From Discontent to UK Content
7 October 2015
Alun Roberts
2/21
About BVG Associates
Selected clientsBVG Associates
• Market and supply chain
• Analysis and
forecasting
• Strategic advice
• Business and supply
chain development
• Economics
• Socioeconomics and
local benefits
• Technology and project
economic modelling
• Policy and local content
assessment
• Technology
• Engineering services
• Due diligence
• Strategy and R&D
support
© BVG Associates 2015
3/21© BVG Associates 2015
4/21
I’m going to talk about …
… the weather
• Why we are here
• How and where UK content will be used
• The reporting framework – how it works
• The data gathering methodology
• The controversial bit
• Concluding thoughts
From discontent … to glorious summer
© BVG Associates 2015
5/21
Why we are here
Once a “target” has been announced, DECC realised that there needed to be a way of measuring
© BVG Associates 2015
• At its meeting on 6 February 2012, the
Offshore Wind Developers Forum (OWDF)
(now reconstituted as the Offshore Wind
Industry Council) agreed to publish a vision for:
“The UK to be the centre for offshore wind
technology and deployment, with a competitive
supply chain in the UK, providing over 50% of the
content of offshore wind farm projects”
• But what does it mean and how do you
measure it?
• 50% of what?
• How to you calculate it?
• How is data gathered and reported?
• DECC, Crown Estate and RUK asked BVGA to
come up with a method
• Industry should take great credit for adopting a
formal and consistent process for measuring it.
A challenge for civil servants
• Deployment and building an industry was a
key objective early on – openness of the UK
market one of its attractions.
• There is political pressure on all major
infrastructure projects - the wind industry is
not unique.
• There are different measures of economic
benefit – it’s ultimately about jobs
• Tends to be ambiguity about job forecasts –
they always seem suspiciously high
Significant shift from emphasis on deployment to
securing economic benefit (with lower cost of)
6/21
How and where UK content will be used
The UK content methodology and supply chain plans are distinct but related initiatives
© BVG Associates 2015
Perception in the UK government that
the UK had successfully created a
market but the economic benefits
were not being realised
Offshore wind industrial
strategy
Offshore Wind Developers
Forum (now Industrial Council)
50% UK content “vision”
UK content methodology
Electricity Market Reform
CfD Supply Chain Plans
7/21
The reporting framework
RenewableUK has taken on the job of gathering and publishing the data
Aim has been to minimise the amount of data needed
© BVG Associates 2015
• Process ‘live’ from January 2015
• Four figures (percentages only) will be published
for UK content:
• UK content in DEVEX
• UK content in CAPEX
• UK content in OPEX (undiscounted)
• UK content in TOTEX (total expenditure)
• Option to provide more detailed data – subdivided
into about 20 categories.
• Data published as a rolling five year average
8/21
RenewableUK reporting framework – how it works
© BVG Associates 2015
No action required
RUK requests new data
on UK Content
Asset Owners complete
data collection process
according to
methodology
Data submitted to RUK
and aggregated for
publication in Year 0
RUK asks if there has
been significant change
since FID
Wind Farm has
reached works
completion in
Year -1?
Wind Farm has
reached FID in
Year -1?
NoYes
No
Asset Owners update
data according to
methodology
Yes
Significant
changes in
expenditure?
No
Yes
There will be an annual cycle
9/21
RenewableUK reporting framework – data aggregation
Data from different wind farms will be weighted by generating capacity
© BVG Associates 2015
AggregatedUK
content published
in year +1
Wind farm at
FID in given
year 0
Wind farm at
FID in given
year 0
Wind farm at
FID in given
year -1
Wind farm at
FID in year -1
Wind farm at
FID in year -2
Wind farm at
FID in year -2
Wind farm at
FID in year -3
Wind farm at
FID in year -3
Wind farm at
FID in year -4
Wind farm at
FID in year -4
10/21
RenewableUK reporting framework – data aggregation
Data from different wind farms will be weighted by generating capacity
© BVG Associates 2015
AggregatedUK
content published
in year +1
Wind farm at
FID in given
year 0
Wind farm at
FID in given
year 0
Wind farm at
FID in given
year -1
Wind farm at
FID in year -1
Wind farm at
FID in year -2
Wind farm at
FID in year -2
Wind farm at
FID in year -3
Wind farm at
FID in year -3
Wind farm at
FID in year -4
Wind farm at
FID in year -4
11/21
Methodology overview
Ready to go after three years in discussion
• Definitions
• Scope
• Rules
• How to gather data – with specific guidance
• Principles
• Simple
• Clear
• Consistent
• Minimal burden
• Respect commercial confidentiality
• No-one has to say how much profit was made or
how much was paid to subsuppliers
• Tried to formalise “common sense”
The document’s coverage
© BVG Associates 2015
12/21© BVG Associates 2015
Wind Farm Has the following attributes:
• It is developed through a single leasing option awarded by The Crown Estate.
• It has two parts: the Generation Asset and the Transmission Asset
• It has a discrete final investment decision (FID), procurement process and construction phase
Wind Farm
Asset
Owner
