SlideShare ist ein Scribd-Unternehmen logo
1 von 15
A Presentation On Load Scheduling &
Load Shedding
Presenting By:
Gehlot Darshan
B.Tech 4th Year
Guided By:
Prof. R.R. Joshi
Head of Department
Department of Electrical Engineering
College of Technology and Engineering, Udaipur
Contents
 Introduction
 What is load
 Load Scheduling in Power Systems
 Need for load Schedule
 Load Shedding
 Effect of excess load
 Reason For Instability
 Advantages & Disadvantages
 Conclusion
Introduction
• Now a days electricity loads are
increasing day by day. So it is
important to manage the supply
side for optimal operation.
Load
• An electrical load is an electrical
component or portion of a circuit
that consumes (active) electric
power. This is opposed to a power
source, such as a battery or
generator, which produces power
Load Scheduling in
Power Systems
• The electrical load scheduling is the
process of estimating the instantaneous
loads operating in an installation.
• The load schedule provides the load for
the particular installation in terms of
apparent, reactive and active power (kVA,
kVAR and kW) and usually carried out at
the sub facility area or at the switchboard.
Cont.
 The load schedule preparation should ideally be the first task to perform
during the electrical system design stage since it relates to the equipment
sizes and other power system requirements.
 Load scheduling is one form of load management action that allows
companies to save energy by minimizing their demand.
 In order to have an efficient load schedule operation, the energy manager or
business should conduct power logging and record all sessions so as to
measure the usage of energy over a specific time.
Need for load Schedule
 Preparing an electrical load schedule eases the work of
designing the system in terms of equipment sizing as well as
in power system studies. The process requires an
understanding of the installation, all the equipment that will
be installed, frequency of using the equipment and their
importance or criticality.
 The load schedule should ideally be started as early as is
practically possible in the design process. One requires an
idea of the main voltage levels required in the installation as
well as all other details of the function of the facility or
building, and the nature of process and non process loads.
Load Shedding
• Load shedding in electrical supply
networks is a controlled process in
which the utility company drops off
part of the load in order to balance the
demand and the generated capacity.
• This is often done whenever there is
excess load on , it involves
disconnecting or shedding some
circuits to prevent an overload
condition.
Effect of excess load
 Stress on the generating equipment.
 It slows down the prime movers, associated generators and other parts of the system as they attempt to cope
with the excess load.
 Protection systems may interrupt the supply due to the excess current resulting from the overload.
 The higher load may also lead to a lower generating and supply frequency.
 The reduced frequency can damage the steam turbines as well as the frequency sensitive load.
Reason For Instability
 Inefficiency and lack of maintenance of generating and distribution systems
 Increased population
 Improved living standards
 Lack of planning
Load Shedding Procedures
 Utility companies use scheduled load shedding so that the available electricity is fairly
shared by the consumers. This involves switching off some parts of the electricity supply
network in a planned and controlled process. They alternate between different parts and
time schedules to ensure that at least everyone gets power at a specific time. By dropping
off the excess load, the power system remains stable.
 Some smaller generators such as those used in domestic applications have inbuilt load
shedding capabilities. This becomes necessary when these are used as standby
generators, in the event of a utility power outage, the emergency supply kicks in. And since
all the circuits and appliances are connected, the load demand may exceed the generator
capacity. When the load becomes too much, the generator sheds some of the smaller non-
critical circuits automatically in an attempt to reduce the load.
Advantages
 Prevents overloading and damage of the power generators
 Prevents instability and system collapse of the electrical generation
and distribution systems
 Ensures that consumers or parts of the network have poweras
opposed to a total blackout.
 The planned schedules ensure that available capacity is shared fairly
and each consumer gets power at one time or another.
 It serves as a warning to the utility hence forcing them to increase
capacity, and efficiency so as to meet the demand.
Disadvantages
• LOSS OF PRODUCTION
• INCREASED CRIME DUE TO
DARKNESS AND
LACK OF JOBS
• THE UTILITIES MAY NOT
INCREASED THE OUTPUT
• RESTORING THE LOAD MAY CAUSE
MORE INSTABILITIES
Conclusion
 Electrical load scheduling is an essential practice that an electrical technician should
carry out at the initial stages of an electrical power installation. The load schedule
provides data that isa close estimate of the amount of power consumed for normal
and peak loads and anything in between
 Load shedding is one of the last things that a utility company should look at. It leads
to frustrated customers and loss of revenue for the consumers as production drops.
In addition,it may cause equipment damage.
 Electricity companies should ensure that they have enough capacity to meet normal
andpeak demands. This can be achieved by planning for future electricity demand
and progressively upgrading the generating equipment, maintain existing systems,
reducing transmission losses and increasing efficiency in the entire system.
Load shedding and load scheduling (ppt)

