2011 AACEi Annual Meeting
                           Anaheim, CA, June 2011




                                 Chris Carson, PSP
                                       35191
                                      Raf Dua


Improving Industry Cross-Pollination by Classification of Schedule Types
                                 January 15, 2010




                         2011 AACEi Annual Meeting                               1
    “Improving Industry Cross-Pollination by Classification of Schedule Types”
                      By Chris Carson, PSP, and Raf Dua
Table of Contents

List of Tables                                                                  iii

Abstract                                                                        4

Introduction                                                                    4

Overview                                                                        5

Scheduling Component Determinants                                               6

The Matrix Concept                                                              9

Compile Matrix into Summaries                                                  10

Identify types of schedules                                                    10
Conclusion                                                                     12
Bibliography                                                                   13




                                                ii




                                2011 AACEi Annual Meeting                               2
           “Improving Industry Cross-Pollination by Classification of Schedule Types”
                             By Chris Carson, PSP, and Raf Dua
List of Tables

Table 1, “Schedule Type Matrix”                                                14




                              2011 AACEi Annual Meeting                               3
         “Improving Industry Cross-Pollination by Classification of Schedule Types”
                           By Chris Carson, PSP, and Raf Dua
Abstract


One scheduler says resource leveling is vital to producing a reasonable schedule, another says no one
uses resources, let alone leveling. Scheduling discussions get passionate yet often schedulers in
different industries do not seem to speak the same language. Some industries are naturally far ahead
of others in the use of specific scheduling components, such as resources, EVM, or Risk
Management, and those leaders are often the source for innovation in the use of those components.
This paper will study how industries use scheduling, attempt to categorize industry scheduling by
common needs and component solutions, and provide an understanding of the differences between
industry schedule use that should allow for better communications and increase the opportunity to
enable innovation from each industry to improve scheduling in all industries.



Introduction


Professional schedulers, those who use scheduling to enhance and improve project management
actions, often lose themselves in their own world of planning and scheduling. They work with other
schedulers who are in the same industry or even the same segment of the same industry, understand
their unique needs and even develop lingo and buzz words that are specific to their segment. The
use of scheduling is fairly standardized, although there is variation in competence and general use of
schedules. Understanding how each segment of the scheduling world is different can help categorize
types of schedules.
Often what seems to be innovative scheduling for one industry is a common practice in another
industry. This observation shows the way to improve scheduling across all industries if the common
practices in one industry that seem innovative in another industry could be shared with other
industries that might be able to use those common practices if they only understood them. This is
typical of the way that Earned Value Management (EVM) has been absorbed into commercial
construction; at one time, EVM was strictly used in defense and other industries. Then contractors
who performed both military defense and commercial construction used the techniques in military
projects and soon realized that there were benefits from the use of EVM in the commercial
construction field.
Currently, there is no scheduling –wide categorization of types of scheduling so there is no simple
way for one industry to view new best practices and incorporate those into their routine scheduling
tasks. In most cases industries do not even know what is being used in other industries with success.
Without the knowledge of what is available and used professionally, industry schedulers will not
have the opportunity or inclination to experiment with new techniques.
The Association for the Advancement of Cost Engineering international (“AACEi”) publication,
Total Cost Management Framework, A Process for Applying the Skills and Knowledge of Cost
Engineering,[1] clearly encompasses all types of industries, yet does not categorize those type of
industries requiring different types of scheduling practices.
The Total Cost Management Framework defines the “strategic assets” of an enterprise as
“shorthand for any unique physical or intellectual property that is of long term or ongoing value to
                                     2011 AACEi Annual Meeting                                           4
           “Improving Industry Cross-Pollination by Classification of Schedule Types”
                                 By Chris Carson, PSP, and Raf Dua
the enterprise” and notes that “the asset may be a building, an industrial plant, a software program,
or a stage production.”
Compiling a system of categorization of schedule types would help to allow the comparison of
similar schedule types, and the more definition that can be applied to each type, the more likely that
improvements that would be useful will be identified and incorporated.
As schedulers recognize that there are scheduling techniques being used successfully in other
industries, there should be an increased demand for understanding the taxonomy of scheduling types.
This is an area where the leading industry associations, like AACE International and the PMI
Scheduling Community of Practice, should encourage studies and opportunities for cross-pollination
between different industries and sectors of industries.


Overview – Rationale for Paper


The authors come from slightly different sectors of the construction industry, with Mr. Dua working
in Australian and Far East manufacturing and construction projects that require extensive planning
and monitoring of resources for us in planning Design-Build-Operate-Maintain type projects. He
has developed his own ADM software, Micro Planner Expert, in an effort to provide the software
flexibility necessary to handle the demands on resource driven scheduling. Mr. Carson works in the
United States primarily in commercial and military projects that require claims avoidance and
subcontractor management efforts. His work primarily involves use of Oracle/Primavera schedule
software and to a much lesser extent, some Microsoft Project software. Both provide risk
assessment and monitoring as part of their planning services, and both work as consultants for both
owners and contractors in their fields. And both require well planned networks that are highly
technical and accurate so that the network calculations will provide reasonable and legitimate values
of total float and identifications of critical and near critical path activities.
Both authors are involved in the industry associations related to planning and scheduling like
AACEi, and as such, have deep exposure to other planners and schedulers in many different
segments of or industries. We have found that communications among all these different planners
and schedulers can often be difficult mostly due to the emphasis on various components used in the
different industries.
Just the differences between Mr. Dua’s extensive involvement in individual manpower resources and
Mr. Carson’s involvement in more crew-related resources highlight the disparities that result in
misunderstandings about scheduling best practices and needs. With the proliferation of more and
more social networks and well managed forums that are related to project controls, there are greater
numbers of schedulers from all sectors of and industries that are exposed to each other. Judging
from the discussions, it is clear that some of the disputes about best practices actually revolve around
the use of the schedules more than the quality of the schedules.
Review of the forums and groups shows how one scheduler will note that resource leveling is not
used in his/her industry, and another scheduler showing concern that without good resource leveling
it is not possible to accurately plan and schedule a project of any kind. Or, one industry scheduler
feels that the attempt to cost load a schedule and use earned value to manage a project reduces the
time management component’s usefulness of the schedule, where another industry scheduler cannot
believe that anyone could plan and schedule a project without using earned value.
The authors believe that the real value in the recognition of these differences is the opportunity to
cross-pollinate industries with scheduling component expertise. If one sector of an industry is using
                               2011 AACEi Annual Meeting                                                   5
          “Improving Industry Cross-Pollination by Classification of Schedule Types”
                            By Chris Carson, PSP, and Raf Dua
individual labor resource components effectively to plan and manage a project, learning from that
sector in order to bring better individual labor resource components into another sector will enable
this other sector to improve the plan.
This is also true with sectors where high penalty risk and legal ramifications of failure promote
higher levels of technical development of the CPM network. This higher level of network
development, if absorbed by other industries where the risks are not as high, will still improve the
value of the output statistics and metrics used to analyze the schedule progress.


Scheduling Component Determinants That Affect Types of Schedules


After numerous discussions and brainstorming, as well as searching for studies or academic papers
that might provide a taxonomy for schedule types, we determined that this would be a useful topic
for an academic study and could be very useful to scheduling associations attempting to provide
value to their membership. That value would arise from the cross-pollination of the technical
scheduling components used in various industries and segments of industries. We call these
scheduling components “determinants” for types of schedules.
From our research and brainstorming, there appear to be approximately nine major schedule
technique and component determinants that define scheduling efforts:

   1.   Level of detail of the schedule
   2.   Frequency of schedule updates
   3.   Resource data and techniques used
   4.   Activity level data collected in updates
   5.   Project participants (categories monitored in schedules)
   6.   Scheduling components
   7.   Drivers for update monitoring and analysis
   8.   Primary project management constraint
   9.   Schedule accuracy

