Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999

Clause No. 8

Commencement, Delays and Suspension

Sub-Clause No. 8.7

Delay Damages






Summary
Delay damages shall be paid for every day which elapses between the relevant time for completion and the date stated
in the taking over certificate subjected to maximum liability as stated in the particular conditions.
Delay damages are due to slow rate of actual progress as compared to the ‘programme’ due to the reasons attributed to
the contractor’s default and leads to additional cost to the employer.
Extension of time creates a win-win situation, through which the employer is protected against the loss of delay
damages and the contractor becomes released from liability for delay damages.
It is not appropriate to agree to milestones in combination with delay damages. However if sections of works (which
are not milestones) have different importance to the employer different delay damages rates can be fixed.

(For the purpose of understanding Delay Damages following Sub-Clauses have been mentioned)
Sub Clause
8.1
8.2
8.3
8.4
8.6

Title
Commencement of Works
Time for Completion
Programme
Extension of Time for Completion
Rate of Progress

Sub-Clause No. 8.1

Commencement of Works

Content of the FIDIC Clause in Brief
Unless otherwise stated in the Contract Agreement:
(a) the Employer shall give the Contractor not less than 7 days' notice of the Commencement Date; and
(b) the Commencement Date shall be within 42 days after the date on which the Contract comes into full force and effect
under Sub-Clause 1.6 [Contract Agreement].
The Contractor shall commence the design and execution of the Works as soon as is reasonably practicable after the
Commencement Date, and shall then proceed with the Works with due expedition and without delay.

Sub-Clause No. 8.2

Time for Completion

Content of the FIDIC Clause in Brief
The Contractor shall complete the whole of the Works, and each Section (if any), within the Time for Completion for the
Works or Section (as the case may be), including:
(a) achieving the passing of the Tests on Completion, and
(b) completing all work which is stated in the Contract as being required for the Works or Section to be considered to be
completed for the purposes of taking over under Sub-Clause 10.1 [Taking Over of the Works and Sections].

Pg. 1/5 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999

The Time-Line of Time for Completion
Schematic (Only symbol
to be considered as time-line)
Time-line of Time for Completion
Programme

Tests on Completion

Taking over

Extension of Time for Completion (an aid for contractor to be released from liability of liquidated delay damages)
Liquidated Delay Damages (an aid for Employer to be protected from the loss of delay attributed to the contractor)

Sub-Clause No. 8.3

Programme

Content of the FIDIC Clause in Brief
The Contractor shall submit a time programme to the Employer within 28 days after the Commencement Date. The
Contractor shall also submit a revised programme whenever the previous programme is inconsistent with actual progress
or with the Contractor's obligations. Unless otherwise stated in the Contract, each programme shall include:
(a) the order in which the Contractor intends to carry out the Works, including the anticipated timing of each major stage
of the Works,
(b) the periods for reviews under Sub-Clause 5.2 [Contractor's Documents],
(c) the sequence and timing of inspections and tests specified in the Contract, and
(d) a supporting report which includes:
(i) a general description of the methods which the Contractor intends to adopt for the execution of each major stage of the
Works, and
(ii) the approximate number of each class of Contractor's Personnel and of each type of Contractor's Equipment for each
major stage.
In this event, or if the Employer gives notice to the Contractor that a programme fails (to the extent stated) to comply with
the Contract or to be consistent with actual progress and the Contractor's stated intentions, the Contractor shall submit a
revised programme to the Employer.
Schematic (Only symbol

to be considered as time-line)
Submission of
Time
Programme by
the Contractor
to the Employer
< 42 Days

Signing of the
Agreement

<28
Commencement
Date

< 7 Days
Employer’s
Notice to the
Contractor
of
Commencement
Date

Pg. 2/5 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999

Sub-Clause No. 8.4

Extension of Time for Completion

Content of the FIDIC Clause in Brief
The Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to an extension of the Time for
Completion if and to the extent that completion for the purposes of Sub-Clause 10.1 [Taking Over of the Works and
Sections] is or will be delayed by any of the following causes:
(a) a Variation (unless an adjustment to the Time for Completion has been agreed under Sub-Clause 13.3 [Variation
Procedure]),
(b) a cause of delay giving an entitlement to extension of time under a Sub-Clause of these Conditions, or
(c) any delay, impediment or prevention caused by or attributable to the Employer, the Employer's Personnel, or the
Employer's other contractors on the Site.
When determining each extension of time under, the Employer shall review previous determinations and may increase, but
shall not decrease, the total extension of time.

