Pharmacy to Kennedy - November meeting
1. METROLINX LAND ACKNOWLEDGMENT
1
Let us take a moment to acknowledge that we are on the traditional territory of Indigenous Peoples
including the Anishnabeg, the Haudenosaunee and the Wendat peoples.
We are all Treaty people. Many of us have come here as settlers and immigrants … in this generation
or generations past.
Metrolinx declares its commitment to building meaningful relationships with Indigenous Peoples.
We acknowledge the historic and continued impacts of colonization and the need to work towards
meaningful reconciliation with the original caretakers of this land.
We acknowledge that Metrolinx operates on lands covered by 20 Treaties, and that we have a
responsibility to recognize and value the rights of Indigenous Nations and Peoples and conduct
business in a matter that is built on the foundation of trust, respect and collaboration.
2. November 30, 2021
Eglinton Crosstown LRT
Pharmacy to Kennedy Station
Construction Liaison Committee
Meeting
4. CONSTRUCTION ACTIVITIES
4
Location Activity Approx. Date & Duration
Brentcliffe – Kennedy
• Vehicle Testing
• Landscaping along Eglinton
• Ongoing through December 2021
• Fall 2021
Don Mills – Rosemount
• Eglinton Square Intersection
• Birchmount Rd – Rosemount Dr
Road Restoration Completed November 2021
Birchmount SE Corner Sidewalk restoration Completed October 2021
Massey Creek Backfill and Landscaping Completed November 2021
• O’Connor Stop (Victoria Park Ave)
• Pharmacy Stop
• Hakimi Lebovic Stop
• Golden Mile Stop (Warden Ave)
• Birchmount Stop
• Ionview Stop
• Platform ramps
• Wayfinding tiles installation
• Architectural finishes / details
• Electrical finishes
• April 2022
5. EAST TESTING & COMMISSIONING
5
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east end
of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and Kennedy
Road through December 2021.
• Dynamic Testing began August 24, 2021, and will
last through Fall 2021.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
6. FINAL ROAD RESTORATION
BRENTCLIFFE – KENNEDY
6
• Final Road Restoration works began in August 2021 and will last through Fall 2021. Works will
resume in 2022
• The approximate timeline for road restoration of the At-Grade is:
o August: Aga Khan – Wynford
o September: Swift – VP; Eglinton Square - Warden
o October: Warden – Ionview; Don Mills – DVP ; Victoria Park Intersection
o November: Wynford – Swift
o November: Eglinton Square, Birchmount – Rosemount
o 2022: Ionview - Kennedy
o 2022: Leslie – Aga Khan
• More specific details regarding the dates and locations of road restoration works will be
communicated to the public as they become available
10. KENNEDY STATION UPDATE
10
Location Activity Approx. Date & Duration
Brentcliffe – Kennedy Vehicle Testing Ongoing through December 2021
Kennedy Station Main Entrance
• Bicycle room glazing
• Parking lot paving
• Electrical finishes for permanent power –
TPSS, ACER room and electrical equipment
• Conduit installation, plumbing and sheet metal
works, tiling, masonry works
• Elevator & escalator installation
• Completed November 2021
• Base layer completed November 2021
• Completed November 2021
• Ongoing through 2021
• Ongoing through Fall 2021
Kennedy Station Box
• Floor tiling
• Glazing
• Completed November 2021
• Fall 2021
Kennedy Station GO Entrance and
Platform
• Retaining wall construction
• Structural steel at GO east platform
• Ongoing through Fall 2021
• Ongoing through December 2021
Kennedy Station – East of GO
• Masonry works
• Electrical finishes for permanent power –
TPSS, ACER room and electrical equipment
• Ongoing through December 2021
• Ongoing through 2021
• South Service Road
• Transway Crescent
• Curbs restoration
• Road Restoration
• Completed November 2021
• December 4, 2021 for approx. two
months
Kennedy Intersection - NE and SE
corners
Curbs and sidewalk restoration Ongoing through December 2021
11. EAST TESTING & COMMISSIONING
11
• On May 25, 26, 27, 31 and June 1 and 2, 6 light
rail vehicles (LRVs) were delivered to the east end
of the alignment.
• Testing and commissioning activities will be
conducted between Brentcliffe Road and Kennedy
Road through December 2021.
• Dynamic Testing began August 24, 2021, and will
last through Fall 2021.
• The LRVs will run mainly on the surface along a
track in the center of Eglinton Avenue.
14. TRANSWAY CRESCENT ROAD RESTORATION
14
December 4, 2021 for approx. two months
• A portion of Transway Crescent
between the South Service Road and
the Kennedy Station Pick-up/Drop-off
Loop will be closed to all traffic.
• Use of the North Service Road will be
reinstated for TTC.
• TTC bus movements will revert to
right turns only between Eglinton
Avenue East and the North and
South Service Roads.
• Use of the Kennedy Station
Passenger Pick-up / Drop-off Loop
will not be impacted.
15. GO WEST PLATFORM RELOCATION AND PEDESTRIAN DETOUR
15
• As part of GO Transit improvements at
Kennedy GO Station, crews at Kennedy
Station have temporarily relocated the west
GO Transit platform
• Pedestrians will be rerouted through the
Kennedy TTC Station
• This configuration will remain in place until
Spring 2022
August 17, 2020 till approx. Spring 2022