SlideShare ist ein Scribd-Unternehmen logo
1 von 42
Downloaden Sie, um offline zu lesen
BUILDING CONSTRUCTION 1 (ARC 1523)
DEGREE YEAR 1 SEM 2 (MAR 14)
PROJECT 2: Construction Activities and Process
YAP ZHI JUN 0310738
Week 1
Construction Activity 1: Earthwork
 Duration: 6 Days
 Skilled worker: Land surveyor (1), land surveyor assistant (1), civil engineer (1), civil engineer
assistant (1)
 Technical information: Survey topography for measurement of earthwork quantities.
Week 2
Construction Activity 1: Earthwork
 Duration: 6 Days
 Equipment: Backhoe (1), excavator (1), dumper (1)
 Skilled worker: Backhoe operator (1), dumper operator (1), general worker (1)
 Technical information: Site is cleared of trees, topsoil, shrubs and rubbish.
Week 3 & 4
Construction Activity 1: Earthwork
 Duration: 12 Days
 Equipment: Portable penetrometer (1)
 Skilled worker: Geotechnical engineer (1), geotechnical engineer assistant (1), civil
engineer (1), civil engineer assistant (1)
 Technical information: Mackintosh Probe (MP) test carried out for testing soft soils
and determining suitable materials.
Week 5
Construction Activity 1: Earthwork
 Duration: 6 Days
 Equipment: Vibrating plate compactor (1), backhoe (1), excavator (1), paver (1), dumper (1)
 Skilled worker: Backhoe operator (1), excavator operator (1), paver (1), dumper operator (1),
general worker (1), grader (1), rollers (1)
 Technical information: Site is excavated to required lengths, depths, breadths, inclinations
and curvatures
Week 6
Construction Activity 1: Earthwork
 Duration: 6 Days
 Materials: Timber formwork, gravel
 Equipment: Table saw (2), shovel (2), long tape measurer, steel tape, strong threads, wire
nails, theodolite, wooden pegs, drill hammer
 Skilled worker: Carpenter (2), general worker (1)
 Technical information: Filling materials to lines, levels and grades required to complete
permanent construction.
Week 7
Construction activity 1: Transporting piles
 Duration: 2 days
 Materials: piles
 Equipment: Lorry (2), Crane (1)
 Skilled worker: Lorry driver (4), Crane Operator (1)
 Technical information: Transporting piles from factory, lift the piles by using crane from lorry
after reaching the site.
Week 8
Construction activity 1: Pile driving process
 Duration: 12 days
 Materials: piles, pile cushion, bituminous paint
 Equipment: Hydraulic drop hammer (1)
 Skilled worker: contractor (1), Hydraulic drop hammer operator (1), General worker (3)
 Technical information: Mobilize the hydraulic drop hammer to the intended pile position
after marking penetration of the piles, set out the position of drop hammer above the pile
point, pile driving, weld the joints between the piles, and apply bituminous paint around the
joints of welded piles to prevent rusting.
Week 9
Construction activity 1: Cut off process
 Duration: 3 days
 Equipment: Multipurpose excavator (1), Pneumatic hammer (1), Oxy-cutter (1)
 Skilled worker: Excavator operator (1), General worker (2)
 Technical information: Excavate 1m to 1.5m depth by using multipurpose excavator, cut the
piles to make sure all are in the same height using Pneumatic hammer, the reinforcement in
the pile is cut by oxy-cutter.
Week 10
Construction activity 1: Set up formwork for pile cap
 Duration: 5 days
 Material: Plywood, nails, reinforcement
 Equipment: hammer, measuring tape, drill, handsaw
 Skilled worker: general worker (3)
 Technical information: Set up formwork for pile cap, insert reinforcement for pile cap, and
set up the reinforcement for column stump before pouring the concrete.
Week 11
Construction activity 1: Pour concrete into the formwork
 Duration: 2 days
 Material: Concrete
 Equipment: Concrete mixer truck, Skip, Concrete vibrator
 Skilled worker: Concrete mixer truck operator (1), general worker (3)
 Technical information: Pour the concrete into the formwork through skip from concrete
mixer truck, vibrate and mix the concrete evenly using concrete vibrator to increase its
strength by preventing air pockets.
Construction activity 2: Pile cap harden process
 Duration: 7 days
 Technical information: Let the concrete pile cap harden for 7 days to wait it mature and
sufficient strength, open formwork after completed.
Week 12
Construction activity 1: Set up formwork for column stump
 Duration: 2 days
 Material: Plywood, nails
 Equipment: hammer, measuring tape, drill, handsaw
 Skilled worker: General worker (2)
 Technical information: Set up formwork for column stump before pouring the concrete.
Construction activity 2: Underground services
 Duration: 6 days
 Material: Metal conduit, steel/ aluminium tubing or PVC tubing, hexagonal plumbing fitting,
plumbing sealant
 Equipment: Plow chute, winch
 Skilled worker: Electrician (1), general worker (2), plumber (1)
 Technical information: Bury cable preinstalled in cable-in-conduit (CIC) and main plumbing
pipes at excavated level.
Week 13
Construction activity 1: Pour concrete into the formwork
Duration: 2 days
 Material: Concrete
 Equipment: Concrete mixer truck, Skip, Concrete vibrator
 Skilled worker:
 Technical information: Pour the concrete into the formwork through skip from concrete
mixer truck, vibrate the concrete to increase its strength.
Construction activity 2: Column stump harden process
 Duration: 7 days
 Technical information: Let the concrete column stump harden for 7 days to wait it mature
and sufficient strength, open formwork after completed
Week 14
Construction activity 1: Back filling the pile foundation
 Duration: 1 day
 Material: soil
 Equipment: Multipurpose excavator (1)
 Skilled worker: Multipurpose excavator Operator
 Technical information: After the harden process, fill up the excavated part around the
foundation to move on to the next process.
Week 15
Construction Activity 1: Construction of ground beam (Ground floor)
 Duration: 6 Days
 Materials: Concrete Grade 30, reinforcement, timber formwork
 Equipment: Concrete vibrator (1), bar bending machine (1), table saw, machine mix concrete
(1)
 Skilled worker: Carpenter (2), bar bender (1), general worker (1)
 Technical information: Determine material, marking form panels, erecting the formwork,
provision a camber, brace the wood with stringer and support by struts and cleat, slump test,
and pour cement concrete.
Week 16
Construction Activity 1: Slab (Ground floor)
 Duration: 6 Days
 Materials: Plywood formwork, reinforced steel, service pipes, concrete Grade 20
 Equipment: Dip-galvanised nails, hammer, measuring tape, table saw, mixer truck,
concrete vibrator, tipper, wheelbarrow.
 Skilled worker: General worker (2), carpenter (1), bar bender (2)
 Technical information: build formwork with plywood, fix reinforced steel, construction
slab formwork, slump test and pour concrete.
 Thickness range of plywood: 7mm - 32mm
Week 17
Construction Activity 1: Construction of columns (Ground floor)
 Duration: 6 Days
 Materials: Concrete Grade 30, reinforcement, timber formwork
 Equipment: Concrete vibrator (1), bar bending machine (1), table saw
 Skilled worker: Carpenter (2), bar bender (1), general worker (1)
 Technical information: Place reinforcement bar and secured to the column formwork and
the floor, slump test and poured concrete.
Week 18
Construction Activity 1: Construction of beam (First floor)
Duration: 6 Days
 Materials: Concrete Grade 30, reinforcement, timber formwork
 Equipment: Concrete vibrator (1), bar bending machine (1), table saw, machine mix concrete
(1)
 Skilled worker: Carpenter (2), bar bender (1), general worker (1)
 Technical information: Determine material, marking form panels, erecting the formwork,
provision a camber, brace the wood with stringer and support by struts and cleat, slump test,
and pour cement concrete.
Week 19
Construction Activity 1: Construction of slab (First Floor)
 Duration: 6 Days
 Materials: Plywood formwork, reinforced steel, service pipes, concrete Grade 20
 Equipment: Dip-galvanised nails, hammer, measuring tape, table saw, mixer truck, concrete
vibrator, tipper, wheelbarrow.
 Skilled worker: General worker (2), carpenter (1), bar bender (2)
 Technical information: build formwork with plywood, fix reinforced steel, construction slab
formwork, slump test and pour concrete.
 Thickness range of plywood: 7mm - 32mm
Week 20
Construction Activity 1: Staircase (Ground floor)
 Duration: 3 Days
 Materials: Ply Woods, Timber Battens
 Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw
 Skilled worker: Carpenter (1), Joinery (1)
 Technical information: Make a pitch board with the angle of 30°. Hold pitch board on the
side to represent the top of the stair slab and mark the riser and tread
Construction Activity 2: Staircase (Ground floor)
 Duration: 3 Days
 Materials: Timber, Metal or Prefabricated Formwork
 Equipment: Drill, Hammer, Hand Saw
 Skilled worker: Bar Benders (1), Formwork Carpenters (1)
 Technical information: Construct formwork by laying out riser heights and tread widths
followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Cut
and nailed cleats to plank, nail riser form boards to the ends of cleats.
Week 21
Construction Activity 1: Staircase (Ground floor)
 Duration: 2 Days
 Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place sleeve
 Equipment: Measuring Tape, chalk line, drill, hammer, hand saw
 Skilled worker: Bar Benders (1), Formwork Carpenters (1)
 Technical information: Create strong grid of rebar, two or more pieces of rebar cross are
joined together. Secure riser form board with cleats attached about an inch above the stairs
layout to the slide form.
Construction Activity 2: Staircase (Ground floor)
 Duration: 4 Days
 Materials: Concrete, Long screws, Nails
 Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board
 Skilled worker: Carpenters (2)
 Technical information: Concrete ceiling and stairs pour. Keep the concrete wet or damp to
prevent cracks for up to one week while it cures.
Week 22
Construction Activity 1: Construction of columns (First floor)