Sub-Clause No. 8.6

Rate of Progress

Content of the FIDIC Clause in Brief
If, at any time:
(a) actual progress is too slow to complete within the Time for Completion, and/or
(b) progress has fallen (or will fall) behind the current programme under Sub-Clause 8.3 [Programme], other than as a
result of a cause listed in Sub-Clause 8.4 [Extension of Time for Completion], then the Employer may instruct the
Contractor to submit, under Sub-Clause 8.3 [Programme], a revised programme and supporting report describing the
revised methods which the Contractor proposes to adopt in order to expedite progress and complete within the Time for
Completion.
Unless the Employer notifies otherwise, the Contractor shall adopt these revised methods, which may require increases in
the working hours and/or in the numbers of Contractor's Personnel and/or Goods, at the risk and cost of the Contractor. If
these revised methods cause the Employer to incur additional costs, the Contractor shall subject to Sub-Clause 2.5
[Employer's Claims] pay these costs to the Employer, in addition to delay damages (if any) under Sub-Clause 8.7.

Sub-Clause No. 8.7

Delay Damages

Content of the FIDIC Clause in Brief
If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion], the Contractor shall subject to Sub-Clause
2.5 [Employer's Claims] pay delay damages to the Employer for this default. These delay damages shall be the sum stated
in the Particular Conditions, which shall be paid for every day which shall elapse between the relevant Time for
Completion and the date stated in the Taking-Over Certificate. However, the total amount due under this Sub-Clause shall
not exceed the maximum amount of delay damages (if any) stated in the Particular Conditions.
These delay damages shall be the only damages due from the Contractor for such default, other than in the event of
termination under Sub-Clause 15.2 [Termination by Employer] prior to completion of the Works. These damages shall not
relieve the Contractor from his obligation to complete the Works, or from any other duties, obligations or responsibilities
which he may have under the Contract.

Pg. 3/5 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999

Schematic (Only symbol

Signing
of
Agreement

< 42
Days

to be considered as time-line)

Commencement
Date

Time for Completion

< 28 Days

Submission
of
Programme

Delay Damages

Taking Over

Delay Attributed to
the Contractor

Tests on
Completion

As per FIDIC, Delay Damages shall be paid for every day which elapse between the relevant Time for Completion and the date stated
in the Taking-Over Certificate.

Guidance for Delay Damages
Delay damages are also called liquidated damages or delay liquidated damages
Delay damages are applicable when pursuant to the clause 8.6 ‘Rate of Progress’ the contractor adopts revised methods,
unless notified as otherwise by the employer when the actual progress is too slow to complete within the time for
completion and/or the progress has fallen (or will fall) behind the current programme. If these revised methods cause the
employer to incur additional costs, the delay damages shall be effective.
The amount of this pre-defined delay damages must represent a reasonable pre-estimate of the employer’s probable loss.
The particular Conditions should specify the daily sum, for the works and for each section, expressed either as an amount
or as a percentage.
Amount of Delay Damages as stated in Particular Conditions
In subclause 8.7, the sum referred to the delay damages shall be 0.02% of the contract price as delay damages in respect
of the works, payable (per day) in the proportions of currencies in which the contract price is payable. For each section,
such daily sum shall be 0.02% of the final contract value of such section, payable (per day) in such currencies. The
maximum amount of delay damages shall be ten percent 10% of the contract price stated in the contract agreement.
Although the % of delay damages are specified in the guidance for particular conditions in FIDIC as mentioned above, it
is usually intended that the % delay damages to be calculated or estimated as the sum of:
 The anticipated average cost to the employer of the extended period of the Engineer’s supervision, plus
 The anticipated average benefit to the employer of the completed works, or an amount roughly equivalent to the
commercial cost of borrowing the accepted contract amount from a local bank.
Notes:
 Delay damages are limitation to liability for delay.
 Liability towards delay damages cease only after the taking over certificate is issued and not on passing test on
completion.
 Delay damages are generally excluded from the insurance policy cover since willful act or negligence will not be in
policy cover.
 Failure to comply with time for completion will lead to the entitlement of delay damages according to subclause 8
with exception of extension of time for completion.
 If and when the contractor is prevented from carrying out the works or if the employer causes delay to the progress
with effect to time for completion, the contractor is entitled to claim for extension of time and is relieved from the
liability of delay damages.
 Extension of time creates a win-win situation, through which the employer is protected against the loss of delay
damages and the contractor becomes released from liability for delay damages.
Pg. 4/5 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999




Delay damages do not fall under national legislation concerning penalties. By contrast they include a promise to pay a
certain amount of money for non compliance with a particular agreement only.
It is not appropriate to agree to milestones in combination with delay damages. FIDIC does not mention milestones
but sections. If sections have been determined within the particular conditions or in the appendix to tender, sectional
completion dates should be stated. If sections have different importance to the employer different delay damages rates
can be fixed. It can be seen that sections make the contract much more flexible and sometimes also more balanced.

