SlideShare ist ein Scribd-Unternehmen logo
1 von 56
Critical Power: Generators and
Generator System Design
Sponsored by:
Today’s Webcast Sponsor:
Learning Objectives:
1.The audience will understand the applicable code requirements
including NFPA 70: National Electrical Code and NFPA 110:
Standard for Emergency and Standby Power Systems
2.Attendees will learn the criteria for selecting the appropriate
generator or generators for the building type and/or application
3.Viewers will understand the criteria for designing the generator
system, and know the differences between prime rated versus
standby rated engines (U.S. EPA standards)
4.Viewers will learn the criteria for commissioning generators and
the electrical systems they support.
Robert R. Jones Jr., PE, LEED AP,
JBA Consulting Engineers,
Las Vegas, Nev.
James Ferris, PE,
TLC Engineering for Architecture,
Orlando, Fla.
Moderator: Jack Smith,
Consulting-Specifying Engineer and Pure Power,
CFE Media, LLC
Presenters:
Critical Power: Generators
and Generator System Design
Robert R. Jones Jr., PE, LEED, AP
JBA Consulting Engineers,
Las Vegas, Nev.
James Ferris, PE,
TLC Engineering for Architecture,
Orlando, Fla.
Codes & Standards
• IBC
– Chapter 27: Electrical
• NFPA 110: Emergency & Standby Power
Systems
• NFPA 101: Life Safety Code
• NFPA 70: National Electrical Code
– Article 445: Generators
– Article 700, 701, & 702: Systems
IBC – 2012 Edition
• Chapter 27 addresses electrical
components, equipment, and systems
• 2702.1 - Emergency and Standby
Systems shall be installed per NFPA 110
• 2702.2 – Emergency and Standby
Systems shall be installed where required
NFPA 110 – 2013 Edition
• Definitions (NFPA 110 Chapter 3)
– Emergency Power Supply (EPS): “The source of electrical
power of the required capacity and quality for an
emergency power supply system (EPSS).”
– Emergency Power Supply System (EPSS): “A complete
functioning EPS system coupled to a system of
conductors, disconnecting means and overcurrent
protective devices, transfer switches and all control,
supervisory and support devices up to and including the
load terminals of the transfer equipment needed for the
system to operate as a safe and reliable source of electric
power.”
LOAD TERMINALS
EPS
EPSS
NFPA 110 – 2013 Edition
• Chapter 4: EPSS Classification
– Class: Minimum time to operate without
refueling/recharging.
– Type: Maximum time to re-energize loads.
– Level: Installation, performance, and
maintenance criteria.
NFPA 110 – 2013 Edition
• Class
– Defined in hours per applicable code, application
and AHJ.
– Battery System
• NEC Article 700.12(A): 1.5-hour minimum, Class 1.5.
– Generator System
• NEC Article 700.12(B)(2): 2-hour minimum, Class 2.
• NFPA 20 Chapter 9.6.2.3: 8-hour minimum, Class 8.
• AIA Guidelines for Design and Construction of
Healthcare Facilities (Joint Commission requirement):
24 hours minimum, Class 24.
NFPA 110 – 2013 Edition
• Type
– Defined in seconds per applicable code,
application and AHJ.
– NEC Article 700.12: 10 seconds maximum,
Type 10.
– NFPA 20 Chapter 9.6.2.1: 10 seconds
maximum, Type 10.
– NEC Article 701.12: 60 seconds maximum,
Type 60.
NFPA 110 – 2013 Edition
• Level 1
– Required where EPSS failure “could result in loss of
human life or serious injuries.”
– NEC Article 700: Emergency System.
– NEC Article 701: Legally Required Standby (NFPA
101 7.14.7.1)
– NEC Article 517: Chapter 3 Essential Electrical
System.
• Level 2
– Required where EPSS failure “is less critical to
human life and safety.”
– NEC Article 701: Legally Required Standby.
NFPA 101 – 2012 Edition
• Type 10, Class 1.5, Level 1 for emergency lighting
(7.9.2.2)
• Type 60, Class 2, Level 1 for occupant evacuation
elevators (7.14.7.1)
• Type 60, Class 1, Level 1 for high-rise standby power
(legally required)
– Electric Fire Pump
– Jockey Pump
– Air Compressor for dry-pipe/pre-action fire suppression
system
– Emergency Command Center
– At least one elevator serving all floors
– Mechanical Smoke Control
NEC (NFPA 70) – 2011 Edition
• Article 445: Generators
– The ampacity of conductors from each
generator to the first overcurrent device must
be at least 115% of the nameplate current
rating (NEC 445.13)
– One or more disconnects with means of
locking in the open position are required
(NEC 445.18)
NEC (NFPA 70) – 2011 Edition
• Article 700: Emergency Systems
– EPS capacity shall be capable of supplying all emergency system loads simultaneously (NEC
700.4(A))
– EPS may serve loads other than emergency if capacity and rating can support all connected loads
simultaneously or transfer equipment incorporates selective load pickup and load shedding.
– Requires automatic transfer switches that supply only emergency loads (NEC 700.12(A) &
700.12(D))
– Wiring shall be contained in separate raceways, enclosures, etc. from all other systems. Separate
vertical switchboard section required when emergency source serves multiple systems (NEC
700.10(B))
• Article 701: Legally Required Standby Systems
– EPS capacity shall be capable of supplying all legally required standby loads intended to operate
simultaneously (NEC 701.4)
– Requires automatic transfer switches (NEC 701.12(A)
– Transfer switches require load shedding capability if generator capacity is not sized to supply all
connected loads at once (NEC 701.4)
• Article 702: Optional Standby Systems
– Permanent installations require manual or automatic transfer switches (NEC 702.5)
– Transfer switches require load shedding capability if generator capacity is not sized to supply all
connected loads at once (NEC 702.4(B)(2))
TO GENSET CONTROL PANEL FOR
SELECTIVE LOAD PICKUP AND SHEDDING
How Loads Are Classified
• Requirements for loads classified as emergency and legally required
standby are generally defined by the AHJ and adopted codes.
• IBC 2702.2 references other IBC sections for emergency and legally
required standby loads. Common applications below.
– Emergency Loads
• Voice/Alarm Communications Systems in Group A Occupancies and Covered and Open Mall
Buildings (IBC 907.5.2.2.4 & 402.7.3)