The company that owns either the Wind Farm Generation Asset (the Generation Asset Owner) or
the Transmission Asset (the offshore transmission owner (OFTO)) during development, construction
or operation
Customer A purchaser of Products for the Wind Farm, which may be a Wind Farm Asset Owner or a Supplier
at any tier of the supply chain (except the bottom tier)
Supplier A provider of products to a Customer. A Subsupplier is a company that is two or more steps down
the supply chain from the Customer. A tier 1 Supplier is one that is directly Contracted by the Wind
Farm Asset Owner.
Contract An agreement between a Customer and a Supplier to provide a Product for an agreed value. It
covers the aggregated payment by the Customer in DEVEX, CAPEX or OPEX to the Supplier. The
Contract value could therefore be made up of a number of transactions.
A Contract may be between a Customer and an external or internal Supplier.
UK Content The %age of the total undiscounted expenditure by the Wind Farm Asset Owner on a Wind Farm
that is ultimately spent through Contracts awarded to companies operating in the UK.
Key definitions
Clarity is vital to the methodology
13/21© BVG Associates 2015
A UK content metaphor
To make the presentation less dry
Non-UKUK
14/21© BVG Associates 2015
The process
UK content is ultimately estimated for all spend
• Contracts less than £10 million? Make an
estimate based on:
• Any information provided by the
Supplier
• The invoice address of the Supplier
• The currency in which the payment
was made
• The Customer’s knowledge of its
Supplier’s activities and Subsuppliers
• The Customer’s knowledge of the
activities and Subsuppliers of similar
companies
Process starts with the developer
Estimate UK content
Review each
contract in turn
Wind farm
reached FID
Asks supplier to report
UK content
Value ≥£10
million?
No
Yes
Assign to supply chain
area* and add data to
data gathering tool
15/21© BVG Associates 2015
Customer
SupplierA
Subsupplier
A1
Subsupplier
A2
Subsupplier
A3
Value
≥£10million
Value < £10
million
Supplier B
Subsupplier
B1
Subsupplier
B2
Subsupplier
B3
Subsupplier
B4
Supplier C
Subsupplier
C1
Subsupplier
C2
Subsupplier
C3
Supplier D
Subsupplier
D1
Subsupplier
D2
Subsupplier
D3
Supplier E Supplier F Supplier G Supplier H
A theoretical example
Expected that few companies below wind farm owner’s tier 2s will need to report
• For the purposes of this presentation:
• Contracts ≥£10 million are “large”
• Contracts <£10 million are “small”
:
16/21© BVG Associates 2015
Supplier Contract
value
(£million)
UK Content in
Contract
% of base cost
in Contract
Contribution of
Supplier’s Contract
to UK Content
Subsupplier Subcontract
(£million)
% of base cost
in Subcontract
UK Content in
Subcontract
A 12 71% 15% 10.6% A1 6 55% 85%
A2 4 36% 55%
A3 1 9% 45%
Margin 1
B 20 47% 25% 11.7% B1 10 43% 25%
B2 5 29% 75%
B3 3 14% 45%
B4 3 14% 75%
Margin -1
C 15 32% 19% 6.1% C1 7 52% 25%
C2 4.5 33% 50%
C3 2 15% 20%
Margin 1.5
D 11 22% 14% 2.9% D1 4 45% 40%
D2 3 33% 5%
D3 2 22% 10%
Margin 2
E 8 46% 10% 4.6%
F 7 85% 9% 7.4%
G 4 65% 5% 3.3%
H 3 90% 4% 3.4%
Base cost 80
Margin 20
Total 100 50.0%
A theoretical example
17/21
Specific challenges
Two types of challenge: the UK content calculation and the attribution of cost to the wind farm
• Large component - project sourced (could be a turbine)
• Large component - dual sourced (could be a foundation)
• Large component – framework (could be a cable)
• Large component – internal (could be a blade)
• Factory running costs
• Corporate overhead
• Factory or vessel investment
• R&D
• Transport and storage
• Rent
A supplier is awarded a contract and fulfils it with a number of subcontracts
© BVG Associates 2015
18/21
Small contracts
Assessment should be made based on a knowledge of the company
© BVG Associates 2015
Type of Product Examples UK Content assumption
for UK-based supplier
Desk-based services Consultancy
PR
Legal
Insurance
95%
Non-desk-based services using low-cost
equipment likely to be imported
Electrical services
Lifting services
70%
Non-desk-based services using high-cost
equipment likely to be UK manufactured
Crew transfer vessels
Transport
85%
19/21
A vision realised?
UK investments will impact soon – but hard to see UK content rising without a bigger market
© BVG Associates 2015
0%
25%
50%
75%
100%
2010 2012 2014 2016 2018 2020
Low CAPEX+DEVEX Low OPEX Low TOTEX
Average CAPEX+DEVEX Average OPEX Average TOTEX
High CAPEX+DEVEX High OPEX High TOTEX
Yearof final investment decision
UKcontent
Not based on real data
20/21
What about the non-UK content?
What if we looked at the origin of all components and services?
© BVG Associates 2015
UK
44%
Germany
16%
Denmark
14%
Netherlands
4%
Belgium
1%
Other Europe
9%
Other
12%
Not based on real data
National content in TOTEX
21/21
Concluding thoughts
© BVG Associates 2015
• 50% UK content not far away – but there shouldn’t be complacency
• Data published as a rolling five year average means that the impact of new UK investments will not
be evident for several years – three years would be better
• Detailed data is only optional – it’s not much more work and can help identify areas for action
• Everyone’s job will be easier if companies spend a little time now getting prepared:
• Talking with suppliers
• Making data gathering tools
• Briefing contract managers
• BVGA is always here to help

