QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE


for


VILLA RICHARDSON


CORSICA




21 March 2011
Version 1




STOCKDALE
58 Streatham High Road
London
SW16 1DA
Tel: 020 8664 6373
VILLA RICHARDSON

                  QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE

                                           INTRODUCTION



NOTES FOR THE CONTRACTOR:

This quantified framework has been produced as an aid to contractors in the production of
order of cost/budget estimates.

When completed by the contractor the document will assist in the setting of a
realistic budget or cost limit and as a platform for further negotiation.

This document is not a Bill of Quantities; the quantities have not been measured in
accordance with the Standard Method of Measurement or the New Rules of
Measurement. The quantities are approximate.

We have assumed that the existing roof will be retained and modified in places
rather than be completely or partially removed to facilitate the works.
The structural engineer and contractor must determine whether which approach is most
practical and cost effective.

This document is available as an XL file. The file is not locked or security restricted.
We recommend that the Contractor checks all formulae within the XL file before submitting a
budget as editting the document may affect the original formulae.
This document has been prepared with reference to the following Michaelis Boyd drawings:

10080-100   Existing site plan              22.11.10
10080-101   existing basement plan          22.11.10
10080-102   existing ground floor plan      22.11.10
10080-103   existing first floor plan        -
10080-104   existing roof plan               -
10080-120   existing north elevation        22.11.10
10080-121   existing south elevation        22.11.10
10080-122   existing east elevation         22.11.10
10080-123   existing west elevation         22.11.10
10080-130   existing section AA             22.11.10
10080-131   existing section BB             22.11.10
10080-140   demolition basement             15.12.10
10080-141   demolition ground floor         15.12.10
10080-142   demolition first floor          15.12.10
10080-200   proposed site plan              15.12.10
10080-201   proposed basement plan          15.12.10
10080-202   proposed ground floor plan      15.12.10
10080-203   proposed first floor plan       15.12.10
10080-204   proposed roof plan              15.12.10
10080-220   existing north elevation        15.12.10   A
10080-221   existing south elevation        15.12.10   A
10080-222   existing east elevation         15.12.10   A
10080-223   existing west elevation         15.12.10   A
10080-230   proposed section AA             15.12.10   A
10080-231   proposed section BB             15.12.10
10080-232   Proposed section CC             15.12.10
10080-240   Proposed garage plan            15.12.10

Existing site photographs dated 24.11.10
VILLA RICHARDSON
                      QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                                 SUMMARY


Costs from attached sheets: -                              Cost/m² of       Total Cost of
                                                             GIFA             Element
                                                               £                  £
        Building Works Estimate: -
        Facilitating works                                     0                        0
        Works to existing buildings                            0                        0
        Substructures                                          0                        0
        Superstructures
          Frame                                                0                        0
          Upper floors                                         0                        0
          Roof                                                 0                        0
          Stairs and ramps                                     0                        0
          External walls                                       0                        0
          Windows and external doors                           0                        0
          Internal walls and partitions                        0                        0
          Internal doors                                       0                        0
        Internal finishes
          Wall finishes                                        0                        0
          Floor finishes                                       0                        0
          Ceiling finishes                                     0                        0
          Decorations                                          0                        0
        Fittings, furnishings and equipment                    0                        0
        Services
          Sanitary appliances                                 70                  35,600
          Mechanical installations                            0                        0
          Electrical installations                             0                       0
          Lift and conveyor installations                      0                       0
          Special installations                                0                       0
        Complete buildings and building units                 0                        0
        External works
          Generally                                            0                        0
          Garage                                               0                        0
        Below ground drainage                                  0                        0
        Main Contractor's preliminaries                        0                        0
        Main Contractor's overheads and profit                 0                        0
        Risk Allowance Estimate                                0                        0

        Total: Building Works Estimate                        70                  35,600

        Tender Inflation                                                                0

        Cost Estimate (excluding fees)                                            35,600

        Project/Design Team Fees and Other                                              0

        Cost Estimate (excluding VAT)                                             35,600

        VAT/TVA assessment                                                              0

        Total of Order of Cost                                          £         35,600




                                                  Page 1
VILLA RICHARDSON

                               QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                        ALL QUANTITIES ARE APPROXIMATE

                                                                                                       Total Cost of
                                  Group Element/Element                     Qty   Unit   Rate   Cost     Element
                                                                                                 £          £
BUILDING WORKS

 Facilitating works -

    Loose furniture and equipment including artwork to be removed
    by Employer

    Items of demolition and alteration are to be carried out carefully to
    afford the minimal damage to work to be retained. Any such damage
    shall be made good at the Contractor's own expense.

    Items of demolition and alteration are to include for all necessary
    making good to floors, walls, ceilings and roofs etc.

    Items of demolition and alteration are to include for removing
    from site all rubbish, debris, etc.

    Cutting, forming, enlarging or adapting openings through existing
    work is to include for quoining jambs, making good existing plaster
    up to and/or extending through same opening, extending any
    necessary floor finish through opening

    Demolishing or removing structures or part of structures, cutting,
    forming or enlarging openings are to include for all necessary
    temporary support whether or not expressly noted and for wedging
    and pinning or packing up to existing structure after inserting
    permanent support work. Temporary supports include maintaining,
    adapting and clearing away on completion.

    Filling openings in existing work is to include for all necessary
    extending of finishes, skirtings and junctions with existing.




                                                                Page 2
VILLA RICHARDSON

                         QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                  ALL QUANTITIES ARE APPROXIMATE

                                                                                                           Total Cost of
                          Group Element/Element                            Qty   Unit    Rate   Cost         Element
                                                                                                 £              £

Isolate/make safe the following services in preparation for
demolition work:
  Electrical services                                                      1     item                  0


 Gas/oil services                                                          1     item                  0


 Water services                                                            1     item                  0


 Telecoms                                                                  1     item                  0


 Drainage                                                                  1     item                  0


Strip out and remove from site the following:
 Electrical services complete                                              1     item                  0


 Plumbing, heating, ventilation gas, oil services complete                 1     item                  0


 Cooling systems                                                           1     item                  0


 Above ground drainage system                                              1     item                  0


 Pool plant and pool pipework and cabling                                  1     item                  0


 Gas/oil storage tanks                                                     1     item                  0

                                                                                     2
 Floor coverings                                                           385   m                     0

                                                                                     2
 Floor screeds and timber floor boards                                     385   m                     0


 Provisional Sum for removing existing ground and basement floor           303   PS                    0
 slabs to allow for increased floor build up to suit underfloor heating,
 reduce levels by say 100mm and relay slab at new level
 NB existing floors may be timber in part or whole in which case
 this item should be amended and priced accordingly

 Internal door sets                                                        20     nr                   0


 Skirtings                                                                 390    m                    0




                                                     Page 3
VILLA RICHARDSON

                        QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                 ALL QUANTITIES ARE APPROXIMATE

                                                                                                             Total Cost of
                           Group Element/Element                             Qty   Unit    Rate   Cost         Element
                                                                                                   £              £

 Bathrooms:
  Basement bathroom and WCs complete                                         1     item                  0


   Ground floor bathrooms and WCs complete                                   1     item                  0


   First floor bathrooms and WCs complete                                    1     item                  0


 Kitchen complete                                                            1     item                  0


 Fittings:
   Basement storage units, shelves and the like                              1     item                  0


   Ground floor storage units, shelves and the like                          1     item                  0
   NB Bureau storage on external wall is removed and to internal wall is
   retained

   First floor storage units, shelves and the like                           1     item                  0


 Internal staircase basement to ground floor                                 1     item                  0


 Internal staircase ground to first floor                                    1     item                  0

                                                                                       2
 Ceilings, basement and ground floor                                         305   m                     0

                                                                                       2
 Ceilings first floor unknown, say                                           45    m                     0


 Window boards                                                               1     item                  0


 All other shelves, plinths, cupboards, hooks, rails and the like to leave   1     item                  0
 all walls, floors and ceilings as a bare shell

                                                                                       2
 Take up existing first floor terrace for area of extended first floor,      20    m                     0
 retaining, adapting and protecting existing terrace decking where
 retained

Making good in connection with demolition and preparation to receive new     1     item                  0
works




                                                      Page 4
VILLA RICHARDSON

                       QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                ALL QUANTITIES ARE APPROXIMATE

                                                                                                            Total Cost of
                          Group Element/Element                              Qty   Unit   Rate   Cost         Element
                                                                                                  £              £

Demolition works and alterations:

NOTE : It is assumed that the existing roofs and structure will be
retained with modifications eg above the Cuisine. The Contractor
shall allow for temporary support to the existing roof structure
or if this is not practical in part or in whole then the Contractor
shall allow for partial or total roof replacement.

The Contractor shall include throughout for all temporary supports
and for removing all arisings from site
Temporary supports are a Contractor Designed Portion

Roof
 Temporary supports                                                          1     item                 0


 Temporary weathering                                                        1     item                 0


 Extra for partial or total replacement of the roof if deemed necessary      1     item                 0


 Remove the entire roof and structure above the existing outdoor             1     item                 0
 cooking and dining area and above the adjacent store. Roof to be
 cut back to line of first floor terrace.


 Cut back the roof and structure to suit the profile of the new roof         1     item                 0
 above the double height space on the North Elevation

 Cut back the roof and structure on north west corner to suit line of        1     item                 0
 extended first floor wall

 Remove the chimney/flue/surround to the existing outdoor                    1     item                 0
 kitchen complete down to ground level

 Remove chimney to high level roof and entire chimney breast                 1     item                 0
 down to ground level

 Cut back and make good first floor terrace pergola structure to suit line   1     item                 0
 of new first floor walls




                                                    Page 5
VILLA RICHARDSON

                        QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                 ALL QUANTITIES ARE APPROXIMATE

                                                                                                         Total Cost of
                             Group Element/Element                       Qty   Unit    Rate   Cost         Element
                                                                                               £              £

External walls
 Temporary supports                                                      1     item                  0

                                                                                   2
 Remove external cladding and framework to last, say                     300   m                     0


 Work to boundary/garden/retaining walls - allow Provisional Sum         1     PS                    0


 Sliding shutters to basement windows WB.02, 03 and 04                   3      nr                   0


 Sliding shutters to first floor Terrace                                 1     item                  0


 Remove single external door set at basement level                       2      nr                   0


 Ditto double                                                            1      nr                   0


 Remove external door set at ground floor level                          6      nr                   0


 Remove window to south elevation between new Cuisine and                1     item                  0
 Cinema and infill opening

 Form opening in external wall for DG09                                  1     item                  0


 Remove large glass external doors and windows to south/west             1     item                  0
 elevation in location of new windows/doors WG02-WG07

 Remove any remaining walls above or below last                          1     item                  0


 Remove 'garage door' to ground floor north elevation                    1     item                  0


 Remove windows to first floor north elevation, 6nr                      1     item                  0


 Ditto west elevation, 1nr                                               1     item                  0


 Ditto south elevation, 2nr                                              1     item                  0


 Remove patio doors to first floor south elevation, 2nr                  1     item                  0


 Demolish external walls at basement level from wall adjacent new door   1     item                  0
 DB01 around to new door DB05 approx total 32m run x 2.8m high
 including thicker nib to right hand side of stairwell on plan

 Demolish external walls at ground floor level to north elevation        1     item                  0
 approx total 13m run x 3.05m high




                                                     Page 6
VILLA RICHARDSON

                       QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                ALL QUANTITIES ARE APPROXIMATE

                                                                                                             Total Cost of
                          Group Element/Element                               Qty   Unit   Rate   Cost         Element
                                                                                                   £              £

Ditto to south elevation approx total 19m run x 3.05m high                    1     item                 0


Demolish angled piers in external facade to south/west elevations             1     item                 0
between glazed elements, 3nr in assorted shapes

Demolish end of garden wall approx 600mm long where wall abuts                1     item                 0
position of new windows WG02 and WG 03

Demolish outdoor kitchen store building complete down to ground level         1     item                 0


Remove external staircase and balustrade wall adjacent                              item


Demolish and rebuild short 'L' shaped section of retaining wall on south      1     item                 0
east corner of outdoor kitchen store including digging back hillside to
relocate the wall approx 1.3m further into the hill

Demolish short section of retaining wall between outdoor kitchen store        1     item                 0
north side and the main house

Demolish external walls at first floor level to north elevation               1     item                 0
for width of W1.09 ie approx 7.5m x 2.5m high

Ditto to entire west elevation approx 7m x 2.5m high (chimney                       item
measured separately)                                                          1                          0


Ditto to south elevation approx 11m x 2.5m high                               1     item                 0


Demolish wide balustrade wall along south elevation at first floor            1     item                 0
including part of return running north south, total length
approx 7.5m including making good/re-forming new end of wall
on north south line where new glass balustrade abuts

