Capability Based Planning for
   Enterprise Services



Prepared by        Capability based planning fits
Niwot Ridge, LLC   naturally with Strategy Based
May 2005
                   Planning and Business
                   Process Improvement

                                              1/35
Risk management is the delivery of a positive
outcome in the presence of uncertainty

Political disorders can be
quickly healed if they are
seen well in advance; when,
for lack of a diagnosis, they
are allowed to grow in such
a way that everyone can
recognize them, remedies
are too late.
Niccolo Machiavelli,
Il Principe, 1513



                                                2/35
“End to end” delivery of Enterprise Services rests on
the keystone of Project Portfolio Management,
balanced by a Scorecard and a Capabilities Plan


                            Project
                           Portfolio
                          Management




      “Demand”                                       “Done”

   Business Mission and Vision       Capabilities Based Planning
    drives capabilities need           defines business outcomes
   Balanced Scorecard defines        Event based tasks are the
    the testable strategies for        basis of increasing
    delivering business value          capabilities maturity

                                                                3/35
The supporting elements must be in place to enable
Capabilities Based Planning to succeed. This
presentation focuses Capabilities Based Planning


                                Project
                               Portfolio
                              Management




      “Demand”                                             “Done”

   Project Portfolio Management          Capabilities Based Planning
    defines the “trade space” for          defines business outcomes
    decisions that impact value            resulting from these decisions
                                          Event based tasks are the
                                           delivery mechanisms for
                                           increasing maturity of the
                                           capabilities

                                                                        4/35
Capabilities Base Planning transforms enterprise
services from the delivery of features and functions to
the delivery processes that support strategy


   Capabilities Based Planning is planning, under
    uncertainty, to provide capabilities suitable for a
    wide range of business challenges and
    circumstances, while working within an
    economic framework
   Capabilities Based Planning emphasizes
    flexibility, adaptiveness and robust capabilities,
    implying a modular building-block approach to
    Enterprise Services
   When transformation takes place it is because
    new modules have come into use
                                                      5/35
Capabilities Based Planning is understood at the
execution level, but needs to be raised to the level of
enterprise process analysis


1. Identify a needed capability in operational
   requirements terms;
2. using the set of capability options to;
3. assess the effectiveness in a operations
   paradigm, and;
4. make choices about requirements and ways to
   achieve the capability using an integrated
   portfolio framework;
5. to produce of output set of options based on
   these operational paradigms.
                                                          6/35
For a requirement (1) consider the options (2), apply
mission system analysis (3) to circumstances (4) to
generate assessment of options (5)


                          2
                       Optional
                      Capabilities




            1
                          3               5
        Business
                      Analysis of    Assessment
       Mission and
                      Capabilities    of Options
          Vision




                          4
                       Scenarios

                                                        7/35
Many enterprise projects focus on the delivery of
     improved features and functions; ignoring the delivery
     of the capabilities needed to implement strategy


Standish Chaos Report Failure Modes           Capabilities Based Planning
Absence of a clear vision and statement       Maturity assessment program events
of the requirements expectations              provide visibility of progress independent
                                              of effort or time
Estimating difficulties and organizational    Capability assessment points define
politics result in unrealistic expectations   “done” using agreed on measures of
                                              progress
Poor project decomposition                    Master Plan and Master Schedule
                                              vertically and horizontally integrated
Inadequate staffing                           Resource loaded schedules
Lack of stakeholder involvement               Capabilities defined by business needs
Lack of strategic focus                       Capabilities connected to Balanced
                                              Scorecard

                                                                                   8/35
Putting Capabilities Based Planning to work requires
a change in our approach to planning – a business
process improvement maturity focus


   Emphasis on operations rather than features
    and functions
       Operational capabilities are the building blocks of
        change
   Emphasis on evaluating capabilities under
    conditions of uncertainty
       Deploying robust building blocks
       Analysis illuminates the feasibility of alternatives



                                                               9/35
Capabilities Based Planning starts with business
  scenarios, the tasks needed to implement the
  scenarios, and testable capability outcomes


      Scenarios                   Work Tasks                   Capabilities
The business units          The individual work           The planned capability of
operational needs in        processes needed to fulfill   the Business Units at each
scenario terms              the scenarios                 level of maturity

Merge a General Ledger       1. Define the data to be     “Acquire a $100M business
from a 3rd party database       acquired from the new     unit in 90 days or less”
through a data                  firm
conversation process         2. Verify data               “Process 100% AP invoices
                                conversation can take     from tier 1 vendors saving
                                place                     $9M annually”
                             3. Verify that business
                                operations can
                                continue

   Business Process
                              Project Management           Strategy Management
     Improvement
                                                                                       10/35
Balanced Scorecard is augmented through a
capabilities based planning process by mapping
strategies to assessment maturity events


   Balanced Scorecard is a framework with
    intrinsic stakeholder focus – placing emphasis
    on internal alignment and elimination of projects
    with little or no strategic value
   Balanced Scorecard does not adequately
    reflect a project management focus, instead on
    objectives and their process indicators




                                                 11/35
Defining the desired maturity of a business processes
is the starting point for integrating Balanced Scorecard
with the Enterprise Services deployment processes


   The Integrated Master Plan (IMP) for Enterprise
    Services starts with the identification of
    increasing maturity of capabilities
   The successful delivery of supporting features
    and functions can be measured by the
    completion of the Significant Accomplishments
    and their Criteria




                                                     12/35
The focus of Capabilities Based Planning is on
assessing the increasing maturity of functionality
defined by the Balanced Scorecard strategy


   Planning under uncertainty, provides
    capabilities suitable for a wide range of
    challenges and circumstances while working
    within an economic framework that necessitates
    choice
   Focus on “possibilities” rather than features
       “What features do we need to achieve the desired
        capabilities?”
       “How much of each capability to we need at this
        point in time?”
       “How robust, flexible, and capable should we be at a
        point time to provide the needed capability?”