Weitere ähnliche Inhalte

Was ist angesagt?

Inspection of Electrical Installations in Homes
Inspection of Electrical Installations in HomesInspection of Electrical Installations in Homes
Inspection of Electrical Installations in HomesLeonardo ENERGY
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSPartha Parida
 
An Optimal Power Flow (OPF) Method with Improved Voltage Stability Analysis
An Optimal Power Flow (OPF) Method withImproved Voltage Stability AnalysisAn Optimal Power Flow (OPF) Method withImproved Voltage Stability Analysis
An Optimal Power Flow (OPF) Method with Improved Voltage Stability AnalysisNiraj Solanki
 
Transformer protection
Transformer protectionTransformer protection
Transformer protectionjawaharramaya
 
UNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMUNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMerramansaini1947
 
Introduction to power system analysis
Introduction to power system analysisIntroduction to power system analysis
Introduction to power system analysisRevathi Subramaniam
 
Fault Calculations
Fault CalculationsFault Calculations
Fault Calculationsmichaeljmack
 
ETAP - Load flow and panel rev2014-1
ETAP - Load flow and panel   rev2014-1ETAP - Load flow and panel   rev2014-1
ETAP - Load flow and panel rev2014-1Himmelstern
 
Power system stability
Power system stabilityPower system stability
Power system stabilityBalaram Das
 
power factor correction soham+niraj
power factor correction soham+nirajpower factor correction soham+niraj
power factor correction soham+nirajsoham patel
 
WIDE AREA MONITORING SYSTEMS(WAMS)
WIDE AREA MONITORING SYSTEMS(WAMS)WIDE AREA MONITORING SYSTEMS(WAMS)
WIDE AREA MONITORING SYSTEMS(WAMS)Vikram Purohit
 
1. power system losses introduction
1. power system losses introduction1. power system losses introduction
1. power system losses introductionYusuf A. KHALIL
 

Was ist angesagt? (20)

Inspection of Electrical Installations in Homes
Inspection of Electrical Installations in HomesInspection of Electrical Installations in Homes
Inspection of Electrical Installations in Homes
 
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMSSWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
SWITCHYARD EQUIPMENTS & PROTECTION SYSTEMS
 
An Optimal Power Flow (OPF) Method with Improved Voltage Stability Analysis
An Optimal Power Flow (OPF) Method withImproved Voltage Stability AnalysisAn Optimal Power Flow (OPF) Method withImproved Voltage Stability Analysis
An Optimal Power Flow (OPF) Method with Improved Voltage Stability Analysis
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
Power systems İntroduction
Power systems İntroductionPower systems İntroduction
Power systems İntroduction
 
UNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEMUNSYMMETRICAL FAULTS IN POWER SYSTEM
UNSYMMETRICAL FAULTS IN POWER SYSTEM
 
Introduction to power system analysis
Introduction to power system analysisIntroduction to power system analysis
Introduction to power system analysis
 
Static var compensator
Static var compensatorStatic var compensator
Static var compensator
 
Power quality
Power qualityPower quality
Power quality
 
Blackout
BlackoutBlackout
Blackout
 
Fault Calculations
Fault CalculationsFault Calculations
Fault Calculations
 
ETAP - Load flow and panel rev2014-1
ETAP - Load flow and panel   rev2014-1ETAP - Load flow and panel   rev2014-1
ETAP - Load flow and panel rev2014-1
 
Power system stability
Power system stabilityPower system stability
Power system stability
 