• Exit Signs and Means of Egress Illumination (IBC 1011.6.3 & 1006.3)
• High-Rise Buildings (IBC 403.4.9)
– Elevator Car Lighting
– Voice/Alarm Communications Systems
– Automatic Fire Detection Systems
– Fire Alarm Systems
– Electrically powered fire pumps
– Legally Required Standby Loads
• Smoke Control Systems (IBC 909.11)
• Accessible means of egress elevators (IBC 1007.4)
• High-Rise Buildings (IBC 403.4.8)
– Power and Lighting for the Fire Command Center
– Ventilation and automatic Fire detection equipment for smoke proof enclosures.
– Elevators
Local AHJ Considerations
• Some AHJs amend codes and standards
before adopting them. This may result in load
classifications varying from region to region.
• Example:
– Southern Nevada AHJs amended the first
paragraph of NEC 700.1; scope to include
specific references to loads that may be
connected to the emergency system. Many of
these loads would be considered Legally
Required Standby in other regions.
Research Codes
System Capacity
and Use
System Design Sequence
1
• Determine/Estimate Total Load of proposed system
• Determine Load that is Required by Code to be on
2
• Plan for anticipated Run Time for the system
3
• If the System is an emergency system, will it be used for Utility
Peak shaving program
4
• Review Fuel Source availability, Quantity of Generators, and
Redundancy
5
• Determine appropriate Accessories for the system
• Running kVA
– Calculated Electrical Loads + Metered
Electrical Loads
• Starting kVA
– What is the biggest starting kVA block (i.e. a
chiller system)
• Special considerations
– High harmonic content
– Intermittent starting
Generator Selection and Sizing
Metered Electrical Loads
NEC 220.87 (125% Rule)
• NEC requires that the existing loads are
metered to determine the “maximum
demand continuously recorded over a
minimum 30-day period,” and then use
125% of that number as the “existing”
load for the system.
• Maximum demand is measured as the
average power over a 15-minute period.
Generator Ratings
• Standby Power:
– Maximum output is available for non-programmed
power outages.
– Average demand during outages should not exceed
continuous rating of generator.
– Typical usage of 200 hrs/yr; max expected usage of
500 hrs/yr.
• Prime Power:
– De-rated capacity, typically 10% reduction from
standby power rating.
– Maximum output available for varying loads for all
outages.
– Average demand should not exceed continuous
rating.
• Continuous Power
– Maximum output available at all times.
– De-rated capacity, typically a 15% reduction from
prime power ratings.
Generator De-Rating
– A prime generator is essentially a standby generator de-rated
plus additional accessories. The same generator de-rated
again is a continuous duty.
– 2000 kW standby = 1825 kW prime = 1600 kW continuous
– But with prime and continuous ratings, everything is bigger:
generators, space to accommodate, air intake requirements,
fuel consumption, but with less capacity.
Warranty Issues
• What does all of this have to do with
my warranty?
– Standard warranty for generators are
defined by run hours and length of time,
and typically include the rating of the
generator.
– Warranties generally do not include:
• Use of standby generators in prime
applications
• Use of blended fuels such as a natural
gas/diesel mixture
• Excessive overloading of the generator.
Generator Tier Ratings
Tier 2 Tier 4
Emergency Systems can be tier 2 when
used for Emergency Purposes only.
Emergency Systems must be tier 4 if
they also participate in a Peak Shaving
program that the utility uses for financial
gain (they can sell power for more than
you get paid).
Can remain tier 2 even if they join a
“emergency demand response” program
offered by the Utility Provider.
Tier 4 requires additional capital
investments and additional equipment.
Maximum Run time, testing time, and
demand response time criteria.
Per Today’s rules - A new Tier 2
generator installed today CANNOT ever
be modified to be a Tier 4 Generator.
Researched
Codes
System
Capacity
and Use
Select a
System
Types of Generators
• Portable
• Stationary Standby
– Diesel
– Liquid Propane
– Natural Gas
– Dual Fuel.
Fuel Considerations
• On-site fuel storage NEC 700.12(B)(3)
• Dual Fuel (or Bi-fuel)
– Can provide an extended runtime.
– Usually an aftermarket retrofit to a diesel generator.
Although, some manufacturers do have a factory
assembled and tested bi-fuel systems.
– Typically achieves a 40%/60% split.
• Fuel Polisher
– Diesel fuel will foul when stored more than 3 to 6
months without conditioning or detergent additives.
– This presents an issue for large on-site fuel storage
systems.
Location
• Indoor
– EPS shall be located in a dedicated room with 2-
hour fire resistance rating (NFPA 110 Chapter
7.2.1)
– EPSS equipment may be located in EPS room
(NFPA 110 Chapter 7.2.1.2)
• Outdoor
– Requires weatherproof enclosure (NFPA 110
Chapter 7.2.2.1)
– EPSS equipment may be located within the EPS
enclosure (NFPA 110 Chapter 7.2.2.3)
How many generators?
• Several reasons to consider more than
one generator.
– Physical Space.
– Redundancy/Resilience.
– Phased expansion.
Redundancy
• Data centers, hospitals, large-scale
hospitality resorts, municipal command
centers, etc.
• N+1, 2N
• Multiple priorities
• Real-time demand load management
Generator Ratings.
• Examine the system voltage. Is the primary
distribution routed at low voltage (600 V or
less) or medium voltage (more than 600 V,
but less than 38 kV)?
• 208 V, 3-Phase System; 900 kW/1125 kVA
• 240 V, 1-Phase System; 600 kW/750 kVA
• 480 V, 3-Phase System; 2000 kW/2500 kVA
• 13 kV, 3-Phase System
Generator Accessories
• Typical Package Generator
– Jacket Heater
– Battery Charger
– Daytank Controls
• Other Considerations
– Remote Radiator
• Radiator Fan
• Aftercooler Water Pump
– Motorized Dampers
– Remote Fuel Pumps
Researched
Codes
System
Capacity and
Use
Select a
System
Installation and
Commissioning
EPSS Commissioning
Generator
Remote Alarm Annunciation
Fuel System Performance
Parallel Switchgear (if applicable)
Load Shedding
Switchgear “Features”