Applied Clauses of the Delay Liquidated Damages for EPC Contracts (FIDIC or Mixed)
The delay liquidated damages and project delay liquidated damages payable pursuant to this clause represent an agreed
genuine pre-estimate of losses likely to be suffered by the employer in the event of delay to taking over of the works
beyond the time for completion and are not a penalty. The contractor shall not be entitled to withhold or set-off any
amounts due pursuant to this clause 8.7 for any reason whatsoever, including for the avoidance of doubt, where the
contractor wishes to dispute the quantum or validity of any such amounts.
Delay liquidated shall be 1% of the contract price per week subjected to maximum liability of 10% of the contract price.


Pg. 5/5 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC

Weitere ähnliche Inhalte

Andere mochten auch

FIDIC & Dispute Boards
FIDIC & Dispute BoardsFIDIC & Dispute Boards
FIDIC & Dispute BoardsFIDIC
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreementabdmuhaiminyunus
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractTom Joseph Mukasa
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanAdrias TAN
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 

Andere mochten auch (7)

FIDIC & Dispute Boards
FIDIC & Dispute BoardsFIDIC & Dispute Boards
FIDIC & Dispute Boards
 
Fidic conditions of subcontract agreement
Fidic conditions of subcontract agreementFidic conditions of subcontract agreement
Fidic conditions of subcontract agreement
 
The Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction ContractThe Case for Standard Forms of Construction Contract
The Case for Standard Forms of Construction Contract
 
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias TanFIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
FIDIC 2016 Day01-1450 Managing Claims Under FIDIC, PPT Adrias Tan
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
Fidic
FidicFidic
Fidic
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 

Mehr von Divyanshu Dayal

The Per Mile Costs of Operating Automobiles and Trucks
The Per Mile Costs of Operating Automobiles and TrucksThe Per Mile Costs of Operating Automobiles and Trucks
The Per Mile Costs of Operating Automobiles and TrucksDivyanshu Dayal
 
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Divyanshu Dayal
 
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Divyanshu Dayal
 
Development of Consulting Rate Structures and Contracts
Development of Consulting Rate Structures and ContractsDevelopment of Consulting Rate Structures and Contracts
Development of Consulting Rate Structures and ContractsDivyanshu Dayal
 
International Classification for Standards (Material Classification and Codif...
International Classification for Standards (Material Classification and Codif...International Classification for Standards (Material Classification and Codif...
International Classification for Standards (Material Classification and Codif...Divyanshu Dayal
 
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)Divyanshu Dayal
 
Coal Facts 2013 Demand Supply
Coal Facts 2013 Demand SupplyCoal Facts 2013 Demand Supply
Coal Facts 2013 Demand SupplyDivyanshu Dayal
 
Price Adjustment in Long Term Coal Contracts- MIT (1987)
Price Adjustment in Long Term Coal Contracts- MIT (1987)Price Adjustment in Long Term Coal Contracts- MIT (1987)
Price Adjustment in Long Term Coal Contracts- MIT (1987)Divyanshu Dayal
 
How to Export From India- An Introduction
How to Export From India- An IntroductionHow to Export From India- An Introduction
How to Export From India- An IntroductionDivyanshu Dayal
 
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Divyanshu Dayal
 
Purchasing Organization and Sourcing Strategy.
Purchasing Organization and Sourcing Strategy.Purchasing Organization and Sourcing Strategy.
Purchasing Organization and Sourcing Strategy.Divyanshu Dayal
 
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...Divyanshu Dayal
 
4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax4. Indian Taxation. Service Tax
4. Indian Taxation. Service TaxDivyanshu Dayal
 
3. Indian Taxation. Value Added Tax (VAT)
3. Indian Taxation. Value Added Tax (VAT)3. Indian Taxation. Value Added Tax (VAT)
3. Indian Taxation. Value Added Tax (VAT)Divyanshu Dayal
 

Mehr von Divyanshu Dayal (20)

incoterms-2010
incoterms-2010incoterms-2010
incoterms-2010
 
RESUME WITH A SOUL
RESUME WITH A SOULRESUME WITH A SOUL
RESUME WITH A SOUL
 
The Per Mile Costs of Operating Automobiles and Trucks
The Per Mile Costs of Operating Automobiles and TrucksThe Per Mile Costs of Operating Automobiles and Trucks
The Per Mile Costs of Operating Automobiles and Trucks
 
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
 
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
Technical Analysis Of The Financial Markets- A Comprehensive Guide To Trading...
 
