Trabajo 02 - METRADOS DE ARQUITECTURA Y ESTRUCTURAS
1.
2. Propietario : Hoja :
Fecha : Plano : Versión :
Hecho por : Revisado :
Largo Ancho Altura
01.00 MUROS Y TABIQUES DE ALBAÑILERIA
01.01 MUROS DE LADRILLO DE ARCILLA
01.01.01 MURO DE LADRILLO SOGA MEZC. C:A 1:5 135.24 M2
1º PISO
EJE A-A 2.00 4.06 2.50 20.30
1.00 3.50 2.50 8.75
EJE B-B 2.00 5.20 2.20 22.88
2º PISO
EJE 3-3 1.00 5.80 2.40 13.92
EJE A-A 2.00 4.06 2.40 19.49
EJE B-B 2.00 4.06 2.20 17.86
SS.HH. 1.00 7.35 2.40 17.64
EN MUROS DE TIMPANO 2.00 8.00 0.50 1.80 14.40
01.01.02 MURO DE LADRILLO CABEZA MEZC. C:A 1:5 66.89 M2
1º PISO
EJE 1-1 Y 4-4 2.00 6.85 2.50 34.25
2º PISO
EJE 1-1 Y 4-4 2.00 6.80 2.40 32.64
02.00 REVOQUES, ENLUCIDOS Y MOLDURAS
02.01 TARRAJEO PRIMARIO RAYADO 25.68 M2
SS.HH. 2.00 5.35 2.40 25.68
02.02 TARRAJEO EN MUROS INTERIORES Y EXTERIORES 187.73 M2
1º PISO
EJE A-A 2.00 4.06 2.50 20.30
1.00 3.50 2.50 8.75
EJE B-B 2.00 5.20 2.20 22.88
EJE 1-1 Y 4-4 2.00 6.85 2.50 34.25
2º PISO
EJE 1-1 Y 4-4 2.00 6.80 2.40 32.64
EJE 3-3 1.00 5.80 2.40 13.92
EJE A-A 2.00 4.06 2.40 19.49
EJE B-B 2.00 4.06 2.20 17.86
SS.HH. 1.00 7.35 2.40 17.64
02.04 TARRAJEO DE COLUMNAS
02.04.01 TARRAJEO DE COLUMNAS - SUPERFICIES 75.46 M2
1º PISO 8.00 0.35 0.25 3.43 2.40
COLUMNETAS 18.00 0.15 0.10 2.20 0.59
2º PISO 8.00 0.35 0.25 2.60 1.82
COLUMNETAS 22.00 0.15 0.10 2.20 0.73
PLACAS DE ESCALERA 8.00 1.15 7.60 69.92
02.05 TARRAJEO DE VIGAS
02.05.01 TARRAJEO DE VIGAS - SUPERFICIES 50.96 M2
EJE 1-1 Y 4-4 2.00 6.80 0.30 4.08
EJE 2-2 y 3-3 2.00 6.80 0.75 10.20
VOLADIZO 4.00 1.20 0.35 1.68
EJE A-A, B-B 4.00 3.80 0.30 4.56
2.00 3.70 0.30 2.22
FRISO 2.00 12.50 0.20 5.00
2.00 9.20 0.20 3.68
2º PISO
EJE 1-1, 4-4 2.00 6.80 0.30 4.08
EJE A-A, B-B 4.00 3.80 0.30 4.56
2.00 3.70 0.30 2.22
FRISO 2.00 12.50 0.20 5.00
2.00 9.20 0.20 3.68
02.06 VESTIDURAS
02.06.01 VESTIDURA DE DERRAMES CON CEMENTO 178.73 ML.
Unidad
Obra :
VIVIENDA UNIFAMILIAR
MedidasN° de
Veces
Especificaciones
Partida
N°
Parcial Total
HOJA DE METRADOS
..de..
ARQUITECTURA
Ing. Omar Hidalgo Quispe
Ing. Omar Hidalgo Quispe
01/10/2005
LLANTOY ZEVALLOS JOSE ANTONIO
Preparado por Omar 01/10/2015 Página 1
3. Propietario : Hoja :
Fecha : Plano : Versión :
Hecho por : Revisado :
Largo Ancho Altura
Unidad
Obra :
VIVIENDA UNIFAMILIAR
MedidasN° de
Veces
Especificaciones
Partida
N°
Parcial Total
HOJA DE METRADOS
..de..
