SlideShare ist ein Scribd-Unternehmen logo
1 von 5
CASE STUDY OF LEAN IMPLEMENTATION IN ELECTRONICS INDUSTRY
Background:
Client is a leading Indian Electronics Systems Design and Manufacturing company with it
manufacturing facilities in Mysore. The company has been in operation for more than two
decades with its customers in India, North America, Europe, Japan and China.
Objective:
 To streamline the operations in one of its units
 To introduce Lean manufacturing in its operations
The scope of workshop was in Unit I of the company which carries out job work on energy
meters and also makes set top boxes.
Diagnostic Study
The lean journey commenced with a current state assessment and road map setting exercise for
energy meters which was being job worked by the company. Keeping in mind the objectives, the
current state of the manufacturing process was defined in a value stream map (VSM) that was
made using the actual cycle times measured for each activity involved in the manufacturing
process. The inventories, number of operators involved were also physically verified on the shop
floor. The summary of the VSM exercise is as follows
Operation Workstation Manpower Cycle time WIP Capacity
Place 250-300
components
in each PCB
3 pick and
place
machines
4 15 secs 3 days 3500
PCB/day (2
shifts)
Reflow
soldering
1 1 8 secs 2 hours 3500
PCB/day (2
shifts)
Testing 1 1 30 secs 1 hour 1800
PCB/day (2
shifts)
Manual
placement of
50-60
components
in each PCB
6 8 3 min. 2 days 2700
PCB/day (3
shifts)
Wave
soldering
1 1 20 secs 1 day 3500
PCB/day (3
shifts)
Manual
placement
and soldering
60 60 12 - 30 secs 2 days
(varying
inventory at
each
workstation)
1800-3800
PCB/day
Testing 3 3 30 secs to 60
secs
- 2000
PCB/day
Drying 1 1 8 hours per -
batch
Back Cover
Assembly
8 8 12 - 30 secs 1 days 1800-3800
/day
Final
Assembly
4 4 12 – 30 secs 1 days 1800-3800 /
day
Baseline study: The existing throughput time for a batch of energy meter to come out of the
facility was varying from 4-6 days. The production rate per day was varying from 1800 to 3200
energy meters per day depending on the demand as well as the number of shifts of production of
various workstations
Due to inventory at almost every workstation, it was observed that there were various instances
of many of the WIP becoming obsolete. The data at various testing workstations showed that the
present quality level was around 98% (20,000 ppm) with some instances of ppm going down to
even 1,00,000 ppm especially after wave soldering.
System Potential: Based on the current state map and our observations, the future state map was
drawn out. It was decided that the throughput time of a batch of energy meters would be brought
down to 2 days considering that 8 hours drying time was essential for every energy meter. The
improvement themes identified were as follows
Improvement themes:
 Reduce the throughput time of energy meters and other products
 Improve the FTR (First Time Right) % of the various workstations
 Provide the flexibility on the lines in order to be able to take up different product mix as
per customer requirement
 Reduce the changeover time of pick and place machine
Roadmap for Lean implementation:
S.No. Current State
Observation
Action Plan Expected
results
Action Mth
1
Mth
2
Mth
3
Mth
4
Mth
5
Mth
6
Mth
7
Mth
8
1 Throughput
time – There
are more than
40
workstations.
Each
workstation had
inventory and
was working
independently.
The total
throughput time
for a batch to
be delivered to
the client was
4-6 days
Future state map
with redesigning
of workstations to
be done. Flow to
be implemented
after the automated
operations till the
drying process
which is in batch
mode. This will
ensure each
workstation pulls
from its upstream
workstation
The
throughput
time was
expected to
be brought
down to 2
days
2 The pacemaker
process was the
Detailed study of
the changeover to
Changeover
time to be
pick and place
process which
places 250-300
components in
each PCB.
Changeover
time in the pick
and place
machines from
one product to
another was
around 90 min.
be carried out.
SMED concepts to
be used to reduce
the changeover
time
reduced to
around 15
min.
3 Defects were
being detected
downstream
much later.
This resulted in
the various
workstations
continuing to
produce bad
quality
components as
feedback is not
received in
time. (Reflow
soldering and
wave soldering
workstations)
Point of
occurrence and
point of detection
to be brought
closer to each
other. Quality
check to be
introduced
immediately after
reflow soldering
and after wave
soldering
PPM is
expected to
be reduced
from 20000
ppm to
around
10000 ppm
4 Reflow
soldering and
wave soldering
were the key
workstations
which
contributes to
the FTR being
low
Identify the root
causes of the
defects and
address them with
temporary and
then permanent
countermeasures.
Expected
that the ppm
of these
workstations
will come
down to
1000 ppm
5 Cycle time at
each of the
workstations
was much
different from
the TAKT time
of pacemaker
process. This
results in line
not being
balanced
Change in the
design of the
workstation to
enable
standardization of
work and equal
distribution of
work across
workstations. This
will also ensure
that irrespective of
product the core