The level of detail in the schedule is often a function of how the schedule is developed; bottom up
schedule development generally experiences a higher level of detail than a top down development.
However the purpose for the chosen level of detail is usually based on the needs; will it be used for
reporting to senior management, managing field and/or engineering resources, general project
overview, or for management of contractors and resources? When a schedule is designed to be used
for reporting, the level of detail is generally fairly low since only enough monitoring is required to
provide an executive summary. When the schedule is used for managing engineering time, the level
of detail must extend to the identification of individual deliverables and the work packages necessary
to provide those deliverables; this will require much more detail.
The frequency of updates is another determinant that drives the type of schedule. For projects such
as engineering projects, software design, or plant maintenance and shutdown, monitoring and
controlling the manpower tends to require hourly level monitoring. The schedule must be
maintained in sufficient detail that updates cannot wait for a week or month. For most commercial
construction projects, if they are managing by the schedule, they need weekly updates, and if they
are managing in more of an overview approach, or allowing the superintendent to provide the short
interim planning, they are happy with monthly updates.
                               2011 AACEi Annual Meeting                                                 6
          “Improving Industry Cross-Pollination by Classification of Schedule Types”
                            By Chris Carson, PSP, and Raf Dua
The use of resource planning and monitoring is one of the areas which has a wide variance among
schedulers, ranging from projects with no resource loading or monitoring to projects where
managing individuals or crews, or quantities and costs, are vital. In projects where each resource is
reasonably equivalent, such as engineering design or piping installers, and the resource is a main
driver of the costs, managing resource data down to the individual or role is necessary to provide the
monitoring and control. But in industries where the labor relies on a foreman and numerous levels
of labor, helper, journeyman, it can be more efficient and effective to manage resources at a crew
level. Crew level resources are not very hard to identify as well. In his paper published in the 2007
AACE International Transactions, “Artificial Resource Loading for Schedule Review” [2], Al Kuhn,
PSP, addresses a way for a schedule reviewer to load crews into a schedule in an effort to evaluate
the network logic and activity durations. Notably, the examples in the paper are from commercial
construction where the labor force is varied in their individual competencies, so crew resource
monitoring works well, but role based individual resource monitoring is very difficult to do because
the data is generally not available.
Another division in industries and sectors of industries involves the use of resource leveling, and this
breaks down into labor and equipment leveling in general. Industries that use large amounts of
similar role resources consider it vital to run resource leveling heuristics to attempt to smooth out
resource usage, or to model limitations in availability of certain resources. This effort cannot be
used in industries or sectors of industries where the technical schedule must remain such that the
network calculations are accurate, and resource leveling will provide float values that do not identify
true critical paths. These sectors or industries typically use CPM calculations of delay to assess
damages for late completion.
Sometimes industry schedule practices can be described by the activity level data collected during
the monitoring phase, if actual resources are recorded and compared to planned resources, it is likely
that the industry or sector deals with large amounts of labor resources or small amounts of labor but
lesser equipment, subcontractors, or materials resources. Identifying whether updates require actual
labor, equipment hour, or materials installed will shift what type of scheduling is performed.
Whether the schedule is updated by time remaining or percent complete helps determine whether the
schedule is driven more by time or costs, or in the case of some construction sectors, both are used
but kept separate by delinking the two components in the scheduling software.
Another way that separates types of schedules is the issue of the project participants in terms of cost
drivers; is it only labor such as engineering, or labor, materials, and equipment such as bridge work,
or labor, materials, equipments, and subcontractors such as commercial or military construction. If
the schedule does not need to monitor subcontractors, that schedule can focus much more on
resource consumption because all resources are under the control of the project management team
and the schedule will be used for planning and controlling the expenditure of those resources. When
subcontractors are involved in the project, the risk of performance is generally carried by those
subcontractors and the master schedule does not need to address monitoring of the subcontractor
resources, except as it affects project performance and delay.
As one examines scheduling components, the use of them in a schedule break down into four major
areas as the authors see it; labor resources, costs resources, earned value, and how the schedule
correlates with project budget. Obviously these could all be interconnected; however, schedules are
very different when used to control labor than when used to control costs. Labor resources evolve
from resource loading to resource leveling to resource driving and then to resource tracking. The
term resources mean many things to many people, from individual engineers to large pieces of
equipment to simply costs of installation.

                               2011 AACEi Annual Meeting                                                   7
          “Improving Industry Cross-Pollination by Classification of Schedule Types”
                            By Chris Carson, PSP, and Raf Dua
Earned Value Management (“EVM”) has been around for years, and it is one of the technical
scheduling components that are migrating from those industries, such as defense, that were early
serious users of the process, to commercial construction, where the need evolved as schedule
analysts needed more tools to monitor projects. Within EVM systems, the two major divisions occur
between costs and labor resources, and to a much lesser extent, materials quantities. Using costs
assigned to activities, it is possible to compare what has been earned to date with what should have
been earned to date based on the original schedule. This is also true of hours earned which can be
compared to what hours should have been earned to date based on the plan. The use of EVM
systems helps categorize types of schedules at a technical level.
 Some schedules are correlated with the project budget while many are not correlated with any
benchmark for comparison. Within those industries that use cost control accounts and Work
Breakdown Structures (“WBS”) to monitor expected cost overruns, often they have a greater
maturity in the correlation between cost and time. This is a different approach from many other
industries who do not correlate cost and time, since the WBS in those mature industries is elaborated
to the level of deliverables or work packages, and those are linked to the cost control accounts,
providing accounting metrics for review and monitoring.
One of the prime determinants for the type of schedule is that of the driving rationale for update
monitoring and analysis. The drivers can range from critical path slippage control to milestone
monitoring to the need to ensure that all activities are progressing according to their plan. There
may be incentives or penalties based on individual milestones, but rarely are there any penalties for
individual activity slippage.
Schedules whose primary drivers are critical path slippage generally are used with projects subject to
damages from penalties for late completion. The range of schedule types purposes include this
protection from damages, the need for re-baselining the schedule for monitoring, protection against
cost overruns due to prolongation of the project, or those schedules where the milestone or
completion dates are allowed to slip without penalty. The existence of penalties creates a culture
where claims prevail, as each party is both protecting itself and documenting the other party’s
failings. As these claims are litigated, case law has developed and established principles based on
previous rulings, and the need to design schedules and manage schedule analysis according to these
overarching legal principles becomes a prominent drive for schedule documentation. Near critical
path monitoring drivers for schedules are similar to critical path drivers, but generally they are
elevated to a higher purpose with multiple contractual milestones or the need to identify and respond
to mid-period critical path shifts. Non-critical path slippage is an important driver for scheduling
when cost overruns due to performance impact the project such as with ship building and aerospace
where huge cost overruns must be identified and monitored. Government demand for monitoring
systems and documentation help push those industries towards similar scheduling types. Where
resources can cause large problems due to lowered production rates and stacking of resources,
schedules tend to focus on resource management. This can even be a secondary purpose for
schedules in industries such as commercial and military construction where disruption can cause
large cost overruns.
Some industries are focused on making sure that each activity is completed on time using the
planned resources, or at least evaluating those activities such as is done in forensic analysis cases,
while others only care about activity slippage as it relates to trade stacking or other disruption issues.
So the major division related to activity slippage monitoring and reporting is the question of the
severity of the risk of activity slippage. And then some industries have fully embraced the use of
EVM for monitoring and controlling, sometimes to the detriment of the critical path analysis.

                               2011 AACEi Annual Meeting                                                     8
          “Improving Industry Cross-Pollination by Classification of Schedule Types”
                            By Chris Carson, PSP, and Raf Dua
One of the other prime schedule type determinants is the issue of which of the project management
“triple” constraints is most important to the project. While every owner will insist that everything is
important, that is rarely true. The major project management constraints include scope, time, cost,
(often called “the triple constraints”) and sometimes adding quality and/or risk. Most projects have
one prime driver; in fact most contractors have a natural inclination to focus on one of the
constraints more than others, no matter what the owner’s point of view. The authors believe that the
most successful and simplest projects occur when the owner and the contractor have an alignment of
these constraints. A quality driven contractor will be more at risk of failure when building a project
for a cost oriented owner. These constraints are an important schedule type determinant.
The last determinant that the authors believe separate schedules into common types is that of the
accuracy of the schedule; meaning the smallest time period used for planning and updates. Very
broad long-term program overview schedules may only be accurate to the nearest year, where more
commonly schedules are accurate to a low level of accuracy at the monthly range, and some projects
take the accuracy down to the day or even hour. A maintenance and shutdown schedule for a coal
fired power plant might need to plan to the nearest hour so they can cycle crews in as soon as
another crew is complete. A commercial or military construction project is likely accurate to the
nearest week, but may be monitored to a daily plan. A forensic schedule is likely trying to identify
the cause of delay in order to assign responsibility to assess liability, so that schedule may likely plan
to be accurate to the nearest day. And a schedule whose output is primarily a monthly invoice may
only be accurate to that level. The accuracy should be a good determinant to categorize schedule
types.

