SlideShare ist ein Scribd-Unternehmen logo
1 von 32
INTERNAL ADVISOR EXTERNAL ADVISOR
OVERVIEW
INTRODUCTION
DATA COLLECTION AND METHDOLOGY
RESULTS & DISCUSSIONS
CONCLUSION
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
 Company Profile:
Alsons AutoParts (Pvt.) Ltd. Is an ISO 9001 and ISO-14001-2004 Certified
company which was established in 1988, and has become a leading name in
the Pakistan Automotive Industry.
 Major Products:
Alsons AutoParts Pvt. Ltd. consists of three main products in their manufacturing
plant, which are given below;
 Plastic Injection Moulding Products
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
 Sheet Metal Products:
 Automotive assembly products:
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
 Existing Situation:
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
The existing situation of press shop is that they have a targeted schedule
of the production of 1200 plates daily for Suzuki with a Takt time of
0.375 min/pcs which is difficult to achieve so in order to meet the
customer demand they go for over time.
The company experiences the following issues in the manufacturing of
backing plate at press shop.
 Lack of Traceability of product.
 Greater lead-time.
 Unnecessary stoppages
 Greater Takt time
 Issues:
INTRODUCTION:
Industries are in the favor to get more capital and resources to improve their
productivity.
It is necessary to optimize their capital, time and working environment. Industries
needed improvement tools to optimize its processes to attain more capable results.
Many improvement techniques and tools were developed and adapted to work in the
different types of business.
Now day’s industries focused on more production with higher efficiency in less lead
time. The companies focused mainly on customer satisfaction. In an increasingly
competitive environment, many manufacturing firms are looking for a winning card
over their competitor. Manufacturers have to understand that the conventional
production system has to connect with the lean tools and techniques.
Lean manufacturing system was developed by Toyota, Japan.
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
Project Background:
A shorter lead time results into better utilization of manufacturing resources,
quick adaptation to customer’s demand, reduced cost and better products.
Today companies are intensively indulging in activities to reduce their
production lead times.
Our Team, keeping in mind, the importance of a short lead time, therefore we
worked in Alsons AutoParts with the intention to reduce Production Lead time.
Technique that the team adopted was Value Stream Mapping .
Value stream mapping is the technique of Lean Manufacturing.
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
VALUE STREAM MAPPING:
Value Stream Mapping (VSM) tool shows all the activities, from supply to
final product through the different processing steps.In other words it is a
sketch of a production line.
Value stream map is the technique that bring the all processing steps at one
place. It shows the big picture of shop floor rather than individual processes
and improving the each area at the production line. It is used to draw
attention to different wastes and eliminating them in Future State Map.
It is necessary that every process as closely as possible produces only what
its customers need. The existing processes have some types the waste in a
production line which is the result of product design and machinery.
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
Lead Time:
• A lead time is the time interval between the initiation and
execution of a process.
• In industry, lead time reduction is an important part of lean manufacturing
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
Critical inputs for the VSM:
The following data are considered to be important in a value stream
mapping project.
• Cycle time
• Number of operators
• Waiting time
• Process time per shift
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
Methodology:
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
1.Selection of the Product:
The selection of the product is very important step in Value Stream Mapping.
Baking plate is the critical product of the Alsons AutoParts due to its
requirement and demand by the Suzuki Automobiles.
There is the lack of traceability, scheduling, greater lead time, unnecessary
stoppages, etc. Due to these problems the completion of the customer
demand on time will be difficult.
After observing all these major issues which will directly effects the whole
production system .BAKING PLATE is our critical product for working for
the improvement
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
2.Collection of Relevant Data:
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
I. Product flow within press shop.
II. Cycle time of each process.
III. Identification of bottlenecks.
IV. Transportation of product within press shop.
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
I. Product Flow within Press Shop:
Process Cycle time
Shearing 13sec
Blanking 23sec
Forming 12sec
Collar Bending 11sec
Flattening 8sec
Piercing 1 10sec
Piercing 2 10sec
Chamfering 11sec
CO2 Welding 20sec
Remering 10sec
Spot Welding 28sec
Debeurring 12sec
 Flattening
It has the capacity of 960 pieces per shift which is a bottleneck for press
shop.
Reason:
Lack of trollies at the workstation, which stops the production after 100
pieces which creates bottleneck for production system.
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
 Spot Welding:
It has the capacity of 450pieces/shift by each machine. Press
shop has 2 spot welding machines which produces 900 pieces
per shift.
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
IV. Transportation Method:
1-With the help of trollies.
2-Fork lifter.
3-Manual lifter
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
3.Current State Map:
Description:
• The current state map shows that the backing plate has the
production lead time of 12.6 hours.
• It clearly shows the unwanted Waiting Time between each
workstation .
• It shows the big picture about the real time process &
performance of the production process.
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
4.Identification the nature of wastes in the process:
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
Wastage of time:
• Un necessary usage of lifter between the process shearing &
blanking which causes delays in production up to 1 hour due to un
availability of lifter at the press shop.
• Lack of availability of trollies at each work station which causes
the process to stop & wait for the raw material inventory .
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
5.Future State Map
Future Product Flow Layout:
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
Description:
• Lead time reduced about 2.25 hours i.e. 20% reduction
which reduces the companies overtime cost.
• Reduced the transportation between the processes.
• Kaizen burst:
1)Machine Relocation
2)Material handling equipments
3)New machine.
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
6.Suggestion for Improvements:
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
Ergonomic trollies should be used
which provides effective
transportation within press shop.
I. Material Handling Equipments
II.Machine Relocation:
Relocation of blanking machine near to shearing machine so that the
operation of lifter will be eliminate which reduces:
1- Transportation time.
2- Transportation cost.
3- Process waiting due to un availability of lifter.
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
III. New Machine
 Another Spot Welding Machine should be install to fulfill the requirements.
 Cooling system must be maintained properly for effective working.
Good quality electrodes will help to increase productivity & on time
delivery of products.
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
Conclusion:
The project was to reduce the production lead time, for this purpose the team
selected lean manufacturing tool Value Stream Mapping.
In addition to reduction of lead time, following benefits were expected after
the completion of the project.
 Improved productivity
 Determination of Value stream
 Better understanding of Wastes and their causes
 A roadmap towards an efficient, lean production line
OVERVIEW INTRODUCTION
DATA
COLLECTION &
METHODOLOGY
RESULTS &
DISCUSSIONS
CONCLUSION
VSM (Lean Manufacturing) Project PPT

