SlideShare ist ein Scribd-Unternehmen logo
1 von 35
helpdesk@construction-productivity.co.uk
htt://www.construction-productivity.co.uk
WORK BREAK DOWNWORK BREAK DOWN
STRUCTURE (WBS)STRUCTURE (WBS)
WORK BRAEK DOWN STRUCTURE (WBS)
A technique by which
the work of a project is
divided and sub divided
for management, and
control purposes.
WORK BRAEK DOWN STRUCTURE
(WBS)
The work is developed through successive
increasing levels of details.
Advantage
• work delegated into coherent packages
• work defined at appropriate levels of detail
for cost control
WORK BRAEK DOWN STRUCTURE
(WBS)
• work defined at appropriate levels of detail
for nesting plans i.e. rolling wave of
program.
• Variances can be measured between
Planned and Actual.
• The work packages are more stable than
long chains of discontinuous work
activities.
• As a result risk is more contained and
measured more accurately.
WORK BRAEK DOWN STRUCTURE
(WBS)
• successive levels of detail may be evolved
• the project sponsor may call for reports
from the Project manager based on the
work content at Level 1, 2 and sometimes
at Level 3,
WORK BRAEK DOWN STRUCTURE
(WBS)
• the Project Manger may call for Reports
from Project Contributors based on work
content at Level 3, 4 and 5,
• the contractor’s Construction Management
Team also may ask for report from Site
Engineers at Level 5 and below Level 5,
WORK BRAEK DOWN STRUCTURE
(WBS)
• Different Levels Breakdown
and Work Package require
different Project Contributors
with different Responsibilities.
• The flow is from Left to Right.
WORK BRAEK DOWN STRUCTURE
(WBS)
• successively at each Level, may be
made to mirror the timing of the work;
• and facilities a Rolling Wave or
Nested Programme;
• from project level down to the lowest
task orientated package level.
WORK BRAEK DOWN STRUCTURE
(WBS)
• each work package can be identified with
a unique cost code;
• and Actual and Planned Cost variances
compared;
• each work package can be fully described,
for example:
• Content;
• what is included and what is excluded in a
package statement.
• WBS (Food Process Factory)-Level
1
Project Definition/Scope
Management Site
Procurement
Outline
Design &
State
Approval
Detail
Design &
Costing
Procurement
And
Construction
Commision
&
Handover
Left to right
WORK BRAEK DOWN STRUCTURE (WBS)
Procurement&
Construction
Bill of
Quantity
Tender &
Negotiation
Work on
Site
Management
Fees
LEFT TO RIGHT
WBS (Food Process Factory)-Level 3
WORK BRAEK DOWN STRUCTURE (WBS)
Work on Site
Preliminary
Works
Sub-
structure
Super-
structure
Claddind &
Envelope
External
Work
Internal
Work
WBS (Food Process Factory)-Level 4 and 5
WORK BRAEK DOWN STRUCTURE (WBS)
Work on Site
Total cost ÂŁ1, 900, 250.00
Preliminary
Works
ÂŁ105.000.00
Sub-
structure
ÂŁ270.00
Super-
Structure
ÂŁ
Claddind &
Envelope
ÂŁ
External
Work
ÂŁ
Internal
Work
ÂŁ
Site
Clearance
ÂŁ
Piling
ÂŁ
Foundation
s
ÂŁ
Drainage
ÂŁ
Floor slab
ÂŁ
WORK BRAEK DOWN STRUCTURE
(WBS)
Project Mgmt
Prelim Design
1.1.1
Title I Design
1.1.2
Final Design
1.1.3
Design
1.1
Procurement
1.2
Construction
1.3 1.4
ACME Project X
1.0
Resource allocation
Project Mgmt
Prelim Design
1.1.1
Title I Design
1.1.2
Final Design
1.1.3
Design
1.1
Procurement
1.2
Construction
1.3 1.4
ACME Project X
1.0
Preliminary Design 1.1.1 Jan Feb Mar Apr May
1.1.1.1 Define Specifications & Req.
1.1.1.2 Develop Preliminary Design
1.1.1.3 Review Preliminary Design
1.1.1.4 Incorporate Comments
1.1.1.5 Preliminary Design Complete
Resource allocation
Project Mgmt
Prelim Design
1.1.1
Title I Design
1.1.2
Final Design
1.1.3
Design
1.1
Procurement
1.2
Construction
1.3 1.4
ACME Project X
1.0
Preliminary Design 1.1.1 Hours Jan Feb Mar Apr May
1.1.1.1 Define Specifications & Req. 1,500 1,000
1.1.1.2 Develop Preliminary Design 2,000 2,000
1.1.1.3 Review Preliminary Design 500 500
1.1.1.4 Incorporate Comments 320 320
1.1.1.5 Preliminary Design Complete 1,000
Resource allocation for each
activity
Project Mgmt
Prelim Design
1.1.1
Title I Design
1.1.2
Final Design
1.1.3
Design
1.1
Procurement
1.2
Construction
1.3 1.4
ACME Project X
1.0
Preliminary Design 1.1.1 Hours Jan Feb Mar Apr May
1.1.1.1 Define Specifications & Req.
1,500 1,000
1.1.1.2 Develop Preliminary Design
2,000 2,000
1.1.1.3 Review Preliminary Design
500 500
1.1.1.4 Incorporate Comments
320 320
1.1.1.5 Preliminary Design Complete
1,000
Resource allocation
ACME Housing Corporation
1
House Building
Project
1.1
Concrete
1.1.1
Framing
1.1.2
Plumbing
1.1.3
Electrical
1.1.4
Interior
1.1.5
Roofing