The Matrix Concept

In an effort to develop categories of schedule types, the authors developed a Schedule Type Matrix,
designed to facilitate the ordering of scheduling into appropriate types based on how the various
industries and sectors of industries use the schedule technique and component determinants.
The process developed included identifying a number of different industries and sectors of industries
and evaluating those sectors as to how they use any of the schedule component determinants. The
industries chosen included:
    • Commercial construction
    • Military construction
    • Hospital construction
    • Power plant construction
    • Maintenance and shutdown of factories and plants
    • Defense projects
    • Oil and gas projects
    • Manufacturing
    • Energy projects
    • Shipbuilding and aerospace construction
    • Pharmaceutical projects
    • Software development projects
    • Information technology projects
    • Engineering projects
    • Transportation construction
    • High-rise construction
                                     2011 AACEi Annual Meeting                                               9
          “Improving Industry Cross-Pollination by Classification of Schedule Types”
                                 By Chris Carson, PSP, and Raf Dua
•   Wide-rise housing construction
   •   Financial projects
   •   Forensic scheduling projects

The construction projects included all types of project delivery; design-bid-build, multi-prime
contracting, EPC, design-build, design-build-operate, design-build-operate-maintain, and At Risk
CM. Of course, once you include other industries outside of construction, the project delivery
methods
It is noteworthy that the authors found that some of the types of projects operate with different
scheduling types at different times during the life cycle of the project. For instance, pharmaceutical
projects may use critical chain methodology early in the pre-project, research and regulatory stages,
with different levels of CPM methodology detail between FEL stage and detailed design,
construction, commissioning, and qualifications. The pharmaceutical regulatory scheduling is
simply milestones, while they use EVM for productivity metrics in engineering and construction
phases.
After the informal research, interviews, and study involved in the development of this topic, the
authors realize that developing a schedule type taxonomy will likely require a formal study with
thousands of schedulers involved, but that is beyond the scope of this paper.
There is clearly not complete agreement as to what schedule type determinants are predominant in
all industries and sectors, mainly due to the complexity and variance in scheduling techniques.
However, the authors have attempted to pull together what they believe is an accurate view of those
industries and sectors of industries.

Compile Matrix Markers into Summaries

After compiling industry and sectors of industries into categories of schedule technique and
component determinants and mapping those industries, the authors combined similar use of the
schedule technique and component determinants so as to cluster industries and sectors of industries.
The result of that correlation and combination is the Schedule Type Matrix.

Identify types of schedules based on schedule components

Based on the effort in developing the Schedule Type Matrix, the authors believe that schedule types
fall into eleven broad categories. These categories are:

   •   Technically-oriented scheduling
   •   Complex phasing-oriented scheduling
   •   Recovery-oriented scheduling
   •   Large resource-oriented scheduling
   •   EV-oriented scheduling
   •   Rolling wave oriented scheduling
   •   Timesheet-oriented or small resource-oriented scheduling
   •   Location-oriented scheduling
   •   Program-oriented overview scheduling
   •   Financial management oriented scheduling
   •   Forensic scheduling
                                  2011 AACEi Annual Meeting                                              10
         “Improving Industry Cross-Pollination by Classification of Schedule Types”
                              By Chris Carson, PSP, and Raf Dua
Technically-oriented scheduling is used where litigation results in case law that forces highly
technical knowledge to be used in the schedule development and maintenance so that careful CPM
analysis of delay and disruption are supported. The risk of time related disputes that result in claims
drives the preparation, review and approvals of schedules to technical extremes so that delays are
identified and responsibility for delay assessed. The use of resources in this schedule type is limited
to macro level, mostly crew resources, and used to verify both duration calculations and resource
planned usage to form a benchmark for analysis of delays, and more importantly, disruption in the
form of labor inefficiencies. Specifications often require resource loading with reporting of actual
resource usage. Resource leveling is rarely used in this type. Examples of this type of scheduling
include most commercial and military construction.
Complex phasing-oriented schedule is used in projects where the location coordination and logistics
of movement of resources around the project, and the component assembly of systems requires
careful use of scheduling. This type may also carry needs of technically oriented scheduling. These
projects often combine with technically-oriented and large resource-oriented scheduling. Examples
of this type of scheduling include hospital construction and renovation as well as process plants.
Recovery-oriented scheduling types of projects evolved due to the fact that costs of each day of
delay could be millions of dollars or abject project failure - the main thing that matters is to crunch
the schedule to meet the original planned completion; mitigation of delay is the main emphasis. The
type often requires some emphasis on the capture of full scope of work in order to complete as much
work as possible within the rigid project time span, and the use of rapid response teams or involved
mitigation schedules. Often the project participants include multiple parties with interrelationships
that require monitoring to avoid disruption. Examples of this type of scheduling include airport
renovation and shut down and maintenance of power plants.
Large resource-oriented scheduling is another type of scheduling that crosses several industries or
sectors of industries and sometimes is combined with other types. It is used where the huge
resources, mostly labor, must be planned and managed at a much greater level of detail than
"normal" – labor resources are so large that they drive production and the system must plan and
manage those large groups of resources. Project participants are mostly labor workers of all trades
and competencies. Examples of this type of schedule use include defense, some phases of oil and
gas construction, and manufacturing.
Earned Value-oriented scheduling becomes a separate category of schedule types due to the primary
management effort; the use of Earned Value metrics. These projects are focused on budgets and
number crunching to check project status. The need for identification and management of the
critical path is not as severe as the technically-oriented scheduling but completion date slippage must
be monitored and documented. Examples of this type of scheduling include large energy projects,
ship and plane building, some defense, and pharmaceutical projects.
Rolling wave oriented scheduling are often those projects where project cycles are very long,
potentially years from approval to final testing, and different phases of the project have vastly
different levels of schedules due to the available information. The ability to plan in detail for work
to be done perhaps years later drives the type to the use of rolling wave scheduling methodology
where the schedule is planned at a high level, typically using milestone and summary master
schedules, and the work is managed by developing detailed schedules for short periods of current
time. Individual project phases may fall into other types of scheduling, such as Earned Value, or
other methodologies such as Critical Chain. Examples include pharmaceuticals, research and
development.

                               2011 AACEi Annual Meeting                                                  11
          “Improving Industry Cross-Pollination by Classification of Schedule Types”
                            By Chris Carson, PSP, and Raf Dua
Timesheet-oriented or maybe more accurately labeled small resource-oriented scheduling occurs
where schedules are used to manage personnel and often capture actual costs - it's all about
managing individuals. Examples include Information Technology projects as well as software
development and engineering.
Location-oriented scheduling is defined by many repetitive fragnets, with logic ties in CPM
scheduling made to sequence work within specific locations of the project. This scheduling type is
popular for use with linear scheduling, often using velocity diagrams, and sometimes combines
velocity diagrams and CPM scheduling. Examples of this schedule type include transportation-type
projects such as utilities, roadways, bridges, and facilities-type such as high-rise office buildings and
housing or condominiums.
Program-oriented overview scheduling is represented by project conditions where schedules have
both resource and delivery constraints, with budgets that span across years while new sections of the
development are opened and completed. These schedules do not need a deep level of detail since the
work is generally repetitive, but sometimes uses very detailed CPM scheduling. Completion dates
are not cast in stone due to the overview nature of the product, so critical path slippage is often
allowed. Examples include the “wide-rise” housing industry where programs typically run over
decades of development as well as general program master schedule monitoring.
Financial management oriented-scheduling is a schedule type that provides schedules used to plan
and monitor business acquisitions, restructuring, and spin offs of divisions. CPM methodology is
not very important; schedule used more to direct wide range of participants, but requires no real
monitoring of Critical Path or float.
Forensic scheduling evolved since schedules are used to determine causality and to identify
responsibility in order to assess liability and resolve time related delay and disruption disputes. It is
most often used in conjunction with technically-oriented, complex phasing-oriented, large resource-
oriented and location-oriented schedule types. Examples include dispute resolution and claims
analysis projects in many industries.


Conclusion


Although we are all working on improving the practices of CPM scheduling, it is difficult sometimes
to communicate across the whole realm of schedule types, so we need to develop a taxonomy to help
identify commonality among schedule types. This will become more and more important as
schedulers continue to look for innovative ways to improve efficiency for the scheduling process.
Identifying the schedule types that are at the forefront of new and established professional
techniques will allow industry associations to help promote those schedule techniques and
component determinants predominant in specialized industries to all industries, providing cross-
pollination of industries with schedule techniques.




