days C C C C C C C C C C C C
If "D" can be fast tracked by 4d
"D" Task of 5 days D D D D D
4 days
8 days
4 days
Total Task Duration = 6+9+12+5 = 32 days
Total Fast Tracked Task Duration = 16 days Duration Saved from Fast tracking
Fast Tracking applicable
for overlapping activities
& phases only
What is the fast tracked duration for above example?
• Yes, that’s correct. It is 16 days.
www.GLOBALSKILLUP.com
6.7 Control Schedule
Inputs
•Project Management Plan
•Project Schedule
•Work Performance Data
•Project Calendars
•Schedule Data
•Organizational Process Assets
Tools & Techniques
•Performance Reviews
•Project Management
Software
•Resource Optimization
Techniques
•Modeling Techniques
•Leads and Lags
•Schedule Compression
•Scheduling Tool
Outputs
•Work Performance
Information
•Schedule Forecasts
•Change Requests
•Project Management Plan
Updates
•Project Document Updates
•Organizational Process Assets
Updates
•Integration
•Monitor and Control Project Work
•Perform Integrated Change Control
•Scope
•Validate Scope
•Control Scope
•Time
•Control Schedule
•Cost
•Control Costs
•Quality
•Control Quality
•Human Resource
•Communications
•Control Communications
•Risk
•Monitor & Control Risks
•Procurement
•Control Procurements
•Stakeholder
•Control Stakeholder Management
Monitoring & Controlling
Process
It is the process of managing the project schedule and
controlling the schedule to ensure the project is
delivered with in the planned schedule timeframe.
Key benefit includes the project schedule is well within
the planned schedule timeframe.
Using control schedule the project can be put back in to
track by corrective and preventive actions.
www.GLOBALSKILLUP.com
It is the data required to manage and control the Schedule itself. It is generally
observed that alternative schedules arising out of the contingency or due to the
funding limit reconciliation are parked here.
Schedule data includes the milestones, schedule related activities, identified risks,
assumptions and schedule related constraints. Data could also include the
histograms whether the resource leveled or not resource leveled.
Schedule Data
www.GLOBALSKILLUP.com
Performance Review of work in progress and work accomplished may be carried in
perspective of:
What is accomplished (actual function/story points to planned function/story points)
at what cost (actual amount of money or percentage wise)
when it is done (actual hours/dates or the deviation dates)
In the Schedule Performance reviews:
actual start date compared to the planned start date
actual end date compared to the planned end date
percentage work accomplished to planned accomplishment
Various Techniques may be used for performance reviews:
Trend Analysis
Critical Path Method
Critical Chain Method
EVM(Earned Value Management)
Performance Reviews
www.GLOBALSKILLUP.com
Schedule Variance (SV) and Schedule Performance Index (SPI) are the two important Schedule Work
Performance Information which need to be kept in radar to have the control on the Schedule.
Continuous monitoring of these two parameters help one understand the progress being made and the
performance of the project on schedule, allowing the recommended corrective and preventive actions.
Progress reports on the schedule during the control schedule are continuously reported to the stakeholders
on desired intervals.
Work Performance Information
Project Status Report
www.GLOBALSKILLUP.com
Schedule Forecasts are future predicted timelines of the
schedule, it may be for a task, activity, module or for a
project.
Mainly the Project schedule forecast is of our importance,
however, at times it may be of critical task, activity or a
module as well.
Scheduled forecast is arrived based on the already work
completed, work in progress and work in future to be
accomplished. In other terms, it is progress against schedule
baseline and the computed time estimate to complete(ETC).
The past performance indicators reflect the future course of
project work accomplishment.
Forecasts are helpful to determine if the project schedule is
within the defined tolerance levels of the schedule ranges.
Schedule Forecasts
www.GLOBALSKILLUP.com
Chapter 6 - Debrief
www.GLOBALSKILLUP.com
THIS BRINGS TO “TIME MANAGEMENT” COMPLETION.
From what we have understood so far is:
 7 Time Management Knowledge Area Processes
 Identified their Inputs, Tools & Techniques, Outputs
Chapter 6
www.GLOBALSKILLUP.com
PMP Group Trainings across India
Bangalore | Hyderabad | Pune | Delhi | Chennai | Mumbai | Noida | Gurgaon
Online Trainings Too
www.GLOBALSKILLUP.com
Acknowledgements & Disclaimer
PMI, PMBOK, PMP, CAPM, PgMP, PMI-
ACP, PMI-RMP, PMI-SP are registered
marks of Project Management Institute,
Inc.
All registered trademarks, symbols, names
are marks of their respective owners and
acknowledged.

Weitere ähnliche Inhalte

Was ist angesagt?

PM Knowledge Areas
PM Knowledge AreasPM Knowledge Areas
PM Knowledge AreasDerya Milner
 
Project Management: Knowledge Areas
Project Management: Knowledge Areas Project Management: Knowledge Areas
Project Management: Knowledge Areas Gregory Mangos
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk managements. Akhlaque
 
Project Management
Project ManagementProject Management
Project Managementajithsrc
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project ManagementSlav Karaslavov
 
Project manager roles responsibilities
Project manager roles responsibilitiesProject manager roles responsibilities
Project manager roles responsibilitiesBlossoms
 
Program or project management process report
Program or project management process report Program or project management process report
Program or project management process report Danes Ganancial
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycleAndrei Crăciun
 
Project management processes Groups
Project management processes GroupsProject management processes Groups
Project management processes GroupsSourabh Kumar
 
Project Life Cycle and Phases with Risk Management discussion
Project Life Cycle and Phases with Risk Management discussionProject Life Cycle and Phases with Risk Management discussion
Project Life Cycle and Phases with Risk Management discussionAbigail Pugal-Somera
 
Project management glossary_of_terms
Project management glossary_of_termsProject management glossary_of_terms
Project management glossary_of_termsnagham ali hasan
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1Imoh Etuk
 

Was ist angesagt? (20)

PM Knowledge Areas
PM Knowledge AreasPM Knowledge Areas
PM Knowledge Areas
 
Project Management: Knowledge Areas
Project Management: Knowledge Areas Project Management: Knowledge Areas
Project Management: Knowledge Areas
 
project management concepts
project management conceptsproject management concepts
project management concepts
 
11 project risk management
11 project risk management11 project risk management
11 project risk management
 
Project Risk Management
Project Risk ManagementProject Risk Management
Project Risk Management
 
Introduction to risk management
Introduction to risk managementIntroduction to risk management
Introduction to risk management
 
Project management
Project managementProject management
Project management
 
Project Management
Project ManagementProject Management
Project Management
 
Different project management methodologies
Different project management methodologiesDifferent project management methodologies
Different project management methodologies
 
PMP_Project Time Management
PMP_Project Time ManagementPMP_Project Time Management
PMP_Project Time Management
 
Project Management
Project ManagementProject Management
Project Management
 
Introduction to Project Management
Introduction to Project ManagementIntroduction to Project Management
Introduction to Project Management
 
Project manager roles responsibilities
Project manager roles responsibilitiesProject manager roles responsibilities
Project manager roles responsibilities
 
Program or project management process report
Program or project management process report Program or project management process report
Program or project management process report
 
Project management life cycle
Project management life cycleProject management life cycle
Project management life cycle
 
Project management processes Groups
Project management processes GroupsProject management processes Groups
Project management processes Groups
 
Project Life Cycle and Phases with Risk Management discussion
Project Life Cycle and Phases with Risk Management discussionProject Life Cycle and Phases with Risk Management discussion
Project Life Cycle and Phases with Risk Management discussion
 
Project management glossary_of_terms
Project management glossary_of_termsProject management glossary_of_terms
Project management glossary_of_terms
 
BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1BPP Training on Project Management - Day 1
BPP Training on Project Management - Day 1
 
9- PMP Training - Communication Management
9- PMP Training - Communication Management9- PMP Training - Communication Management
9- PMP Training - Communication Management
 

Andere mochten auch

Online PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsOnline PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsGlobalSkillup
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaGlobalSkillup
 
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...GlobalSkillup
 
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for ExamEasy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for ExamGlobalSkillup
 
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...GlobalSkillup
 
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...GlobalSkillup
 
Pmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalPmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalYudha Pratama, PMP
 
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryPMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryYudha Pratama, PMP
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkejlp12
 
A Risk Perspective -- Rolling Wave Planning
A Risk Perspective -- Rolling Wave PlanningA Risk Perspective -- Rolling Wave Planning
A Risk Perspective -- Rolling Wave PlanningJohn Goodpasture
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisIntaver Insititute
 
Pmbok 5cartulinas
Pmbok 5cartulinasPmbok 5cartulinas
Pmbok 5cartulinasPedro Arcas
 
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...GBS PAVONE Groupware GmbH
 
PMI-PBA 商業分析讀書會 20150725
PMI-PBA 商業分析讀書會 20150725PMI-PBA 商業分析讀書會 20150725
PMI-PBA 商業分析讀書會 20150725moris lee
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project managementPavan Kumar
 
PMP preparation and PMI Framework
PMP preparation and PMI FrameworkPMP preparation and PMI Framework
PMP preparation and PMI FrameworkUzma Khan
 
Pmp pmbok 5 updates vs pmbok 4
Pmp pmbok 5 updates vs pmbok 4Pmp pmbok 5 updates vs pmbok 4
Pmp pmbok 5 updates vs pmbok 4Hujaj Khan
 
Rohit demo sap ps_module_training
Rohit demo sap ps_module_trainingRohit demo sap ps_module_training
Rohit demo sap ps_module_trainingmultimediasunil
 

Andere mochten auch (20)

Online PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groupsOnline PMP Prep Material for PMP Exam - Project management process groups
Online PMP Prep Material for PMP Exam - Project management process groups
 
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge AreaOnline PMP Training Material for PMP Exam - Quality Management Knowledge Area
Online PMP Training Material for PMP Exam - Quality Management Knowledge Area
 
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
Online PMP Training Material for PMP Exam - Human Resources Management Knowle...
 
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for ExamEasy 1-2-3 like Steps for PMI ACP Application Submission for Exam
Easy 1-2-3 like Steps for PMI ACP Application Submission for Exam
 
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
Online PMP Training Material for PMP Exam - Procurement Management Knowledge ...
 
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
Complete Online PMP Study Training Material for PMP Exam Provided Free for PM...
 
PMP_Project Procurement Management
PMP_Project Procurement ManagementPMP_Project Procurement Management
PMP_Project Procurement Management
 
Pmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management finalPmp – pmbok 5th edition chapter4 project integration management final
Pmp – pmbok 5th edition chapter4 project integration management final
 
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT SummaryPMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
PMBOK 5th Edition - Chapter 6 PROJECT TIME MANAGEMENT Summary
 
PMP Training - 01 introduction to framework
PMP Training - 01 introduction to frameworkPMP Training - 01 introduction to framework
PMP Training - 01 introduction to framework
 
A Risk Perspective -- Rolling Wave Planning
A Risk Perspective -- Rolling Wave PlanningA Risk Perspective -- Rolling Wave Planning
A Risk Perspective -- Rolling Wave Planning
 
Monte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk AnalysisMonte Carlo Schedule Risk Analysis
Monte Carlo Schedule Risk Analysis
 
Pmbok 5cartulinas
Pmbok 5cartulinasPmbok 5cartulinas
Pmbok 5cartulinas
 
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
Workflow Management Software with IBM Lotus Notes, Business Process Managemen...
 
PMI-PBA 商業分析讀書會 20150725
PMI-PBA 商業分析讀書會 20150725PMI-PBA 商業分析讀書會 20150725
PMI-PBA 商業分析讀書會 20150725
 
10 me667 chap2 project management
10 me667 chap2 project management10 me667 chap2 project management
10 me667 chap2 project management
 
PMP preparation and PMI Framework
PMP preparation and PMI FrameworkPMP preparation and PMI Framework
PMP preparation and PMI Framework
 
Pmp pmbok 5 updates vs pmbok 4
Pmp pmbok 5 updates vs pmbok 4Pmp pmbok 5 updates vs pmbok 4
Pmp pmbok 5 updates vs pmbok 4
 
Pm training 1 18
Pm training 1 18Pm training 1 18
Pm training 1 18
 
Rohit demo sap ps_module_training
Rohit demo sap ps_module_trainingRohit demo sap ps_module_training
Rohit demo sap ps_module_training
 

Ähnlich wie Online PMP Training Material for PMP Exam - Time Management Knowledge Area

Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life CycleReema
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01samansari22
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01petch phanpha
 
component 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfcomponent 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfAnatole9
 
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxprojectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxChandrasen Sharma
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project ManagementRasan Samarasinghe
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management areaZaur Ahmadov, PMP
 
All about project management
All about project managementAll about project management
All about project managementTudor Bejan
 
Pm4 dev the_project_managment_processes
Pm4 dev the_project_managment_processesPm4 dev the_project_managment_processes
Pm4 dev the_project_managment_processesYemi Osinubi, CFA
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheederKarin Rheeder
 
software (1).pptx
software (1).pptxsoftware (1).pptx
software (1).pptxayanadamtew
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptxHarsimratDeo1
 

Ähnlich wie Online PMP Training Material for PMP Exam - Time Management Knowledge Area (20)

6396901
63969016396901
6396901
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Project Management Life Cycle
Project Management Life CycleProject Management Life Cycle
Project Management Life Cycle
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
Project management
Project managementProject management
Project management
 
component 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdfcomponent 5 project planning, monitoring and evaluation.pdf
component 5 project planning, monitoring and evaluation.pdf
 
Project Management
Project ManagementProject Management
Project Management
 
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxprojectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptx
 
DISE - Introduction to Project Management
DISE - Introduction to Project ManagementDISE - Introduction to Project Management
DISE - Introduction to Project Management
 
PMP-Schedule Management area
PMP-Schedule Management areaPMP-Schedule Management area
PMP-Schedule Management area
 
All about project management
All about project managementAll about project management
All about project management
 
bingsusu.pptx
bingsusu.pptxbingsusu.pptx
bingsusu.pptx
 
06 project time management m
06 project time management m06 project time management m
06 project time management m
 
Pm4 dev the_project_managment_processes
Pm4 dev the_project_managment_processesPm4 dev the_project_managment_processes
Pm4 dev the_project_managment_processes
 
Project management master class karin rheeder
Project management master class   karin rheederProject management master class   karin rheeder
Project management master class karin rheeder
 
software (1).pptx
software (1).pptxsoftware (1).pptx
software (1).pptx
 
2) PMT & PIM.pptx
2) PMT & PIM.pptx2) PMT & PIM.pptx
2) PMT & PIM.pptx
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Project planning.pptx
Project planning.pptxProject planning.pptx
Project planning.pptx
 

Kürzlich hochgeladen

Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningCIToolkit
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...Pooja Nehwal
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Hedda Bird
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Alex Marques
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Smisbafathima9940
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girladitipandeya
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 

Kürzlich hochgeladen (20)

Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdfImagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
Imagine - HR; are handling the 'bad banter' - Stella Chandler.pdf
 
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...Call Now Pooja Mehta :  7738631006 Door Step Call Girls Rate 100% Satisfactio...
Call Now Pooja Mehta : 7738631006 Door Step Call Girls Rate 100% Satisfactio...
 