ARQUITECTURA
Ing. Omar Hidalgo Quispe
Ing. Omar Hidalgo Quispe
01/10/2005
LLANTOY ZEVALLOS JOSE ANTONIO
PUERTA 01 8.00 5.90 47.20
PUERTA 02 2.00 5.70 11.40
VENTANA 01 4.00 8.48 33.92
VENTANA 02 3.00 3.86 11.58
VENTANA 03 1.00 3.90 3.90
VENTANA 04 1.00 3.70 3.70
VENTANA 05 1.00 3.15 3.15
VENTANA 06 3.00 15.36 46.08
VENTANA 07 2.00 5.70 11.40
VENTANA 08 2.00 3.20 6.40
02.07 ENCHAPES
02.07.01 ENCHAPE CON CERAMICO 0.20x0.30 25.68 M2
SS.HH. 2.00 5.35 2.40 25.68
02.08 BRUÑAS
02.08.01 BRUÑAS PERIMETRALES 1.00 136.00 136.00 136.00 ML
03.00 CIELORRASOS
03.01 CIELORASO CON MEZCLA
03.01.01 TARRAJEO CON MEZCLA SOBRE CIELO RASO 123.20 M2
S.U.M. 1.00 12.00 7.70 92.40
VOLADIZO 1.00 13.00 1.20 15.60
TECHO DE ESCALERA 1.00 15.20 1.00 15.20
03.02 CIELORRASOS SUSPENDIDOS
03.02.01 CON BALDOSAS
03.02.01.01 CIELO RASO CON BALDOSA DE FIBRA MINERAL 1.00 13.70 10.70 146.59 146.59 M2
04.00 PISOS Y PAVIMENTOS
04.01 CONTRAPISOS
04.01.01 CONTRAPISO DE CEMENTO 111.99 M2
S.U.M. 1.00 12.00 7.70 92.40
SS.HH. 2.00 1.90 1.05 3.99
PASADIZO 1.00 13.00 1.20 15.60
04.02 PISOS
04.02.01 PISO DE CERAMICO
04.02.01.01 PISO DE CERAMICO 0.30x0.30 4.20 M2
SS.HH. 2.00 2.00 1.05 4.20
04.02.02 PISO DE MADERA
04.03.01 PISO DE MADERA MACHIHEMBRADA 102.00 M2
OFICINAS 1.00 8.35 8.00 66.80
SALA DE ESPERA, SECRET. Y OF. PRINCIPAL 1.00 8.00 4.40 35.20
04.03 PISO CONCRETO
04.03.01 PISO DE CEMENTO PULIDO 10.63 M2
PASADIZO 1.00 8.50 1.25 10.63
04.03.01 PISO DE CEMENTO COLOREADO 92.40 M2
S.U.M. 1.00 12.00 7.70 92.40
04.04 VEREDAS
04.04.01 VEREDA DE E=4" 47.60 M2
PARTE FRONTAL Y POSTERIOR 2.00 13.70 1.50 41.10
LATERAL 1.00 6.50 1.00 6.50
05.00 CONTRAZOCALOS
05.01 DE MADERA
05.01.01 CONTRAZOCALO DE MADERA CEDRO 68.42 ML
OFICINAS, SALA DE ESPERA Y SECRETARIA 1.00 68.42 68.42
06.00 CARPINTERIA DE MADERA
06.01 PUERTAS
06.01.01 PUERTA APANELADA P01 8.00 8.00 8.00 UND
06.01.02 PUERTA APANELADA P02 2.00 2.00 2.00 UND
06.02 VENTANAS 50.61 M2
VENTANA 01 4.00 2.76 1.48 16.34
Preparado por Omar 01/10/2015 Página 2
4. Propietario : Hoja :
Fecha : Plano : Versión :
Hecho por : Revisado :
Largo Ancho Altura
Unidad
Obra :
VIVIENDA UNIFAMILIAR
MedidasN° de
Veces
Especificaciones
Partida
N°
Parcial Total
HOJA DE METRADOS
..de..