                               2011 AACEi Annual Meeting                                                    12
          “Improving Industry Cross-Pollination by Classification of Schedule Types”
                            By Chris Carson, PSP, and Raf Dua
Bibliography



No.       Description

1         Hollmann, J.K., PE CCE
          Copyright 2006
          Total Cost Management Framework, A Process for Applying the Skills and
          Knowledge of Cost Engineering
          First Edition
          AACE International, Morgantown, WV

2         Kuhn, A., PSP
          2007
          Artificial Resource Loading for Schedule Review
          2007 AACE International Transactions
          AACE International, Morgantown, WV




                           2011 AACEi Annual Meeting                               13
      “Improving Industry Cross-Pollination by Classification of Schedule Types”
                        By Chris Carson, PSP, and Raf Dua
Schedule Type Matrix                                                               Schedule Types - Crosses Industry or Segments of Industry
                                                                                                  Large         Earned        Rolling      Small   Location -                         Financial
  Schedule Technique & Component Determinants           Technical Phasing Recovery                                                                            Program                               Forensic
                                                                                                 Resource        Value        Wave        Resource   Linear                           Mgmnt.
                                                                                                                 Energy,                                                                              Dispute
                                                                       Hospitals,      Plant      Defense,                                 IT, Software Transportation,   Wide-Rise   Also called
                                                        Commercial                                              Defense,      Pharma-                                                               Resolution &
                                            Examples:   Construction
                                                                        Process     Shutdown &    Oil/Gas,
                                                                                                              shipbuilding,   ceuticals
                                                                                                                                          Development,     High-Rise       Housing     Mgmnt
                                                                                                                                                                                                       Claims
                                                                         Plants     Maintenance Manufacturing                              Engineering   Construction     Industry    Accounting
                                                                                                                Pharma                                                                                Analysis

Level of detail
          Overview Management for Reporting                  x             x
          Resource Management                                              x             x             x            x            x             x               x             x                           x
          Detailed Labor Management                                        x             x             x            x                          x                                                         x
          Detailed Subcontractor Management                  x             x                                                                                   x             x                           x
Frequency of Updates
          Hourly
          Daily                                                            x             x                                                     x                                                         x
          Weekly                                             x             x             x             x            x                          x               x                                         x
          Monthly                                            x             x                           x            x            x                             x             x            x              x
          Larger Period
Resource Data Managed
          No resources                                       x
          Individual resources (by name)                                                                                                       x
          Role resources (by position)                                     x                           x            x                                                        x                           x
          Crew resources (by trade crew)                     x             x             x                                                                     x                                         x
          Cost resources                                     x             x             x             x            x            x                             x             x            x              x
          Quantity resources                                 x             x             x             x            x            x                             x             x                           x
          Leveling of resources commonly performed                                       x             x            x            x                                           x
Activity Level Data Collected in Updates
          Resource Time Consumed                             x             x             x             x            x            x             x               x             x                           x
          Resource Quantity Consumed                         x             x             x             x            x                                          x                                         x
          Time Remaining                                     x             x             x                                                                     x                                         x
          Percent Complete                                   x                                         x            x            x             x                             x            x
Project Participants
          Labor only                                                                                                                           x
          Labor and Materials                                                                                                    x
          Labor, Materials, Equipment                                                                  x            x
          Labor, Materials, Equipment, Subcontractors        x             x             x                                                                     x             x                           x
          Subcontractors only                                                                                                    x                                                        x

Scheduling Components
        Resources - Labor
                    Resource loading                         x             x             x             x            x                          x               x             x                           x
                    Resource leveling                                      x             x             x            x                          x                             x                           x
                    Resource driving                                                     x             x                                       x                             x                           x
                    Consumed labor                           x             x             x             x            x                          x               x             x            x              x
        Resources - Costs
                    Sell costs                               x             x                                                                                   x             x            x
                    Planned costs                            x             x             x             x            x            x             x               x             x                           x
                    Actual costs                                                         x             x            x            x             x                                          x              x
        Resources - Quantity
                    Planned quantities                                     x             x             x            x                                                                                    x
                    Consumed quantities                                    x             x             x            x                                                                                    x
        Earned Value Orientation
                    Costs                                    x             x                                                     x                             x             x            x              x
                    Quantities                                                           x             x            x                                                                                    x
                    Labor                                                                x             x            x                          x                                                         x
                    Uses Earned Schedule                     x                                                                                                 x
        Correlation with Budget
                    WBS                                      x             x             x             x            x            x             x               x             x            x              x
                    Cost Accounts                                          x             x             x            x            x             x                                          x              x
Primary Driver for Update Monitoring/Analysis
        Critical Path Slippage                               x                                                                                                 x                                         x
        Near Critical Path Slippage
        Non-Critical Path Slippage
        General Activity Slippage                                                        x




Table 1, “Schedule Type Matrix”



                                      2011 AACEi Annual Meeting                                                                                                                                                    14
                 “Improving Industry Cross-Pollination by Classification of Schedule Types”
                                   By Chris Carson, PSP, and Raf Dua

Weitere ähnliche Inhalte

Was ist angesagt?

Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationChris Carson
 
Construction delays
Construction delaysConstruction delays
Construction delaysSaida Njim
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project ManagementShyam Kerkar
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11PMA Consultants
 
Projectcontrol
ProjectcontrolProjectcontrol
ProjectcontrolRaj Sampat
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project ManagementRodolfo Siles
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Allan Leyte
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.pptPedadaSaikumar
 
Budgeting and cost estimation
Budgeting and cost estimationBudgeting and cost estimation
Budgeting and cost estimationLibra chudry
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Abhishek Pachisia
 

Was ist angesagt? (20)

CCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and SchedulingCCP_SEC3_Planning and Scheduling
CCP_SEC3_Planning and Scheduling
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Budgeting
BudgetingBudgeting
Budgeting
 
Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
Construction delays
Construction delaysConstruction delays
Construction delays
 
Npv Irr
Npv IrrNpv Irr
Npv Irr
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Schedule levels-as-presented 02-may11
Schedule levels-as-presented  02-may11Schedule levels-as-presented  02-may11
Schedule levels-as-presented 02-may11
 
Projectcontrol
ProjectcontrolProjectcontrol
Projectcontrol
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 
Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3
 
Methodologies of Project Progress Measurement
Methodologies of Project Progress MeasurementMethodologies of Project Progress Measurement
Methodologies of Project Progress Measurement
 
PMP_Economic Selection Criteria
PMP_Economic Selection CriteriaPMP_Economic Selection Criteria
PMP_Economic Selection Criteria
 
8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt8. (lecture 6) Project Cost Control.ppt
8. (lecture 6) Project Cost Control.ppt
 
Budgeting and cost estimation
Budgeting and cost estimationBudgeting and cost estimation
Budgeting and cost estimation
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 

Andere mochten auch

Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
25 Corazon
25  Corazon25  Corazon
25 Corazonignacio
 
Economic order quantity
Economic order quantityEconomic order quantity
Economic order quantitySafik Ashik
 
inventory management ppt
inventory management pptinventory management ppt
inventory management pptMayank Baheti
 
Operation scheduling
Operation schedulingOperation scheduling
Operation schedulingsai precious
 
Inventory Management
Inventory ManagementInventory Management
Inventory Managementanoos
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project managementBarun_agnihotri
 
Inventory management
Inventory managementInventory management
Inventory managementsaurabhsabiba
 
Inventory management
Inventory managementInventory management
Inventory managementKuldeep Uttam
 
types of production system
types of production systemtypes of production system
types of production systemram4181
 
Basic of Human Resource Management
Basic of Human Resource ManagementBasic of Human Resource Management
Basic of Human Resource ManagementAshit Jain
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleAndrew Schwartz
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Jeremy Jay Lim
 
The Project Management Process - Week 1
The Project Management Process -  Week 1The Project Management Process -  Week 1
The Project Management Process - Week 1Craig Brown
 
Introduction to human resource management
Introduction to human resource managementIntroduction to human resource management
Introduction to human resource managementTanuj Poddar
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPTbletindia
 

Andere mochten auch (20)

scheduling
schedulingscheduling
scheduling
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
25 Corazon
25  Corazon25  Corazon
25 Corazon
 
Inventory management
Inventory managementInventory management
Inventory management
 
Economic order quantity
Economic order quantityEconomic order quantity
Economic order quantity
 
Inventory Control
Inventory ControlInventory Control
Inventory Control
 
inventory management ppt
inventory management pptinventory management ppt
inventory management ppt
 
Operation scheduling
Operation schedulingOperation scheduling
Operation scheduling
 
Inventory Management
Inventory ManagementInventory Management
Inventory Management
 
Introduction to project management
Introduction to project managementIntroduction to project management
Introduction to project management
 
Inventory management
Inventory managementInventory management
Inventory management
 
Inventory management
Inventory managementInventory management
Inventory management
 
types of production system
types of production systemtypes of production system
types of production system
 
Basic of Human Resource Management
Basic of Human Resource ManagementBasic of Human Resource Management
Basic of Human Resource Management
 