Demolish short length of balustrade wall at first floor level at north east   1     item                 0
corner approx 1m long

Enlarge and adapt opening for WB01 at Chambre 1 and form pocket for           1     item                 0
sliding door

Enlarge/adapt window opening WG01                                             1     item                 0


Demolish outdoor kitchen store building complete down to ground level         1     item                 0




                                                    Page 7
VILLA RICHARDSON

                       QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                ALL QUANTITIES ARE APPROXIMATE

                                                                                                         Total Cost of
                          Group Element/Element                           Qty   Unit   Rate   Cost         Element
                                                                                               £              £

Internal
NOTE: Load bearing partitions have not been identified. For now
the Contractor shall assume that all partitions over 100mm thick
are load bearing

 Temporary supports                                                       1     item                 0


 Remove partitions at basement level approx total 5m run x 2.3m           1     item                 0
 high

 Remove thicker partitions eg at stairwell total approx 6m run x          1     item                 0
 2.3m high

 Remove partitions at ground floor level approx total 12.5m run x         1     item                 0
 2.4m high

 Remove thicker partitions eg at stairwell total approx 13.5m run x       1     item                 0
 2.4m high including pier adjoining north elevation

 Remove partitions at first floor level approx total 5m run x 3.0m        1     item                 0
 average height

 Remove thicker partitions eg at stairwell total approx 20m run x 3.0m    1     item                 0
 average height and including double thickness pier to stairwell and at
 head of landing

 Enlarge door opening:
  Salle de Bain 2 shower                                                  1     item                 0


   Salle de Bain 3 shower                                                 1     item                 0


 Form new door opening:
  DB10                                                                    1     item                 0


 Making good to walls and floors in connection with strip out             1     item                 0


Demolition in connection with External Works:
 Temporary supports                                                       1     item                 0


 Decommission pool and drain down                                         1     item                 0


 Remove pool plant, pipework and cabling etc                              1     item                 0




                                                   Page 8
VILLA RICHARDSON

                          QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                   ALL QUANTITIES ARE APPROXIMATE

                                                                                                             Total Cost of
                             Group Element/Element                            Qty   Unit   Rate   Cost           Element
                                                                                                   £               £

    Demolish/break out existing swimming pool complete with all walls,        1     item                 0
    base, foundations, low level and high level pool channels etc

    Grub out all plants below pool level adjacent to the low level pool       1     item                 0
    channel

    Grub out trees and plants to courtyard adjacent to outdoor kitchen        1     item                 0


    Grub out trees and plants to bank on north west corner for new            1     item                 0
    basement excavation

    Take up timber deck surrounding the pool to allow new pool excavation     1     item                 0
    etc and set aside for possible re-use

    Provisional Sum for taking down section of garden/retaining wall on the   1     PS                   0
    north west corner adjacent WG11, to enable basement excavation etc


   Retain and protect:
    Bureau fittings                                                           1     item                 0


    Sliding door to Bureau                                                    1     item                 0


    Fireplaces                                                                1     item                 0


    Low level storage to Salon adjacent fireplace                             1     item                 0


    Retained windows and doors                                                1     item                 0


   Notwithstanding the above the Contractor shall retain and protect all      1     item                 0
   other structures, finishes, external works etc which are retained


                                                                                                         0   £             -

Works to existing buildings -
  Measured with new elements



                                                                                                         0   £             -




                                                      Page 9
VILLA RICHARDSON

                           QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                    ALL QUANTITIES ARE APPROXIMATE

                                                                                                                Total Cost of
                               Group Element/Element                            Qty   Unit    Rate   Cost         Element
                                                                                                      £              £

Substructures -
  Provisional Sum for removing any existing concrete piers as required          1     PS                    0
  for basement or pool excavation

                                                                                          2
   Break up drive way/remove decking and build up on north side to enable       50    m                     0
   basement excavation of gymnasium and basement stairwell etc

   Extra for additional area for working space as deemed necessary              1     item                  0
   by the Contractor

                                                                                          2
   Break up existing ground floor slab or take up existing first floor timber   50    m                     0
   structure within area of existing building footprint to enable basement
   excavation at east end

   Extra for additional area for working space as deemed necessary              1     item                  0
   by the Contractor

   Expose existing basement structure in areas of extension                     1     item                  0


   Excavate for new basement volume and cart away - site visit required for
   accurate assessment but assume:
                                                                                          3
     Gymnase area                                                               49    m                     0

                                                                                          3
     Stairwell area                                                             50    m                     0

                                                                                          3
     Salle de Jeux - trimming hill side                                         26    m                     0

                                                                                          3
     Hamam and Salle de Bain 1                                                  93    m                     0

                                                                                          3
   Excavate for new stair volume etc beyond DG07                                15    m                     0

                                                                                          3
   Extra for excavating in rock, say                                            233   m                     0


   Extra for working space and ground stabilisation                             1     item                  0


   Assume no piling or foundations due to rock base

   Disposal of ground water                                                     1     item                  0


   Disposal of surface water                                                    1     item                  0




                                                       Page 10
VILLA RICHARDSON

                        QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                 ALL QUANTITIES ARE APPROXIMATE

                                                                                                           Total Cost of
                           Group Element/Element                           Qty   Unit    Rate   Cost           Element
                                                                                                 £               £

                                                                                     2
Basement floor slab                                                        100   m                     0
say 250mm thick on 200mm hardcore and blinding and inc insulation
formwork and reinforcement
Contractor to allow for concrete but it may be established in due course
that simple masonry walls will suffice due to rock base

                                                                                     2
Basement walls external                                                    143   m                     0
say 250mm thick and inc insulation, formwork and reinforcement
Contractor to allow for concrete but it may be established in due course
that simple masonry walls will suffice due to rock base

                                                                                     2
Ground floor slab above new basement                                       100   m                     0
say 250mm thick including formwork and reinforcement
Contractor to allow for concrete but it may be established in due course
that timber structure will suffice

                                                                                     2
Ditto where new ground floor extends beyond the basement ie Cuisine,       56    m                     0
the north of Chambre 5, the new back stairs, corner at WG07 etc

Extra for small areas/irregular shapes                                     1     item                  0


Jointing new slabs/floors to existing                                      80     m                    0


Basement tanking
                                                                                     2
(photographs do not appear to show any waterproofing, possibly due to      172   m                     0
location/ground characteristics?) - say 50% of wall area and 100% of
floor area

Jointing new basement tanking with existing tanking                        1     item                  0


Waterproofing existing basement 'lid' to south west corner where small     1     item                  0
triangular section projects beyond adjusted building line at WG 05 say
2m x 1.5m extreme

Provisional Sum for other sub structure works which cannot be              1     PS                    0
determined at this stage


                                                                                                       0   £             -




                                                   Page 11
VILLA RICHARDSON

                            QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                     ALL QUANTITIES ARE APPROXIMATE

                                                                                                        Total Cost of
                              Group Element/Element                    Qty   Unit     Rate   Cost           Element
                                                                                              £               £

Superstructures -

   Frame -
   Adapt roof structure above ground floor where sections removed to   1     item                   0
   accommodate extended first floor area to north west corner

   Steelwork within ground floor to reduce floor spans, say            2     tonne                  0
   and to accommodate re-distribution of loads above

   Steelwork to large new openings to ground floor walls               4     tonne                  0


   Steel framework to double height voids at W1.09, W1.04-06 and       5     tonne                  0
   over large new openings to first floor walls

   Steelwork supporting edge of extended first floor terrace           1     tonne                  0


   Padstones, say                                                      30     nr                    0


   Bolting to existing structures                                      1     item                   0


   NB Timber structure may be more appropriate in due course


                                                                                                    0   £             -




   Upper floors -
                                                                                  2
   Extend floor structure and deck to where footprint of first floor   16     m                     0
   increases

                                                                                  2
   Extend timber structure and deck at first floor externally to       14     m                     0
   form walkway from Terrace to new external stair

   Edge details to last                                                22     m                     0


   Form opening in first floor for void at W1.04-W1.06                 1     item                   0


                                                                                                    0   £             -




                                                        Page 12
VILLA RICHARDSON

                        QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                 ALL QUANTITIES ARE APPROXIMATE

                                                                                                     Total Cost of
                            Group Element/Element                    Qty   Unit    Rate   Cost         Element
                                                                                           £              £

Roof -
Prepare edge of monopitch roof over Salle a Manger for extension     5      m                    0
over the Cuisine/Cuisine BBQ

New Pitched Roof over Cuisine/Cuisine BBQ:
                                                                               2
 Form new pitched roof structure to match existing as extension to   28    m                     0
 monopitch roof over Cuisine/Cuisine BBQ

                                                                               2
 Insulation to last                                                  28    m                     0

                                                                               2
 Cedar shingle finish to last                                        28    m                     0


 Mono ridge and joint with new flat roof                             6      m                    0


 Joint with existing pitched roof                                    5      m                    0


 Eaves                                                               6      m                    0


 Verge                                                               1      m                    0


 Abutment with new parapet wall                                      4      m                    0


 Fascia to match existing                                            6      m                    0


New Pitched Roof over WC 8:
                                                                               2
 Form new pitched roof structure                                     5     m                     0

                                                                               2
 Insulation to last                                                  5     m                     0

                                                                               2
 Cedar shingle finish to last                                        5     m                     0


 Mono ridge                                                          3      m                    0
                                                                                                 0
 Eaves                                                               3      m                    0


 Verge                                                               4      m                    0


 Fascia to match existing                                            3      m                    0




                                                    Page 13
VILLA RICHARDSON

                        QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                 ALL QUANTITIES ARE APPROXIMATE

                                                                                                          Total Cost of
                            Group Element/Element                         Qty   Unit    Rate   Cost           Element
                                                                                                £               £

New Pitched Roof over W1.09/Stair void:
                                                                                    2
 Form new pitched roof structure                                          11    m                     0

                                                                                    2
 Insulation to last                                                       11    m                     0

                                                                                    2
 Cedar shingle finish to last                                             11    m                     0


 Abutment with existing roof                                              7      m                    0


 Eaves                                                                    7      m                    0


 Verge                                                                    3      m                    0


 Fascia to match existing                                                 7      m                    0


New Flat Roof over Cuisine:
                                                                                    2
 Form new flat roof structure over Cuisine                                26    m                     0

                                                                                    2
 Insulation to last                                                       26    m                     0

                                                                                    2
 Waterproof covering to last                                              26    m                     0

                                                                                    2
 Cedar shingle secondary finish                                           26    m                     0


 Abutments/upstands                                                       21     m                    0


Glass roof to Douche:
 Safety glass roof approx 1.4m x 1.8m                                     1      nr                   0


 Abutment between glass and external wall                                 2      m                    0


 Detail to top of walls visible through glass roof                        3      m                    0


Infill roof structure and covering where high level chimney removed       1     item                  0


Make good roof and refinish into new external walls where roof above      1     item                  0
ground floor meets new first floor walls on north west corner

Provisional Sum for refurbishment of existing roofs and rainwater goods   1     PS                    0


Provisional Sum for extension of rainwater drainage system to new roofs   1     PS                    0



                                                                                                      0   £             -




                                                     Page 14
VILLA RICHARDSON

                         QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                  ALL QUANTITIES ARE APPROXIMATE

                                                                                                   Total Cost of
                            Group Element/Element                   Qty   Unit   Rate   Cost           Element
                                                                                         £               £

Stairs and ramps -

New stair from basement to first floor in 2 straight flights        1     item                 0
Assumed specification:
 Stainless steel carriage with concealed fixings
 Timber treads and risers to match flooring
 Timber clad soffit following profile of treads and risers
 Glass balustrade with concealed fixings

New external stair leading to first floor terrace                   1     item                 0
Assumed specification:
 Timber structure
 Timber treads and risers to match decking
 Balustrades to match timber clad external walls and including
 balustrade capping to match existing


                                                                                               0   £             -




                                                      Page 15
VILLA RICHARDSON

                         QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                  ALL QUANTITIES ARE APPROXIMATE

                                                                                                        Total Cost of
                           Group Element/Element                        Qty   Unit    Rate   Cost           Element
                                                                                              £               £

External walls -
External wall, assumed specification:
 Studwork double wall framework
 200mm high performance insulation
 Breathable membrane
 Battens
 Counter battens
 Cedar cladding
 Plasterboard lining

Generally measured over door and window openings but not
over screens

                                                                                  2
External wall                                                           182   m                     0
(measured over windows and doors - Contractor to allow extra for
forming reveals if necessary)

                                                                                  2
Extra for curved work                                                   23    m                     0


Reveals to screens etc                                                  71     m                    0

                                                                                  2
New cladding to existing walls including battens, counter battens and   97    m                     0
breather membrane