Power Quality
Power QualityPower Quality
Power Quality
 
Fault analysis
Fault analysisFault analysis
Fault analysis
 
Swing equation
Swing equationSwing equation
Swing equation
 
power factor correction soham+niraj
power factor correction soham+nirajpower factor correction soham+niraj
power factor correction soham+niraj
 
What is load management
What is load managementWhat is load management
What is load management
 
WIDE AREA MONITORING SYSTEMS(WAMS)
WIDE AREA MONITORING SYSTEMS(WAMS)WIDE AREA MONITORING SYSTEMS(WAMS)
WIDE AREA MONITORING SYSTEMS(WAMS)
 
1. power system losses introduction
1. power system losses introduction1. power system losses introduction
1. power system losses introduction
 

Ähnlich wie Load shedding and load scheduling (ppt)

Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingBIJAY NAYAK
 
What are Ancillary Services In Power System ?
What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?
What are Ancillary Services In Power System ?Power System Operation
 
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Living Online
 
Electrical Substation and Switchyard Design
Electrical Substation and Switchyard DesignElectrical Substation and Switchyard Design
Electrical Substation and Switchyard DesignLiving Online
 
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...IRJET Journal
 
Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptxPoojaAnupGarg
 
EDS Unit 1 (Part 1).pptx
EDS Unit 1 (Part 1).pptxEDS Unit 1 (Part 1).pptx
EDS Unit 1 (Part 1).pptxDr. Rohit Babu
 
Solar power plant at peak load by smart dsiatribution system
Solar power plant at peak load by smart dsiatribution systemSolar power plant at peak load by smart dsiatribution system
Solar power plant at peak load by smart dsiatribution systemeSAT Publishing House
 
IRJET- Analysis of Demand Side Management of Distribution Systems
IRJET-  	  Analysis of Demand Side Management of Distribution SystemsIRJET-  	  Analysis of Demand Side Management of Distribution Systems
IRJET- Analysis of Demand Side Management of Distribution SystemsIRJET Journal
 
Automatic generation control problem in interconnected power systems
Automatic generation control problem in interconnected power systemsAutomatic generation control problem in interconnected power systems
Automatic generation control problem in interconnected power systemsAlexander Decker
 
Integration of Renewable Energy In Grid
Integration of Renewable Energy In GridIntegration of Renewable Energy In Grid
Integration of Renewable Energy In GridTejaswi Shukla
 
IRJET- Analysis of Load Frequency Control for a Distributed Grid System Invol...
IRJET- Analysis of Load Frequency Control for a Distributed Grid System Invol...IRJET- Analysis of Load Frequency Control for a Distributed Grid System Invol...
IRJET- Analysis of Load Frequency Control for a Distributed Grid System Invol...IRJET Journal
 
Unit V part-2 windfarm grid issues.pptx
Unit V part-2 windfarm grid issues.pptxUnit V part-2 windfarm grid issues.pptx
Unit V part-2 windfarm grid issues.pptxsundeepsiddula
 
IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...
IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...
IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...IRJET Journal
 
144624132-Sizing-a-PV-system-ppt.ppt
144624132-Sizing-a-PV-system-ppt.ppt144624132-Sizing-a-PV-system-ppt.ppt
144624132-Sizing-a-PV-system-ppt.pptBlessyJoy18
 
Power factor correction of 6.6 kv distribution line in lc11 rmhs department, ...
Power factor correction of 6.6 kv distribution line in lc11 rmhs department, ...Power factor correction of 6.6 kv distribution line in lc11 rmhs department, ...
Power factor correction of 6.6 kv distribution line in lc11 rmhs department, ...eSAT Publishing House
 
IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...
IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...
IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...IRJET Journal
 
Power factor
Power factorPower factor
Power factorwkugubre
 

Ähnlich wie Load shedding and load scheduling (ppt) (20)

Seminar on load scheduling and load shedding
Seminar on load scheduling and load sheddingSeminar on load scheduling and load shedding
Seminar on load scheduling and load shedding
 
What are Ancillary Services In Power System ?
What are Ancillary Services In Power System ?What are Ancillary Services In Power System ?
What are Ancillary Services In Power System ?
 