ARQUITECTURA
Ing. Omar Hidalgo Quispe
Ing. Omar Hidalgo Quispe
01/10/2005
LLANTOY ZEVALLOS JOSE ANTONIO
VENTANA 02 3.00 0.60 1.33 2.39
VENTANA 03 2.00 3.90 0.48 3.74
VENTANA 04 1.00 3.70 0.48 1.78
VENTANA 05 1.00 3.15 0.48 1.51
VENTANA 06 3.00 0.99 6.68 19.84
VENTANA 07 2.00 1.50 1.35 4.05
VENTANA 08 2.00 1.20 0.40 0.96
07.00 CARPINTERIA METALICA Y HERRER.
07.01 ELEMENTOS METALICOS ESPECIALES
07.01.01 BARANDA METALICA 12.55 ML
EN PARAPETO 1.00 7.60 7.60
EN ESCALERA 1.00 4.95 4.95
08.00 VIDRIOS, CRISTALES Y SIMILARES
08.01 VIDRIOS Y CRISTALES
08.01.01 VIDRIO DE COLOR SEMIDOBLE 551.20 P2
V-1 4.00 2.76 10.89 1.48 177.93
V-2 3.00 0.60 10.89 1.33 26.07
V-3 2.00 3.90 10.89 0.48 40.77
V-4 1.00 3.70 10.89 0.48 19.34
V-5 1.00 3.15 10.89 0.48 16.47
V-6 3.00 0.99 10.89 6.68 216.05
V-7 2.00 1.50 10.89 1.35 44.10
V-8 2.00 1.20 10.89 0.40 10.45
09.00 PINTURA
09.01 DE CIELORRASOS, MUROS Y OTROS
09.01.01 PINTURA EN VIGAS Y COLUMNAS 126.42 M2
SUPERFICIE DE COLUMNAS
1º PISO 8.00 0.35 0.25 3.43 2.40
COLUMNETAS 18.00 0.15 0.10 2.20 0.59
2º PISO 8.00 0.35 0.25 2.60 1.82
COLUMNETAS 22.00 0.15 0.10 2.20 0.73
PLACAS DE ESCALERA 8.00 1.15 7.60 69.92
SUPERFICIE DE VIGAS
EJE 1-1 Y 4-4 2.00 6.80 0.30 4.08
EJE 2-2 y 3-3 2.00 6.80 0.75 10.20
VOLADIZO 4.00 1.20 0.35 1.68
EJE A-A, B-B 4.00 3.80 0.30 4.56
2.00 3.70 0.30 2.22
FRISO 2.00 12.50 0.20 5.00
2.00 9.20 0.20 3.68
2º PISO
EJE 1-1, 4-4 2.00 6.80 0.30 4.08
EJE A-A, B-B 4.00 3.80 0.30 4.56
2.00 3.70 0.30 2.22
FRISO 2.00 12.50 0.20 5.00
2.00 9.20 0.20 3.68
09.01.02 PINTURA EN MUROS INTERIORES Y EXTERIORES 187.73 M2
1º PISO
EJE A-A 2.00 4.06 2.50 20.30
1.00 3.50 2.50 8.75
EJE B-B 2.00 5.20 2.20 22.88
EJE 1-1 Y 4-4 2.00 6.85 2.50 34.25
2º PISO
EJE 1-1 Y 4-4 2.00 6.80 2.40 32.64
EJE 3-3 1.00 5.80 2.40 13.92
EJE A-A 2.00 4.06 2.40 19.49
EJE B-B 2.00 4.06 2.20 17.86
Preparado por Omar 01/10/2015 Página 3
5. Propietario : Hoja :
Fecha : Plano : Versión :
Hecho por : Revisado :
Largo Ancho Altura
Unidad
Obra :
VIVIENDA UNIFAMILIAR
MedidasN° de
Veces
Especificaciones
Partida
N°
Parcial Total
HOJA DE METRADOS
..de..
ARQUITECTURA
Ing. Omar Hidalgo Quispe
Ing. Omar Hidalgo Quispe
01/10/2005
LLANTOY ZEVALLOS JOSE ANTONIO
SS.HH. 1.00 7.35 2.40 17.64
09.01.04 PINTURA CON ESMALTE 12.55 M2
EN PARAPETO 1.00 7.60 7.60
EN ESCALERA 1.00 4.95 4.95
10.00 VARIOS, LIMPIEZA, JARDINERIA
10.01 LIMPIEZA CONSTANTE DE OBRA 1.00 13.70 10.70 146.59 146.59 M2
Preparado por Omar 01/10/2015 Página 4
6. Propietario : Hoja :
Fecha : Plano : Versión :
Hecho por : Revisado :