Generator Assembly
• Load Bank Testing
• Sound Testing
• Emissions Testing
• Accessory Review and Testing
Generator Load Bank Test
• Resistive Load Bank Test
– Load Bank is set to the generator Rated
Power Factor (0.8 PF)
– Commonly a factory test
• Reactive Load Bank Test (1.0 PF)
• Only allowed in field IF reactive was done in
factory (NFPA 110)
Generator Load Bank Test
• NFPA 110 minimum load bank test.
• 2 hours at full load.
• 5 minute cool down.
• Full rating block load to start the second
half. Take a wave capture of the unit
performance during the block load.
• 2-hour run at full load.
• Recordings every 15 minutes for the
duration of the test.
• Sound Testing
– Sound criteria requirements at certain locations
• Air Performance
– Sufficient air to the generator engines
– Emissions too close to an intake
– Air emissions testing
• Generator Accessories
– Battery charger goes back on with generator
power
– Jacket heater turns off when unit is running
Alarm Annunciation
• Alarms annunciate
at Unit Mounted
Controller (CV)
• Alarms Annunciate
at Remote
Annunciator (RA)
• Doesn’t address
parallel system
alarms!
• Per NFPA 110 and
NFPA 99
Alarm CV S RA
(a) Overcrank X X X
(b) Low Water Temp. <70
o
F (21
o
C) X X
(c) High Engine Temp Prealarm X X
(d) High Engine Temperature X X X
(e) Low Lube Oil Pressure Prealarm X X
(f) Low Lube Oil Pressure X X X
(g) Overspeed X X X
(h) Low Fuel Main Tank (@ 48 hrs. fuel remaining) X X
(i) Low coolant level X X
(j) EPS Supplying Load X
(k) Control or Test Switch Not in Auto. Position X X
(l) High Battery Voltage X
(m) Low cranking voltage X X
(n) Low Voltage in Battery X
(o) Battery charger ac failure X
(p) Lamp Test X
(q) Audible Alarm Silencing Switch X
(r) Low Starting Air Pressure X
(s) Low Starting Hydraulic Pressure X
(t) Air Shutdown Damper when used X X X
(u) Remote Emergency Stop X
(v) Day tank Hi-low Alarm X X
(w) Leak detection inner cavity of skid mount fuel tank X X
(x) Remote Radiator Breaker Position X X
KEY:
CV Control panel-mtd. visual indication
RA Remote Audible
S Shutdown of EPS
X Required
Alarm Annunciation
• Most alarms can be simulated at the
generator, and verified at the annunciator.
• Must include audible and visual
annunciation at remote location.
• Recommend adding parallel switchgear
(EPSS) alarms where used.
• Other codes supplement this too, such as
high-rise requirements in NFPA 101.
Fuel System Performance
• Verify each day tank if used can call for
fuel individually and generators are
getting correct amount of fuel.
• Verify low fuel alarm is set to the
appropriate point and works.
Low fuel Settings
• Required Generator
Class = Required Low
Fuel Setting
• Class 48 = 48 hrs of fuel
• Class 10 = 10 hrs of fuel
• 48 hrs x Generator
Hourly Consumption =
Low Fuel Level Alarm
Low Fuel Alarm
Parallel Switchgear Commissioning
• Multiple Generators Operating as a
system so…
• Complete System operation must be
checked!
• Manufacturers can use PLC inputs or
potentially PC overrides to “simulate”
system loads.
Parallel Switchgear Functions
• Load Shed – Function where Transfer
Switches are assigned a different priority
– Essential System would be a 1.
– Equipment loads may be a 2.
– Non-essential may be a 3.
• Usually will relate to the number of
generators on the bus.
Parallel Switchgear Load Shed
Essential System Load Priority Schedule
ATS NUMBER BRANCH BYPASS VOLT. Pri. 100 Priority 200
ISOLATION LOAD SUB No. L.S. T.I. LOAD
ATS-CHCEP Critical Y 480 26.7
ATS-FP Fire Pump Y 480 75
ATS-CR1 Critical Y 480 283.5
ATS-CR2 Critical Y 480 129
ATS-LS1 Life Safety Y 480 220.6
ATS-EQ2 Equipment Y 480 119.2
ATS-XRAY Equipment Y 480 201 Y Y
ATS-EQ1 Equipment Y 480 202 Y Y
ATS-EQHCEPA Equipment Y 480 203 Y Y
ATS-EQHCEPB Equipment Y 480 204 Y Y 213
ATS-EQHCEPC Equipment Y 480 205 Y Y 1082
ATS-N1 Non-Essential Y 480 206 Y Y 143.8
Total (KVA) 854 Total (KVA) 1439
Total (KW @ 0.9 P.F.) 768.6 Total (KW @ 0.9 P.F.) 1295
Total Priority 100 + 200 Loads (KW) 2063.9
Capacity 3000
Parallel Switchgear Commissioning
Sample Switchgear Commissioning Document (Partial)
Mode: Bus Optimization Off / Generator Demand Off (with Amp Generator)
Operation: Generators will load each priority level as a block. The quantity of priority
Blocks connected is the same as the priority block connected. If a generator fails,
the block associated with that generator will shed.
Scenario 1: Startup. Turn off Normal power, system should call for start. Priority 1
loads will transfer within 10 seconds. Priority 2 will transfer after their associated
time delays.
Scenario 2: Second Generator Failure – Priority two Block Loads shed. Turn
Second Gen back on and all Priority 2 loads add in one block.
Scenario 3: Gen 1,2 Operating. System Bus overload of 105 % over two
generators simulated by a 4-20ma generator. (3000 kW * 1.05 = 3150 kW); Priority 2
loads should shed in descending priority & sub priority order.
Parallel Switchgear Functions
• Other features to test
– Generator Demand Mode (Used to turn off
Generators when demand is low enough to
warrant it.
• Bus under-frequency
– (Sheds loads and locks out!)
• Emergency stop buttons
• Remote ATS control (where applicable)
Learning Summary
Researched
Codes
• NEC
• NFPA 110, 99
• IBC
System
Capacity and
Use
• Demand and
Calculated Loads
• Tier Ratings
Select a System
• Fuel Source
• Location
• Parallel?
• Redundancy
Installation and
Commissioning
• Load Bank
• Annunciation
• System Testing
Code References
• International Building Code
• NFPA 20
• NFPA 70 (NEC)
• NFPA 99
• NFPA 101
• NFPA 110
Robert R. Jones Jr., PE, LEED AP,
JBA Consulting Engineers,
Las Vegas, Nev.
James Ferris, PE,
TLC Engineering for Architecture,
Orlando, Fla.
Moderator: Jack Smith,
Consulting-Specifying Engineer and Pure Power,
CFE Media, LLC
Presenters:
Thanks to Today’s Webcast Sponsor:
Webcasts and Research
• Critical Power: Standby Versus
Emergency Power Systems
• Critical Power: Standby Power for Mission
Critical Facilities
• 2013 Electrical/Power Research Study
Critical Power: Generators and
Generator System Design
Sponsored by:

Weitere ähnliche Inhalte

Was ist angesagt?

Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
Priten Vasa
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing System
Salil Vaidya
 
Generator cooling and sealing system 2
Generator cooling and sealing system 2Generator cooling and sealing system 2
Generator cooling and sealing system 2
Mohammad Basid
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
Dinesh Sarda
 

Was ist angesagt? (20)

Electrical Design calculations
Electrical Design calculationsElectrical Design calculations
Electrical Design calculations
 
Basics of Diesel Generator System
Basics of Diesel Generator SystemBasics of Diesel Generator System
Basics of Diesel Generator System
 
Safety During Installation of Plant and Equipment | Gaurav Singh Rajput
Safety During Installation of Plant and Equipment | Gaurav Singh RajputSafety During Installation of Plant and Equipment | Gaurav Singh Rajput
Safety During Installation of Plant and Equipment | Gaurav Singh Rajput
 
Static excitation-system
Static excitation-systemStatic excitation-system
Static excitation-system
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
 
Electrical System Design
Electrical System Design Electrical System Design
Electrical System Design
 
Automatic Generation Control
Automatic Generation ControlAutomatic Generation Control
Automatic Generation Control
 
Equipment and Stability Constraints : System Operation
Equipment and Stability Constraints : System OperationEquipment and Stability Constraints : System Operation
Equipment and Stability Constraints : System Operation
 
Generator Protection
Generator ProtectionGenerator Protection
Generator Protection
 
Fire Pump Transfer Switch Basics
Fire Pump Transfer Switch BasicsFire Pump Transfer Switch Basics
Fire Pump Transfer Switch Basics
 
RTCC & AVR
RTCC & AVRRTCC & AVR
RTCC & AVR
 
Turbine Governing System
Turbine Governing SystemTurbine Governing System
Turbine Governing System
 
Generator cooling and sealing system 2
Generator cooling and sealing system 2Generator cooling and sealing system 2
Generator cooling and sealing system 2
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
Power Quality & Benefits of Power Quality
Power Quality & Benefits of Power Quality Power Quality & Benefits of Power Quality
Power Quality & Benefits of Power Quality
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 
Flywheel Energy Storage System
Flywheel Energy Storage SystemFlywheel Energy Storage System
Flywheel Energy Storage System
 
Power system security
Power system security Power system security
Power system security
 
An overview of FACTS devices
An overview of FACTS devicesAn overview of FACTS devices
An overview of FACTS devices
 

Ähnlich wie Critical Power: Generators and Generator System Design

Nec emergency requirements
Nec emergency requirementsNec emergency requirements
Nec emergency requirements
michaeljmack
 
Standby power systems for hospitals
Standby power systems for hospitalsStandby power systems for hospitals
Standby power systems for hospitals
michaeljmack
 
Artificial lift forum ul 1741 presentation - final
Artificial lift forum   ul 1741 presentation - finalArtificial lift forum   ul 1741 presentation - final
Artificial lift forum ul 1741 presentation - final
Ron Henderson
 
IRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdfIRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdf
PowerSystemDynamicsS
 
Case studies of installation inspections of a demand response program
Case studies of installation inspections of a demand response programCase studies of installation inspections of a demand response program
Case studies of installation inspections of a demand response program
Zondits
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
Philippe AGULLO
 
Ratings and Load Factor - B. Egan Sep2016 no spkr notes ar.ppt
Ratings and Load Factor - B. Egan Sep2016 no spkr notes ar.pptRatings and Load Factor - B. Egan Sep2016 no spkr notes ar.ppt
Ratings and Load Factor - B. Egan Sep2016 no spkr notes ar.ppt
e05dinuka
 
ATS, Grounding Issues & Installation Considerations
ATS, Grounding Issues & Installation ConsiderationsATS, Grounding Issues & Installation Considerations
ATS, Grounding Issues & Installation Considerations
michaeljmack
 

Ähnlich wie Critical Power: Generators and Generator System Design (20)

Critical Power: NFPA 110: Standard for Emergency and Standby Power
Critical Power: NFPA 110: Standard for Emergency and Standby Power Critical Power: NFPA 110: Standard for Emergency and Standby Power
Critical Power: NFPA 110: Standard for Emergency and Standby Power
 
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
Energy Storage: New Capabilities for the Electric Grid – The Tehachapi Energy...
 
Nec emergency requirements
Nec emergency requirementsNec emergency requirements
Nec emergency requirements
 
NAPT-5675-EN
NAPT-5675-ENNAPT-5675-EN
NAPT-5675-EN
 
NAPT-5675-EN
NAPT-5675-ENNAPT-5675-EN
NAPT-5675-EN
 
Standby power systems for hospitals
Standby power systems for hospitalsStandby power systems for hospitals
Standby power systems for hospitals
 
Energy in Factory Automation and the Role of Industrial Networks
Energy in Factory Automation and the Role of Industrial NetworksEnergy in Factory Automation and the Role of Industrial Networks
Energy in Factory Automation and the Role of Industrial Networks
 
Energy in Factory Automation and the Role of Industrial Networks
Energy in Factory Automation and the Role of Industrial Networks Energy in Factory Automation and the Role of Industrial Networks
Energy in Factory Automation and the Role of Industrial Networks
 
Artificial lift forum ul 1741 presentation - final
Artificial lift forum   ul 1741 presentation - finalArtificial lift forum   ul 1741 presentation - final
Artificial lift forum ul 1741 presentation - final
 
IRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdfIRPTF_Workshop_Presentations (1).pdf
IRPTF_Workshop_Presentations (1).pdf
 
Case studies of installation inspections of a demand response program
Case studies of installation inspections of a demand response programCase studies of installation inspections of a demand response program
Case studies of installation inspections of a demand response program
 
Power factor correction
Power factor correctionPower factor correction
Power factor correction
 
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia LaboratoryRT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
RT15 Berkeley | Optimized Power Flow Control in Microgrids - Sandia Laboratory
 
Power Presentation West Palm
Power Presentation West PalmPower Presentation West Palm
Power Presentation West Palm
 
Ratings and Load Factor - B. Egan Sep2016 no spkr notes ar.ppt
Ratings and Load Factor - B. Egan Sep2016 no spkr notes ar.pptRatings and Load Factor - B. Egan Sep2016 no spkr notes ar.ppt
Ratings and Load Factor - B. Egan Sep2016 no spkr notes ar.ppt
 
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGSCRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
 
Power station
Power stationPower station
Power station
 
Grid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power SystemGrid Event Analysis In Indian Power System
Grid Event Analysis In Indian Power System
 
M A MALLICK ppt. for FDP SEPT. 2019
M A MALLICK ppt. for  FDP SEPT. 2019M A MALLICK ppt. for  FDP SEPT. 2019
M A MALLICK ppt. for FDP SEPT. 2019
 
ATS, Grounding Issues & Installation Considerations
ATS, Grounding Issues & Installation ConsiderationsATS, Grounding Issues & Installation Considerations
ATS, Grounding Issues & Installation Considerations
 

Mehr von ConsultingSpecifyingEngineer

The State of the Electrical/Power Engineering Industry
The State of the Electrical/Power Engineering Industry The State of the Electrical/Power Engineering Industry
The State of the Electrical/Power Engineering Industry
ConsultingSpecifyingEngineer
 

Mehr von ConsultingSpecifyingEngineer (15)

Fire and Life Safety: Integration: Building Automation Systems and Fire/Life ...
Fire and Life Safety: Integration: Building Automation Systems and Fire/Life ...Fire and Life Safety: Integration: Building Automation Systems and Fire/Life ...
Fire and Life Safety: Integration: Building Automation Systems and Fire/Life ...
 
HVAC: New chiller requirements
HVAC: New chiller requirementsHVAC: New chiller requirements
HVAC: New chiller requirements
 
Critical power: Transfer switches and switchgear
Critical power: Transfer switches and switchgearCritical power: Transfer switches and switchgear
Critical power: Transfer switches and switchgear
 
Electrical Systems: Designing electrical rooms
Electrical Systems: Designing electrical roomsElectrical Systems: Designing electrical rooms
Electrical Systems: Designing electrical rooms
 
HVAC for Data Centers
HVAC for Data CentersHVAC for Data Centers
HVAC for Data Centers
 
Critical Power: Integrating Renewable Power into Buildings
Critical Power: Integrating Renewable Power into BuildingsCritical Power: Integrating Renewable Power into Buildings
Critical Power: Integrating Renewable Power into Buildings
 
Modular Data Center Design
Modular Data Center DesignModular Data Center Design
Modular Data Center Design
 
Fire and Life Safety: Notification and Emergency Communication Systems
Fire and Life Safety: Notification and Emergency Communication SystemsFire and Life Safety: Notification and Emergency Communication Systems
Fire and Life Safety: Notification and Emergency Communication Systems
 
Critical Power: Circuit Protection in Health Care Facilities
Critical Power: Circuit Protection in Health Care FacilitiesCritical Power: Circuit Protection in Health Care Facilities
Critical Power: Circuit Protection in Health Care Facilities
 
Create Marketing Engineers Love
Create Marketing Engineers LoveCreate Marketing Engineers Love
Create Marketing Engineers Love
 
Industrial Branding: The Lost Art in the Industrial Marketplace
Industrial Branding: The Lost Art in the Industrial MarketplaceIndustrial Branding: The Lost Art in the Industrial Marketplace
Industrial Branding: The Lost Art in the Industrial Marketplace
 
Creating an Integrated Marketing Campaign for Impact and Results
Creating an Integrated Marketing Campaign for Impact and ResultsCreating an Integrated Marketing Campaign for Impact and Results
Creating an Integrated Marketing Campaign for Impact and Results
 
Marketing New Product Introductions in Mobility & SaaS: Ideation to Marketing...
Marketing New Product Introductions in Mobility & SaaS: Ideation to Marketing...Marketing New Product Introductions in Mobility & SaaS: Ideation to Marketing...
Marketing New Product Introductions in Mobility & SaaS: Ideation to Marketing...
 
Integrating the Marketing and Engineering Points of View in Marketing Communi...
Integrating the Marketing and Engineering Points of View in Marketing Communi...Integrating the Marketing and Engineering Points of View in Marketing Communi...
Integrating the Marketing and Engineering Points of View in Marketing Communi...
 
The State of the Electrical/Power Engineering Industry
The State of the Electrical/Power Engineering Industry The State of the Electrical/Power Engineering Industry
The State of the Electrical/Power Engineering Industry
 

KĂźrzlich hochgeladen

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
heathfieldcps1
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
AnaAcapella
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 

KĂźrzlich hochgeladen (20)

The basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptxThe basics of sentences session 3pptx.pptx
The basics of sentences session 3pptx.pptx
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
Fostering Friendships - Enhancing Social Bonds in the Classroom
Fostering Friendships - Enhancing Social Bonds  in the ClassroomFostering Friendships - Enhancing Social Bonds  in the Classroom
Fostering Friendships - Enhancing Social Bonds in the Classroom
 
ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701ComPTIA Overview | Comptia Security+ Book SY0-701
ComPTIA Overview | Comptia Security+ Book SY0-701
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Unit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptxUnit-IV; Professional Sales Representative (PSR).pptx
Unit-IV; Professional Sales Representative (PSR).pptx
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 