Types of production systems
Types of production systemsTypes of production systems
Types of production systems
 
Project Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern SampleProject Management PowerPoint PPT Content Modern Sample
Project Management PowerPoint PPT Content Modern Sample
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
The Project Management Process - Week 1
The Project Management Process -  Week 1The Project Management Process -  Week 1
The Project Management Process - Week 1
 
Introduction to human resource management
Introduction to human resource managementIntroduction to human resource management
Introduction to human resource management
 
Project Management PPT
Project Management PPTProject Management PPT
Project Management PPT
 

Ähnlich wie Types Of Industry Scheduling

London Ambulance Services (LAS) In a state of Emergency
London Ambulance Services (LAS) In a state of EmergencyLondon Ambulance Services (LAS) In a state of Emergency
London Ambulance Services (LAS) In a state of EmergencyMonzer Osama Alchikh WARAK
 
study on project analysis through critical path method
study on project analysis through critical path methodstudy on project analysis through critical path method
study on project analysis through critical path methodrahul waghmare
 
MBA Thesis Final
MBA Thesis FinalMBA Thesis Final
MBA Thesis FinalTerry Ross
 
AN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMS
AN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMSAN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMS
AN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMSijseajournal
 
AN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMS
AN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMSAN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMS
AN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMSijseajournal
 
An Exploratory Study of Usability Practice from User-Centered Design View: M...
An Exploratory Study of Usability Practice from  User-Centered Design View: M...An Exploratory Study of Usability Practice from  User-Centered Design View: M...
An Exploratory Study of Usability Practice from User-Centered Design View: M...Ruby Kuo
 
Act5 08 Hajos Schenk Webseite
Act5 08 Hajos Schenk WebseiteAct5 08 Hajos Schenk Webseite
Act5 08 Hajos Schenk WebseiteAntalHajos
 
Causes of Business Process Reengineering Failure in the Kingdom of Bahrain an...
Causes of Business Process Reengineering Failure in the Kingdom of Bahrain an...Causes of Business Process Reengineering Failure in the Kingdom of Bahrain an...
Causes of Business Process Reengineering Failure in the Kingdom of Bahrain an...Dr. Amarjeet Singh
 
PwC Tech Forecast Winter 2009
PwC Tech Forecast Winter 2009PwC Tech Forecast Winter 2009
PwC Tech Forecast Winter 2009Kurt J. Bilafer
 
IT PROJECT SHOWSTOPPER FRAMEWORK: THE VIEW OF PRACTITIONERS
IT PROJECT SHOWSTOPPER FRAMEWORK: THE VIEW OF PRACTITIONERSIT PROJECT SHOWSTOPPER FRAMEWORK: THE VIEW OF PRACTITIONERS
IT PROJECT SHOWSTOPPER FRAMEWORK: THE VIEW OF PRACTITIONERSijseajournal
 
Actionable Knowledge Discovery
 Actionable Knowledge Discovery  Actionable Knowledge Discovery
Actionable Knowledge Discovery murthynani1
 
DESIGN, DEVELOPMENT & IMPLEMENTATION OF ONTOLOGICAL KNOWLEDGE BASED SYSTEM FO...
DESIGN, DEVELOPMENT & IMPLEMENTATION OF ONTOLOGICAL KNOWLEDGE BASED SYSTEM FO...DESIGN, DEVELOPMENT & IMPLEMENTATION OF ONTOLOGICAL KNOWLEDGE BASED SYSTEM FO...
DESIGN, DEVELOPMENT & IMPLEMENTATION OF ONTOLOGICAL KNOWLEDGE BASED SYSTEM FO...IJDKP
 
Use of resource based view in industrial cluster strategic analysis
Use of resource based view in industrial cluster strategic analysisUse of resource based view in industrial cluster strategic analysis
Use of resource based view in industrial cluster strategic analysistamoni
 
Supply Chain Optimization under New Product Development and Emergence of Risk...
Supply Chain Optimization under New Product Development and Emergence of Risk...Supply Chain Optimization under New Product Development and Emergence of Risk...
Supply Chain Optimization under New Product Development and Emergence of Risk...IIJSRJournal
 
Dumbacher
DumbacherDumbacher
DumbacherNASAPMC
 

Ähnlich wie Types Of Industry Scheduling (20)

London Ambulance Services (LAS) In a state of Emergency
London Ambulance Services (LAS) In a state of EmergencyLondon Ambulance Services (LAS) In a state of Emergency
London Ambulance Services (LAS) In a state of Emergency
 
study on project analysis through critical path method
study on project analysis through critical path methodstudy on project analysis through critical path method
study on project analysis through critical path method
 
MBA Thesis Final
MBA Thesis FinalMBA Thesis Final
MBA Thesis Final
 
AN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMS
AN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMSAN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMS
AN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMS
 
AN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMS
AN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMSAN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMS
AN ITERATIVE HYBRID AGILE METHODOLOGY FOR DEVELOPING ARCHIVING SYSTEMS
 
Finding Balance
Finding BalanceFinding Balance
Finding Balance
 
An Exploratory Study of Usability Practice from User-Centered Design View: M...
An Exploratory Study of Usability Practice from  User-Centered Design View: M...An Exploratory Study of Usability Practice from  User-Centered Design View: M...
An Exploratory Study of Usability Practice from User-Centered Design View: M...
 
2009 ASME final
2009 ASME final2009 ASME final
2009 ASME final
 
Act5 08 Hajos Schenk Webseite
Act5 08 Hajos Schenk WebseiteAct5 08 Hajos Schenk Webseite
Act5 08 Hajos Schenk Webseite
 
Causes of Business Process Reengineering Failure in the Kingdom of Bahrain an...
Causes of Business Process Reengineering Failure in the Kingdom of Bahrain an...Causes of Business Process Reengineering Failure in the Kingdom of Bahrain an...
Causes of Business Process Reengineering Failure in the Kingdom of Bahrain an...
 
PwC Tech Forecast Winter 2009
PwC Tech Forecast Winter 2009PwC Tech Forecast Winter 2009
PwC Tech Forecast Winter 2009
 
A0340105
A0340105A0340105
A0340105
 
IT PROJECT SHOWSTOPPER FRAMEWORK: THE VIEW OF PRACTITIONERS
IT PROJECT SHOWSTOPPER FRAMEWORK: THE VIEW OF PRACTITIONERSIT PROJECT SHOWSTOPPER FRAMEWORK: THE VIEW OF PRACTITIONERS
IT PROJECT SHOWSTOPPER FRAMEWORK: THE VIEW OF PRACTITIONERS
 
Aircraft
AircraftAircraft
Aircraft
 
Aircraft
AircraftAircraft
Aircraft
 
Actionable Knowledge Discovery
 Actionable Knowledge Discovery  Actionable Knowledge Discovery
Actionable Knowledge Discovery
 
DESIGN, DEVELOPMENT & IMPLEMENTATION OF ONTOLOGICAL KNOWLEDGE BASED SYSTEM FO...
DESIGN, DEVELOPMENT & IMPLEMENTATION OF ONTOLOGICAL KNOWLEDGE BASED SYSTEM FO...DESIGN, DEVELOPMENT & IMPLEMENTATION OF ONTOLOGICAL KNOWLEDGE BASED SYSTEM FO...
DESIGN, DEVELOPMENT & IMPLEMENTATION OF ONTOLOGICAL KNOWLEDGE BASED SYSTEM FO...
 
Use of resource based view in industrial cluster strategic analysis
Use of resource based view in industrial cluster strategic analysisUse of resource based view in industrial cluster strategic analysis
Use of resource based view in industrial cluster strategic analysis
 
Supply Chain Optimization under New Product Development and Emergence of Risk...
Supply Chain Optimization under New Product Development and Emergence of Risk...Supply Chain Optimization under New Product Development and Emergence of Risk...
Supply Chain Optimization under New Product Development and Emergence of Risk...
 