Largo Ancho Altura
01.00 OBRAS PROVISIONALES
01.01 CONSTRUCCIONES PROVISIONALES
01.01.01 CARTEL DE IDENTIFICACION DE OBRA 1.00 1.00 1.00 UND
01.01.02 ALQUILER DE ALMACEN Y GUARDIANIA 3.00 3.00 3.00 mes
02.00 TRABAJOS PRELIMINARES
02.01 LIMPIEZA DE TERRENO
02.01.01 LIMPIEZA DE TERRENO 1.00 13.70 10.70 146.59 146.59 M2
02.02 TRAZOS NIVELES Y REPLANTEO
02.02.01 TRAZOS, NIVELES Y REPLANTEO PRELIMINAR 1.00 13.70 10.70 146.59 146.59 M2
02.02.02 TRAZO Y REPLANTEO DURANTE EL PROCESO 1.00 13.70 10.70 146.59 146.59 M2
03.00 MOVIMIENTO DE TIERRAS
03.01 NIVELACION DEL TERRENO
03.01.01 NIVELACION MANUAL DEL TERRENO 1.00 13.70 10.70 0.25 36.65 36.65 M3
03.02 EXCAVACIONES
03.02.01 EXCAVACION DE ZANJAS 17.08 M3
EJE 1-1 Y 4-4 2.00 6.85 0.40 1.00 5.48
EJE A-A 2.00 4.33 0.40 1.00 3.46
1.00 3.70 0.40 1.00 1.48
EJE B-B 2.00 5.85 0.40 1.00 4.68
ESCALERA 1.00 4.95 0.40 1.00 1.98
03.02.02 EXCAVACION PARA ZAPATAS 37.68 M3
Z-01 4.00 1.85 1.45 2.05 22.00
Z-02 2.00 1.70 1.30 2.05 9.06
Z-03 2.00 1.70 0.95 2.05 6.62
03.03 RELLENOS
03.03.01 RELLENO Y COMPACTADO CON MATERIAL PROPIO 12.58 M3.
EJE 1-1 Y 4-4 2.00 5.95 0.35 0.15 0.62
EJE A-A 1.00 4.00 0.35 0.15 0.21
1.00 3.10 0.35 0.15 0.16
1.00 2.60 0.35 0.15 0.14
EJE B-B 1.00 2.80 0.35 0.15 0.15
1.00 2.70 0.35 0.15 0.14
1.00 2.50 0.35 0.15 0.13
ZAPATA - 01 4.00 1.85 1.45 0.60 6.44
ZAPATA - 02 2.00 1.70 1.30 0.60 2.65
ZAPATA - 03 2.00 1.70 0.95 0.60 1.94
03.04 ELIMINACIONES
03.04.01 ELIMINACION DE MATERIAL EXCEDENTE 83.77 M3
DE EXCAVACIONES
DE ZANJAS 1.30 17.08 22.21
DE ZAPATAS 1.30 37.68 48.98
(menos el relleno con material propìo) 1.00 12.58 12.58
04.00 OBRAS DE CONCRETO SIMPLE
04.01 CIMIENTOS CORRIDOS
04.01.01 CONCRETO CIMIENTO CORRIDO - Cº CICLOPEO 1:10 + 30% P.G. 17.08 M3
EJE 1-1 Y 4-4 2.00 6.85 0.40 1.00 5.48
EJE A-A 2.00 4.33 0.40 1.00 3.46
1.00 3.70 0.40 1.00 1.48
EJE B-B 2.00 5.85 0.40 1.00 4.68
ESCALERA 1.00 4.95 0.40 1.00 1.98
04.02 SOLADOS
04.02.01 FALSA ZAPATA C:H 1:10 + 30% P.G. 15.62 M3
Z-01 4.00 1.85 1.45 0.85 9.12
Z-02 2.00 1.70 1.30 0.85 3.76
Z-03 2.00 1.70 0.95 0.85 2.75
04.02.02 FALSA CIMENTACION C:H 1:10 + 30% P.G. 3.55 M3
EJE 1-1 Y 4-4 2.00 5.95 0.60 0.20 1.43
HOJA DE METRADOS
..de..
ESTRUCTURAS
Ing. Omar Hidalgo Quispe
Ing. Omar Hidalgo Quispe
01/10/2005
LLANTOY ZEVALLOS JOSE ANTONIO
Unidad
Obra :
VIVIENDA UNIFAMILIAR
MedidasN° de
Veces
Especificaciones
Partida
N°
Parcial Total
Preparado por Omar 01/10/2015 Página 1
8. Propietario : Hoja :
Fecha : Plano : Versión :
Hecho por : Revisado :
Largo Ancho Altura
HOJA DE METRADOS
..de..
ESTRUCTURAS
Ing. Omar Hidalgo Quispe
Ing. Omar Hidalgo Quispe
01/10/2005
LLANTOY ZEVALLOS JOSE ANTONIO
Unidad
Obra :
VIVIENDA UNIFAMILIAR
MedidasN° de
Veces
Especificaciones
Partida
N°
Parcial Total
COLUMNETAS 22.00 2.00 2.20 0.56 54.21 KG.
PLACAS DE ESCALERA 4.00 6.00 8.85 0.99 210.28 KG.