Weitere ähnliche Inhalte

Was ist angesagt?

Green Foods presentation
Green Foods presentationGreen Foods presentation
Green Foods presentation
Chian Wen Chan
 
SEAI - National Energy Research and Policy Conference 2021 - Session 2
SEAI - National Energy Research and Policy Conference 2021 - Session 2SEAI - National Energy Research and Policy Conference 2021 - Session 2
SEAI - National Energy Research and Policy Conference 2021 - Session 2
SustainableEnergyAut
 
Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...
Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...
Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...
KTN
 
Britain chp market
Britain chp marketBritain chp market
Britain chp market
guigu85c
 
G20 Workshop Session ii
G20 Workshop Session iiG20 Workshop Session ii
G20 Workshop Session ii
nooone
 
Sasha Davies, head of strategic development Wales, Horizon Nuclear Power
Sasha Davies, head of strategic development Wales, Horizon Nuclear PowerSasha Davies, head of strategic development Wales, Horizon Nuclear Power
Sasha Davies, head of strategic development Wales, Horizon Nuclear Power
Emma Pawlowski
 

Was ist angesagt? (20)

141208 AER Public Forum - TransGrid Revenue Proposal
141208 AER Public Forum - TransGrid Revenue Proposal141208 AER Public Forum - TransGrid Revenue Proposal
141208 AER Public Forum - TransGrid Revenue Proposal
 
Acquisition of a strategic stake in De Nora
Acquisition of a strategic stake in De NoraAcquisition of a strategic stake in De Nora
Acquisition of a strategic stake in De Nora
 
UK Catalysis: Innovation opportunities for an enabling technology
UK Catalysis: Innovation opportunities for an enabling technologyUK Catalysis: Innovation opportunities for an enabling technology
UK Catalysis: Innovation opportunities for an enabling technology
 
Green Foods presentation
Green Foods presentationGreen Foods presentation
Green Foods presentation
 
SEAI - National Energy Research and Policy Conference 2021 - Session 2
SEAI - National Energy Research and Policy Conference 2021 - Session 2SEAI - National Energy Research and Policy Conference 2021 - Session 2
SEAI - National Energy Research and Policy Conference 2021 - Session 2
 
CCS in H2020: Overview, Lessons Learned and Next Steps - webinar hosted by th...
CCS in H2020: Overview, Lessons Learned and Next Steps - webinar hosted by th...CCS in H2020: Overview, Lessons Learned and Next Steps - webinar hosted by th...
CCS in H2020: Overview, Lessons Learned and Next Steps - webinar hosted by th...
 
Refit london Hadjidakis
Refit london HadjidakisRefit london Hadjidakis
Refit london Hadjidakis
 
2020 status report building integrated photovoltaics BIPV
2020 status report building integrated photovoltaics BIPV2020 status report building integrated photovoltaics BIPV
2020 status report building integrated photovoltaics BIPV
 
Ben Allwright - Flowmatik
Ben Allwright - FlowmatikBen Allwright - Flowmatik
Ben Allwright - Flowmatik
 
Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...
Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...
Zero Emission Road Freight: Enabling a Future Large Scale Demonstration - Fun...
 
