SlideShare ist ein Scribd-Unternehmen logo
1 von 37
Downloaden Sie, um offline zu lesen
CONTROLLING PRODUCTIVITY IN
CONSTRUCTION PROJECTS
Labor Productivity Improvement in Construction Projects using
WBS & OBS integration
Essam, Bio
2
• Essam Lotfi is a Project Manager-MEP at Trojan general contracting in UAE.
• BSc. in Electrical Engineering, Power Distribution through Zagazig University, Egypt since
2001. Pursued and achieved his certificates in Project Management (PMP®) from PMI-
USA since 2013, and certificate in Cost Management (CCP®) from AACE International
since june-2014.
• 15 years extensive hands on experience in various aspects of projects and project
management within maintenance, power distribution networks monitoring and
supervision and construction projects as well.
• Authored, Co-Authored at PMWorld Library, PWLJ.
• Volunteered at PMI-Global Congress EMEA-2014 – Dubai, 5th to 8th May 2014.
• Technical presentation at PMI-AGC 15th International conference –Bahrain 19th to 21st
January 2015.
• Technical presentation at 54th AACEi-SF Bay Annual Western Winter Workshop, Lake
Tahoe, Nevada, USA
• Technical presentation 55th AACEi-SF Bay Annual Western Winter Workshop, Indian
Wells, CA, USA
• Independent Project Management and cost engineering/Control Instructor.
• Common causes of loss in productivity.
• Using earned value implementation in labor productivity
monitoring & Controlling.
• Labor productivity improvement using WBS & OBS
integration model.
Outlines
The Objectives of this presentation is to show the effect of implementing
WBS & OBS integration matrix to monitor the project performance and
improve the labor productivity by assigning specific work packages to
appropriate organizational units.
Objectives
Team Member Role Reporting To Responsibilities
Project Manager (PM) 1- Lead project Team Organization Management 1- Monitor Cost
2- Monitor Time
3- Achieve Planned cost
4- Achieve Planned Time
Construction Manager (CM) 1-Lead Activities Execution Project Manager (PM) 1-Monitor progress
2- Monitor Progress 2-Momitor Subcontractors
Performance
3-prepare payments
4-Follow issues with consultant
Project Engineer (PE) 1- Lead Drawing approvals Construction Manager (CM) 1- Deliver Drawings & materials
2- Lead material approvals As per project requirements
3- Follow material delivery 2-Issue Materials orders.
4- Distribute activities 3- Follow materials delivery
4- Distribute activities with related
Materials & Drawings.
5- Conform Quality.
Site Engineer (SE)
1-Leads Supervisors
Project Engineer (PE)
1- Distribute supervisors & Technicians
2- Lead Technicians 2- Follow planned Activities.
3- Lead Store 3- Issue materials from stores
4- Achieve progress
5- Perform Quality
Supervisors 1- Lead Technicians Site Engineer (SE) 1- Perform Drawings
2- Supervise installation 2- Control Technicians productivity
3- Control Materials installation
4- Achieve Quality
9
We should discriminate between and .
Production in construction projects has many definitions, as full product is
“Completed Project”, while the project has many parts such as Activities it
means “Each Activity Completed is a Product”. While Productivity in
construction refers to relation among activities completion against time
spent to complete those activities , it’s a measure of labor efficiency. Our
approach is to analyze productivity against time planned for each activity.
On a simple word Production is a measure of output although Productivity
is a measure of production performance. To achieve our goal we should
realize the common causes, circumstances and events that may affect the
productivity.
Technical Issues.
Incomplete drawings or specifications for each activity may create ambiguity to project
team and this may creates uncertainties due to lack of information’s.
COMMON CAUSES OF LOSS IN PRODUCTIVITY
Missed Supervision.
”Relocation of work force before task is completed”. And over loading supervisors with
multitasks in different areas. This two major categories resulting missed supervision and low
performance as well.
COMMON CAUSES OF LOSS IN PRODUCTIVITY
Wrong Distribution of resources.
The right materials, tools, equipment's and any other resources must be provided
to that location in order to have the desired productivity. Unplanned distribution