4.00 45.00 0.95 0.56 95.76
05.02.03 COLUMNAS - CONCRETO F'C=210 KG/Cm2 38.17 M3
1º PISO 8.00 0.35 0.25 3.43 2.40
COLUMNETAS 18.00 0.15 0.10 2.20 0.59
2º PISO 8.00 0.35 0.25 2.50 1.75
COLUMNETAS 22.00 0.15 0.10 2.50 0.83
PLACAS DE ESCALERA 4.00 1.00 8.15 32.60
05.03 VIGAS
05.03.01 VIGA DE CIMENTACION - ENCOFRADO Y DESENCOFRADO 14.00 M2
EJE 1-1 Y 4-4 2.00 8.00 0.35 5.60
EJE A-A y B-B 2.00 12.00 0.35 8.40
05.03.02 VIGA DE CIMENTACION - ACERO F'y=4,200 Kg/cm2 343.63
EJE 1-1 Y 4-4 Ø 1/2" 2.00 8.00 6.00 1.02 97.92 KG.
ESTRIBOS Ø 3/8" 2.00 30.00 1.20 0.58 41.76 KG.
EJE A-A y B-B Ø 1/2" 2.00 12.00 6.00 1.02 146.88 KG.
ESTRIBOS Ø 3/8" 2.00 41.00 1.20 0.58 57.07 KG.
05.03.03 VIGADE CIMENTACION - CONCRETO F'c=210 Kg/cm2 3.50 M3
EJE 1-1 Y 4-4 2.00 8.00 0.25 0.35 1.40
EJE A-A y B-B 2.00 12.00 0.25 0.35 2.10
05.03.04 VIGAS - ENCOFRADO Y DESENCOFRADO 90.19 M2
1º PISO
EJE 1-1 1.00 9.20 0.50 4.60
EJE 2-2 1.00 9.80 0.60 5.88
1.00 9.80 0.30 2.94
EJE 3-3 1.00 9.20 0.60 5.52
1.00 9.20 0.30 2.76
EJE 4-4 1.00 9.20 0.50 4.60
EJE A-A 2.00 11.50 0.20 4.60
2.00 11.50 0.30 6.90
EJE B-B 2.00 12.50 0.20 5.00
2.00 12.50 0.30 7.50
VIGUETAS 2.00 12.50 0.20 5.00
FRISO 2.00 12.50 0.20 5.00
2º PISO 0.00
EJE 1-1, 4-4 2.00 8.00 0.50 8.00
EJE A-A, B-B 2.00 12.00 0.20 4.80
2.00 12.00 0.30 7.20
VIGA DE TECHO DE ESCALERA 1.00 4.95 0.25 1.24
1.00 14.60 0.25 3.65
FRISO 2.00 12.50 0.20 5.00
05.03.05 VIGAS - ACERO F'y=4,200 Kg/cm2 1,383.68
1º PISO
EJE 1-1 Ø 5/8" 1.00 9.50 4.00 1.56 59.28 KG.
Ø 5/8" 1.00 2.10 2.00 1.56 6.55 KG.
Ø 5/8" 1.00 3.28 2.00 1.56 10.23 KG.
ESTRIBOS Ø 3/8" 1.00 1.20 55.00 0.58 38.28 KG.
EJE 2-2 Ø 5/8" 1.00 10.20 7.00 1.56 111.38 KG.
Ø 5/8" 1.00 2.73 2.00 1.56 8.52 KG.
Ø 5/8" 1.00 4.80 2.00 1.56 14.98 KG.
Ø 5/8" 1.00 3.35 2.00 1.56 10.45 KG.
ESTRIBOS Ø 3/8" 1.00 1.50 60.00 0.58 52.20 KG.
EJE 3-3 Ø 5/8" 1.00 9.60 7.00 1.56 104.83 KG.
Ø 5/8" 1.00 2.35 2.00 1.56 7.33 KG.
Ø 5/8" 1.00 4.80 2.00 1.56 14.98 KG.
Ø 5/8" 1.00 3.35 2.00 1.56 10.45 KG.
Preparado por Omar 01/10/2015 Página 3
9. Propietario : Hoja :
Fecha : Plano : Versión :
Hecho por : Revisado :
Largo Ancho Altura
HOJA DE METRADOS
..de..
ESTRUCTURAS
Ing. Omar Hidalgo Quispe
Ing. Omar Hidalgo Quispe
01/10/2005
LLANTOY ZEVALLOS JOSE ANTONIO
Unidad
Obra :
VIVIENDA UNIFAMILIAR
MedidasN° de
Veces
Especificaciones
Partida
N°
Parcial Total
ESTRIBOS Ø 3/8" 1.00 1.50 55.00 0.58 47.85 KG.
EJE 4-4 Ø 5/8" 1.00 9.50 4.00 1.56 59.28 KG.
Ø 5/8" 1.00 2.10 2.00 1.56 6.55 KG.
Ø 5/8" 1.00 3.28 2.00 1.56 10.23 KG.
ESTRIBOS Ø 3/8" 1.00 1.20 55.00 0.58 38.28 KG.
EJE A-A Ø 1/2" 1.00 12.90 4.00 1.02 52.63 KG.
