SlideShare ist ein Scribd-Unternehmen logo
1 von 21
Downloaden Sie, um offline zu lesen
22
3
Extended Construction Hours Continue
• Starting November 11, 2019, crews will work extended hours to accelerate construction
(4:30 a.m. – 11:00 p.m.). Construction activities may include, guideway construction, road
widening, retaining wall construction, hydro utility installation and bridge rehabilitation.
• The period between 4:30 a.m. – 7:00 a.m. will be primarily used to perform less noisy work,
such as site and traffic staging, preparatory works, excavation, concrete pours, deliveries and
hauling
What to Expect
• Daily temporary lane closures along Eglinton Ave E and cross streets between the West Don
River Bridge and Victoria Park Ave will be in effect to facilitate construction and deliveries
• Short-term pedestrian rerouting as well as temporary sidewalk and crosswalk closures may
be required to safely facilitate construction
• Noise from construction activities and equipment, such as removal of asphalt, excavation,
trucks and generators can be expected
• Site lighting can be expected
4
Brentcliffe Portal to Leslie Street
December 19 through to Mid-June 2020
• The traffic configuration will
accommodate:
• Guideway construction on the
West Don River Bridge and
portal.
• Wet utility relocations, road
widening, sidewalks and curb
works on the south side of
Eglinton Ave East between
Brentcliffe Road and the east
portal.
• The pedestrian sidewalk will be
available on the south side of
Eglinton Avenue East only.
5
Brentcliffe Portal to Leslie Street
June 2020 for approximately one month
• The traffic configuration will
accommodate road works in the
centre of Eglinton Avenue East
between Brentcliffe Road and the
east portal.
• Construction activities
include:
• Excavation
• Concrete and asphalt
removal
• Backfill
• Compaction
• Paving
• The pedestrian sidewalk will be available on the south side of
Eglington Avenue East only.
6
Retaining Wall Construction
North Side of Eglinton, East of Brentcliffe Road
• This retaining wall is required
to hold and stabilize the
embankment created from the
newly widened road.
• Construction is expected to
begin late May 2020 for a
period of 4 months.
• Construction activities will
include:
• Excavation: Excavators,
dump trucks and loaders
• Hydrovacing
• Backfill and compaction:
Loader and vibratory
roller/compactor
• Concrete works: concrete
trucks and pumps
• Installation of concrete
blocks with mobile crane
7
Sunnybrook Park Stop (Leslie Street)
Ongoing Activities
• Road widening continues on the south side of Eglinton between Brentcliffe Road and the
east portal.
• Construction of Multi Use Path is underway on the north side of the West Don River Bridge.
• Guideway construction will continue east and west of the Leslie Street intersection.
• Guideway construction and trackwork is advancing between the Leslie St. intersection to
Celestica Bridge.
CONCRETE WORKS FOR
PEDESTRIAN STAIRCASE AT
LESLIE STREET
NORTH SIDE WEST DON
RIVER BRIDGE
GUIDEWAY WEST OF
LESLIE STREET
8
9
Science Centre Station Traffic
Configuration Decking Removal
Current through to late June 2020
• Science Centre Station has advanced to a
state to allow the temporary traffic deck to
be removed.
• The removal will take place in two stages,
with the second stage beginning early May
2020.
• The road will be restored to an improved
surface.
• North south traffic will be reduced to two
lanes and aligned to the west side of Don
Mills Road.
• Northbound, southbound and eastbound
left turns will be restricted.
Bus Detours:
• Route 34C diverting to Ferrand and
Rochefort.
10
Science Centre Station Traffic
Configuration Gervais Drive