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg PartnershipUnlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
Unlocking the Future - Dr Max Blumberg, Founder of Blumberg Partnership
 
Peak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian DugmorePeak Performance & Resilience - Dr Dorian Dugmore
Peak Performance & Resilience - Dr Dorian Dugmore
 
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...Dealing with Poor Performance - get the full picture from 3C Performance Mana...
Dealing with Poor Performance - get the full picture from 3C Performance Mana...
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024
 
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 
situational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima Ssituational leadership theory by Misba Fathima S
situational leadership theory by Misba Fathima S
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Ameerpet high-profile Call Girl
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 

Online PMP Training Material for PMP Exam - Time Management Knowledge Area

  • 4. www.GLOBALSKILLUP.com Chapter 6 Objectives Understand the different Time Management Processes Their Inputs, Tools and Techniques, Outputs This chapter entails one to understand the various Time Management aspects required to understand the customer delivery timeline needs. Also, how the timeline will be approached, managed and finally honored – making the project successful!
  • 5. www.GLOBALSKILLUP.com Project Time Management includes processes to ensure the schedule is defined, managed, controlled and has updated schedule baseline to meet project timeline. Establishing a Project schedule involves using the Project Information, Project Scheduling Methods & Tools. Most common scheduling methods include Critical Path Method (CPM) & Critical Chain Method (CCM). Schedule may be represented in many a ways including the Bar Chart, Network Diagram and/or Activity List. Knowledge Area: Time Management
  • 6. www.GLOBALSKILLUP.com There are 7 Time Management processes: 1. Plan Schedule Management Establishing Project Schedule in Schedule Management Plan Document which will be used across project to control timelines as project evolves and changes occur. 2. Define Activities Breaking down the larger chunks of scope into actionable small activities using the WBS by defining project activities 3. Sequence Activities Establishing the relationships between the defined project activities to ensure the sequence of activities are done in rightful manner 4. Estimate Activity Resources What type and amount of estimated resources are required to accomplish sequenced activity 5. Estimate Activity Durations How long will it take to ensure the estimated resources perform the activity assigned 6. Develop Schedule Based on all the available information from defined activities to sequence activities to estimate resource & durations will aid to arrive at develop schedule 7. Control Schedule Monitoring and Controlling the project schedule across the project duration w.r.t schedule baseline and achieve the project objectives Knowledge Area: Time Management
  • 7. www.GLOBALSKILLUP.com 6.1 Plan Schedule Management Inputs • Project Management Plan • Project Charter • Requirements Documentation • Organizational Process Assets Tools & Techniques • Expert Judgment • Analytical Techniques • Meetings Outputs • Schedule Management Plan •Integration •Develop Project Management Plan •Scope •Plan Scope Management •Collect Requirements •Define Scope •Create WBS •Time •Plan Schedule Management •Define Activities •Sequence Activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule •Cost •Plan Cost Management •Estimate Costs •Determine Budget •Quality •Plan Quality Management •Human Resource •Plan HR Management •Communications •Plan Communications Management •Risk •Plan Risk Management •Identify Risks •Perform Qualitative Risk Analysis •Perform Quantitative Risk Analysis •Plan Risk Responses •Procurement •Plan Procurement Management •Stakeholder •Plan Stakeholder Management Planning Process Is the process to ensure project schedule is managed from beginning of the project to the end of the project with a defined approach. Key benefit of this means to provide a guidance and oversight on how the project schedule is to be managed with an upfront defined schedule thresholds. The schedule management plan also defines how schedule contingencies will be reported and assessed over the course of the project delivery.
  • 8. www.GLOBALSKILLUP.com This may involve options to estimate and schedule the project using the Scheduling methodology, scheduling Tools and techniques, estimation approaches, formats and project management software. Approaches are defined to ensure speedy delivery while ensuring the project risk is managed well. Crashing or Fast Tracking are common schedule compression techniques using which the work is parallelized. While delivery of the work in parallel is beneficial this may also increase the risk on the project. These decisions are to be well explained to the relevant stakeholders as the case may be. In some cases, organizations with well established frameworks ensure to have organization policies and procedures with defined techniques to employ such as: Rolling wave planning Leads and lags Alternative analysis Methods for reviewing schedule performance Analytical Techniques
  • 9. www.GLOBALSKILLUP.com Schedule Management Plan defines the criteria and activities for developing, monitoring and controlling project schedule. It establishes the following: Project Schedule Model Development → Scheduling Methodology & Scheduling Tool to be used Level of Accuracy → Extent of the estimates supposed to be accurate. Include any contingency for estimation gaps Units of Measure → What units will be applied, staff hours, staff days, weeks, meters, liters, kilometers and so on Organizational Procedure Links → Links to the phases, activities from the WBS to ensure consistency and resulting schedules Project Schedule Model Maintenance → Define the updates and changes to the schedule during the execution phase of the project Control Thresholds → Percentage deviations which ensure that the actions are taken for any threshold value deviations Rules of Performance Management EVM (Earned Value Management) rules or similar performance management rules are set How the percentage completion will be established? Control Accounts on which the management review to be performed EVM techniques applied SV (Schedule Variance) & SPI (Schedule Performance Indicator) against the Schedule baseline Reporting formats → What reports are required, Which format and at What frequency Process descriptions → Any processes which will administer the schedule performance and management across the project course Schedule Management Plan
  • 10. www.GLOBALSKILLUP.com 6.2 Define Activities Inputs • Schedule Management Plan • Scope Baseline • Enterprise Environmental Factors • Organizational Process Assets Tools & Techniques • Decomposition • Rolling Wave Planning • Expert Judgment Outputs • Activity List • Activity Attributes • Milestone List •Integration •Develop Project Management Plan •Scope •Plan Scope Management •Collect Requirements •Define Scope •Create WBS •Time •Plan Schedule Management •Define Activities •Sequence Activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule •Cost •Plan Cost Management •Estimate Costs •Determine Budget •Quality •Plan Quality Management •Human Resource •Plan HR Management •Communications •Plan Communications Management •Risk •Plan Risk Management •Identify Risks •Perform Qualitative Risk Analysis •Perform Quantitative Risk Analysis •Plan Risk Responses •Procurement •Plan Procurement Management •Stakeholder •Plan Stakeholder Management Planning Process Define Activities process is performed to ensure the actions are identified and documented to produce end project deliverables. Key benefit of this process is to provide an understanding of breaking down the work packages into activities that can be easily estimated, scheduled, executed, monitored and controlled. The purpose of this process is to identify the specific tasks needed to be done in order to produce the project’s deliverables. Scope Baseline is used as a starting point to breakdown documented deliverables even further, as well as a guide to assure that entire scope of Project is covered, but not extend beyond boundaries of Project.