1.1.6
Resource allocation-after WBS
ACME Housing Corporation
1
House Building
Project
1.1
Concrete
1.1.1
Pour Foundation
1.1.1.1
Install Patio
1.1.1.2
Stairway
1.1.1.3
Framing
1.1.2
Frame Exterior
Walls
1.1.2.1
Frame Interior
Walls
1.1.2.2
Install Roofing
Trusses
1.1.2.3
Plumbing
1.1.3
Install Water
Lines
1.1.3.1
Install Gas Lines
1.1.3.2
Install B/K
Fixtures
1.1.3.3
Electrical
1.1.4
Install Wiring
1.1.4.1
Install Outlets/
Switches
1.1.4.2
Install Fixtures
1.1.4.3
Interior
1.1.5
Install Drywall
1.1.5.1
Install Carpets
1.1.5.2
Install Painting
1.1.5.3
Roofing
1.1.6
Install Felt
1.1.6.1
Install Shingles
1.1.6.2
Install Vents
1.1.6.3
MILESTONE PROGRAMMING
• The Milestone programmes provide the
‘administrative level’ in the planning
hierarchy.
• The activity programme provides the
detailed ‘technical level’.
• It focused on goals and not on the method of
reaching them.
• The Milestones and Objectives remain
reasonably constant through out the project.
• Methods of reaching goals may change.
MILESTONE PROGRAMMING
• Goal Directed Project Management
(GDPM) is a powerful, pragmatic
approach for gaining consensus from
all stakeholders on the overall
objectives of a business program or
project.
MILESTONE PROGRAMMING
• The approach is fully compatible with
industry standards such as:
• PRINCE2
• SUMMIT
• V-Model or HERMES
• It provides a single-page, top-level view of
the goals of the project (a milestone plan).
DEVELOPING THE MILESTONE PROGRAMME
1-The planning team
• The team responsible for ensuring
that the project objectives are met
should be present to formulate the
Milestone programme.
2-The result paths
• The project Objectives and Scope are
set out in the project definition
Document.
MILESTONE PROGRAMMING
• The team considers at each level, the
Primary Objectives such as:
• How will success be judged?
• What are the critical factors to monitor?
• What are Key Performance Indicators for
this project?
DEVELOPING THE MILESTONE PROGRAMME
3-Milestones
• The team actively generates ideas for the
like list of Milestones.
• Each Milestone description should:
• form a check point towards the final
objective,
• describe a condition or state that the
project must occupy at various stages in
order to reach it’s final objective,
DEVELOPING THE MILESTONE
PROGRAMME
• show a logical sequence towards the final
objective;
• state what to achieve, and not how to
achieve;
• focus on the goal;
• state a specific outcome, such as,
approval of a report and who approve it;
DEVELOPING THE MILESTONE
PROGRAMME
• Also Milestone should:
• be natural;
• represent important decisions;
• be controllable, either quantitively or
qualitatively;
• be few in number (10 TO 20);
• be at useful intervals(ie monthly);
4- Drafting the Milestone Plan
NESTED PROGRAMMING
• The primary objectives of the project
are provided in the Level 1 Project
Programme.
• Below The Work Breakdown Structure
(WBS) most projects are capable of
being split into a member of Stages or
Phases (Work Packages).
NESTED PROGRAMMING
• A milestoneplan may be produced
for each of these phases.
• for example at Level 1-Reported at
20 max controlled Milestones.
• Or at Level-2- let us say 4 Stages –
each Reported at 20 max controlled
Milestones.
NESTED PROGRAMMING
• At Level 3 and below, the influence of
detail activities can make it difficult to
develop meaningful Milestone
Programme.
• At this level down on the WBS, it is
normal to revert to activity
programmes.
NESTED PROGRAMMING
• At the lowest activity and task levels,
Milestones occur along the path of
networked activities (CPM) and are shown
as ‘Flagging’ up on the network or Gantt
chart.
• Some packages allow them to be fixed
and generate ‘Supper Critical Paths’. (See
Oxford Brookes University-Micro Planner).
DEVELOPING THE MILESTONE
PROGRAMME
Conclusion
• The Milestone methods is purely a means of
monitoring and controlling progress towards the
Projects Objectives at the highest level of WBS.
• It is useful where there is insufficient detailed
information to produce meaningful accurate
lower level Activities based programmes.
Define Goals
Tchnological Communication
s
Cost
Latest Process
plant
Latest Road Rail Package
Latest Hygiene Finishes
Latest Building Management System
Latest Computer Process System
Latest Robotics
Negociation
And
Completion
of Rdad/Rail
link to EU
To Cmply with Finacial and
Strategic Plans
Example of Level 1- Factory Project
134 work break break down structure
134 work break break down structure