                                                        13/35
Capabilities Based Planning takes a near term and
long term view of the emerging functional maturity
needed to implement the Enterprise Services strategy


   Near term effective use of processes, tools,
    features and functions
   Future use of sound infrastructure and system
    capabilities
       Joint solutions to problem by identifying vertical
        connections between business processes
       Risk tradeoff assessment of vertical solutions within
        and across business processes
       Build capability to respond to a wide variety of
        possible demands

                                                          14/35
The difference between capability and function is the
difference between the delivery of a solution and the
creation of the foundation for change


   Focus on outcomes is important
   Focus on the underlying tasks that produce
    outcomes is all important
   Defining the needed maturity and assessing its
    presence provides feedback to the business
    strategy in ways KPI’s can’t




                                                    15/35
Six trusted friends of a project based organization are
  the basis of capabilities based planning and balanced
  scorecard



              Why are we doing this? Balanced Scorecard
               What is it we’re doing? Program Events
How is this going to be accomplished? Significant Accomplishments
        When will we know it is done? Accomplishment Criteria
              When will we be done? Tasks
Who going to do the work at what cost? Resources
       Where will the work take place? Teams




                                                            16/35
Start the hierarchy of Enterprise Services processes
with strategy and end with plans; traceable to this
strategy through portfolios of projects




      Strategies define the desired outcome
    Capabilities enable the strategy
      Portfolios manage capabilities
          Plans manage the delivery effort




                                                   17/35
The measure of Enterprise Services Business Effect’s
         is made visible at each maturity assessment point.
         “Is this want done looks like?” must be the question

                                                                 Business               Business
                 Capability 1      Capability 2
                                                                  Effect                 Effect



  Sub-                  Sub-           Sub-              Capability        Capability         Capability
Capability            Capability     Capability



    Sub-Sub-          Sub-Sub-        Sub-Sub-
    Capability        Capability      Capability                    Sub-
                                                                  Capability                  Sub-
    Sub-Sub-          Sub-Sub-                                                              Capability
                                      Sub-Sub-
    Capability        Capability                      Sub-
                                      Capability                                 Sub-
                                                    Capability                                               Sub-
                                                                               Capability
                                                                                                           Capability



 Functional decomposition of capabilities          Derive business effects from capabilities
 Capabilities must be Collectively Exhaustive      Link capabilities to effects
  and Mutually Exclusive                            Explicitly identify cross links and
 Provide a “menu” from which operations can         interdependencies between capabilities
  choose required capabilities                      Highlight “enabler” capabilities
                                                                                                         18/35
Evidence that the strategy is being fulfilled is tested in
the “units of measure” of the capabilities of a project
whose maturity is assessed at periodic events



 Program Maturity What are the maturity assessment points
     Assessment along the way to completion?
          Events
      Significant What accomplishments must take place in
 Accomplishments order for this maturity to have occurred?
  Accomplishment What is the evidence that the
          Criteria accomplishments occurred?
             Tasks What effort must take place for the
                   accomplishments to have be completed?



                                                        19/35
Capabilities Based Planning separates effort from
results, measuring an assessment event’s effect on
the organization, rather than the passage of time


   The passage of time does not mean progress;
    delivery of capabilities does
   Measuring increasing maturity of capability
    makes visible the systems value in terms the
    business units can directly assess




                                                     20/35
The process drivers for Capabilities Based Planning
starts with functionality and ends with deliverable
effects on the business process


   Functional or feature planning does not deliver
    the real value to the business units
       Features are not connected to strategy
           Balanced Scorecard connections are capabilities not
            features
           Testing strategy involves a capabilities impact not the
            presence of a feature
       Features are not connected to business value
           Business strategy is tested through scenarios and
            capabilities
           Delivered value results from the use of a capability in a
            scenario
                                                                21/35
Capabilities Based Planning augments features with
business value, traceable to strategy through a
portfolio of projects and their Program Events


   Plan the delivery of capabilities rather than the
    delivery of features and functions
   Features and functions are the raw materials of
    Capabilities
   Capabilities enable the delivery of the strategy




                                                  22/35
Program Events are evaluation points in the project
for assessing the maturity of the capability and its
effect on the business


   Program Events are Celebratory Opportunities
    along the path to maturity
       Significant accomplishments enable a new capability
        that supports a strategy
       The maturity of the derived effects are assured
        through the assessment of the Significant
        Accomplishment




                                                       23/35
Significant Accomplishments describe the delivery of
capability needed to fulfill a business strategy using
work processes of the system


   A Capability is the deployment or delivery of a
    feature or function in support of a business
    process, product or service initiative
   Significant Accomplishments deliver this
    capability
   Stating the needed maturity connects the
    capability with strategy



                                                     24/35
Accomplishment Criteria are the “exit criteria” for the
Significant Accomplishments, assuring the intent of
the Accomplishment is met


   Exit criteria are the evidence that the significant
    accomplishment has been achieved
   The gathering and assessment of the Balance
    Scorecard KPI in support of a Significant
    Accomplishment




                                                      25/35
Tasks are the raw material to implement the
functionality needed for the business process to
deliver on the capabilities


   The effort expended to deliver the
    Accomplishment Criteria in support of the
    Significant Accomplishment
   Short duration activities (20 to 40 working days)
    with clearly defined deliverables
       0% or 100% credit for the deliverables
       No partial completion of tasks
       Predefined technical outcomes



                                                   26/35
Management consists of Capabilities Assessments
(Events), the Significant Accomplishments (SA) and
the Accomplishment Criteria (AC)


                       Defines                   Events                  State of the
  Business Strategy                                                        Project

                                                      Team Status

                                     Customer/Program
                                         Direction
                      Demonstrates         Accomplishments               State of the    Something
  WBS Element or        Maturity
   Subsystem                                                              Capability     Completed
                                                 Significant
                                              Accomplishments
                                                    (SA)

                                     Program/Team          Team Status
                                       Direction
                                                                         State of the
     Subsystem         Identifies
                                                Criteria                  Process
                       End Item
                                             Accomplishment
                                               Criteria (AC)

                                                           Performance
                                     Team Direction
                                                                         Deliverables     Effort
                                                                                        Expended
  IMP Process Step      How                      Tasks



                                                                                              27/35
A set of concise capability specific phrases provide a
“stand alone” description of “done” independent of the
existence of individual features


      Maturity              Action             Capability              State




      Adjective             Verb                 Noun                  Verb


    Demonstrates                                                      Closure      Perform
      Maturity        Step in the Process       End Item               State        Work