Quantifying the Benefits of Meteorological services presentation, Claire Ross...
Quantifying the Benefits of Meteorological services presentation, Claire Ross...Quantifying the Benefits of Meteorological services presentation, Claire Ross...
Quantifying the Benefits of Meteorological services presentation, Claire Ross...
 
Britain chp market
Britain chp marketBritain chp market
Britain chp market
 
G20 Workshop Session ii
G20 Workshop Session iiG20 Workshop Session ii
G20 Workshop Session ii
 
EPC in the Irish Prison Service
EPC in the Irish Prison ServiceEPC in the Irish Prison Service
EPC in the Irish Prison Service
 
Sasha Davies, head of strategic development Wales, Horizon Nuclear Power
Sasha Davies, head of strategic development Wales, Horizon Nuclear PowerSasha Davies, head of strategic development Wales, Horizon Nuclear Power
Sasha Davies, head of strategic development Wales, Horizon Nuclear Power
 
Snam - 2018 9M results and 2019 - 2022 strategic plan
Snam - 2018 9M results and 2019 - 2022 strategic plan Snam - 2018 9M results and 2019 - 2022 strategic plan
Snam - 2018 9M results and 2019 - 2022 strategic plan
 
PSI AG - DZ Bank Sustainable Technologies Conference
PSI AG - DZ Bank Sustainable Technologies ConferencePSI AG - DZ Bank Sustainable Technologies Conference
PSI AG - DZ Bank Sustainable Technologies Conference
 
2014 Enbridge Day - Enbridge Gas Distribution
2014 Enbridge Day - Enbridge Gas Distribution2014 Enbridge Day - Enbridge Gas Distribution
2014 Enbridge Day - Enbridge Gas Distribution
 
Mike Kiely - The Bit Commons
Mike Kiely - The Bit CommonsMike Kiely - The Bit Commons
Mike Kiely - The Bit Commons
 
Subject: Ex-post impact evaluations of energy efficiency policies in Europe
Subject:	Ex-post impact evaluations of energy efficiency policies in EuropeSubject:	Ex-post impact evaluations of energy efficiency policies in Europe
Subject: Ex-post impact evaluations of energy efficiency policies in Europe
 

Andere mochten auch (7)

Ghadeer04 05of11
Ghadeer04 05of11Ghadeer04 05of11
Ghadeer04 05of11
 
Daycare level i.PDF
Daycare level i.PDFDaycare level i.PDF
Daycare level i.PDF
 
Urologia cto 7
Urologia cto 7Urologia cto 7
Urologia cto 7
 
Direito do cosumidor pgdf
Direito do cosumidor pgdfDireito do cosumidor pgdf
Direito do cosumidor pgdf
 
India now-vol-1-issue-02-june-july-2010
India now-vol-1-issue-02-june-july-2010India now-vol-1-issue-02-june-july-2010
India now-vol-1-issue-02-june-july-2010
 
Shipping industry in India
Shipping industry in IndiaShipping industry in India
Shipping industry in India
 
Ind nan 2012
Ind nan 2012Ind nan 2012
Ind nan 2012
 

Ähnlich wie From Discontent to UK Content

Webinar: The business case for CCS in the power industry: a case study of the...
Webinar: The business case for CCS in the power industry: a case study of the...Webinar: The business case for CCS in the power industry: a case study of the...
Webinar: The business case for CCS in the power industry: a case study of the...
Global CCS Institute
 
Fy 15 results_presentation
Fy 15 results_presentationFy 15 results_presentation
Fy 15 results_presentation
absmartkarma
 

Ähnlich wie From Discontent to UK Content (20)

Opportunities in the journey to ‘subsidy free’
Opportunities in the journey to ‘subsidy free’ Opportunities in the journey to ‘subsidy free’
Opportunities in the journey to ‘subsidy free’
 
Does the permitting process in France need a further overhaul?
Does the permitting process in France need a further overhaul?Does the permitting process in France need a further overhaul?
Does the permitting process in France need a further overhaul?
 
Innovation landscape All Energy 2017
Innovation landscape All Energy 2017Innovation landscape All Energy 2017
Innovation landscape All Energy 2017
 
UK offshore wind vision of the market and technology development Giles Hundl...
UK offshore wind  vision of the market and technology development Giles Hundl...UK offshore wind  vision of the market and technology development Giles Hundl...
UK offshore wind vision of the market and technology development Giles Hundl...
 