Weitere ähnliche Inhalte

Was ist angesagt?

Project-Planning
Project-PlanningProject-Planning
Project-PlanningRon Drew
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and schedulingadeel hamid
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource SmoothingDavidMcLachlan1
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structureproject management
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost controlGuhan M
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project ManagementAravind Samala
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structureAbhishek Pachisia
 
Construction project management
Construction project managementConstruction project management
Construction project managementSenthil Kannan
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?Kenny Hirschmann
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primeverasneha saranya
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure pptnazi2020
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULEAjeesh Mk
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project managementKabilan Kabi
 
WBS presentation
WBS presentationWBS presentation
WBS presentationjpstewar
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structureCOEPD HR
 
Project cost control
Project cost controlProject cost control
Project cost controlSourabh Modgil
 

Was ist angesagt? (20)

Project-Planning
Project-PlanningProject-Planning
Project-Planning
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing6.5 Resource Leveling and Resource Smoothing
6.5 Resource Leveling and Resource Smoothing
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
PM using P6
PM using P6PM using P6
PM using P6
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
MS Project
MS ProjectMS Project
MS Project
 
What is a Work Breakdown Structure?
What is a Work Breakdown Structure?What is a Work Breakdown Structure?
What is a Work Breakdown Structure?
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Work breakdown structure ppt
Work breakdown structure pptWork breakdown structure ppt
Work breakdown structure ppt
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
WBS presentation
WBS presentationWBS presentation
WBS presentation
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Project cost control
Project cost controlProject cost control
Project cost control
 

Andere mochten auch

Construction safety management
Construction safety managementConstruction safety management
Construction safety managementGERServices
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structureMD SABBIR SHARIF
 
Project scheduling and work break down structure(wbs) 12 cs18
Project scheduling and work break down structure(wbs) 12 cs18Project scheduling and work break down structure(wbs) 12 cs18
Project scheduling and work break down structure(wbs) 12 cs18Engr Imran Ashraf
 
Work Break Down Structure
Work Break Down StructureWork Break Down Structure
Work Break Down StructureSomtel
 
USAID HOUSING PROGRAM IN HAITI FALLS SHORT
USAID HOUSING PROGRAM IN HAITI FALLS SHORTUSAID HOUSING PROGRAM IN HAITI FALLS SHORT
USAID HOUSING PROGRAM IN HAITI FALLS SHORTStanleylucas
 
