2. Fixed Beds: Catalyst Discharge
Issues to consider
• reduced catalysts: self heating
HTS, MTS, LTS and methanation
• inert discharge or in situ
oxidation/passivation
• in situ oxidation with O2 or passivation with
H2O
• carbon contamination: self
heating/pyrophoric
possible for HDS and ZnO
• inert or wet discharge if necessary
• agglomerated catalysts
cause usually fouling or wetting
• physical breakage may be required
Catalyst history affects procedure
3. Fixed Beds: Catalyst Discharge
Preparation
• select discharge method
• cool and purge reactor
• oxidize or passivate catalyst (if
required)
• water can be a weak oxidant and/or
inerting medium
beware of evolved H2 hazard
• metal + H2O => metal oxide + H2
water fills catalyst pores
• slows rate of O2 diffusion
4. Fixed Beds: Catalyst Discharge
In situ oxidation with air
• purge all combustibles from process
• cool with steam or nitrogen
at 600-1000 h-1 space velocity
to 204 oC (400 oF) for HTS and 177 oC (350
oF) for LTS
• meter 1% air into bed and monitor
exotherm
31 oC (55 oF)/% air for HTS; 14 oC (25
oF)/% air for LTS or MTS
• Once exotherm stable, slowly increase
air
up to 3 % initially and monitor exotherm
hold peak temperature below hardware
limits
5. Fixed Beds: Catalyst Discharge
In situ oxidation with air
(cont.)
• continue to increase air level
keep below vessel or piping temperature
limitations
• oxidation is complete when
exotherm has passed through bed
air level is 7-10%
• replace steam or nitrogen flow with air
flow
• cool catalyst in air to discharge
temperature
below 38 oC (110 oF) for dry methods
below 93 oC (200 oF) for wet method
6. Fixed Beds: Catalyst Discharge
• Top discharge by
vacuum
– Man enters from top
under vessel entry
permit
– Vacuum hose is 4 - 6”
dia (10 - 15 cm)
– Support material > 1”
dia (2.5 cm) has to be
removed by hand
Man works evenly
across and down bed
For inert discharge, N2
is cooled and recycled
7. Fixed Beds: Catalyst Discharge
Bottom discharge - dry
• most common method
• requires a proper dump chute and
containers (bins or drums) for
discharged catalyst
• keep positive N2 pressure for inert
discharge
catalyst bins must be inerted
• water hose available in case of heat
generation
wet catalyst during discharge if required
8. Fixed Beds: Catalyst Discharge
Bottom discharge - wet
• less common
• cool catalyst below 93 oC (200 oF)
• ensure suitable isolations for H2O
• fill vessel with water
• dump vessel contents through bottom
drain valve
• remove catalyst through bottom manway
discharge of wet catalyst is very messy
water may not completely oxidise the catalyst
9. Fixed Beds: Catalyst Handling
& Loading
Vessel inspection
• inspect vessel for stress damage
• thermocouples: check condition if
present
document T/C locations relative to fixed
point
• eg inlet flange or tangent line
• support grids: check condition if
present
correct any damaged clips, grid blinding, etc
• reactor clean and dry
10. Fixed Beds: Catalyst Handling
& Loading
Pre-loading checks
• ensure vessel is free from rubbish
• bottom manway door and spider in place
• inspect reclaimed support/hold down
materials
remove broken or extraneous contaminants
• inspect new catalyst
type and condition
• inspect new support/hold down materials
type and condition
ceramic versus alumina
11. Fixed Beds: Catalyst Handling
& Loading
Pre-loading checks (cont.)
• appropriate personal protection available
- and is used - inside and outside vessel
eg dust masks
• for vessel entry
air tests
breathing air and/or air movers
usual stringent vessel entry precautions
boards to support worker inside
• minimises catalyst damage
12. Fixed Beds: Catalyst Handling
& Loading
Loading methods
• manual
most common by far
• pneumatic
specialised techniques (eg from Technivac)
not considered further
• dense loading
specialised technique (eg from Petroval
DENSICATTM)
not considered further
13. Fixed Beds: Typical Loading
6” (15cm) of
1”- 2” balls
(25 - 50mm)
Catalyst/
absorbent
6” (15cm) of
0.5” balls
(13mm)
4” (10cm) of
0.25”- 0.5” balls
(6 - 13mm)
6” (15cm) of
1”balls
(25mm)
1”- 2” balls
(25 - 50mm)
Support grid
Spider
14. Fixed Beds: Manual Loading
• Key points
– use hopper or
supersack with
attached sock
– move sock to ensure
uniform distribution
– catalyst freefall
• maximum 3 ft (1m)
• minimum 1 ft (0.3 m)
– try to keep sock full
– cut sock as vessel
fills
15. Fixed Beds: Manual Loading
Charging tube -
fixed position
More smaller particles:
higher pressure drop
Support Grid
Catalyst Support
More larger particles:
lower pressure drop
Distribution issue