2. Essam, Bio
2
• Essam Lotfi is a Project Manager-MEP at Trojan general contracting in UAE.
• BSc. in Electrical Engineering, Power Distribution through Zagazig University, Egypt since
2001. Pursued and achieved his certificates in Project Management (PMP®) from PMI-
USA since 2013, and certificate in Cost Management (CCP®) from AACE International
since june-2014.
• 15 years extensive hands on experience in various aspects of projects and project
management within maintenance, power distribution networks monitoring and
supervision and construction projects as well.
• Authored, Co-Authored at PMWorld Library, PWLJ.
• Volunteered at PMI-Global Congress EMEA-2014 – Dubai, 5th to 8th May 2014.
• Technical presentation at PMI-AGC 15th International conference –Bahrain 19th to 21st
January 2015.
• Technical presentation at 54th AACEi-SF Bay Annual Western Winter Workshop, Lake
Tahoe, Nevada, USA
• Technical presentation 55th AACEi-SF Bay Annual Western Winter Workshop, Indian
Wells, CA, USA
• Independent Project Management and cost engineering/Control Instructor.
3. • Common causes of loss in productivity.
• Using earned value implementation in labor productivity
monitoring & Controlling.
• Labor productivity improvement using WBS & OBS
integration model.
Outlines
4. The Objectives of this presentation is to show the effect of implementing
WBS & OBS integration matrix to monitor the project performance and
improve the labor productivity by assigning specific work packages to
appropriate organizational units.
Objectives
5.
6.
7. Team Member Role Reporting To Responsibilities
Project Manager (PM) 1- Lead project Team Organization Management 1- Monitor Cost
2- Monitor Time
3- Achieve Planned cost
4- Achieve Planned Time
Construction Manager (CM) 1-Lead Activities Execution Project Manager (PM) 1-Monitor progress
2- Monitor Progress 2-Momitor Subcontractors
Performance
3-prepare payments
4-Follow issues with consultant
Project Engineer (PE) 1- Lead Drawing approvals Construction Manager (CM) 1- Deliver Drawings & materials
2- Lead material approvals As per project requirements
3- Follow material delivery 2-Issue Materials orders.
4- Distribute activities 3- Follow materials delivery
4- Distribute activities with related
Materials & Drawings.
5- Conform Quality.
Site Engineer (SE)
1-Leads Supervisors
Project Engineer (PE)
1- Distribute supervisors & Technicians
2- Lead Technicians 2- Follow planned Activities.
3- Lead Store 3- Issue materials from stores
4- Achieve progress
5- Perform Quality
Supervisors 1- Lead Technicians Site Engineer (SE) 1- Perform Drawings
2- Supervise installation 2- Control Technicians productivity
3- Control Materials installation
4- Achieve Quality
8.
9. 9
We should discriminate between and .
Production in construction projects has many definitions, as full product is
“Completed Project”, while the project has many parts such as Activities it
means “Each Activity Completed is a Product”. While Productivity in
construction refers to relation among activities completion against time
spent to complete those activities , it’s a measure of labor efficiency. Our
approach is to analyze productivity against time planned for each activity.
On a simple word Production is a measure of output although Productivity
is a measure of production performance. To achieve our goal we should
realize the common causes, circumstances and events that may affect the
productivity.
10. Technical Issues.
Incomplete drawings or specifications for each activity may create ambiguity to project
team and this may creates uncertainties due to lack of information’s.
COMMON CAUSES OF LOSS IN PRODUCTIVITY
11. Missed Supervision.
”Relocation of work force before task is completed”. And over loading supervisors with
multitasks in different areas. This two major categories resulting missed supervision and low
performance as well.
COMMON CAUSES OF LOSS IN PRODUCTIVITY
12. Wrong Distribution of resources.
The right materials, tools, equipment's and any other resources must be provided
to that location in order to have the desired productivity. Unplanned distribution
result in delays due to shifting wrong materials and any other resources to the area
of subject matter work is required.
COMMON CAUSES OF LOSS IN PRODUCTIVITY
13. Resource Over allocation
Each zone and/or activity has limited capacity hence assigning extra
people to perform same activity results into idle status.
COMMON CAUSES OF LOSS IN PRODUCTIVITY
14. Overtime
It’s a technique but has limited usage privileges, it can be used for a
certain activities but cannot be general practice as it exhaust labors
and this will results in less productivity.
COMMON CAUSES OF LOSS IN PRODUCTIVITY
15. Installation of Air Duct (Shoe Collar) for Exhaust system at parking area
,Normally follow the following criteria
SEQUENCE OF ACTIVITIES
18. Comparing Criteria (A) & (B)
Manpower
used(Nrs.)
Duration
(Hrs.)
Production
(Nrs.)