Weitere ähnliche Inhalte

Was ist angesagt?

Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream Mapping
mahawar1987
 

Was ist angesagt? (20)

8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
 
Lean Manufacturing
Lean Manufacturing Lean Manufacturing
Lean Manufacturing
 
Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream Mapping
 
World Class Manufacturing
World Class Manufacturing World Class Manufacturing
World Class Manufacturing
 
Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream Mapping
 
Cycle time reduction
Cycle time reductionCycle time reduction
Cycle time reduction
 
JIT case study of Toyota
JIT case study of ToyotaJIT case study of Toyota
JIT case study of Toyota
 
Learning Six Sigma
Learning Six SigmaLearning Six Sigma
Learning Six Sigma
 
Value stream mapping
Value stream mappingValue stream mapping
Value stream mapping
 
Core Lean Tools
Core Lean ToolsCore Lean Tools
Core Lean Tools
 
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
 
Lean Manufacturing
Lean ManufacturingLean Manufacturing
Lean Manufacturing
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
 
Dmaic
DmaicDmaic
Dmaic
 
Lean manufacturing
Lean manufacturingLean manufacturing
Lean manufacturing
 
Lean Thinking - An Introduction to Lean
Lean Thinking - An Introduction to LeanLean Thinking - An Introduction to Lean
Lean Thinking - An Introduction to Lean
 
Lean Managment
Lean ManagmentLean Managment
Lean Managment
 
SMED - Quick Change Over
SMED - Quick Change OverSMED - Quick Change Over
SMED - Quick Change Over
 
value added manufacturing
value added manufacturing value added manufacturing
value added manufacturing
 
Lean manufacturing ppt
Lean manufacturing pptLean manufacturing ppt
Lean manufacturing ppt
 

Andere mochten auch

Vsm Control - General Product Description V02
Vsm Control - General Product Description V02Vsm Control - General Product Description V02
Vsm Control - General Product Description V02
Radikal Ltd.
 
applicationof vsm
applicationof vsmapplicationof vsm
applicationof vsm
Aro Ephrem
 

Andere mochten auch (10)

Improving Your Business by Combining VSM with VOC
Improving Your Business by Combining VSM with VOCImproving Your Business by Combining VSM with VOC
Improving Your Business by Combining VSM with VOC
 
Vsm Control - General Product Description V02
Vsm Control - General Product Description V02Vsm Control - General Product Description V02
Vsm Control - General Product Description V02
 
applicationof vsm
applicationof vsmapplicationof vsm
applicationof vsm
 
Introduction to lean
Introduction to leanIntroduction to lean
Introduction to lean
 
Lean Manufacturing VSM Value Stream Mapping
Lean Manufacturing VSM Value Stream MappingLean Manufacturing VSM Value Stream Mapping
Lean Manufacturing VSM Value Stream Mapping
 