Current through to late 2020
• Traffic on Gervais Road at
Eglinton Avenue East has
been realigned to
accommodate upcoming civil
works at the east end of the
bus terminal.
• Southbound traffic at the foot
of Gervais Drive will be
rerouted east of original
ramp.
• The south sidewalk will be
shifted to Ferrand Drive east
of Gervais Drive and will
reconnect with existing
sidewalk on Eglinton Avenue
East at the west Don Valley
Parkway ramps.
11
Science Centre Station Construction
Activities
Area Current Activities
Station Box
• Installation of Mechanical plumbing and HVAC duct is ongoing
• First elevator installation is ongoing
• Masonry works, drywall installation and rough ceiling and stud
installations are in progress
• Installation of electrical equipment continues
• Backfill and decking removal continues
• Precast platform edge installation is ongoing
Main Entrance
• Wall tiling and rough ceiling works are in progress
• Louver installation is ongoing
Pedestrian
Tunnel/Bus
Terminal
• Wall tiling and civil works have started at the pedestrian tunnel
• Steel decking is being installed at the bus terminal
• Glazing continues at the bus terminal
• Masonry and civil works are in progress at the bus terminal
Portals
• Waterproofing and backfilling is ongoing at the east portal
• Installation of lighting fixtures is ongoing at the west and east portals
12
Science Centre Station Progress
Photos
GLAZING AT THE BUS TERMINALEAST PORTAL: BACKFILL AND
WATERPROOFING
13
14
Section 2 At-Grade Ongoing
Construction Activities
Area Activities Date
Wynford Bridge
• Construction of plinths Late May 2020
Wynford Stop • Stop construction Ongoing
East Don River Bridge • Construction of plinths Ongoing to mid-May 2020
Sloane Stop
• Concrete Works May 4 – 8, 2020
Wilson Brook Culvert
• Concrete works
• Creek realignment
Ongoing
Ongoing
East Don River Bridge to
Wynford Drive
• Road widening on the north
side
Late May 2020
Bermondsey Road to
Victoria Park Avenue
• Guideway construction
• Concrete works
Ongoing
May 4-8, 2020
15
Aga Khan Park Stop Traffic
Configuration
Current through 2020
16
Wynford Stop (Wynford Drive)
Current through 2020
17
Credit Union and Swift Drive Traffic
Configuration
Traffic movements reflect the permanent intersection configuration. The westbound
left turn movement will be permanently prohibited. Guideway construction will
continue east and west of the intersection.
Permanent Configuration
18
Sloane Stop Traffic Configuration
Mid December 2019 through to late spring 2020
• Guideway construction continues east and west of the Sloane/Bermondsey intersection.
o Concrete barriers may be temporarily removed for construction vehicles entering
and exiting the guideway work zone.
o Temporary lane closures may be required.
o Construction at the Wilson Brook Culvert continues on the north side of Eglinton
Avenue East.
19
Jonesville Crescent to Victoria Park Avenue
Traffic Configuration
April 27, 2020 for three (3) weeks
• Closure of the eastbound curb
lane on Eglinton Ave E between
Cranborne Ave and Victoria Park
Ave.
• Sidewalk and curb restoration on
the south side of Eglinton
Avenue East between Cranborne
Ave and Victoria Park Ave
• Excavators, bobcats, dump
trucks, compactors, hand tools
and concrete pumps and trucks
will be utilized.
20
Progress Photos
WEST DON RIVER BRIDGE
NORTH SIDE
WYNFORD STOP
PLINTH CONCRETE POUR AT
EAST DON RIVER BRIDGE
21
416-782-8118 or 416-482-7411
24 hours/7days a week
www.thecrosstown.ca
crosstown@metrolinx.com
facebook.com/thecrosstown
twitter.com/crosstownTO
instagram.com/eglinton_crosstown
Crosstown West Office
1848 Eglinton Ave W (at Dufferin)
Crosstown East Office
660 Eglinton Ave E (at Bayview)
Stay in Touch

