2. LEAN CONSTRUCTION
In the past 50 years, manufacturing
industries have greatly improved their
competitiveness.
This has been achieved through the use of
lean methods such as:
Supply Chain Management
Just-In-Time techniques.
Also, for several years lean methods have
been applied to the construction industry,
3. LEAN CONSTRUCTION
Lean construction is a process used to
maximizes value and reduces waste.
Lean construction comes from Lean
production.
It captures these objectives through
the use of Supply Chain Management
(SCM) and Just-In-Time (JIT)
techniques,
Also, by sharing information between
all the parties involved in the
production process.
4. LEAN CONSTRUCTION
It is based on lean manufacturing,
of the Toyota Production system.
developed by Taichii Ohno in the
1950s.
Ohno learnt from mass production at
Ford Motor manufacturing facilities
in the U.S. and witnessed high level
of waste during production.
5. LEAN CONSTRUCTION
Ohno identified several
wastes in mass production
systems in car industry such
as:
1. overproducing
2. waiting time
3. transporting
6. LEAN CONSTRUCTION
also, in other areas such as:
1. processing methods;
2. unnecessary stock on hand;
3. unnecessary motion;
4. defective goods;
5. failure to meet customers’ needs;
6. high waste through out the
process.
7. LEAN CONSTRUCTION
The Toyota Production System was
based on the “Just –In – Time (JIT)
philosophy;
The main objectives were:
minimizing waste
continuous improvement from
inception to completion
with highly motivated work force
8. LEAN CONSTRUCTION
The outcome was:
reduced inventories
High productivity
better equipment utilization
of machinery
shorter lead times
9. LEAN CONSTRUCTION
Less errors
Highly motivated workforce
with higher morale
JIT is a pull system that responds
to actual customer demand.
products are “pulled from ” the JIT
system.
10. LEAN CONSTRUCTION
JIT only considers the resources
required to meet the customer’s
needs.
In the mid – 1970’s Toyota
reduced the time needed to
produce a car from fifteen days to
one day, by using JIT.
11. LEAN CONSTRUCTION
Applying Lean Thinking in construction
Using experienced design teams
The same design team working on the design
of the project from beginning to end.
Speed up the design process.
Use innovative approaches to speed up the
design process.
Innovative ideas in design and assembly.
The use of pre-fabricated building elements.
Manufactured off site and pre-assembled on
site.
12. LEAN CONSTRUCTION
Supporting sub-contractors in developing
tools for improving processes.
In order to keep up with Leanconstruction
It is important to follow the work of
Construction Lean Improvement
Programme (CLIP).
CLIP operates across the whole
construction supply chain, from raw
materials processors to clients.
13. LEAN CONSTRUCTION
Researchers believe that project cost
will increase up to ten percent because
of poor supply chain design.
Supply Chain Management (SCM)
analyzes the impact of design on the
construction process.
Through SCM, all parties are kept
aware of commitments, schedules, etc.
14. LEAN CONSTRUCTION
All the parties work for high quality
product with minimal lead-time,
including:
minimizing wastage;
eliminating delays and disruptions.
Ballard and Howell designed the
Last Planner System as one
method for applying lean
techniques to construction.
15. LEAN CONSTRUCTION
Womack and Jones (1996) suggested
that there are five key principles that
need to be monitored when lean
construction systems are applied in
construction. Those are:
Value-clarifying the customer’s needs;
the supply chain involvement in all
stages, from inception to completion;
By clarifying activities or products
that signify value.
16. LEAN CONSTRUCTION
Value stream: By mapping the
whole value stream
establishing cooperation between
all parties involved;
identifying and eliminating waste;
From taking such steps the
construction process can be
improved.
17. LEAN CONSTRUCTION
Flow:
Business flow includes project
information such as:
1. specifications
2. contracts
3. plans, etc.
Job site flow involves the activities and
the way they have to be carried out.
Supply flow refers to the materials
used in a project.
18. LEAN CONSTRUCTION
Pull:
The efforts of all participants
provides smooth pulls during the
construction process.
Perfection:
Use of best methods of work
instructions and best procedures.
Introduction of best quality
control methods.
19. Current practice V lean construction
CURRENT LEAN
Construction
management is either
activity or contract
centred
Coordination between
organizations or crews is
primarily controlled from
a central plan
that central plan
establishes sequence and
determines when an
activity starts/finish
in lean production, the
production is managed
in a manor that the
main objective is best
product at lowest cost
for customer
Project duration and
cost are considered in
“project-as-production
system” terms
project total cost and
duration are more
important than the cost
or duration of an
activity
20. Current practice V lean construction
CURRENT LEAN
costs, errors, and
learning occur while
work in progress
cost savings results
from productivity
improving
Often not achievable
resulting in cost, time
overrun
project duration is cut
short by increasing
manpower, machinery,
by adding additional
activities to reduce time
Coordination is
accomplished in
general by the central
schedule
the details of work
flow are managed
throughout the
organization by
people who are
project goals
orientated
Time, cost, quality,..
21. LEAN CONSTRUCTION
CURRENT LEAN
Additional cost
due to waste
which could have
been avoided
within the
activities,
Delays and
disruption which
could have been
avoided within
activities,
customers are
valued highly,
primary objectives
is the
work flow,
Movement of
information,
good
communication
amongst all,
Movement of
materials,
22. LEAN CONSTRUCTION
CURRENT LEAN
rework which
could have been
avoided,
all add to total
time of the
project,
disrupt in critical
path
Increases time
and cost,
Waste control,
Highly motivated
work force,
Removal of
hygiene factors
(de-motivating
factors),
23. LEAN CONSTRUCTION
Lean thinking forces attention on
how value is generated rather
than how any one activity is
managed.
An overall success.