processes are
standardized
All
workstations
to work with
even TAKT
time of
pacemaker
process (15
seconds)
6 All the
workstations
have to be
synchronized
Synchronize and
level schedule
based delivery
dates. Improve the
Reduce the
throughput
time by 10%
with the
pacemaker
process.
monitoring system
through 5S
7 Standardize the
complete
process of
scheduling for
different
product mix
based on client
requirements
Establish SOPs,
visual
management,
monitoring
systems etc.
Consistently
achieve
OTIF (On
time In Full)
of 99.9%
Implementation Methodology
KIAP has a unique intensive workshop methodology to improvement and problem solving in strategic
areas. 2-3 day workshops were conducted in each stage taking up projects in accordance with the lean
roadmap. During these workshops, process improvement and Problem Solving are accelerated thereby
giving significant improvement.
In each workshop, cross-functional teams were formed, each team working on improvement of one
strategically important area. Over a one-year period, participation was ensured from all functions
including finance, stores, marketing and HR. The participants in the workshop simultaneously learn the
relevant lean tools and techniques by actually implementing them. Top Management (owner)
commitment is the pre-requisite for the success of any such initiative and this was obtained by their
physical presence during the presentation/ experience sharing sessions at the start and end of each day of
the workshop.
Standardization of the improvements made was reviewed within 3-4 weeks after each workshop.
Improvement Projects
Project 1 – Implementation of flow
The automated pick and place machines were identified as the pacemaker process as they were
the main influencers in determining the capacity of the entire line. Accordingly, all the manual
workstations were redesigned in terms of processes at each workstation, in such a manner that
every workstation had a cycle time close to the cycle time of pick and place operations i.e.
approx 15 secs. A total of 40 workstations were thus established.
The workstations were then relaid and flow was established from the pick and place process till
the drying process. This ensured that a particular PCB whose processing was started was able to
complete all the processes and reach the drying stage within 2 hours.
Flow was then established, post the drying process, till the final assembly. The total throughput
time achieved for one PCB to get converted to an energy meter was approx 16 hours spread over
two days, including the drying time of 8 hours
The total shop floor space occupied in the new layout was 60% less than the earlier layout.
Project 2 – Changeover time reduction in pick and place machines
The total changeover time in pick and place machines from one product to another was
approximately 90 min. The changeover process involved unloading and reloading of cartridges
carrying various components. The various activities in the changeover process was classified into
online and offline activities and all offline activities were carried out before the start of the actual
changeover. Without the presence of all the cartridges needed for the changeover, the
changeover was not started. This resulted in the total changeover time being reduced to 15 min.
Project 3 – Point of detection of mistakes was made as close to point of occurrence as
possible
The wave soldering operations was identified as the point of occurrences for a number of defects.
However since these defects were actually detected atleast two or three workstations downstream
of the wave soldering workstations, it resulted in a number of PCBs being defectively produced
even thought the defects had already been detected. An inspection workstation was introduced
for the PCBs coming out of wave soldering. This ensured that feedback on wave soldering was
immediately provided and this prevented further defective components produced from wave
soldering. This brought down the ppm after wave soldering from a range of around 20000 ppm
to 10000 ppm
Project 4 – Lifting of components during wave soldering causing quality defects
One of the root causes of quality defects out of wave soldering was the lifting of a transformer
when it is passing over the solder wave. A jig was designed to hold down the transformer which
resulted in the ppm coming down by further 4000 ppm. Thus the quality defects reduced to 6000
ppm after wave soldering.
The above improvements were implemented during the first workshop carried out by us. Further
improvements are still in process and the lean journey is continuing in the organization.
Summary of Results obtained
Parameter Before After Improvement
Throughput time 4 – 6 days 2 days 60% reduction
Floor space occupied 7500 sq.ft. 3000 sq.ft. 60% reduction
Changeover time 90 min. 15 min. 83% reduction
FTR 20000 ppm 6000 ppm 70% reduction
No. of persons 80 persons 60 persons 25% reduction
WIP > 10 days 2 days 80% reduction
The benefits obtained have resulted in the company being able to service the customer with
shorter lead times, take orders of different products and thus be in tune with the market
requirements without compromising on the productivity and quality.