  • 11. www.GLOBALSKILLUP.com Rolling Wave Planning Rolling wave planning is the iterative planning technique to plan the immediate work in detail and subsequent work at higher levels in at progressive elaboration manner. As an example, in the early stages of the project work packages are defined at a higher level for different phases. However, as we enter the phase more clarity is available and the work packages are made granular. Understand it this way, waves closer to us give better clarity on what they bring along with them. Similar to the immediate work at hand, we know more detailed view of them to accomplish, than the far away waves or work. This is a comprehensive list of all activities to be performed as part of the project. Each activity is supplemented with an activity identifier and sufficient detailed scope of work so as that could be accomplished. Is Activity List same as WBS? An activity list is a list of “What we are doing” in the project to accomplish deliverables. Whereas a WBS is a list of “What we are making” in the project as deliverables. Imagine this as WBS is a high level view of deliverables and Activity list as a low level view of the deliverables. Activity List
  • 12. www.GLOBALSKILLUP.com Activity Attributes Often the activity has just more than the activity identifier like WBS ID, Activity label, Activity code, successor activity code, predecessor activity code, logical relationship definition, leads, lags, resource associated, cost associated, geographic tag, the project calendar the activity is assigned, effort type(level of effort, apportioned effort, discrete effort) and so on. All these attributes help bring more organized and clarity in the accomplishment of each activity. A Milestone is an important event of accomplishment of major work. These milestone activities are simply put, the zero duration activities. They could be either internal to the organization or external market commitment requirements. Milestone List
  • 13. www.GLOBALSKILLUP.com 6.3 Sequence Activities Inputs •Schedule Management Plan •Activity List •Activity Attributes •Milestone List. •Scope Statement •Enterprise Environmental Factors •Organizational Process Assets Tools & Techniques •Precedence Diagramming Method (PDM) •Dependency Determination •Leads And Lags Outputs •Project Schedule Network Diagrams •Project Document Updates •Integration •Develop Project Management Plan •Scope •Plan Scope Management •Collect Requirements •Define Scope •Create WBS •Time •Plan Schedule Management •Define Activities •Sequence Activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule •Cost •Plan Cost Management •Estimate Costs •Determine Budget •Quality •Plan Quality Management •Human Resource •Plan HR Management •Communications •Plan Communications Management •Risk •Plan Risk Management •Identify Risks •Perform Qualitative Risk Analysis •Perform Quantitative Risk Analysis •Plan Risk Responses •Procurement •Plan Procurement Management •Stakeholder •Plan Stakeholder Management Planning Process Activities need to be sequenced or connected with each other by a relation and dependencies to ensure the proper flow and completion of the project work considering all the constraints. This also ensures realistic schedules and efficiency in delivery of project work since the appropriate leads and lags are added. All activities other than the very first and very last activity/milestone, rest all of them need to be connected with each other.
  • 14. www.GLOBALSKILLUP.com PDM is one of the activity sequencing techniques in practice; in which activities are represented in a graphical manner to show precedence of activities to be accomplished in sequence. In this technique, activities are represented as Nodes. Also known as AON (Activity on Node). Most software packages use this type of representation including Microsoft Project. PDM (Precedence Diagramming Method) Start A B C D E G H Finish
  • 15. www.GLOBALSKILLUP.com PDM (Precedence Diagramming Method) Finish to Finish RelationshipStart to Start Relationship Research Data Started Produce Report Started Data Transfer Finished Migration Finished Start to Finish Relationship Most Rarely Used Server Installation Started Vendor Job Finished Finish to Start Relationship Most Commonly Used Draft Manual Finished Print Manual Started PDM also used logical relationships between activity to activity. Four types of relationships:
  • 16. www.GLOBALSKILLUP.com Dependencies can be of different nature. Mandatory → These are the legally or contractually required or inherent in the nature of work being done. Hard logic which has to be met at any cost. Discretionary → These dependencies are at discretion of Project Team. And are the preferred dependencies based on the best practices of work done in the past or as defined by the SME(Subject Matter Experts) for an alternate option. Also know as Soft logic which can undergo an alternate option. External → Dependencies where the project team has to consider the external work done beyond the project team’s control. This is more rampant in case of Contractual Projects. This is beyond control of project team. Internal → Dependencies where project team has to lookup to internal precedence to ensure the previous work is accomplished. This is in the control of the Project team. These 4 dependencies can be clubbed in combination: Mandatory External Dependencies Mandatory Internal Dependencies Discretionary External Dependencies Discretionary Internal Dependencies Dependency Determination
  • 17. www.GLOBALSKILLUP.com Lead Time Let us understand what a lead is with an example. For a movie, Activity A(movie shooting) takes 5 Days. Post the movie shooting, Activity B(mass production) takes another 10 Days for release. The movie in such a scenario is produced for release at 5+10=15 days. Let us now consider a little smart situation. Activity A takes 5 days. Activity B takes another 10 days for mass production. However, as the movie is been shot, the production activities can be started with 3 days in advance(lead) to completion of movie shooting. This would mean the new release date of the movie can be as early as 12 days instead of 15 days with a lead time of 3 days for production. Let us understand what a lag is with an example. For a wooden house construction, Activity A(Procurement of wood) takes 4 days. Activity B(Construction of house) takes 6 days. The schedule for the house construction in such an ideal scenario is 4+6=10 days. Let us now consider a little practicality, After the wood is procured, we would want to ideally have the wood seasoned for 3 days(Lag) during which time, neither the procurement can be done nor the construction can begin. This would mean the practical end to end of construction of wooden house is 4+3+6=13 days. More realistic sense. Lag Time A – 5 Days B – 10 Days Lead of 3 Days Total Duration 2+10=12 Days A – 4 Days B – 6 Days Lag of 3 Days Total Duration 4+3+6=13 Days
  • 18. www.GLOBALSKILLUP.com Pay attention to Tasks where convergence and divergence occurs. These are critical tasks. Any defects introduced in these tasks or delays will lead to major quality deficit. Activity Convergence – Many outputs of activities converge into one activity making it critical activity Activity Divergence – Many outputs will diverge from this activity making it critical activity Activity Activity Output Many Outputs Input Many Inputs A project is termed highly complex with many activities with convergences and divergences, not just the many number of tasks on the Project schedule network.
  • 19. www.GLOBALSKILLUP.com As the name suggests it is a graphical representation of the Project Schedule in a Network format. Though it is usually represented in graphical manner, it is also accompanied by descriptions for any exceptions represented in the graphic. A B D I C E K J F L G Start End H Exceptions ----------- ----------- ----------- ----------- Project Schedule Network Diagram
  • 20. www.GLOBALSKILLUP.com 6.4 Estimate Activity Resources Inputs •Schedule Management Plan •Activity List •Activity Attributes •Resource Calendars •Risk Register •Activity Cost Estimates •Enterprise Environmental Factors •Organizational Process Assets Tools & Techniques •Expert Judgment •Alternative Analysis •Published Estimating Data •Bottom Up Estimating •Project Management Software Outputs •Activity Resource Requirements •Resource Breakdown Structure •Project Document Updates •Integration •Develop Project Management Plan •Scope •Plan Scope Management •Collect Requirements •Define Scope •Create WBS •Time •Plan Schedule Management •Define Activities •Sequence Activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule •Cost •Plan Cost Management •Estimate Costs •Determine Budget •Quality •Plan Quality Management •Human Resource •Plan HR Management •Communications •Plan Communications Management •Risk •Plan Risk Management •Identify Risks •Perform Qualitative Risk Analysis •Perform Quantitative Risk Analysis •Plan Risk Responses •Procurement •Plan Procurement Management •Stakeholder •Plan Stakeholder Management Planning Process This is the process of estimating based on the type, quantity, quality of human resources, material resources to arrive at more accurate estimate(key benefit). Estimate Activity Resources and Estimate Costs are closely linked to each other. For example, a high rise tower construction needs specialized government approvals and specialized skilled workers to execute tasks at such a high rise tower. This means additional cost incurred to procure these resources.
