When designing generator systems, consulting engineers must ensure that the generators and the building electrical systems that they support are appropriate for the specific application. Whether providing standby power for health care facilities or prime power for rural processing plants, engineers must make decisions regarding generator sizing, load types, whether generators should be paralleled, fuel storage, switching scenarios, and many other criteria. In addition to being up to speed on the applicable codes, consulting engineers must work with the authorities having jurisdiction (AHJ) to ensure approval for the generator system is attained.
3. Learning Objectives:
1.The audience will understand the applicable code requirements
including NFPA 70: National Electrical Code and NFPA 110:
Standard for Emergency and Standby Power Systems
2.Attendees will learn the criteria for selecting the appropriate
generator or generators for the building type and/or application
3.Viewers will understand the criteria for designing the generator
system, and know the differences between prime rated versus
standby rated engines (U.S. EPA standards)
4.Viewers will learn the criteria for commissioning generators and
the electrical systems they support.
4. Robert R. Jones Jr., PE, LEED AP,
JBA Consulting Engineers,
Las Vegas, Nev.
James Ferris, PE,
TLC Engineering for Architecture,
Orlando, Fla.
Moderator: Jack Smith,
Consulting-Specifying Engineer and Pure Power,
CFE Media, LLC
Presenters:
5. Critical Power: Generators
and Generator System Design
Robert R. Jones Jr., PE, LEED, AP
JBA Consulting Engineers,
Las Vegas, Nev.
James Ferris, PE,
TLC Engineering for Architecture,
Orlando, Fla.
6. Codes & Standards
⢠IBC
â Chapter 27: Electrical
⢠NFPA 110: Emergency & Standby Power
Systems
⢠NFPA 101: Life Safety Code
⢠NFPA 70: National Electrical Code
â Article 445: Generators
â Article 700, 701, & 702: Systems
7. IBC â 2012 Edition
⢠Chapter 27 addresses electrical
components, equipment, and systems
⢠2702.1 - Emergency and Standby
Systems shall be installed per NFPA 110
⢠2702.2 â Emergency and Standby
Systems shall be installed where required
8. NFPA 110 â 2013 Edition
⢠Definitions (NFPA 110 Chapter 3)
â Emergency Power Supply (EPS): âThe source of electrical
power of the required capacity and quality for an
emergency power supply system (EPSS).â
â Emergency Power Supply System (EPSS): âA complete
functioning EPS system coupled to a system of
conductors, disconnecting means and overcurrent
protective devices, transfer switches and all control,
supervisory and support devices up to and including the
load terminals of the transfer equipment needed for the
system to operate as a safe and reliable source of electric
power.â
10. NFPA 110 â 2013 Edition
⢠Chapter 4: EPSS Classification
â Class: Minimum time to operate without
refueling/recharging.
â Type: Maximum time to re-energize loads.
â Level: Installation, performance, and
maintenance criteria.
11. NFPA 110 â 2013 Edition
⢠Class
â Defined in hours per applicable code, application
and AHJ.
â Battery System
⢠NEC Article 700.12(A): 1.5-hour minimum, Class 1.5.
â Generator System
⢠NEC Article 700.12(B)(2): 2-hour minimum, Class 2.
⢠NFPA 20 Chapter 9.6.2.3: 8-hour minimum, Class 8.
⢠AIA Guidelines for Design and Construction of
Healthcare Facilities (Joint Commission requirement):
24 hours minimum, Class 24.
12. NFPA 110 â 2013 Edition
⢠Type
â Defined in seconds per applicable code,
application and AHJ.
â NEC Article 700.12: 10 seconds maximum,
Type 10.
â NFPA 20 Chapter 9.6.2.1: 10 seconds
maximum, Type 10.
â NEC Article 701.12: 60 seconds maximum,
Type 60.
13. NFPA 110 â 2013 Edition
⢠Level 1
â Required where EPSS failure âcould result in loss of
human life or serious injuries.â
â NEC Article 700: Emergency System.
