INTRODCTION
Project management involves the application of various
knowledge areas, tools and skills along with numerous
techniques to congregate project requirements like duration
and cost.
The factors that affect project management are:
• Project cost
• Project time
• Project scope
• Project requirement
3CHETANRAJ
MICROSOFT PROJECT
• Microsoft Project is a project management software
product, developed and sold by Microsoft.
• It is designed to assist a project manager in developing a
plan, assigning resources to tasks, tracking progress,
managing the budget, and analyzing workloads.
• Streamline project, resource, and portfolio management
with Microsoft Project. Integrated planning tools help you
keep track of projects and stay organized.
4CHETANRAJ
OBJECTIVES
• Collecting data and information.
• Use of Microsoft Project in scheduling.
• Prepare scheduling technique by network models (CPM).
• Prepare construction sequence of work for Construction.
• Estimating the time duration required to complete the
individual activity.
• Create Baseline & Tracking.
• Identify risks in construction activities which causes delay.
5CHETANRAJ
SCOPE
• The Development of Planning and Scheduling in
Construction industries.
• The Project only focusing on sequence of work for
building construction project.
• The Project will carried based solely on one project
scheduling software that is Microsoft Project.
• The area of study only covered the ongoing site
construction in xxxxxxxxx xxxxxxx.
6CHETANRAJ
LITERATRE REVIEW
AUTHOR NAME YEAR TITLE
Monish Kumar K &
Maheshwar S 2017
CONSTRUCTION PROJECT
SCHEDULING OF MK
APARTMENT USING MSP
Shubham Laddha,
Prerna Chanda &
Sneha Khedekar
2017
PLANNING AND SCHEDULING
OF A PROJECT BY MSP 2013
P M Wale,
N D. Jain,
N R Godhani &
S R Beniwal
2015
PLANNING AND SCHEDULING
OF PROJECT USING MICROSOFT
PROJECT
7CHETANRAJ
LITERATRE REVIEW
Monish Kumar K (2017) Project on CONSTRUCTION
PROJECT SCHEDULING OF MK APARTMENT USING
MSP
A two phase methodology is adapted in which the first
phase comprise of the collection of basic information
required for the schedule development and the second phase
comprise of the development of a formidable schedule.
Using MSP2013 as a construction project management tool,
project planning is done accurately, this enables
management to organize the resources required for the
project effectively.
8CHETANRAJ
LITERATRE REVIEW
Shubham Laddha (2017) Research on PLANNING
AND SCHEDULING OF A PROJECT USING
MICROSOFT PROJECT 2013
Microsoft Project is the modern tool of Project
Management that aid to overcome the obstacles faced
owing to traditional way of Planning and Management.
It helps for the optimum and effective organization of
activities which helps to give the vision to complete the
project in planned duration and within the Economy.
9CHETANRAJ
LITERATRE REVIEW
P M Wale (2015) analysed PLANNING AND
SCHEDULING OF PROJECT USING MICROSOFT
PROJECT USING MICROSOFT PROJECT 2013 by Case
Study of a building in India.
Construction of building using Traditional way proves to be
uneconomical and consumes more time with many
complexibility and enormous error which actual execution
of the Project.
Labour management becomes easier as the over allocated
activities are levelled using the levelling option available in
MSP 2013
10CHETANRAJ
PROJECT BRIEF
• Project: xxxxxx xxx xxxxxxxx xxxxxxxxx xxxx xxxx
• Client: xxxxx xxxxxxxxxxx xxxxxx xxxxxxxx xxxx
• Contractor: xxxxxx xxxxxxxxxxx xxxxxx xxxx xxxxxx