Ø 1/2" 1.00 1.05 2.00 1.02 2.14 KG.
Ø 1/2" 1.00 2.65 2.00 1.02 5.41 KG.
Ø 1/2" 1.00 1.15 2.00 1.02 2.35 KG.
Ø 1/2" 1.00 2.60 1.00 1.02 2.65 KG.
ESTRIBOS Ø 3/8" 1.00 1.00 77.00 0.58 44.66 KG.
EJE B-B Ø 1/2" 1.00 13.90 4.00 1.02 56.71 KG.
Ø 1/2" 1.00 2.05 1.00 1.02 2.09 KG.
Ø 1/2" 1.00 1.05 1.00 1.02 1.07 KG.
Ø 1/2" 1.00 2.65 2.00 1.02 5.41 KG.
Ø 1/2" 1.00 1.15 2.00 1.02 2.35 KG.
Ø 1/2" 1.00 2.60 1.00 1.02 2.65 KG.
ESTRIBOS Ø 3/8" 1.00 1.00 85.00 0.58 49.30 KG.
VIGUETAS Ø 3/8" 1.00 13.90 2.00 0.58 16.12 KG.
2º PISO
EJE 1-1, 4-4 Ø 1/2" 2.00 8.40 4.00 1.02 68.54 KG.
Ø 1/2" 2.00 2.10 2.00 1.02 8.57 KG.
Ø 1/2" 2.00 3.28 2.00 1.02 13.38 KG.
ESTRIBOS Ø 3/8" 2.00 1.20 48.00 0.58 66.82 KG.
EJE A-A, B-B Ø 1/2" 2.00 12.90 4.00 1.02 105.26 KG.
Ø 1/2" 2.00 1.05 2.00 1.02 4.28 KG.
Ø 1/2" 2.00 2.65 2.00 1.02 10.81 KG.
Ø 1/2" 2.00 1.15 2.00 1.02 4.69 KG.
Ø 1/2" 2.00 2.60 1.00 1.02 5.30 KG.
ESTRIBOS Ø 3/8" 2.00 1.00 77.00 0.58 89.32 KG.
VIGA DE TECHO DE ESCALERA Ø 1/2" 1.00 5.35 4.00 1.02 21.83 KG.
Ø 1/2" 1.00 1.15 2.00 1.02 2.35 KG.
Ø 1/2" 1.00 3.60 1.00 1.02 3.67 KG.
ESTRIBOS Ø 3/8" 2.00 1.00 25.00 0.58 29.00 KG.
VIGA CIRCULAR Ø 1/2" 1.00 15.60 4.00 1.02 63.65 KG.
ESTRIBOS Ø 3/8" 2.00 1.00 25.00 0.58 29.00 KG.
05.03.06 VIGAS - CONCRETO F'c=210 Kg/cm2 12.60 M3
1º PISO
EJE 1-1 1.00 9.20 0.25 0.50 1.15 M3
EJE 2-2 1.00 9.80 0.30 0.50 1.47 M3
EJE 3-3 1.00 9.20 0.30 0.50 1.38 M3
EJE 4-4 1.00 9.20 0.25 0.50 1.15 M3
EJE A-A 2.00 11.50 0.30 0.20 1.38 M3
EJE B-B 2.00 12.50 0.30 0.20 1.50 M3
VIGUETAS 2.00 12.50 0.15 0.20 0.75 M3
2º PISO
EJE 1-1, 4-4 2.00 8.00 0.25 0.35 1.40 M3
EJE A-A, B-B 2.00 12.00 0.30 0.20 1.44 M3
VIGA DE TECHO DE ESCALERA 1.00 4.95 0.25 0.20 0.25 M3
1.00 14.60 0.25 0.20 0.73 M3
05.04 LOSAS
05.04.01 LOSAS ALIGERADAS
05.04.01.01 LOSA ALIGERADA - ENCOFRADO Y DESENCOFRAD 123.20 M2
S.U.M. 1.00 12.00 7.70 92.40
VOLADIZO 1.00 13.00 1.20 15.60
TECHO DE ESCALERA 1.00 15.20 1.00 15.20
05.04.01.02 LOSA ALIGERADA - ACERO F'y=4,200 Kg/cm2 782.24
Preparado por Omar 01/10/2015 Página 4
10. Propietario : Hoja :
Fecha : Plano : Versión :
Hecho por : Revisado :
Largo Ancho Altura
HOJA DE METRADOS
..de..
ESTRUCTURAS
Ing. Omar Hidalgo Quispe
Ing. Omar Hidalgo Quispe
01/10/2005
LLANTOY ZEVALLOS JOSE ANTONIO
Unidad
Obra :
VIVIENDA UNIFAMILIAR
MedidasN° de
Veces
Especificaciones
Partida
N°
Parcial Total
VIGUETAS 1.00 24.00 14.10 0.99 335.02 KG.