â NEC Article 701: Legally Required Standby (NFPA
101 7.14.7.1)
â NEC Article 517: Chapter 3 Essential Electrical
System.
⢠Level 2
â Required where EPSS failure âis less critical to
human life and safety.â
â NEC Article 701: Legally Required Standby.
14. NFPA 101 â 2012 Edition
⢠Type 10, Class 1.5, Level 1 for emergency lighting
(7.9.2.2)
⢠Type 60, Class 2, Level 1 for occupant evacuation
elevators (7.14.7.1)
⢠Type 60, Class 1, Level 1 for high-rise standby power
(legally required)
â Electric Fire Pump
â Jockey Pump
â Air Compressor for dry-pipe/pre-action fire suppression
system
â Emergency Command Center
â At least one elevator serving all floors
â Mechanical Smoke Control
15. NEC (NFPA 70) â 2011 Edition
⢠Article 445: Generators
â The ampacity of conductors from each
generator to the first overcurrent device must
be at least 115% of the nameplate current
rating (NEC 445.13)
â One or more disconnects with means of
locking in the open position are required
(NEC 445.18)
16. NEC (NFPA 70) â 2011 Edition
⢠Article 700: Emergency Systems
â EPS capacity shall be capable of supplying all emergency system loads simultaneously (NEC
700.4(A))
â EPS may serve loads other than emergency if capacity and rating can support all connected loads
simultaneously or transfer equipment incorporates selective load pickup and load shedding.
â Requires automatic transfer switches that supply only emergency loads (NEC 700.12(A) &
700.12(D))
â Wiring shall be contained in separate raceways, enclosures, etc. from all other systems. Separate
vertical switchboard section required when emergency source serves multiple systems (NEC
700.10(B))
⢠Article 701: Legally Required Standby Systems
â EPS capacity shall be capable of supplying all legally required standby loads intended to operate
simultaneously (NEC 701.4)
â Requires automatic transfer switches (NEC 701.12(A)
â Transfer switches require load shedding capability if generator capacity is not sized to supply all
connected loads at once (NEC 701.4)
⢠Article 702: Optional Standby Systems
â Permanent installations require manual or automatic transfer switches (NEC 702.5)
â Transfer switches require load shedding capability if generator capacity is not sized to supply all
connected loads at once (NEC 702.4(B)(2))
18. How Loads Are Classified
⢠Requirements for loads classified as emergency and legally required
standby are generally defined by the AHJ and adopted codes.
⢠IBC 2702.2 references other IBC sections for emergency and legally
required standby loads. Common applications below.
â Emergency Loads
⢠Voice/Alarm Communications Systems in Group A Occupancies and Covered and Open Mall
Buildings (IBC 907.5.2.2.4 & 402.7.3)
⢠Exit Signs and Means of Egress Illumination (IBC 1011.6.3 & 1006.3)
⢠High-Rise Buildings (IBC 403.4.9)
â Elevator Car Lighting
â Voice/Alarm Communications Systems
â Automatic Fire Detection Systems
â Fire Alarm Systems
â Electrically powered fire pumps
â Legally Required Standby Loads
⢠Smoke Control Systems (IBC 909.11)
⢠Accessible means of egress elevators (IBC 1007.4)
⢠High-Rise Buildings (IBC 403.4.8)
â Power and Lighting for the Fire Command Center
â Ventilation and automatic Fire detection equipment for smoke proof enclosures.
â Elevators
19. Local AHJ Considerations
⢠Some AHJs amend codes and standards
before adopting them. This may result in load
classifications varying from region to region.
⢠Example:
â Southern Nevada AHJs amended the first
paragraph of NEC 700.1; scope to include
specific references to loads that may be
connected to the emergency system. Many of
these loads would be considered Legally
Required Standby in other regions.