 Duration: 6 Days
 Materials: Concrete Grade 30, reinforcement, timber formwork
 Equipment: Concrete vibrator (1), bar bending machine (1), table saw
 Skilled worker: Carpenter (2), bar bender (1), general worker (1)
 Technical information: Place reinforcement bar and secured to the column formwork and
the floor, slump test and poured concrete.
Week 23
Construction Activity 1: Construction of beam (Second floor)
 Duration: 6 Days
 Materials: Concrete Grade 30, reinforcement, timber formwork
 Equipment: Concrete vibrator (1), bar bending machine (1), table saw, machine mix concrete
(1)
 Skilled worker: Carpenter (2), bar bender (1), general worker (1)
 Technical information: Determine material, marking form panels, erecting the formwork,
provision a camber, brace the wood with stringer and support by struts and cleat, slump test,
and pour cement concrete.
Week 24
Construction Activity 1: Slab (Second Floor)
 Duration: 6 Days
 Materials: Plywood formwork, reinforced steel, service pipes, concrete Grade 20
 Equipment: Dip-galvanised nails, hammer, measuring tape, table saw, mixer truck, concrete
vibrator, tipper, wheelbarrow.
 Skilled worker: General worker (2), carpenter (1), bar bender (2)
 Technical information: build formwork with plywood, fix reinforced steel, construction slab
formwork, slump test and pour concrete.
 Thickness range of plywood: 7mm - 32mm
Week 25
Construction Activity 1: Staircase (First floor)
 Duration: 3 Days
 Materials: Ply Woods, Timber Battens
 Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw
 Skilled worker: Carpenter (1), Joinery (1)
 Technical information: Make a pitch board with the angle of 30°. Hold pitch board on the
side to represent the top of the stair slab and mark the riser and tread
Construction Activity 2: Staircase (First floor)
 Duration: 3 Days
 Materials: Timber, Metal or Prefabricated Formwork
 Equipment: Drill, Hammer, Hand Saw
 Skilled worker: Bar Benders (1), Formwork Carpenters (1)
 Technical information: Construct formwork by laying out riser heights and tread widths
followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Cut
and nailed cleats to plank, nail riser form boards to the ends of cleats.
Week 26
Construction Activity 1: Staircase (First floor)
 Duration: 2 Days
 Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place sleeve
 Equipment: Measuring Tape, chalk line, drill, hammer, hand saw
 Skilled worker: Bar Benders (1), Formwork Carpenters (1)
 Technical information: Create strong grid of rebar, two or more pieces of rebar cross are
joined together. Secure riser form board with cleats attached about an inch above the stairs
layout to the slide form.
Construction Activity 2: Staircase (First floor)
 Duration: 4 Days
 Materials: Concrete, Long screws, Nails
 Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board
 Skilled worker: Carpenters (2)
 Technical information: Concrete ceiling and stairs pour. Keep the concrete wet or damp to
prevent cracks for up to one week while it cures.
Week 27
Construction Activity 1: Construction of columns (Second floor)
 Duration: 6 Days
 Materials: Concrete Grade 30, reinforcement, timber formwork
 Equipment: Concrete vibrator (1), bar bending machine (1), table saw
 Skilled worker: Carpenter (2), bar bender (1), general worker (1)
 Technical information: Place reinforcement bar and secured to the column formwork and
the floor, slump test and poured concrete.
Week 28
Construction Activity 1: Construction of beam (Third floor)
 Duration: 6 Days
 Materials: Concrete Grade 30, reinforcement, timber formwork
 Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix
concrete (1)
 Skilled worker: Carpenter (2) , bar bender (1), general worker (1)
 Technical information: Determine material, marking form panels, erecting the formwork,
provision a camber, brace the wood with stringer and support by struts and cleat, slump test,
and pour cement concrete.
Week 29
Construction Activity 1: Brickwork (Ground floor)
 Duration: 5 days
 Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
 Equipment: Rose Brick Trowels, carpenter level, brick jointer
 Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1).
 Technical information: Brickwork process including bricks, beds and perpends. The bed is
made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled
with mortar.
Construction Activity 2: Installation of door frame (Ground floor)
 Duration: 2 days
 Materials: Screws, ‘L’ bracket, jambs, striker plate, PVC stopper, head, adaptor bar, brick ties,
hinges, spreader bars.
 Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler,
measuring tape, stapler, and screwdriver
 Skilled worker: general worker (1), door and window installer (1)
 Technical information: Mark door and bricks area, use timber to prop up door to standing
position, use spirit to plumb the frame, secure timber stays with bricks, lay the bricks, place
mortar into gap of the brick and frame, insert wire brick ties.
Week 30
Construction Activity 1: Brickwork (First floor)
 Duration: 5 days
 Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
 Equipment: Rose Brick Trowels, carpenter level, brick jointer
 Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1).
 Technical information: Brickwork process including bricks, beds and perpends. The bed is
made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled
with mortar.
Construction Activity 2: Brickwork – Rendering (Ground floor)
 Duration: 3 Days
 Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White
Cement
Equipment: Masonry Brushes, Sled Runners,
 Skilled worker: Pointing, cleaning, and caulking workers (1) and plasterer (1).
 Technical information:
 Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch
first coat of render before it set to provide key for second layer. Skim coat mixed blended
white cement on it.
Week 31
Construction Activity 1: Brickwork (Second floor)
 Duration: 5 days
 Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh
 Equipment: Rose Brick Trowels, carpenter level, brick jointer
 Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1).
 Technical information: Brickwork process including bricks, beds and perpends. The bed is
made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled
with mortar.
Construction Activity 2: Brickwork – Rendering (First floor)
 Duration: 3 Days
 Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White
Cement
Equipment: Masonry Brushes, Sled Runners,
 Skilled worker: Pointing, cleaning, and caulking workers (1) and plasterer (1).
 Technical information:
 Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch
first coat of render before it set to provide key for second layer. Skim coat mixed blended
white cement on it.
Week 32
Construction Activity 2: Brickwork – Rendering (Second floor)
 Duration: 3 Days
 Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White
Cement
Equipment: Masonry Brushes, Sled Runners,
 Skilled worker: Pointing, cleaning, and caulking workers (1) and plasterer (1).
 Technical information:
 Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch
first coat of render before it set to provide key for second layer. Skim coat mixed blended
white cement on it.
Construction Activity 2: Installation of door frame (First and Second floors)
 Duration: 2 days
 Materials: Screws, ‘L’ bracket, jambs, striker plate, PVC stopper, head, adaptor bar, brick ties,
hinges, spreader bars.
 Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler,
measuring tape, stapler, and screwdriver
 Skilled worker: general worker (1), door and window installer (1)
 Technical information: Mark door and bricks area, use timber to prop up door to standing
position, use spirit to plumb the frame, secure timber stays with bricks, lay the bricks, place
mortar into gap of the brick and frame, insert wire brick ties.
Week 33
Construction Activity 1: Roof
 Duration: 6 Days
 Materials: Meranti timber formwork, metal trusses
 Equipment: Crane (1), lorry (1), handsaw, driller, dip-galvanised nails, hammer,
measuring tape
 Skilled worker: Roofer (1), general worker (1), crane operator (1), lorry driver (1)
 Technical information: Check trusses, interior/exterior alignment, prepare clear access
to worksite, prepare storage for trusses.
Week 34
Construction Activity 1: Roof
 Duration: 6 Days
 Materials: Meranti timber formwork
 Equipment: Crane (1), handsaw, driller, dip-galvanised nails, double-headed nails, measuring
tape
 Skilled worker: Roofer (1), general worker (1), carpenter (1), crane operator (1), scaffolder (1)
 Technical information: Attach bearers to bearer block and wall scab, timber scaffolding.
Construction Activity 2: Roof
 Duration: 6 Days
 Materials: Meranti timber formwork
 Equipment: Crane (1), handsaw, driller, dip-galvanised nails, double-headed nails, measuring
tape
 Skilled worker: Roofer (1), general worker (1), carpenter (1), crane operator (1), scaffolder (1)
 Technical information: Progressively install temporary bracing as scaffolding is erected.
Week 35
Construction Activity 1: Roof
 Duration: 6 Days
 Materials: Metal trusses
 Equipment: Driller, screw driver, spiral screw, measuring tape
 Skilled worker: General worker (1), truss erector (1)
 Technical information: Fix truss.
Construction Activity 2: Roof
 Duration: 6 Days
 Materials: Meranti timber formwork
 Equipment: Crane (1), handsaw, driller, dip-galvanised nails, double-headed nails,
measuring tape
 Skilled worker: Roofer (1), general worker (1), carpenter (1), crane operator (1), scaffold
(1)
 Technical information: Progressively install temporary brace as scaffolding is erected.
Construction Activity 3: Roof
 Duration: 6 Days
 Materials: Metal trusses
 Equipment: Crane (1), Driller, screw driver, spiral screw, measuring tape
 Skilled worker: Roofer (1), general worker (1), truss erector (1), crane operator (1)
 Technical information: Install permanent lateral bracing to truss.
Week 36
Construction Activity 1: Roof