    Preliminary            Close            General Ledger         Successful




    “A01B02a: Preliminary Month End Close of the General Ledger Successful”




                                                                                28/35
Starting with a “mini-Kaizen,” the maturity Assessment
Points (Events) are gathered along with the Significant
Accomplishments and Accomplishment Criteria




                                                    29/35
A mini-Kaizen transfers “Sticky’s” to a Mind Map, then
to a Master Schedule then, to a Hanging PERT –
producing a “Wall of Truth” for Enterprise Services

Working session Sticky’s




  A Mind Map™ of the Sticky’s           PERT Chart Expert™ on the Wall of Truth




                                MS Project™ export of
                                the Mind Map


                                                                      30/35
The three levels of the Integrated Master Plan define
the granularity of the deliverables, report progress to
plan and project the future cost and effort of tasks

 Monthly statusing:
 – Validate schedule status      WBS
   (start/complete/slip)                                                                    IMP
 – Validate work package
                                 Levels
   % complete                    1, 2, 3
 – Claims earned value
 – Identify/process cost ETCs
                                                         Funding Profile
 Weekly statusing:                         Near term RW period
 – Roll up of lower level        WBS                                 Planning Package
                                                                        Future RW periods
   schedule                      Levels
   status                        4, 5                               Schedule tasks
 – Roll up of lower level %
   complete                                                         (at Work Package
               or                                                   level)
 – Milestone start/complete
 – Milestone slip (early/late,                       20 to 40
   start/complete)
                                 WBS’s            Workday tasks
                                                                    Schedule tasks
 – % complete of tasks
                                 Below                              (one/two levels
Weekly statusing:                Work
– Milestone start/complete                                          below WP level)
– Milestone slip (early/late,
                                 Package              Or even
                                                    weekly tasks
  start/complete)
– % complete of tasks
                                                                                            31/35
A simple example of vertical and horizontal linking of
    the capability — provisioning a new employee
    illustrates the assessment of maturity


    Capability: Provide Buying Authority within 10 working days of hire


                              Human Resources

                           Information Technology

                                      Finance

                         Supply Chain Management
New Employee                                                             Ready to Work

                                   Charge account setup
                        Laptop Account Setup
                                                          Buying authority available
                     Insurance
                     Orientation
                                                                                   32/35
Maturity assessments allow progress to be measured
in how terms of “capability” effects the business; not
just the consumption of time and resources


   Define the desired maturity points along the
    path to completion
   Measure the accomplishments
   Assess the effect on business improvement
   Engage all participants in a conversation about
    capability




                                                    33/35
The deployment of Capabilities Based Planning is the
basis of managing the deployment of Enterprise
Services


   What does done look like in terms of
    operational capabilities?
   How can we measure the increasing maturity of
    Enterprise Services in terms of “done,” rather
    than the passage of time?
   How can the user community define their
    operational needs in terms of capabilities rather
    than features and functions?


                                                  34/35
References

   Miller, Roger and Donald R. Lessard, The Strategic Management of
    Large-Scale Engineering Projects: Shaping Institutions, Risk, and
    Governance, MIT Press, 2001.
   Guide to Capabilities Based Planning, The Technical Cooperation
    Program, Joint Systems and Analysis Group, Technical Panel 3.
   Allen, Tom, Analysis to Support Capabilities-Based Planning,
    Capabilities-Based Planning Workshop, October 19-21, 2004.
   Davis, Paul K., Analytical Architecture for Capabilities-Based
    Planning, Mission-System Analysis, and Transformation, RAND
    Corporation, MR1513
   Davis, Paul K., “Exploratory Analysis Enabled by Multiresolution,
    Multiperspective Modeling,” Proceedings of the 2000 Winter
    Simulation Conference.
   Machiavelli, Niccolo, The Prince and The Discourses, Introduction by
    Max Lerner, Modern Library,1950


                                                                   35/35

Weitere ähnliche Inhalte

Was ist angesagt?

Structured Approach to Solution Architecture
Structured Approach to Solution ArchitectureStructured Approach to Solution Architecture
Structured Approach to Solution ArchitectureAlan McSweeney
 
Managed Services
Managed ServicesManaged Services
Managed ServicesVenkat J
 
Capability-based Business Model Transformation
Capability-based Business Model TransformationCapability-based Business Model Transformation
Capability-based Business Model TransformationIlia Bider
 
Application Management Framework
Application Management FrameworkApplication Management Framework
Application Management FrameworkRory Mackay
 
Building a more cohesive organisation using business architecture
Building a more cohesive organisation using business architectureBuilding a more cohesive organisation using business architecture
Building a more cohesive organisation using business architectureCraig Martin
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance ManagementGlen Alleman
 
Agile2009 Product Manager - Product Owner Dilemma
Agile2009 Product Manager - Product Owner DilemmaAgile2009 Product Manager - Product Owner Dilemma
Agile2009 Product Manager - Product Owner DilemmaEnthiosys Inc
 
On business capabilities, functions and application features
On business capabilities, functions and application featuresOn business capabilities, functions and application features
On business capabilities, functions and application featuresJörgen Dahlberg
 
Enterprise Architecture in Strategy Deployment
Enterprise Architecture in Strategy DeploymentEnterprise Architecture in Strategy Deployment
Enterprise Architecture in Strategy DeploymentJouko Poutanen
 
Business Composability
Business ComposabilityBusiness Composability
Business ComposabilityCOMPETENSIS
 
Solution architecture
Solution architectureSolution architecture
Solution architectureiasaglobal
 
Re-Positioning the value of the architecture practice
Re-Positioning the value of the architecture practiceRe-Positioning the value of the architecture practice
Re-Positioning the value of the architecture practiceCraig Martin
 
Design of Business in an Age of Disruption
Design of Business in an Age of DisruptionDesign of Business in an Age of Disruption
Design of Business in an Age of DisruptionCraig Martin
 
Integrated Project and Solution Delivery And Business Engagement Model
Integrated Project and Solution Delivery And Business Engagement ModelIntegrated Project and Solution Delivery And Business Engagement Model
Integrated Project and Solution Delivery And Business Engagement ModelAlan McSweeney
 
EA Intensive Course "Building Enterprise Architecture" by mr.danairat
EA Intensive Course "Building Enterprise Architecture" by mr.danairatEA Intensive Course "Building Enterprise Architecture" by mr.danairat
EA Intensive Course "Building Enterprise Architecture" by mr.danairatSoftware Park Thailand
 