21. System Design Sequence
1
⢠Determine/Estimate Total Load of proposed system
⢠Determine Load that is Required by Code to be on
2
⢠Plan for anticipated Run Time for the system
3
⢠If the System is an emergency system, will it be used for Utility
Peak shaving program
4
⢠Review Fuel Source availability, Quantity of Generators, and
Redundancy
5
⢠Determine appropriate Accessories for the system
22. ⢠Running kVA
â Calculated Electrical Loads + Metered
Electrical Loads
⢠Starting kVA
â What is the biggest starting kVA block (i.e. a
chiller system)
⢠Special considerations
â High harmonic content
â Intermittent starting
Generator Selection and Sizing
23. Metered Electrical Loads
NEC 220.87 (125% Rule)
⢠NEC requires that the existing loads are
metered to determine the âmaximum
demand continuously recorded over a
minimum 30-day period,â and then use
125% of that number as the âexistingâ
load for the system.
⢠Maximum demand is measured as the
average power over a 15-minute period.
24. Generator Ratings
⢠Standby Power:
â Maximum output is available for non-programmed
power outages.
â Average demand during outages should not exceed
continuous rating of generator.
â Typical usage of 200 hrs/yr; max expected usage of
500 hrs/yr.
⢠Prime Power:
â De-rated capacity, typically 10% reduction from
standby power rating.
â Maximum output available for varying loads for all
outages.
â Average demand should not exceed continuous
rating.
⢠Continuous Power
â Maximum output available at all times.
â De-rated capacity, typically a 15% reduction from
prime power ratings.
25. Generator De-Rating
â A prime generator is essentially a standby generator de-rated
plus additional accessories. The same generator de-rated
again is a continuous duty.
â 2000 kW standby = 1825 kW prime = 1600 kW continuous
â But with prime and continuous ratings, everything is bigger:
generators, space to accommodate, air intake requirements,
fuel consumption, but with less capacity.
26. Warranty Issues
⢠What does all of this have to do with
my warranty?
â Standard warranty for generators are
defined by run hours and length of time,
and typically include the rating of the
generator.
â Warranties generally do not include:
⢠Use of standby generators in prime
applications
⢠Use of blended fuels such as a natural
gas/diesel mixture
⢠Excessive overloading of the generator.
27. Generator Tier Ratings
Tier 2 Tier 4
Emergency Systems can be tier 2 when
used for Emergency Purposes only.
Emergency Systems must be tier 4 if
they also participate in a Peak Shaving
program that the utility uses for financial
gain (they can sell power for more than
you get paid).
Can remain tier 2 even if they join a
âemergency demand responseâ program
offered by the Utility Provider.
Tier 4 requires additional capital
investments and additional equipment.
Maximum Run time, testing time, and
demand response time criteria.
Per Todayâs rules - A new Tier 2
generator installed today CANNOT ever
be modified to be a Tier 4 Generator.
29. Types of Generators
⢠Portable
⢠Stationary Standby
â Diesel
â Liquid Propane
â Natural Gas
â Dual Fuel.
30. Fuel Considerations
⢠On-site fuel storage NEC 700.12(B)(3)
⢠Dual Fuel (or Bi-fuel)
â Can provide an extended runtime.
â Usually an aftermarket retrofit to a diesel generator.
Although, some manufacturers do have a factory
assembled and tested bi-fuel systems.
â Typically achieves a 40%/60% split.
⢠Fuel Polisher
â Diesel fuel will foul when stored more than 3 to 6
months without conditioning or detergent additives.
â This presents an issue for large on-site fuel storage
systems.
31. Location
⢠Indoor
â EPS shall be located in a dedicated room with 2-
hour fire resistance rating (NFPA 110 Chapter
7.2.1)
â EPSS equipment may be located in EPS room
(NFPA 110 Chapter 7.2.1.2)
⢠Outdoor
â Requires weatherproof enclosure (NFPA 110
Chapter 7.2.2.1)
â EPSS equipment may be located within the EPS
enclosure (NFPA 110 Chapter 7.2.2.3)
32. How many generators?
⢠Several reasons to consider more than
one generator.
â Physical Space.