  • 21. www.GLOBALSKILLUP.com Activity Cost Estimates are the probable costs which may be incurred on the particular activities and summed to arrive at the project completion cost. The cost of resources may impact resource selection to keep the project cost optimal to respect the triple constraints. Activity Costs may be direct or indirect : Direct: Labor Cost, Materials, Equipment, Services Interest Charges, Exchange Rates, Cost Contingency Reserve Indirect: Depends on the performing business unit and/or Organization Activity Cost Estimates
  • 22. www.GLOBALSKILLUP.com Alternative Analysis Many activities can be accomplished in more than one way. Alternative Analysis is the ways of finding the best optimal manner to accomplish the activities and project completion. This includes various skill levels of the resources, type of resources used, size and performance of the machines used, manual or automated tools, make-rent-or-buy decisions and so on. A make-or-buy analysis results whether work can best be accomplished by project team or purchased from contracted sources. In Practice, these type of decisions are some times best defined by the organizational culture and project manager’s decision is limited in nature. Some organizations prefer to always buy a new tool instead of development of one. And some other prefer to develop their own tool instead of buy. A few also venture out to sell their own use tools to the market. Many Organizations have a predefined rate lists, estimation production chart data, per unit costs defined for geographies, countries, time zones, special work days and so on. This type of data is readily usable to arrive at the estimation. In this technique, the activity is compared to the activities for which data exists and the actual cost or durations of the closest comparable activity is selected from the data and used as the estimate. The advantage of this technique is that it is very accurate when the project conditions match the conditions under which the published data was generated. The disadvantages are that data does not exist for many activities and that the published data that does exist is based upon the characteristics of the organizations who compiled and published the data. Published Estimating Data
  • 23. www.GLOBALSKILLUP.com Bottom up Estimating Aggregation of all the bottom most elements which can be individually estimated to sum up for estimate is known as bottom up estimate. All WBS elements broken down into work packages and further granular elements are used to arrive at the bottom up estimating. Advantage of such estimate analysis is that it is highly accurate form of estimate as the work is better understood. Disadvantage of such estimate analysis is that it is time consuming and also may not be practical at the beginning of the project since it may not have a decomposed WBS. Advance in technology has led us to utilize the software tools to ensure we have more accurate and reliable estimates based on the input collaboration of various project management aspects like scheduling, risks, optimized resource utilization, breakdown structures and so on. Project Management Software Source Acknowledged: http://www.tenrox.com/
  • 24. www.GLOBALSKILLUP.com Defines the list of resources to be applied for any given activity on the project. Identification of Set of Responsibilities for a Role. Pooling all different roles into Resource requirements for meeting the Project objectives. Activity Resource Requirements It is a structural illustration of resources based on category and type. This is useful for organizing and reporting project schedule data with resource utilization information. Resource Breakdown Structure Project Resources Management Leads Analysts Design Development Project Manager Sr. Management Materials Notepads Sketch Boards Marketing Brochures Equipment Computers Photo Copiers Project Staff Architects & Designers Developers Quality Assurance Control
  • 25. www.GLOBALSKILLUP.com 6.5 Estimate Activity Duration Inputs •Schedule Management Plan •Activity List •Activity Attributes •Activity Resource Requirements •Resource Calendars •Project Scope Statement •Risk Register •Resource Breakdown Structure •Enterprise Environmental Factors •Organizational Process Assets Tools & Techniques •Expert Judgment •Analogous Estimating •Parametric Estimating •Three-Point Estimating •Group-Decision Making •Reserve Analysis Outputs •Activity Duration Estimates •Project Document Updates •Integration •Develop Project Management Plan •Scope •Plan Scope Management •Collect Requirements •Define Scope •Create WBS •Time •Plan Schedule Management •Define Activities •Sequence Activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule •Cost •Plan Cost Management •Estimate Costs •Determine Budget •Quality •Plan Quality Management •Human Resource •Plan HR Management •Communications •Plan Communications Management •Risk •Plan Risk Management •Identify Risks •Perform Qualitative Risk Analysis •Perform Quantitative Risk Analysis •Plan Risk Responses •Procurement •Plan Procurement Management •Stakeholder •Plan Stakeholder Management Planning Process This is one of the most important process which aids in the overall estimation of the project size in terms of duration. It is the process of estimating the period taken for each activity to complete with estimated resources. May not be possible to estimate completely at the beginning and may be progressively elaborated for accurate estimations. Assumptions should be called out to the reviewer. Estimates usually originate from the person or group with the most familiarity about the task at hand. This minimizes estimation gaps upfront due to ambiguity of task. Estimation activity uses multiple information including activity scope of work, required resource types, estimated resource quantities and resource calendars.
  • 26. www.GLOBALSKILLUP.com Example. For your new bungalow, installing an artificial lawn will take 80 hours of effort. With one worker who can work 40 hours a week(8 hours a day for 5days) will take 10 work days of duration which is 2 weeks of elapsed time to complete 80 hours of effort. With two workers who can work 40 hours a week(8 hours a day for 5days) will take 5 work days of duration which is 1 week of elapsed time to complete 80 hours of effort. With four workers who can work 40 hours a week(8 hours a day for 5days) will take 2.5 work days of duration which is 1/2 week of elapsed time to complete 80 hours of effort. With two workers who can work 80 hours a week(16 hours a day for 5days) will take 2.5 work days of duration which is 1 week of elapsed time to complete 80 hours of effort. Effort ↔ Duration ↔ Elapsed Time
  • 27. www.GLOBALSKILLUP.com Analogous Estimating (Cost or Duration) Based on the previous experiences or historical information, one may readily come up with the duration or cost estimate for a similar work. This is known as Analogous(equivalent) estimating also sometimes knows as Gross value estimating. Most easily and commonly used form of estimation, costless form of estimation. However, it is also less accurate. Example: Two years back I spent 4 months for this Based on my past experience of such a, I believe the new would cost us the same 4 months. Based on the estimating technique in which an algorithm is used to calculate cost or duration using the historical information or project parameters(statistical relationship). Example: For a 1 square foot of construction, it took INR 3500 in the previous construction project. For the construction of the 50 square foot of new construction project, The estimate will be 50*3500 = INR 175000. Parametric Estimating (Cost or Duration) project project