Dumbacher
DumbacherDumbacher
Dumbacher
 

Mehr von Chris Carson

Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop ConferenceChris Carson
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesChris Carson
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpChris Carson
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodChris Carson
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotChris Carson
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminChris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...Chris Carson
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesChris Carson
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful MediationChris Carson
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule RevisionsChris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex ProjectChris Carson
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesChris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - AirportChris Carson
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse WeatherChris Carson
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony MistakesChris Carson
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor SchedulingChris Carson
 

Mehr von Chris Carson (20)

Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 
Testimony Mistakes
Testimony MistakesTestimony Mistakes
Testimony Mistakes
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Subcontractor Scheduling
Subcontractor SchedulingSubcontractor Scheduling
Subcontractor Scheduling
 

Types Of Industry Scheduling

  • 1. 2011 AACEi Annual Meeting Anaheim, CA, June 2011 Chris Carson, PSP 35191 Raf Dua Improving Industry Cross-Pollination by Classification of Schedule Types January 15, 2010 2011 AACEi Annual Meeting 1 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 2. Table of Contents List of Tables iii Abstract 4 Introduction 4 Overview 5 Scheduling Component Determinants 6 The Matrix Concept 9 Compile Matrix into Summaries 10 Identify types of schedules 10 Conclusion 12 Bibliography 13 ii 2011 AACEi Annual Meeting 2 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 3. List of Tables Table 1, “Schedule Type Matrix” 14 2011 AACEi Annual Meeting 3 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 4. Abstract One scheduler says resource leveling is vital to producing a reasonable schedule, another says no one uses resources, let alone leveling. Scheduling discussions get passionate yet often schedulers in different industries do not seem to speak the same language. Some industries are naturally far ahead of others in the use of specific scheduling components, such as resources, EVM, or Risk Management, and those leaders are often the source for innovation in the use of those components. This paper will study how industries use scheduling, attempt to categorize industry scheduling by common needs and component solutions, and provide an understanding of the differences between industry schedule use that should allow for better communications and increase the opportunity to enable innovation from each industry to improve scheduling in all industries. Introduction Professional schedulers, those who use scheduling to enhance and improve project management actions, often lose themselves in their own world of planning and scheduling. They work with other schedulers who are in the same industry or even the same segment of the same industry, understand their unique needs and even develop lingo and buzz words that are specific to their segment. The use of scheduling is fairly standardized, although there is variation in competence and general use of schedules. Understanding how each segment of the scheduling world is different can help categorize types of schedules. Often what seems to be innovative scheduling for one industry is a common practice in another industry. This observation shows the way to improve scheduling across all industries if the common practices in one industry that seem innovative in another industry could be shared with other industries that might be able to use those common practices if they only understood them. This is typical of the way that Earned Value Management (EVM) has been absorbed into commercial construction; at one time, EVM was strictly used in defense and other industries. Then contractors who performed both military defense and commercial construction used the techniques in military projects and soon realized that there were benefits from the use of EVM in the commercial construction field. Currently, there is no scheduling –wide categorization of types of scheduling so there is no simple way for one industry to view new best practices and incorporate those into their routine scheduling tasks. In most cases industries do not even know what is being used in other industries with success. Without the knowledge of what is available and used professionally, industry schedulers will not have the opportunity or inclination to experiment with new techniques. The Association for the Advancement of Cost Engineering international (“AACEi”) publication, Total Cost Management Framework, A Process for Applying the Skills and Knowledge of Cost Engineering,[1] clearly encompasses all types of industries, yet does not categorize those type of industries requiring different types of scheduling practices. The Total Cost Management Framework defines the “strategic assets” of an enterprise as “shorthand for any unique physical or intellectual property that is of long term or ongoing value to 2011 AACEi Annual Meeting 4 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 5. the enterprise” and notes that “the asset may be a building, an industrial plant, a software program, or a stage production.” Compiling a system of categorization of schedule types would help to allow the comparison of similar schedule types, and the more definition that can be applied to each type, the more likely that improvements that would be useful will be identified and incorporated. As schedulers recognize that there are scheduling techniques being used successfully in other industries, there should be an increased demand for understanding the taxonomy of scheduling types. This is an area where the leading industry associations, like AACE International and the PMI Scheduling Community of Practice, should encourage studies and opportunities for cross-pollination between different industries and sectors of industries. Overview – Rationale for Paper The authors come from slightly different sectors of the construction industry, with Mr. Dua working in Australian and Far East manufacturing and construction projects that require extensive planning and monitoring of resources for us in planning Design-Build-Operate-Maintain type projects. He has developed his own ADM software, Micro Planner Expert, in an effort to provide the software flexibility necessary to handle the demands on resource driven scheduling. Mr. Carson works in the United States primarily in commercial and military projects that require claims avoidance and subcontractor management efforts. His work primarily involves use of Oracle/Primavera schedule software and to a much lesser extent, some Microsoft Project software. Both provide risk assessment and monitoring as part of their planning services, and both work as consultants for both owners and contractors in their fields. And both require well planned networks that are highly technical and accurate so that the network calculations will provide reasonable and legitimate values of total float and identifications of critical and near critical path activities. Both authors are involved in the industry associations related to planning and scheduling like AACEi, and as such, have deep exposure to other planners and schedulers in many different segments of or industries. We have found that communications among all these different planners and schedulers can often be difficult mostly due to the emphasis on various components used in the different industries. Just the differences between Mr. Dua’s extensive involvement in individual manpower resources and Mr. Carson’s involvement in more crew-related resources highlight the disparities that result in misunderstandings about scheduling best practices and needs. With the proliferation of more and more social networks and well managed forums that are related to project controls, there are greater numbers of schedulers from all sectors of and industries that are exposed to each other. Judging from the discussions, it is clear that some of the disputes about best practices actually revolve around the use of the schedules more than the quality of the schedules. Review of the forums and groups shows how one scheduler will note that resource leveling is not used in his/her industry, and another scheduler showing concern that without good resource leveling it is not possible to accurately plan and schedule a project of any kind. Or, one industry scheduler feels that the attempt to cost load a schedule and use earned value to manage a project reduces the time management component’s usefulness of the schedule, where another industry scheduler cannot believe that anyone could plan and schedule a project without using earned value. The authors believe that the real value in the recognition of these differences is the opportunity to cross-pollinate industries with scheduling component expertise. If one sector of an industry is using 2011 AACEi Annual Meeting 5 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 6. individual labor resource components effectively to plan and manage a project, learning from that sector in order to bring better individual labor resource components into another sector will enable this other sector to improve the plan. This is also true with sectors where high penalty risk and legal ramifications of failure promote higher levels of technical development of the CPM network. This higher level of network development, if absorbed by other industries where the risks are not as high, will still improve the value of the output statistics and metrics used to analyze the schedule progress. Scheduling Component Determinants That Affect Types of Schedules After numerous discussions and brainstorming, as well as searching for studies or academic papers that might provide a taxonomy for schedule types, we determined that this would be a useful topic for an academic study and could be very useful to scheduling associations attempting to provide value to their membership. That value would arise from the cross-pollination of the technical scheduling components used in various industries and segments of industries. We call these scheduling components “determinants” for types of schedules. From our research and brainstorming, there appear to be approximately nine major schedule technique and component determinants that define scheduling efforts: 1. Level of detail of the schedule 2. Frequency of schedule updates 3. Resource data and techniques used 4. Activity level data collected in updates 5. Project participants (categories monitored in schedules) 6. Scheduling components 7. Drivers for update monitoring and analysis 8. Primary project management constraint 9. Schedule accuracy The level of detail in the schedule is often a function of how the schedule is developed; bottom up schedule development generally experiences a higher level of detail than a top down development. However the purpose for the chosen level of detail is usually based on the needs; will it be used for reporting to senior management, managing field and/or engineering resources, general project overview, or for management of contractors and resources? When a schedule is designed to be used for reporting, the level of detail is generally fairly low since only enough monitoring is required to provide an executive summary. When the schedule is used for managing engineering time, the level of detail must extend to the identification of individual deliverables and the work packages necessary to provide those deliverables; this will require much more detail. The frequency of updates is another determinant that drives the type of schedule. For projects such as engineering projects, software design, or plant maintenance and shutdown, monitoring and controlling the manpower tends to require hourly level monitoring. The schedule must be maintained in sufficient detail that updates cannot wait for a week or month. For most commercial construction projects, if they are managing by the schedule, they need weekly updates, and if they are managing in more of an overview approach, or allowing the superintendent to provide the short interim planning, they are happy with monthly updates. 