Development of Consulting Rate Structures and Contracts
Development of Consulting Rate Structures and ContractsDevelopment of Consulting Rate Structures and Contracts
Development of Consulting Rate Structures and Contracts
 
Purchasing Management
Purchasing ManagementPurchasing Management
Purchasing Management
 
International Classification for Standards (Material Classification and Codif...
International Classification for Standards (Material Classification and Codif...International Classification for Standards (Material Classification and Codif...
International Classification for Standards (Material Classification and Codif...
 
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
Business Guide on Indonesia by Embassy of Indian in Jakarta (2007)
 
Coal Facts 2013 Demand Supply
Coal Facts 2013 Demand SupplyCoal Facts 2013 Demand Supply
Coal Facts 2013 Demand Supply
 
Mining Law in Asia
Mining Law in AsiaMining Law in Asia
Mining Law in Asia
 
Price Adjustment in Long Term Coal Contracts- MIT (1987)
Price Adjustment in Long Term Coal Contracts- MIT (1987)Price Adjustment in Long Term Coal Contracts- MIT (1987)
Price Adjustment in Long Term Coal Contracts- MIT (1987)
 
How to Export From India- An Introduction
How to Export From India- An IntroductionHow to Export From India- An Introduction
How to Export From India- An Introduction
 
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
Clause 14.9 Payment of Retention Money-Understanding Clauses in FIDIC ‘Condit...
 
Type of Contracts.
Type of Contracts.Type of Contracts.
Type of Contracts.
 
Purchasing Organization and Sourcing Strategy.
Purchasing Organization and Sourcing Strategy.Purchasing Organization and Sourcing Strategy.
Purchasing Organization and Sourcing Strategy.
 
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
Legal Regulatory and Contractual Policy Frame Work in Public Private Partners...
 
Resume
ResumeResume
Resume
 
4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax
 
3. Indian Taxation. Value Added Tax (VAT)
3. Indian Taxation. Value Added Tax (VAT)3. Indian Taxation. Value Added Tax (VAT)
3. Indian Taxation. Value Added Tax (VAT)
 

Kürzlich hochgeladen

Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfAdmir Softic
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756dollysharma2066
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...lizamodels9
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyEthan lee
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 

Kürzlich hochgeladen (20)

Dr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdfDr. Admir Softic_ presentation_Green Club_ENG.pdf
Dr. Admir Softic_ presentation_Green Club_ENG.pdf
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Majnu Ka Tilla, Delhi Contact Us 8377877756
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
Russian Call Girls In Gurgaon ❤️8448577510 ⊹Best Escorts Service In 24/7 Delh...
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case studyThe Coffee Bean & Tea Leaf(CBTL), Business strategy case study
The Coffee Bean & Tea Leaf(CBTL), Business strategy case study
 
How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 

Clause 8.7 Delay Damages-Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999.