Sustainable development and project management
Sustainable development and project managementSustainable development and project management
Sustainable development and project managementOmar Latif
 
Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)stakeholdermap
 
Construction Site Health & Safety
Construction Site Health & SafetyConstruction Site Health & Safety
Construction Site Health & SafetySAURABH SINGH
 
Avoiding Common Legal Billing pitfalls
Avoiding Common Legal Billing pitfallsAvoiding Common Legal Billing pitfalls
Avoiding Common Legal Billing pitfallsRakesh (Rick) Kabra
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management OverviewMadhumalti Sharma
 
Managing Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsManaging Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsAGC of California
 
Hands on Measurement for K-2 Learners
Hands on Measurement for K-2 LearnersHands on Measurement for K-2 Learners
Hands on Measurement for K-2 Learnersmflaming
 
Construction Project Management.
Construction Project Management.Construction Project Management.
Construction Project Management.Yousef Abujubba
 
Wbs For Building Project
Wbs For Building ProjectWbs For Building Project
Wbs For Building Projectproject management
 
Work Breakdown Structure Use This
Work Breakdown Structure Use ThisWork Breakdown Structure Use This
Work Breakdown Structure Use Thisproject management
 

Andere mochten auch (20)

Wbs Building Use This
Wbs Building Use ThisWbs Building Use This
Wbs Building Use This
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Construction safety management
Construction safety managementConstruction safety management
Construction safety management
 
Certified Master Project Manager MPM
Certified Master Project Manager MPMCertified Master Project Manager MPM
Certified Master Project Manager MPM
 
Work breakdown structure
Work breakdown structureWork breakdown structure
Work breakdown structure
 
Project scheduling and work break down structure(wbs) 12 cs18
Project scheduling and work break down structure(wbs) 12 cs18Project scheduling and work break down structure(wbs) 12 cs18
Project scheduling and work break down structure(wbs) 12 cs18
 
Work Break Down Structure
Work Break Down StructureWork Break Down Structure
Work Break Down Structure
 
USAID HOUSING PROGRAM IN HAITI FALLS SHORT
USAID HOUSING PROGRAM IN HAITI FALLS SHORTUSAID HOUSING PROGRAM IN HAITI FALLS SHORT
USAID HOUSING PROGRAM IN HAITI FALLS SHORT
 
Sustainable development and project management
Sustainable development and project managementSustainable development and project management
Sustainable development and project management
 
Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)Work Breakdown Structures (WBS)
Work Breakdown Structures (WBS)
 
Construction Site Health & Safety
Construction Site Health & SafetyConstruction Site Health & Safety
Construction Site Health & Safety
 
Avoiding Common Legal Billing pitfalls
Avoiding Common Legal Billing pitfallsAvoiding Common Legal Billing pitfalls
Avoiding Common Legal Billing pitfalls
 
Project Management Overview
Project Management OverviewProject Management Overview
Project Management Overview
 
Managing Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsManaging Cash Flows On Construction Projects
Managing Cash Flows On Construction Projects
 
Hands on Measurement for K-2 Learners
Hands on Measurement for K-2 LearnersHands on Measurement for K-2 Learners
Hands on Measurement for K-2 Learners
 
Construction Project Management.
Construction Project Management.Construction Project Management.
Construction Project Management.
 
Cashbook, Passbook and BRC
Cashbook, Passbook and BRCCashbook, Passbook and BRC
Cashbook, Passbook and BRC
 
Measurements
MeasurementsMeasurements
Measurements
 
Wbs For Building Project
Wbs For Building ProjectWbs For Building Project
Wbs For Building Project
 
Work Breakdown Structure Use This
Work Breakdown Structure Use ThisWork Breakdown Structure Use This
Work Breakdown Structure Use This
 

Ähnlich wie 134 work break break down structure

PositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docxPositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docxChantellPantoja184
 
unit-vpart-2.ppt
unit-vpart-2.pptunit-vpart-2.ppt
unit-vpart-2.pptTejaTeja57
 
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter
 
SPM_UNIT-2.pptx
SPM_UNIT-2.pptxSPM_UNIT-2.pptx
SPM_UNIT-2.pptxSushant895574
 
Software management disciplines
Software management disciplinesSoftware management disciplines
Software management disciplinesKuppusamy P
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Projectproject management
 
Defining The Project
Defining The ProjectDefining The Project
Defining The ProjectEarl Tongol
 
Project management-professional-free-sample
Project management-professional-free-sampleProject management-professional-free-sample
Project management-professional-free-sampleReadytoTrain .
 