Bringing Architecture Thinking to the People - An introduction into the PEOPL...
Bringing Architecture Thinking to the People - An introduction into the PEOPL...Bringing Architecture Thinking to the People - An introduction into the PEOPL...
Bringing Architecture Thinking to the People - An introduction into the PEOPL...Craig Martin
 
BPM (Business Process Management), CRM and Cross-Functional Enterprise-Level ...
BPM (Business Process Management), CRM and Cross-Functional Enterprise-Level ...BPM (Business Process Management), CRM and Cross-Functional Enterprise-Level ...
BPM (Business Process Management), CRM and Cross-Functional Enterprise-Level ...Alan McSweeney
 
Role of BA over project lifecycle
Role of BA over project lifecycleRole of BA over project lifecycle
Role of BA over project lifecycleSudeep Mathur
 
Solution Architecture Framework
Solution Architecture FrameworkSolution Architecture Framework
Solution Architecture FrameworkFirmansyahIrma1
 

Was ist angesagt? (20)

Structured Approach to Solution Architecture
Structured Approach to Solution ArchitectureStructured Approach to Solution Architecture
Structured Approach to Solution Architecture
 
Managed Services
Managed ServicesManaged Services
Managed Services
 
Capability-based Business Model Transformation
Capability-based Business Model TransformationCapability-based Business Model Transformation
Capability-based Business Model Transformation
 
Application Management Framework
Application Management FrameworkApplication Management Framework
Application Management Framework
 
Building a more cohesive organisation using business architecture
Building a more cohesive organisation using business architectureBuilding a more cohesive organisation using business architecture
Building a more cohesive organisation using business architecture
 
Integrated Program Performance Management
Integrated Program Performance ManagementIntegrated Program Performance Management
Integrated Program Performance Management
 
Agile2009 Product Manager - Product Owner Dilemma
Agile2009 Product Manager - Product Owner DilemmaAgile2009 Product Manager - Product Owner Dilemma
Agile2009 Product Manager - Product Owner Dilemma
 
On business capabilities, functions and application features
On business capabilities, functions and application featuresOn business capabilities, functions and application features
On business capabilities, functions and application features
 
Enterprise Architecture in Strategy Deployment
Enterprise Architecture in Strategy DeploymentEnterprise Architecture in Strategy Deployment
Enterprise Architecture in Strategy Deployment
 
Business Composability
Business ComposabilityBusiness Composability
Business Composability
 
Solution architecture
Solution architectureSolution architecture
Solution architecture
 
PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?PMBOK 7th Edition What is Changing?
PMBOK 7th Edition What is Changing?
 
Re-Positioning the value of the architecture practice
Re-Positioning the value of the architecture practiceRe-Positioning the value of the architecture practice
Re-Positioning the value of the architecture practice
 
Design of Business in an Age of Disruption
Design of Business in an Age of DisruptionDesign of Business in an Age of Disruption
Design of Business in an Age of Disruption
 
Integrated Project and Solution Delivery And Business Engagement Model
Integrated Project and Solution Delivery And Business Engagement ModelIntegrated Project and Solution Delivery And Business Engagement Model
Integrated Project and Solution Delivery And Business Engagement Model
 
EA Intensive Course "Building Enterprise Architecture" by mr.danairat
EA Intensive Course "Building Enterprise Architecture" by mr.danairatEA Intensive Course "Building Enterprise Architecture" by mr.danairat
EA Intensive Course "Building Enterprise Architecture" by mr.danairat
 
Bringing Architecture Thinking to the People - An introduction into the PEOPL...
Bringing Architecture Thinking to the People - An introduction into the PEOPL...Bringing Architecture Thinking to the People - An introduction into the PEOPL...
Bringing Architecture Thinking to the People - An introduction into the PEOPL...
 
BPM (Business Process Management), CRM and Cross-Functional Enterprise-Level ...
BPM (Business Process Management), CRM and Cross-Functional Enterprise-Level ...BPM (Business Process Management), CRM and Cross-Functional Enterprise-Level ...
BPM (Business Process Management), CRM and Cross-Functional Enterprise-Level ...
 
Role of BA over project lifecycle
Role of BA over project lifecycleRole of BA over project lifecycle
Role of BA over project lifecycle
 
Solution Architecture Framework
Solution Architecture FrameworkSolution Architecture Framework
Solution Architecture Framework
 

Andere mochten auch

Project maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business valueProject maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business valueGlen Alleman
 
Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Glen Alleman
 
Paradigm of agile project management
Paradigm of agile project managementParadigm of agile project management
Paradigm of agile project managementGlen Alleman
 
Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based PlanningGlen Alleman
 
Agile in the government
Agile in the government Agile in the government
Agile in the government Glen Alleman
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News WebinarGlen Alleman
 
Managing in the presence of uncertainty
Managing in the presence of uncertaintyManaging in the presence of uncertainty
Managing in the presence of uncertaintyGlen Alleman
 
Agile at scale resources
Agile at scale resourcesAgile at scale resources
Agile at scale resourcesGlen Alleman
 
Risk management using risk+ (v5)
Risk management using risk+ (v5)Risk management using risk+ (v5)
Risk management using risk+ (v5)Glen Alleman
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governanceGlen Alleman
 
Building the perfect schedule (v6)
Building the perfect schedule (v6)Building the perfect schedule (v6)
Building the perfect schedule (v6)Glen Alleman
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleGlen Alleman
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanGlen Alleman
 
Notes on balanced scorecard
Notes on balanced scorecardNotes on balanced scorecard
Notes on balanced scorecardGlen Alleman
 
5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 secondsGlen Alleman
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big DataGlen Alleman
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Glen Alleman
 
Architectured Centered Design
Architectured Centered DesignArchitectured Centered Design
Architectured Centered DesignGlen Alleman
 

Andere mochten auch (20)

Project maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business valueProject maturity flow is the incremental delivery of business value
Project maturity flow is the incremental delivery of business value
 
Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®Principles and Practices of Performance-Based Project Management®
Principles and Practices of Performance-Based Project Management®
 