                                                                                  2
Extra for upgrading insulation to last                                  97    m                     0


Reveals to screens etc                                                  26     m                    0

                                                                                  2
Insulation to concrete basement walls where not timber clad             100   m                     0


                                                                                                    0   £             -




                                                   Page 16
VILLA RICHARDSON

                       QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                ALL QUANTITIES ARE APPROXIMATE

                                                                                                      Total Cost of
                          Group Element/Element                        Qty   Unit   Rate   Cost         Element
                                                                                            £              £

Windows and external doors -
Assumed specification unless otherwise stated:
 Slim line aluminium frames
 Double glazed units throughout, argon filled
 Low E glass
 Solar glare reducing coating to glass
 Sliding openers or tilt and turn (where single pane)
 Ultra slim line locking handles in stainless steel

New windows as follows:
 WB.21 approx 3.05m x 1.50m high                                       1     nr                   0


 WB.07, 08, 09, 10, 11, 12 approx 0.56m x say 1.0m                     6     nr                   0


 WG.02 approx 6.10m x 2.20m high                                       1     nr                   0


 Curved window/door composite comprising WG.03, 04, 05, 06, 07         1     nr                   0
 with curved glass and frames, WG.04 and 05 to slide
 Approx 9.0m wide around line of curve x 2.2m high

 WG.08 approx 1.0m x 2.2m high                                         1     nr                   0


 WG.09 approx 4.1m x 2.2m high                                         1     nr                   0


 WG.10 approx 4.5m x 2.2m high                                         1     nr                   0


 WG.14 approx 2.35m x 1.40m high                                       1     nr                   0


 WG.12 approx 6.4m x 4.5m high                                         1     nr                   0


 W1.01 approx 4.40m x 2.1m high                                        1     nr                   0


 W1.03 approx 3.8m x 2.1m high                                         1     nr                   0


 W1.04 approx 1.35m wide x full height of sloping internal soffit ie   1     nr                   0
 sloping head approx 2.1m up to 2.8m approx at highest point

 W1.05 approx 1.2m wide x full height internally ie 2.8m               1     nr                   0


 W1.06 ditto 1.4m x 2.8m                                               1     nr                   0


 W1.10 approx 1.1m x 1.1m                                              1     nr                   0




                                                   Page 17
VILLA RICHARDSON

                       QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                ALL QUANTITIES ARE APPROXIMATE

                                                                                                        Total Cost of
                         Group Element/Element                           Qty   Unit   Rate   Cost           Element
                                                                                              £               £

 3 sided full height frameless fixed panels in front of W1.04-W1.06      1      nr                  0
 surrounding floor void on 3 sides approx 0.5m, 1.8m and 2.9m x 2.4m
 average height

 WG.14 approx 1.35m x 2.2m high                                          1      nr                  0


New external doors as follows:
 DB.01 single door approx 0.95m x 2.10m high, solid timber clad          1      nr                  0


 Ditto - DG.02, 06, 07 and 08 assumed as DB.01                           4      nr                  0


 WB.08 sliding pocket window/door approx 1.40m x 2.10m                   1      nr                  0


 W1.02 approx 4.80m x 2.1m high, sliding patio door                      1      nr                  0


 D1.08 sliding frameless glass door approx 1.1m x 2.1m                   1      nr                  0


Refurbish and overhaul existing windows and external doors as follows:
 WB.02, 03, 04 sliding pocket door                                       3      nr                  0


 WB.06 Salle de Bain 2                                                   1      nr                  0


 WG.01 Bureau                                                            1      nr                  0


 WG.11 Bureau                                                            1      nr                  0


 DG.01 Entree                                                            1      nr                  0


 W1.07                                                                   1      nr                  0


 W1.08                                                                   1      nr                  0


Sliding shutters to WB.02-04 and WB.08                                   4      nr                  0
approx 1.60m x 2.10m, pattern as drawing 233

Overhaul and refurbish existing sliding door gear to accommodate new     1     item                 0
shutters

Window boards, assume solid timber                                       12     m                   0


Mastic sealant to all new and existing windows and external doors        1     item                 0



                                                                                                    0   £             -




                                                 Page 18
VILLA RICHARDSON

                        QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                 ALL QUANTITIES ARE APPROXIMATE

                                                                                                           Total Cost of
                          Group Element/Element                            Qty   Unit    Rate   Cost           Element
                                                                                                 £               £

Internal walls and partitions -
Generally measured over door and window openings but not
over screens

                                                                                     2
Partition in blockwork or studwork clad in plasterboard                    106   m                     0
(measured over windows and doors - Contractor to allow extra for
forming reveals if necessary)

                                                                                     2
Extra for curved work                                                      9     m                     0

                                                                                     2
Double thickness partition in blockwork or studwork clad in plasterboard   59    m                     0
(measured over windows and doors - Contractor to allow extra for
forming reveals if necessary)

                                                                                     2
Ditto in masonry thickening to external wall in basement                   7     m                     0
south east corner adjacent Haman average thickness 600mm

                                                                                                       0   £             -



Internal doors -
Door set consisting of spray lacquered flush door complete with
frame and architrave , hung on 3 stainless steel hinges
and including stainless steel lever handles and lock/latch/bathroom
lock as appropriate :
  Approx 0.90m x 2.10m structural opening                                  15    nr                    0
  DB.03, 04, 05, 06, 07, 08, 09, 10
  DG.03, 04, 05, 10
  D1.01, 06, 07

 Approx 1.10m x 2.10m structural opening                                   1     nr                    0
 DB.02

Sliding door set consisting of spray lacquered flush door with heavy
duty door gear concealed within ceiling and complete with stainless
steel flush pulls. Door to slide back fully into pocket in wall :

 Approx 1.10m x 2.10m structural opening                                   1     nr                    0
 DG.09

 Approx 1.2m x 2.10m structural opening                                    2     nr                    0
 D1.02, 03




                                                  Page 19
VILLA RICHARDSON

                           QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                    ALL QUANTITIES ARE APPROXIMATE

                                                                                                                Total Cost of
                              Group Element/Element                             Qty   Unit    Rate   Cost           Element
                                                                                                      £               £

   Sliding door set consisting of acid etched glass with heavy duty stainless
   steel door gear and stainless steel flush pulls :

     Approx 0.90m x 2.10m structural opening                                    2      nr                   0
     D1.04, 05

   Extra for bespoke stainless steel support to end of sliding track at         1      nr                   0
   junction with W1.04

   Refurbish and overhaul DG.11, sliding door to Bureau                         1      nr                   0


   WG.13 Internal window approx 4.3m x 2.2m high, assume fire rated             1      nr                   0
   clear glass


                                                                                                            0   £             -

Internal finishes -

   Wall finishes -
   Generally measured over door and window openings but not
   over screens

                                                                                          2
   Plaster finish to new external walls                                         325   m                     0
   (measured over windows and doors - Contractor to allow extra for
   forming reveals if necessary)

                                                                                          2
   Extra for curved work                                                        23    m                     0

                                                                                          2
   Plaster finish to new partitions                                             336   m                     0
   (measured over windows and doors - Contractor to allow extra for
   forming reveals if necessary)

                                                                                          2
   Extra for curved work                                                        18    m                     0


   Allowance for stainless steel angle and stop beads                           1     item                  0


   Form reveal to screens inc WG.13 etc                                         150    m                    0


   Extra for curved work                                                        9      m                    0




                                                       Page 20
VILLA RICHARDSON

                       QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                ALL QUANTITIES ARE APPROXIMATE

                                                                                                   Total Cost of
                          Group Element/Element                    Qty   Unit    Rate   Cost           Element
                                                                                         £               £

Stone wall tiling/slabs to bathrooms:
  Supply only, assume Prime Cost Sum for supply of 100€/m2         110   m
                                                                             2
                                                                                               0
  Contractor to allow for all waste, overheads and profit

                                                                             2
 Ditto in cladding to cistern boxings, say                         12    m                     0


 Ditto in cistern boxing tops not exceeding 300mm wide             10     m                    0

                                                                             2
 Lay stone tiling on plaster or plywood base including adhesive,   110   m                     0
 ground and sealant inc Hamam benching and Douche

                                                                             2
 Ditto in cladding to cistern boxings, say                         12    m                     0


 Ditto in cistern boxing tops not exceeding 300mm wide             10     m                    0

                                                                             2
 Extra for flexible waterproof lining layer such as Bal tanking    110   m                     0

                                                                             2
 Extra for additional layer of Marine plywood                      110   m                     0

                                                                             2
 Extra for separating membrane such as Ditra matting               110   m                     0


                                                                                               0   £             -




                                                   Page 21
VILLA RICHARDSON

                        QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                 ALL QUANTITIES ARE APPROXIMATE

                                                                                                              Total Cost of
                           Group Element/Element                              Qty   Unit    Rate   Cost           Element
                                                                                                    £               £

Floor finishes -
                                                                                        2
75mm min screed                                                               156   m                     0
including incorporation of underfloor heating pipes (measured separately)
NB existing floors may be timber and so new floors may also be timber in
part or whole in which case this item should be amended and priced
accordingly

                                                                                        2
Insulation to whole of basement floor to suit underfloor heating              178   m                     0

                                                                                        2
Ditto ground floor                                                            242   m                     0

                                                                                        2
Ditto first floor                                                             88    m                     0


Parquet flooring:
 Supply only, assume Prime Cost Sum for supply of 100€/m2                     461   m
                                                                                        2
                                                                                                          0
 Contractor to allow for all waste, overheads and profit

                                                                                        2
  Lay parquet floor on screed or timber base                                  461   m                     0


Stone flooring to bathrooms:
  Supply only, assume Prime Cost Sum for supply of 100€/m2                    47    m
                                                                                        2
                                                                                                          0
  Contractor to allow for all waste, overheads and profit

                                                                                        2
  Lay stone tiling on screed or timber base including adhesive,               47    m                     0
  ground and sealant including to Hamam and Douche

                                                                                        2
  Extra for flexible waterproof lining layer such as Bal tanking              47    m                     0

                                                                                        2
  Extra for additional layer of Marine plywood should floors be timber        47    m                     0

                                                                                        2
  Extra for separating membrane such as Ditra matting                         47    m                     0


  Extra for forming concealed shower gulley, assume Harmer or                 8     nr                    0
  similar shower outlet fitted within concealed trough with stainless steel
  linear slot set into tiles above

Provisional allowance for skirtings, various types                            445    m                    0


                                                                                                          0   £             -




                                                     Page 22
VILLA RICHARDSON

                           QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                    ALL QUANTITIES ARE APPROXIMATE

                                                                                                           Total Cost of
                            Group Element/Element                         Qty    Unit    Rate   Cost           Element
                                                                                                 £               £

Ceiling finishes -
                                                                                     2
New plasterboard ceilings flat or sloping and including plaster finish   420     m                     0


Assume first floor exposed timber roof soffit throughout

                                                                                     2
Matching timber soffit over stairwell at first floor                      11     m                     0

                                                                                     2
Ditto to outdoor kitchen                                                  26     m                     0



                                                                                                       0   £             -




Decorations -
Decorate the following internally:
                                                                                     2
 New and existing plastered walls                                        1,163   m                     0

                                                                                     2
  New ceilings                                                           420     m                     0

                                                                                     2
  New and existing timber soffits                                        150     m                     0


  Decorations to timber trusses                                           1      item                  0


  New skirtings                                                          445      m                    0


  Door frame and architrave sets                                          20      nr                   0


Decorate the following externally:
Generally measured over door and window openings but not
over screens

                                                                                     2
Decorations to new cladding                                              280     m                     0
(measured over windows and doors - Contractor to allow extra for
forming reveals if necessary)

Extra for reveals                                                         97     item                  0

                                                                                     2
Decorations to existing cladding, soffits and fascias                    319     m                     0


Decorations to timber trusses                                             1      item                  0




                                                       Page 23
VILLA RICHARDSON

                        QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                 ALL QUANTITIES ARE APPROXIMATE

                                                                                                        Total Cost of
                           Group Element/Element                         Qty   Unit   Rate   Cost           Element
                                                                                              £               £

Decorate existing first floor Terrace pergola                            1     item                 0


Silcone sealant to all vertical and horizontal junctions between stone   1     item                 0
and between stone and other finishes


                                                                                                    0   £             -




                                                   Page 24
VILLA RICHARDSON

                           QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                    ALL QUANTITIES ARE APPROXIMATE

                                                                                                        Total Cost of
                              Group Element/Element                      Qty   Unit   Rate   Cost         Element
                                                                                              £              £

Fittings, furnishings and equipment -
    Loose furniture and equipment, soft furnishings, blinds, beds
    and bedside tables -assume by Employer