  • 28. www.GLOBALSKILLUP.com Accuracy of the estimates may be significantly improved considering the risk and uncertainty of every estimate. This can be achieved by using the PERT(Program Evaluation and Review Techniques) values. PERT uses 3 different estimates to define an approximate range for an activity’s duration. Most Likely (M) – This is the most likely estimate Optimistic (O) – based on thinking best case scenario Pessimistic (P) – based on thinking worst case scenario Considering the range of risk and uncertainty, the 3 different estimates can be either: Triangular Distribution (simple average). Estimate =(O+M+P) / 3 Beta Distribution (weighted average). Estimate = (O+4M+P) / 6 Three Point Estimating Example: For development of an e-commerce website: • It will take 3 days to complete (optimistic) – Best case scenario • It will take 5 days to complete (most likely) • It will take 13 days to complete (pessimistic) – Worst case scenario Realistic Estimate = (3+4*5+13)/6 = 3+20+13 /6 = 36/ 6 = 6 Days Realistic Estimate will always be closer to Most Likely Estimate.
  • 29. www.GLOBALSKILLUP.com Learning Curve Estimation A common learning curve on Project depicts that the cumulative average time to complete a manual task which involves learning will decrease 20% whenever volume doubles. This is referred to as an 80% learning curve. Let's illustrate the 80% learning curve with a person learning to design and code websites of similar size and complexity. If the first website takes 100 hours, then after the second website the cumulative average time will be 80 hours (80% of 100 hours). The cumulative average of 80 hours consists of 100 hours for the first website plus only 60 hours for the second website resulting in a total of 160 hours divided by 2 websites. After the fourth website the cumulative average time will be 64 hours (80% of 80 hours). After the eighth website the cumulative average will be 51.2 hours (80% of 64 hours). In other words, total time to complete all eight websites will be 409.6 hours (8 websites times an average time of 51.2 hours). Improvements in technology can mean time and cost reductions beyond those in the learning curve. For example, software may become available to assist in the design and coding, computer processing speeds might increase, there may be lower costs of processing and storage, etc. The learning curve is important for setting standards, estimating costs, and establishing selling prices.
  • 30. www.GLOBALSKILLUP.com Estimates may sometimes include the Contingency Reserve (Time reserves or Money buffers) which is included for estimates considering the “known- unknowns” of the estimates. However, these are different from Management Reserve, which are kept for any “unknown unknowns” scope additions by management. Contingency Reserve is used by Project Manager. Management Reserve is used by Stakeholders(Management). ReserveAnalysis
  • 31. www.GLOBALSKILLUP.com 6.6 Develop Schedule Inputs •Schedule Management Plan •Activity List •Activity Attributes •Activity Resource Requirements •Resource Calendars •Project Scope Statement •Risk Register •Risk Breakdown Structure •Enterprise Environmental Factors •Organizational Process Assets Tools & Techniques •Schedule Network Analysis •Critical Path Method •Critical Chain Method •Resource Optimization Technique •Modeling Techniques •Leads And Lags •Schedule Compression •Scheduling Tool Outputs •Schedule Baseline •Project Schedule •Schedule Data •Project Calendars •Project Management Plan Updates •Project Document Updates •Integration •Develop Project Management Plan •Scope •Plan Scope Management •Collect Requirements •Define Scope •Create WBS •Time •Plan Schedule Management •Define Activities •Sequence Activities •Estimate Activity Resources •Estimate Activity Duration •Develop Schedule •Cost •Plan Cost Management •Estimate Costs •Determine Budget •Quality •Plan Quality Management •Human Resource •Plan HR Management •Communications •Plan Communications Management •Risk •Plan Risk Management •Identify Risks •Perform Qualitative Risk Analysis •Perform Quantitative Risk Analysis •Plan Risk Responses •Procurement •Plan Procurement Management •Stakeholder •Plan Stakeholder Management Planning Process It is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create project schedule model. Key benefit is that by entering schedule activities, durations, resources, resource availabilities, and logical relationships into the scheduling tool, it generates a schedule model with planned dates for completing project activities. As the project evolves, it is a continuous process to ensure the schedule is updated for changes.
  • 32. www.GLOBALSKILLUP.com It is a technique that generates the project schedule model. More importantly the analysis will help you identify the points of path convergence and divergence. This helps in schedule compression analysis and ensuring the key points and paths are given due diligence. Schedule Network Analysis
  • 33. www.GLOBALSKILLUP.com The longest duration path of the project is known as the critical path. The duration of the project is determined by activities listed on critical path. Critical Path Method Technique is to identify the minimum longest duration path of project. Any activity on this critical path is called a critical path activity. Any activity other than the critical path activity with total float gives the schedule flexibility without altering the Project end dates. Critical Path Method S F 5 3 6 4 9 8 S F 5+3+6=14 4+9=13 8 Longest Path is Critical Path This path of activities would have a Float of 6 (14-8) This path of activities would have a Float of 1 (14-13)
  • 34. www.GLOBALSKILLUP.com End D 5 F 9 E 8 C 6 Start Early Start(ES) Early Finish(EF) Total Float Task name & Duration Late Start(LS) Late Finish(LF) Branch1: Non Critical Path: ABCF(3+4+6+9= 22) Branch2: Critical Path: ADEF(3+5+8+9=25) – The longest duration path on the project is identified also known as Critical Path. Critical Path Method using Forward Pass & Backward Pass B 4 A 3 Representation of the task in the Project Schedule This method helps the project manager identify the critical activities on the entire project by identification of the Critical Path and also to understand how much delays on tasks is acceptable without impacting the project. In forward pass, each of the activities, Early Start & Early Finish can be arrived for entire project. In backward pass, each of the activities, Late Start & Late Finish can be arrived for entire project duration. After both forward pass & back ward pass, once we have identified ES, EF & LS, LF, one can easily come up with the total float on each of the activities for entire project duration.
  • 35. www.GLOBALSKILLUP.com End 3 8 D 5 16 25 F 9 8 16 E 8 7 13 C 6 Start Early Start(ES) Early Finish(EF) Total Float Activity name & Duration Late Start(LS) Late Finish(LF) Forward Pass (EF = ES + Duration) 3 7 B 4 0 3 A 3 Branch1(ABCF) the last EF is 13. Branch2(ADEF) the last EF is 16. In forward pass, pick the largest previous EF number from the branches, which will also become the ES for merging activity F. Hence, ES(Task F) will be 16. On Activity F ES(Task F) = 16 EF(Task F) = ES(Task F) + Duration(Task F) = 16 + 9 = 25 days On Activity A ES(Task A) = 0. Start the first activity as soon as possible, 0. EF(Task A) = ES(Task A) + Duration(Task A) = 0 + 3 = 3 days Let us calculate ES & EF of all branches first. Branch 1(ABCF) On Activity B EF(Task A) = 3, This value is assigned to ES(Task B) EF(Task B) = ES(Task B) + Duration(Task B) = 3 + 4 = 7 days On Activity C EF(Task B) = 7, This value is assigned to ES(Task C) EF(Task C) = ES(Task C) + Duration(Task C) = 7 + 6 = 13 days Branch2(ADEF) On Activity D EF(Task A) = 3, This value is assigned to ES(Task D) EF(Task D) = ES(Task D) + Duration(Task D) = 3 + 5 = 8 days On Activity E EF(Task D) = 8, This value is assigned to ES(Task E) EF(Task E) = ES(Task E) + Duration(Task E) = 8 + 8 = 16 days Task representation legend
  • 36. www.GLOBALSKILLUP.com End 3 8 D 5 3 8 16 25 F 9 16 258 16 E 8 8 16 7 13 C 6 10 16 Start Early Start(ES) Early Finish(EF) Total Float Activity name & Duration Late Start(LS) Late Finish(LF) Backward Pass (LF – DURATION = LS) 3 7 B 4 6 100 3 A 3 0 3 Branch1(ABCF) the first LS is 6. Branch2(ADEF) the first LS is 3. In backward pass, pick the smallest LS number from the branches(6 or 3?) which will also become the LF for activity A. Hence, LF(Task A) will be 3. On Activity A LS(Task A) = LF(Task A) – Duration(Task A) = 3 – 3 = 0. When ES & LS are ‘0’, that would mean all calculations so far are correct. On Activity F EF(Task F) = 25, This value is assigned to LF(Task F) ES(Task F) = EF(Task F) – Duration(Task F) = 25 – 9 = 16 days Let us calculate LS & LF of all branches now. Branch 1(ABCF) On Activity C LF(Task F) = 16, This value is assigned to LF(Task C) LS(Task C) = LF(Task C) – Duration(Task C) = 16 – 6 = 10 days On Activity B LS(Task C) = 10, This value is assigned to LF(Task B) LS(Task B) = LF(Task B) – Duration(Task B) = 10 – 4 = 6 days Branch2(ADEF) On Activity E LS(Task F) = 16, This value is assigned to LF(Task E) LS(Task E) = LF(Task E) – Duration(Task E) = 16 – 8 = 8 days On Activity D LS(Task E) = 8, This value is assigned to LF(Task D) LS(Task D) = LF(Task D) – Duration(Task D) = 8 – 5 = 3 days Task representation legend