Control systems
Control systemsControl systems
Control systems
 
Paradigm of agile project management
Paradigm of agile project managementParadigm of agile project management
Paradigm of agile project management
 
Deliverables Based Planning
Deliverables Based PlanningDeliverables Based Planning
Deliverables Based Planning
 
Agile in the government
Agile in the government Agile in the government
Agile in the government
 
Measurement News Webinar
Measurement News WebinarMeasurement News Webinar
Measurement News Webinar
 
Managing in the presence of uncertainty
Managing in the presence of uncertaintyManaging in the presence of uncertainty
Managing in the presence of uncertainty
 
Agile at scale resources
Agile at scale resourcesAgile at scale resources
Agile at scale resources
 
Risk management using risk+ (v5)
Risk management using risk+ (v5)Risk management using risk+ (v5)
Risk management using risk+ (v5)
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governance
 
Building the perfect schedule (v6)
Building the perfect schedule (v6)Building the perfect schedule (v6)
Building the perfect schedule (v6)
 
The integrated master plan and integrated master schedule
The integrated master plan and integrated master scheduleThe integrated master plan and integrated master schedule
The integrated master plan and integrated master schedule
 
Improving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master PlanImproving DOE Project Performance Using the DOD Integrated Master Plan
Improving DOE Project Performance Using the DOD Integrated Master Plan
 
Notes on balanced scorecard
Notes on balanced scorecardNotes on balanced scorecard
Notes on balanced scorecard
 
5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds5 immutable principles and 5 processes in 60 seconds
5 immutable principles and 5 processes in 60 seconds
 
Earned Value Management Meets Big Data
Earned Value Management Meets Big DataEarned Value Management Meets Big Data
Earned Value Management Meets Big Data
 
Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)Performance based planning in a nut shell (V5)
Performance based planning in a nut shell (V5)
 
Architectured Centered Design
Architectured Centered DesignArchitectured Centered Design
Architectured Centered Design
 
Governance
GovernanceGovernance
Governance
 

Ähnlich wie Capability Based Planning Transforms Enterprise Services

Capabilities based planning essay
Capabilities based planning essayCapabilities based planning essay
Capabilities based planning essayGlen Alleman
 
Acto It Consulting Presentation
Acto It Consulting   PresentationActo It Consulting   Presentation
Acto It Consulting PresentationArthurScheffer
 
Acto It Consulting Presentation
Acto It Consulting   PresentationActo It Consulting   Presentation
Acto It Consulting Presentationguest6c269db
 
Acto.IT Consulting Presentation
Acto.IT Consulting PresentationActo.IT Consulting Presentation
Acto.IT Consulting PresentationAlex Bomjardim
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governanceGlen Alleman
 
A Comprehensive Approach to Application Portfolio Rationalization
A Comprehensive Approach to Application Portfolio RationalizationA Comprehensive Approach to Application Portfolio Rationalization
A Comprehensive Approach to Application Portfolio RationalizationCognizant
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planningGlen Alleman
 
10 tips for Chartering a Project
10 tips for Chartering a Project10 tips for Chartering a Project
10 tips for Chartering a ProjectGlen Alleman
 
UEP Getting Ahead Through Six Practices, Practice 5 World Class Integrated Pl...
UEP Getting Ahead Through Six Practices, Practice 5 World Class Integrated Pl...UEP Getting Ahead Through Six Practices, Practice 5 World Class Integrated Pl...
UEP Getting Ahead Through Six Practices, Practice 5 World Class Integrated Pl...Danielle Butler-Miles
 
Install pms in moccis - a proposal
Install pms in moccis - a proposalInstall pms in moccis - a proposal
Install pms in moccis - a proposalHj Arriffin Mansor
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic AbundanceGlen Alleman
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueGlen Alleman
 
Val.lunz
Val.lunzVal.lunz
Val.lunzNASAPMC
 
Realizing the Business Value of PPM - What to Expect When Implementing PPM
Realizing the Business Value of PPM - What to Expect When Implementing PPMRealizing the Business Value of PPM - What to Expect When Implementing PPM
Realizing the Business Value of PPM - What to Expect When Implementing PPMEPM Live
 
Principia21 Overview And Example Case Studies
Principia21 Overview And Example Case StudiesPrincipia21 Overview And Example Case Studies
Principia21 Overview And Example Case StudiesCraig B. DeLano
 
Professional Business Results & Selected Accomplishments
Professional Business Results & Selected AccomplishmentsProfessional Business Results & Selected Accomplishments
Professional Business Results & Selected Accomplishmentsmjleib
 
My Single Point project portfolio and demand
My Single Point project portfolio and demandMy Single Point project portfolio and demand
My Single Point project portfolio and demandPHILIPPE CORNETTE
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbookGlen Alleman
 

Ähnlich wie Capability Based Planning Transforms Enterprise Services (20)

Capabilities based planning essay
Capabilities based planning essayCapabilities based planning essay
Capabilities based planning essay
 
Acto It Consulting Presentation
Acto It Consulting   PresentationActo It Consulting   Presentation
Acto It Consulting Presentation
 
Acto It Consulting Presentation
Acto It Consulting   PresentationActo It Consulting   Presentation
Acto It Consulting Presentation
 
Acto.IT Consulting Presentation
Acto.IT Consulting PresentationActo.IT Consulting Presentation
Acto.IT Consulting Presentation
 
Principles of program governance
Principles of program governancePrinciples of program governance
Principles of program governance
 
A Comprehensive Approach to Application Portfolio Rationalization
A Comprehensive Approach to Application Portfolio RationalizationA Comprehensive Approach to Application Portfolio Rationalization
A Comprehensive Approach to Application Portfolio Rationalization
 
Capabilities based planning
Capabilities based planningCapabilities based planning
Capabilities based planning
 
10 tips for Chartering a Project
10 tips for Chartering a Project10 tips for Chartering a Project
10 tips for Chartering a Project
 
UEP Getting Ahead Through Six Practices, Practice 5 World Class Integrated Pl...
UEP Getting Ahead Through Six Practices, Practice 5 World Class Integrated Pl...UEP Getting Ahead Through Six Practices, Practice 5 World Class Integrated Pl...
UEP Getting Ahead Through Six Practices, Practice 5 World Class Integrated Pl...
 