result in delays due to shifting wrong materials and any other resources to the area
of subject matter work is required.
COMMON CAUSES OF LOSS IN PRODUCTIVITY
Resource Over allocation
Each zone and/or activity has limited capacity hence assigning extra
people to perform same activity results into idle status.
COMMON CAUSES OF LOSS IN PRODUCTIVITY
Overtime
It’s a technique but has limited usage privileges, it can be used for a
certain activities but cannot be general practice as it exhaust labors
and this will results in less productivity.
COMMON CAUSES OF LOSS IN PRODUCTIVITY
Installation of Air Duct (Shoe Collar) for Exhaust system at parking area
,Normally follow the following criteria
SEQUENCE OF ACTIVITIES
SEQUENCE OF ACTIVITIES
SEQUENCE OF ACTIVITIES
Comparing Criteria (A) & (B)
Manpower
used(Nrs.)
Duration
(Hrs.)
Production
(Nrs.)
IncurredCost(Hrs/Pc)
Cost
Hrs/Psc
Criteria(A) 3 10 3 (10Hrs*3Labors)/3Pcs 10Hrs/Pcs
Criteria(B) 2 10 8 (10Hrs*2Labors)/8Pcs 2.5Hrs/Pcs
Conclusion
Criteria (B) proved to be higher productivity rates per hour which means less cost & better
timing to complete the same task.
SEQUENCE OF ACTIVITIES
19
Effect of Learning Curve in Labor Productivity
Learning Curve
It’s a technique achieved by repeating same activity in different zones by a fixed group of
technicians, in case those groups got interrupted before completing same activity in all
zones the productivity of those groups will be lower when we assign them again to the
previous activity zone, Look at the following example to find the implications of interrupting
learning curve.
Example
In residential tower has typical floors, we assigned a group of
technicians to fix light fitting under supervision of one supervisor,
we noticed the following,
20
Floor 1st
2nd
3rd
4th
5th
6th
7th
Light fitting Ficxed 169 169 169 169 169 169 169
Duratation (Days) 3 3 3 2.5 2.5 2 2
Productivity / Day 56.3 56.3 56.3 67.6 67.6 84.5 84.5
21
Floor 1st
2nd
3rd
4th
5th
6th
7th
Light fitting Ficxed 169 169 169 169 169 169 169
Duratation (Days) 3 3 0 0 0 3 3
Productivity / Day 56.3 56.3 0.0 0.0 0.0 56.3 56.3
22
Effect of Learning Curve in Labor Productivity
Looking to previous tables which Indicates that fixing group of 3
technicians to perform the same activity repeatedly will increase their
productivity day to day as the same group will be more familiar with the
type of the light fitting and site conditions hence give more productivity
(See Graph showing learning curve improvement), while interrupting
those groups will disrupt the learning curve of the technicians as in
second building with same specifications we have the same
arrangements, but the activity were interrupted by reassigning the
technicians to other activities then returning back to the light fitting
installation activity as shown in the following graph.
23
EARNED VALUE IMPLEMENTATION
24
ActivityName
PlannedManpower
TotalGroup
Productivity
Rate/Group/Day
Unit
TargetDuration/Days
Actualay1
Actualay2
Actualay3
Actualay4
Actualay5
Actualay6
Actualay7
Actualay8
Actualay9
Actualay10
Actualay11
Actualay12
Actualay13
Actualay14
ManpowerCumulative
Completedfloors
plannedtarget
Targetfloors
BalanceWork
Earned
Value Of
Manpow
er Hours
Lightfixtures
TypicalFloor
24 3G 1
Floor
11 13 13 13 13 13 13 13 13 14 15 15 14 5 2 169 8 6.5 11 3 360.0
• Work required to be completed “Light Fixture Installation in Typical Floors”.
• Planned manpower required to complete 1 Floor is 1 Group of 8 labors.
• Planned Duration for 1 Group to complete 1 Floor is 1 day (10 Working hours) and
Total Duration for this activity is 11 Days and Total planned manpower is 24 labors per
day.
• Actual work done in the period (from 1st Day to 14th Day) is 63%.
25
ActivityName
PlannedManpower
TotalGroup
Productivity
Rate/Group/Day
Unit
TargetDuration/Days
Actualay1
Actualay2
Actualay3
Actualay4
Actualay5
Actualay6
Actualay7
Actualay8
Actualay9
Actualay10
Actualay11
Actualay12
Actualay13
Actualay14
ManpowerCumulative
Completedfloors
plannedtarget
Targetfloors
BalanceWork
Earned
Value Of
Manpow
er Hours
Lightfixtures
TypicalFloor
24 3G 1
Floor
11 13 13 13 13 13 13 13 13 14 15 15 14 5 2 169 8 6.5 11 3 360.0
• Actual consumed manpower in the period (from 1st Day to 14th Day) is 169 labors.
• Planned work to be completed is 33 floors in 11 days using 3 groups (24 labors) per day
or total 264 labors.