Weitere ähnliche Inhalte

Was ist angesagt?

VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.EngVOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.EngJulian Kalac P.Eng
 
SMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineSMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineParth Patel
 
Manufacturing Excellence Case Studies By Tetrahedron
Manufacturing Excellence Case Studies By Tetrahedron Manufacturing Excellence Case Studies By Tetrahedron
Manufacturing Excellence Case Studies By Tetrahedron Sagar Sangam Sahu
 
Summer Internship Presentation
Summer Internship PresentationSummer Internship Presentation
Summer Internship PresentationTan Quan
 
Rework Reduction in Construction Project
Rework Reduction in Construction ProjectRework Reduction in Construction Project
Rework Reduction in Construction ProjectDr. Firdaus Basbeth
 
Tkis general-quality-containment-2016
Tkis general-quality-containment-2016Tkis general-quality-containment-2016
Tkis general-quality-containment-2016Laura Weiler
 
Cip sip-ctd solution-ivt_presentation
Cip sip-ctd solution-ivt_presentationCip sip-ctd solution-ivt_presentation
Cip sip-ctd solution-ivt_presentationAraik Ambartsumyan
 
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...IRJET Journal
 
A simple nonlinear PD controller for integrating processes
A simple nonlinear PD controller for integrating processesA simple nonlinear PD controller for integrating processes
A simple nonlinear PD controller for integrating processesISA Interchange
 
Julian Kalac lean 6 sigma project list--2018
 Julian Kalac lean 6 sigma  project list--2018 Julian Kalac lean 6 sigma  project list--2018
Julian Kalac lean 6 sigma project list--2018Julian Kalac P.Eng
 
Guidelines for Setting Filter and Module Execution Rate
Guidelines for Setting Filter and Module Execution RateGuidelines for Setting Filter and Module Execution Rate
Guidelines for Setting Filter and Module Execution RateEmerson Exchange
 
Implementation of Lean - Case Study
Implementation of Lean - Case StudyImplementation of Lean - Case Study
Implementation of Lean - Case StudyAmeer Hasan Malik
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSJulian Kalac P.Eng
 
How to implement Single minute exchange of die
How to implement Single minute exchange of die How to implement Single minute exchange of die
How to implement Single minute exchange of die Nikunj Rana
 
Team Optimus_IIM K
Team Optimus_IIM KTeam Optimus_IIM K
Team Optimus_IIM KPravin Bokil
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakharMohammad IFTAKHAR
 

Was ist angesagt? (20)

Asian Paints
Asian PaintsAsian Paints
Asian Paints
 
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.EngVOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
 
SMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineSMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping Line
 
Manufacturing Excellence Case Studies By Tetrahedron
Manufacturing Excellence Case Studies By Tetrahedron Manufacturing Excellence Case Studies By Tetrahedron
Manufacturing Excellence Case Studies By Tetrahedron
 
Summer Internship Presentation
Summer Internship PresentationSummer Internship Presentation
Summer Internship Presentation
 
Rework Reduction in Construction Project
Rework Reduction in Construction ProjectRework Reduction in Construction Project
Rework Reduction in Construction Project
 
Lean Assessment 03-09-11
Lean Assessment 03-09-11Lean Assessment 03-09-11
Lean Assessment 03-09-11
 
Tkis general-quality-containment-2016
Tkis general-quality-containment-2016Tkis general-quality-containment-2016
Tkis general-quality-containment-2016
 
Cip sip-ctd solution-ivt_presentation
Cip sip-ctd solution-ivt_presentationCip sip-ctd solution-ivt_presentation
Cip sip-ctd solution-ivt_presentation
 
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
Identification of Bottleneck and Reducing Cycle Time of an Industrial Oven by...
 