  • 1. Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999 Clause No. 8 Commencement, Delays and Suspension Sub-Clause No. 8.7 Delay Damages     Summary Delay damages shall be paid for every day which elapses between the relevant time for completion and the date stated in the taking over certificate subjected to maximum liability as stated in the particular conditions. Delay damages are due to slow rate of actual progress as compared to the ‘programme’ due to the reasons attributed to the contractor’s default and leads to additional cost to the employer. Extension of time creates a win-win situation, through which the employer is protected against the loss of delay damages and the contractor becomes released from liability for delay damages. It is not appropriate to agree to milestones in combination with delay damages. However if sections of works (which are not milestones) have different importance to the employer different delay damages rates can be fixed. (For the purpose of understanding Delay Damages following Sub-Clauses have been mentioned) Sub Clause 8.1 8.2 8.3 8.4 8.6 Title Commencement of Works Time for Completion Programme Extension of Time for Completion Rate of Progress Sub-Clause No. 8.1 Commencement of Works Content of the FIDIC Clause in Brief Unless otherwise stated in the Contract Agreement: (a) the Employer shall give the Contractor not less than 7 days' notice of the Commencement Date; and (b) the Commencement Date shall be within 42 days after the date on which the Contract comes into full force and effect under Sub-Clause 1.6 [Contract Agreement]. The Contractor shall commence the design and execution of the Works as soon as is reasonably practicable after the Commencement Date, and shall then proceed with the Works with due expedition and without delay. Sub-Clause No. 8.2 Time for Completion Content of the FIDIC Clause in Brief The Contractor shall complete the whole of the Works, and each Section (if any), within the Time for Completion for the Works or Section (as the case may be), including: (a) achieving the passing of the Tests on Completion, and (b) completing all work which is stated in the Contract as being required for the Works or Section to be considered to be completed for the purposes of taking over under Sub-Clause 10.1 [Taking Over of the Works and Sections]. Pg. 1/5 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
  • 2. Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999 The Time-Line of Time for Completion Schematic (Only symbol to be considered as time-line) Time-line of Time for Completion Programme Tests on Completion Taking over Extension of Time for Completion (an aid for contractor to be released from liability of liquidated delay damages) Liquidated Delay Damages (an aid for Employer to be protected from the loss of delay attributed to the contractor) Sub-Clause No. 8.3 Programme Content of the FIDIC Clause in Brief The Contractor shall submit a time programme to the Employer within 28 days after the Commencement Date. The Contractor shall also submit a revised programme whenever the previous programme is inconsistent with actual progress or with the Contractor's obligations. Unless otherwise stated in the Contract, each programme shall include: (a) the order in which the Contractor intends to carry out the Works, including the anticipated timing of each major stage of the Works, (b) the periods for reviews under Sub-Clause 5.2 [Contractor's Documents], (c) the sequence and timing of inspections and tests specified in the Contract, and (d) a supporting report which includes: (i) a general description of the methods which the Contractor intends to adopt for the execution of each major stage of the Works, and (ii) the approximate number of each class of Contractor's Personnel and of each type of Contractor's Equipment for each major stage. In this event, or if the Employer gives notice to the Contractor that a programme fails (to the extent stated) to comply with the Contract or to be consistent with actual progress and the Contractor's stated intentions, the Contractor shall submit a revised programme to the Employer. Schematic (Only symbol to be considered as time-line) Submission of Time Programme by the Contractor to the Employer < 42 Days Signing of the Agreement <28 Commencement Date < 7 Days Employer’s Notice to the Contractor of Commencement Date Pg. 2/5 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
  • 3. Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999 Sub-Clause No. 8.4 Extension of Time for Completion Content of the FIDIC Clause in Brief The Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor's Claims] to an extension of the Time for Completion if and to the extent that completion for the purposes of Sub-Clause 10.1 [Taking Over of the Works and Sections] is or will be delayed by any of the following causes: (a) a Variation (unless an adjustment to the Time for Completion has been agreed under Sub-Clause 13.3 [Variation Procedure]), (b) a cause of delay giving an entitlement to extension of time under a Sub-Clause of these Conditions, or (c) any delay, impediment or prevention caused by or attributable to the Employer, the Employer's Personnel, or the Employer's other contractors on the Site. When determining each extension of time under, the Employer shall review previous determinations and may increase, but shall not decrease, the total extension of time. Sub-Clause No. 8.6 Rate of Progress Content of the FIDIC Clause in Brief If, at any time: (a) actual progress is too slow to complete within the Time for Completion, and/or (b) progress has fallen (or will fall) behind the current programme under Sub-Clause 8.3 [Programme], other than as a result of a cause listed in Sub-Clause 8.4 [Extension of Time for Completion], then the Employer may instruct the Contractor to submit, under Sub-Clause 8.3 [Programme], a revised programme and supporting report describing the revised methods which the Contractor proposes to adopt in order to expedite progress and complete within the Time for Completion. Unless the Employer notifies otherwise, the Contractor shall adopt these revised methods, which may require increases in the working hours and/or in the numbers of Contractor's