Sam Hassoun GLA presentation to CalAPA Fall Conference Oct 27 2022

  1. SWOT To eradicate arbitration and litigation from the construction industry Our Mission:
  2. Work Is Love Made Visible The Goal is not to Live Forever, But to Create Something That Does Khalil Gibran
  3. 3 Abundance!
  4. 4
  5. Middle-Mile Broadband Initiative First Mile Global Internet Networks Broadband Reliable, high-speed internet that is always on Middle Mile The physical infrastructure required to connect global internet networks with local networks Last Mile The final leg of a network that allows local carriers to provide service to homes, businesses, and community institutions
  6. Middle-Mile Broadband Initiative Building the Network Broadband Middle Mile Network State Highways District Boundaries
  7. Aging Workforce 1 Lack of Quality Workers 2 Attracting Talent 3
  8. Your Challenge: Keeping Pace with Technology!
  9. Transportation Infrastructure 19
  10. Multi-Modal Transportation Solutions 20
  11. 2015 2020
  12. Question: ∙ How Much Did You Put In Your Bid for Disputes?
  13. ∙ Dispute Prevention vs Dispute Resolution ?
  14. SWOT To eradicate arbitration and litigation from the construction industry Our Mission:
  15. ∙ Demonetize & Democratize Partnering
  16. Is Partnering a Cost or Investment? Average Project: $50M-$100M Average Duration: 36 Months Partnering Cost: $2,500/Month ($90,000/Project) Average Claim (2020-2021): $37.9M ROI: 0.0023 (0.23%) of an Average Claim 0.0012 (0.12%) of an Average Project Budget
  17. Collaborative Dispute Mitigation (CDM) – Partnering Spec Dispute Prevention Dispute Resolution ∙ Executive Alignment ∙ Partnering Kick Off & Follow Ups ∙ Monthly & Weekly Goals Tracking & Measurements ∙ Risk Mitigation ∙ Facilitated Dispute Resolution (FDR) ∙ Mediation ROI: 0.0012 (0.12%) of Project Budget
  18. ∙ My Project Under $10M – Under 200 WD ∙ No Partnering Spec ∙ No Partnering Budget! Classic Scenarios
  19. Projects Under $10M Findings ∙ Mostly Small & DBE Contractors ∙ No Partnering Training or Culture (RE or PM) ∙ Partnering is a Cost Factor ∙ Outcome: 80% of Delays & Claims Projects with No Partnering
  20. Partnering Under $10M Regardless of #of WD $100/Month/$1M Fee Scale
  21. Partnering Under $10M & Under 200 WD ∙ Virtual Kickoff & Monthly Sessions ∙ Part of the Weekly Meeting Agenda ∙ Measurement & Accountability Tools - DashTech
  22. Question ∙ What Do Contractors Expect From Owners?
  23. Legitimate Industry Expectations 1. Be Treated Fairly – No Open Checkbook 2. Keep the Job Moving – Avoid Delays 3. Collaboratively Resolve Project Disputes Outcome: Contractor Keeps Profit Margin
  24. Some will Never Change – Why Should I?
  25. Plan - A ∙ Invest in Partnering even if not in the Spec ∙ Pursue VE & Innovation – Always! ∙ Double Down on Dispute Prevention & Resolution (FDR, DRB ..etc.) ∙ Utilize Escalation Ladder AND Your Partnering Facilitator
  26. Or: Plan B 33% of Your Time Dealing with Conflict
  27. Your Role ∙ Sharpen Your Partnering Skills ∙ Be the Leader in: Mission Zero Disputes Project End ∙ Owners & Industry Contractors Will Follow Your Lead
  28. Construction Industry Brand Ambassador
  29. SWOT Be the CHANGE you want to see in the world Mahatma Gandhi
  30. Work Is Love Made Visible The Goal is not to Live Forever, But to Create Something That Does Khalil Gibran
  31. SWOT To eradicate arbitration and litigation from the construction industry Our Mission: Thank YOU!