• Apply earned value calculations using Earned Value Equation. the actual spent
manpower 169 should give 8 floor where the planned should be 6.3 floors using the same
number of manpower, which means although we are behind schedule the productivity
achieved by the available manpower achieved 136 hours under budget
EARNED VALUE
26
Productivity Improvement
As we see from the example a clear scope for specific single organizational
component in the organizational break down structure (OBS) will give the right
framework of monitoring project performance and labor productivity as well,
further to this it’s apparent that this model reflects avoidance of many causes
of productivity loss. Such as miss of supervision and resource wrong
distribution. This will bring to mind where the necessity of WBS & OBS
integration matrix is and what the real effect of direct labor cost control is?,
here we come to the objective of this Presentation which is how to improve
labor direct cost using WBS & OBS integration and how it can be implemented.
27
Productivity Improvement
 To monitor labor performance during construction you must have
clear framework.
 This framework requires all team members to know their roles and
responsibilities thru. RAM.
 Use WBS & OBS integration matrix to assign specific resources to
specific task
28
USING WBS & OBS TO CONTROL PRODUCTIVITY
29
Working Example
Create WBS & Assign Tasks
Assigning the data
on the smallest
elements (tasks)
and integrating
the results for the
work packages,
control accounts
and WBS elements
Break down the
project according
to the view of
the project
Context
30
Construction WBS
PROJECT (WBS) (0)
Zone1
0.1
Zone2
0.2
Zone3
0.3
Zone4
0.4
Zone5
0.5
Level (0)
Level (1)
0.1.1 Earth work 0.1.2 Substructure 0.1.3 Super structure
0.1.4 Internal
Finishing
0.1.5 MEP
1.5.1 HVAC 1.5.2 Plumbing 1.5.3 Firefighting
1.5.4 electrical
work
1.5.1.G ground floor 1.5.1.1 First floor
Level (2)
Level
(3)
Power Cabling - 3.1.0 - First Floor
Lighting Points - First Floor
Power Points - First Floor
lighting & Power wire - First Floor
Lighting power - First FloorDetailed level activities or steps for
estimating the required resources for
OBS Assignments
Work packages
31
Date: Duty OT
Electricial
SL. Res. Engineer Foreman
Group
(M.U.I.xx)
ID No Employee Name Designation P A Zone Villa Description Of Work
Actual
Qty
Target
Qty
Duty
Over
Time
Bonus
Hours
Remarks
1 □ □
2 □ □
3 □ □
4 □ □
5 □ □
6 □ □
7 □ □
8 □ □
Charge hand
Electrician
Assistant Electrician
Total
Create Assignment sheet of each OBS Unit
32
Collect the WBS-OBS assignment progress
33
Collect the WBS-OBS assignment progress Daily Basis
34
WBS-OBS Variance Analysis in Daily Basis
The previous figure shows that each and every work package is assigned to specific group to
facilitate resource control including manpower and performance monitoring and this scheme
should be incorporated with the roles and responsibility matrix. Hence WBS & OBS integration
technique will results in:
 All team members will understand the required activities and tasks to be performed.
 All team members will be aware of their responsibilities.
 Well define scope, WBS decomposition and activities duration will avoid over manning and
excessive overtime as well.
 Well defined scope and WBS will avoid wrong sequence of activity and give high rate of
manpower productivity.
 Fixing specific groups will avoid learning curve disturbance and strengthen it and results in
high productivity rate due to awareness of the activities
USING WBS & OBS TO CONTROL PRODUCTIVITY
WBS & OBS integration technique is arises as useful methodology to achieve productivity improvement, and this
will results in:
Invest the manpower by continues appraisals’
Give the organization a clear idea about recourse pool availability for other projects within the organization
Manpower productivity rates improvement will give the organization to bid competitive prices for new projects
acquisition.
A high productivity rates prevent outsourcing.
A high productivity rate gives the organization standard index of activities duration which will results in right cost
and time estimation.
High productivity rates and targets completion on time will give the organization chance to award the team
members which will motivate team members.
CONCLUSION
THANK YOU FOR ATTENDING
THE PRESENTATION