Critical Power: Generators and Generator System Design

  • 1. Critical Power: Generators and Generator System Design Sponsored by:
  • 3. Learning Objectives: 1.The audience will understand the applicable code requirements including NFPA 70: National Electrical Code and NFPA 110: Standard for Emergency and Standby Power Systems 2.Attendees will learn the criteria for selecting the appropriate generator or generators for the building type and/or application 3.Viewers will understand the criteria for designing the generator system, and know the differences between prime rated versus standby rated engines (U.S. EPA standards) 4.Viewers will learn the criteria for commissioning generators and the electrical systems they support.
  • 4. Robert R. Jones Jr., PE, LEED AP, JBA Consulting Engineers, Las Vegas, Nev. James Ferris, PE, TLC Engineering for Architecture, Orlando, Fla. Moderator: Jack Smith, Consulting-Specifying Engineer and Pure Power, CFE Media, LLC Presenters:
  • 5. Critical Power: Generators and Generator System Design Robert R. Jones Jr., PE, LEED, AP JBA Consulting Engineers, Las Vegas, Nev. James Ferris, PE, TLC Engineering for Architecture, Orlando, Fla.
  • 6. Codes & Standards • IBC – Chapter 27: Electrical • NFPA 110: Emergency & Standby Power Systems • NFPA 101: Life Safety Code • NFPA 70: National Electrical Code – Article 445: Generators – Article 700, 701, & 702: Systems
  • 7. IBC – 2012 Edition • Chapter 27 addresses electrical components, equipment, and systems • 2702.1 - Emergency and Standby Systems shall be installed per NFPA 110 • 2702.2 – Emergency and Standby Systems shall be installed where required
  • 8. NFPA 110 – 2013 Edition • Definitions (NFPA 110 Chapter 3) – Emergency Power Supply (EPS): “The source of electrical power of the required capacity and quality for an emergency power supply system (EPSS).” – Emergency Power Supply System (EPSS): “A complete functioning EPS system coupled to a system of conductors, disconnecting means and overcurrent protective devices, transfer switches and all control, supervisory and support devices up to and including the load terminals of the transfer equipment needed for the system to operate as a safe and reliable source of electric power.”
  • 10. NFPA 110 – 2013 Edition • Chapter 4: EPSS Classification – Class: Minimum time to operate without refueling/recharging. – Type: Maximum time to re-energize loads. – Level: Installation, performance, and maintenance criteria.
  • 11. NFPA 110 – 2013 Edition • Class – Defined in hours per applicable code, application and AHJ. – Battery System • NEC Article 700.12(A): 1.5-hour minimum, Class 1.5. – Generator System • NEC Article 700.12(B)(2): 2-hour minimum, Class 2. • NFPA 20 Chapter 9.6.2.3: 8-hour minimum, Class 8. • AIA Guidelines for Design and Construction of Healthcare Facilities (Joint Commission requirement): 24 hours minimum, Class 24.
  • 12. NFPA 110 – 2013 Edition • Type – Defined in seconds per applicable code, application and AHJ. – NEC Article 700.12: 10 seconds maximum, Type 10. – NFPA 20 Chapter 9.6.2.1: 10 seconds maximum, Type 10. – NEC Article 701.12: 60 seconds maximum, Type 60.
  • 13. NFPA 110 – 2013 Edition • Level 1 – Required where EPSS failure “could result in loss of human life or serious injuries.” – NEC Article 700: Emergency System. – NEC Article 701: Legally Required Standby (NFPA 101 7.14.7.1) – NEC Article 517: Chapter 3 Essential Electrical System. • Level 2 – Required where EPSS failure “is less critical to human life and safety.” – NEC Article 701: Legally Required Standby.
  • 14. NFPA 101 – 2012 Edition • Type 10, Class 1.5, Level 1 for emergency lighting (7.9.2.2) • Type 60, Class 2, Level 1 for occupant evacuation elevators (7.14.7.1) • Type 60, Class 1, Level 1 for high-rise standby power (legally required) – Electric Fire Pump – Jockey Pump – Air Compressor for dry-pipe/pre-action fire suppression system – Emergency Command Center – At least one elevator serving all floors – Mechanical Smoke Control
  • 15. NEC (NFPA 70) – 2011 Edition • Article 445: Generators – The ampacity of conductors from each generator to the first overcurrent device must be at least 115% of the nameplate current rating (NEC 445.13) – One or more disconnects with means of locking in the open position are required (NEC 445.18)
  • 16. NEC (NFPA 70) – 2011 Edition • Article 700: Emergency Systems – EPS capacity shall be capable of supplying all emergency system loads simultaneously (NEC 700.4(A)) – EPS may serve loads other than emergency if capacity and rating can support all connected loads simultaneously or transfer equipment incorporates selective load pickup and load shedding. – Requires automatic transfer switches that supply only emergency loads (NEC 700.12(A) & 700.12(D)) – Wiring shall be contained in separate raceways, enclosures, etc. from all other systems. Separate vertical switchboard section required when emergency source serves multiple systems (NEC 700.10(B)) • Article 701: Legally Required Standby Systems – EPS capacity shall be capable of supplying all legally required standby loads intended to operate simultaneously (NEC 701.4) – Requires automatic transfer switches (NEC 701.12(A) – Transfer switches require load shedding capability if generator capacity is not sized to supply all connected loads at once (NEC 701.4) • Article 702: Optional Standby Systems – Permanent installations require manual or automatic transfer switches (NEC 702.5) – Transfer switches require load shedding capability if generator capacity is not sized to supply all connected loads at once (NEC 702.4(B)(2))
  • 17. TO GENSET CONTROL PANEL FOR SELECTIVE LOAD PICKUP AND SHEDDING