  • 37. www.GLOBALSKILLUP.com A Float (also known as Slack) is the amount of time an activity may be delayed without having any further impact. Free Float is known as the delay on the activity without impacting the subsequent tasks. Total Float is known as the delay on the activity without impacting overall project completion itself. With Floats, Project Manager has little comfort to realign the activity priorities and reschedule for any constraints. Floats on a Project A B C D E F X Y 7 4 9 3 8 1 9 Alternate Path of Activities Critical Path of Activities Free Float of X 8 Free Float of Y 9 + 8 = 17 Total Float of X 8 Total Float of Y All Critical Path Activities (A, B, C, D, E, F) will have Zero Free Float Duration & Zero Total Float Duration End Start
  • 38. www.GLOBALSKILLUP.com End 3 8 0 D 5 3 8 16 25 0 F 9 16 258 16 0 E 8 8 16 7 13 3 C 6 10 16 Start Early Start(ES) Early Finish(EF) Total Float Activity name & Duration Late Start(LS) Late Finish(LF) Let us calculate “Float/Slack” now! 3 7 3 B 4 6 100 3 0 A 3 0 3 Did you notice all activities falling on the critical path? All activities on this critical path by default have Zero Slack or Zero Float. In order to calculate Float on all activities, simply use the LS – ES otherwise LF – EF. On Activity A 0 – 0 = 0. Float on Activity A is 0. On Activity B 6 -3 = 3. Float on Activity B is 3 days On Activity C 10 – 7 = 3. Float on Activity C is 3 days. Please observe, either Activity B or Activity C can be delayed by 3 days, with out impacting the project. This does not mean you can delay both B and C together by 3 & 3 days. On Activity D 3 – 3 = 0. Float on Activity D is 0. On Activity E 8 – 8 = 0. Float on Activity E is 0. On Activity F 16 – 16 = 0. Float on Activity F is 0. Task representation legend
  • 39. www.GLOBALSKILLUP.com Activity: Please perform A4 B6 D9 C7 E4 F5 G6 FinishStart Q1. Identify the Critical path of the project? Q2. How early can we finish the project itself? Q3. How late can we finish the project without impacting Client? Q4. What is the float on the task C? Q5. What would be the new critical path duration if C7 become C14?
  • 40. www.GLOBALSKILLUP.com Activity: Answers A4 B6 D9 C7 E4 F5 G6 FinishStart Q1. Identify the Critical path of the project? A4-D9-F5-G6 Q2. How early can we finish the project itself? 24 Days Q3. How late can we finish the project without impacting Client? On 24th Day Q4. What is the float on the task C? 2 Days Q5. What would be the new critical path duration if C7 become C14? 29 Days 0 4 0 4 18 24 18 24 10 14 14 18 13 18 13 18 4 10 8 14 4 11 6 13 4 13 4 13
  • 41. www.GLOBALSKILLUP.com Project Buffer A B C Project Buffer In reality, Project Completion with no Project Buffer may derail the end market commitments and cause major business reputation loss Ideal Project Completion Ideally, 1 Task is assigned to 1 Project Resource at any given point in time. No multitasking by same resources. G H X Y Project Start Project End Critical Path of Project with Project Buffer makes the project more realistic towards end result. Start-A-B-C-End is the Critical Path. Start-G-H-B-C-End is alternate path. Start-X-Y-B-C-End is alternate path. Many a times, in order to suppress the ambiguity on projects and overcome the uncertainty, Project buffer’s are used. This is simply sometimes an extra timeline after the anticipated Ideal Project Completion. Project Buffers should not be planned thinking resources on the project will not be productive!
  • 42. www.GLOBALSKILLUP.com Feeding Buffer Critical Path of Project with Project Buffer makes the project more realistic towards end result. In addition, all alternate paths collision to critical path activities need to be buffered(feeding buffer) to stop derailment of critical path activities. This will protect the Project timeline by not cascading on each individual critical path activity. Each feeding buffer size must account for uncertainty/ambiguity in the duration of the chain of dependent activities leading up to that buffer. A B C Project Buffer Ideal Project Completion Ideally, 1 Task is assigned to 1 Project Resource at any given point in time. No multitasking by same resources. G H X Y Project Start Project End Feeding Buffer Feeding Buffer Real Project Completion
  • 43. www.GLOBALSKILLUP.com Critical Chain Method In a typical project to calculate the project duration, we would look into Sequencing of Activities through critical path. And this critical path can be considered as the actual project duration, if the assumption of 1 Task Per Resource Per Project is true. However, in reality – we would want to achieve some benefit(including resource optimization) by applying same resource(SME’s sometimes) to work on some activities, such as in the case depicted above. This application of resource over multiple places on the project alters the critical chain of the project. This optimized resource constrained critical path is sometimes known as Critical Chain. Look at task H & Y to be performed by the same resource Person 1 after task A. This would mean that automatically the project critical path which was earlier Start-A-B-C-End this has now altered to become Start-A-H-Y-B-C-End As new Critical Chain path emerges, feeding buffers will change so that critical path activities are not cascaded further. A Person1 B Person1 C Person 4 Project Buffer Ideal Project Completion G Person2 H Person1 X Person 3 Y Person1 Project Start Project End Real Project Completion Feeding Buffer Feeding Buffer
  • 44. www.GLOBALSKILLUP.com Resource Leveling Resource allocation on particular activities may require critical resources which are in high demand. This may impose these critical resources to be over allocated on parallel activities and/or multiple projects. Resource leveling ensures these critical resources are optimally spread across parallel activities and multiple projects so that they don’t need to work 16 hours a day! Resource Smoothing Activities with free float are re-adjusted so that the resources work is evened out. Readjustment of these activities should not cause changes to the project schedule duration. Resource Optimization Techniques 0 10 20 30 40 50 60 70 W1 W2 W3 W4 W5 W6 W7 W8 W9 0 10 20 30 40 50 60 70 W1 W2 W3 W4 W5 W6 W7 W8 W9 40WorkHours 40WorkHours Leveling
  • 45. www.GLOBALSKILLUP.com What-IF Scenario Analysis Process to evaluate the scenarios and their anticipated outcomes which may be either Positive, Negative or Unknown. Based on the outcome of the scenarios, the schedule network analysis is performed which may result into actionable results such as delayed production delivery, impacted financial revenue from the product delivery, extended periods of delivery so on. The outcomes may also be used in adverse situation planning such as in case of a labor union unrest, what may be the contingency plan or response to such situation. Simulation Simulation involves calculation of multiple project durations based on the activity assumptions. This may be based on the 3 point estimates distribution(Optimistic, Most Likely, Pessimistic) or Monte Carlo Simulation. Monte Carlo Simulation is the most common simulation in which a distribution of possible activity durations (based on 3-point estimating – Optimistic, Pessimistic, Most Likely) are defined based on probabilistic random number ranges. This simulation aides the project manager to come up with variations and extremes which in turn helps project manager to inform stakeholders and set rightful expectations on the project schedules and costs. Stakeholders are in advantage situation to make a better informed decision based on at least some probabilistic patterns of simulation instead of pulling numbers from thin air. Modeling Techniques