Install pms in moccis - a proposal
Install pms in moccis - a proposalInstall pms in moccis - a proposal
Install pms in moccis - a proposal
 
Stanford apm ashish v0.1
Stanford apm   ashish v0.1Stanford apm   ashish v0.1
Stanford apm ashish v0.1
 
Heliotropic Abundance
Heliotropic AbundanceHeliotropic Abundance
Heliotropic Abundance
 
Successfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned ValueSuccessfully Integrating Agile and Earned Value
Successfully Integrating Agile and Earned Value
 
Val.lunz
Val.lunzVal.lunz
Val.lunz
 
Realizing the Business Value of PPM - What to Expect When Implementing PPM
Realizing the Business Value of PPM - What to Expect When Implementing PPMRealizing the Business Value of PPM - What to Expect When Implementing PPM
Realizing the Business Value of PPM - What to Expect When Implementing PPM
 
Principia21 Overview And Example Case Studies
Principia21 Overview And Example Case StudiesPrincipia21 Overview And Example Case Studies
Principia21 Overview And Example Case Studies
 
Professional Business Results & Selected Accomplishments
Professional Business Results & Selected AccomplishmentsProfessional Business Results & Selected Accomplishments
Professional Business Results & Selected Accomplishments
 
NuStratis Brochure
NuStratis BrochureNuStratis Brochure
NuStratis Brochure
 
My Single Point project portfolio and demand
My Single Point project portfolio and demandMy Single Point project portfolio and demand
My Single Point project portfolio and demand
 
Deliverables based planning handbook
Deliverables based planning handbookDeliverables based planning handbook
Deliverables based planning handbook
 

Mehr von Glen Alleman

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planningGlen Alleman
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSGlen Alleman
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project SuccessGlen Alleman
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMGlen Alleman
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk managementGlen Alleman
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk ManagementGlen Alleman
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Glen Alleman
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringGlen Alleman
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideGlen Alleman
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineGlen Alleman
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Glen Alleman
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by StepGlen Alleman
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)Glen Alleman
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possibleGlen Alleman
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for AgileGlen Alleman
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement BaselineGlen Alleman
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaGlen Alleman
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure RolloutGlen Alleman
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan DevelopmentGlen Alleman
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management TheoryGlen Alleman
 

Mehr von Glen Alleman (20)

Managing risk with deliverables planning
Managing risk with deliverables planningManaging risk with deliverables planning
Managing risk with deliverables planning
 
A Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMSA Gentle Introduction to the IMP/IMS
A Gentle Introduction to the IMP/IMS
 
Increasing the Probability of Project Success
Increasing the Probability of Project SuccessIncreasing the Probability of Project Success
Increasing the Probability of Project Success
 
Process Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPMProcess Flow and Narrative for Agile+PPM
Process Flow and Narrative for Agile+PPM
 
Practices of risk management
Practices of risk managementPractices of risk management
Practices of risk management
 
Principles of Risk Management
Principles of Risk ManagementPrinciples of Risk Management
Principles of Risk Management
 
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
 
From Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems EngineeringFrom Principles to Strategies for Systems Engineering
From Principles to Strategies for Systems Engineering
 
NAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guideNAVAIR Integrated Master Schedule Guide guide
NAVAIR Integrated Master Schedule Guide guide
 
Building a Credible Performance Measurement Baseline
Building a Credible Performance Measurement BaselineBuilding a Credible Performance Measurement Baseline
Building a Credible Performance Measurement Baseline
 
Integrated master plan methodology (v2)
Integrated master plan methodology (v2)Integrated master plan methodology (v2)
Integrated master plan methodology (v2)
 
IMP / IMS Step by Step
IMP / IMS Step by StepIMP / IMS Step by Step
IMP / IMS Step by Step
 
DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)DHS - Using functions points to estimate agile development programs (v2)
DHS - Using functions points to estimate agile development programs (v2)
 
Making the impossible possible
Making the impossible possibleMaking the impossible possible
Making the impossible possible
 
Process Flow and Narrative for Agile
Process Flow and Narrative for AgileProcess Flow and Narrative for Agile
Process Flow and Narrative for Agile
 
Building the Performance Measurement Baseline
Building the Performance Measurement BaselineBuilding the Performance Measurement Baseline
Building the Performance Measurement Baseline
 
Program Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six SigmaProgram Management Office Lean Software Development and Six Sigma
Program Management Office Lean Software Development and Six Sigma
 
Policy and Procedure Rollout
Policy and Procedure RolloutPolicy and Procedure Rollout
Policy and Procedure Rollout
 
Integrated Master Plan Development
Integrated Master Plan DevelopmentIntegrated Master Plan Development
Integrated Master Plan Development
 
Project Management Theory
Project Management TheoryProject Management Theory
Project Management Theory
 