 Duration: 6 Days
 Materials: Metal trusses
 Equipment: Crane (1), Driller, screw driver, spiral screw, measuring tape
 Skilled worker: Roofer (1), general worker (1), truss erector (1), crane operator (1)
 Technical information: Install permanent lateral bracing to truss.
Construction Activity 2: Roof
 Duration: 6 Days
 Materials: Metal anchor sling, roof anchor bracket
 Equipment: Driller, screw driver, spiral screw, measuring tape, metal bender
 Skilled worker: Roofer (1), general worker (1), bar bender (1)
 Technical information: Install anchor slings.
Week 37
Construction Activity 1: Roof
 Duration: 3 Days
 Materials: Chicken netting
 Equipment: Measuring tape, metal bender, dip-galvanised nails, hammer, metal cutter
 Skilled worker: Roofer (1), general worker (1)
 Technical information: Install chicken netting.
Construction Activity 2: Roof
 Materials: Aluminium sheet
 Equipment: Measuring tape, metal bender, dip-galvanised nails, hammer, metal cutter
 Skilled worker: Roofer (1), general worker (1)
 Technical information: Install aluminium sheathing.
Week 38
Construction Activity 1: Roof
 Duration: 6 Days
 Materials: Metal batten strips (aluminium)
 Equipment: Measuring tape, metal bender, dip-galvanised nails, hammer, metal cutter
 Skilled worker: Roofer (1), general worker (1)
 Technical information: Install batten.
Week 39
Construction Activity 1: Roof
 Duration: 6 Days
 Materials: Cement tiles
 Equipment: Measuring tape, dip-galvanised nails, hammer
 Skilled worker: Roofer (1), general worker (1), roof tiler (1)
 Technical information: Place cement tiles and nail every third row
Week 40
Construction Activity 1: Roof
 Duration: 6 Days
 Materials: Ridge metal (aluminium), ridge bracket, ridge vent
 Equipment: Driller, screw driver, spiral screw, measuring tape, metal bender
 Skilled worker: Roofer (1), general worker (1), bar bender (1)
 Technical information: Install ridge block.
Construction Activity 2: Roof
 Duration: 6 Days
 Materials: Fascia board ribbon, fascia board bracket
 Equipment: Driller, screw driver, spiral screw, measuring tape, metal bender
 Skilled worker: Roofer (1), general worker (1), bar bender (1)
 Technical information: Install fascia board.
Week 41
Construction Activity 1: Wall Finishes – primer (Ground floor and First floors)
 Duration: 3 Days
 Materials: Primer
 Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking, Patching and Repair,
Caulks, Sealants and Caulking Tools
Skilled worker: Pointing, cleaning, and caulking workers and plasterer (1), painters (1)
 Technical information: Before applying primer, the wall need to be patched if there is any
holes or scuffs on the wall. A primer is a lighter coat of paint that absorbs colours well.
Construction Activity 2: Wall Finishes – 1st
layer painting (Ground floor and first floors)
 Duration: 3 Day
 Materials: paint
 Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking
Skilled worker: Painter (2)
 Technical information: Wall painting with colour chosen.
Week 42
Construction Activity 1: Installation of door (Ground floor)
 Duration: 3 days
 Materials: Required door, door lock, doorknob and screws
 Equipment: Screw driver, measuring tape
 Skilled worker: general worker (1), window and door installer (2)
 Technical information: Install required door types and measurement with door lock and
doorknob
Construction Activity 2: Wall Finishes – primer (Second floor)
 Duration: 3 Days
 Materials: Primer
 Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking, Patching and Repair,
Caulks, Sealants and Caulking Tools
Skilled worker: Pointing, cleaning, and caulking workers and plasterer (1), painters (1)
 Technical information: Before applying primer, the wall need to be patched if there is any
holes or scuffs on the wall. A primer is a lighter coat of paint that absorbs colours well.
Construction Activity 3: Wall Finishes – 1st
layer painting (Second floor)
 Duration: 3 Day
 Materials: paint
 Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking
Skilled worker: Painter (2)
 Technical information: Wall painting with colour chosen.
Week 43
Construction Activity 1: Installation of door (First and Second floors)
 Duration: 3 days
 Materials: Required door, door lock, doorknob and screws
 Equipment: Screw driver, measuring tape
 Skilled worker: general worker (1), window and door installer (2)
 Technical information: Install required door types and measurement with door lock and
doorknob
Construction Activity 2: Installation of door trim (All floors)
 Duration: 3 days
 Materials: nails, door trim panels
 Equipment: Finish hammer, hand plane, measuring tape, carpenter’s glue, sandpaper, jigsaw,
combination square, compass, pencil, utility knife, putty knife, miter saw, drill with bit
 Skilled worker: general worker (1), carpenter (2)
 Technical information: Mark the reveals, cut all miters, cut and test-fit side casings, make
adjustments, secure casing, and cross-nail miters.
Week 44
Construction Activity 1: Installation of windows (All floors)
 Duration: 3 days
 Materials: Required windows, backer rod, insulation, shims, roofing nails, screws, silicone
sealant, flashing, fastener, corner guard
 Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler,
measuring tape, stapler, and screwdriver
 Skilled worker: general worker (1), door and window installer (2)
 Technical information: Verify window opening, apply weather resistant barrier, create
flashing, prepare window for installation, set the unit and secure, apply flashing at jambs
and head, seal and insulate interior cavity, insert backer rod.
Week 45
Construction Activity 1: Installation of plumbing
 Duration: 4 days
 Materials: cast iron pipe, galvanized iron pipe, and galvanized steel pipe, vitrified clay pipe,
PVC pipe, copper tubing, fittings, hangers, insulating materials, oakum
 Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threaded, steel
pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter
 Skilled worker: Plumber (1), General worker (1)
 Technical information: The major categories of plumbing systems or subsystems are potable
cold and hot tap water supply, plumbing drainage venting, septic systems, rainwater, surface,
and subsurface water drainage, fuel gas piping.
Construction Activity 2: Installation of main electrical panel
 Duration: 1 day
 Materials: Sheet steel/cold role steel, breakers, plastic
 Equipment: Driller, locknut, screw
 Skilled worker: Electrical Contractor (1), Electrician (1)
 Technical information: The panel distributes the electricity to all the electrical circuits that
are installed in the house to protect the wiring from damage by “tripping” when an electrical
short or overcurrent occurs.
Week 46
Construction Activity 1: Installation of railings
 Duration: 3 days
 Materials: Ordered glass railing, stainless steel screws
 Equipment: level, scaffolding, measuring tape, sealant, gloves and screwdriver
 Skilled worker: general worker (1), railing installer (1)
 Technical information: Insert measured bottom rail and top plate and insert glass panel, fix
them with sealant or screws.
Week 47
Construction Activity 1: Installation of ceiling
 Duration: 3 days
 Materials: Steel brandering, insulation, jointing strip, drywall screw, plasterboards, Lafarge
access panel
 Equipment: ladder, gloves and screwdriver
 Skilled worker: ceiling installer (1), general worker (1)
 Technical information: Determine amount of steel brandering needed, planning the
direction of plasterboard, calculate number of plasterboard needed, install it on one by one.
Construction Activity 2: Installation of tiles
 Duration: 6 days
 Materials: Cement board, tiles, thinset mortar, grout
 Equipment: Floor cleaner, measuring tape, square, trowel, level and brush
 Skilled worker: Tiler (1), general worker (1)
 Technical information: Calculate surface area, decide types and size of tiles to use, apply
mortar, install tiles, grout the joints and clean.
Week 48
Construction Activity 2: Wall Finishes (Whole house 2nd
layer painting)
 Duration: 6 Days
 Materials: Selected paints
 Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking
Skilled worker: painters (2)
 Technical information: Wall painting with colour chosen.
Week 49
Construction Activity 1: Bathroom Equipment Installation
 Duration: 3 days
 Materials: Sockets, Heaters, Showers, Shower pumps, Water closet, Sink, PVC pipes
 Equipment: clamp tool, measuring tape, steel pipe wrench, flaring pliers, pipe vice, pipe
bending machine, pipe cutter
 Skilled worker: Plumber (1), General worker (1)
 Technical information: Materials are installed at first fix stage as they need to be fitted prior
to the commencement of tiling. This is essential to get professional watertight seals, as
water ingress resulting from doing things in the wrong order can cause massive problems
later on.
Construction Activity 2: Installation of receptacle
 Duration: 1 day
 Materials: Nickel/silver, beryllium copper, plastic
 Equipment: Screw, screwdriver
 Skilled worker: Electrician (2)
 Technical information: Electrician installs receptacles for outlets, lights and switches and
runs wires from the breaker panel to each receptacle. Wiring for telephones, TV cable and
network cable is included in this work.
Week 50
Construction Activity 1: Landscaping
 Duration: 4 days
 Materials: Grass, soil, stone, trees, plants
 Equipment: wheelbarrow, shovel, hoe, shears
 Skilled worker: General worker (1), landscape designer (1)
 Technical information: Design of landscaping make the whole house look more attractive
and lively. (Porches, sidewalks, decks, driveways, final grade and seed)
Week 51
Construction Activity 1: Final touch up
Duration: 2 days
 Technical information: punch out walk-thru list, trim and adjust doors, paint touch-up
Week 52
Construction Activity 1: Cleaning
Duration: 3 days
 Equipment: Cleaning tools
 Skilled worker: General worker (5)
 Technical information: Windows, floors final clean.