   Assumed joinery specification unless otherwise stated:
    Spray lacquered MDF finish
    Doors and shelves to be adequate thickness to avoid bowing
    Robust stainless steel hinges or sliding gear to doors
    Soft close door and drawer mechanisms
    Profiled drawer and door edges to act as pulls

   Chambre 1
    No new joinery

   Chambre 2
    No new joinery

     Fireplace? - protect and retain                                     1     item                 0


   Chambre 3
    Full height wardrobe approx 1.7m wide, assume 4 half width drawers   1      nr                  0
    internally and hanging rail full width, sliding doors

     Fireplace? - protect and retain                                     1      nr                  0


   Chambre 4
    Full height wardrobe approx 1.7m wide, assume 4 half width drawers   1      nr                  0
    internally and hanging rail full width, sliding doors

   Chambre 5
    Full height wardrobe approx 1.5m wide, assume 4 half width drawers   1      nr                  0
    internally and hanging rail full width, sliding doors

   Chambre 6
    Full height wardrobe approx 1.4m wide, assume 4 half width drawers   1      nr                  0
    internally and hanging rail full width, 2nr hinged doors

     Bedhead storage unit approx 3.5m wide, assume open shelving say     1      nr                  0
     2.0m high

   Master Chambre
    No new joinery




                                                      Page 25
VILLA RICHARDSON

                      QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                               ALL QUANTITIES ARE APPROXIMATE

                                                                                                     Total Cost of
                           Group Element/Element                      Qty   Unit   Rate   Cost         Element
                                                                                           £              £

Salle de Bain 1
 Mirrored cabinet over basin say 0.60m x 0.30m x 1.0m                 1     nr                   0


Salle de Bain 2
 Mirrored cabinet over basin say 0.60m x 0.30m x 1.0m                 2     nr                   0


Salle de Bain 3
 Mirrored cabinet over basin say 0.60m x 0.30m x 1.0m                 1     nr                   0


Salle de Bain 4
 Mirrored cabinet over basin say 0.60m x 0.30m x 1.0m                 1     nr                   0


Salle de Bain 5
 Cistern boxing approx 2.5m wide for stone cladding (measured         1     nr                   0
 separately)

 Mirrored cabinet over basin and WC say 2.5mx 0.30m x 1.0m            1     nr                   0


Salle de Bain 6
  Cistern boxing approx 1.7m wide for stone cladding (measured        1     nr                   0
separately)
  Mirrored cabinet over basin and WC say 1.7mx 0.30m x 1.0m           1     nr                   0


WC 8
  Cistern boxing approx 1.3m wide for stone cladding (measured        1     nr                   0
separately)
  Mirrored cabinet over basin and WC say 0.6mx 0.30m x 1.0m           1     nr                   0


Master Salle de Bain
 Vanity unit approx 3.0m wide x say 0.7m high with cupboards and      1     nr                   0
 stone top

 Mirrored cabinet over basin and WC say 3.0mx 0.30m x 1.0m            1     nr                   0


Gymnase
 Full height wardrobe approx 4.1m wide, assume 4 full width drawers   1     nr                   0
 internally and 4 full width robust shelves, 6nr hinged doors

 Mirror, say 4.8m x 2.0m                                              1     nr                   0


Salle de Jeux
 Full height wardrobe approx 3.0m wide, assume 4 full width drawers   1     nr                   0
 internally and 4 full width robust shelves, sliding doors




                                                   Page 26
VILLA RICHARDSON

                       QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                ALL QUANTITIES ARE APPROXIMATE

                                                                                                         Total Cost of
                         Group Element/Element                            Qty   Unit   Rate   Cost         Element
                                                                                               £              £

Haman
 Concrete benches to receive Mosaic tiling (measured separately)
  2.15m maximum length                                                    1     nr                   0
  2.30m min                                                               1     nr                   0
  3.55m maximum length                                                    1     nr                   0


Vestaire
 Full height wardrobe approx 3.8m wide, assume full width shoe            1     nr                   0
 rack internally and full width hanging rail, sliding doors

Entrance Hall adjacent DG.02
 Full height wardrobe approx 2.8m wide, assume full width shoe            1     nr                   0
 rack internally and full width hanging rail, sliding doors

Bureau
 Desk unit under window WG.01 approx 3.1m wide to match existing          1     nr                   0
 Bureau cabinet finish

Salon
 No new joinery

Salle a Manger
 Full height storage unit approx 2.7m wide, assume 50% cupboards and      1     nr                   0
 50% drawers at low level with open storage above

Cinema
 Full height media storage unit approx 2.0m wide, assume open shelving    1     nr                   0


 TV cabinet approx 3.2m wide, say 0.7m high, assume 50% drawers           1     nr                   0
 and 50% cupboards

Cuisine
 Provisional Sum for design, supply and installation of main kitchen      1     PS                   0
 including units, worktops, splashbacks, appliances and extract canopy

Cuisine BBQ
 Provisional Sum for design, supply and installation of outdoor kitchen   1     PS                   0
 including units, worktops, splashbacks, appliances and extract canopy
 or chimney




                                                 Page 27
VILLA RICHARDSON

                       QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                ALL QUANTITIES ARE APPROXIMATE

                                                                                                           Total Cost of
                          Group Element/Element                             Qty   Unit   Rate   Cost           Element
                                                                                                 £               £

Dressing
 Dressing unit approx 2.8m wide by say 2.9m high with sliding mirrored      1     nr                   0
 doors, assume full width hanging rail, 8nr drawers internally, extensive
 shelving and shoe rack

 Ditto approx 4.0m wide with 16nr drawers, large shoe rack and area         1     nr                   0


                                                                                                       0   £             -




                                                   Page 28
VILLA RICHARDSON

                           QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                    ALL QUANTITIES ARE APPROXIMATE

                                                                                                             Total Cost of
                             Group Element/Element                      Qty     Unit     Rate       Cost          Element
                                                                                                      £             £

Services -

   Sanitary appliances -
   Include the following Provisional Sums for the supply of sanitary
   fittings:
      Salle de Bain 1
         WC complete                                                     1      PS      600.00         600
         Basin and taps complete                                         1      PS      600.00         600
         Shower spray and handset, shower valve                          1      PS      500.00         500
         Shower floor gulley                                             1      PS      100.00         100
         Shower tray                                                   Bespoke tiled shower tray - see Finishes
         Towel warmer                                                    1      PS      500.00         500
         Accessories such as towel rail, soap dish, mirror               1      PS      200.00         200


    Salle de Bain 2
     WC complete                                                         1      PS      600.00         600
     Basin and taps complete                                             1      PS     1200.00       1,200
     Shower spray and handset, shower valve                              1      PS      500.00         500
     Shower floor gulley                                                 1      PS      100.00         100
     Shower tray                                                       Bespoke tiled shower tray - see Finishes
     Towel warmer                                                        1      PS      500.00         500
     Accessories such as towel rail, soap dish, mirror                   1      PS      200.00         200


    Salle de Bain 3
     WC complete                                                         1      PS      600.00         600
     Basin and taps complete                                             1      PS      600.00         600
     Shower spray and handset, shower valve                              1      PS      500.00         500
     Shower floor gulley                                                 1      PS      100.00         100
     Shower tray                                                       Bespoke tiled shower tray - see Finishes
     Towel warmer                                                        1      PS      500.00         500
     Accessories such as towel rail, soap dish, mirror                   1      PS      200.00         200


    Salle de Bain 4
     WC complete                                                         1      PS      600.00         600
     Basin and taps complete                                             1      PS      600.00         600
     Towel warmer                                                        1      PS      500.00         500
     Accessories such as towel rail, soap dish, mirror                   1      PS      150.00         150




                                                      Page 29
VILLA RICHARDSON

                     QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                              ALL QUANTITIES ARE APPROXIMATE

                                                                                                      Total Cost of
                        Group Element/Element                  Qty     Unit     Rate       Cost          Element
                                                                                             £             £

Salle de Bain 5
 WC complete with cistern frame                                 1      PS      800.00         800
 Basin and taps complete                                        1      PS      600.00         600
 Shower spray and handset, shower valve                         1      PS     1000.00       1,000
 Shower floor gulley                                            1      PS      100.00         100
 Shower tray                                                  Bespoke tiled shower tray - see Finishes
 Towel warmer                                                   1      PS      500.00         500
 Accessories such as towel rail, soap dish, mirror              1      PS      200.00         200


Salle de Bain 6
 WC complete with cistern frame                                 1      PS      800.00         800
 Basin and taps complete                                        1      PS      600.00         600
 Shower spray and handset, shower valve                         1      PS     1000.00       1,000
 Shower floor gulley                                            1      PS      100.00         100
 Shower tray                                                  Bespoke tiled shower tray - see Finishes
 Towel warmer                                                   1      PS      500.00         500
 Accessories such as towel rail, soap dish, mirror              1      PS      200.00         200


Salle de Bain 7
 WC complete with cistern frame                                 1      PS      800.00         800
 Basin and taps complete                                        1      PS      600.00         600
 Towel warmer                                                   1      PS      500.00         500
 Accessories such as towel rail, soap dish, mirror              1      PS      150.00         150


WC 8
 WC complete with cistern frame                                 1      PS      800.00         800
 Basin and taps complete                                        1      PS      600.00         600
 Towel warmer                                                   1      PS      500.00         500
 Accessories such as towel rail, soap dish, mirror              1      PS      150.00         150


Douche
 Shower spray and handset, shower valve                         1      PS     1500.00       1,500
 Shower floor gulley                                            1      PS      100.00         100
 Shower tray                                                  Bespoke tiled shower tray - see Finishes
 Accessories such as towel rail, soap dish, mirror              1      PS       50.00            50




                                                Page 30
VILLA RICHARDSON

                        QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                 ALL QUANTITIES ARE APPROXIMATE

                                                                                                                    Total Cost of
                          Group Element/Element                              Qty     Unit     Rate       Cost           Element
                                                                                                           £              £

 Master Salle de Bain
  WC complete with cistern frame                                              1      PS      800.00         800
  Basin and taps complete                                                     1      PS     2000.00       2,000
  Free standing bath and taps complete                                        1      PS     5000.00       5,000
  Shower spray and handset, shower valve                                      1      PS     2000.00       2,000
  Shower floor gulley                                                         1      PS      100.00         100
  Shower tray                                                               Bespoke tiled shower tray - see Finishes
  Towel warmer                                                                1      PS     1200.00       1,200
  Accessories such as towel rail, soap dish, mirror                           1      PS      300.00         300


 Haman
  Steam generator                                                             1      PS     1000.00       1,000
  Shower floor gulley                                                         1      PS      100.00         100


Fix only the following sanitary ware :
    WC suite with exposed cistern                                             4       nr                        0
    WC suite with concealed cistern frame and remote flush                    5       nr                        0
    Basin and taps with waste and trap                                        11      nr                        0
    Shower spray and handset, shower valve                                    7       nr                        0
    Shower floor gulley                                                       8       nr                        0
    Free standing bath and taps, trap and plinth                              1       nr                        0
    Towel warmers (see Services for pipework)                                 10      nr                        0
    Steam generator (see Services for wiring and pipework)                    1       nr                        0


Provisional Sum for fixing accessories                                        1      PS     1000.00       1,000


Frameless glass shower screens:
  Approx 0.80m x 2.0m as door                                                 4       nr                        0


 Approx 1.50m x 2.0m with 0.80m door and 0.70m fixed panel                    1       nr                        0


 Assume Douche is open, no door or screen

Silcone sealant to all joints between sanitary ware and adjacent finishes     1       nr                        0


                                                                                                         35,600     £     35,600




                                                   Page 31
VILLA RICHARDSON

                            QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                     ALL QUANTITIES ARE APPROXIMATE

                                                                                                       Total Cost of
                               Group Element/Element                    Qty   Unit   Rate   Cost         Element
                                                                                             £              £

Mechanical installations -
Contractor Designed Portion:

Preliminaries and General Conditions                                    1     item                 0


Isolation and stripping out existing installations                      1     item                 0
(measured separately)

Boiler plant                                                            1     item                 0


Underfloor Heating Installation throughout including insulation,        1     item                 0
manifolds reflectors etc.
                                                                                                   0
Bathroom towel warmers                                                  1     item


New Cold Water Booster Set                                              1     item                 0


Cold Water Installation including kitchen supplies                      1     item                 0


Hot Water Installation including kitchen supplies                       1     item                 0


Kitchen ventilation (extract hood by kitchen supplier)                  1     item                 0


Bathroom ventilation                                                    1     item                 0


Gas services to fireplaces and to kitchen appliances                    1     item                 0


Thermal insulation to all pipework                                      1     item                 0


Above ground drainage installation                                      1     item                 0


Controls and Associated Wiring                                          1     item                 0