Capability Based Planning Transforms Enterprise Services

  • 1. Capability Based Planning for Enterprise Services Prepared by Capability based planning fits Niwot Ridge, LLC naturally with Strategy Based May 2005 Planning and Business Process Improvement 1/35
  • 2. Risk management is the delivery of a positive outcome in the presence of uncertainty Political disorders can be quickly healed if they are seen well in advance; when, for lack of a diagnosis, they are allowed to grow in such a way that everyone can recognize them, remedies are too late. Niccolo Machiavelli, Il Principe, 1513 2/35
  • 3. “End to end” delivery of Enterprise Services rests on the keystone of Project Portfolio Management, balanced by a Scorecard and a Capabilities Plan Project Portfolio Management “Demand” “Done”  Business Mission and Vision  Capabilities Based Planning drives capabilities need defines business outcomes  Balanced Scorecard defines  Event based tasks are the the testable strategies for basis of increasing delivering business value capabilities maturity 3/35
  • 4. The supporting elements must be in place to enable Capabilities Based Planning to succeed. This presentation focuses Capabilities Based Planning Project Portfolio Management “Demand” “Done”  Project Portfolio Management  Capabilities Based Planning defines the “trade space” for defines business outcomes decisions that impact value resulting from these decisions  Event based tasks are the delivery mechanisms for increasing maturity of the capabilities 4/35
  • 5. Capabilities Base Planning transforms enterprise services from the delivery of features and functions to the delivery processes that support strategy  Capabilities Based Planning is planning, under uncertainty, to provide capabilities suitable for a wide range of business challenges and circumstances, while working within an economic framework  Capabilities Based Planning emphasizes flexibility, adaptiveness and robust capabilities, implying a modular building-block approach to Enterprise Services  When transformation takes place it is because new modules have come into use 5/35
  • 6. Capabilities Based Planning is understood at the execution level, but needs to be raised to the level of enterprise process analysis 1. Identify a needed capability in operational requirements terms; 2. using the set of capability options to; 3. assess the effectiveness in a operations paradigm, and; 4. make choices about requirements and ways to achieve the capability using an integrated portfolio framework; 5. to produce of output set of options based on these operational paradigms. 6/35
  • 7. For a requirement (1) consider the options (2), apply mission system analysis (3) to circumstances (4) to generate assessment of options (5) 2 Optional Capabilities 1 3 5 Business Analysis of Assessment Mission and Capabilities of Options Vision 4 Scenarios 7/35
  • 8. Many enterprise projects focus on the delivery of improved features and functions; ignoring the delivery of the capabilities needed to implement strategy Standish Chaos Report Failure Modes Capabilities Based Planning Absence of a clear vision and statement Maturity assessment program events of the requirements expectations provide visibility of progress independent of effort or time Estimating difficulties and organizational Capability assessment points define politics result in unrealistic expectations “done” using agreed on measures of progress Poor project decomposition Master Plan and Master Schedule vertically and horizontally integrated Inadequate staffing Resource loaded schedules Lack of stakeholder involvement Capabilities defined by business needs Lack of strategic focus Capabilities connected to Balanced Scorecard 8/35
  • 9. Putting Capabilities Based Planning to work requires a change in our approach to planning – a business process improvement maturity focus  Emphasis on operations rather than features and functions  Operational capabilities are the building blocks of change  Emphasis on evaluating capabilities under conditions of uncertainty  Deploying robust building blocks  Analysis illuminates the feasibility of alternatives 9/35
  • 10. Capabilities Based Planning starts with business scenarios, the tasks needed to implement the scenarios, and testable capability outcomes Scenarios Work Tasks Capabilities The business units The individual work The planned capability of operational needs in processes needed to fulfill the Business Units at each scenario terms the scenarios level of maturity Merge a General Ledger 1. Define the data to be “Acquire a $100M business from a 3rd party database acquired from the new unit in 90 days or less” through a data firm conversation process 2. Verify data “Process 100% AP invoices conversation can take from tier 1 vendors saving place $9M annually” 3. Verify that business operations can continue Business Process Project Management Strategy Management Improvement 10/35
  • 11. Balanced Scorecard is augmented through a capabilities based planning process by mapping strategies to assessment maturity events  Balanced Scorecard is a framework with intrinsic stakeholder focus – placing emphasis on internal alignment and elimination of projects with little or no strategic value  Balanced Scorecard does not adequately reflect a project management focus, instead on objectives and their process indicators 11/35
  • 12. Defining the desired maturity of a business processes is the starting point for integrating Balanced Scorecard with the Enterprise Services deployment processes  The Integrated Master Plan (IMP) for Enterprise Services starts with the identification of increasing maturity of capabilities  The successful delivery of supporting features and functions can be measured by the completion of the Significant Accomplishments and their Criteria 12/35
  • 13. The focus of Capabilities Based Planning is on assessing the increasing maturity of functionality defined by the Balanced Scorecard strategy  Planning under uncertainty, provides capabilities suitable for a wide range of challenges and circumstances while working within an economic framework that necessitates choice  Focus on “possibilities” rather than features  “What features do we need to achieve the desired capabilities?”  “How much of each capability to we need at this point in time?”  “How robust, flexible, and capable should we be at a point time to provide the needed capability?” 13/35
  • 14. Capabilities Based Planning takes a near term and long term view of the emerging functional maturity needed to implement the Enterprise Services strategy  Near term effective use of processes, tools, features and functions  Future use of sound infrastructure and system capabilities  Joint solutions to problem by identifying vertical connections between business processes  Risk tradeoff assessment of vertical solutions within and across business processes  Build capability to respond to a wide variety of possible demands 14/35
  • 15. The difference between capability and function is the difference between the delivery of a solution and the creation of the foundation for change  Focus on outcomes is important  Focus on the underlying tasks that produce outcomes is all important  Defining the needed maturity and assessing its presence provides feedback to the business strategy in ways KPI’s can’t 15/35
  • 16. Six trusted friends of a project based organization are the basis of capabilities based planning and balanced scorecard Why are we doing this? Balanced Scorecard What is it we’re doing? Program Events How is this going to be accomplished? Significant Accomplishments When will we know it is done? Accomplishment Criteria When will we be done? Tasks Who going to do the work at what cost? Resources Where will the work take place? Teams 16/35
  • 17. Start the hierarchy of Enterprise Services processes with strategy and end with plans; traceable to this strategy through portfolios of projects Strategies define the desired outcome Capabilities enable the strategy Portfolios manage capabilities Plans manage the delivery effort 17/35