• Project type: xxxxx xxxxxxxxxx xxxxxxx xxx xxxxx
• Project Cost: xxxxxx
• Place: xxxxxxxxxxx xxxxxxx xxxxxx xxxxxx xxxxxx
11CHETANRAJ
PROJECT BRIEF
General Details
• RCC framed structure.
• Brick work, interior and exterior cement plaster.
• Well finished emulsion paint for interior and external
walls.
• Sub-contractors are involved in the construction
process.
• Water proofing treatment.
• Highly Secured Building.
12CHETANRAJ
THE COMPANY
• Company Name: XXX XXX XXXXXXXX
• Office: XXXXX XXXXXXXXX XXXXXXXXXX,
BENGALURU-560065, KARNATAKA
13CHETANRAJ
METHODOLOGY
1) Selection of project
2) The collection of data required
3) Starting a Project in Microsoft Project 2013
4) Providing Project Information
5) Developing Gantt Chart
6) Creating Calendars
14CHETANRAJ
METHODOLOGY
7) Resource Management
8) Levelling the Activity and Resources
9) Calculate The Project
10) Create Baseline
11) Tracking
12) Results and Discussion
15CHETANRAJ
1) Selection of project
• Benefits
• Feasibility
16
2) The collection of data required
• Basic Data
• Key Components
CHETANRAJ
3) Starting a Project in Microsoft Project
• Get the Software MSP2013
17
4) Providing Project Information
• Provide Title of the project,
Company Name, Manager, Author Name, etc.
• Provide Start Date
CHETANRAJ
5) Developing Gantt Chart
18
MSP Schedule: List of activities with WBSCHETANRAJ
Prepare Task List
19
Every task in the Construction of building is listed one by
one by using Collected Data, Architecture drawing, and bill
of quantity.
Example: 1. Start,
2. Arrangement of electricity,
3. Install Temporary water Service,
115 tasks are prepared.
CHETANRAJ
Divided Task List
20
Construction activities Tasks are divided as
• Mobilize On Site
• Substructure
• Superstructure
• Water Supply & Sanitary Works
• Painting
• Final Cleanup And Inspection
CHETANRAJ
Link all Tasks with respect to WBS And Each
WBS Activities code Defined
21
Example:
Construction
Activities
Mobilize on
site
Start
Arrangement
of electricity
Substructure Excavation
WBS TASK NAME
1 1 Construction Activities
2 1.1 Mobilize on site
3 1.1.1 Start
4 1.1.2 Arrangement of electricity
5 1.2 Substructure
6 1.2.1 Excavation
WBS Preparation
WBS Activities code Defined at MSP
CHETANRAJ
Task Duration analysis Example:
Total quantity of External Painting work = 320sqm ..A
Productivity of 1 painter & 2 Helper = 13sqm per day ..B
Available 5 painter ..C
10 helper
Product per day = Available painters X Output per painter per day
= 5 x 13 ..(B x C)
= 65sqm ..D
Task Duration = 320/65 = 4.9 = 5 days ..(A / D)
22CHETANRAJ
6) Creating Calendars
23
Change working time WindowCHETANRAJ
MSP Schedule: Gantt Chart developed at
right panel
24
Gantt Chart
CHETANRAJ
7) Resource Management
25
• Work - human resource, or equipment rented by
the hour or day.
• Cost - time independent resources, like Airplane
tickets.
• Material - consumables like bricks, oil, concrete
etc.
CHETANRAJ
8) Levelling task resources
• Over Allocation are on red  After levelling
26CHETANRAJ
9) Calculate The Project
27
• Renumbering WBS
• Calculate the Project After you make a change
10) Create Baseline
• Save plan
• Compare with planned and actual process
CHETANRAJ
11) Tracking
28
Updating finished Process as per the date.
12) Results And Discussion
Project Report available after Tracking
• Dashboard Reports
• Resource Reports
• Cost Reports
• Progress Reports
CHETANRAJ
RESULTS AND DISCUSSION
29
Network diagram sheet