Weitere ähnliche Inhalte

Was ist angesagt?

Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Crosstown TO
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Crosstown TO
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Crosstown TO
 

Was ist angesagt? (20)

CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House Deck
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
Eglinton Crosstown LRT Project Virtual Open House - East - Science Centre to ...
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021
 
Eastern Works Open House - October 24, 2019
Eastern Works Open House  - October 24, 2019Eastern Works Open House  - October 24, 2019
Eastern Works Open House - October 24, 2019
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)Cedarvale & Forest Hill Construction Update (September 29, 2021)
Cedarvale & Forest Hill Construction Update (September 29, 2021)
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
 
Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021Fairbank-Oakwood Construction Update - September 2021
Fairbank-Oakwood Construction Update - September 2021
 

Ähnlich wie Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May 2020

CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
Crosstown TO
 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018
Crosstown TO
 
Virtual Open House: Eastern Works
Virtual Open House: Eastern WorksVirtual Open House: Eastern Works
Virtual Open House: Eastern Works
Crosstown TO
 
Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018
Crosstown TO
 

Ähnlich wie Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May 2020 (20)

Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
 
Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020Avenue & Chaplin CLC - Construction Update: September 9, 2020
Avenue & Chaplin CLC - Construction Update: September 9, 2020
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 Slides
 
West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014West Open House - Progress Update Sept 2014
West Open House - Progress Update Sept 2014
 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018
 
Central West Open House
Central West Open HouseCentral West Open House
Central West Open House
 
Leaside - Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside - Laird Construction Liaison Committee (CLC) Meeting PresentationLeaside - Laird Construction Liaison Committee (CLC) Meeting Presentation
Leaside - Laird Construction Liaison Committee (CLC) Meeting Presentation
 
Virtual Open House: Eastern Works
Virtual Open House: Eastern WorksVirtual Open House: Eastern Works
Virtual Open House: Eastern Works
 
Western works final
Western works final Western works final
Western works final
 
Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
 

Mehr von Crosstown TO

Mehr von Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Kürzlich hochgeladen

Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Chandigarh Call girls 9053900678 Call girls in Chandigarh
 
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Kürzlich hochgeladen (20)

Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
Russian🍌Dazzling Hottie Get☎️ 9053900678 ☎️call girl In Chandigarh By Chandig...
 
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'IsraëlAntisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
Antisemitism Awareness Act: pénaliser la critique de l'Etat d'Israël
 
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
Call Girls in Chandni Chowk (delhi) call me [9953056974] escort service 24X7
 
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...Booking open Available Pune Call Girls Shukrawar Peth  6297143586 Call Hot In...
Booking open Available Pune Call Girls Shukrawar Peth 6297143586 Call Hot In...
 
Postal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptxPostal Ballots-For home voting step by step process 2024.pptx
Postal Ballots-For home voting step by step process 2024.pptx
 
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
WORLD DEVELOPMENT REPORT 2024 - Economic Growth in Middle-Income Countries.
 
2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar2024 Zoom Reinstein Legacy Asbestos Webinar
2024 Zoom Reinstein Legacy Asbestos Webinar
 
Scaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP processScaling up coastal adaptation in Maldives through the NAP process
Scaling up coastal adaptation in Maldives through the NAP process
 
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
The Most Attractive Pune Call Girls Handewadi Road 8250192130 Will You Miss T...
 
Election 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdfElection 2024 Presiding Duty Keypoints_01.pdf
Election 2024 Presiding Duty Keypoints_01.pdf
 
Expressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptxExpressive clarity oral presentation.pptx
Expressive clarity oral presentation.pptx
 
World Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - PosterWorld Press Freedom Day 2024; May 3rd - Poster
World Press Freedom Day 2024; May 3rd - Poster
 
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Chakan Call Me 7737669865 Budget Friendly No Advance Booking
 
The NAP process & South-South peer learning
The NAP process & South-South peer learningThe NAP process & South-South peer learning
The NAP process & South-South peer learning
 
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance BookingCall Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
Call Girls Nanded City Call Me 7737669865 Budget Friendly No Advance Booking
 
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
Just Call Vip call girls Wardha Escorts ☎️8617370543 Starting From 5K to 25K ...
 