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
Emergency Power Supplies: Electrical Distribution Design, Installation and Co...
 
Unit-5.pptx
Unit-5.pptxUnit-5.pptx
Unit-5.pptx
 
Electrical Substation and Switchyard Design
Electrical Substation and Switchyard DesignElectrical Substation and Switchyard Design
Electrical Substation and Switchyard Design
 
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
Power Factor Control at ABA Control 33/11kV Injection Substation Using Auto T...
 
Energy Efficiency in Electrical Systems.pptx
Energy  Efficiency in Electrical Systems.pptxEnergy  Efficiency in Electrical Systems.pptx
Energy Efficiency in Electrical Systems.pptx
 
EDS Unit 1 (Part 1).pptx
EDS Unit 1 (Part 1).pptxEDS Unit 1 (Part 1).pptx
EDS Unit 1 (Part 1).pptx
 
Solar power plant at peak load by smart dsiatribution system
Solar power plant at peak load by smart dsiatribution systemSolar power plant at peak load by smart dsiatribution system
Solar power plant at peak load by smart dsiatribution system
 
IRJET- Analysis of Demand Side Management of Distribution Systems
IRJET-  	  Analysis of Demand Side Management of Distribution SystemsIRJET-  	  Analysis of Demand Side Management of Distribution Systems
IRJET- Analysis of Demand Side Management of Distribution Systems
 
Automatic generation control problem in interconnected power systems
Automatic generation control problem in interconnected power systemsAutomatic generation control problem in interconnected power systems
Automatic generation control problem in interconnected power systems
 
Final ppt
Final pptFinal ppt
Final ppt
 
Integration of Renewable Energy In Grid
Integration of Renewable Energy In GridIntegration of Renewable Energy In Grid
Integration of Renewable Energy In Grid
 
IRJET- Analysis of Load Frequency Control for a Distributed Grid System Invol...
IRJET- Analysis of Load Frequency Control for a Distributed Grid System Invol...IRJET- Analysis of Load Frequency Control for a Distributed Grid System Invol...
IRJET- Analysis of Load Frequency Control for a Distributed Grid System Invol...
 
Unit V part-2 windfarm grid issues.pptx
Unit V part-2 windfarm grid issues.pptxUnit V part-2 windfarm grid issues.pptx
Unit V part-2 windfarm grid issues.pptx
 
IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...
IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...
IRJET- Improved Electrical Power Supply to Trans-Amadi Industrial Layout, Por...
 
144624132-Sizing-a-PV-system-ppt.ppt
144624132-Sizing-a-PV-system-ppt.ppt144624132-Sizing-a-PV-system-ppt.ppt
144624132-Sizing-a-PV-system-ppt.ppt
 
Power factor correction of 6.6 kv distribution line in lc11 rmhs department, ...
Power factor correction of 6.6 kv distribution line in lc11 rmhs department, ...Power factor correction of 6.6 kv distribution line in lc11 rmhs department, ...
Power factor correction of 6.6 kv distribution line in lc11 rmhs department, ...
 
IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...
IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...
IRJET- Review of Power Quality Problem Improvement by Integration of Solar PV...
 
Power factor
Power factorPower factor
Power factor
 

Kürzlich hochgeladen

CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Bookingroncy bisnoi
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoordharasingh5698
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01KreezheaRecto
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringmulugeta48
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 

Kürzlich hochgeladen (20)

Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Walvekar Nagar Call Me 7737669865 Budget Friendly No Advance Booking
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoorTop Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
Top Rated Call Girls In chittoor 📱 {7001035870} VIP Escorts chittoor
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 

Load shedding and load scheduling (ppt)