CHETANRAJ
RESULTS AND DISCUSSION
30
Critical Task at Reports
CHETANRAJ
RESULTS AND DISCUSSION
31
Cost Reports
CHETANRAJ
RESULTS AND DISCUSSION
• Project schedule of 130 days are developed.
• Activity Sequence is listed with duration and relationship
with other tasks.
• Project finish date will be delivered as per the calendar
after providing start date.
• Project duration can be calculated from finish date as well
as start date.
• Critical path obtained.
• Over allocations are levelled.
32CHETANRAJ
CONCLUSION
• Microsoft Project 2003 is a very easy software to
work with. Simple way to develop tasks and
resources.
• MSP helps to Identify Critical path of the project, as
well as Helps to find the over allocated resources.
• The results will be automatically calculated with
tracking which allows to manage project.
33CHETANRAJ
CONCLUSION
• By Task sequencing and accurate scheduled connection
among the tasks, the project length can be achieved
without any interruption.
• The Gantt charts will be a pure representation for the
site engineers, easy performance of task and have
arranged for the forthcoming tasks.
• MSP provides Easy way to represent fast tracking of
tasks
34CHETANRAJ
FUTURE SCOPE
• Once schedule is developed in MSP will allows to
update for upcoming tasks.
• Tracking continued until the end of the project for the
best construction outcome. Every tracking process will
provide earned value changes.
• Allows the task comparison with the saved baselines.
And with 11 available saves.
• The MSP file are easy to save, share and backup same
as MICROSOFT OFFICE Files.
35CHETANRAJ
REFERENCES
[1] Monish Kumar K, Maheshwar S, “Construction Project Scheduling of MK
Apartment Using MSP”, IJRET, Volume 04 Issue 07, PP 2275-2279, July 2017
[2] Manisha N. Ghotnekar, Shashank U. Vanakudari, “Planning & Scheduling
of Commercial Building Using Microsoft Project & Application of Principles of
Theory of Constraints for Achieving High Efficiency Cutting edge Construction
Project”, IRJET, Volume 04 Issue 07, PP 2545-2549, July 2017
[3] Rashmi J, Amey A Kelkar, Vishwanath K G, “Planning and scheduling of
a multi-storeyed residential building with conventional execution approach as
compared with application of project management techniques”, IRJET, Volume
04 Issue 07, PP 2682-2685, July 2017
[4] Shubham Laddha, Prerna Chanda and Sneha Khedekar, “Planning And
Scheduling Of Project Using Microsoft Project 2013”, IJAR
10.21474/IJAR01/4394, PP 161-168, June 2017
[5] S.Ragavi, Dr.R.N.Uma, “Review of project management softwares-ms
project and primavera” IJRET, Volume 03 Issue 11, PP 1260-1263, Nov -2016
36CHETANRAJ
REFERENCES
[6] P M Wale, N D. Jain, N R Godhani, S R Beniwal, “Planning Scheduling of
Project using Microsoft Project”, IOSR, Volume 12, Issue 3 Ver. III, PP 57-63,
Jun 2015
[7] Rhuta Joshi, Prof. V. Z. Patil “Resource Scheduling of Construction
Project Case Study” IJSR Volume 4 Issue 5, PP 563-568, May 2015
[8] Ashwini R. Patil, Smita V. Pataskar, “Analyzing Material Management
Techniques on Construction Project”, IJEIT, Volume 3, Issue 4, PP 96-100,
October 2013
[9] C. Chantrapornchai, D. Sawangkokrouk and T Leadprathom, “Project
Management Software Allocation and Scheduling Aspects”, IJSST, Vol. 6, No. 3,
PP 35-42, June 2013
[10] P. Dayakar , “Study On Project Management Of Ongoing Construction
Project Using Msp - Sub Structure”, IJBTT, Volume2 Issue 5, PP 11-23, Oct 2012
37CHETANRAJ
THANK YOU
38CHETANRAJ