2.00 24.00 1.30 0.56 34.94
2.00 24.00 2.35 0.99 111.67
ACERO TEMPERATURA 1.00 53.00 10.70 0.26 147.45 KG.
1.00 43.00 13.70 0.26 153.17
05.04.01.03 LOSA ALIGERADA CONCRETO F'c=210 Kg/cm2 10.50 M3
VIGUETAS 48.00 3.80 0.10 0.15 2.74
24.00 3.70 0.10 0.15 1.33
23.00 0.80 0.10 0.15 0.28
LOSA E= 0.05m 1.00 12.00 7.70 0.05 4.62
1.00 13.00 1.20 0.05 0.78
1.00 15.20 1.00 0.05 0.76
05.04.01.04 LOSA ALIGERADA - LADRILLO HUECO 933.08 UND
S.U.M 2.00 7.95 3.55 8.33 470.19
1.00 7.90 3.50 8.33 230.32
VOLADIZO 2.00 1.20 3.55 8.33 70.97
1.00 1.20 3.50 8.33 34.99
TECHO DE ESCALERA 1.00 15.20 1.00 8.33 126.62
05.05 ESCALERAS
05.05.01 ESCALERA ENCOFRADO DESENCOFRADO 11.27 M2
FONDO DE ESCALERA 1.00 4.95 1.20 5.94
CONTRAPASO 16.00 1.20 0.20 3.84
LATERAL IZQUIERDO 1.00 4.95 0.30 1.49
05.05.02 ESCALERA ACERO F'y=4,200 Kg/cm2 99.54
ACERO LONGITUDINAL 1.00 7.00 5.75 0.99 39.85 KG.
1.00 6.00 2.00 0.99 11.88
1.00 6.00 1.80 0.99 10.69
ACERO TRANSVERSAL 1.00 25.00 1.50 0.99 37.13 KG.
05.05.03 ESCALERA - CONCRETO F'c=210 Kg/cm2 2.28 M3
ZAPATA 1.00 1.20 0.50 0.80 0.48
GARGANTA 1.00 4.95 1.20 0.15 0.89
DESCANZO 2.00 1.20 1.00 0.20 0.48
CONTRAPAZOS 8.00 1.20 0.25 0.18 0.43
05.06 PLACAS DE CONCRETO
05.06.01 PLACA DE ESCALERA - ENCOFRADO DESENCOFRADO 8.00 0.99 7.73 61.22 61.22 M2
05.06.02 PLACA DE ESCALERA - ACERO F'y=4,200 Kg/cm2 911.73
ACERO LONGITUDINAL Ø 1/2" 9.35 47.00 1.02 448.24 KG.
ACERO TRANSVERSAL Ø 1/2" 1.00 11.36 40.00 1.02 463.49 KG.
05.06.03 PLACA DE ESCALERA - CONCRETO F'c=210 Kg/cm2 12.20 M3
PLACA TIPO CIRCULAR 1.00 10.36 0.15 7.85 12.20
05.07 MUROS DE CONTENCIÓN
05.07.01 MURO DE CONTENCION - ENCOFRADO DESENCOFRADO 1.00 14.40 1.90 27.36 27.36 M2
05.07.02 MURO DE CONTENCION - ACERO F'y=4,200 Kg/cm2 288.26 KG.
EN PANTALLA
ACERO LONGITUDINAL Ø 3/8" 2.00 2.15 30.00 0.58 74.82 KG.
1.00 0.85 30.00 0.58 14.79
ACERO TRANSVERSAL Ø 3/8" 1.00 15.40 12.00 0.58 107.18 KG.
EN ZAPATA
ACERO LONGITUDINAL Ø 3/8" 1.00 15.40 8.00 0.58 71.46 KG.
ACERO TRANSVERSAL Ø 3/8" 1.00 1.15 30.00 0.58 20.01 KG.
05.07.03 MURO DE CONTENCION - CONCRETO F'c=210 Kg/cm2 9.68 M3
PANTALLA 1.00 14.40 0.20 1.90 5.47
ZAPATA 1.00 14.40 1.17 0.25 4.21
06.00 ESTRUCTURAS DE MADERA Y COBERTURAS
06.01 TIJERALES
06.01.01 TIJERAL DE MADERA 7.00 7.00 7.00 PZA.
06.02 CORREAS MADERA
Preparado por Omar 01/10/2015 Página 5
11. Propietario : Hoja :
Fecha : Plano : Versión :
Hecho por : Revisado :
Largo Ancho Altura
HOJA DE METRADOS
..de..