Mechanical and Plumbing testing and commissioning                       1     item                 0


Provision of record documents                                           1     item                 0


Provision of design and installation drawings and design information    1     item                 0


Provision of working drawings                                           1     item                 0




                                                         Page 32
VILLA RICHARDSON

                         QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                  ALL QUANTITIES ARE APPROXIMATE

                                                                                                   Total Cost of
                            Group Element/Element                   Qty   Unit   Rate   Cost           Element
                                                                                         £               £

Design of all services                                              1     item                 0


Any mechanical or plumbing items not listed above                   1     item                 0


Builders work in connection with mechanical services                1     item                 0


                                                                                               0   £             -




                                                       Page 33
VILLA RICHARDSON

                             QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                      ALL QUANTITIES ARE APPROXIMATE

                                                                                                                     Total Cost of
                               Group Element/Element                                  Qty   Unit   Rate   Cost         Element
                                                                                                           £              £

Electrical installations -
Contractor Designed Portion:

Preliminaries and General Conditions                                                  1     item                 0


Isolation and stripping out existing installations                                    1     item                 0
(measured separately)

Switchgear and sub-mains                                                              1     item                 0


Small power installation including accessories                                        1     item                 0


Fire and smoke alarm systems                                                          1     item                 0


Security Alarm                                                                        1     item                 0


Earthing and Bonding                                                                  1     item                 0


Supply of light fittings, transformers, lamps etc                                     1     item                 0


Installation of light fittings, transformers, lamps etc                               1     item                 0


Specialist lighting control and audio visual package including all equipment,         1     PS                   0
supply of specialist cables and termination of cables. Provisional Sum

Installation of the following free issue cabling                                                                 0
  Speaker cable                                                                       1     item                 0


  Satelite cable                                                                      1     item                 0


  Lutron cable                                                                        1     item                 0


  Cat 6 structured cabling                                                            1     item                 0


  Door entry data control cable                                                       1     item                 0


  Supply and install all power cabling and mains connections etc                      1     item                 0


  Liaison and attendance including but not limited to attendance at meetings          1     item                 0
  with lighting control/audio visual specialist, provision of site welfare, rubbish
  clearance, use of standing scaffolding etc




                                                             Page 34
VILLA RICHARDSON

                               QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                        ALL QUANTITIES ARE APPROXIMATE

                                                                                                            Total Cost of
                                  Group Element/Element                      Qty   Unit   Rate   Cost           Element
                                                                                                  £               £

   Power to kitchen appliances                                               1     item                 0


   External Lighting
    Supply of light fittings, transformers, lamps etc                        1     item                 0


     Installation of light fittings, transformers, lamps etc                 1     item                 0


   Electrical wiring in connection with mechanical systems                   1     item                 0


   Electrical testing and commissioning                                      1     item                 0


   Provision of record documents                                             1     item                 0


   Provision of design and installation drawings and design information      1     item                 0


   Provision of working drawings                                             1     item                 0


   Design of all services                                                    1     item                 0


   Any electrical items not listed above                                     1     item                 0


   Builders work in connection with electrical services                      1     item                 0
                                                                                                        0



                                                                                                        0   £             -

   Lift and conveyor installations -
   N/A


                                                                                                        0   £             -

   Special installations -
   Mechanical Services in connection with the Pool Installation              1     item


   Electrical Services in connection with the Pool Installation              1     item


                                                                                                        0   £             -

Complete buildings and building units -
  N/A

                                                                                                        0   £             -




                                                               Page 35
VILLA RICHARDSON

                            QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE
                                     ALL QUANTITIES ARE APPROXIMATE

                                                                                                          Total Cost of
                               Group Element/Element                      Qty   Unit    Rate   Cost         Element
                                                                                                £              £

External works -
   Generally -
   Provisional Sum for removing any existing concrete piers as required   1     PS                    0
   for basement or pool excavation

   Work to boundary walls and garden walls adjoining the house            1     PS                    0
   cannot be determined at this stage.
   Provisional Sum for alteration, extension, re-cladding as required

   Works to the driveways cannot be determined at this stage.             1     PS                    0
   Provisional Sum for extension and alteration and for making good
   following basement excavation

   Landscaping - By Employer

   Swimming Pool:
    Pool shell 20m x 5.8m plus new steps 2.5m x 1.75m
    Depth not noted, assume 1.2m minimum graduating to 2.5m deep
    at diving area
    Waterproofing
    Carrelage Warm tiling to pool and steps 30cm x 60cm                    1    item                  0
    New pool plant
    Pool plant room and access
    Diving board
    Pool cover

   Builders work in connection with pool eg trenches, holes etc            1    item                  0


   Stone wall to hill side forming infinity edge to long side of pool      1    item                  0

                                                                                    3
   Extra for excavating in rock, say                                      150   m                     0

                                                                                    3
   Filling to make up levels, assume crushing and compacting              100   m                     0
   rock from basement/pool excavations, say

   Disposal of ground water                                               1     item                  0


   Disposal of surface water                                              1     item                  0

                                                                                    2
   Extend sub structure for deck                                          210   m                     0

                                                                                    2
   New decking                                                            210   m                     0




                                                         Page 36
Budget estimate quantified framework   richardson villa 21.3.01 for issue
Budget estimate quantified framework   richardson villa 21.3.01 for issue
Budget estimate quantified framework   richardson villa 21.3.01 for issue
Budget estimate quantified framework   richardson villa 21.3.01 for issue
Budget estimate quantified framework   richardson villa 21.3.01 for issue
Budget estimate quantified framework   richardson villa 21.3.01 for issue

Weitere ähnliche Inhalte

Andere mochten auch

Benetton Group - 2011 Preliminary Highlights
Benetton Group - 2011 Preliminary HighlightsBenetton Group - 2011 Preliminary Highlights
Benetton Group - 2011 Preliminary HighlightsBenetton Group
 
Benetton Group - 2011 Nine Months Results
Benetton Group - 2011 Nine Months ResultsBenetton Group - 2011 Nine Months Results
Benetton Group - 2011 Nine Months ResultsBenetton Group
 
Browser dan search engine
Browser dan search engineBrowser dan search engine
Browser dan search engineDwi Tanu
 
1.4 decision matrix
1.4 decision matrix1.4 decision matrix
1.4 decision matrixUmair Khalid
 
Shared leadership skills
Shared leadership skillsShared leadership skills
Shared leadership skillsSalman Irshad
 
Benetton Group - 2011 Annual Results
Benetton Group - 2011 Annual ResultsBenetton Group - 2011 Annual Results
Benetton Group - 2011 Annual ResultsBenetton Group
 
Accounts of special customers
Accounts of special customersAccounts of special customers
Accounts of special customersSalman Irshad
 
Bcqc prelims final with_questions_only
Bcqc prelims final with_questions_onlyBcqc prelims final with_questions_only
Bcqc prelims final with_questions_onlyVikram Joshi
 
Mengenal pecahan 2
Mengenal pecahan 2Mengenal pecahan 2
Mengenal pecahan 2Cahaya Yahya
 

Andere mochten auch (12)

Benetton Group - 2011 Preliminary Highlights
Benetton Group - 2011 Preliminary HighlightsBenetton Group - 2011 Preliminary Highlights
Benetton Group - 2011 Preliminary Highlights
 
Ciberassetjament
CiberassetjamentCiberassetjament
Ciberassetjament
 
Benetton Group - 2011 Nine Months Results
Benetton Group - 2011 Nine Months ResultsBenetton Group - 2011 Nine Months Results
Benetton Group - 2011 Nine Months Results
 
Mengenal pecahan
Mengenal pecahanMengenal pecahan
Mengenal pecahan
 
Browser dan search engine
Browser dan search engineBrowser dan search engine
Browser dan search engine
 
Proposal nscd 2015
Proposal nscd 2015Proposal nscd 2015
Proposal nscd 2015
 
1.4 decision matrix
1.4 decision matrix1.4 decision matrix
1.4 decision matrix
 
Shared leadership skills
Shared leadership skillsShared leadership skills
Shared leadership skills
 
Benetton Group - 2011 Annual Results
Benetton Group - 2011 Annual ResultsBenetton Group - 2011 Annual Results
Benetton Group - 2011 Annual Results
 
Accounts of special customers
Accounts of special customersAccounts of special customers
Accounts of special customers
 
Bcqc prelims final with_questions_only
Bcqc prelims final with_questions_onlyBcqc prelims final with_questions_only
Bcqc prelims final with_questions_only
 
Mengenal pecahan 2
Mengenal pecahan 2Mengenal pecahan 2
Mengenal pecahan 2
 

Kürzlich hochgeladen

Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Roland Driesen
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Servicediscovermytutordmt
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Dipal Arora
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...Suhani Kapoor
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 

Kürzlich hochgeladen (20)

Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...Boost the utilization of your HCL environment by reevaluating use cases and f...
Boost the utilization of your HCL environment by reevaluating use cases and f...
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
Call Girls in Gomti Nagar - 7388211116 - With room Service
Call Girls in Gomti Nagar - 7388211116  - With room ServiceCall Girls in Gomti Nagar - 7388211116  - With room Service
Call Girls in Gomti Nagar - 7388211116 - With room Service
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
Call Girls Navi Mumbai Just Call 9907093804 Top Class Call Girl Service Avail...
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
VIP Call Girls Gandi Maisamma ( Hyderabad ) Phone 8250192130 | ₹5k To 25k Wit...
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 