Personnel and/or Goods, at the risk and cost of the Contractor. If these revised methods cause the Employer to incur additional costs, the Contractor shall subject to Sub-Clause 2.5 [Employer's Claims] pay these costs to the Employer, in addition to delay damages (if any) under Sub-Clause 8.7. Sub-Clause No. 8.7 Delay Damages Content of the FIDIC Clause in Brief If the Contractor fails to comply with Sub-Clause 8.2 [Time for Completion], the Contractor shall subject to Sub-Clause 2.5 [Employer's Claims] pay delay damages to the Employer for this default. These delay damages shall be the sum stated in the Particular Conditions, which shall be paid for every day which shall elapse between the relevant Time for Completion and the date stated in the Taking-Over Certificate. However, the total amount due under this Sub-Clause shall not exceed the maximum amount of delay damages (if any) stated in the Particular Conditions. These delay damages shall be the only damages due from the Contractor for such default, other than in the event of termination under Sub-Clause 15.2 [Termination by Employer] prior to completion of the Works. These damages shall not relieve the Contractor from his obligation to complete the Works, or from any other duties, obligations or responsibilities which he may have under the Contract. Pg. 3/5 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
  • 4. Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999 Schematic (Only symbol Signing of Agreement < 42 Days to be considered as time-line) Commencement Date Time for Completion < 28 Days Submission of Programme Delay Damages Taking Over Delay Attributed to the Contractor Tests on Completion As per FIDIC, Delay Damages shall be paid for every day which elapse between the relevant Time for Completion and the date stated in the Taking-Over Certificate. Guidance for Delay Damages Delay damages are also called liquidated damages or delay liquidated damages Delay damages are applicable when pursuant to the clause 8.6 ‘Rate of Progress’ the contractor adopts revised methods, unless notified as otherwise by the employer when the actual progress is too slow to complete within the time for completion and/or the progress has fallen (or will fall) behind the current programme. If these revised methods cause the employer to incur additional costs, the delay damages shall be effective. The amount of this pre-defined delay damages must represent a reasonable pre-estimate of the employer’s probable loss. The particular Conditions should specify the daily sum, for the works and for each section, expressed either as an amount or as a percentage. Amount of Delay Damages as stated in Particular Conditions In subclause 8.7, the sum referred to the delay damages shall be 0.02% of the contract price as delay damages in respect of the works, payable (per day) in the proportions of currencies in which the contract price is payable. For each section, such daily sum shall be 0.02% of the final contract value of such section, payable (per day) in such currencies. The maximum amount of delay damages shall be ten percent 10% of the contract price stated in the contract agreement. Although the % of delay damages are specified in the guidance for particular conditions in FIDIC as mentioned above, it is usually intended that the % delay damages to be calculated or estimated as the sum of:  The anticipated average cost to the employer of the extended period of the Engineer’s supervision, plus  The anticipated average benefit to the employer of the completed works, or an amount roughly equivalent to the commercial cost of borrowing the accepted contract amount from a local bank. Notes:  Delay damages are limitation to liability for delay.  Liability towards delay damages cease only after the taking over certificate is issued and not on passing test on completion.  Delay damages are generally excluded from the insurance policy cover since willful act or negligence will not be in policy cover.  Failure to comply with time for completion will lead to the entitlement of delay damages according to subclause 8 with exception of extension of time for completion.  If and when the contractor is prevented from carrying out the works or if the employer causes delay to the progress with effect to time for completion, the contractor is entitled to claim for extension of time and is relieved from the liability of delay damages.  Extension of time creates a win-win situation, through which the employer is protected against the loss of delay damages and the contractor becomes released from liability for delay damages. Pg. 4/5 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC
  • 5. Understanding Clauses in FIDIC ‘Conditions of Contract for EPC/ Turnkey Projects’ First Edition 1999   Delay damages do not fall under national legislation concerning penalties. By contrast they include a promise to pay a certain amount of money for non compliance with a particular agreement only. It is not appropriate to agree to milestones in combination with delay damages. FIDIC does not mention milestones but sections. If sections have been determined within the particular conditions or in the appendix to tender, sectional completion dates should be stated. If sections have different importance to the employer different delay damages rates can be fixed. It can be seen that sections make the contract much more flexible and sometimes also more balanced. Applied Clauses of the Delay Liquidated Damages for EPC Contracts (FIDIC or Mixed) The delay liquidated damages and project delay liquidated damages payable pursuant to this clause represent an agreed genuine pre-estimate of losses likely to be suffered by the employer in the event of delay to taking over of the works beyond the time for completion and are not a penalty. The contractor shall not be entitled to withhold or set-off any amounts due pursuant to this clause 8.7 for any reason whatsoever, including for the avoidance of doubt, where the contractor wishes to dispute the quantum or validity of any such amounts. Delay liquidated shall be 1% of the contract price per week subjected to maximum liability of 10% of the contract price.  Pg. 5/5 Compiled by Divyanshu Dayal. dayal1005@gmail.com Portfolio-FIDIC