Weitere ähnliche Inhalte

Was ist angesagt?

Wblff (1)
Wblff (1)Wblff (1)
Wblff (1)ahmong4
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1KhangWei Chin
 
Construction of Brick Wall
Construction of Brick WallConstruction of Brick Wall
Construction of Brick WallI'mMiss Lily
 
Bq preamble
Bq preambleBq preamble
Bq preambleaizat76
 
Ct2 Precast concrete piles
Ct2 Precast concrete pilesCt2 Precast concrete piles
Ct2 Precast concrete pilesSze Ting Kuek
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & SequenceDavid H Moloney
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement worksMohd Nizam Mohd Zan
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQashleyyeap
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
Mooc smm substructure_2
Mooc smm substructure_2Mooc smm substructure_2
Mooc smm substructure_2Azizan Supardi
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017bee_by
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavationAl-Amin Ahmed Nabin
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculationZIyeeTan
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - BriefKai Yun Pang
 

Was ist angesagt? (20)

Wblff (1)
Wblff (1)Wblff (1)
Wblff (1)
 
Site visit report qs semester 1
Site visit report   qs semester 1Site visit report   qs semester 1
Site visit report qs semester 1
 
Construction of Brick Wall
Construction of Brick WallConstruction of Brick Wall
Construction of Brick Wall
 
Bq preamble
Bq preambleBq preamble
Bq preamble
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
Spun pile
Spun pileSpun pile
Spun pile
 
Ct2 Precast concrete piles
Ct2 Precast concrete pilesCt2 Precast concrete piles
Ct2 Precast concrete piles
 
ECA form
ECA formECA form
ECA form
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Method of Statement - Pavement works
Method of Statement - Pavement worksMethod of Statement - Pavement works
Method of Statement - Pavement works
 
Site visit report
Site visit reportSite visit report
Site visit report
 
Measurement II BQ
Measurement II BQMeasurement II BQ
Measurement II BQ
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
Mooc smm substructure_2
Mooc smm substructure_2Mooc smm substructure_2
Mooc smm substructure_2
 
Pile and pile driving equipments
Pile and pile driving equipmentsPile and pile driving equipments
Pile and pile driving equipments
 
Site visit report 2017
Site visit report 2017Site visit report 2017
Site visit report 2017
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
 
Estimating calculation
Estimating calculationEstimating calculation
Estimating calculation
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
Site Possession
Site PossessionSite Possession
Site Possession
 

Ähnlich wie Building Construction Project Process

Bcon final report
Bcon final reportBcon final report
Bcon final reportQing Cheng
 
Building Construction 1 - Final Project
Building Construction 1 - Final ProjectBuilding Construction 1 - Final Project
Building Construction 1 - Final ProjectEvelyn Paul
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1Jing Chuang
 
Building Construction Project 2 Report
Building Construction Project 2 ReportBuilding Construction Project 2 Report
Building Construction Project 2 ReportappleManiac
 
Construction maintenance
Construction maintenanceConstruction maintenance
Construction maintenanceDeepsonJohn1
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement reportKailyn Lee
 
Integrated site vite report
Integrated site vite reportIntegrated site vite report
Integrated site vite reportxennechau
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit ReportHasif Alias
 
Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...Akshaya Selvam
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1Zi Shan
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Make a Gantt Chart from the activities and tasks - Case Descriptio.pdf
Make a Gantt Chart  from the activities and tasks -    Case Descriptio.pdfMake a Gantt Chart  from the activities and tasks -    Case Descriptio.pdf
Make a Gantt Chart from the activities and tasks - Case Descriptio.pdfPierschdJohnstonb
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIPMkh Nantu
 
2016 DEID Madagascar Post Implementation Report
2016 DEID Madagascar Post Implementation Report2016 DEID Madagascar Post Implementation Report
2016 DEID Madagascar Post Implementation ReportDylan Kaiser
 

Ähnlich wie Building Construction Project Process (20)

Bcon final report
Bcon final reportBcon final report
Bcon final report
 
Building Construction 1 - Final Project
Building Construction 1 - Final ProjectBuilding Construction 1 - Final Project
Building Construction 1 - Final Project
 
MCB Final report
MCB Final reportMCB Final report
MCB Final report
 
M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1M1 CTec1 BMat Rep1
M1 CTec1 BMat Rep1
 
Building Construction Project 2 Report
Building Construction Project 2 ReportBuilding Construction Project 2 Report
Building Construction Project 2 Report
 
Construction maintenance
Construction maintenanceConstruction maintenance
Construction maintenance
 
Ct bm measurement report
Ct bm measurement reportCt bm measurement report
Ct bm measurement report
 
Integrated site vite report
Integrated site vite reportIntegrated site vite report
Integrated site vite report
 
BQS Site Visit Report
BQS Site Visit ReportBQS Site Visit Report
BQS Site Visit Report
 
Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...Environment friendly indian_building_material_technologies_for_cost_effective...
Environment friendly indian_building_material_technologies_for_cost_effective...
 