Driving the Electric Revolution: Supply Chains for Net Zero - Competition Bri...
Driving the Electric Revolution: Supply Chains for Net Zero - Competition Bri...Driving the Electric Revolution: Supply Chains for Net Zero - Competition Bri...
Driving the Electric Revolution: Supply Chains for Net Zero - Competition Bri...
 
Alan Duncan's All Energy 2017 Offshore wind: the importance of the supply chain
Alan Duncan's All Energy 2017 Offshore wind: the importance of the supply chainAlan Duncan's All Energy 2017 Offshore wind: the importance of the supply chain
Alan Duncan's All Energy 2017 Offshore wind: the importance of the supply chain
 
Catalysing Green Innovation: Strand 1, advancing PEMD supply chain
Catalysing Green Innovation: Strand 1, advancing PEMD supply chainCatalysing Green Innovation: Strand 1, advancing PEMD supply chain
Catalysing Green Innovation: Strand 1, advancing PEMD supply chain
 
THE VALUE OF WIND ENERGY TO IRELAND - Patrick Mohr, poyry
THE VALUE OF WIND ENERGY TO IRELAND - Patrick Mohr, poyryTHE VALUE OF WIND ENERGY TO IRELAND - Patrick Mohr, poyry
THE VALUE OF WIND ENERGY TO IRELAND - Patrick Mohr, poyry
 
Catalysing Green Innovation Strand 2
Catalysing Green Innovation Strand 2Catalysing Green Innovation Strand 2
Catalysing Green Innovation Strand 2
 
Between a ROC and a hard place : UK content and EMR Alun Roberts 12 June 2014
Between a ROC and a hard place :  UK content and EMR Alun Roberts 12 June 2014Between a ROC and a hard place :  UK content and EMR Alun Roberts 12 June 2014
Between a ROC and a hard place : UK content and EMR Alun Roberts 12 June 2014
 
Webinar: The business case for CCS in the power industry: a case study of the...
Webinar: The business case for CCS in the power industry: a case study of the...Webinar: The business case for CCS in the power industry: a case study of the...
Webinar: The business case for CCS in the power industry: a case study of the...
 
Offshore Cost of Energy NREL WESE Workship Bruce Valpy 14 Jan 2015
Offshore Cost of Energy NREL WESE Workship Bruce Valpy 14 Jan 2015Offshore Cost of Energy NREL WESE Workship Bruce Valpy 14 Jan 2015
Offshore Cost of Energy NREL WESE Workship Bruce Valpy 14 Jan 2015
 
Industrial Energy Transformational Fund Phase 2 Spring 2022 - Competition Bri...
Industrial Energy Transformational Fund Phase 2 Spring 2022 - Competition Bri...Industrial Energy Transformational Fund Phase 2 Spring 2022 - Competition Bri...
Industrial Energy Transformational Fund Phase 2 Spring 2022 - Competition Bri...
 
Fy 15 results_presentation
Fy 15 results_presentationFy 15 results_presentation
Fy 15 results_presentation
 
UK Construction in 2015 #FISorg
UK Construction in 2015 #FISorgUK Construction in 2015 #FISorg
UK Construction in 2015 #FISorg
 
Dutch Power - 26 maart 2024 - Diederik Peereboom - T&D Europe
Dutch Power - 26 maart 2024 - Diederik Peereboom - T&D EuropeDutch Power - 26 maart 2024 - Diederik Peereboom - T&D Europe
Dutch Power - 26 maart 2024 - Diederik Peereboom - T&D Europe
 
Stepping stones for floating foundations r02
Stepping stones for floating foundations r02Stepping stones for floating foundations r02
Stepping stones for floating foundations r02
 
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New ParadigmFERC Order 1000: Understanding Transmission Planning in a New Paradigm
FERC Order 1000: Understanding Transmission Planning in a New Paradigm
 
RE:FIT LONDON – Making London a resilient, sustainable and resource efficient...
RE:FIT LONDON – Making London a resilient, sustainable and resource efficient...RE:FIT LONDON – Making London a resilient, sustainable and resource efficient...
RE:FIT LONDON – Making London a resilient, sustainable and resource efficient...
 
Challenges and best practices in financing to accelerate industry decarbonisa...
Challenges and best practices in financing to accelerate industry decarbonisa...Challenges and best practices in financing to accelerate industry decarbonisa...
Challenges and best practices in financing to accelerate industry decarbonisa...
 