Lean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.comLean Manufacturing : Concept & Overview nkchawla@gmail.com
Lean Manufacturing : Concept & Overview nkchawla@gmail.com
 
Lean presentation ppt
Lean presentation pptLean presentation ppt
Lean presentation ppt
 
Value stream mapping for non manufacturing environments
Value stream mapping for non manufacturing environmentsValue stream mapping for non manufacturing environments
Value stream mapping for non manufacturing environments
 
Value Stream Mapping Project Template by Operational Excellence Consulting
Value Stream Mapping Project Template by Operational Excellence ConsultingValue Stream Mapping Project Template by Operational Excellence Consulting
Value Stream Mapping Project Template by Operational Excellence Consulting
 
10 Things your Audience Hates About your Presentation
10 Things your Audience Hates About your Presentation10 Things your Audience Hates About your Presentation
10 Things your Audience Hates About your Presentation
 

Ähnlich wie VSM (Lean Manufacturing) Project PPT

Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
ijmech
 
thesis-presentation (1)
thesis-presentation (1)thesis-presentation (1)
thesis-presentation (1)
Asim Aslam
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
ijsrd.com
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
Karina Islam
 

Ähnlich wie VSM (Lean Manufacturing) Project PPT (20)

Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 
Joined document 24_5
Joined document 24_5Joined document 24_5
Joined document 24_5
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry [irjet-v4 ...
 
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump IndustryManufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
Manufacturing Lead Time Reduction in Monoblock (SWJ) Pump Industry
 
Lean Manufacturing Methods for Process Improvement
Lean Manufacturing Methods for Process ImprovementLean Manufacturing Methods for Process Improvement
Lean Manufacturing Methods for Process Improvement
 
paper-presentation
paper-presentationpaper-presentation
paper-presentation
 
IRJET- Single Minute Exchange of Dies (SMED) Concept
IRJET-  	  Single Minute Exchange of Dies (SMED) ConceptIRJET-  	  Single Minute Exchange of Dies (SMED) Concept
IRJET- Single Minute Exchange of Dies (SMED) Concept
 
Operations Research & Methodology project report
Operations Research & Methodology  project reportOperations Research & Methodology  project report
Operations Research & Methodology project report
 
Toyota
ToyotaToyota
Toyota
 
thesis-presentation (1)
thesis-presentation (1)thesis-presentation (1)
thesis-presentation (1)
 
Toyota's jit revolution ppt
Toyota's jit revolution pptToyota's jit revolution ppt
Toyota's jit revolution ppt
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
 
IRJET- Enhance the Capacity of Outer Tube Machining Cell
IRJET-  	  Enhance the Capacity of Outer Tube Machining CellIRJET-  	  Enhance the Capacity of Outer Tube Machining Cell
IRJET- Enhance the Capacity of Outer Tube Machining Cell
 
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...IRJET-  	  Productivity Improvement by Implementing Lean Manufacturing Tools ...
IRJET- Productivity Improvement by Implementing Lean Manufacturing Tools ...
 
Lean consulting
Lean consultingLean consulting
Lean consulting
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
M.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis PresentationM.tech (Production and Industrial Engineering) Thesis Presentation
M.tech (Production and Industrial Engineering) Thesis Presentation
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
 