A simple nonlinear PD controller for integrating processes
A simple nonlinear PD controller for integrating processesA simple nonlinear PD controller for integrating processes
A simple nonlinear PD controller for integrating processes
 
Pcsu chapter 1
Pcsu chapter 1Pcsu chapter 1
Pcsu chapter 1
 
Julian Kalac lean 6 sigma project list--2018
 Julian Kalac lean 6 sigma  project list--2018 Julian Kalac lean 6 sigma  project list--2018
Julian Kalac lean 6 sigma project list--2018
 
Guidelines for Setting Filter and Module Execution Rate
Guidelines for Setting Filter and Module Execution RateGuidelines for Setting Filter and Module Execution Rate
Guidelines for Setting Filter and Module Execution Rate
 
Implementation of Lean - Case Study
Implementation of Lean - Case StudyImplementation of Lean - Case Study
Implementation of Lean - Case Study
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
 
How to implement Single minute exchange of die
How to implement Single minute exchange of die How to implement Single minute exchange of die
How to implement Single minute exchange of die
 
Team Optimus_IIM K
Team Optimus_IIM KTeam Optimus_IIM K
Team Optimus_IIM K
 
Lean six sigma black belt project by iftakhar
Lean six sigma black belt project   by iftakharLean six sigma black belt project   by iftakhar
Lean six sigma black belt project by iftakhar
 
CV_2016_rev_4_RW
CV_2016_rev_4_RWCV_2016_rev_4_RW
CV_2016_rev_4_RW
 

Andere mochten auch

Lean journey from changodar to colombo - case study of pump mfg. company - 3r...
Lean journey from changodar to colombo - case study of pump mfg. company - 3r...Lean journey from changodar to colombo - case study of pump mfg. company - 3r...
Lean journey from changodar to colombo - case study of pump mfg. company - 3r...ADD VALUE CONSULTING Inc
 
5 Steps to Building a Social Customer Service Team
5 Steps to Building a Social Customer Service Team5 Steps to Building a Social Customer Service Team
5 Steps to Building a Social Customer Service TeamMichael Pace
 
S3 and EC2 Rails Scenarios
S3 and EC2 Rails ScenariosS3 and EC2 Rails Scenarios
S3 and EC2 Rails ScenariosMartin Rehfeld
 
Improving customer service within the supply chain
Improving customer service within the supply chainImproving customer service within the supply chain
Improving customer service within the supply chainSiddharth Chandrasekar
 
Underperforming Team Case Study
Underperforming Team Case StudyUnderperforming Team Case Study
Underperforming Team Case StudyTushar G
 
Case study customer service southwest airlines
Case study customer service southwest airlinesCase study customer service southwest airlines
Case study customer service southwest airlinesLisa Fields
 
Lean manufacturing case study
Lean manufacturing case studyLean manufacturing case study
Lean manufacturing case studyTri Dung Nguyen
 
Tinker Tower DFSS Class Exercise
Tinker Tower DFSS Class ExerciseTinker Tower DFSS Class Exercise
Tinker Tower DFSS Class ExerciseRamon Balisnomo
 
Effective Team Behaveor
Effective Team BehaveorEffective Team Behaveor
Effective Team Behaveorkanaidi
 
Customer service training for mobil filling station attendants(1)
Customer service training for mobil filling station attendants(1)Customer service training for mobil filling station attendants(1)
Customer service training for mobil filling station attendants(1)Olatunji Olajide
 
How to provide excellent customer service in your leisure centre
How to provide excellent customer service in your leisure centreHow to provide excellent customer service in your leisure centre
How to provide excellent customer service in your leisure centreSports Marketing Network
 
Operations Management at Petrol retail outlet
Operations Management at Petrol retail outletOperations Management at Petrol retail outlet
Operations Management at Petrol retail outletDarshit Paun
 
75 Customer Service Facts, Quotes & Statistics
75 Customer Service Facts, Quotes & Statistics75 Customer Service Facts, Quotes & Statistics
75 Customer Service Facts, Quotes & StatisticsHelp Scout
 
Ace enablers energy saving machine uptime-harmonic mitigation
Ace enablers energy saving machine uptime-harmonic mitigationAce enablers energy saving machine uptime-harmonic mitigation
Ace enablers energy saving machine uptime-harmonic mitigationSrinivasan Jeyaram
 
Customer service training[1]
Customer service training[1]Customer service training[1]
Customer service training[1]loryn_aquino
 

Andere mochten auch (18)

Lean journey from changodar to colombo - case study of pump mfg. company - 3r...
Lean journey from changodar to colombo - case study of pump mfg. company - 3r...Lean journey from changodar to colombo - case study of pump mfg. company - 3r...
Lean journey from changodar to colombo - case study of pump mfg. company - 3r...
 