  • 18. How Loads Are Classified • Requirements for loads classified as emergency and legally required standby are generally defined by the AHJ and adopted codes. • IBC 2702.2 references other IBC sections for emergency and legally required standby loads. Common applications below. – Emergency Loads • Voice/Alarm Communications Systems in Group A Occupancies and Covered and Open Mall Buildings (IBC 907.5.2.2.4 & 402.7.3) • Exit Signs and Means of Egress Illumination (IBC 1011.6.3 & 1006.3) • High-Rise Buildings (IBC 403.4.9) – Elevator Car Lighting – Voice/Alarm Communications Systems – Automatic Fire Detection Systems – Fire Alarm Systems – Electrically powered fire pumps – Legally Required Standby Loads • Smoke Control Systems (IBC 909.11) • Accessible means of egress elevators (IBC 1007.4) • High-Rise Buildings (IBC 403.4.8) – Power and Lighting for the Fire Command Center – Ventilation and automatic Fire detection equipment for smoke proof enclosures. – Elevators
  • 19. Local AHJ Considerations • Some AHJs amend codes and standards before adopting them. This may result in load classifications varying from region to region. • Example: – Southern Nevada AHJs amended the first paragraph of NEC 700.1; scope to include specific references to loads that may be connected to the emergency system. Many of these loads would be considered Legally Required Standby in other regions.
  • 21. System Design Sequence 1 • Determine/Estimate Total Load of proposed system • Determine Load that is Required by Code to be on 2 • Plan for anticipated Run Time for the system 3 • If the System is an emergency system, will it be used for Utility Peak shaving program 4 • Review Fuel Source availability, Quantity of Generators, and Redundancy 5 • Determine appropriate Accessories for the system
  • 22. • Running kVA – Calculated Electrical Loads + Metered Electrical Loads • Starting kVA – What is the biggest starting kVA block (i.e. a chiller system) • Special considerations – High harmonic content – Intermittent starting Generator Selection and Sizing
  • 23. Metered Electrical Loads NEC 220.87 (125% Rule) • NEC requires that the existing loads are metered to determine the “maximum demand continuously recorded over a minimum 30-day period,” and then use 125% of that number as the “existing” load for the system. • Maximum demand is measured as the average power over a 15-minute period.
  • 24. Generator Ratings • Standby Power: – Maximum output is available for non-programmed power outages. – Average demand during outages should not exceed continuous rating of generator. – Typical usage of 200 hrs/yr; max expected usage of 500 hrs/yr. • Prime Power: – De-rated capacity, typically 10% reduction from standby power rating. – Maximum output available for varying loads for all outages. – Average demand should not exceed continuous rating. • Continuous Power – Maximum output available at all times. – De-rated capacity, typically a 15% reduction from prime power ratings.
  • 25. Generator De-Rating – A prime generator is essentially a standby generator de-rated plus additional accessories. The same generator de-rated again is a continuous duty. – 2000 kW standby = 1825 kW prime = 1600 kW continuous – But with prime and continuous ratings, everything is bigger: generators, space to accommodate, air intake requirements, fuel consumption, but with less capacity.
  • 26. Warranty Issues • What does all of this have to do with my warranty? – Standard warranty for generators are defined by run hours and length of time, and typically include the rating of the generator. – Warranties generally do not include: • Use of standby generators in prime applications • Use of blended fuels such as a natural gas/diesel mixture • Excessive overloading of the generator.
  • 27. Generator Tier Ratings Tier 2 Tier 4 Emergency Systems can be tier 2 when used for Emergency Purposes only. Emergency Systems must be tier 4 if they also participate in a Peak Shaving program that the utility uses for financial gain (they can sell power for more than you get paid). Can remain tier 2 even if they join a “emergency demand response” program offered by the Utility Provider. Tier 4 requires additional capital investments and additional equipment. Maximum Run time, testing time, and demand response time criteria. Per Today’s rules - A new Tier 2 generator installed today CANNOT ever be modified to be a Tier 4 Generator.
  • 29. Types of Generators • Portable • Stationary Standby – Diesel – Liquid Propane – Natural Gas – Dual Fuel.
  • 30. Fuel Considerations • On-site fuel storage NEC 700.12(B)(3) • Dual Fuel (or Bi-fuel) – Can provide an extended runtime. – Usually an aftermarket retrofit to a diesel generator. Although, some manufacturers do have a factory assembled and tested bi-fuel systems. – Typically achieves a 40%/60% split. • Fuel Polisher – Diesel fuel will foul when stored more than 3 to 6 months without conditioning or detergent additives. – This presents an issue for large on-site fuel storage systems.
  • 31. Location • Indoor – EPS shall be located in a dedicated room with 2- hour fire resistance rating (NFPA 110 Chapter 7.2.1) – EPSS equipment may be located in EPS room (NFPA 110 Chapter 7.2.1.2) • Outdoor – Requires weatherproof enclosure (NFPA 110 Chapter 7.2.2.1) – EPSS equipment may be located within the EPS enclosure (NFPA 110 Chapter 7.2.2.3)
  • 32. How many generators? • Several reasons to consider more than one generator. – Physical Space. – Redundancy/Resilience. – Phased expansion.
  • 33. Redundancy • Data centers, hospitals, large-scale hospitality resorts, municipal command centers, etc. • N+1, 2N • Multiple priorities • Real-time demand load management
  • 34. Generator Ratings. • Examine the system voltage. Is the primary distribution routed at low voltage (600 V or less) or medium voltage (more than 600 V, but less than 38 kV)? • 208 V, 3-Phase System; 900 kW/1125 kVA • 240 V, 1-Phase System; 600 kW/750 kVA • 480 V, 3-Phase System; 2000 kW/2500 kVA • 13 kV, 3-Phase System
  • 35. Generator Accessories • Typical Package Generator – Jacket Heater – Battery Charger – Daytank Controls • Other Considerations – Remote Radiator • Radiator Fan • Aftercooler Water Pump – Motorized Dampers – Remote Fuel Pumps
  • 37. EPSS Commissioning Generator Remote Alarm Annunciation Fuel System Performance Parallel Switchgear (if applicable) Load Shedding Switchgear “Features”
  • 38. Generator Assembly • Load Bank Testing • Sound Testing • Emissions Testing • Accessory Review and Testing