Mehr von BVG Associates

Mehr von BVG Associates (15)

Rationing offshore wind in a post-subsidy world
Rationing offshore wind in a post-subsidy worldRationing offshore wind in a post-subsidy world
Rationing offshore wind in a post-subsidy world
 
Floating offshore wind and LCOE Giles Hundleby
Floating offshore wind and LCOE Giles HundlebyFloating offshore wind and LCOE Giles Hundleby
Floating offshore wind and LCOE Giles Hundleby
 
Bigger, larger, heavier
Bigger, larger, heavierBigger, larger, heavier
Bigger, larger, heavier
 
Innovation and cost reduction in offshore wind
Innovation and cost reduction in offshore windInnovation and cost reduction in offshore wind
Innovation and cost reduction in offshore wind
 
Learning to love supply chain plans
Learning to love supply chain plansLearning to love supply chain plans
Learning to love supply chain plans
 
Offshore wind innovation for cost reduction Wind Europe Summit 2016 Freeman/KIC
Offshore wind innovation for cost reduction Wind Europe Summit 2016 Freeman/KICOffshore wind innovation for cost reduction Wind Europe Summit 2016 Freeman/KIC
Offshore wind innovation for cost reduction Wind Europe Summit 2016 Freeman/KIC
 
Atlantic stakeholder platform conference MARIBE presentation
Atlantic stakeholder platform conference MARIBE presentationAtlantic stakeholder platform conference MARIBE presentation
Atlantic stakeholder platform conference MARIBE presentation
 
Can Combining with Other Blue Sectors Further Reduce Offshore Wind's LCOE?
Can Combining with Other Blue Sectors Further Reduce Offshore Wind's LCOE?Can Combining with Other Blue Sectors Further Reduce Offshore Wind's LCOE?
Can Combining with Other Blue Sectors Further Reduce Offshore Wind's LCOE?
 
Where did the "The Saudi Arabia of Renewables' story go wrong?
Where did the "The Saudi Arabia of Renewables' story go wrong?Where did the "The Saudi Arabia of Renewables' story go wrong?
Where did the "The Saudi Arabia of Renewables' story go wrong?
 
Will combining sectors deliver blue growth
Will combining sectors deliver blue growthWill combining sectors deliver blue growth
Will combining sectors deliver blue growth
 
Adu all energy diversification 160505
Adu all energy diversification 160505Adu all energy diversification 160505
Adu all energy diversification 160505
 
Bvga hundleby icoe 2016
Bvga hundleby icoe 2016Bvga hundleby icoe 2016
Bvga hundleby icoe 2016
 
Creating data harmonisation between seven wind farms Martin Elliot 20 Novembe...
Creating data harmonisation between seven wind farms Martin Elliot 20 Novembe...Creating data harmonisation between seven wind farms Martin Elliot 20 Novembe...
Creating data harmonisation between seven wind farms Martin Elliot 20 Novembe...
 
Offshore wind farms - can the industry deliver (again) Bruce Valpy October 2010
Offshore wind farms - can the industry deliver (again) Bruce Valpy October 2010Offshore wind farms - can the industry deliver (again) Bruce Valpy October 2010
Offshore wind farms - can the industry deliver (again) Bruce Valpy October 2010
 
Offshore wind technology cost reduction one year on Bruce Valpy Feb 2013
Offshore wind technology cost reduction   one year on  Bruce Valpy Feb 2013Offshore wind technology cost reduction   one year on  Bruce Valpy Feb 2013
Offshore wind technology cost reduction one year on Bruce Valpy Feb 2013
 

Kürzlich hochgeladen

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
Tonystark477637
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Christo Ananth
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Kürzlich hochgeladen (20)

Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 

From Discontent to UK Content

  • 1. 1/21 From Discontent to UK Content 7 October 2015 Alun Roberts
  • 2. 2/21 About BVG Associates Selected clientsBVG Associates • Market and supply chain • Analysis and forecasting • Strategic advice • Business and supply chain development • Economics • Socioeconomics and local benefits • Technology and project economic modelling • Policy and local content assessment • Technology • Engineering services • Due diligence • Strategy and R&D support © BVG Associates 2015
  • 4. 4/21 I’m going to talk about … … the weather • Why we are here • How and where UK content will be used • The reporting framework – how it works • The data gathering methodology • The controversial bit • Concluding thoughts From discontent … to glorious summer © BVG Associates 2015
  • 5. 5/21 Why we are here Once a “target” has been announced, DECC realised that there needed to be a way of measuring © BVG Associates 2015 • At its meeting on 6 February 2012, the Offshore Wind Developers Forum (OWDF) (now reconstituted as the Offshore Wind Industry Council) agreed to publish a vision for: “The UK to be the centre for offshore wind technology and deployment, with a competitive supply chain in the UK, providing over 50% of the content of offshore wind farm projects” • But what does it mean and how do you measure it? • 50% of what? • How to you calculate it? • How is data gathered and reported? • DECC, Crown Estate and RUK asked BVGA to come up with a method • Industry should take great credit for adopting a formal and consistent process for measuring it. A challenge for civil servants • Deployment and building an industry was a key objective early on – openness of the UK market one of its attractions. • There is political pressure on all major infrastructure projects - the wind industry is not unique. • There are different measures of economic benefit – it’s ultimately about jobs • Tends to be ambiguity about job forecasts – they always seem suspiciously high Significant shift from emphasis on deployment to securing economic benefit (with lower cost of)
  • 6. 6/21 How and where UK content will be used The UK content methodology and supply chain plans are distinct but related initiatives © BVG Associates 2015 Perception in the UK government that the UK had successfully created a market but the economic benefits were not being realised Offshore wind industrial strategy Offshore Wind Developers Forum (now Industrial Council) 50% UK content “vision” UK content methodology Electricity Market Reform CfD Supply Chain Plans
  • 7. 7/21 The reporting framework RenewableUK has taken on the job of gathering and publishing the data Aim has been to minimise the amount of data needed © BVG Associates 2015 • Process ‘live’ from January 2015 • Four figures (percentages only) will be published for UK content: • UK content in DEVEX • UK content in CAPEX • UK content in OPEX (undiscounted) • UK content in TOTEX (total expenditure) • Option to provide more detailed data – subdivided into about 20 categories. • Data published as a rolling five year average
  • 8. 8/21 RenewableUK reporting framework – how it works © BVG Associates 2015 No action required RUK requests new data on UK Content Asset Owners complete data collection process according to methodology Data submitted to RUK and aggregated for publication in Year 0 RUK asks if there has been significant change since FID Wind Farm has reached works completion in Year -1? Wind Farm has reached FID in Year -1? NoYes No Asset Owners update data according to methodology Yes Significant changes in expenditure? No Yes There will be an annual cycle
  • 9. 9/21 RenewableUK reporting framework – data aggregation Data from different wind farms will be weighted by generating capacity © BVG Associates 2015 AggregatedUK content published in year +1 Wind farm at FID in given year 0 Wind farm at FID in given year 0 Wind farm at FID in given year -1 Wind farm at FID in year -1 Wind farm at FID in year -2 Wind farm at FID in year -2 Wind farm at FID in year -3 Wind farm at FID in year -3 Wind farm at FID in year -4 Wind farm at FID in year -4
  • 10. 10/21 RenewableUK reporting framework – data aggregation Data from different wind farms will be weighted by generating capacity © BVG Associates 2015 AggregatedUK content published in year +1 Wind farm at FID in given year 0 Wind farm at FID in given year 0 Wind farm at FID in given year -1 Wind farm at FID in year -1 Wind farm at FID in year -2 Wind farm at FID in year -2 Wind farm at FID in year -3 Wind farm at FID in year -3 Wind farm at FID in year -4 Wind farm at FID in year -4
  • 11. 11/21 Methodology overview Ready to go after three years in discussion • Definitions • Scope • Rules • How to gather data – with specific guidance • Principles • Simple • Clear • Consistent • Minimal burden • Respect commercial confidentiality • No-one has to say how much profit was made or how much was paid to subsuppliers • Tried to formalise “common sense” The document’s coverage © BVG Associates 2015