  • 46. www.GLOBALSKILLUP.com Schedule Compression Techniques are applied to shorten schedule duration of the entire project. Crashing Cost & Schedule tradeoffs are analyzed to determine how to obtain the greatest amount of compression with least incremental cost. As the compression is achieved, the risk and the cost on the particular task dramatically increases. It may not be best to crash always. Methods to apply crashing include adding additional resources approving overtime resources adding incentives for finishing early General practice is to ensure the tasks on critical path are crashed first. Fast Tracking Activities or Phases performed in parallel instead of sequential leading to quick delivery, though increased cost and/or some rework. This only works when the activities overlap on each other for some duration. Schedule Compression Techniques 40 Work Hours done by 1 Person 40 Work Hours done by 2 Person Crashing done by addition of resources to save time
  • 47. www.GLOBALSKILLUP.com Crashing Graphically Terminate (T) Start (S) 7M 6M 8M 7M Critical Path: Longest Duration Path of Project. Any delay on this path of activity will further delay Project itself. Alternate Path: This path if wanted could be delayed by a flexibility of 2M. This flexibility is called Float. Terminate (T) Start (S) 7M 6M 8M 7M Months
  • 48. www.GLOBALSKILLUP.com Crashing Graphically Terminate (T) Start (S) 7M 6M 8M 7M Instead of 1 Person working for 8M, let us say 2 people work on this task to complete in 2M 1 Person 1 Person 1 Person 1 Person Terminate (T) Start (S) 7M 6M 2M 7M With 2 Person working now, duration of task reduced to 2M from 8M, incurring an extra cost of maybe 1 extra machine /extra salary for new person 1 Person 1 Person 1 Person 2 Person New Critical Path is 13M with an Extra Cost of 1 Person This is the new Alternate Path with a Float of 13M-9M = 4M
  • 49. www.GLOBALSKILLUP.com Crashing Exam Example What activities can be crashed? • All Critical Path Activities with Zero Float Activity can be crashed. • Non-Critical Path Activities need not be crashed as they don’t generate any additional benefit to the project schedule compression. Which will be most beneficial activity that can be crashed from the list? • Activity F will be the most beneficial from the activities among B, C, F, H, J since it has Cost per Month of 433 which is the least. Activity Critical Path Activity Activity Float (Slack) Project Float Duration (month) Crash Duration Time Savings Cost (month) Crash Cost Extra Cost Cost Per Month A 1 5 9 1 8 9300 12000 2700 338 B √ 0 5 4 3 1 6800 9000 2200 2200 C √ 0 5 3 2 1 8000 14000 6000 6000 D 2 5 4 3 1 13700 18000 4300 4300 E √ 3 5 6 1 5 6600 10000 3400 680 F √ 0 5 5 2 3 9700 11000 1300 433 G 2 5 8 2 6 7400 8500 1100 183 H √ 0 5 7 3 4 10100 12500 2400 600 I 2 5 10 3 7 12200 17500 5300 757 J √ 0 5 8 4 4 5800 9500 3700 925 Project has a float of 5 months, what would be the best possible crash activity to ensure the 5 months float is saved? • Zero slack critical path activities B, C, F, H, J. • Combining them together to achieve 5 months, looking into Time savings B+C+F, B+J, C+J, B+H, C+H which will be 2200+6000+433, 2200+925, 6000+925, 2200+600, 6000+600 • The best option is to pick the lowest crash cost per month combination which is B+H. What is the cost incurred to crash this Project? • Cost incurred to crash any project would be to crash all the critical path zero slack activities and utilize the complete Project float value(in this case 5 Months) to pick the lowest crash cost per month combination as calculated earlier. • So the combination is B+H which is 2200+600 = 2800 (Crash cost of the project)
  • 50. www.GLOBALSKILLUP.com Fast Tracking Example Days -> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 "A" Task of 6 days A A A A A A "B" Task of 9 days B B B B B B B B B "C" Task of 12 days C C C C C C C C C C C C "D" Task of 5 days D D D D D Days -> 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 "A" Task of 6 days A A A A A A If "B" can be fast tracked by 4d "B" Task of 9 days B B B B B B B B B If "C" can be fast tracked by 8d "C" Task of 12 days C C C C C C C C C C C C If "D" can be fast tracked by 4d "D" Task of 5 days D D D D D 4 days 8 days 4 days Total Task Duration = 6+9+12+5 = 32 days Total Fast Tracked Task Duration = 16 days Duration Saved from Fast tracking Fast Tracking applicable for overlapping activities & phases only What is the fast tracked duration for above example? • Yes, that’s correct. It is 16 days.
  • 51. www.GLOBALSKILLUP.com 6.7 Control Schedule Inputs •Project Management Plan •Project Schedule •Work Performance Data •Project Calendars •Schedule Data •Organizational Process Assets Tools & Techniques •Performance Reviews •Project Management Software •Resource Optimization Techniques •Modeling Techniques •Leads and Lags •Schedule Compression •Scheduling Tool Outputs •Work Performance Information •Schedule Forecasts •Change Requests •Project Management Plan Updates •Project Document Updates •Organizational Process Assets Updates •Integration •Monitor and Control Project Work •Perform Integrated Change Control •Scope •Validate Scope •Control Scope •Time •Control Schedule •Cost •Control Costs •Quality •Control Quality •Human Resource •Communications •Control Communications •Risk •Monitor & Control Risks •Procurement •Control Procurements •Stakeholder •Control Stakeholder Management Monitoring & Controlling Process It is the process of managing the project schedule and controlling the schedule to ensure the project is delivered with in the planned schedule timeframe. Key benefit includes the project schedule is well within the planned schedule timeframe. Using control schedule the project can be put back in to track by corrective and preventive actions.
  • 52. www.GLOBALSKILLUP.com It is the data required to manage and control the Schedule itself. It is generally observed that alternative schedules arising out of the contingency or due to the funding limit reconciliation are parked here. Schedule data includes the milestones, schedule related activities, identified risks, assumptions and schedule related constraints. Data could also include the histograms whether the resource leveled or not resource leveled. Schedule Data
  • 53. www.GLOBALSKILLUP.com Performance Review of work in progress and work accomplished may be carried in perspective of: What is accomplished (actual function/story points to planned function/story points) at what cost (actual amount of money or percentage wise) when it is done (actual hours/dates or the deviation dates) In the Schedule Performance reviews: actual start date compared to the planned start date actual end date compared to the planned end date percentage work accomplished to planned accomplishment Various Techniques may be used for performance reviews: Trend Analysis Critical Path Method Critical Chain Method EVM(Earned Value Management) Performance Reviews
  • 54. www.GLOBALSKILLUP.com Schedule Variance (SV) and Schedule Performance Index (SPI) are the two important Schedule Work Performance Information which need to be kept in radar to have the control on the Schedule. Continuous monitoring of these two parameters help one understand the progress being made and the performance of the project on schedule, allowing the recommended corrective and preventive actions. Progress reports on the schedule during the control schedule are continuously reported to the stakeholders on desired intervals. Work Performance Information Project Status Report
  • 55. www.GLOBALSKILLUP.com Schedule Forecasts are future predicted timelines of the schedule, it may be for a task, activity, module or for a project. Mainly the Project schedule forecast is of our importance, however, at times it may be of critical task, activity or a module as well. Scheduled forecast is arrived based on the already work completed, work in progress and work in future to be accomplished. In other terms, it is progress against schedule baseline and the computed time estimate to complete(ETC). The past performance indicators reflect the future course of project work accomplishment. Forecasts are helpful to determine if the project schedule is within the defined tolerance levels of the schedule ranges. Schedule Forecasts
  • 57. www.GLOBALSKILLUP.com THIS BRINGS TO “TIME MANAGEMENT” COMPLETION. From what we have understood so far is:  7 Time Management Knowledge Area Processes  Identified their Inputs, Tools & Techniques, Outputs Chapter 6
  • 58. www.GLOBALSKILLUP.com PMP Group Trainings across India Bangalore | Hyderabad | Pune | Delhi | Chennai | Mumbai | Noida | Gurgaon Online Trainings Too
  • 59. www.GLOBALSKILLUP.com Acknowledgements & Disclaimer PMI, PMBOK, PMP, CAPM, PgMP, PMI- ACP, PMI-RMP, PMI-SP are registered marks of Project Management Institute, Inc. All registered trademarks, symbols, names are marks of their respective owners and acknowledged.