VSM (Lean Manufacturing) Project PPT

  • 1.
  • 2.
  • 4. OVERVIEW INTRODUCTION DATA COLLECTION AND METHDOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 5. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION  Company Profile: Alsons AutoParts (Pvt.) Ltd. Is an ISO 9001 and ISO-14001-2004 Certified company which was established in 1988, and has become a leading name in the Pakistan Automotive Industry.
  • 6.  Major Products: Alsons AutoParts Pvt. Ltd. consists of three main products in their manufacturing plant, which are given below;  Plastic Injection Moulding Products OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 7.  Sheet Metal Products:  Automotive assembly products: OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 8.  Existing Situation: OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION The existing situation of press shop is that they have a targeted schedule of the production of 1200 plates daily for Suzuki with a Takt time of 0.375 min/pcs which is difficult to achieve so in order to meet the customer demand they go for over time. The company experiences the following issues in the manufacturing of backing plate at press shop.  Lack of Traceability of product.  Greater lead-time.  Unnecessary stoppages  Greater Takt time  Issues:
  • 9. INTRODUCTION: Industries are in the favor to get more capital and resources to improve their productivity. It is necessary to optimize their capital, time and working environment. Industries needed improvement tools to optimize its processes to attain more capable results. Many improvement techniques and tools were developed and adapted to work in the different types of business. Now day’s industries focused on more production with higher efficiency in less lead time. The companies focused mainly on customer satisfaction. In an increasingly competitive environment, many manufacturing firms are looking for a winning card over their competitor. Manufacturers have to understand that the conventional production system has to connect with the lean tools and techniques. Lean manufacturing system was developed by Toyota, Japan. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 10. Project Background: A shorter lead time results into better utilization of manufacturing resources, quick adaptation to customer’s demand, reduced cost and better products. Today companies are intensively indulging in activities to reduce their production lead times. Our Team, keeping in mind, the importance of a short lead time, therefore we worked in Alsons AutoParts with the intention to reduce Production Lead time. Technique that the team adopted was Value Stream Mapping . Value stream mapping is the technique of Lean Manufacturing. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 11. VALUE STREAM MAPPING: Value Stream Mapping (VSM) tool shows all the activities, from supply to final product through the different processing steps.In other words it is a sketch of a production line. Value stream map is the technique that bring the all processing steps at one place. It shows the big picture of shop floor rather than individual processes and improving the each area at the production line. It is used to draw attention to different wastes and eliminating them in Future State Map. It is necessary that every process as closely as possible produces only what its customers need. The existing processes have some types the waste in a production line which is the result of product design and machinery. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 12. Lead Time: • A lead time is the time interval between the initiation and execution of a process. • In industry, lead time reduction is an important part of lean manufacturing OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 13. Critical inputs for the VSM: The following data are considered to be important in a value stream mapping project. • Cycle time • Number of operators • Waiting time • Process time per shift OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 15. 1.Selection of the Product: The selection of the product is very important step in Value Stream Mapping. Baking plate is the critical product of the Alsons AutoParts due to its requirement and demand by the Suzuki Automobiles. There is the lack of traceability, scheduling, greater lead time, unnecessary stoppages, etc. Due to these problems the completion of the customer demand on time will be difficult. After observing all these major issues which will directly effects the whole production system .BAKING PLATE is our critical product for working for the improvement OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 16. 2.Collection of Relevant Data: OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION I. Product flow within press shop. II. Cycle time of each process. III. Identification of bottlenecks. IV. Transportation of product within press shop.
  • 17. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION I. Product Flow within Press Shop:
  • 18. Process Cycle time Shearing 13sec Blanking 23sec Forming 12sec Collar Bending 11sec Flattening 8sec Piercing 1 10sec Piercing 2 10sec Chamfering 11sec CO2 Welding 20sec Remering 10sec Spot Welding 28sec Debeurring 12sec
  • 19.  Flattening It has the capacity of 960 pieces per shift which is a bottleneck for press shop. Reason: Lack of trollies at the workstation, which stops the production after 100 pieces which creates bottleneck for production system. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 20.  Spot Welding: It has the capacity of 450pieces/shift by each machine. Press shop has 2 spot welding machines which produces 900 pieces per shift. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 21. IV. Transportation Method: 1-With the help of trollies. 2-Fork lifter. 3-Manual lifter OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 22. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION 3.Current State Map:
  • 23. Description: • The current state map shows that the backing plate has the production lead time of 12.6 hours. • It clearly shows the unwanted Waiting Time between each workstation . • It shows the big picture about the real time process & performance of the production process. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 24. 4.Identification the nature of wastes in the process: OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION Wastage of time: • Un necessary usage of lifter between the process shearing & blanking which causes delays in production up to 1 hour due to un availability of lifter at the press shop. • Lack of availability of trollies at each work station which causes the process to stop & wait for the raw material inventory .
  • 25. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION 5.Future State Map
  • 26. Future Product Flow Layout: OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 27. Description: • Lead time reduced about 2.25 hours i.e. 20% reduction which reduces the companies overtime cost. • Reduced the transportation between the processes. • Kaizen burst: 1)Machine Relocation 2)Material handling equipments 3)New machine. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 28. 6.Suggestion for Improvements: OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION Ergonomic trollies should be used which provides effective transportation within press shop. I. Material Handling Equipments
  • 29. II.Machine Relocation: Relocation of blanking machine near to shearing machine so that the operation of lifter will be eliminate which reduces: 1- Transportation time. 2- Transportation cost. 3- Process waiting due to un availability of lifter. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 30. III. New Machine  Another Spot Welding Machine should be install to fulfill the requirements.  Cooling system must be maintained properly for effective working. Good quality electrodes will help to increase productivity & on time delivery of products. OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION
  • 31. Conclusion: The project was to reduce the production lead time, for this purpose the team selected lean manufacturing tool Value Stream Mapping. In addition to reduction of lead time, following benefits were expected after the completion of the project.  Improved productivity  Determination of Value stream  Better understanding of Wastes and their causes  A roadmap towards an efficient, lean production line OVERVIEW INTRODUCTION DATA COLLECTION & METHODOLOGY RESULTS & DISCUSSIONS CONCLUSION