  • 1. A Presentation On Load Scheduling & Load Shedding Presenting By: Gehlot Darshan B.Tech 4th Year Guided By: Prof. R.R. Joshi Head of Department Department of Electrical Engineering College of Technology and Engineering, Udaipur
  • 2. Contents  Introduction  What is load  Load Scheduling in Power Systems  Need for load Schedule  Load Shedding  Effect of excess load  Reason For Instability  Advantages & Disadvantages  Conclusion
  • 3. Introduction • Now a days electricity loads are increasing day by day. So it is important to manage the supply side for optimal operation.
  • 4. Load • An electrical load is an electrical component or portion of a circuit that consumes (active) electric power. This is opposed to a power source, such as a battery or generator, which produces power
  • 5. Load Scheduling in Power Systems • The electrical load scheduling is the process of estimating the instantaneous loads operating in an installation. • The load schedule provides the load for the particular installation in terms of apparent, reactive and active power (kVA, kVAR and kW) and usually carried out at the sub facility area or at the switchboard.
  • 6. Cont.  The load schedule preparation should ideally be the first task to perform during the electrical system design stage since it relates to the equipment sizes and other power system requirements.  Load scheduling is one form of load management action that allows companies to save energy by minimizing their demand.  In order to have an efficient load schedule operation, the energy manager or business should conduct power logging and record all sessions so as to measure the usage of energy over a specific time.
  • 7. Need for load Schedule  Preparing an electrical load schedule eases the work of designing the system in terms of equipment sizing as well as in power system studies. The process requires an understanding of the installation, all the equipment that will be installed, frequency of using the equipment and their importance or criticality.  The load schedule should ideally be started as early as is practically possible in the design process. One requires an idea of the main voltage levels required in the installation as well as all other details of the function of the facility or building, and the nature of process and non process loads.
  • 8. Load Shedding • Load shedding in electrical supply networks is a controlled process in which the utility company drops off part of the load in order to balance the demand and the generated capacity. • This is often done whenever there is excess load on , it involves disconnecting or shedding some circuits to prevent an overload condition.
  • 9. Effect of excess load  Stress on the generating equipment.  It slows down the prime movers, associated generators and other parts of the system as they attempt to cope with the excess load.  Protection systems may interrupt the supply due to the excess current resulting from the overload.  The higher load may also lead to a lower generating and supply frequency.  The reduced frequency can damage the steam turbines as well as the frequency sensitive load.
  • 10. Reason For Instability  Inefficiency and lack of maintenance of generating and distribution systems  Increased population  Improved living standards  Lack of planning
  • 11. Load Shedding Procedures  Utility companies use scheduled load shedding so that the available electricity is fairly shared by the consumers. This involves switching off some parts of the electricity supply network in a planned and controlled process. They alternate between different parts and time schedules to ensure that at least everyone gets power at a specific time. By dropping off the excess load, the power system remains stable.  Some smaller generators such as those used in domestic applications have inbuilt load shedding capabilities. This becomes necessary when these are used as standby generators, in the event of a utility power outage, the emergency supply kicks in. And since all the circuits and appliances are connected, the load demand may exceed the generator capacity. When the load becomes too much, the generator sheds some of the smaller non- critical circuits automatically in an attempt to reduce the load.
  • 12. Advantages  Prevents overloading and damage of the power generators  Prevents instability and system collapse of the electrical generation and distribution systems  Ensures that consumers or parts of the network have poweras opposed to a total blackout.  The planned schedules ensure that available capacity is shared fairly and each consumer gets power at one time or another.  It serves as a warning to the utility hence forcing them to increase capacity, and efficiency so as to meet the demand.
  • 13. Disadvantages • LOSS OF PRODUCTION • INCREASED CRIME DUE TO DARKNESS AND LACK OF JOBS • THE UTILITIES MAY NOT INCREASED THE OUTPUT • RESTORING THE LOAD MAY CAUSE MORE INSTABILITIES
  • 14. Conclusion  Electrical load scheduling is an essential practice that an electrical technician should carry out at the initial stages of an electrical power installation. The load schedule provides data that isa close estimate of the amount of power consumed for normal and peak loads and anything in between  Load shedding is one of the last things that a utility company should look at. It leads to frustrated customers and loss of revenue for the consumers as production drops. In addition,it may cause equipment damage.  Electricity companies should ensure that they have enough capacity to meet normal andpeak demands. This can be achieved by planning for future electricity demand and progressively upgrading the generating equipment, maintain existing systems, reducing transmission losses and increasing efficiency in the entire system.