Weitere ähnliche Inhalte

Was ist angesagt?

Labour Productivity for construction projects
Labour Productivity for construction projectsLabour Productivity for construction projects
Labour Productivity for construction projectsKapugantikapuganti Gupta
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateSHAZEBALIKHAN1
 
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONPROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONDAVIDSON ECHIDIKE
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Shrikant Kate
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in constructionMahSobeh
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction CostingManish Kandpal
 
Introduction to Lean Construction
Introduction to Lean ConstructionIntroduction to Lean Construction
Introduction to Lean ConstructionVedzen Consultants
 
Quality in Construction
Quality in ConstructionQuality in Construction
Quality in ConstructionDr K M SONI
 
Lean Construction_PMI_Nov 19, 2016
Lean Construction_PMI_Nov 19, 2016Lean Construction_PMI_Nov 19, 2016
Lean Construction_PMI_Nov 19, 2016Murali Naidu
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 
Last planner system
Last planner systemLast planner system
Last planner systemAnshi Verma
 
total quality management in construction industry
total quality management in construction industrytotal quality management in construction industry
total quality management in construction industryMohammed Faazil
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Controlakashpadole
 

Was ist angesagt? (20)

Labour Productivity for construction projects
Labour Productivity for construction projectsLabour Productivity for construction projects
Labour Productivity for construction projects
 
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
Module 2:Resource Management,Construction Equipments,Materials Inventory by D...
 
All About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel TemplateAll About Construction Labour Planning- Excel Template
All About Construction Labour Planning- Excel Template
 
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISIONPROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
PROJECT CONSTRUCTION SUPERVISOR AND SUPERVISION
 
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
Construction Scheduling, Work Study and Work Measurement _ Unit 2 _ Construct...
 
Procurement in construction
Procurement in constructionProcurement in construction
Procurement in construction
 
Construction Supervising Site Engineer - Duties & Responsibilities
Construction Supervising Site Engineer - Duties & ResponsibilitiesConstruction Supervising Site Engineer - Duties & Responsibilities
Construction Supervising Site Engineer - Duties & Responsibilities
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Introduction to Lean Construction
Introduction to Lean ConstructionIntroduction to Lean Construction
Introduction to Lean Construction
 
Quality in Construction
Quality in ConstructionQuality in Construction
Quality in Construction
 
Total Quality Management In Construction
Total Quality Management In ConstructionTotal Quality Management In Construction
Total Quality Management In Construction
 
An introduction to value management
An introduction to value managementAn introduction to value management
An introduction to value management
 
Lean Construction_PMI_Nov 19, 2016
Lean Construction_PMI_Nov 19, 2016Lean Construction_PMI_Nov 19, 2016
Lean Construction_PMI_Nov 19, 2016
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Last planner system
Last planner systemLast planner system
Last planner system
 
total quality management in construction industry
total quality management in construction industrytotal quality management in construction industry
total quality management in construction industry
 
Lean Construction Management
Lean Construction Management Lean Construction Management
Lean Construction Management
 
05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control05 Project Monitoring & Cost Control
05 Project Monitoring & Cost Control
 

Ähnlich wie Controling productivity in construction projects

Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Essam Lotffy, PMP®, CCP®
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Offssuserfe1b72
 
Productivity Improvement Study
Productivity Improvement StudyProductivity Improvement Study
Productivity Improvement Studysaranshshah
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfkripeshdubey1
 
1. Which of the following is INCORRECT regarding the process capab.docx
1. Which of the following is INCORRECT regarding the process capab.docx1. Which of the following is INCORRECT regarding the process capab.docx
1. Which of the following is INCORRECT regarding the process capab.docxjackiewalcutt
 
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaaSCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaainfinitepestcontrol
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPIRJET Journal
 
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...IRJET Journal
 
Automobile parts design diploma mechanical engineering
Automobile parts design diploma mechanical engineeringAutomobile parts design diploma mechanical engineering
Automobile parts design diploma mechanical engineeringlovely467637
 
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...IRJET Journal
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & ControlKunalJagtap5
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9Moustafa Ismail Abu Dief
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...Karina Islam
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materialspikuoec
 

Ähnlich wie Controling productivity in construction projects (20)

Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...Labor productivity improvement in construction projects using wbs obs integra...
Labor productivity improvement in construction projects using wbs obs integra...
 
Time Cost Trade Off
Time Cost Trade OffTime Cost Trade Off
Time Cost Trade Off
 
Productivity Improvement Study
Productivity Improvement StudyProductivity Improvement Study
Productivity Improvement Study
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
 
1. Which of the following is INCORRECT regarding the process capab.docx
1. Which of the following is INCORRECT regarding the process capab.docx1. Which of the following is INCORRECT regarding the process capab.docx
1. Which of the following is INCORRECT regarding the process capab.docx
 
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaaSCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
 
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSPCOMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
COMPARATIVE STUDY OF ACTUAL AND CRASHED SCHEDULE OF BUILDING USING MSP
 
Process design
Process designProcess design
Process design
 
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
 
Chapter4EN.PDF.pdf
Chapter4EN.PDF.pdfChapter4EN.PDF.pdf
Chapter4EN.PDF.pdf
 
Automobile parts design diploma mechanical engineering
Automobile parts design diploma mechanical engineeringAutomobile parts design diploma mechanical engineering
Automobile parts design diploma mechanical engineering
 
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...IRJET-  	  Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
IRJET- Enhancing Line Efficiency of Road Machinery Assembly Line at Volvo...
 