2011 AACEi Annual Meeting 6 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 7. The use of resource planning and monitoring is one of the areas which has a wide variance among schedulers, ranging from projects with no resource loading or monitoring to projects where managing individuals or crews, or quantities and costs, are vital. In projects where each resource is reasonably equivalent, such as engineering design or piping installers, and the resource is a main driver of the costs, managing resource data down to the individual or role is necessary to provide the monitoring and control. But in industries where the labor relies on a foreman and numerous levels of labor, helper, journeyman, it can be more efficient and effective to manage resources at a crew level. Crew level resources are not very hard to identify as well. In his paper published in the 2007 AACE International Transactions, “Artificial Resource Loading for Schedule Review” [2], Al Kuhn, PSP, addresses a way for a schedule reviewer to load crews into a schedule in an effort to evaluate the network logic and activity durations. Notably, the examples in the paper are from commercial construction where the labor force is varied in their individual competencies, so crew resource monitoring works well, but role based individual resource monitoring is very difficult to do because the data is generally not available. Another division in industries and sectors of industries involves the use of resource leveling, and this breaks down into labor and equipment leveling in general. Industries that use large amounts of similar role resources consider it vital to run resource leveling heuristics to attempt to smooth out resource usage, or to model limitations in availability of certain resources. This effort cannot be used in industries or sectors of industries where the technical schedule must remain such that the network calculations are accurate, and resource leveling will provide float values that do not identify true critical paths. These sectors or industries typically use CPM calculations of delay to assess damages for late completion. Sometimes industry schedule practices can be described by the activity level data collected during the monitoring phase, if actual resources are recorded and compared to planned resources, it is likely that the industry or sector deals with large amounts of labor resources or small amounts of labor but lesser equipment, subcontractors, or materials resources. Identifying whether updates require actual labor, equipment hour, or materials installed will shift what type of scheduling is performed. Whether the schedule is updated by time remaining or percent complete helps determine whether the schedule is driven more by time or costs, or in the case of some construction sectors, both are used but kept separate by delinking the two components in the scheduling software. Another way that separates types of schedules is the issue of the project participants in terms of cost drivers; is it only labor such as engineering, or labor, materials, and equipment such as bridge work, or labor, materials, equipments, and subcontractors such as commercial or military construction. If the schedule does not need to monitor subcontractors, that schedule can focus much more on resource consumption because all resources are under the control of the project management team and the schedule will be used for planning and controlling the expenditure of those resources. When subcontractors are involved in the project, the risk of performance is generally carried by those subcontractors and the master schedule does not need to address monitoring of the subcontractor resources, except as it affects project performance and delay. As one examines scheduling components, the use of them in a schedule break down into four major areas as the authors see it; labor resources, costs resources, earned value, and how the schedule correlates with project budget. Obviously these could all be interconnected; however, schedules are very different when used to control labor than when used to control costs. Labor resources evolve from resource loading to resource leveling to resource driving and then to resource tracking. The term resources mean many things to many people, from individual engineers to large pieces of equipment to simply costs of installation. 2011 AACEi Annual Meeting 7 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 8. Earned Value Management (“EVM”) has been around for years, and it is one of the technical scheduling components that are migrating from those industries, such as defense, that were early serious users of the process, to commercial construction, where the need evolved as schedule analysts needed more tools to monitor projects. Within EVM systems, the two major divisions occur between costs and labor resources, and to a much lesser extent, materials quantities. Using costs assigned to activities, it is possible to compare what has been earned to date with what should have been earned to date based on the original schedule. This is also true of hours earned which can be compared to what hours should have been earned to date based on the plan. The use of EVM systems helps categorize types of schedules at a technical level. Some schedules are correlated with the project budget while many are not correlated with any benchmark for comparison. Within those industries that use cost control accounts and Work Breakdown Structures (“WBS”) to monitor expected cost overruns, often they have a greater maturity in the correlation between cost and time. This is a different approach from many other industries who do not correlate cost and time, since the WBS in those mature industries is elaborated to the level of deliverables or work packages, and those are linked to the cost control accounts, providing accounting metrics for review and monitoring. One of the prime determinants for the type of schedule is that of the driving rationale for update monitoring and analysis. The drivers can range from critical path slippage control to milestone monitoring to the need to ensure that all activities are progressing according to their plan. There may be incentives or penalties based on individual milestones, but rarely are there any penalties for individual activity slippage. Schedules whose primary drivers are critical path slippage generally are used with projects subject to damages from penalties for late completion. The range of schedule types purposes include this protection from damages, the need for re-baselining the schedule for monitoring, protection against cost overruns due to prolongation of the project, or those schedules where the milestone or completion dates are allowed to slip without penalty. The existence of penalties creates a culture where claims prevail, as each party is both protecting itself and documenting the other party’s failings. As these claims are litigated, case law has developed and established principles based on previous rulings, and the need to design schedules and manage schedule analysis according to these overarching legal principles becomes a prominent drive for schedule documentation. Near critical path monitoring drivers for schedules are similar to critical path drivers, but generally they are elevated to a higher purpose with multiple contractual milestones or the need to identify and respond to mid-period critical path shifts. Non-critical path slippage is an important driver for scheduling when cost overruns due to performance impact the project such as with ship building and aerospace where huge cost overruns must be identified and monitored. Government demand for monitoring systems and documentation help push those industries towards similar scheduling types. Where resources can cause large problems due to lowered production rates and stacking of resources, schedules tend to focus on resource management. This can even be a secondary purpose for schedules in industries such as commercial and military construction where disruption can cause large cost overruns. Some industries are focused on making sure that each activity is completed on time using the planned resources, or at least evaluating those activities such as is done in forensic analysis cases, while others only care about activity slippage as it relates to trade stacking or other disruption issues. So the major division related to activity slippage monitoring and reporting is the question of the severity of the risk of activity slippage. And then some industries have fully embraced the use of EVM for monitoring and controlling, sometimes to the detriment of the critical path analysis. 2011 AACEi Annual Meeting 8 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 9. One of the other prime schedule type determinants is the issue of which of the project management “triple” constraints is most important to the project. While every owner will insist that everything is important, that is rarely true. The major project management constraints include scope, time, cost, (often called “the triple constraints”) and sometimes adding quality and/or risk. Most projects have one prime driver; in fact most contractors have a natural inclination to focus on one of the constraints more than others, no matter what the owner’s point of view. The authors believe that the most successful and simplest projects occur when the owner and the contractor have an alignment of these constraints. A quality driven contractor will be more at risk of failure when building a project for a cost oriented owner. These constraints are an important schedule type determinant. The last determinant that the authors believe separate schedules into common types is that of the accuracy of the schedule; meaning the smallest time period used for planning and updates. Very broad long-term program overview schedules may only be accurate to the nearest year, where more commonly schedules are accurate to a low level of accuracy at the monthly range, and some projects take the accuracy down to the day or even hour. A maintenance and shutdown schedule for a coal fired power plant might need to plan to the nearest hour so they can cycle crews in as soon as another crew is complete. A commercial or military construction project is likely accurate to the nearest week, but may be monitored to a daily plan. A forensic schedule is likely trying to identify the cause of delay in order to assign responsibility to assess liability, so that schedule may likely plan to be accurate to the nearest day. And a schedule whose output is primarily a monthly invoice may only be accurate to that level. The accuracy should be a good determinant to categorize schedule types. The Matrix Concept In an effort to develop categories of schedule types, the authors developed a Schedule Type Matrix, designed to facilitate the ordering of scheduling into appropriate types based on how the various industries and sectors of industries use the schedule technique and component determinants. The process developed included identifying a number of different industries and sectors of industries and evaluating those sectors as to how they use any of the schedule component determinants. The industries chosen included: • Commercial construction • Military construction • Hospital construction • Power plant construction • Maintenance and shutdown of factories and plants • Defense projects • Oil and gas projects • Manufacturing • Energy projects • Shipbuilding and aerospace construction • Pharmaceutical projects • Software development projects • Information technology projects • Engineering projects • Transportation construction • High-rise construction 2011 AACEi Annual Meeting 9 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 10. Wide-rise housing construction • Financial projects • Forensic scheduling projects The construction projects included all types of project delivery; design-bid-build, multi-prime contracting, EPC, design-build, design-build-operate, design-build-operate-maintain, and At Risk CM. Of course, once you include other