Budget estimate quantified framework richardson villa 21.3.01 for issue

  • 1. QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE for VILLA RICHARDSON CORSICA 21 March 2011 Version 1 STOCKDALE 58 Streatham High Road London SW16 1DA Tel: 020 8664 6373
  • 2. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE INTRODUCTION NOTES FOR THE CONTRACTOR: This quantified framework has been produced as an aid to contractors in the production of order of cost/budget estimates. When completed by the contractor the document will assist in the setting of a realistic budget or cost limit and as a platform for further negotiation. This document is not a Bill of Quantities; the quantities have not been measured in accordance with the Standard Method of Measurement or the New Rules of Measurement. The quantities are approximate. We have assumed that the existing roof will be retained and modified in places rather than be completely or partially removed to facilitate the works. The structural engineer and contractor must determine whether which approach is most practical and cost effective. This document is available as an XL file. The file is not locked or security restricted. We recommend that the Contractor checks all formulae within the XL file before submitting a budget as editting the document may affect the original formulae.
  • 3. This document has been prepared with reference to the following Michaelis Boyd drawings: 10080-100 Existing site plan 22.11.10 10080-101 existing basement plan 22.11.10 10080-102 existing ground floor plan 22.11.10 10080-103 existing first floor plan - 10080-104 existing roof plan - 10080-120 existing north elevation 22.11.10 10080-121 existing south elevation 22.11.10 10080-122 existing east elevation 22.11.10 10080-123 existing west elevation 22.11.10 10080-130 existing section AA 22.11.10 10080-131 existing section BB 22.11.10 10080-140 demolition basement 15.12.10 10080-141 demolition ground floor 15.12.10 10080-142 demolition first floor 15.12.10 10080-200 proposed site plan 15.12.10 10080-201 proposed basement plan 15.12.10 10080-202 proposed ground floor plan 15.12.10 10080-203 proposed first floor plan 15.12.10 10080-204 proposed roof plan 15.12.10 10080-220 existing north elevation 15.12.10 A 10080-221 existing south elevation 15.12.10 A 10080-222 existing east elevation 15.12.10 A 10080-223 existing west elevation 15.12.10 A 10080-230 proposed section AA 15.12.10 A 10080-231 proposed section BB 15.12.10 10080-232 Proposed section CC 15.12.10 10080-240 Proposed garage plan 15.12.10 Existing site photographs dated 24.11.10
  • 4. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE SUMMARY Costs from attached sheets: - Cost/m² of Total Cost of GIFA Element £ £ Building Works Estimate: - Facilitating works 0 0 Works to existing buildings 0 0 Substructures 0 0 Superstructures Frame 0 0 Upper floors 0 0 Roof 0 0 Stairs and ramps 0 0 External walls 0 0 Windows and external doors 0 0 Internal walls and partitions 0 0 Internal doors 0 0 Internal finishes Wall finishes 0 0 Floor finishes 0 0 Ceiling finishes 0 0 Decorations 0 0 Fittings, furnishings and equipment 0 0 Services Sanitary appliances 70 35,600 Mechanical installations 0 0 Electrical installations 0 0 Lift and conveyor installations 0 0 Special installations 0 0 Complete buildings and building units 0 0 External works Generally 0 0 Garage 0 0 Below ground drainage 0 0 Main Contractor's preliminaries 0 0 Main Contractor's overheads and profit 0 0 Risk Allowance Estimate 0 0 Total: Building Works Estimate 70 35,600 Tender Inflation 0 Cost Estimate (excluding fees) 35,600 Project/Design Team Fees and Other 0 Cost Estimate (excluding VAT) 35,600 VAT/TVA assessment 0 Total of Order of Cost £ 35,600 Page 1
  • 5. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ BUILDING WORKS Facilitating works - Loose furniture and equipment including artwork to be removed by Employer Items of demolition and alteration are to be carried out carefully to afford the minimal damage to work to be retained. Any such damage shall be made good at the Contractor's own expense. Items of demolition and alteration are to include for all necessary making good to floors, walls, ceilings and roofs etc. Items of demolition and alteration are to include for removing from site all rubbish, debris, etc. Cutting, forming, enlarging or adapting openings through existing work is to include for quoining jambs, making good existing plaster up to and/or extending through same opening, extending any necessary floor finish through opening Demolishing or removing structures or part of structures, cutting, forming or enlarging openings are to include for all necessary temporary support whether or not expressly noted and for wedging and pinning or packing up to existing structure after inserting permanent support work. Temporary supports include maintaining, adapting and clearing away on completion. Filling openings in existing work is to include for all necessary extending of finishes, skirtings and junctions with existing. Page 2
  • 6. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Isolate/make safe the following services in preparation for demolition work: Electrical services 1 item 0 Gas/oil services 1 item 0 Water services 1 item 0 Telecoms 1 item 0 Drainage 1 item 0 Strip out and remove from site the following: Electrical services complete 1 item 0 Plumbing, heating, ventilation gas, oil services complete 1 item 0 Cooling systems 1 item 0 Above ground drainage system 1 item 0 Pool plant and pool pipework and cabling 1 item 0 Gas/oil storage tanks 1 item 0 2 Floor coverings 385 m 0 2 Floor screeds and timber floor boards 385 m 0 Provisional Sum for removing existing ground and basement floor 303 PS 0 slabs to allow for increased floor build up to suit underfloor heating, reduce levels by say 100mm and relay slab at new level NB existing floors may be timber in part or whole in which case this item should be amended and priced accordingly Internal door sets 20 nr 0 Skirtings 390 m 0 Page 3
  • 7. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Bathrooms: Basement bathroom and WCs complete 1 item 0 Ground floor bathrooms and WCs complete 1 item 0 First floor bathrooms and WCs complete 1 item 0 Kitchen complete 1 item 0 Fittings: Basement storage units, shelves and the like 1 item 0 Ground floor storage units, shelves and the like 1 item 0 NB Bureau storage on external wall is removed and to internal wall is retained First floor storage units, shelves and the like 1 item 0 Internal staircase basement to ground floor 1 item 0 Internal staircase ground to first floor 1 item 0 2 Ceilings, basement and ground floor 305 m 0 2 Ceilings first floor unknown, say 45 m 0 Window boards 1 item 0 All other shelves, plinths, cupboards, hooks, rails and the like to leave 1 item 0 all walls, floors and ceilings as a bare shell 2 Take up existing first floor terrace for area of extended first floor, 20 m 0 retaining, adapting and protecting existing terrace decking where retained Making good in connection with demolition and preparation to receive new 1 item 0 works Page 4
  • 8. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Demolition works and alterations: NOTE : It is assumed that the existing roofs and structure will be retained with modifications eg above the Cuisine. The Contractor shall allow for temporary support to the existing roof structure or if this is not practical in part or in whole then the Contractor shall allow for partial or total roof replacement. The Contractor shall include throughout for all temporary supports and for removing all arisings from site Temporary supports are a Contractor Designed Portion Roof Temporary supports 1 item 0 Temporary weathering 1 item 0 Extra for partial or total replacement of the roof if deemed necessary 1 item 0 Remove the entire roof and structure above the existing outdoor 1 item 0 cooking and dining area and above the adjacent store. Roof to be cut back to line of first floor terrace. Cut back the roof and structure to suit the profile of the new roof 1 item 0 above the double height space on the North Elevation Cut back the roof and structure on north west corner to suit line of 1 item 0 extended first floor wall Remove the chimney/flue/surround to the existing outdoor 1 item 0 kitchen complete down to ground level Remove chimney to high level roof and entire chimney breast 1 item 0 down to ground level Cut back and make good first floor terrace pergola structure to suit line 1 item 0 of new first floor walls Page 5
  • 9. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ External walls Temporary supports 1 item 0 2 Remove external cladding and framework to last, say 300 m 0 Work to boundary/garden/retaining walls - allow Provisional Sum 1 PS 0 Sliding shutters to basement windows WB.02, 03 and 04 3 nr 0 Sliding shutters to first floor Terrace 1 item 0 Remove single external door set at basement level 2 nr 0 Ditto double 1 nr 0 Remove external door set at ground floor level 6 nr 0 Remove window to south elevation between new Cuisine and 1 item 0 Cinema and infill opening Form opening in external wall for DG09 1 item 0 Remove large glass external doors and windows to south/west 1 item 0 elevation in location of new windows/doors WG02-WG07 Remove any remaining walls above or below last 1 item 0 Remove 'garage door' to ground floor north elevation 1 item 0 Remove windows to first floor north elevation, 6nr 1 item 0 Ditto west elevation, 1nr 1 item 0 Ditto south elevation, 2nr 1 item 0 Remove patio doors to first floor south elevation, 2nr 1 item 0 Demolish external walls at basement level from wall adjacent new door 1 item 0 DB01 around to new door DB05 approx total 32m run x 2.8m high including thicker nib to right hand side of stairwell on plan Demolish external walls at ground floor level to north elevation 1 item 0 approx total 13m run x 3.05m high Page 6
  • 10. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Ditto to south elevation approx total 19m run x 3.05m high 1 item 0 Demolish angled piers in external facade to south/west elevations 1 item 0 between glazed elements, 3nr in assorted shapes Demolish end of garden wall approx 600mm long where wall abuts 1 item 0 position of new windows WG02 and WG 03 Demolish outdoor kitchen store building complete down to ground level 1 item 0 Remove external staircase and balustrade wall adjacent item Demolish and rebuild short 'L' shaped section of retaining wall on south 1 item 0 east corner of outdoor kitchen store including digging back hillside to relocate the wall approx 1.3m further into the hill Demolish short section of retaining wall between outdoor kitchen store 1 item 0 north side and the main house Demolish external walls at first floor level to north elevation 1 item 0 for width of W1.09 ie approx 7.5m x 2.5m high Ditto to entire west elevation approx 7m x 2.5m high (chimney item measured separately) 1 0 Ditto to south elevation approx 11m x 2.5m high 1 item 0 Demolish wide balustrade wall along south elevation at first floor 1 item 0 including part of return running north south, total length approx 7.5m including making good/re-forming new end of wall on north south line where new glass balustrade abuts Demolish short length of balustrade wall at first floor level at north east 1 item 0 corner approx 1m long Enlarge and adapt opening for WB01 at Chambre 1 and form pocket for 1 item 0 sliding door Enlarge/adapt window opening WG01 1 item 0 Demolish outdoor kitchen store building complete down to ground level 1 item 0 Page 7
  • 11. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Internal NOTE: Load bearing partitions have not been identified. For now the Contractor shall assume that all partitions over 100mm thick are load bearing Temporary supports 1 item 0 Remove partitions at basement level approx total 5m run x 2.3m 1 item 0 high Remove thicker partitions eg at stairwell total approx 6m run x 1 item 0 2.3m high Remove partitions at ground floor level approx total 12.5m run x 1 item 0 2.4m high Remove thicker partitions eg at stairwell total approx 13.5m run x 1 item 0 2.4m high including pier adjoining north elevation Remove partitions at first floor level approx total 5m run x 3.0m 1 item 0 average height Remove thicker partitions eg at stairwell total approx 20m run x 3.0m 1 item 0 average height and including double thickness pier to stairwell and at head of landing Enlarge door opening: Salle de Bain 2 shower 1 item 0 Salle de Bain 3 shower 1 item 0 Form new door opening: DB10 1 item 0 Making good to walls and floors in connection with strip out 1 item 0 Demolition in connection with External Works: Temporary supports 1 item 0 Decommission pool and drain down 1 item 0 Remove pool plant, pipework and cabling etc 1 item 0 Page 8
  • 12. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Demolish/break out existing swimming pool complete with all walls, 1 item 0 base, foundations, low level and high level pool channels etc Grub out all plants below pool level adjacent to the low level pool 1 item 0 channel Grub out trees and plants to courtyard adjacent to outdoor kitchen 1 item 0 Grub out trees and plants to bank on north west corner for new 1 item 0 basement excavation Take up timber deck surrounding the pool to allow new pool excavation 1 item 0 etc and set aside for possible re-use Provisional Sum for taking down section of garden/retaining wall on the 1 PS 0 north west corner adjacent WG11, to enable basement excavation etc Retain and protect: Bureau fittings 1 item 0 Sliding door to Bureau 1 item 0 Fireplaces 1 item 0 Low level storage to Salon adjacent fireplace 1 item 0 Retained windows and doors 1 item 0 Notwithstanding the above the Contractor shall retain and protect all 1 item 0 other structures, finishes, external works etc which are retained 0 £ - Works to existing buildings - Measured with new elements 0 £ - Page 9