1 Work Breakdown Structures (WBS) 2 WBS .docx
1 Work Breakdown Structures (WBS) 2 WBS .docx1 Work Breakdown Structures (WBS) 2 WBS .docx
1 Work Breakdown Structures (WBS) 2 WBS .docxSONU61709
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxkiranroy6777
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sampleAnnsstand
 
Project management-professional-free-sample
Project management-professional-free-sampleProject management-professional-free-sample
Project management-professional-free-sampleReadytoTrain .
 
MIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project MMIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project MIlonaThornburg83
 
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersPMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersReady to Train
 
802003 634318955109991250
802003 634318955109991250802003 634318955109991250
802003 634318955109991250rajat898
 
Project scope management
 Project scope management Project scope management
Project scope managementSidraSaleem17
 

Ähnlich wie 134 work break break down structure (20)

PositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docxPositioningPositioning of Product or ServiceParis based weig.docx
PositioningPositioning of Product or ServiceParis based weig.docx
 
PME UNIT-3.pptx
PME UNIT-3.pptxPME UNIT-3.pptx
PME UNIT-3.pptx
 
Babu 143
Babu 143Babu 143
Babu 143
 
unit-vpart-2.ppt
unit-vpart-2.pptunit-vpart-2.ppt
unit-vpart-2.ppt
 
Sameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle itSameer Mitter - What is Project Management and How to Handle it
Sameer Mitter - What is Project Management and How to Handle it
 
SPM_UNIT-2.pptx
SPM_UNIT-2.pptxSPM_UNIT-2.pptx
SPM_UNIT-2.pptx
 
Software management disciplines
Software management disciplinesSoftware management disciplines
Software management disciplines
 
Chap 4 Defining A Project
Chap 4 Defining A ProjectChap 4 Defining A Project
Chap 4 Defining A Project
 
Defining The Project
Defining The ProjectDefining The Project
Defining The Project
 
Project management-professional-free-sample
Project management-professional-free-sampleProject management-professional-free-sample
Project management-professional-free-sample
 
1 Work Breakdown Structures (WBS) 2 WBS .docx
1 Work Breakdown Structures (WBS) 2 WBS .docx1 Work Breakdown Structures (WBS) 2 WBS .docx
1 Work Breakdown Structures (WBS) 2 WBS .docx
 
D22MB040_Unit_6.pptx
D22MB040_Unit_6.pptxD22MB040_Unit_6.pptx
D22MB040_Unit_6.pptx
 
Pmp project management professional free sample
Pmp project management professional free samplePmp project management professional free sample
Pmp project management professional free sample
 
Project management-professional-free-sample
Project management-professional-free-sampleProject management-professional-free-sample
Project management-professional-free-sample
 
MIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project MMIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project M
 
Gantt Charts.ppt
Gantt Charts.pptGantt Charts.ppt
Gantt Charts.ppt
 
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for TrainersPMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
PMP Exam Prep Training Materials based on PMBOK Guide 5th edition for Trainers
 
802003 634318955109991250
802003 634318955109991250802003 634318955109991250
802003 634318955109991250
 
Lecture 3.pptx
Lecture 3.pptxLecture 3.pptx
Lecture 3.pptx
 
Project scope management
 Project scope management Project scope management
Project scope management
 

Mehr von Dr Fereidoun Dejahang

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020Dr Fereidoun Dejahang
 
28 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-201928 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-2019Dr Fereidoun Dejahang
 
16 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-201916 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-2019Dr Fereidoun Dejahang
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrunDr Fereidoun Dejahang
 
027 fast-tracked projects-materials
027 fast-tracked projects-materials027 fast-tracked projects-materials
027 fast-tracked projects-materialsDr Fereidoun Dejahang
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvementDr Fereidoun Dejahang
 
