12. Scope validation involves
formal acceptance of the
completed project
deliverables
Acceptance is often
achieved by a customer
inspection and then sign-off
on key deliverables
13. Influence the factors
that cause scope changes
Assure changes are
processed according to
procedures developed as
part of integrated change
control
Manage changes when
they occur
Variance??
14. Lagaan : A Project Management case study
on the making of the film
CASE STUDY
15. • Pre – production Planning and arrangements
• Scheduling and Budgeting
•Actual shooting procedure and post – production activities
•Complete in schedule time
•Managing and controlling
SCOPE OF THE PROJECT
17. Sponsor : Aamir Khan
Director : Ashutosh Gowariker
Team : stake holders like musicians, artist, actors,
screenplay, cooks, producers, directors,
costume designers
British actors
three hundred strong unit from Mumbai
Sixty odd actors from town of Bhuj
Around ten thousand villagers.
STAKEHOLDER ANALYSIS AND HUMAN
RESOURCE MANAGEMENT
22. Risk factors involved in the film making
process…
• Time and Money
•Managing Stakeholders
•Uncertainty
•Environment
•Accommodation
•Health and safety
•Technical
•Controlling Resources
•Local Labour Laws
RISK ANALYSIS