  • 39. Generator Load Bank Test • Resistive Load Bank Test – Load Bank is set to the generator Rated Power Factor (0.8 PF) – Commonly a factory test • Reactive Load Bank Test (1.0 PF) • Only allowed in field IF reactive was done in factory (NFPA 110)
  • 40. Generator Load Bank Test • NFPA 110 minimum load bank test. • 2 hours at full load. • 5 minute cool down. • Full rating block load to start the second half. Take a wave capture of the unit performance during the block load. • 2-hour run at full load. • Recordings every 15 minutes for the duration of the test.
  • 41. • Sound Testing – Sound criteria requirements at certain locations • Air Performance – Sufficient air to the generator engines – Emissions too close to an intake – Air emissions testing • Generator Accessories – Battery charger goes back on with generator power – Jacket heater turns off when unit is running
  • 42. Alarm Annunciation • Alarms annunciate at Unit Mounted Controller (CV) • Alarms Annunciate at Remote Annunciator (RA) • Doesn’t address parallel system alarms! • Per NFPA 110 and NFPA 99 Alarm CV S RA (a) Overcrank X X X (b) Low Water Temp. <70 o F (21 o C) X X (c) High Engine Temp Prealarm X X (d) High Engine Temperature X X X (e) Low Lube Oil Pressure Prealarm X X (f) Low Lube Oil Pressure X X X (g) Overspeed X X X (h) Low Fuel Main Tank (@ 48 hrs. fuel remaining) X X (i) Low coolant level X X (j) EPS Supplying Load X (k) Control or Test Switch Not in Auto. Position X X (l) High Battery Voltage X (m) Low cranking voltage X X (n) Low Voltage in Battery X (o) Battery charger ac failure X (p) Lamp Test X (q) Audible Alarm Silencing Switch X (r) Low Starting Air Pressure X (s) Low Starting Hydraulic Pressure X (t) Air Shutdown Damper when used X X X (u) Remote Emergency Stop X (v) Day tank Hi-low Alarm X X (w) Leak detection inner cavity of skid mount fuel tank X X (x) Remote Radiator Breaker Position X X KEY: CV Control panel-mtd. visual indication RA Remote Audible S Shutdown of EPS X Required
  • 43. Alarm Annunciation • Most alarms can be simulated at the generator, and verified at the annunciator. • Must include audible and visual annunciation at remote location. • Recommend adding parallel switchgear (EPSS) alarms where used. • Other codes supplement this too, such as high-rise requirements in NFPA 101.
  • 44. Fuel System Performance • Verify each day tank if used can call for fuel individually and generators are getting correct amount of fuel. • Verify low fuel alarm is set to the appropriate point and works.
  • 45. Low fuel Settings • Required Generator Class = Required Low Fuel Setting • Class 48 = 48 hrs of fuel • Class 10 = 10 hrs of fuel • 48 hrs x Generator Hourly Consumption = Low Fuel Level Alarm Low Fuel Alarm
  • 46. Parallel Switchgear Commissioning • Multiple Generators Operating as a system so… • Complete System operation must be checked! • Manufacturers can use PLC inputs or potentially PC overrides to “simulate” system loads.
  • 47. Parallel Switchgear Functions • Load Shed – Function where Transfer Switches are assigned a different priority – Essential System would be a 1. – Equipment loads may be a 2. – Non-essential may be a 3. • Usually will relate to the number of generators on the bus.
  • 48. Parallel Switchgear Load Shed Essential System Load Priority Schedule ATS NUMBER BRANCH BYPASS VOLT. Pri. 100 Priority 200 ISOLATION LOAD SUB No. L.S. T.I. LOAD ATS-CHCEP Critical Y 480 26.7 ATS-FP Fire Pump Y 480 75 ATS-CR1 Critical Y 480 283.5 ATS-CR2 Critical Y 480 129 ATS-LS1 Life Safety Y 480 220.6 ATS-EQ2 Equipment Y 480 119.2 ATS-XRAY Equipment Y 480 201 Y Y ATS-EQ1 Equipment Y 480 202 Y Y ATS-EQHCEPA Equipment Y 480 203 Y Y ATS-EQHCEPB Equipment Y 480 204 Y Y 213 ATS-EQHCEPC Equipment Y 480 205 Y Y 1082 ATS-N1 Non-Essential Y 480 206 Y Y 143.8 Total (KVA) 854 Total (KVA) 1439 Total (KW @ 0.9 P.F.) 768.6 Total (KW @ 0.9 P.F.) 1295 Total Priority 100 + 200 Loads (KW) 2063.9 Capacity 3000
  • 49. Parallel Switchgear Commissioning Sample Switchgear Commissioning Document (Partial) Mode: Bus Optimization Off / Generator Demand Off (with Amp Generator) Operation: Generators will load each priority level as a block. The quantity of priority Blocks connected is the same as the priority block connected. If a generator fails, the block associated with that generator will shed. Scenario 1: Startup. Turn off Normal power, system should call for start. Priority 1 loads will transfer within 10 seconds. Priority 2 will transfer after their associated time delays. Scenario 2: Second Generator Failure – Priority two Block Loads shed. Turn Second Gen back on and all Priority 2 loads add in one block. Scenario 3: Gen 1,2 Operating. System Bus overload of 105 % over two generators simulated by a 4-20ma generator. (3000 kW * 1.05 = 3150 kW); Priority 2 loads should shed in descending priority & sub priority order.
  • 50. Parallel Switchgear Functions • Other features to test – Generator Demand Mode (Used to turn off Generators when demand is low enough to warrant it. • Bus under-frequency – (Sheds loads and locks out!) • Emergency stop buttons • Remote ATS control (where applicable)
  • 51. Learning Summary Researched Codes • NEC • NFPA 110, 99 • IBC System Capacity and Use • Demand and Calculated Loads • Tier Ratings Select a System • Fuel Source • Location • Parallel? • Redundancy Installation and Commissioning • Load Bank • Annunciation • System Testing
  • 52. Code References • International Building Code • NFPA 20 • NFPA 70 (NEC) • NFPA 99 • NFPA 101 • NFPA 110
  • 53. Robert R. Jones Jr., PE, LEED AP, JBA Consulting Engineers, Las Vegas, Nev. James Ferris, PE, TLC Engineering for Architecture, Orlando, Fla. Moderator: Jack Smith, Consulting-Specifying Engineer and Pure Power, CFE Media, LLC Presenters:
  • 54. Thanks to Today’s Webcast Sponsor:
  • 55. Webcasts and Research • Critical Power: Standby Versus Emergency Power Systems • Critical Power: Standby Power for Mission Critical Facilities • 2013 Electrical/Power Research Study
  • 56. Critical Power: Generators and Generator System Design Sponsored by:

Hinweis der Redaktion

  1. OCPD generally located directly on LV generators.MV generator OCPD located off generator in switchgear.