SITE REPORT
SITE REPORTSITE REPORT
SITE REPORT
 
Site Visit Report CT BM M1
Site Visit Report CT BM M1Site Visit Report CT BM M1
Site Visit Report CT BM M1
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Make a Gantt Chart from the activities and tasks - Case Descriptio.pdf
Make a Gantt Chart  from the activities and tasks -    Case Descriptio.pdfMake a Gantt Chart  from the activities and tasks -    Case Descriptio.pdf
Make a Gantt Chart from the activities and tasks - Case Descriptio.pdf
 
Construction basic SIP
Construction basic SIPConstruction basic SIP
Construction basic SIP
 
presentation
presentationpresentation
presentation
 
Site report 1
Site report 1Site report 1
Site report 1
 
2016 DEID Madagascar Post Implementation Report
2016 DEID Madagascar Post Implementation Report2016 DEID Madagascar Post Implementation Report
2016 DEID Madagascar Post Implementation Report
 
Major Project ppt
Major Project ppt Major Project ppt
Major Project ppt
 

Mehr von Ah Jun

B science 2 project 1
B science 2 project 1B science 2 project 1
B science 2 project 1Ah Jun
 
Theories project part 2: the image of the city
Theories project part 2: the image of the city Theories project part 2: the image of the city
Theories project part 2: the image of the city Ah Jun
 
Project 1 fettucine truss bridge
Project 1 fettucine truss bridgeProject 1 fettucine truss bridge
Project 1 fettucine truss bridgeAh Jun
 
Building structures Group
Building structures GroupBuilding structures Group
Building structures GroupAh Jun
 
Structure extension jun
Structure extension junStructure extension jun
Structure extension junAh Jun
 
Building Services Project 1 - Summit Mall
Building Services Project 1 - Summit MallBuilding Services Project 1 - Summit Mall
Building Services Project 1 - Summit MallAh Jun
 
Asian Architecture Research paper
Asian Architecture Research paperAsian Architecture Research paper
Asian Architecture Research paperAh Jun
 
Asian Architecture Presentation Slide
Asian Architecture Presentation Slide Asian Architecture Presentation Slide
Asian Architecture Presentation Slide Ah Jun
 
Asian Architecture Presentation Slide
Asian Architecture Presentation Slide Asian Architecture Presentation Slide
Asian Architecture Presentation Slide Ah Jun
 
Jun individual
Jun individualJun individual
Jun individualAh Jun
 
Proposal2 esd1 klang
Proposal2 esd1 klangProposal2 esd1 klang
Proposal2 esd1 klangAh Jun
 
Chin woo stadium
Chin woo stadiumChin woo stadium
Chin woo stadiumAh Jun
 
Edited essay
Edited essayEdited essay
Edited essayAh Jun
 
Yap zhi jun extra credit essay
Yap zhi jun extra credit essayYap zhi jun extra credit essay
Yap zhi jun extra credit essayAh Jun
 
Epc individual essay
Epc individual essayEpc individual essay
Epc individual essayAh Jun
 
Math presentation slides
Math presentation slidesMath presentation slides
Math presentation slidesAh Jun
 
Assignment 2 essay (movie)
Assignment 2 essay (movie)Assignment 2 essay (movie)
Assignment 2 essay (movie)Ah Jun
 
Mustard greens
Mustard greensMustard greens
Mustard greensAh Jun
 
English final assignment research report
English final assignment research reportEnglish final assignment research report
English final assignment research reportAh Jun
 
Eng research presentation slide
Eng research presentation slideEng research presentation slide
Eng research presentation slideAh Jun
 

Mehr von Ah Jun (20)

B science 2 project 1
B science 2 project 1B science 2 project 1
B science 2 project 1
 
Theories project part 2: the image of the city
Theories project part 2: the image of the city Theories project part 2: the image of the city
Theories project part 2: the image of the city
 
Project 1 fettucine truss bridge
Project 1 fettucine truss bridgeProject 1 fettucine truss bridge
Project 1 fettucine truss bridge
 
Building structures Group
Building structures GroupBuilding structures Group
Building structures Group
 
Structure extension jun
Structure extension junStructure extension jun
Structure extension jun
 
Building Services Project 1 - Summit Mall
Building Services Project 1 - Summit MallBuilding Services Project 1 - Summit Mall
Building Services Project 1 - Summit Mall
 
Asian Architecture Research paper
Asian Architecture Research paperAsian Architecture Research paper
Asian Architecture Research paper
 
Asian Architecture Presentation Slide
Asian Architecture Presentation Slide Asian Architecture Presentation Slide
Asian Architecture Presentation Slide
 
Asian Architecture Presentation Slide
Asian Architecture Presentation Slide Asian Architecture Presentation Slide
Asian Architecture Presentation Slide
 
Jun individual
Jun individualJun individual
Jun individual
 
Proposal2 esd1 klang
Proposal2 esd1 klangProposal2 esd1 klang
Proposal2 esd1 klang
 
Chin woo stadium
Chin woo stadiumChin woo stadium
Chin woo stadium
 
Edited essay
Edited essayEdited essay
Edited essay
 
Yap zhi jun extra credit essay
Yap zhi jun extra credit essayYap zhi jun extra credit essay
Yap zhi jun extra credit essay
 
Epc individual essay
Epc individual essayEpc individual essay
Epc individual essay
 
Math presentation slides
Math presentation slidesMath presentation slides
Math presentation slides
 
Assignment 2 essay (movie)
Assignment 2 essay (movie)Assignment 2 essay (movie)
Assignment 2 essay (movie)
 
Mustard greens
Mustard greensMustard greens
Mustard greens
 
English final assignment research report
English final assignment research reportEnglish final assignment research report
English final assignment research report
 
Eng research presentation slide
Eng research presentation slideEng research presentation slide
Eng research presentation slide
 

Kürzlich hochgeladen

RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...anilsa9823
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessAggregage
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Delhi Call girls
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth MarketingShawn Pang
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 

Kürzlich hochgeladen (20)

RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
Lucknow 💋 Escorts in Lucknow - 450+ Call Girl Cash Payment 8923113531 Neha Th...
 
Sales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for SuccessSales & Marketing Alignment: How to Synergize for Success
Sales & Marketing Alignment: How to Synergize for Success
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
Best VIP Call Girls Noida Sector 40 Call Me: 8448380779
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
Tech Startup Growth Hacking 101  - Basics on Growth MarketingTech Startup Growth Hacking 101  - Basics on Growth Marketing
Tech Startup Growth Hacking 101 - Basics on Growth Marketing
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 