025 enterprise resources management
025 enterprise resources management025 enterprise resources management
025 enterprise resources managementDr Fereidoun Dejahang
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-writeDr Fereidoun Dejahang
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)Dr Fereidoun Dejahang
 
021 construction productivity (1)
021 construction productivity (1)021 construction productivity (1)
021 construction productivity (1)Dr Fereidoun Dejahang
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sectorDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projectsDr Fereidoun Dejahang
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning processDr Fereidoun Dejahang
 
011 business performance management
011 business performance management011 business performance management
011 business performance managementDr Fereidoun Dejahang
 

Mehr von Dr Fereidoun Dejahang (20)

27 j20 my news punch -dr f dejahang 27-01-2020
27 j20 my news punch -dr f dejahang  27-01-202027 j20 my news punch -dr f dejahang  27-01-2020
27 j20 my news punch -dr f dejahang 27-01-2020
 
28 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-201928 dej my news punch rev 28-12-2019
28 dej my news punch rev 28-12-2019
 
16 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-201916 fd my news punch rev 16-12-2019
16 fd my news punch rev 16-12-2019
 
029 fast-tracking projects
029 fast-tracking projects029 fast-tracking projects
029 fast-tracking projects
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun
 
027 fast-tracked projects-materials
027 fast-tracked projects-materials027 fast-tracked projects-materials
027 fast-tracked projects-materials
 
026 fast react-productivity improvement
026 fast react-productivity improvement026 fast react-productivity improvement
026 fast react-productivity improvement
 
025 enterprise resources management
025 enterprise resources management025 enterprise resources management
025 enterprise resources management
 
022 b construction productivity-write
022 b construction productivity-write022 b construction productivity-write
022 b construction productivity-write
 
022 a construction productivity (2)
022 a construction productivity (2)022 a construction productivity (2)
022 a construction productivity (2)
 
021 construction productivity (1)
021 construction productivity (1)021 construction productivity (1)
021 construction productivity (1)
 
019 competencies-managers
019 competencies-managers019 competencies-managers
019 competencies-managers
 
018 company productivity
018 company productivity018 company productivity
018 company productivity
 
017 communication
017 communication017 communication
017 communication
 
016 communication in construction sector
016 communication in construction sector016 communication in construction sector
016 communication in construction sector
 
015 changes-process model
015 changes-process model015 changes-process model
015 changes-process model
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
013 changes in construction projects
013 changes in construction projects013 changes in construction projects
013 changes in construction projects
 
012 bussiness planning process
012 bussiness planning process012 bussiness planning process
012 bussiness planning process
 
011 business performance management
011 business performance management011 business performance management
011 business performance management
 

KĂźrzlich hochgeladen

CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitterShivangiSharma879191
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoĂŁo Esperancinha
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 

KĂźrzlich hochgeladen (20)

CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter8251 universal synchronous asynchronous receiver transmitter
8251 universal synchronous asynchronous receiver transmitter
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 