industries outside of construction, the project delivery methods It is noteworthy that the authors found that some of the types of projects operate with different scheduling types at different times during the life cycle of the project. For instance, pharmaceutical projects may use critical chain methodology early in the pre-project, research and regulatory stages, with different levels of CPM methodology detail between FEL stage and detailed design, construction, commissioning, and qualifications. The pharmaceutical regulatory scheduling is simply milestones, while they use EVM for productivity metrics in engineering and construction phases. After the informal research, interviews, and study involved in the development of this topic, the authors realize that developing a schedule type taxonomy will likely require a formal study with thousands of schedulers involved, but that is beyond the scope of this paper. There is clearly not complete agreement as to what schedule type determinants are predominant in all industries and sectors, mainly due to the complexity and variance in scheduling techniques. However, the authors have attempted to pull together what they believe is an accurate view of those industries and sectors of industries. Compile Matrix Markers into Summaries After compiling industry and sectors of industries into categories of schedule technique and component determinants and mapping those industries, the authors combined similar use of the schedule technique and component determinants so as to cluster industries and sectors of industries. The result of that correlation and combination is the Schedule Type Matrix. Identify types of schedules based on schedule components Based on the effort in developing the Schedule Type Matrix, the authors believe that schedule types fall into eleven broad categories. These categories are: • Technically-oriented scheduling • Complex phasing-oriented scheduling • Recovery-oriented scheduling • Large resource-oriented scheduling • EV-oriented scheduling • Rolling wave oriented scheduling • Timesheet-oriented or small resource-oriented scheduling • Location-oriented scheduling • Program-oriented overview scheduling • Financial management oriented scheduling • Forensic scheduling 2011 AACEi Annual Meeting 10 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 11. Technically-oriented scheduling is used where litigation results in case law that forces highly technical knowledge to be used in the schedule development and maintenance so that careful CPM analysis of delay and disruption are supported. The risk of time related disputes that result in claims drives the preparation, review and approvals of schedules to technical extremes so that delays are identified and responsibility for delay assessed. The use of resources in this schedule type is limited to macro level, mostly crew resources, and used to verify both duration calculations and resource planned usage to form a benchmark for analysis of delays, and more importantly, disruption in the form of labor inefficiencies. Specifications often require resource loading with reporting of actual resource usage. Resource leveling is rarely used in this type. Examples of this type of scheduling include most commercial and military construction. Complex phasing-oriented schedule is used in projects where the location coordination and logistics of movement of resources around the project, and the component assembly of systems requires careful use of scheduling. This type may also carry needs of technically oriented scheduling. These projects often combine with technically-oriented and large resource-oriented scheduling. Examples of this type of scheduling include hospital construction and renovation as well as process plants. Recovery-oriented scheduling types of projects evolved due to the fact that costs of each day of delay could be millions of dollars or abject project failure - the main thing that matters is to crunch the schedule to meet the original planned completion; mitigation of delay is the main emphasis. The type often requires some emphasis on the capture of full scope of work in order to complete as much work as possible within the rigid project time span, and the use of rapid response teams or involved mitigation schedules. Often the project participants include multiple parties with interrelationships that require monitoring to avoid disruption. Examples of this type of scheduling include airport renovation and shut down and maintenance of power plants. Large resource-oriented scheduling is another type of scheduling that crosses several industries or sectors of industries and sometimes is combined with other types. It is used where the huge resources, mostly labor, must be planned and managed at a much greater level of detail than "normal" – labor resources are so large that they drive production and the system must plan and manage those large groups of resources. Project participants are mostly labor workers of all trades and competencies. Examples of this type of schedule use include defense, some phases of oil and gas construction, and manufacturing. Earned Value-oriented scheduling becomes a separate category of schedule types due to the primary management effort; the use of Earned Value metrics. These projects are focused on budgets and number crunching to check project status. The need for identification and management of the critical path is not as severe as the technically-oriented scheduling but completion date slippage must be monitored and documented. Examples of this type of scheduling include large energy projects, ship and plane building, some defense, and pharmaceutical projects. Rolling wave oriented scheduling are often those projects where project cycles are very long, potentially years from approval to final testing, and different phases of the project have vastly different levels of schedules due to the available information. The ability to plan in detail for work to be done perhaps years later drives the type to the use of rolling wave scheduling methodology where the schedule is planned at a high level, typically using milestone and summary master schedules, and the work is managed by developing detailed schedules for short periods of current time. Individual project phases may fall into other types of scheduling, such as Earned Value, or other methodologies such as Critical Chain. Examples include pharmaceuticals, research and development. 2011 AACEi Annual Meeting 11 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 12. Timesheet-oriented or maybe more accurately labeled small resource-oriented scheduling occurs where schedules are used to manage personnel and often capture actual costs - it's all about managing individuals. Examples include Information Technology projects as well as software development and engineering. Location-oriented scheduling is defined by many repetitive fragnets, with logic ties in CPM scheduling made to sequence work within specific locations of the project. This scheduling type is popular for use with linear scheduling, often using velocity diagrams, and sometimes combines velocity diagrams and CPM scheduling. Examples of this schedule type include transportation-type projects such as utilities, roadways, bridges, and facilities-type such as high-rise office buildings and housing or condominiums. Program-oriented overview scheduling is represented by project conditions where schedules have both resource and delivery constraints, with budgets that span across years while new sections of the development are opened and completed. These schedules do not need a deep level of detail since the work is generally repetitive, but sometimes uses very detailed CPM scheduling. Completion dates are not cast in stone due to the overview nature of the product, so critical path slippage is often allowed. Examples include the “wide-rise” housing industry where programs typically run over decades of development as well as general program master schedule monitoring. Financial management oriented-scheduling is a schedule type that provides schedules used to plan and monitor business acquisitions, restructuring, and spin offs of divisions. CPM methodology is not very important; schedule used more to direct wide range of participants, but requires no real monitoring of Critical Path or float. Forensic scheduling evolved since schedules are used to determine causality and to identify responsibility in order to assess liability and resolve time related delay and disruption disputes. It is most often used in conjunction with technically-oriented, complex phasing-oriented, large resource- oriented and location-oriented schedule types. Examples include dispute resolution and claims analysis projects in many industries. Conclusion Although we are all working on improving the practices of CPM scheduling, it is difficult sometimes to communicate across the whole realm of schedule types, so we need to develop a taxonomy to help identify commonality among schedule types. This will become more and more important as schedulers continue to look for innovative ways to improve efficiency for the scheduling process. Identifying the schedule types that are at the forefront of new and established professional techniques will allow industry associations to help promote those schedule techniques and component determinants predominant in specialized industries to all industries, providing cross- pollination of industries with schedule techniques. 2011 AACEi Annual Meeting 12 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 13. Bibliography No. Description 1 Hollmann, J.K., PE CCE Copyright 2006 Total Cost Management Framework, A Process for Applying the Skills and Knowledge of Cost Engineering First Edition AACE International, Morgantown, WV 2 Kuhn, A., PSP 2007 Artificial Resource Loading for Schedule Review 2007 AACE International Transactions AACE International, Morgantown, WV 2011 AACEi Annual Meeting 13 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua
  • 14. Schedule Type Matrix Schedule Types - Crosses Industry or Segments of Industry Large Earned Rolling Small Location - Financial Schedule Technique & Component Determinants Technical Phasing Recovery Program Forensic Resource Value Wave Resource Linear Mgmnt. Energy, Dispute Hospitals, Plant Defense, IT, Software Transportation, Wide-Rise Also called Commercial Defense, Pharma- Resolution & Examples: Construction Process Shutdown & Oil/Gas, shipbuilding, ceuticals Development, High-Rise Housing Mgmnt Claims Plants Maintenance Manufacturing Engineering Construction Industry Accounting Pharma Analysis Level of detail Overview Management for Reporting x x Resource Management x x x x x x x x x Detailed Labor Management x x x x x x Detailed Subcontractor Management x x x x x Frequency of Updates Hourly Daily x x x x Weekly x x x x x x x x Monthly x x x x x x x x x Larger Period Resource Data Managed No resources x Individual resources (by name) x Role resources (by position) x x x x x Crew resources (by trade crew) x x x x x Cost resources x x x x x x x x x x Quantity resources x x x x x x x x x Leveling of resources commonly performed x x x x x Activity Level Data Collected in Updates Resource Time Consumed x x x x x x x x x x Resource Quantity Consumed x x x x x x x Time Remaining x x x x x Percent Complete x x x x x x x Project Participants Labor only x Labor and Materials x Labor, Materials, Equipment x x Labor, Materials, Equipment, Subcontractors x x x x x x Subcontractors only x x Scheduling Components Resources - Labor Resource loading x x x x x x x x x Resource leveling x x x x x x x Resource driving x x x x x Consumed labor x x x x x x x x x x Resources - Costs Sell costs x x x x x Planned costs x x x x x x x x x x Actual costs x x x x x x x Resources - Quantity Planned quantities x x x x x Consumed quantities x x x x x Earned Value Orientation Costs x x x x x x x Quantities x x x x Labor x x x x x Uses Earned Schedule x x Correlation with Budget WBS x x x x x x x x x x x Cost Accounts x x x x x x x x Primary Driver for Update Monitoring/Analysis Critical Path Slippage x x x Near Critical Path Slippage Non-Critical Path Slippage General Activity Slippage x Table 1, “Schedule Type Matrix” 2011 AACEi Annual Meeting 14 “Improving Industry Cross-Pollination by Classification of Schedule Types” By Chris Carson, PSP, and Raf Dua