Building Construction Project Process

  • 1. BUILDING CONSTRUCTION 1 (ARC 1523) DEGREE YEAR 1 SEM 2 (MAR 14) PROJECT 2: Construction Activities and Process YAP ZHI JUN 0310738
  • 2. Week 1 Construction Activity 1: Earthwork  Duration: 6 Days  Skilled worker: Land surveyor (1), land surveyor assistant (1), civil engineer (1), civil engineer assistant (1)  Technical information: Survey topography for measurement of earthwork quantities. Week 2 Construction Activity 1: Earthwork  Duration: 6 Days  Equipment: Backhoe (1), excavator (1), dumper (1)  Skilled worker: Backhoe operator (1), dumper operator (1), general worker (1)  Technical information: Site is cleared of trees, topsoil, shrubs and rubbish.
  • 3. Week 3 & 4 Construction Activity 1: Earthwork  Duration: 12 Days  Equipment: Portable penetrometer (1)  Skilled worker: Geotechnical engineer (1), geotechnical engineer assistant (1), civil engineer (1), civil engineer assistant (1)  Technical information: Mackintosh Probe (MP) test carried out for testing soft soils and determining suitable materials.
  • 4. Week 5 Construction Activity 1: Earthwork  Duration: 6 Days  Equipment: Vibrating plate compactor (1), backhoe (1), excavator (1), paver (1), dumper (1)  Skilled worker: Backhoe operator (1), excavator operator (1), paver (1), dumper operator (1), general worker (1), grader (1), rollers (1)  Technical information: Site is excavated to required lengths, depths, breadths, inclinations and curvatures Week 6 Construction Activity 1: Earthwork  Duration: 6 Days  Materials: Timber formwork, gravel  Equipment: Table saw (2), shovel (2), long tape measurer, steel tape, strong threads, wire nails, theodolite, wooden pegs, drill hammer  Skilled worker: Carpenter (2), general worker (1)  Technical information: Filling materials to lines, levels and grades required to complete permanent construction.
  • 5. Week 7 Construction activity 1: Transporting piles  Duration: 2 days  Materials: piles  Equipment: Lorry (2), Crane (1)  Skilled worker: Lorry driver (4), Crane Operator (1)  Technical information: Transporting piles from factory, lift the piles by using crane from lorry after reaching the site. Week 8 Construction activity 1: Pile driving process  Duration: 12 days  Materials: piles, pile cushion, bituminous paint  Equipment: Hydraulic drop hammer (1)  Skilled worker: contractor (1), Hydraulic drop hammer operator (1), General worker (3)  Technical information: Mobilize the hydraulic drop hammer to the intended pile position after marking penetration of the piles, set out the position of drop hammer above the pile point, pile driving, weld the joints between the piles, and apply bituminous paint around the joints of welded piles to prevent rusting.
  • 6. Week 9 Construction activity 1: Cut off process  Duration: 3 days  Equipment: Multipurpose excavator (1), Pneumatic hammer (1), Oxy-cutter (1)  Skilled worker: Excavator operator (1), General worker (2)  Technical information: Excavate 1m to 1.5m depth by using multipurpose excavator, cut the piles to make sure all are in the same height using Pneumatic hammer, the reinforcement in the pile is cut by oxy-cutter. Week 10 Construction activity 1: Set up formwork for pile cap  Duration: 5 days  Material: Plywood, nails, reinforcement  Equipment: hammer, measuring tape, drill, handsaw  Skilled worker: general worker (3)  Technical information: Set up formwork for pile cap, insert reinforcement for pile cap, and set up the reinforcement for column stump before pouring the concrete.
  • 7. Week 11 Construction activity 1: Pour concrete into the formwork  Duration: 2 days  Material: Concrete  Equipment: Concrete mixer truck, Skip, Concrete vibrator  Skilled worker: Concrete mixer truck operator (1), general worker (3)  Technical information: Pour the concrete into the formwork through skip from concrete mixer truck, vibrate and mix the concrete evenly using concrete vibrator to increase its strength by preventing air pockets. Construction activity 2: Pile cap harden process  Duration: 7 days  Technical information: Let the concrete pile cap harden for 7 days to wait it mature and sufficient strength, open formwork after completed.
  • 8. Week 12 Construction activity 1: Set up formwork for column stump  Duration: 2 days  Material: Plywood, nails  Equipment: hammer, measuring tape, drill, handsaw  Skilled worker: General worker (2)  Technical information: Set up formwork for column stump before pouring the concrete. Construction activity 2: Underground services  Duration: 6 days  Material: Metal conduit, steel/ aluminium tubing or PVC tubing, hexagonal plumbing fitting, plumbing sealant  Equipment: Plow chute, winch  Skilled worker: Electrician (1), general worker (2), plumber (1)  Technical information: Bury cable preinstalled in cable-in-conduit (CIC) and main plumbing pipes at excavated level.
  • 9. Week 13 Construction activity 1: Pour concrete into the formwork Duration: 2 days  Material: Concrete  Equipment: Concrete mixer truck, Skip, Concrete vibrator  Skilled worker:  Technical information: Pour the concrete into the formwork through skip from concrete mixer truck, vibrate the concrete to increase its strength. Construction activity 2: Column stump harden process  Duration: 7 days  Technical information: Let the concrete column stump harden for 7 days to wait it mature and sufficient strength, open formwork after completed
  • 10. Week 14 Construction activity 1: Back filling the pile foundation  Duration: 1 day  Material: soil  Equipment: Multipurpose excavator (1)  Skilled worker: Multipurpose excavator Operator  Technical information: After the harden process, fill up the excavated part around the foundation to move on to the next process.
  • 11. Week 15 Construction Activity 1: Construction of ground beam (Ground floor)  Duration: 6 Days  Materials: Concrete Grade 30, reinforcement, timber formwork  Equipment: Concrete vibrator (1), bar bending machine (1), table saw, machine mix concrete (1)  Skilled worker: Carpenter (2), bar bender (1), general worker (1)  Technical information: Determine material, marking form panels, erecting the formwork, provision a camber, brace the wood with stringer and support by struts and cleat, slump test, and pour cement concrete.
  • 12. Week 16 Construction Activity 1: Slab (Ground floor)  Duration: 6 Days  Materials: Plywood formwork, reinforced steel, service pipes, concrete Grade 20  Equipment: Dip-galvanised nails, hammer, measuring tape, table saw, mixer truck, concrete vibrator, tipper, wheelbarrow.  Skilled worker: General worker (2), carpenter (1), bar bender (2)  Technical information: build formwork with plywood, fix reinforced steel, construction slab formwork, slump test and pour concrete.  Thickness range of plywood: 7mm - 32mm
  • 13. Week 17 Construction Activity 1: Construction of columns (Ground floor)  Duration: 6 Days  Materials: Concrete Grade 30, reinforcement, timber formwork  Equipment: Concrete vibrator (1), bar bending machine (1), table saw  Skilled worker: Carpenter (2), bar bender (1), general worker (1)  Technical information: Place reinforcement bar and secured to the column formwork and the floor, slump test and poured concrete.
  • 14. Week 18 Construction Activity 1: Construction of beam (First floor) Duration: 6 Days  Materials: Concrete Grade 30, reinforcement, timber formwork  Equipment: Concrete vibrator (1), bar bending machine (1), table saw, machine mix concrete (1)  Skilled worker: Carpenter (2), bar bender (1), general worker (1)  Technical information: Determine material, marking form panels, erecting the formwork, provision a camber, brace the wood with stringer and support by struts and cleat, slump test, and pour cement concrete.
  • 15. Week 19 Construction Activity 1: Construction of slab (First Floor)  Duration: 6 Days  Materials: Plywood formwork, reinforced steel, service pipes, concrete Grade 20  Equipment: Dip-galvanised nails, hammer, measuring tape, table saw, mixer truck, concrete vibrator, tipper, wheelbarrow.  Skilled worker: General worker (2), carpenter (1), bar bender (2)  Technical information: build formwork with plywood, fix reinforced steel, construction slab formwork, slump test and pour concrete.  Thickness range of plywood: 7mm - 32mm
  • 16. Week 20 Construction Activity 1: Staircase (Ground floor)  Duration: 3 Days  Materials: Ply Woods, Timber Battens  Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw  Skilled worker: Carpenter (1), Joinery (1)  Technical information: Make a pitch board with the angle of 30°. Hold pitch board on the side to represent the top of the stair slab and mark the riser and tread Construction Activity 2: Staircase (Ground floor)  Duration: 3 Days  Materials: Timber, Metal or Prefabricated Formwork  Equipment: Drill, Hammer, Hand Saw  Skilled worker: Bar Benders (1), Formwork Carpenters (1)  Technical information: Construct formwork by laying out riser heights and tread widths followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Cut and nailed cleats to plank, nail riser form boards to the ends of cleats.
  • 17. Week 21 Construction Activity 1: Staircase (Ground floor)  Duration: 2 Days  Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place sleeve  Equipment: Measuring Tape, chalk line, drill, hammer, hand saw  Skilled worker: Bar Benders (1), Formwork Carpenters (1)  Technical information: Create strong grid of rebar, two or more pieces of rebar cross are joined together. Secure riser form board with cleats attached about an inch above the stairs layout to the slide form. Construction Activity 2: Staircase (Ground floor)  Duration: 4 Days  Materials: Concrete, Long screws, Nails  Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board  Skilled worker: Carpenters (2)  Technical information: Concrete ceiling and stairs pour. Keep the concrete wet or damp to prevent cracks for up to one week while it cures.