  • 13. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Substructures - Provisional Sum for removing any existing concrete piers as required 1 PS 0 for basement or pool excavation 2 Break up drive way/remove decking and build up on north side to enable 50 m 0 basement excavation of gymnasium and basement stairwell etc Extra for additional area for working space as deemed necessary 1 item 0 by the Contractor 2 Break up existing ground floor slab or take up existing first floor timber 50 m 0 structure within area of existing building footprint to enable basement excavation at east end Extra for additional area for working space as deemed necessary 1 item 0 by the Contractor Expose existing basement structure in areas of extension 1 item 0 Excavate for new basement volume and cart away - site visit required for accurate assessment but assume: 3 Gymnase area 49 m 0 3 Stairwell area 50 m 0 3 Salle de Jeux - trimming hill side 26 m 0 3 Hamam and Salle de Bain 1 93 m 0 3 Excavate for new stair volume etc beyond DG07 15 m 0 3 Extra for excavating in rock, say 233 m 0 Extra for working space and ground stabilisation 1 item 0 Assume no piling or foundations due to rock base Disposal of ground water 1 item 0 Disposal of surface water 1 item 0 Page 10
  • 14. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ 2 Basement floor slab 100 m 0 say 250mm thick on 200mm hardcore and blinding and inc insulation formwork and reinforcement Contractor to allow for concrete but it may be established in due course that simple masonry walls will suffice due to rock base 2 Basement walls external 143 m 0 say 250mm thick and inc insulation, formwork and reinforcement Contractor to allow for concrete but it may be established in due course that simple masonry walls will suffice due to rock base 2 Ground floor slab above new basement 100 m 0 say 250mm thick including formwork and reinforcement Contractor to allow for concrete but it may be established in due course that timber structure will suffice 2 Ditto where new ground floor extends beyond the basement ie Cuisine, 56 m 0 the north of Chambre 5, the new back stairs, corner at WG07 etc Extra for small areas/irregular shapes 1 item 0 Jointing new slabs/floors to existing 80 m 0 Basement tanking 2 (photographs do not appear to show any waterproofing, possibly due to 172 m 0 location/ground characteristics?) - say 50% of wall area and 100% of floor area Jointing new basement tanking with existing tanking 1 item 0 Waterproofing existing basement 'lid' to south west corner where small 1 item 0 triangular section projects beyond adjusted building line at WG 05 say 2m x 1.5m extreme Provisional Sum for other sub structure works which cannot be 1 PS 0 determined at this stage 0 £ - Page 11
  • 15. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Superstructures - Frame - Adapt roof structure above ground floor where sections removed to 1 item 0 accommodate extended first floor area to north west corner Steelwork within ground floor to reduce floor spans, say 2 tonne 0 and to accommodate re-distribution of loads above Steelwork to large new openings to ground floor walls 4 tonne 0 Steel framework to double height voids at W1.09, W1.04-06 and 5 tonne 0 over large new openings to first floor walls Steelwork supporting edge of extended first floor terrace 1 tonne 0 Padstones, say 30 nr 0 Bolting to existing structures 1 item 0 NB Timber structure may be more appropriate in due course 0 £ - Upper floors - 2 Extend floor structure and deck to where footprint of first floor 16 m 0 increases 2 Extend timber structure and deck at first floor externally to 14 m 0 form walkway from Terrace to new external stair Edge details to last 22 m 0 Form opening in first floor for void at W1.04-W1.06 1 item 0 0 £ - Page 12
  • 16. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Roof - Prepare edge of monopitch roof over Salle a Manger for extension 5 m 0 over the Cuisine/Cuisine BBQ New Pitched Roof over Cuisine/Cuisine BBQ: 2 Form new pitched roof structure to match existing as extension to 28 m 0 monopitch roof over Cuisine/Cuisine BBQ 2 Insulation to last 28 m 0 2 Cedar shingle finish to last 28 m 0 Mono ridge and joint with new flat roof 6 m 0 Joint with existing pitched roof 5 m 0 Eaves 6 m 0 Verge 1 m 0 Abutment with new parapet wall 4 m 0 Fascia to match existing 6 m 0 New Pitched Roof over WC 8: 2 Form new pitched roof structure 5 m 0 2 Insulation to last 5 m 0 2 Cedar shingle finish to last 5 m 0 Mono ridge 3 m 0 0 Eaves 3 m 0 Verge 4 m 0 Fascia to match existing 3 m 0 Page 13
  • 17. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ New Pitched Roof over W1.09/Stair void: 2 Form new pitched roof structure 11 m 0 2 Insulation to last 11 m 0 2 Cedar shingle finish to last 11 m 0 Abutment with existing roof 7 m 0 Eaves 7 m 0 Verge 3 m 0 Fascia to match existing 7 m 0 New Flat Roof over Cuisine: 2 Form new flat roof structure over Cuisine 26 m 0 2 Insulation to last 26 m 0 2 Waterproof covering to last 26 m 0 2 Cedar shingle secondary finish 26 m 0 Abutments/upstands 21 m 0 Glass roof to Douche: Safety glass roof approx 1.4m x 1.8m 1 nr 0 Abutment between glass and external wall 2 m 0 Detail to top of walls visible through glass roof 3 m 0 Infill roof structure and covering where high level chimney removed 1 item 0 Make good roof and refinish into new external walls where roof above 1 item 0 ground floor meets new first floor walls on north west corner Provisional Sum for refurbishment of existing roofs and rainwater goods 1 PS 0 Provisional Sum for extension of rainwater drainage system to new roofs 1 PS 0 0 £ - Page 14
  • 18. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Stairs and ramps - New stair from basement to first floor in 2 straight flights 1 item 0 Assumed specification: Stainless steel carriage with concealed fixings Timber treads and risers to match flooring Timber clad soffit following profile of treads and risers Glass balustrade with concealed fixings New external stair leading to first floor terrace 1 item 0 Assumed specification: Timber structure Timber treads and risers to match decking Balustrades to match timber clad external walls and including balustrade capping to match existing 0 £ - Page 15
  • 19. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ External walls - External wall, assumed specification: Studwork double wall framework 200mm high performance insulation Breathable membrane Battens Counter battens Cedar cladding Plasterboard lining Generally measured over door and window openings but not over screens 2 External wall 182 m 0 (measured over windows and doors - Contractor to allow extra for forming reveals if necessary) 2 Extra for curved work 23 m 0 Reveals to screens etc 71 m 0 2 New cladding to existing walls including battens, counter battens and 97 m 0 breather membrane 2 Extra for upgrading insulation to last 97 m 0 Reveals to screens etc 26 m 0 2 Insulation to concrete basement walls where not timber clad 100 m 0 0 £ - Page 16
  • 20. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Windows and external doors - Assumed specification unless otherwise stated: Slim line aluminium frames Double glazed units throughout, argon filled Low E glass Solar glare reducing coating to glass Sliding openers or tilt and turn (where single pane) Ultra slim line locking handles in stainless steel New windows as follows: WB.21 approx 3.05m x 1.50m high 1 nr 0 WB.07, 08, 09, 10, 11, 12 approx 0.56m x say 1.0m 6 nr 0 WG.02 approx 6.10m x 2.20m high 1 nr 0 Curved window/door composite comprising WG.03, 04, 05, 06, 07 1 nr 0 with curved glass and frames, WG.04 and 05 to slide Approx 9.0m wide around line of curve x 2.2m high WG.08 approx 1.0m x 2.2m high 1 nr 0 WG.09 approx 4.1m x 2.2m high 1 nr 0 WG.10 approx 4.5m x 2.2m high 1 nr 0 WG.14 approx 2.35m x 1.40m high 1 nr 0 WG.12 approx 6.4m x 4.5m high 1 nr 0 W1.01 approx 4.40m x 2.1m high 1 nr 0 W1.03 approx 3.8m x 2.1m high 1 nr 0 W1.04 approx 1.35m wide x full height of sloping internal soffit ie 1 nr 0 sloping head approx 2.1m up to 2.8m approx at highest point W1.05 approx 1.2m wide x full height internally ie 2.8m 1 nr 0 W1.06 ditto 1.4m x 2.8m 1 nr 0 W1.10 approx 1.1m x 1.1m 1 nr 0 Page 17
  • 21. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ 3 sided full height frameless fixed panels in front of W1.04-W1.06 1 nr 0 surrounding floor void on 3 sides approx 0.5m, 1.8m and 2.9m x 2.4m average height WG.14 approx 1.35m x 2.2m high 1 nr 0 New external doors as follows: DB.01 single door approx 0.95m x 2.10m high, solid timber clad 1 nr 0 Ditto - DG.02, 06, 07 and 08 assumed as DB.01 4 nr 0 WB.08 sliding pocket window/door approx 1.40m x 2.10m 1 nr 0 W1.02 approx 4.80m x 2.1m high, sliding patio door 1 nr 0 D1.08 sliding frameless glass door approx 1.1m x 2.1m 1 nr 0 Refurbish and overhaul existing windows and external doors as follows: WB.02, 03, 04 sliding pocket door 3 nr 0 WB.06 Salle de Bain 2 1 nr 0 WG.01 Bureau 1 nr 0 WG.11 Bureau 1 nr 0 DG.01 Entree 1 nr 0 W1.07 1 nr 0 W1.08 1 nr 0 Sliding shutters to WB.02-04 and WB.08 4 nr 0 approx 1.60m x 2.10m, pattern as drawing 233 Overhaul and refurbish existing sliding door gear to accommodate new 1 item 0 shutters Window boards, assume solid timber 12 m 0 Mastic sealant to all new and existing windows and external doors 1 item 0 0 £ - Page 18
  • 22. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Internal walls and partitions - Generally measured over door and window openings but not over screens 2 Partition in blockwork or studwork clad in plasterboard 106 m 0 (measured over windows and doors - Contractor to allow extra for forming reveals if necessary) 2 Extra for curved work 9 m 0 2 Double thickness partition in blockwork or studwork clad in plasterboard 59 m 0 (measured over windows and doors - Contractor to allow extra for forming reveals if necessary) 2 Ditto in masonry thickening to external wall in basement 7 m 0 south east corner adjacent Haman average thickness 600mm 0 £ - Internal doors - Door set consisting of spray lacquered flush door complete with frame and architrave , hung on 3 stainless steel hinges and including stainless steel lever handles and lock/latch/bathroom lock as appropriate : Approx 0.90m x 2.10m structural opening 15 nr 0 DB.03, 04, 05, 06, 07, 08, 09, 10 DG.03, 04, 05, 10 D1.01, 06, 07 Approx 1.10m x 2.10m structural opening 1 nr 0 DB.02 Sliding door set consisting of spray lacquered flush door with heavy duty door gear concealed within ceiling and complete with stainless steel flush pulls. Door to slide back fully into pocket in wall : Approx 1.10m x 2.10m structural opening 1 nr 0 DG.09 Approx 1.2m x 2.10m structural opening 2 nr 0 D1.02, 03 Page 19
  • 23. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Sliding door set consisting of acid etched glass with heavy duty stainless steel door gear and stainless steel flush pulls : Approx 0.90m x 2.10m structural opening 2 nr 0 D1.04, 05 Extra for bespoke stainless steel support to end of sliding track at 1 nr 0 junction with W1.04 Refurbish and overhaul DG.11, sliding door to Bureau 1 nr 0 WG.13 Internal window approx 4.3m x 2.2m high, assume fire rated 1 nr 0 clear glass 0 £ - Internal finishes - Wall finishes - Generally measured over door and window openings but not over screens 2 Plaster finish to new external walls 325 m 0 (measured over windows and doors - Contractor to allow extra for forming reveals if necessary) 2 Extra for curved work 23 m 0 2 Plaster finish to new partitions 336 m 0 (measured over windows and doors - Contractor to allow extra for forming reveals if necessary) 2 Extra for curved work 18 m 0 Allowance for stainless steel angle and stop beads 1 item 0 Form reveal to screens inc WG.13 etc 150 m 0 Extra for curved work 9 m 0 Page 20
  • 24. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Stone wall tiling/slabs to bathrooms: Supply only, assume Prime Cost Sum for supply of 100€/m2 110 m 2 0 Contractor to allow for all waste, overheads and profit 2 Ditto in cladding to cistern boxings, say 12 m 0 Ditto in cistern boxing tops not exceeding 300mm wide 10 m 0 2 Lay stone tiling on plaster or plywood base including adhesive, 110 m 0 ground and sealant inc Hamam benching and Douche 2 Ditto in cladding to cistern boxings, say 12 m 0 Ditto in cistern boxing tops not exceeding 300mm wide 10 m 0 2 Extra for flexible waterproof lining layer such as Bal tanking 110 m 0 2 Extra for additional layer of Marine plywood 110 m 0 2 Extra for separating membrane such as Ditra matting 110 m 0 0 £ - Page 21
  • 25. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Floor finishes - 2 75mm min screed 156 m 0 including incorporation of underfloor heating pipes (measured separately) NB existing floors may be timber and so new floors may also be timber in part or whole in which case this item should be amended and priced accordingly 2 Insulation to whole of basement floor to suit underfloor heating 178 m 0 2 Ditto ground floor 242 m 0 2 Ditto first floor 88 m 0 Parquet flooring: Supply only, assume Prime Cost Sum for supply of 100€/m2 461 m 2 0 Contractor to allow for all waste, overheads and profit 2 Lay parquet floor on screed or timber base 461 m 0 Stone flooring to bathrooms: Supply only, assume Prime Cost Sum for supply of 100€/m2 47 m 2 0 Contractor to allow for all waste, overheads and profit 2 Lay stone tiling on screed or timber base including adhesive, 47 m 0 ground and sealant including to Hamam and Douche 2 Extra for flexible waterproof lining layer such as Bal tanking 47 m 0 2 Extra for additional layer of Marine plywood should floors be timber 47 m 0 2 Extra for separating membrane such as Ditra matting 47 m 0 Extra for forming concealed shower gulley, assume Harmer or 8 nr 0 similar shower outlet fitted within concealed trough with stainless steel linear slot set into tiles above Provisional allowance for skirtings, various types 445 m 0 0 £ - Page 22