Production Planning & Control
Production Planning & ControlProduction Planning & Control
Production Planning & Control
 
Final Review
Final ReviewFinal Review
Final Review
 
Introduction to schedule management
Introduction to schedule managementIntroduction to schedule management
Introduction to schedule management
 
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9Ss 04 cost engineering management  training- nov 2017 - moustafa part ii- ch 9
Ss 04 cost engineering management training- nov 2017 - moustafa part ii- ch 9
 
Pom unit 3
Pom unit 3Pom unit 3
Pom unit 3
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
Production And Operation Materials
Production And Operation MaterialsProduction And Operation Materials
Production And Operation Materials
 

Mehr von Essam Lotffy, PMP®, CCP®

Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsEssam Lotffy, PMP®, CCP®
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plansEssam Lotffy, PMP®, CCP®
 
Failure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.finalFailure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.finalEssam Lotffy, PMP®, CCP®
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEssam Lotffy, PMP®, CCP®
 
Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...Essam Lotffy, PMP®, CCP®
 
Effect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEffect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEssam Lotffy, PMP®, CCP®
 
A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period Essam Lotffy, PMP®, CCP®
 

Mehr von Essam Lotffy, PMP®, CCP® (16)

Introduction to quality management
Introduction to quality managementIntroduction to quality management
Introduction to quality management
 
Common contract types
Common contract typesCommon contract types
Common contract types
 
Pmp selective process data flow
Pmp selective process data flowPmp selective process data flow
Pmp selective process data flow
 
PMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introductionPMBoK6Ed.lect1.introduction
PMBoK6Ed.lect1.introduction
 
Sample cosntructability report Template
Sample cosntructability report Template Sample cosntructability report Template
Sample cosntructability report Template
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Essam lotffy this project is not in line with organizational strategic plans
Essam lotffy   this project is not in line with organizational strategic plansEssam lotffy   this project is not in line with organizational strategic plans
Essam lotffy this project is not in line with organizational strategic plans
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Pmp introduction
Pmp introductionPmp introduction
Pmp introduction
 
Failure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.finalFailure in construction due to ineffective project management information.final
Failure in construction due to ineffective project management information.final
 
Eot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contractsEot claims due to scope change under fidic contracts
Eot claims due to scope change under fidic contracts
 
Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...Failures in construction due to ineffective project management information sy...
Failures in construction due to ineffective project management information sy...
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Effect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo successEffect of organizational unwritten rules on pmo success
Effect of organizational unwritten rules on pmo success
 
A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period A simple example to calculate net present value and pay back period
A simple example to calculate net present value and pay back period
 

Kürzlich hochgeladen

Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siligurimeghakumariji156
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxAaron Stannard
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalWilliam (Bill) H. Bender, FCSI
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdfAlejandromexEspino
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamraAllTops
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentNimot Muili
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.aruny7087
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxssuserf63bd7
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownSandaliGurusinghe2
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxssuserf63bd7
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdfArtiSrivastava23
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelNitya salvi
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field ArtilleryKennethSwanberg
 

Kürzlich hochgeladen (14)

Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime SiliguriSiliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
Siliguri Escorts Service Girl ^ 9332606886, WhatsApp Anytime Siliguri
 
How Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptxHow Software Developers Destroy Business Value.pptx
How Software Developers Destroy Business Value.pptx
 
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professionalW.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
W.H.Bender Quote 62 - Always strive to be a Hospitality Service professional
 
International Ocean Transportation p.pdf
International Ocean Transportation p.pdfInternational Ocean Transportation p.pdf
International Ocean Transportation p.pdf
 
internship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamrainternship thesis pakistan aeronautical complex kamra
internship thesis pakistan aeronautical complex kamra
 
Beyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable developmentBeyond the Codes_Repositioning towards sustainable development
Beyond the Codes_Repositioning towards sustainable development
 
Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.Persuasive and Communication is the art of negotiation.
Persuasive and Communication is the art of negotiation.
 
Marketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docxMarketing Management 16th edition by Philip Kotler test bank.docx
Marketing Management 16th edition by Philip Kotler test bank.docx
 
The Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard BrownThe Psychology Of Motivation - Richard Brown
The Psychology Of Motivation - Richard Brown
 
Information Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docxInformation Technology Project Management, Revised 7th edition test bank.docx
Information Technology Project Management, Revised 7th edition test bank.docx
 
digital Human resource management presentation.pdf
digital Human resource management presentation.pdfdigital Human resource management presentation.pdf
digital Human resource management presentation.pdf
 
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot ModelGautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
Gautam Buddh Nagar Call Girls 🥰 8617370543 Service Offer VIP Hot Model
 
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTECAbortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
Abortion pills in Jeddah |• +966572737505 ] GET CYTOTEC
 
Safety T fire missions army field Artillery
Safety T fire missions army field ArtillerySafety T fire missions army field Artillery
Safety T fire missions army field Artillery
 

Controling productivity in construction projects

  • 1. CONTROLLING PRODUCTIVITY IN CONSTRUCTION PROJECTS Labor Productivity Improvement in Construction Projects using WBS & OBS integration
  • 2. Essam, Bio 2 • Essam Lotfi is a Project Manager-MEP at Trojan general contracting in UAE. • BSc. in Electrical Engineering, Power Distribution through Zagazig University, Egypt since 2001. Pursued and achieved his certificates in Project Management (PMP®) from PMI- USA since 2013, and certificate in Cost Management (CCP®) from AACE International since june-2014. • 15 years extensive hands on experience in various aspects of projects and project management within maintenance, power distribution networks monitoring and supervision and construction projects as well. • Authored, Co-Authored at PMWorld Library, PWLJ. • Volunteered at PMI-Global Congress EMEA-2014 – Dubai, 5th to 8th May 2014. • Technical presentation at PMI-AGC 15th International conference –Bahrain 19th to 21st January 2015. • Technical presentation at 54th AACEi-SF Bay Annual Western Winter Workshop, Lake Tahoe, Nevada, USA • Technical presentation 55th AACEi-SF Bay Annual Western Winter Workshop, Indian Wells, CA, USA • Independent Project Management and cost engineering/Control Instructor.
  • 3. • Common causes of loss in productivity. • Using earned value implementation in labor productivity monitoring & Controlling. • Labor productivity improvement using WBS & OBS integration model. Outlines
  • 4. The Objectives of this presentation is to show the effect of implementing WBS & OBS integration matrix to monitor the project performance and improve the labor productivity by assigning specific work packages to appropriate organizational units. Objectives
  • 5.
  • 6.
  • 7. Team Member Role Reporting To Responsibilities Project Manager (PM) 1- Lead project Team Organization Management 1- Monitor Cost 2- Monitor Time 3- Achieve Planned cost 4- Achieve Planned Time Construction Manager (CM) 1-Lead Activities Execution Project Manager (PM) 1-Monitor progress 2- Monitor Progress 2-Momitor Subcontractors Performance 3-prepare payments 4-Follow issues with consultant Project Engineer (PE) 1- Lead Drawing approvals Construction Manager (CM) 1- Deliver Drawings & materials 2- Lead material approvals As per project requirements 3- Follow material delivery 2-Issue Materials orders. 4- Distribute activities 3- Follow materials delivery 4- Distribute activities with related Materials & Drawings. 5- Conform Quality. Site Engineer (SE) 1-Leads Supervisors Project Engineer (PE) 1- Distribute supervisors & Technicians 2- Lead Technicians 2- Follow planned Activities. 3- Lead Store 3- Issue materials from stores 4- Achieve progress 5- Perform Quality Supervisors 1- Lead Technicians Site Engineer (SE) 1- Perform Drawings 2- Supervise installation 2- Control Technicians productivity 3- Control Materials installation 4- Achieve Quality
  • 8.
  • 9. 9 We should discriminate between and . Production in construction projects has many definitions, as full product is “Completed Project”, while the project has many parts such as Activities it means “Each Activity Completed is a Product”. While Productivity in construction refers to relation among activities completion against time spent to complete those activities , it’s a measure of labor efficiency. Our approach is to analyze productivity against time planned for each activity. On a simple word Production is a measure of output although Productivity is a measure of production performance. To achieve our goal we should realize the common causes, circumstances and events that may affect the productivity.