Weitere ähnliche Inhalte

Was ist angesagt?

Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
Nithin Dev
 

Was ist angesagt? (20)

Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
construction project planing
 construction project planing construction project planing
construction project planing
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
 
MS Project
MS ProjectMS Project
MS Project
 
03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling03 Construction Project Planning and Scheduling
03 Construction Project Planning and Scheduling
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
Primavara
PrimavaraPrimavara
Primavara
 
Project Management using MS Project 2010
Project Management using MS Project 2010Project Management using MS Project 2010
Project Management using MS Project 2010
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Project management-planning and scheduling
Project management-planning and schedulingProject management-planning and scheduling
Project management-planning and scheduling
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
Project management
Project managementProject management
Project management
 
Construction scheduling & Cost control
Construction scheduling & Cost controlConstruction scheduling & Cost control
Construction scheduling & Cost control
 
Primavera P6
Primavera P6Primavera P6
Primavera P6
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 

Ähnlich wie Scheduling by using microsoft project 2013

Sharing Knowledge Microsoft Project 2013.pptx
Sharing Knowledge Microsoft Project 2013.pptxSharing Knowledge Microsoft Project 2013.pptx
Sharing Knowledge Microsoft Project 2013.pptx
LukasDhani
 
MIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project MMIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project M
IlonaThornburg83
 
Resume-Sanjay_Sahai-7
Resume-Sanjay_Sahai-7Resume-Sanjay_Sahai-7
Resume-Sanjay_Sahai-7
sanjay sahai
 

Ähnlich wie Scheduling by using microsoft project 2013 (20)

Planning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptxPlanning & Scheduling 222030008.pptx
Planning & Scheduling 222030008.pptx
 
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
Planning, Scheduling and Allocation of Resources for Multi – storiedStructure...
 
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
Planning and Scheduling of a Multi-Storeyed Residential Building with Convent...
 
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
Planning, Scheduling and Resource Optimization for A Villa by Using Ms-Projec...
 
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGSOPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
OPTIMAL PLANNING AND SCHEDULING OF HIGH RISE BUILDINGS
 
sample456.pptx
sample456.pptxsample456.pptx
sample456.pptx
 
Application of GIS in Construction Management
Application of GIS in Construction ManagementApplication of GIS in Construction Management
Application of GIS in Construction Management
 
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...IRJET-  	  Optimization of Time and Cost of Building Construction using Fast ...
IRJET- Optimization of Time and Cost of Building Construction using Fast ...
 
Sharing Knowledge Microsoft Project 2013.pptx
Sharing Knowledge Microsoft Project 2013.pptxSharing Knowledge Microsoft Project 2013.pptx
Sharing Knowledge Microsoft Project 2013.pptx
 
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-ProjectIRJET-  	  Planning and Scheduling for a Multi-Storied Building using MS-Project
IRJET- Planning and Scheduling for a Multi-Storied Building using MS-Project
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
 
MIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project MMIS485 Capstone Project in MIS 2MGT 400 - Project M
MIS485 Capstone Project in MIS 2MGT 400 - Project M
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
 
Resume-Sanjay_Sahai-7
Resume-Sanjay_Sahai-7Resume-Sanjay_Sahai-7
Resume-Sanjay_Sahai-7
 
Project Planning and Scheduling
Project Planning and SchedulingProject Planning and Scheduling
Project Planning and Scheduling
 
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
IRJET-  	  Optimized Project Planning and Scheduling of Multistorey BuildingIRJET-  	  Optimized Project Planning and Scheduling of Multistorey Building
IRJET- Optimized Project Planning and Scheduling of Multistorey Building
 
76 s201905
76 s20190576 s201905
76 s201905
 
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
Planning, Scheduling and Allocation of Resources for Multi-Storied Structure ...
 
Chapter 4
Chapter 4Chapter 4
Chapter 4
 

Kürzlich hochgeladen

Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
ciinovamais
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
Chris Hunter
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
heathfieldcps1
 

Kürzlich hochgeladen (20)

INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptxINDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
INDIA QUIZ 2024 RLAC DELHI UNIVERSITY.pptx
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Measures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and ModeMeasures of Central Tendency: Mean, Median and Mode
Measures of Central Tendency: Mean, Median and Mode
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
Making and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdfMaking and Justifying Mathematical Decisions.pdf
Making and Justifying Mathematical Decisions.pdf
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Z Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot GraphZ Score,T Score, Percential Rank and Box Plot Graph
Z Score,T Score, Percential Rank and Box Plot Graph
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
Ecological Succession. ( ECOSYSTEM, B. Pharmacy, 1st Year, Sem-II, Environmen...
 