5 Steps to Building a Social Customer Service Team
5 Steps to Building a Social Customer Service Team5 Steps to Building a Social Customer Service Team
5 Steps to Building a Social Customer Service Team
 
S3 and EC2 Rails Scenarios
S3 and EC2 Rails ScenariosS3 and EC2 Rails Scenarios
S3 and EC2 Rails Scenarios
 
Improving customer service within the supply chain
Improving customer service within the supply chainImproving customer service within the supply chain
Improving customer service within the supply chain
 
Underperforming Team Case Study
Underperforming Team Case StudyUnderperforming Team Case Study
Underperforming Team Case Study
 
Case study customer service southwest airlines
Case study customer service southwest airlinesCase study customer service southwest airlines
Case study customer service southwest airlines
 
Lean manufacturing case study
Lean manufacturing case studyLean manufacturing case study
Lean manufacturing case study
 
Tinker Tower DFSS Class Exercise
Tinker Tower DFSS Class ExerciseTinker Tower DFSS Class Exercise
Tinker Tower DFSS Class Exercise
 
Effective Team Behaveor
Effective Team BehaveorEffective Team Behaveor
Effective Team Behaveor
 
Customer service training for mobil filling station attendants(1)
Customer service training for mobil filling station attendants(1)Customer service training for mobil filling station attendants(1)
Customer service training for mobil filling station attendants(1)
 
brain teaser
brain teaserbrain teaser
brain teaser
 
How to provide excellent customer service in your leisure centre
How to provide excellent customer service in your leisure centreHow to provide excellent customer service in your leisure centre
How to provide excellent customer service in your leisure centre
 
Operations Management at Petrol retail outlet
Operations Management at Petrol retail outletOperations Management at Petrol retail outlet
Operations Management at Petrol retail outlet
 
75 Customer Service Facts, Quotes & Statistics
75 Customer Service Facts, Quotes & Statistics75 Customer Service Facts, Quotes & Statistics
75 Customer Service Facts, Quotes & Statistics
 
Team Building & Team Work
Team Building & Team WorkTeam Building & Team Work
Team Building & Team Work
 
Ace enablers energy saving machine uptime-harmonic mitigation
Ace enablers energy saving machine uptime-harmonic mitigationAce enablers energy saving machine uptime-harmonic mitigation
Ace enablers energy saving machine uptime-harmonic mitigation
 
Lean Manufacturing - Toyota Production System
Lean Manufacturing - Toyota Production SystemLean Manufacturing - Toyota Production System
Lean Manufacturing - Toyota Production System
 
Customer service training[1]
Customer service training[1]Customer service training[1]
Customer service training[1]
 

Ähnlich wie Case study electronics industry

Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industryGanesh TN
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS Julian Kalac P.Eng
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryijmech
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.Raheem Arif
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study ChallengeNikhil Kejriwal
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTFASI93
 
Nokia manaus090828 final_presentation_vsa_v4
Nokia manaus090828 final_presentation_vsa_v4Nokia manaus090828 final_presentation_vsa_v4
Nokia manaus090828 final_presentation_vsa_v4CarlosMoura111
 
Lean Manufacturing Consultants in Chennai - Hash Management Services LLP
Lean Manufacturing Consultants in Chennai - Hash Management Services LLPLean Manufacturing Consultants in Chennai - Hash Management Services LLP
Lean Manufacturing Consultants in Chennai - Hash Management Services LLPHash Management Services LLP
 
Ngo Chian Ming profile
Ngo Chian Ming profileNgo Chian Ming profile
Ngo Chian Ming profileChian Ming Ngo
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)MohammedLahssaini1
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...Karina Islam
 
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGPALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGFuratAj
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysisvideoaakash15
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysisvideoaakash15
 
Supply chain design and operation
Supply chain design and operationSupply chain design and operation
Supply chain design and operationAngelainBay
 
Ch12 jit+&+lean+systems
Ch12 jit+&+lean+systemsCh12 jit+&+lean+systems
Ch12 jit+&+lean+systemsvideoaakash15
 
Capacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningCapacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningRaju Pegada
 

Ähnlich wie Case study electronics industry (20)

Case study furniture industry
Case study   furniture industryCase study   furniture industry
Case study furniture industry
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
 
Application of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industryApplication of value stream mapping tool to reduce wastes in bearing industry
Application of value stream mapping tool to reduce wastes in bearing industry
 
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
PRODUCTIVITY IMPROVEMENT OF PRE-TREATMENTS & POWDER COATING PROCESS.
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study Challenge
 
Mid Year Review
Mid Year ReviewMid Year Review
Mid Year Review
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPT
 
Scheduling Dedicated
Scheduling DedicatedScheduling Dedicated
Scheduling Dedicated
 