  • 18. Week 22 Construction Activity 1: Construction of columns (First floor)  Duration: 6 Days  Materials: Concrete Grade 30, reinforcement, timber formwork  Equipment: Concrete vibrator (1), bar bending machine (1), table saw  Skilled worker: Carpenter (2), bar bender (1), general worker (1)  Technical information: Place reinforcement bar and secured to the column formwork and the floor, slump test and poured concrete.
  • 19. Week 23 Construction Activity 1: Construction of beam (Second floor)  Duration: 6 Days  Materials: Concrete Grade 30, reinforcement, timber formwork  Equipment: Concrete vibrator (1), bar bending machine (1), table saw, machine mix concrete (1)  Skilled worker: Carpenter (2), bar bender (1), general worker (1)  Technical information: Determine material, marking form panels, erecting the formwork, provision a camber, brace the wood with stringer and support by struts and cleat, slump test, and pour cement concrete.
  • 20. Week 24 Construction Activity 1: Slab (Second Floor)  Duration: 6 Days  Materials: Plywood formwork, reinforced steel, service pipes, concrete Grade 20  Equipment: Dip-galvanised nails, hammer, measuring tape, table saw, mixer truck, concrete vibrator, tipper, wheelbarrow.  Skilled worker: General worker (2), carpenter (1), bar bender (2)  Technical information: build formwork with plywood, fix reinforced steel, construction slab formwork, slump test and pour concrete.  Thickness range of plywood: 7mm - 32mm
  • 21. Week 25 Construction Activity 1: Staircase (First floor)  Duration: 3 Days  Materials: Ply Woods, Timber Battens  Equipment: Measuring Tape, Chalk Line, Drill, Hammer, Hand Saw  Skilled worker: Carpenter (1), Joinery (1)  Technical information: Make a pitch board with the angle of 30°. Hold pitch board on the side to represent the top of the stair slab and mark the riser and tread Construction Activity 2: Staircase (First floor)  Duration: 3 Days  Materials: Timber, Metal or Prefabricated Formwork  Equipment: Drill, Hammer, Hand Saw  Skilled worker: Bar Benders (1), Formwork Carpenters (1)  Technical information: Construct formwork by laying out riser heights and tread widths followed by soffit, joist and stringer lines. Then lay out thickness of risers from boards. Cut and nailed cleats to plank, nail riser form boards to the ends of cleats.
  • 22. Week 26 Construction Activity 1: Staircase (First floor)  Duration: 2 Days  Materials: Hook, NLT 25’, VERT RR pins, rebar wire, cast aluminium, Cast in place sleeve  Equipment: Measuring Tape, chalk line, drill, hammer, hand saw  Skilled worker: Bar Benders (1), Formwork Carpenters (1)  Technical information: Create strong grid of rebar, two or more pieces of rebar cross are joined together. Secure riser form board with cleats attached about an inch above the stairs layout to the slide form. Construction Activity 2: Staircase (First floor)  Duration: 4 Days  Materials: Concrete, Long screws, Nails  Equipment: Portable Cement Mixer, Concrete Vibrator, Spade, Screed Board  Skilled worker: Carpenters (2)  Technical information: Concrete ceiling and stairs pour. Keep the concrete wet or damp to prevent cracks for up to one week while it cures.
  • 23. Week 27 Construction Activity 1: Construction of columns (Second floor)  Duration: 6 Days  Materials: Concrete Grade 30, reinforcement, timber formwork  Equipment: Concrete vibrator (1), bar bending machine (1), table saw  Skilled worker: Carpenter (2), bar bender (1), general worker (1)  Technical information: Place reinforcement bar and secured to the column formwork and the floor, slump test and poured concrete.
  • 24. Week 28 Construction Activity 1: Construction of beam (Third floor)  Duration: 6 Days  Materials: Concrete Grade 30, reinforcement, timber formwork  Equipment: Concrete vibrator (1) , bar bending machine (1), table saw, machine mix concrete (1)  Skilled worker: Carpenter (2) , bar bender (1), general worker (1)  Technical information: Determine material, marking form panels, erecting the formwork, provision a camber, brace the wood with stringer and support by struts and cleat, slump test, and pour cement concrete.
  • 25. Week 29 Construction Activity 1: Brickwork (Ground floor)  Duration: 5 days  Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh  Equipment: Rose Brick Trowels, carpenter level, brick jointer  Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1).  Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled with mortar. Construction Activity 2: Installation of door frame (Ground floor)  Duration: 2 days  Materials: Screws, ‘L’ bracket, jambs, striker plate, PVC stopper, head, adaptor bar, brick ties, hinges, spreader bars.  Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler, measuring tape, stapler, and screwdriver  Skilled worker: general worker (1), door and window installer (1)  Technical information: Mark door and bricks area, use timber to prop up door to standing position, use spirit to plumb the frame, secure timber stays with bricks, lay the bricks, place mortar into gap of the brick and frame, insert wire brick ties.
  • 26. Week 30 Construction Activity 1: Brickwork (First floor)  Duration: 5 days  Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh  Equipment: Rose Brick Trowels, carpenter level, brick jointer  Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1).  Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled with mortar. Construction Activity 2: Brickwork – Rendering (Ground floor)  Duration: 3 Days  Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White Cement Equipment: Masonry Brushes, Sled Runners,  Skilled worker: Pointing, cleaning, and caulking workers (1) and plasterer (1).  Technical information:  Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch first coat of render before it set to provide key for second layer. Skim coat mixed blended white cement on it.
  • 27. Week 31 Construction Activity 1: Brickwork (Second floor)  Duration: 5 days  Materials: Red Burnt Clay Bricks, Cement mixer, reinforce mesh  Equipment: Rose Brick Trowels, carpenter level, brick jointer  Skilled worker: Brick Layers (3), Pointing, cleaning, and caulking workers (1).  Technical information: Brickwork process including bricks, beds and perpends. The bed is made up with mortar with brick is laid. Perpends is a vertical joint between two bricks filled with mortar. Construction Activity 2: Brickwork – Rendering (First floor)  Duration: 3 Days  Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White Cement Equipment: Masonry Brushes, Sled Runners,  Skilled worker: Pointing, cleaning, and caulking workers (1) and plasterer (1).  Technical information:  Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch first coat of render before it set to provide key for second layer. Skim coat mixed blended white cement on it.
  • 28. Week 32 Construction Activity 2: Brickwork – Rendering (Second floor)  Duration: 3 Days  Materials: Red Burnt Clay Bricks, Mixed Portland Composite Cement, Mixed Blended White Cement Equipment: Masonry Brushes, Sled Runners,  Skilled worker: Pointing, cleaning, and caulking workers (1) and plasterer (1).  Technical information:  Cement render on the surface of brick wall after cleaning with masonry brush. Then, scratch first coat of render before it set to provide key for second layer. Skim coat mixed blended white cement on it. Construction Activity 2: Installation of door frame (First and Second floors)  Duration: 2 days  Materials: Screws, ‘L’ bracket, jambs, striker plate, PVC stopper, head, adaptor bar, brick ties, hinges, spreader bars.  Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler, measuring tape, stapler, and screwdriver  Skilled worker: general worker (1), door and window installer (1)  Technical information: Mark door and bricks area, use timber to prop up door to standing position, use spirit to plumb the frame, secure timber stays with bricks, lay the bricks, place mortar into gap of the brick and frame, insert wire brick ties.
  • 29. Week 33 Construction Activity 1: Roof  Duration: 6 Days  Materials: Meranti timber formwork, metal trusses  Equipment: Crane (1), lorry (1), handsaw, driller, dip-galvanised nails, hammer, measuring tape  Skilled worker: Roofer (1), general worker (1), crane operator (1), lorry driver (1)  Technical information: Check trusses, interior/exterior alignment, prepare clear access to worksite, prepare storage for trusses. Week 34 Construction Activity 1: Roof  Duration: 6 Days  Materials: Meranti timber formwork  Equipment: Crane (1), handsaw, driller, dip-galvanised nails, double-headed nails, measuring tape  Skilled worker: Roofer (1), general worker (1), carpenter (1), crane operator (1), scaffolder (1)  Technical information: Attach bearers to bearer block and wall scab, timber scaffolding. Construction Activity 2: Roof  Duration: 6 Days  Materials: Meranti timber formwork  Equipment: Crane (1), handsaw, driller, dip-galvanised nails, double-headed nails, measuring tape  Skilled worker: Roofer (1), general worker (1), carpenter (1), crane operator (1), scaffolder (1)  Technical information: Progressively install temporary bracing as scaffolding is erected.
  • 30. Week 35 Construction Activity 1: Roof  Duration: 6 Days  Materials: Metal trusses  Equipment: Driller, screw driver, spiral screw, measuring tape  Skilled worker: General worker (1), truss erector (1)  Technical information: Fix truss. Construction Activity 2: Roof  Duration: 6 Days  Materials: Meranti timber formwork  Equipment: Crane (1), handsaw, driller, dip-galvanised nails, double-headed nails, measuring tape  Skilled worker: Roofer (1), general worker (1), carpenter (1), crane operator (1), scaffold (1)  Technical information: Progressively install temporary brace as scaffolding is erected. Construction Activity 3: Roof  Duration: 6 Days  Materials: Metal trusses  Equipment: Crane (1), Driller, screw driver, spiral screw, measuring tape  Skilled worker: Roofer (1), general worker (1), truss erector (1), crane operator (1)  Technical information: Install permanent lateral bracing to truss.