134 work break break down structure

  • 2. WORK BRAEK DOWN STRUCTURE (WBS) A technique by which the work of a project is divided and sub divided for management, and control purposes.
  • 3. WORK BRAEK DOWN STRUCTURE (WBS) The work is developed through successive increasing levels of details. Advantage • work delegated into coherent packages • work defined at appropriate levels of detail for cost control
  • 4. WORK BRAEK DOWN STRUCTURE (WBS) • work defined at appropriate levels of detail for nesting plans i.e. rolling wave of program. • Variances can be measured between Planned and Actual. • The work packages are more stable than long chains of discontinuous work activities. • As a result risk is more contained and measured more accurately.
  • 5. WORK BRAEK DOWN STRUCTURE (WBS) • successive levels of detail may be evolved • the project sponsor may call for reports from the Project manager based on the work content at Level 1, 2 and sometimes at Level 3,
  • 6. WORK BRAEK DOWN STRUCTURE (WBS) • the Project Manger may call for Reports from Project Contributors based on work content at Level 3, 4 and 5, • the contractor’s Construction Management Team also may ask for report from Site Engineers at Level 5 and below Level 5,
  • 7. WORK BRAEK DOWN STRUCTURE (WBS) • Different Levels Breakdown and Work Package require different Project Contributors with different Responsibilities. • The flow is from Left to Right.
  • 8. WORK BRAEK DOWN STRUCTURE (WBS) • successively at each Level, may be made to mirror the timing of the work; • and facilities a Rolling Wave or Nested Programme; • from project level down to the lowest task orientated package level.
  • 9. WORK BRAEK DOWN STRUCTURE (WBS) • each work package can be identified with a unique cost code; • and Actual and Planned Cost variances compared; • each work package can be fully described, for example: • Content; • what is included and what is excluded in a package statement.
  • 10. • WBS (Food Process Factory)-Level 1 Project Definition/Scope Management Site Procurement Outline Design & State Approval Detail Design & Costing Procurement And Construction Commision & Handover Left to right
  • 11. WORK BRAEK DOWN STRUCTURE (WBS) Procurement& Construction Bill of Quantity Tender & Negotiation Work on Site Management Fees LEFT TO RIGHT WBS (Food Process Factory)-Level 3
  • 12. WORK BRAEK DOWN STRUCTURE (WBS) Work on Site Preliminary Works Sub- structure Super- structure Claddind & Envelope External Work Internal Work WBS (Food Process Factory)-Level 4 and 5
  • 13. WORK BRAEK DOWN STRUCTURE (WBS) Work on Site Total cost ÂŁ1, 900, 250.00 Preliminary Works ÂŁ105.000.00 Sub- structure ÂŁ270.00 Super- Structure ÂŁ Claddind & Envelope ÂŁ External Work ÂŁ Internal Work ÂŁ Site Clearance ÂŁ Piling ÂŁ Foundation s ÂŁ Drainage ÂŁ Floor slab ÂŁ
  • 14. WORK BRAEK DOWN STRUCTURE (WBS) Project Mgmt Prelim Design 1.1.1 Title I Design 1.1.2 Final Design 1.1.3 Design 1.1 Procurement 1.2 Construction 1.3 1.4 ACME Project X 1.0
  • 15. Resource allocation Project Mgmt Prelim Design 1.1.1 Title I Design 1.1.2 Final Design 1.1.3 Design 1.1 Procurement 1.2 Construction 1.3 1.4 ACME Project X 1.0 Preliminary Design 1.1.1 Jan Feb Mar Apr May 1.1.1.1 Define Specifications & Req. 1.1.1.2 Develop Preliminary Design 1.1.1.3 Review Preliminary Design 1.1.1.4 Incorporate Comments 1.1.1.5 Preliminary Design Complete
  • 16. Resource allocation Project Mgmt Prelim Design 1.1.1 Title I Design 1.1.2 Final Design 1.1.3 Design 1.1 Procurement 1.2 Construction 1.3 1.4 ACME Project X 1.0 Preliminary Design 1.1.1 Hours Jan Feb Mar Apr May 1.1.1.1 Define Specifications & Req. 1,500 1,000 1.1.1.2 Develop Preliminary Design 2,000 2,000 1.1.1.3 Review Preliminary Design 500 500 1.1.1.4 Incorporate Comments 320 320 1.1.1.5 Preliminary Design Complete 1,000
  • 17. Resource allocation for each activity Project Mgmt Prelim Design 1.1.1 Title I Design 1.1.2 Final Design 1.1.3 Design 1.1 Procurement 1.2 Construction 1.3 1.4 ACME Project X 1.0 Preliminary Design 1.1.1 Hours Jan Feb Mar Apr May 1.1.1.1 Define Specifications & Req. 1,500 1,000 1.1.1.2 Develop Preliminary Design 2,000 2,000 1.1.1.3 Review Preliminary Design 500 500 1.1.1.4 Incorporate Comments 320 320 1.1.1.5 Preliminary Design Complete 1,000
  • 18. Resource allocation ACME Housing Corporation 1 House Building Project 1.1 Concrete 1.1.1 Framing 1.1.2 Plumbing 1.1.3 Electrical 1.1.4 Interior 1.1.5 Roofing 1.1.6