Nokia manaus090828 final_presentation_vsa_v4
Nokia manaus090828 final_presentation_vsa_v4Nokia manaus090828 final_presentation_vsa_v4
Nokia manaus090828 final_presentation_vsa_v4
 
Lean Manufacturing Consultants in Chennai - Hash Management Services LLP
Lean Manufacturing Consultants in Chennai - Hash Management Services LLPLean Manufacturing Consultants in Chennai - Hash Management Services LLP
Lean Manufacturing Consultants in Chennai - Hash Management Services LLP
 
Ngo Chian Ming profile
Ngo Chian Ming profileNgo Chian Ming profile
Ngo Chian Ming profile
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
 
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY  IMPLEMENTING LEAN TOOLS AN...
IMPROVING OSH & PRODUCTIVITY OF RMG INDUSTRIES BY IMPLEMENTING LEAN TOOLS AN...
 
PALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPINGPALCO INDUSTRY USING VALUE STREAM MAPPING
PALCO INDUSTRY USING VALUE STREAM MAPPING
 
MyPGDMM_MS_Chap12_TQM (1).pdf
MyPGDMM_MS_Chap12_TQM (1).pdfMyPGDMM_MS_Chap12_TQM (1).pdf
MyPGDMM_MS_Chap12_TQM (1).pdf
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
 
Ch5 process+analysis
Ch5 process+analysisCh5 process+analysis
Ch5 process+analysis
 
Supply chain design and operation
Supply chain design and operationSupply chain design and operation
Supply chain design and operation
 
Ch12 jit+&+lean+systems
Ch12 jit+&+lean+systemsCh12 jit+&+lean+systems
Ch12 jit+&+lean+systems
 
Capacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity PlanningCapacity Requirement Planning, Rough Cut Capacity Planning
Capacity Requirement Planning, Rough Cut Capacity Planning
 

Kürzlich hochgeladen

Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Pooja Nehwal
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Alex Marques
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningCIToolkit
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxalinstan901
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607dollysharma2066
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampPLCLeadershipDevelop
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptxAss.Prof. Dr. Mogeeb Mosleh
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girladitipandeya
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceanilsa9823
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic managementharfimakarim
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, MumbaiPooja Nehwal
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyHafizMuhammadAbdulla5
 

Kürzlich hochgeladen (20)

Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
Call now : 9892124323 Nalasopara Beautiful Call Girls Vasai virar Best Call G...
 
Disrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdfDisrupt or be Disrupted - Kirk Vallis.pdf
Disrupt or be Disrupted - Kirk Vallis.pdf
 
Empowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdfEmpowering Local Government Frontline Services - Mo Baines.pdf
Empowering Local Government Frontline Services - Mo Baines.pdf
 
Discover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdfDiscover -CQ Master Class - Rikita Wadhwa.pdf
Discover -CQ Master Class - Rikita Wadhwa.pdf
 
Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024Construction Project Management | Coursera 2024
Construction Project Management | Coursera 2024
 
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdfImagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
Imagine - Creating Healthy Workplaces - Anthony Montgomery.pdf
 
Continuous Improvement Infographics for Learning
Continuous Improvement Infographics for LearningContinuous Improvement Infographics for Learning
Continuous Improvement Infographics for Learning
 
Agile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptxAgile Coaching Change Management Framework.pptx
Agile Coaching Change Management Framework.pptx
 
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607GENUINE Babe,Call Girls IN Baderpur  Delhi | +91-8377087607
GENUINE Babe,Call Girls IN Baderpur Delhi | +91-8377087607
 
LoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner CircleLoveLocalGov - Chris Twigg, Inner Circle
LoveLocalGov - Chris Twigg, Inner Circle
 
Day 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC BootcampDay 0- Bootcamp Roadmap for PLC Bootcamp
Day 0- Bootcamp Roadmap for PLC Bootcamp
 
Reviewing and summarization of university ranking system to.pptx
Reviewing and summarization of university ranking system  to.pptxReviewing and summarization of university ranking system  to.pptx
Reviewing and summarization of university ranking system to.pptx
 
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call GirlVIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
VIP 7001035870 Find & Meet Hyderabad Call Girls Kondapur high-profile Call Girl
 
Becoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette ThompsonBecoming an Inclusive Leader - Bernadette Thompson
Becoming an Inclusive Leader - Bernadette Thompson
 