  • 26. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Ceiling finishes - 2 New plasterboard ceilings flat or sloping and including plaster finish 420 m 0 Assume first floor exposed timber roof soffit throughout 2 Matching timber soffit over stairwell at first floor 11 m 0 2 Ditto to outdoor kitchen 26 m 0 0 £ - Decorations - Decorate the following internally: 2 New and existing plastered walls 1,163 m 0 2 New ceilings 420 m 0 2 New and existing timber soffits 150 m 0 Decorations to timber trusses 1 item 0 New skirtings 445 m 0 Door frame and architrave sets 20 nr 0 Decorate the following externally: Generally measured over door and window openings but not over screens 2 Decorations to new cladding 280 m 0 (measured over windows and doors - Contractor to allow extra for forming reveals if necessary) Extra for reveals 97 item 0 2 Decorations to existing cladding, soffits and fascias 319 m 0 Decorations to timber trusses 1 item 0 Page 23
  • 27. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Decorate existing first floor Terrace pergola 1 item 0 Silcone sealant to all vertical and horizontal junctions between stone 1 item 0 and between stone and other finishes 0 £ - Page 24
  • 28. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Fittings, furnishings and equipment - Loose furniture and equipment, soft furnishings, blinds, beds and bedside tables -assume by Employer Assumed joinery specification unless otherwise stated: Spray lacquered MDF finish Doors and shelves to be adequate thickness to avoid bowing Robust stainless steel hinges or sliding gear to doors Soft close door and drawer mechanisms Profiled drawer and door edges to act as pulls Chambre 1 No new joinery Chambre 2 No new joinery Fireplace? - protect and retain 1 item 0 Chambre 3 Full height wardrobe approx 1.7m wide, assume 4 half width drawers 1 nr 0 internally and hanging rail full width, sliding doors Fireplace? - protect and retain 1 nr 0 Chambre 4 Full height wardrobe approx 1.7m wide, assume 4 half width drawers 1 nr 0 internally and hanging rail full width, sliding doors Chambre 5 Full height wardrobe approx 1.5m wide, assume 4 half width drawers 1 nr 0 internally and hanging rail full width, sliding doors Chambre 6 Full height wardrobe approx 1.4m wide, assume 4 half width drawers 1 nr 0 internally and hanging rail full width, 2nr hinged doors Bedhead storage unit approx 3.5m wide, assume open shelving say 1 nr 0 2.0m high Master Chambre No new joinery Page 25
  • 29. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Salle de Bain 1 Mirrored cabinet over basin say 0.60m x 0.30m x 1.0m 1 nr 0 Salle de Bain 2 Mirrored cabinet over basin say 0.60m x 0.30m x 1.0m 2 nr 0 Salle de Bain 3 Mirrored cabinet over basin say 0.60m x 0.30m x 1.0m 1 nr 0 Salle de Bain 4 Mirrored cabinet over basin say 0.60m x 0.30m x 1.0m 1 nr 0 Salle de Bain 5 Cistern boxing approx 2.5m wide for stone cladding (measured 1 nr 0 separately) Mirrored cabinet over basin and WC say 2.5mx 0.30m x 1.0m 1 nr 0 Salle de Bain 6 Cistern boxing approx 1.7m wide for stone cladding (measured 1 nr 0 separately) Mirrored cabinet over basin and WC say 1.7mx 0.30m x 1.0m 1 nr 0 WC 8 Cistern boxing approx 1.3m wide for stone cladding (measured 1 nr 0 separately) Mirrored cabinet over basin and WC say 0.6mx 0.30m x 1.0m 1 nr 0 Master Salle de Bain Vanity unit approx 3.0m wide x say 0.7m high with cupboards and 1 nr 0 stone top Mirrored cabinet over basin and WC say 3.0mx 0.30m x 1.0m 1 nr 0 Gymnase Full height wardrobe approx 4.1m wide, assume 4 full width drawers 1 nr 0 internally and 4 full width robust shelves, 6nr hinged doors Mirror, say 4.8m x 2.0m 1 nr 0 Salle de Jeux Full height wardrobe approx 3.0m wide, assume 4 full width drawers 1 nr 0 internally and 4 full width robust shelves, sliding doors Page 26
  • 30. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Haman Concrete benches to receive Mosaic tiling (measured separately) 2.15m maximum length 1 nr 0 2.30m min 1 nr 0 3.55m maximum length 1 nr 0 Vestaire Full height wardrobe approx 3.8m wide, assume full width shoe 1 nr 0 rack internally and full width hanging rail, sliding doors Entrance Hall adjacent DG.02 Full height wardrobe approx 2.8m wide, assume full width shoe 1 nr 0 rack internally and full width hanging rail, sliding doors Bureau Desk unit under window WG.01 approx 3.1m wide to match existing 1 nr 0 Bureau cabinet finish Salon No new joinery Salle a Manger Full height storage unit approx 2.7m wide, assume 50% cupboards and 1 nr 0 50% drawers at low level with open storage above Cinema Full height media storage unit approx 2.0m wide, assume open shelving 1 nr 0 TV cabinet approx 3.2m wide, say 0.7m high, assume 50% drawers 1 nr 0 and 50% cupboards Cuisine Provisional Sum for design, supply and installation of main kitchen 1 PS 0 including units, worktops, splashbacks, appliances and extract canopy Cuisine BBQ Provisional Sum for design, supply and installation of outdoor kitchen 1 PS 0 including units, worktops, splashbacks, appliances and extract canopy or chimney Page 27
  • 31. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Dressing Dressing unit approx 2.8m wide by say 2.9m high with sliding mirrored 1 nr 0 doors, assume full width hanging rail, 8nr drawers internally, extensive shelving and shoe rack Ditto approx 4.0m wide with 16nr drawers, large shoe rack and area 1 nr 0 0 £ - Page 28
  • 32. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Services - Sanitary appliances - Include the following Provisional Sums for the supply of sanitary fittings: Salle de Bain 1 WC complete 1 PS 600.00 600 Basin and taps complete 1 PS 600.00 600 Shower spray and handset, shower valve 1 PS 500.00 500 Shower floor gulley 1 PS 100.00 100 Shower tray Bespoke tiled shower tray - see Finishes Towel warmer 1 PS 500.00 500 Accessories such as towel rail, soap dish, mirror 1 PS 200.00 200 Salle de Bain 2 WC complete 1 PS 600.00 600 Basin and taps complete 1 PS 1200.00 1,200 Shower spray and handset, shower valve 1 PS 500.00 500 Shower floor gulley 1 PS 100.00 100 Shower tray Bespoke tiled shower tray - see Finishes Towel warmer 1 PS 500.00 500 Accessories such as towel rail, soap dish, mirror 1 PS 200.00 200 Salle de Bain 3 WC complete 1 PS 600.00 600 Basin and taps complete 1 PS 600.00 600 Shower spray and handset, shower valve 1 PS 500.00 500 Shower floor gulley 1 PS 100.00 100 Shower tray Bespoke tiled shower tray - see Finishes Towel warmer 1 PS 500.00 500 Accessories such as towel rail, soap dish, mirror 1 PS 200.00 200 Salle de Bain 4 WC complete 1 PS 600.00 600 Basin and taps complete 1 PS 600.00 600 Towel warmer 1 PS 500.00 500 Accessories such as towel rail, soap dish, mirror 1 PS 150.00 150 Page 29
  • 33. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Salle de Bain 5 WC complete with cistern frame 1 PS 800.00 800 Basin and taps complete 1 PS 600.00 600 Shower spray and handset, shower valve 1 PS 1000.00 1,000 Shower floor gulley 1 PS 100.00 100 Shower tray Bespoke tiled shower tray - see Finishes Towel warmer 1 PS 500.00 500 Accessories such as towel rail, soap dish, mirror 1 PS 200.00 200 Salle de Bain 6 WC complete with cistern frame 1 PS 800.00 800 Basin and taps complete 1 PS 600.00 600 Shower spray and handset, shower valve 1 PS 1000.00 1,000 Shower floor gulley 1 PS 100.00 100 Shower tray Bespoke tiled shower tray - see Finishes Towel warmer 1 PS 500.00 500 Accessories such as towel rail, soap dish, mirror 1 PS 200.00 200 Salle de Bain 7 WC complete with cistern frame 1 PS 800.00 800 Basin and taps complete 1 PS 600.00 600 Towel warmer 1 PS 500.00 500 Accessories such as towel rail, soap dish, mirror 1 PS 150.00 150 WC 8 WC complete with cistern frame 1 PS 800.00 800 Basin and taps complete 1 PS 600.00 600 Towel warmer 1 PS 500.00 500 Accessories such as towel rail, soap dish, mirror 1 PS 150.00 150 Douche Shower spray and handset, shower valve 1 PS 1500.00 1,500 Shower floor gulley 1 PS 100.00 100 Shower tray Bespoke tiled shower tray - see Finishes Accessories such as towel rail, soap dish, mirror 1 PS 50.00 50 Page 30
  • 34. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Master Salle de Bain WC complete with cistern frame 1 PS 800.00 800 Basin and taps complete 1 PS 2000.00 2,000 Free standing bath and taps complete 1 PS 5000.00 5,000 Shower spray and handset, shower valve 1 PS 2000.00 2,000 Shower floor gulley 1 PS 100.00 100 Shower tray Bespoke tiled shower tray - see Finishes Towel warmer 1 PS 1200.00 1,200 Accessories such as towel rail, soap dish, mirror 1 PS 300.00 300 Haman Steam generator 1 PS 1000.00 1,000 Shower floor gulley 1 PS 100.00 100 Fix only the following sanitary ware : WC suite with exposed cistern 4 nr 0 WC suite with concealed cistern frame and remote flush 5 nr 0 Basin and taps with waste and trap 11 nr 0 Shower spray and handset, shower valve 7 nr 0 Shower floor gulley 8 nr 0 Free standing bath and taps, trap and plinth 1 nr 0 Towel warmers (see Services for pipework) 10 nr 0 Steam generator (see Services for wiring and pipework) 1 nr 0 Provisional Sum for fixing accessories 1 PS 1000.00 1,000 Frameless glass shower screens: Approx 0.80m x 2.0m as door 4 nr 0 Approx 1.50m x 2.0m with 0.80m door and 0.70m fixed panel 1 nr 0 Assume Douche is open, no door or screen Silcone sealant to all joints between sanitary ware and adjacent finishes 1 nr 0 35,600 £ 35,600 Page 31
  • 35. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Mechanical installations - Contractor Designed Portion: Preliminaries and General Conditions 1 item 0 Isolation and stripping out existing installations 1 item 0 (measured separately) Boiler plant 1 item 0 Underfloor Heating Installation throughout including insulation, 1 item 0 manifolds reflectors etc. 0 Bathroom towel warmers 1 item New Cold Water Booster Set 1 item 0 Cold Water Installation including kitchen supplies 1 item 0 Hot Water Installation including kitchen supplies 1 item 0 Kitchen ventilation (extract hood by kitchen supplier) 1 item 0 Bathroom ventilation 1 item 0 Gas services to fireplaces and to kitchen appliances 1 item 0 Thermal insulation to all pipework 1 item 0 Above ground drainage installation 1 item 0 Controls and Associated Wiring 1 item 0 Mechanical and Plumbing testing and commissioning 1 item 0 Provision of record documents 1 item 0 Provision of design and installation drawings and design information 1 item 0 Provision of working drawings 1 item 0 Page 32
  • 36. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Design of all services 1 item 0 Any mechanical or plumbing items not listed above 1 item 0 Builders work in connection with mechanical services 1 item 0 0 £ - Page 33
  • 37. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Electrical installations - Contractor Designed Portion: Preliminaries and General Conditions 1 item 0 Isolation and stripping out existing installations 1 item 0 (measured separately) Switchgear and sub-mains 1 item 0 Small power installation including accessories 1 item 0 Fire and smoke alarm systems 1 item 0 Security Alarm 1 item 0 Earthing and Bonding 1 item 0 Supply of light fittings, transformers, lamps etc 1 item 0 Installation of light fittings, transformers, lamps etc 1 item 0 Specialist lighting control and audio visual package including all equipment, 1 PS 0 supply of specialist cables and termination of cables. Provisional Sum Installation of the following free issue cabling 0 Speaker cable 1 item 0 Satelite cable 1 item 0 Lutron cable 1 item 0 Cat 6 structured cabling 1 item 0 Door entry data control cable 1 item 0 Supply and install all power cabling and mains connections etc 1 item 0 Liaison and attendance including but not limited to attendance at meetings 1 item 0 with lighting control/audio visual specialist, provision of site welfare, rubbish clearance, use of standing scaffolding etc Page 34
  • 38. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ Power to kitchen appliances 1 item 0 External Lighting Supply of light fittings, transformers, lamps etc 1 item 0 Installation of light fittings, transformers, lamps etc 1 item 0 Electrical wiring in connection with mechanical systems 1 item 0 Electrical testing and commissioning 1 item 0 Provision of record documents 1 item 0 Provision of design and installation drawings and design information 1 item 0 Provision of working drawings 1 item 0 Design of all services 1 item 0 Any electrical items not listed above 1 item 0 Builders work in connection with electrical services 1 item 0 0 0 £ - Lift and conveyor installations - N/A 0 £ - Special installations - Mechanical Services in connection with the Pool Installation 1 item Electrical Services in connection with the Pool Installation 1 item 0 £ - Complete buildings and building units - N/A 0 £ - Page 35
  • 39. VILLA RICHARDSON QUANTIFIED FRAMEWORK FOR ORDER OF COST ESTIMATE ALL QUANTITIES ARE APPROXIMATE Total Cost of Group Element/Element Qty Unit Rate Cost Element £ £ External works - Generally - Provisional Sum for removing any existing concrete piers as required 1 PS 0 for basement or pool excavation Work to boundary walls and garden walls adjoining the house 1 PS 0 cannot be determined at this stage. Provisional Sum for alteration, extension, re-cladding as required Works to the driveways cannot be determined at this stage. 1 PS 0 Provisional Sum for extension and alteration and for making good following basement excavation Landscaping - By Employer Swimming Pool: Pool shell 20m x 5.8m plus new steps 2.5m x 1.75m Depth not noted, assume 1.2m minimum graduating to 2.5m deep at diving area Waterproofing Carrelage Warm tiling to pool and steps 30cm x 60cm 1 item 0 New pool plant Pool plant room and access Diving board Pool cover Builders work in connection with pool eg trenches, holes etc 1 item 0 Stone wall to hill side forming infinity edge to long side of pool 1 item 0 3 Extra for excavating in rock, say 150 m 0 3 Filling to make up levels, assume crushing and compacting 100 m 0 rock from basement/pool excavations, say Disposal of ground water 1 item 0 Disposal of surface water 1 item 0 2 Extend sub structure for deck 210 m 0 2 New decking 210 m 0 Page 36