Scheduling by using microsoft project 2013

  • 1. PROJECT REVIEW ON “SCHEDULING BY USING MICROSOFT PROJECT” Presenting by CHETANRAJ 1
  • 2. CONTENT • Introduction • Objectives • Literature Review • Methodology • Results & Discussions • Conclusion 2CHETANRAJ
  • 3. INTRODCTION Project management involves the application of various knowledge areas, tools and skills along with numerous techniques to congregate project requirements like duration and cost. The factors that affect project management are: • Project cost • Project time • Project scope • Project requirement 3CHETANRAJ
  • 4. MICROSOFT PROJECT • Microsoft Project is a project management software product, developed and sold by Microsoft. • It is designed to assist a project manager in developing a plan, assigning resources to tasks, tracking progress, managing the budget, and analyzing workloads. • Streamline project, resource, and portfolio management with Microsoft Project. Integrated planning tools help you keep track of projects and stay organized. 4CHETANRAJ
  • 5. OBJECTIVES • Collecting data and information. • Use of Microsoft Project in scheduling. • Prepare scheduling technique by network models (CPM). • Prepare construction sequence of work for Construction. • Estimating the time duration required to complete the individual activity. • Create Baseline & Tracking. • Identify risks in construction activities which causes delay. 5CHETANRAJ
  • 6. SCOPE • The Development of Planning and Scheduling in Construction industries. • The Project only focusing on sequence of work for building construction project. • The Project will carried based solely on one project scheduling software that is Microsoft Project. • The area of study only covered the ongoing site construction in xxxxxxxxx xxxxxxx. 6CHETANRAJ
  • 7. LITERATRE REVIEW AUTHOR NAME YEAR TITLE Monish Kumar K & Maheshwar S 2017 CONSTRUCTION PROJECT SCHEDULING OF MK APARTMENT USING MSP Shubham Laddha, Prerna Chanda & Sneha Khedekar 2017 PLANNING AND SCHEDULING OF A PROJECT BY MSP 2013 P M Wale, N D. Jain, N R Godhani & S R Beniwal 2015 PLANNING AND SCHEDULING OF PROJECT USING MICROSOFT PROJECT 7CHETANRAJ
  • 8. LITERATRE REVIEW Monish Kumar K (2017) Project on CONSTRUCTION PROJECT SCHEDULING OF MK APARTMENT USING MSP A two phase methodology is adapted in which the first phase comprise of the collection of basic information required for the schedule development and the second phase comprise of the development of a formidable schedule. Using MSP2013 as a construction project management tool, project planning is done accurately, this enables management to organize the resources required for the project effectively. 8CHETANRAJ
  • 9. LITERATRE REVIEW Shubham Laddha (2017) Research on PLANNING AND SCHEDULING OF A PROJECT USING MICROSOFT PROJECT 2013 Microsoft Project is the modern tool of Project Management that aid to overcome the obstacles faced owing to traditional way of Planning and Management. It helps for the optimum and effective organization of activities which helps to give the vision to complete the project in planned duration and within the Economy. 9CHETANRAJ
  • 10. LITERATRE REVIEW P M Wale (2015) analysed PLANNING AND SCHEDULING OF PROJECT USING MICROSOFT PROJECT USING MICROSOFT PROJECT 2013 by Case Study of a building in India. Construction of building using Traditional way proves to be uneconomical and consumes more time with many complexibility and enormous error which actual execution of the Project. Labour management becomes easier as the over allocated activities are levelled using the levelling option available in MSP 2013 10CHETANRAJ