â Redundancy/Resilience.
â Phased expansion.
33. Redundancy
⢠Data centers, hospitals, large-scale
hospitality resorts, municipal command
centers, etc.
⢠N+1, 2N
⢠Multiple priorities
⢠Real-time demand load management
34. Generator Ratings.
⢠Examine the system voltage. Is the primary
distribution routed at low voltage (600 V or
less) or medium voltage (more than 600 V,
but less than 38 kV)?
⢠208 V, 3-Phase System; 900 kW/1125 kVA
⢠240 V, 1-Phase System; 600 kW/750 kVA
⢠480 V, 3-Phase System; 2000 kW/2500 kVA
⢠13 kV, 3-Phase System
38. Generator Assembly
⢠Load Bank Testing
⢠Sound Testing
⢠Emissions Testing
⢠Accessory Review and Testing
39. Generator Load Bank Test
⢠Resistive Load Bank Test
â Load Bank is set to the generator Rated
Power Factor (0.8 PF)
â Commonly a factory test
⢠Reactive Load Bank Test (1.0 PF)
⢠Only allowed in field IF reactive was done in
factory (NFPA 110)
40. Generator Load Bank Test
⢠NFPA 110 minimum load bank test.
⢠2 hours at full load.
⢠5 minute cool down.
⢠Full rating block load to start the second
half. Take a wave capture of the unit
performance during the block load.
⢠2-hour run at full load.
⢠Recordings every 15 minutes for the
duration of the test.
41. ⢠Sound Testing
â Sound criteria requirements at certain locations
⢠Air Performance
â Sufficient air to the generator engines
â Emissions too close to an intake
â Air emissions testing
⢠Generator Accessories
â Battery charger goes back on with generator
power
â Jacket heater turns off when unit is running
42. Alarm Annunciation
⢠Alarms annunciate
at Unit Mounted
Controller (CV)
⢠Alarms Annunciate
at Remote
Annunciator (RA)
⢠Doesnât address
parallel system
alarms!
⢠Per NFPA 110 and
NFPA 99
Alarm CV S RA
(a) Overcrank X X X
(b) Low Water Temp. <70
o
F (21
o
C) X X
(c) High Engine Temp Prealarm X X
(d) High Engine Temperature X X X
(e) Low Lube Oil Pressure Prealarm X X
(f) Low Lube Oil Pressure X X X
(g) Overspeed X X X
(h) Low Fuel Main Tank (@ 48 hrs. fuel remaining) X X
(i) Low coolant level X X
(j) EPS Supplying Load X
(k) Control or Test Switch Not in Auto. Position X X
(l) High Battery Voltage X
(m) Low cranking voltage X X
(n) Low Voltage in Battery X
(o) Battery charger ac failure X
(p) Lamp Test X
(q) Audible Alarm Silencing Switch X
(r) Low Starting Air Pressure X
(s) Low Starting Hydraulic Pressure X
(t) Air Shutdown Damper when used X X X
(u) Remote Emergency Stop X
(v) Day tank Hi-low Alarm X X
(w) Leak detection inner cavity of skid mount fuel tank X X
(x) Remote Radiator Breaker Position X X
KEY:
CV Control panel-mtd. visual indication
RA Remote Audible
S Shutdown of EPS
X Required
43. Alarm Annunciation
⢠Most alarms can be simulated at the
generator, and verified at the annunciator.
⢠Must include audible and visual
annunciation at remote location.
⢠Recommend adding parallel switchgear
(EPSS) alarms where used.
⢠Other codes supplement this too, such as
high-rise requirements in NFPA 101.
44. Fuel System Performance
⢠Verify each day tank if used can call for
fuel individually and generators are
getting correct amount of fuel.
⢠Verify low fuel alarm is set to the
appropriate point and works.