  • 19. Resource allocation-after WBS ACME Housing Corporation 1 House Building Project 1.1 Concrete 1.1.1 Pour Foundation 1.1.1.1 Install Patio 1.1.1.2 Stairway 1.1.1.3 Framing 1.1.2 Frame Exterior Walls 1.1.2.1 Frame Interior Walls 1.1.2.2 Install Roofing Trusses 1.1.2.3 Plumbing 1.1.3 Install Water Lines 1.1.3.1 Install Gas Lines 1.1.3.2 Install B/K Fixtures 1.1.3.3 Electrical 1.1.4 Install Wiring 1.1.4.1 Install Outlets/ Switches 1.1.4.2 Install Fixtures 1.1.4.3 Interior 1.1.5 Install Drywall 1.1.5.1 Install Carpets 1.1.5.2 Install Painting 1.1.5.3 Roofing 1.1.6 Install Felt 1.1.6.1 Install Shingles 1.1.6.2 Install Vents 1.1.6.3
  • 20. MILESTONE PROGRAMMING • The Milestone programmes provide the ‘administrative level’ in the planning hierarchy. • The activity programme provides the detailed ‘technical level’. • It focused on goals and not on the method of reaching them. • The Milestones and Objectives remain reasonably constant through out the project. • Methods of reaching goals may change.
  • 21. MILESTONE PROGRAMMING • Goal Directed Project Management (GDPM) is a powerful, pragmatic approach for gaining consensus from all stakeholders on the overall objectives of a business program or project.
  • 22. MILESTONE PROGRAMMING • The approach is fully compatible with industry standards such as: • PRINCE2 • SUMMIT • V-Model or HERMES • It provides a single-page, top-level view of the goals of the project (a milestone plan).
  • 23. DEVELOPING THE MILESTONE PROGRAMME 1-The planning team • The team responsible for ensuring that the project objectives are met should be present to formulate the Milestone programme. 2-The result paths • The project Objectives and Scope are set out in the project definition Document.
  • 24. MILESTONE PROGRAMMING • The team considers at each level, the Primary Objectives such as: • How will success be judged? • What are the critical factors to monitor? • What are Key Performance Indicators for this project?
  • 25. DEVELOPING THE MILESTONE PROGRAMME 3-Milestones • The team actively generates ideas for the like list of Milestones. • Each Milestone description should: • form a check point towards the final objective, • describe a condition or state that the project must occupy at various stages in order to reach it’s final objective,
  • 26. DEVELOPING THE MILESTONE PROGRAMME • show a logical sequence towards the final objective; • state what to achieve, and not how to achieve; • focus on the goal; • state a specific outcome, such as, approval of a report and who approve it;
  • 27. DEVELOPING THE MILESTONE PROGRAMME • Also Milestone should: • be natural; • represent important decisions; • be controllable, either quantitively or qualitatively; • be few in number (10 TO 20); • be at useful intervals(ie monthly); 4- Drafting the Milestone Plan
  • 28. NESTED PROGRAMMING • The primary objectives of the project are provided in the Level 1 Project Programme. • Below The Work Breakdown Structure (WBS) most projects are capable of being split into a member of Stages or Phases (Work Packages).
  • 29. NESTED PROGRAMMING • A milestoneplan may be produced for each of these phases. • for example at Level 1-Reported at 20 max controlled Milestones. • Or at Level-2- let us say 4 Stages – each Reported at 20 max controlled Milestones.
  • 30. NESTED PROGRAMMING • At Level 3 and below, the influence of detail activities can make it difficult to develop meaningful Milestone Programme. • At this level down on the WBS, it is normal to revert to activity programmes.
  • 31. NESTED PROGRAMMING • At the lowest activity and task levels, Milestones occur along the path of networked activities (CPM) and are shown as ‘Flagging’ up on the network or Gantt chart. • Some packages allow them to be fixed and generate ‘Supper Critical Paths’. (See Oxford Brookes University-Micro Planner).
  • 32. DEVELOPING THE MILESTONE PROGRAMME Conclusion • The Milestone methods is purely a means of monitoring and controlling progress towards the Projects Objectives at the highest level of WBS. • It is useful where there is insufficient detailed information to produce meaningful accurate lower level Activities based programmes.
  • 33. Define Goals Tchnological Communication s Cost Latest Process plant Latest Road Rail Package Latest Hygiene Finishes Latest Building Management System Latest Computer Process System Latest Robotics Negociation And Completion of Rdad/Rail link to EU To Cmply with Finacial and Strategic Plans Example of Level 1- Factory Project