  • 31. Week 36 Construction Activity 1: Roof  Duration: 6 Days  Materials: Metal trusses  Equipment: Crane (1), Driller, screw driver, spiral screw, measuring tape  Skilled worker: Roofer (1), general worker (1), truss erector (1), crane operator (1)  Technical information: Install permanent lateral bracing to truss. Construction Activity 2: Roof  Duration: 6 Days  Materials: Metal anchor sling, roof anchor bracket  Equipment: Driller, screw driver, spiral screw, measuring tape, metal bender  Skilled worker: Roofer (1), general worker (1), bar bender (1)  Technical information: Install anchor slings. Week 37 Construction Activity 1: Roof  Duration: 3 Days  Materials: Chicken netting  Equipment: Measuring tape, metal bender, dip-galvanised nails, hammer, metal cutter  Skilled worker: Roofer (1), general worker (1)  Technical information: Install chicken netting. Construction Activity 2: Roof  Materials: Aluminium sheet  Equipment: Measuring tape, metal bender, dip-galvanised nails, hammer, metal cutter  Skilled worker: Roofer (1), general worker (1)  Technical information: Install aluminium sheathing.
  • 32. Week 38 Construction Activity 1: Roof  Duration: 6 Days  Materials: Metal batten strips (aluminium)  Equipment: Measuring tape, metal bender, dip-galvanised nails, hammer, metal cutter  Skilled worker: Roofer (1), general worker (1)  Technical information: Install batten. Week 39 Construction Activity 1: Roof  Duration: 6 Days  Materials: Cement tiles  Equipment: Measuring tape, dip-galvanised nails, hammer  Skilled worker: Roofer (1), general worker (1), roof tiler (1)  Technical information: Place cement tiles and nail every third row
  • 33. Week 40 Construction Activity 1: Roof  Duration: 6 Days  Materials: Ridge metal (aluminium), ridge bracket, ridge vent  Equipment: Driller, screw driver, spiral screw, measuring tape, metal bender  Skilled worker: Roofer (1), general worker (1), bar bender (1)  Technical information: Install ridge block. Construction Activity 2: Roof  Duration: 6 Days  Materials: Fascia board ribbon, fascia board bracket  Equipment: Driller, screw driver, spiral screw, measuring tape, metal bender  Skilled worker: Roofer (1), general worker (1), bar bender (1)  Technical information: Install fascia board.
  • 34. Week 41 Construction Activity 1: Wall Finishes – primer (Ground floor and First floors)  Duration: 3 Days  Materials: Primer  Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking, Patching and Repair, Caulks, Sealants and Caulking Tools Skilled worker: Pointing, cleaning, and caulking workers and plasterer (1), painters (1)  Technical information: Before applying primer, the wall need to be patched if there is any holes or scuffs on the wall. A primer is a lighter coat of paint that absorbs colours well. Construction Activity 2: Wall Finishes – 1st layer painting (Ground floor and first floors)  Duration: 3 Day  Materials: paint  Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking Skilled worker: Painter (2)  Technical information: Wall painting with colour chosen.
  • 35. Week 42 Construction Activity 1: Installation of door (Ground floor)  Duration: 3 days  Materials: Required door, door lock, doorknob and screws  Equipment: Screw driver, measuring tape  Skilled worker: general worker (1), window and door installer (2)  Technical information: Install required door types and measurement with door lock and doorknob Construction Activity 2: Wall Finishes – primer (Second floor)  Duration: 3 Days  Materials: Primer  Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking, Patching and Repair, Caulks, Sealants and Caulking Tools Skilled worker: Pointing, cleaning, and caulking workers and plasterer (1), painters (1)  Technical information: Before applying primer, the wall need to be patched if there is any holes or scuffs on the wall. A primer is a lighter coat of paint that absorbs colours well. Construction Activity 3: Wall Finishes – 1st layer painting (Second floor)  Duration: 3 Day  Materials: paint  Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking Skilled worker: Painter (2)  Technical information: Wall painting with colour chosen.
  • 36. Week 43 Construction Activity 1: Installation of door (First and Second floors)  Duration: 3 days  Materials: Required door, door lock, doorknob and screws  Equipment: Screw driver, measuring tape  Skilled worker: general worker (1), window and door installer (2)  Technical information: Install required door types and measurement with door lock and doorknob Construction Activity 2: Installation of door trim (All floors)  Duration: 3 days  Materials: nails, door trim panels  Equipment: Finish hammer, hand plane, measuring tape, carpenter’s glue, sandpaper, jigsaw, combination square, compass, pencil, utility knife, putty knife, miter saw, drill with bit  Skilled worker: general worker (1), carpenter (2)  Technical information: Mark the reveals, cut all miters, cut and test-fit side casings, make adjustments, secure casing, and cross-nail miters.
  • 37. Week 44 Construction Activity 1: Installation of windows (All floors)  Duration: 3 days  Materials: Required windows, backer rod, insulation, shims, roofing nails, screws, silicone sealant, flashing, fastener, corner guard  Equipment: Safety glasses, utility knife, hammer, caulk gun, level, scaffolding, square ruler, measuring tape, stapler, and screwdriver  Skilled worker: general worker (1), door and window installer (2)  Technical information: Verify window opening, apply weather resistant barrier, create flashing, prepare window for installation, set the unit and secure, apply flashing at jambs and head, seal and insulate interior cavity, insert backer rod.
  • 38. Week 45 Construction Activity 1: Installation of plumbing  Duration: 4 days  Materials: cast iron pipe, galvanized iron pipe, and galvanized steel pipe, vitrified clay pipe, PVC pipe, copper tubing, fittings, hangers, insulating materials, oakum  Equipment: pressure test pump, clamp tool, measuring tape, electric pipe threaded, steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter  Skilled worker: Plumber (1), General worker (1)  Technical information: The major categories of plumbing systems or subsystems are potable cold and hot tap water supply, plumbing drainage venting, septic systems, rainwater, surface, and subsurface water drainage, fuel gas piping. Construction Activity 2: Installation of main electrical panel  Duration: 1 day  Materials: Sheet steel/cold role steel, breakers, plastic  Equipment: Driller, locknut, screw  Skilled worker: Electrical Contractor (1), Electrician (1)  Technical information: The panel distributes the electricity to all the electrical circuits that are installed in the house to protect the wiring from damage by “tripping” when an electrical short or overcurrent occurs.
  • 39. Week 46 Construction Activity 1: Installation of railings  Duration: 3 days  Materials: Ordered glass railing, stainless steel screws  Equipment: level, scaffolding, measuring tape, sealant, gloves and screwdriver  Skilled worker: general worker (1), railing installer (1)  Technical information: Insert measured bottom rail and top plate and insert glass panel, fix them with sealant or screws.
  • 40. Week 47 Construction Activity 1: Installation of ceiling  Duration: 3 days  Materials: Steel brandering, insulation, jointing strip, drywall screw, plasterboards, Lafarge access panel  Equipment: ladder, gloves and screwdriver  Skilled worker: ceiling installer (1), general worker (1)  Technical information: Determine amount of steel brandering needed, planning the direction of plasterboard, calculate number of plasterboard needed, install it on one by one. Construction Activity 2: Installation of tiles  Duration: 6 days  Materials: Cement board, tiles, thinset mortar, grout  Equipment: Floor cleaner, measuring tape, square, trowel, level and brush  Skilled worker: Tiler (1), general worker (1)  Technical information: Calculate surface area, decide types and size of tiles to use, apply mortar, install tiles, grout the joints and clean.
  • 41. Week 48 Construction Activity 2: Wall Finishes (Whole house 2nd layer painting)  Duration: 6 Days  Materials: Selected paints  Equipment: Paint Brushes, Ladders, Scaffolds, Tape and Masking Skilled worker: painters (2)  Technical information: Wall painting with colour chosen. Week 49 Construction Activity 1: Bathroom Equipment Installation  Duration: 3 days  Materials: Sockets, Heaters, Showers, Shower pumps, Water closet, Sink, PVC pipes  Equipment: clamp tool, measuring tape, steel pipe wrench, flaring pliers, pipe vice, pipe bending machine, pipe cutter  Skilled worker: Plumber (1), General worker (1)  Technical information: Materials are installed at first fix stage as they need to be fitted prior to the commencement of tiling. This is essential to get professional watertight seals, as water ingress resulting from doing things in the wrong order can cause massive problems later on. Construction Activity 2: Installation of receptacle  Duration: 1 day  Materials: Nickel/silver, beryllium copper, plastic  Equipment: Screw, screwdriver  Skilled worker: Electrician (2)  Technical information: Electrician installs receptacles for outlets, lights and switches and runs wires from the breaker panel to each receptacle. Wiring for telephones, TV cable and network cable is included in this work. Week 50 Construction Activity 1: Landscaping  Duration: 4 days  Materials: Grass, soil, stone, trees, plants  Equipment: wheelbarrow, shovel, hoe, shears  Skilled worker: General worker (1), landscape designer (1)  Technical information: Design of landscaping make the whole house look more attractive and lively. (Porches, sidewalks, decks, driveways, final grade and seed)
  • 42. Week 51 Construction Activity 1: Final touch up Duration: 2 days  Technical information: punch out walk-thru list, trim and adjust doors, paint touch-up Week 52 Construction Activity 1: Cleaning Duration: 3 days  Equipment: Cleaning tools  Skilled worker: General worker (5)  Technical information: Windows, floors final clean.