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual serviceCALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
CALL ON ➥8923113531 🔝Call Girls Charbagh Lucknow best sexual service
 
internal analysis on strategic management
internal analysis on strategic managementinternal analysis on strategic management
internal analysis on strategic management
 
Intro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptxIntro_University_Ranking_Introduction.pptx
Intro_University_Ranking_Introduction.pptx
 
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
{ 9892124323 }} Call Girls & Escorts in Hotel JW Marriott juhu, Mumbai
 
CEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biographyCEO of Google, Sunder Pichai's biography
CEO of Google, Sunder Pichai's biography
 
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 16 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 

Case study electronics industry

  • 1. CASE STUDY OF LEAN IMPLEMENTATION IN ELECTRONICS INDUSTRY Background: Client is a leading Indian Electronics Systems Design and Manufacturing company with it manufacturing facilities in Mysore. The company has been in operation for more than two decades with its customers in India, North America, Europe, Japan and China. Objective:  To streamline the operations in one of its units  To introduce Lean manufacturing in its operations The scope of workshop was in Unit I of the company which carries out job work on energy meters and also makes set top boxes. Diagnostic Study The lean journey commenced with a current state assessment and road map setting exercise for energy meters which was being job worked by the company. Keeping in mind the objectives, the current state of the manufacturing process was defined in a value stream map (VSM) that was made using the actual cycle times measured for each activity involved in the manufacturing process. The inventories, number of operators involved were also physically verified on the shop floor. The summary of the VSM exercise is as follows Operation Workstation Manpower Cycle time WIP Capacity Place 250-300 components in each PCB 3 pick and place machines 4 15 secs 3 days 3500 PCB/day (2 shifts) Reflow soldering 1 1 8 secs 2 hours 3500 PCB/day (2 shifts) Testing 1 1 30 secs 1 hour 1800 PCB/day (2 shifts) Manual placement of 50-60 components in each PCB 6 8 3 min. 2 days 2700 PCB/day (3 shifts) Wave soldering 1 1 20 secs 1 day 3500 PCB/day (3 shifts) Manual placement and soldering 60 60 12 - 30 secs 2 days (varying inventory at each workstation) 1800-3800 PCB/day Testing 3 3 30 secs to 60 secs - 2000 PCB/day Drying 1 1 8 hours per -
  • 2. batch Back Cover Assembly 8 8 12 - 30 secs 1 days 1800-3800 /day Final Assembly 4 4 12 – 30 secs 1 days 1800-3800 / day Baseline study: The existing throughput time for a batch of energy meter to come out of the facility was varying from 4-6 days. The production rate per day was varying from 1800 to 3200 energy meters per day depending on the demand as well as the number of shifts of production of various workstations Due to inventory at almost every workstation, it was observed that there were various instances of many of the WIP becoming obsolete. The data at various testing workstations showed that the present quality level was around 98% (20,000 ppm) with some instances of ppm going down to even 1,00,000 ppm especially after wave soldering. System Potential: Based on the current state map and our observations, the future state map was drawn out. It was decided that the throughput time of a batch of energy meters would be brought down to 2 days considering that 8 hours drying time was essential for every energy meter. The improvement themes identified were as follows Improvement themes:  Reduce the throughput time of energy meters and other products  Improve the FTR (First Time Right) % of the various workstations  Provide the flexibility on the lines in order to be able to take up different product mix as per customer requirement  Reduce the changeover time of pick and place machine Roadmap for Lean implementation: S.No. Current State Observation Action Plan Expected results Action Mth 1 Mth 2 Mth 3 Mth 4 Mth 5 Mth 6 Mth 7 Mth 8 1 Throughput time – There are more than 40 workstations. Each workstation had inventory and was working independently. The total throughput time for a batch to be delivered to the client was 4-6 days Future state map with redesigning of workstations to be done. Flow to be implemented after the automated operations till the drying process which is in batch mode. This will ensure each workstation pulls from its upstream workstation The throughput time was expected to be brought down to 2 days 2 The pacemaker process was the Detailed study of the changeover to Changeover time to be
  • 3. pick and place process which places 250-300 components in each PCB. Changeover time in the pick and place machines from one product to another was around 90 min. be carried out. SMED concepts to be used to reduce the changeover time reduced to around 15 min. 3 Defects were being detected downstream much later. This resulted in the various workstations continuing to produce bad quality components as feedback is not received in time. (Reflow soldering and wave soldering workstations) Point of occurrence and point of detection to be brought closer to each other. Quality check to be introduced immediately after reflow soldering and after wave soldering PPM is expected to be reduced from 20000 ppm to around 10000 ppm 4 Reflow soldering and wave soldering were the key workstations which contributes to the FTR being low Identify the root causes of the defects and address them with temporary and then permanent countermeasures. Expected that the ppm of these workstations will come down to 1000 ppm 5 Cycle time at each of the workstations was much different from the TAKT time of pacemaker process. This results in line not being balanced Change in the design of the workstation to enable standardization of work and equal distribution of work across workstations. This will also ensure that irrespective of product the core processes are standardized All workstations to work with even TAKT time of pacemaker process (15 seconds) 6 All the workstations have to be synchronized Synchronize and level schedule based delivery dates. Improve the Reduce the throughput time by 10%