  • 18. The measure of Enterprise Services Business Effect’s is made visible at each maturity assessment point. “Is this want done looks like?” must be the question Business Business Capability 1 Capability 2 Effect Effect Sub- Sub- Sub- Capability Capability Capability Capability Capability Capability Sub-Sub- Sub-Sub- Sub-Sub- Capability Capability Capability Sub- Capability Sub- Sub-Sub- Sub-Sub- Capability Sub-Sub- Capability Capability Sub- Capability Sub- Capability Sub- Capability Capability  Functional decomposition of capabilities  Derive business effects from capabilities  Capabilities must be Collectively Exhaustive  Link capabilities to effects and Mutually Exclusive  Explicitly identify cross links and  Provide a “menu” from which operations can interdependencies between capabilities choose required capabilities  Highlight “enabler” capabilities 18/35
  • 19. Evidence that the strategy is being fulfilled is tested in the “units of measure” of the capabilities of a project whose maturity is assessed at periodic events Program Maturity What are the maturity assessment points Assessment along the way to completion? Events Significant What accomplishments must take place in Accomplishments order for this maturity to have occurred? Accomplishment What is the evidence that the Criteria accomplishments occurred? Tasks What effort must take place for the accomplishments to have be completed? 19/35
  • 20. Capabilities Based Planning separates effort from results, measuring an assessment event’s effect on the organization, rather than the passage of time  The passage of time does not mean progress; delivery of capabilities does  Measuring increasing maturity of capability makes visible the systems value in terms the business units can directly assess 20/35
  • 21. The process drivers for Capabilities Based Planning starts with functionality and ends with deliverable effects on the business process  Functional or feature planning does not deliver the real value to the business units  Features are not connected to strategy  Balanced Scorecard connections are capabilities not features  Testing strategy involves a capabilities impact not the presence of a feature  Features are not connected to business value  Business strategy is tested through scenarios and capabilities  Delivered value results from the use of a capability in a scenario 21/35
  • 22. Capabilities Based Planning augments features with business value, traceable to strategy through a portfolio of projects and their Program Events  Plan the delivery of capabilities rather than the delivery of features and functions  Features and functions are the raw materials of Capabilities  Capabilities enable the delivery of the strategy 22/35
  • 23. Program Events are evaluation points in the project for assessing the maturity of the capability and its effect on the business  Program Events are Celebratory Opportunities along the path to maturity  Significant accomplishments enable a new capability that supports a strategy  The maturity of the derived effects are assured through the assessment of the Significant Accomplishment 23/35
  • 24. Significant Accomplishments describe the delivery of capability needed to fulfill a business strategy using work processes of the system  A Capability is the deployment or delivery of a feature or function in support of a business process, product or service initiative  Significant Accomplishments deliver this capability  Stating the needed maturity connects the capability with strategy 24/35
  • 25. Accomplishment Criteria are the “exit criteria” for the Significant Accomplishments, assuring the intent of the Accomplishment is met  Exit criteria are the evidence that the significant accomplishment has been achieved  The gathering and assessment of the Balance Scorecard KPI in support of a Significant Accomplishment 25/35
  • 26. Tasks are the raw material to implement the functionality needed for the business process to deliver on the capabilities  The effort expended to deliver the Accomplishment Criteria in support of the Significant Accomplishment  Short duration activities (20 to 40 working days) with clearly defined deliverables  0% or 100% credit for the deliverables  No partial completion of tasks  Predefined technical outcomes 26/35
  • 27. Management consists of Capabilities Assessments (Events), the Significant Accomplishments (SA) and the Accomplishment Criteria (AC) Defines Events State of the Business Strategy Project Team Status Customer/Program Direction Demonstrates Accomplishments State of the Something WBS Element or Maturity Subsystem Capability Completed Significant Accomplishments (SA) Program/Team Team Status Direction State of the Subsystem Identifies Criteria Process End Item Accomplishment Criteria (AC) Performance Team Direction Deliverables Effort Expended IMP Process Step How Tasks 27/35
  • 28. A set of concise capability specific phrases provide a “stand alone” description of “done” independent of the existence of individual features Maturity Action Capability State Adjective Verb Noun Verb Demonstrates Closure Perform Maturity Step in the Process End Item State Work Preliminary Close General Ledger Successful “A01B02a: Preliminary Month End Close of the General Ledger Successful” 28/35
  • 29. Starting with a “mini-Kaizen,” the maturity Assessment Points (Events) are gathered along with the Significant Accomplishments and Accomplishment Criteria 29/35
  • 30. A mini-Kaizen transfers “Sticky’s” to a Mind Map, then to a Master Schedule then, to a Hanging PERT – producing a “Wall of Truth” for Enterprise Services Working session Sticky’s A Mind Map™ of the Sticky’s PERT Chart Expert™ on the Wall of Truth MS Project™ export of the Mind Map 30/35
  • 31. The three levels of the Integrated Master Plan define the granularity of the deliverables, report progress to plan and project the future cost and effort of tasks Monthly statusing: – Validate schedule status WBS (start/complete/slip) IMP – Validate work package Levels % complete 1, 2, 3 – Claims earned value – Identify/process cost ETCs Funding Profile Weekly statusing: Near term RW period – Roll up of lower level WBS Planning Package Future RW periods schedule Levels status 4, 5 Schedule tasks – Roll up of lower level % complete (at Work Package or level) – Milestone start/complete – Milestone slip (early/late, 20 to 40 start/complete) WBS’s Workday tasks Schedule tasks – % complete of tasks Below (one/two levels Weekly statusing: Work – Milestone start/complete below WP level) – Milestone slip (early/late, Package Or even weekly tasks start/complete) – % complete of tasks 31/35
  • 32. A simple example of vertical and horizontal linking of the capability — provisioning a new employee illustrates the assessment of maturity Capability: Provide Buying Authority within 10 working days of hire Human Resources Information Technology Finance Supply Chain Management New Employee Ready to Work Charge account setup Laptop Account Setup Buying authority available Insurance Orientation 32/35
  • 33. Maturity assessments allow progress to be measured in how terms of “capability” effects the business; not just the consumption of time and resources  Define the desired maturity points along the path to completion  Measure the accomplishments  Assess the effect on business improvement  Engage all participants in a conversation about capability 33/35
  • 34. The deployment of Capabilities Based Planning is the basis of managing the deployment of Enterprise Services  What does done look like in terms of operational capabilities?  How can we measure the increasing maturity of Enterprise Services in terms of “done,” rather than the passage of time?  How can the user community define their operational needs in terms of capabilities rather than features and functions? 34/35
  • 35. References  Miller, Roger and Donald R. Lessard, The Strategic Management of Large-Scale Engineering Projects: Shaping Institutions, Risk, and Governance, MIT Press, 2001.  Guide to Capabilities Based Planning, The Technical Cooperation Program, Joint Systems and Analysis Group, Technical Panel 3.  Allen, Tom, Analysis to Support Capabilities-Based Planning, Capabilities-Based Planning Workshop, October 19-21, 2004.  Davis, Paul K., Analytical Architecture for Capabilities-Based Planning, Mission-System Analysis, and Transformation, RAND Corporation, MR1513  Davis, Paul K., “Exploratory Analysis Enabled by Multiresolution, Multiperspective Modeling,” Proceedings of the 2000 Winter Simulation Conference.  Machiavelli, Niccolo, The Prince and The Discourses, Introduction by Max Lerner, Modern Library,1950 35/35