The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)The U.S. Budget and Economic Outlook (Presentation)
The U.S. Budget and Economic Outlook (Presentation)
 
Government e Marketplace GeM Presentation
Government e Marketplace GeM PresentationGovernment e Marketplace GeM Presentation
Government e Marketplace GeM Presentation
 
2024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 302024: The FAR, Federal Acquisition Regulations, Part 30
2024: The FAR, Federal Acquisition Regulations, Part 30
 
Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)Tuvalu Coastal Adaptation Project (TCAP)
Tuvalu Coastal Adaptation Project (TCAP)
 

Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May 2020

  • 1.
  • 2. 22
  • 3. 3 Extended Construction Hours Continue • Starting November 11, 2019, crews will work extended hours to accelerate construction (4:30 a.m. – 11:00 p.m.). Construction activities may include, guideway construction, road widening, retaining wall construction, hydro utility installation and bridge rehabilitation. • The period between 4:30 a.m. – 7:00 a.m. will be primarily used to perform less noisy work, such as site and traffic staging, preparatory works, excavation, concrete pours, deliveries and hauling What to Expect • Daily temporary lane closures along Eglinton Ave E and cross streets between the West Don River Bridge and Victoria Park Ave will be in effect to facilitate construction and deliveries • Short-term pedestrian rerouting as well as temporary sidewalk and crosswalk closures may be required to safely facilitate construction • Noise from construction activities and equipment, such as removal of asphalt, excavation, trucks and generators can be expected • Site lighting can be expected
  • 4. 4 Brentcliffe Portal to Leslie Street December 19 through to Mid-June 2020 • The traffic configuration will accommodate: • Guideway construction on the West Don River Bridge and portal. • Wet utility relocations, road widening, sidewalks and curb works on the south side of Eglinton Ave East between Brentcliffe Road and the east portal. • The pedestrian sidewalk will be available on the south side of Eglinton Avenue East only.
  • 5. 5 Brentcliffe Portal to Leslie Street June 2020 for approximately one month • The traffic configuration will accommodate road works in the centre of Eglinton Avenue East between Brentcliffe Road and the east portal. • Construction activities include: • Excavation • Concrete and asphalt removal • Backfill • Compaction • Paving • The pedestrian sidewalk will be available on the south side of Eglington Avenue East only.
  • 6. 6 Retaining Wall Construction North Side of Eglinton, East of Brentcliffe Road • This retaining wall is required to hold and stabilize the embankment created from the newly widened road. • Construction is expected to begin late May 2020 for a period of 4 months. • Construction activities will include: • Excavation: Excavators, dump trucks and loaders • Hydrovacing • Backfill and compaction: Loader and vibratory roller/compactor • Concrete works: concrete trucks and pumps • Installation of concrete blocks with mobile crane
  • 7. 7 Sunnybrook Park Stop (Leslie Street) Ongoing Activities • Road widening continues on the south side of Eglinton between Brentcliffe Road and the east portal. • Construction of Multi Use Path is underway on the north side of the West Don River Bridge. • Guideway construction will continue east and west of the Leslie Street intersection. • Guideway construction and trackwork is advancing between the Leslie St. intersection to Celestica Bridge. CONCRETE WORKS FOR PEDESTRIAN STAIRCASE AT LESLIE STREET NORTH SIDE WEST DON RIVER BRIDGE GUIDEWAY WEST OF LESLIE STREET
  • 8. 8
  • 9. 9 Science Centre Station Traffic Configuration Decking Removal Current through to late June 2020 • Science Centre Station has advanced to a state to allow the temporary traffic deck to be removed. • The removal will take place in two stages, with the second stage beginning early May 2020. • The road will be restored to an improved surface. • North south traffic will be reduced to two lanes and aligned to the west side of Don Mills Road. • Northbound, southbound and eastbound left turns will be restricted. Bus Detours: • Route 34C diverting to Ferrand and Rochefort.