  • 11. PROJECT BRIEF • Project: xxxxxx xxx xxxxxxxx xxxxxxxxx xxxx xxxx • Client: xxxxx xxxxxxxxxxx xxxxxx xxxxxxxx xxxx • Contractor: xxxxxx xxxxxxxxxxx xxxxxx xxxx xxxxxx • Project type: xxxxx xxxxxxxxxx xxxxxxx xxx xxxxx • Project Cost: xxxxxx • Place: xxxxxxxxxxx xxxxxxx xxxxxx xxxxxx xxxxxx 11CHETANRAJ
  • 12. PROJECT BRIEF General Details • RCC framed structure. • Brick work, interior and exterior cement plaster. • Well finished emulsion paint for interior and external walls. • Sub-contractors are involved in the construction process. • Water proofing treatment. • Highly Secured Building. 12CHETANRAJ
  • 13. THE COMPANY • Company Name: XXX XXX XXXXXXXX • Office: XXXXX XXXXXXXXX XXXXXXXXXX, BENGALURU-560065, KARNATAKA 13CHETANRAJ
  • 14. METHODOLOGY 1) Selection of project 2) The collection of data required 3) Starting a Project in Microsoft Project 2013 4) Providing Project Information 5) Developing Gantt Chart 6) Creating Calendars 14CHETANRAJ
  • 15. METHODOLOGY 7) Resource Management 8) Levelling the Activity and Resources 9) Calculate The Project 10) Create Baseline 11) Tracking 12) Results and Discussion 15CHETANRAJ
  • 16. 1) Selection of project • Benefits • Feasibility 16 2) The collection of data required • Basic Data • Key Components CHETANRAJ
  • 17. 3) Starting a Project in Microsoft Project • Get the Software MSP2013 17 4) Providing Project Information • Provide Title of the project, Company Name, Manager, Author Name, etc. • Provide Start Date CHETANRAJ
  • 18. 5) Developing Gantt Chart 18 MSP Schedule: List of activities with WBSCHETANRAJ
  • 19. Prepare Task List 19 Every task in the Construction of building is listed one by one by using Collected Data, Architecture drawing, and bill of quantity. Example: 1. Start, 2. Arrangement of electricity, 3. Install Temporary water Service, 115 tasks are prepared. CHETANRAJ
  • 20. Divided Task List 20 Construction activities Tasks are divided as • Mobilize On Site • Substructure • Superstructure • Water Supply & Sanitary Works • Painting • Final Cleanup And Inspection CHETANRAJ
  • 21. Link all Tasks with respect to WBS And Each WBS Activities code Defined 21 Example: Construction Activities Mobilize on site Start Arrangement of electricity Substructure Excavation WBS TASK NAME 1 1 Construction Activities 2 1.1 Mobilize on site 3 1.1.1 Start 4 1.1.2 Arrangement of electricity 5 1.2 Substructure 6 1.2.1 Excavation WBS Preparation WBS Activities code Defined at MSP CHETANRAJ
  • 22. Task Duration analysis Example: Total quantity of External Painting work = 320sqm ..A Productivity of 1 painter & 2 Helper = 13sqm per day ..B Available 5 painter ..C 10 helper Product per day = Available painters X Output per painter per day = 5 x 13 ..(B x C) = 65sqm ..D Task Duration = 320/65 = 4.9 = 5 days ..(A / D) 22CHETANRAJ
  • 23. 6) Creating Calendars 23 Change working time WindowCHETANRAJ
  • 24. MSP Schedule: Gantt Chart developed at right panel 24 Gantt Chart CHETANRAJ
  • 25. 7) Resource Management 25 • Work - human resource, or equipment rented by the hour or day. • Cost - time independent resources, like Airplane tickets. • Material - consumables like bricks, oil, concrete etc. CHETANRAJ
  • 26. 8) Levelling task resources • Over Allocation are on red  After levelling 26CHETANRAJ
  • 27. 9) Calculate The Project 27 • Renumbering WBS • Calculate the Project After you make a change 10) Create Baseline • Save plan • Compare with planned and actual process CHETANRAJ
  • 28. 11) Tracking 28 Updating finished Process as per the date. 12) Results And Discussion Project Report available after Tracking • Dashboard Reports • Resource Reports • Cost Reports • Progress Reports CHETANRAJ