  • 10. Technical Issues. Incomplete drawings or specifications for each activity may create ambiguity to project team and this may creates uncertainties due to lack of information’s. COMMON CAUSES OF LOSS IN PRODUCTIVITY
  • 11. Missed Supervision. ”Relocation of work force before task is completed”. And over loading supervisors with multitasks in different areas. This two major categories resulting missed supervision and low performance as well. COMMON CAUSES OF LOSS IN PRODUCTIVITY
  • 12. Wrong Distribution of resources. The right materials, tools, equipment's and any other resources must be provided to that location in order to have the desired productivity. Unplanned distribution result in delays due to shifting wrong materials and any other resources to the area of subject matter work is required. COMMON CAUSES OF LOSS IN PRODUCTIVITY
  • 13. Resource Over allocation Each zone and/or activity has limited capacity hence assigning extra people to perform same activity results into idle status. COMMON CAUSES OF LOSS IN PRODUCTIVITY
  • 14. Overtime It’s a technique but has limited usage privileges, it can be used for a certain activities but cannot be general practice as it exhaust labors and this will results in less productivity. COMMON CAUSES OF LOSS IN PRODUCTIVITY
  • 15. Installation of Air Duct (Shoe Collar) for Exhaust system at parking area ,Normally follow the following criteria SEQUENCE OF ACTIVITIES
  • 18. Comparing Criteria (A) & (B) Manpower used(Nrs.) Duration (Hrs.) Production (Nrs.) IncurredCost(Hrs/Pc) Cost Hrs/Psc Criteria(A) 3 10 3 (10Hrs*3Labors)/3Pcs 10Hrs/Pcs Criteria(B) 2 10 8 (10Hrs*2Labors)/8Pcs 2.5Hrs/Pcs Conclusion Criteria (B) proved to be higher productivity rates per hour which means less cost & better timing to complete the same task. SEQUENCE OF ACTIVITIES
  • 19. 19 Effect of Learning Curve in Labor Productivity Learning Curve It’s a technique achieved by repeating same activity in different zones by a fixed group of technicians, in case those groups got interrupted before completing same activity in all zones the productivity of those groups will be lower when we assign them again to the previous activity zone, Look at the following example to find the implications of interrupting learning curve. Example In residential tower has typical floors, we assigned a group of technicians to fix light fitting under supervision of one supervisor, we noticed the following,
  • 20. 20 Floor 1st 2nd 3rd 4th 5th 6th 7th Light fitting Ficxed 169 169 169 169 169 169 169 Duratation (Days) 3 3 3 2.5 2.5 2 2 Productivity / Day 56.3 56.3 56.3 67.6 67.6 84.5 84.5
  • 21. 21 Floor 1st 2nd 3rd 4th 5th 6th 7th Light fitting Ficxed 169 169 169 169 169 169 169 Duratation (Days) 3 3 0 0 0 3 3 Productivity / Day 56.3 56.3 0.0 0.0 0.0 56.3 56.3
  • 22. 22 Effect of Learning Curve in Labor Productivity Looking to previous tables which Indicates that fixing group of 3 technicians to perform the same activity repeatedly will increase their productivity day to day as the same group will be more familiar with the type of the light fitting and site conditions hence give more productivity (See Graph showing learning curve improvement), while interrupting those groups will disrupt the learning curve of the technicians as in second building with same specifications we have the same arrangements, but the activity were interrupted by reassigning the technicians to other activities then returning back to the light fitting installation activity as shown in the following graph.
  • 24. 24 ActivityName PlannedManpower TotalGroup Productivity Rate/Group/Day Unit TargetDuration/Days Actualay1 Actualay2 Actualay3 Actualay4 Actualay5 Actualay6 Actualay7 Actualay8 Actualay9 Actualay10 Actualay11 Actualay12 Actualay13 Actualay14 ManpowerCumulative Completedfloors plannedtarget Targetfloors BalanceWork Earned Value Of Manpow er Hours Lightfixtures TypicalFloor 24 3G 1 Floor 11 13 13 13 13 13 13 13 13 14 15 15 14 5 2 169 8 6.5 11 3 360.0 • Work required to be completed “Light Fixture Installation in Typical Floors”. • Planned manpower required to complete 1 Floor is 1 Group of 8 labors. • Planned Duration for 1 Group to complete 1 Floor is 1 day (10 Working hours) and Total Duration for this activity is 11 Days and Total planned manpower is 24 labors per day. • Actual work done in the period (from 1st Day to 14th Day) is 63%.