  • 10. 10 Science Centre Station Traffic Configuration Gervais Drive Current through to late 2020 • Traffic on Gervais Road at Eglinton Avenue East has been realigned to accommodate upcoming civil works at the east end of the bus terminal. • Southbound traffic at the foot of Gervais Drive will be rerouted east of original ramp. • The south sidewalk will be shifted to Ferrand Drive east of Gervais Drive and will reconnect with existing sidewalk on Eglinton Avenue East at the west Don Valley Parkway ramps.
  • 11. 11 Science Centre Station Construction Activities Area Current Activities Station Box • Installation of Mechanical plumbing and HVAC duct is ongoing • First elevator installation is ongoing • Masonry works, drywall installation and rough ceiling and stud installations are in progress • Installation of electrical equipment continues • Backfill and decking removal continues • Precast platform edge installation is ongoing Main Entrance • Wall tiling and rough ceiling works are in progress • Louver installation is ongoing Pedestrian Tunnel/Bus Terminal • Wall tiling and civil works have started at the pedestrian tunnel • Steel decking is being installed at the bus terminal • Glazing continues at the bus terminal • Masonry and civil works are in progress at the bus terminal Portals • Waterproofing and backfilling is ongoing at the east portal • Installation of lighting fixtures is ongoing at the west and east portals
  • 12. 12 Science Centre Station Progress Photos GLAZING AT THE BUS TERMINALEAST PORTAL: BACKFILL AND WATERPROOFING
  • 13. 13
  • 14. 14 Section 2 At-Grade Ongoing Construction Activities Area Activities Date Wynford Bridge • Construction of plinths Late May 2020 Wynford Stop • Stop construction Ongoing East Don River Bridge • Construction of plinths Ongoing to mid-May 2020 Sloane Stop • Concrete Works May 4 – 8, 2020 Wilson Brook Culvert • Concrete works • Creek realignment Ongoing Ongoing East Don River Bridge to Wynford Drive • Road widening on the north side Late May 2020 Bermondsey Road to Victoria Park Avenue • Guideway construction • Concrete works Ongoing May 4-8, 2020
  • 15. 15 Aga Khan Park Stop Traffic Configuration Current through 2020
  • 16. 16 Wynford Stop (Wynford Drive) Current through 2020
  • 17. 17 Credit Union and Swift Drive Traffic Configuration Traffic movements reflect the permanent intersection configuration. The westbound left turn movement will be permanently prohibited. Guideway construction will continue east and west of the intersection. Permanent Configuration
  • 18. 18 Sloane Stop Traffic Configuration Mid December 2019 through to late spring 2020 • Guideway construction continues east and west of the Sloane/Bermondsey intersection. o Concrete barriers may be temporarily removed for construction vehicles entering and exiting the guideway work zone. o Temporary lane closures may be required. o Construction at the Wilson Brook Culvert continues on the north side of Eglinton Avenue East.
  • 19. 19 Jonesville Crescent to Victoria Park Avenue Traffic Configuration April 27, 2020 for three (3) weeks • Closure of the eastbound curb lane on Eglinton Ave E between Cranborne Ave and Victoria Park Ave. • Sidewalk and curb restoration on the south side of Eglinton Avenue East between Cranborne Ave and Victoria Park Ave • Excavators, bobcats, dump trucks, compactors, hand tools and concrete pumps and trucks will be utilized.
  • 20. 20 Progress Photos WEST DON RIVER BRIDGE NORTH SIDE WYNFORD STOP PLINTH CONCRETE POUR AT EAST DON RIVER BRIDGE
  • 21. 21 416-782-8118 or 416-482-7411 24 hours/7days a week www.thecrosstown.ca crosstown@metrolinx.com facebook.com/thecrosstown twitter.com/crosstownTO instagram.com/eglinton_crosstown Crosstown West Office 1848 Eglinton Ave W (at Dufferin) Crosstown East Office 660 Eglinton Ave E (at Bayview) Stay in Touch