IncurredCost(Hrs/Pc)
Cost
Hrs/Psc
Criteria(A) 3 10 3 (10Hrs*3Labors)/3Pcs 10Hrs/Pcs
Criteria(B) 2 10 8 (10Hrs*2Labors)/8Pcs 2.5Hrs/Pcs
Conclusion
Criteria (B) proved to be higher productivity rates per hour which means less cost & better
timing to complete the same task.
SEQUENCE OF ACTIVITIES
19. 19
Effect of Learning Curve in Labor Productivity
Learning Curve
It’s a technique achieved by repeating same activity in different zones by a fixed group of
technicians, in case those groups got interrupted before completing same activity in all
zones the productivity of those groups will be lower when we assign them again to the
previous activity zone, Look at the following example to find the implications of interrupting
learning curve.
Example
In residential tower has typical floors, we assigned a group of
technicians to fix light fitting under supervision of one supervisor,
we noticed the following,
22. 22
Effect of Learning Curve in Labor Productivity
Looking to previous tables which Indicates that fixing group of 3
technicians to perform the same activity repeatedly will increase their
productivity day to day as the same group will be more familiar with the
type of the light fitting and site conditions hence give more productivity
(See Graph showing learning curve improvement), while interrupting
those groups will disrupt the learning curve of the technicians as in
second building with same specifications we have the same
arrangements, but the activity were interrupted by reassigning the
technicians to other activities then returning back to the light fitting
installation activity as shown in the following graph.
26. 26
Productivity Improvement
As we see from the example a clear scope for specific single organizational
component in the organizational break down structure (OBS) will give the right
framework of monitoring project performance and labor productivity as well,
further to this it’s apparent that this model reflects avoidance of many causes
of productivity loss. Such as miss of supervision and resource wrong
distribution. This will bring to mind where the necessity of WBS & OBS
integration matrix is and what the real effect of direct labor cost control is?,
here we come to the objective of this Presentation which is how to improve
labor direct cost using WBS & OBS integration and how it can be implemented.
27. 27
Productivity Improvement
To monitor labor performance during construction you must have
clear framework.
This framework requires all team members to know their roles and
responsibilities thru. RAM.
Use WBS & OBS integration matrix to assign specific resources to
specific task
29. 29
Working Example
Create WBS & Assign Tasks
Assigning the data
on the smallest
elements (tasks)
and integrating
the results for the
work packages,
control accounts
and WBS elements
Break down the
project according
to the view of
the project
Context
30. 30
Construction WBS
PROJECT (WBS) (0)
Zone1
0.1
Zone2
0.2
Zone3
0.3
Zone4
0.4
Zone5
0.5
Level (0)
Level (1)
0.1.1 Earth work 0.1.2 Substructure 0.1.3 Super structure
0.1.4 Internal
Finishing
0.1.5 MEP
1.5.1 HVAC 1.5.2 Plumbing 1.5.3 Firefighting
1.5.4 electrical
work
1.5.1.G ground floor 1.5.1.1 First floor
Level (2)
Level
(3)
Power Cabling - 3.1.0 - First Floor
Lighting Points - First Floor
Power Points - First Floor
lighting & Power wire - First Floor
Lighting power - First FloorDetailed level activities or steps for
estimating the required resources for
OBS Assignments
Work packages
31. 31
Date: Duty OT
Electricial
SL. Res. Engineer Foreman
Group
(M.U.I.xx)
ID No Employee Name Designation P A Zone Villa Description Of Work
Actual
Qty
Target
Qty
Duty
Over
Time
Bonus
Hours
Remarks
1 □ □
2 □ □
3 □ □
4 □ □
5 □ □
6 □ □
7 □ □
8 □ □
Charge hand
Electrician
Assistant Electrician
Total
Create Assignment sheet of each OBS Unit
35. The previous figure shows that each and every work package is assigned to specific group to
facilitate resource control including manpower and performance monitoring and this scheme
should be incorporated with the roles and responsibility matrix. Hence WBS & OBS integration
technique will results in:
All team members will understand the required activities and tasks to be performed.
All team members will be aware of their responsibilities.
Well define scope, WBS decomposition and activities duration will avoid over manning and
excessive overtime as well.
Well defined scope and WBS will avoid wrong sequence of activity and give high rate of
manpower productivity.
Fixing specific groups will avoid learning curve disturbance and strengthen it and results in
high productivity rate due to awareness of the activities
USING WBS & OBS TO CONTROL PRODUCTIVITY
36. WBS & OBS integration technique is arises as useful methodology to achieve productivity improvement, and this
will results in:
Invest the manpower by continues appraisals’
Give the organization a clear idea about recourse pool availability for other projects within the organization
Manpower productivity rates improvement will give the organization to bid competitive prices for new projects
acquisition.
A high productivity rates prevent outsourcing.
A high productivity rate gives the organization standard index of activities duration which will results in right cost
and time estimation.
High productivity rates and targets completion on time will give the organization chance to award the team
members which will motivate team members.
CONCLUSION