45. Low fuel Settings
⢠Required Generator
Class = Required Low
Fuel Setting
⢠Class 48 = 48 hrs of fuel
⢠Class 10 = 10 hrs of fuel
⢠48 hrs x Generator
Hourly Consumption =
Low Fuel Level Alarm
Low Fuel Alarm
46. Parallel Switchgear Commissioning
⢠Multiple Generators Operating as a
system soâŚ
⢠Complete System operation must be
checked!
⢠Manufacturers can use PLC inputs or
potentially PC overrides to âsimulateâ
system loads.
47. Parallel Switchgear Functions
⢠Load Shed â Function where Transfer
Switches are assigned a different priority
â Essential System would be a 1.
â Equipment loads may be a 2.
â Non-essential may be a 3.
⢠Usually will relate to the number of
generators on the bus.
48. Parallel Switchgear Load Shed
Essential System Load Priority Schedule
ATS NUMBER BRANCH BYPASS VOLT. Pri. 100 Priority 200
ISOLATION LOAD SUB No. L.S. T.I. LOAD
ATS-CHCEP Critical Y 480 26.7
ATS-FP Fire Pump Y 480 75
ATS-CR1 Critical Y 480 283.5
ATS-CR2 Critical Y 480 129
ATS-LS1 Life Safety Y 480 220.6
ATS-EQ2 Equipment Y 480 119.2
ATS-XRAY Equipment Y 480 201 Y Y
ATS-EQ1 Equipment Y 480 202 Y Y
ATS-EQHCEPA Equipment Y 480 203 Y Y
ATS-EQHCEPB Equipment Y 480 204 Y Y 213
ATS-EQHCEPC Equipment Y 480 205 Y Y 1082
ATS-N1 Non-Essential Y 480 206 Y Y 143.8
Total (KVA) 854 Total (KVA) 1439
Total (KW @ 0.9 P.F.) 768.6 Total (KW @ 0.9 P.F.) 1295
Total Priority 100 + 200 Loads (KW) 2063.9
Capacity 3000
49. Parallel Switchgear Commissioning
Sample Switchgear Commissioning Document (Partial)
Mode: Bus Optimization Off / Generator Demand Off (with Amp Generator)
Operation: Generators will load each priority level as a block. The quantity of priority
Blocks connected is the same as the priority block connected. If a generator fails,
the block associated with that generator will shed.
ďąScenario 1: Startup. Turn off Normal power, system should call for start. Priority 1
loads will transfer within 10 seconds. Priority 2 will transfer after their associated
time delays.
ďąScenario 2: Second Generator Failure â Priority two Block Loads shed. Turn
Second Gen back on and all Priority 2 loads add in one block.
ďąScenario 3: Gen 1,2 Operating. System Bus overload of 105 % over two
generators simulated by a 4-20ma generator. (3000 kW * 1.05 = 3150 kW); Priority 2
loads should shed in descending priority & sub priority order.
50. Parallel Switchgear Functions
⢠Other features to test
â Generator Demand Mode (Used to turn off
Generators when demand is low enough to
warrant it.
⢠Bus under-frequency
â (Sheds loads and locks out!)
⢠Emergency stop buttons
⢠Remote ATS control (where applicable)
51. Learning Summary
Researched
Codes
⢠NEC
⢠NFPA 110, 99
⢠IBC
System
Capacity and
Use
⢠Demand and
Calculated Loads
⢠Tier Ratings
Select a System
⢠Fuel Source
⢠Location
⢠Parallel?
⢠Redundancy
Installation and
Commissioning
⢠Load Bank
⢠Annunciation
⢠System Testing
53. Robert R. Jones Jr., PE, LEED AP,
JBA Consulting Engineers,
Las Vegas, Nev.
James Ferris, PE,
TLC Engineering for Architecture,
Orlando, Fla.
Moderator: Jack Smith,
Consulting-Specifying Engineer and Pure Power,
CFE Media, LLC
Presenters:
55. Webcasts and Research
⢠Critical Power: Standby Versus
Emergency Power Systems
⢠Critical Power: Standby Power for Mission
Critical Facilities
⢠2013 Electrical/Power Research Study