  • 29. RESULTS AND DISCUSSION 29 Network diagram sheet CHETANRAJ
  • 30. RESULTS AND DISCUSSION 30 Critical Task at Reports CHETANRAJ
  • 31. RESULTS AND DISCUSSION 31 Cost Reports CHETANRAJ
  • 32. RESULTS AND DISCUSSION • Project schedule of 130 days are developed. • Activity Sequence is listed with duration and relationship with other tasks. • Project finish date will be delivered as per the calendar after providing start date. • Project duration can be calculated from finish date as well as start date. • Critical path obtained. • Over allocations are levelled. 32CHETANRAJ
  • 33. CONCLUSION • Microsoft Project 2003 is a very easy software to work with. Simple way to develop tasks and resources. • MSP helps to Identify Critical path of the project, as well as Helps to find the over allocated resources. • The results will be automatically calculated with tracking which allows to manage project. 33CHETANRAJ
  • 34. CONCLUSION • By Task sequencing and accurate scheduled connection among the tasks, the project length can be achieved without any interruption. • The Gantt charts will be a pure representation for the site engineers, easy performance of task and have arranged for the forthcoming tasks. • MSP provides Easy way to represent fast tracking of tasks 34CHETANRAJ
  • 35. FUTURE SCOPE • Once schedule is developed in MSP will allows to update for upcoming tasks. • Tracking continued until the end of the project for the best construction outcome. Every tracking process will provide earned value changes. • Allows the task comparison with the saved baselines. And with 11 available saves. • The MSP file are easy to save, share and backup same as MICROSOFT OFFICE Files. 35CHETANRAJ
  • 36. REFERENCES [1] Monish Kumar K, Maheshwar S, “Construction Project Scheduling of MK Apartment Using MSP”, IJRET, Volume 04 Issue 07, PP 2275-2279, July 2017 [2] Manisha N. Ghotnekar, Shashank U. Vanakudari, “Planning & Scheduling of Commercial Building Using Microsoft Project & Application of Principles of Theory of Constraints for Achieving High Efficiency Cutting edge Construction Project”, IRJET, Volume 04 Issue 07, PP 2545-2549, July 2017 [3] Rashmi J, Amey A Kelkar, Vishwanath K G, “Planning and scheduling of a multi-storeyed residential building with conventional execution approach as compared with application of project management techniques”, IRJET, Volume 04 Issue 07, PP 2682-2685, July 2017 [4] Shubham Laddha, Prerna Chanda and Sneha Khedekar, “Planning And Scheduling Of Project Using Microsoft Project 2013”, IJAR 10.21474/IJAR01/4394, PP 161-168, June 2017 [5] S.Ragavi, Dr.R.N.Uma, “Review of project management softwares-ms project and primavera” IJRET, Volume 03 Issue 11, PP 1260-1263, Nov -2016 36CHETANRAJ
  • 37. REFERENCES [6] P M Wale, N D. Jain, N R Godhani, S R Beniwal, “Planning Scheduling of Project using Microsoft Project”, IOSR, Volume 12, Issue 3 Ver. III, PP 57-63, Jun 2015 [7] Rhuta Joshi, Prof. V. Z. Patil “Resource Scheduling of Construction Project Case Study” IJSR Volume 4 Issue 5, PP 563-568, May 2015 [8] Ashwini R. Patil, Smita V. Pataskar, “Analyzing Material Management Techniques on Construction Project”, IJEIT, Volume 3, Issue 4, PP 96-100, October 2013 [9] C. Chantrapornchai, D. Sawangkokrouk and T Leadprathom, “Project Management Software Allocation and Scheduling Aspects”, IJSST, Vol. 6, No. 3, PP 35-42, June 2013 [10] P. Dayakar , “Study On Project Management Of Ongoing Construction Project Using Msp - Sub Structure”, IJBTT, Volume2 Issue 5, PP 11-23, Oct 2012 37CHETANRAJ