  • 12. 12/21© BVG Associates 2015 Wind Farm Has the following attributes: • It is developed through a single leasing option awarded by The Crown Estate. • It has two parts: the Generation Asset and the Transmission Asset • It has a discrete final investment decision (FID), procurement process and construction phase Wind Farm Asset Owner The company that owns either the Wind Farm Generation Asset (the Generation Asset Owner) or the Transmission Asset (the offshore transmission owner (OFTO)) during development, construction or operation Customer A purchaser of Products for the Wind Farm, which may be a Wind Farm Asset Owner or a Supplier at any tier of the supply chain (except the bottom tier) Supplier A provider of products to a Customer. A Subsupplier is a company that is two or more steps down the supply chain from the Customer. A tier 1 Supplier is one that is directly Contracted by the Wind Farm Asset Owner. Contract An agreement between a Customer and a Supplier to provide a Product for an agreed value. It covers the aggregated payment by the Customer in DEVEX, CAPEX or OPEX to the Supplier. The Contract value could therefore be made up of a number of transactions. A Contract may be between a Customer and an external or internal Supplier. UK Content The %age of the total undiscounted expenditure by the Wind Farm Asset Owner on a Wind Farm that is ultimately spent through Contracts awarded to companies operating in the UK. Key definitions Clarity is vital to the methodology
  • 13. 13/21© BVG Associates 2015 A UK content metaphor To make the presentation less dry Non-UKUK
  • 14. 14/21© BVG Associates 2015 The process UK content is ultimately estimated for all spend • Contracts less than £10 million? Make an estimate based on: • Any information provided by the Supplier • The invoice address of the Supplier • The currency in which the payment was made • The Customer’s knowledge of its Supplier’s activities and Subsuppliers • The Customer’s knowledge of the activities and Subsuppliers of similar companies Process starts with the developer Estimate UK content Review each contract in turn Wind farm reached FID Asks supplier to report UK content Value ≥£10 million? No Yes Assign to supply chain area* and add data to data gathering tool
  • 15. 15/21© BVG Associates 2015 Customer SupplierA Subsupplier A1 Subsupplier A2 Subsupplier A3 Value ≥£10million Value < £10 million Supplier B Subsupplier B1 Subsupplier B2 Subsupplier B3 Subsupplier B4 Supplier C Subsupplier C1 Subsupplier C2 Subsupplier C3 Supplier D Subsupplier D1 Subsupplier D2 Subsupplier D3 Supplier E Supplier F Supplier G Supplier H A theoretical example Expected that few companies below wind farm owner’s tier 2s will need to report • For the purposes of this presentation: • Contracts ≥£10 million are “large” • Contracts <£10 million are “small” :
  • 16. 16/21© BVG Associates 2015 Supplier Contract value (£million) UK Content in Contract % of base cost in Contract Contribution of Supplier’s Contract to UK Content Subsupplier Subcontract (£million) % of base cost in Subcontract UK Content in Subcontract A 12 71% 15% 10.6% A1 6 55% 85% A2 4 36% 55% A3 1 9% 45% Margin 1 B 20 47% 25% 11.7% B1 10 43% 25% B2 5 29% 75% B3 3 14% 45% B4 3 14% 75% Margin -1 C 15 32% 19% 6.1% C1 7 52% 25% C2 4.5 33% 50% C3 2 15% 20% Margin 1.5 D 11 22% 14% 2.9% D1 4 45% 40% D2 3 33% 5% D3 2 22% 10% Margin 2 E 8 46% 10% 4.6% F 7 85% 9% 7.4% G 4 65% 5% 3.3% H 3 90% 4% 3.4% Base cost 80 Margin 20 Total 100 50.0% A theoretical example
  • 17. 17/21 Specific challenges Two types of challenge: the UK content calculation and the attribution of cost to the wind farm • Large component - project sourced (could be a turbine) • Large component - dual sourced (could be a foundation) • Large component – framework (could be a cable) • Large component – internal (could be a blade) • Factory running costs • Corporate overhead • Factory or vessel investment • R&D • Transport and storage • Rent A supplier is awarded a contract and fulfils it with a number of subcontracts © BVG Associates 2015
  • 18. 18/21 Small contracts Assessment should be made based on a knowledge of the company © BVG Associates 2015 Type of Product Examples UK Content assumption for UK-based supplier Desk-based services Consultancy PR Legal Insurance 95% Non-desk-based services using low-cost equipment likely to be imported Electrical services Lifting services 70% Non-desk-based services using high-cost equipment likely to be UK manufactured Crew transfer vessels Transport 85%
  • 19. 19/21 A vision realised? UK investments will impact soon – but hard to see UK content rising without a bigger market © BVG Associates 2015 0% 25% 50% 75% 100% 2010 2012 2014 2016 2018 2020 Low CAPEX+DEVEX Low OPEX Low TOTEX Average CAPEX+DEVEX Average OPEX Average TOTEX High CAPEX+DEVEX High OPEX High TOTEX Yearof final investment decision UKcontent Not based on real data
  • 20. 20/21 What about the non-UK content? What if we looked at the origin of all components and services? © BVG Associates 2015 UK 44% Germany 16% Denmark 14% Netherlands 4% Belgium 1% Other Europe 9% Other 12% Not based on real data National content in TOTEX
  • 21. 21/21 Concluding thoughts © BVG Associates 2015 • 50% UK content not far away – but there shouldn’t be complacency • Data published as a rolling five year average means that the impact of new UK investments will not be evident for several years – three years would be better • Detailed data is only optional – it’s not much more work and can help identify areas for action • Everyone’s job will be easier if companies spend a little time now getting prepared: • Talking with suppliers • Making data gathering tools • Briefing contract managers • BVGA is always here to help