  • 25. 25 ActivityName PlannedManpower TotalGroup Productivity Rate/Group/Day Unit TargetDuration/Days Actualay1 Actualay2 Actualay3 Actualay4 Actualay5 Actualay6 Actualay7 Actualay8 Actualay9 Actualay10 Actualay11 Actualay12 Actualay13 Actualay14 ManpowerCumulative Completedfloors plannedtarget Targetfloors BalanceWork Earned Value Of Manpow er Hours Lightfixtures TypicalFloor 24 3G 1 Floor 11 13 13 13 13 13 13 13 13 14 15 15 14 5 2 169 8 6.5 11 3 360.0 • Actual consumed manpower in the period (from 1st Day to 14th Day) is 169 labors. • Planned work to be completed is 33 floors in 11 days using 3 groups (24 labors) per day or total 264 labors. • Apply earned value calculations using Earned Value Equation. the actual spent manpower 169 should give 8 floor where the planned should be 6.3 floors using the same number of manpower, which means although we are behind schedule the productivity achieved by the available manpower achieved 136 hours under budget EARNED VALUE
  • 26. 26 Productivity Improvement As we see from the example a clear scope for specific single organizational component in the organizational break down structure (OBS) will give the right framework of monitoring project performance and labor productivity as well, further to this it’s apparent that this model reflects avoidance of many causes of productivity loss. Such as miss of supervision and resource wrong distribution. This will bring to mind where the necessity of WBS & OBS integration matrix is and what the real effect of direct labor cost control is?, here we come to the objective of this Presentation which is how to improve labor direct cost using WBS & OBS integration and how it can be implemented.
  • 27. 27 Productivity Improvement  To monitor labor performance during construction you must have clear framework.  This framework requires all team members to know their roles and responsibilities thru. RAM.  Use WBS & OBS integration matrix to assign specific resources to specific task
  • 28. 28 USING WBS & OBS TO CONTROL PRODUCTIVITY
  • 29. 29 Working Example Create WBS & Assign Tasks Assigning the data on the smallest elements (tasks) and integrating the results for the work packages, control accounts and WBS elements Break down the project according to the view of the project Context
  • 30. 30 Construction WBS PROJECT (WBS) (0) Zone1 0.1 Zone2 0.2 Zone3 0.3 Zone4 0.4 Zone5 0.5 Level (0) Level (1) 0.1.1 Earth work 0.1.2 Substructure 0.1.3 Super structure 0.1.4 Internal Finishing 0.1.5 MEP 1.5.1 HVAC 1.5.2 Plumbing 1.5.3 Firefighting 1.5.4 electrical work 1.5.1.G ground floor 1.5.1.1 First floor Level (2) Level (3) Power Cabling - 3.1.0 - First Floor Lighting Points - First Floor Power Points - First Floor lighting & Power wire - First Floor Lighting power - First FloorDetailed level activities or steps for estimating the required resources for OBS Assignments Work packages
  • 31. 31 Date: Duty OT Electricial SL. Res. Engineer Foreman Group (M.U.I.xx) ID No Employee Name Designation P A Zone Villa Description Of Work Actual Qty Target Qty Duty Over Time Bonus Hours Remarks 1 □ □ 2 □ □ 3 □ □ 4 □ □ 5 □ □ 6 □ □ 7 □ □ 8 □ □ Charge hand Electrician Assistant Electrician Total Create Assignment sheet of each OBS Unit
  • 32. 32 Collect the WBS-OBS assignment progress
  • 33. 33 Collect the WBS-OBS assignment progress Daily Basis
  • 35. The previous figure shows that each and every work package is assigned to specific group to facilitate resource control including manpower and performance monitoring and this scheme should be incorporated with the roles and responsibility matrix. Hence WBS & OBS integration technique will results in:  All team members will understand the required activities and tasks to be performed.  All team members will be aware of their responsibilities.  Well define scope, WBS decomposition and activities duration will avoid over manning and excessive overtime as well.  Well defined scope and WBS will avoid wrong sequence of activity and give high rate of manpower productivity.  Fixing specific groups will avoid learning curve disturbance and strengthen it and results in high productivity rate due to awareness of the activities USING WBS & OBS TO CONTROL PRODUCTIVITY
  • 36. WBS & OBS integration technique is arises as useful methodology to achieve productivity improvement, and this will results in: Invest the manpower by continues appraisals’ Give the organization a clear idea about recourse pool availability for other projects within the organization Manpower productivity rates improvement will give the organization to bid competitive prices for new projects acquisition. A high productivity rates prevent outsourcing. A high productivity rate gives the organization standard index of activities duration which will results in right cost and time estimation. High productivity rates and targets completion on time will give the organization chance to award the team members which will motivate team members. CONCLUSION
  • 37. THANK YOU FOR ATTENDING THE PRESENTATION