  • 4. with the pacemaker process. monitoring system through 5S 7 Standardize the complete process of scheduling for different product mix based on client requirements Establish SOPs, visual management, monitoring systems etc. Consistently achieve OTIF (On time In Full) of 99.9% Implementation Methodology KIAP has a unique intensive workshop methodology to improvement and problem solving in strategic areas. 2-3 day workshops were conducted in each stage taking up projects in accordance with the lean roadmap. During these workshops, process improvement and Problem Solving are accelerated thereby giving significant improvement. In each workshop, cross-functional teams were formed, each team working on improvement of one strategically important area. Over a one-year period, participation was ensured from all functions including finance, stores, marketing and HR. The participants in the workshop simultaneously learn the relevant lean tools and techniques by actually implementing them. Top Management (owner) commitment is the pre-requisite for the success of any such initiative and this was obtained by their physical presence during the presentation/ experience sharing sessions at the start and end of each day of the workshop. Standardization of the improvements made was reviewed within 3-4 weeks after each workshop. Improvement Projects Project 1 – Implementation of flow The automated pick and place machines were identified as the pacemaker process as they were the main influencers in determining the capacity of the entire line. Accordingly, all the manual workstations were redesigned in terms of processes at each workstation, in such a manner that every workstation had a cycle time close to the cycle time of pick and place operations i.e. approx 15 secs. A total of 40 workstations were thus established. The workstations were then relaid and flow was established from the pick and place process till the drying process. This ensured that a particular PCB whose processing was started was able to complete all the processes and reach the drying stage within 2 hours. Flow was then established, post the drying process, till the final assembly. The total throughput time achieved for one PCB to get converted to an energy meter was approx 16 hours spread over two days, including the drying time of 8 hours The total shop floor space occupied in the new layout was 60% less than the earlier layout. Project 2 – Changeover time reduction in pick and place machines The total changeover time in pick and place machines from one product to another was approximately 90 min. The changeover process involved unloading and reloading of cartridges carrying various components. The various activities in the changeover process was classified into online and offline activities and all offline activities were carried out before the start of the actual changeover. Without the presence of all the cartridges needed for the changeover, the changeover was not started. This resulted in the total changeover time being reduced to 15 min.
  • 5. Project 3 – Point of detection of mistakes was made as close to point of occurrence as possible The wave soldering operations was identified as the point of occurrences for a number of defects. However since these defects were actually detected atleast two or three workstations downstream of the wave soldering workstations, it resulted in a number of PCBs being defectively produced even thought the defects had already been detected. An inspection workstation was introduced for the PCBs coming out of wave soldering. This ensured that feedback on wave soldering was immediately provided and this prevented further defective components produced from wave soldering. This brought down the ppm after wave soldering from a range of around 20000 ppm to 10000 ppm Project 4 – Lifting of components during wave soldering causing quality defects One of the root causes of quality defects out of wave soldering was the lifting of a transformer when it is passing over the solder wave. A jig was designed to hold down the transformer which resulted in the ppm coming down by further 4000 ppm. Thus the quality defects reduced to 6000 ppm after wave soldering. The above improvements were implemented during the first workshop carried out by us. Further improvements are still in process and the lean journey is continuing in the organization. Summary of Results obtained Parameter Before After Improvement Throughput time 4 – 6 days 2 days 60% reduction Floor space occupied 7500 sq.ft. 3000 sq.ft. 60% reduction Changeover time 90 min. 15 min. 83% reduction FTR 20000 ppm 6000 ppm 70% reduction No. of persons 80 persons 60 persons 25% reduction WIP > 10 days 2 days 80% reduction The benefits obtained have resulted in the company being able to service the customer with shorter lead times, take orders of different products and thus be in tune with the market requirements without compromising on the productivity and quality.