ESTRUCTURAS
Ing. Omar Hidalgo Quispe
Ing. Omar Hidalgo Quispe
01/10/2005
LLANTOY ZEVALLOS JOSE ANTONIO
Unidad
Obra :
VIVIENDA UNIFAMILIAR
MedidasN° de
Veces
Especificaciones
Partida
N°
Parcial Total
06.02.01 CORREA DE 3" x 2" 16.00 13.50 216.00 216.00 ML
06.03 COBERTURAS
06.03.01 COBERTURA CALAMINA GALVANIZADA 2.00 5.60 13.50 151.20 151.20 M2
06.03.02 CUMBRERA 1.00 13.50 13.50 13.50 ML.
06.03.03 COLOCACION DE VENDAS 8" (FRISO) 49.40 ML
2.00 13.50 27.00
4.00 5.60 22.40
07.00 VARIOS
07.01 TRANSPORTE DE MATERIALES Y AGREGADOS
07.01.01 FLETE TERRESTRE 1.00 1.00 1.00 GLOBAL
07.02 JUNTAS DE SEPARACION
07.02.01 RELLENO DE JUNTAS 22.00 22.00 22.00 ML.
Preparado por Omar 01/10/2015 Página 6
12. Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
01 OBRAS PROVISIONALES 1,000.00
01.01 CONSTRUCCIONES PROVISIONALES 1,000.00
01.01.01 CARTEL DE IDENTIFICACION DE OBRA und 1.00 400.00 400.00
01.01.02 ALQUILER DE ALMACEN Y GUARDIANIA mes 3.00 200.00 600.00
02 TRABAJOS PRELIMINARES 543.85
02.01 LIMPIEZA DE TERRENO 150.99
02.01.01 LIMPIEZA DE TERRENO m2 146.59 1.03 150.99
02.02 TRAZO, NIVELES Y REPLANTEO 392.86
02.02.01 TRAZOS, NIVELES Y REPLANTEO PRELIMINAR m2 146.59 1.34 196.43
02.02.02 TRAZO Y REPLANTEO DURANTE EL PROCESO m2 146.59 1.34 196.43
03 MOVIMIENTO DE TIERRAS 2,849.08
03.01 NIVELACION DE TERRENO 377.50
03.01.01 NIVELACIÓN MANUAL DE TERRENO m3 36.65 10.30 377.50
03.02 EXCAVACIONES 544.40
03.02.01 EXCAVACION DE ZANJAS m3 17.08 13.73 234.51
03.02.02 EXCAVACION PARA ZAPATAS m3 22.57 13.73 309.89
03.03 RELLENOS 918.35
03.03.01 RELLENO Y COMPACTADO CON MATERIAL DE PRESTAMOm3 24.72 37.15 918.35
03.04 ELIMINACIONES 1,008.83
03.04.01 ELIMINACION DE MATERIAL EXCEDENTE m3 51.55 19.57 1,008.83
04 OBRAS DE CONCRETO SIMPLE 2,206.74
04.01 CIMIENTOS CORRIDOS 1,926.45
04.01.01 CONCRETO CIMIENTO CORRIDO C:H 1:10 + 30 P.G. m3 17.08 112.79 1,926.45
04.02 SOLADOS 112.79
04.02.01 FALSA ZAPATA C:H 1:10 + 30% P.G. m3 1.00 112.79 112.79
04.02.02 FALSA CIMENTACIÓN C:H 1:10 + 30% P.G. m3 0.00 111.12 0.00
04.03 SOBRECIMIENTOS 167.50
04.03.01 SOBRECIMIENTO - CONCRETO 1:8 + 25% P.M. m3 1.00 145.17 145.17
04.03.02 SOBRECIMIENTO - ENCOFRADO Y DESENCOFRADO m3 1.00 22.33 22.33
04.04 FALSO PISO 0.00
04.04.01 FALSO PISO DE 4" DE CONCRETO 1:10 m2 0.00 19.54 0.00
05 OBRAS DE CONCRETO ARMADO 2,187.78
05.01 ZAPATAS 198.52
05.01.01 ZAPATAS - ACERO fy=4,200 kg/cm2 kg 1.00 3.65 3.65
05.01.02 ZAPATAS - CONCRETO f'c=210 kg/cm2 m3 1.00 194.87 194.87
05.02 COLUMNAS 295.86
05.02.01 COLUMNAS - ENCOFRADO Y DESENCOFRADO m2 1.00 27.63 27.63
05.02.02 COLUMNAS - ACERO fy=4,200 kg/cm2 kg 1.00 3.65 3.65
05.02.03 COLUMNAS - CONCRETO f'c=210 kg/cm2 m3 1.00 264.58 264.58
05.03 VIGAS 551.72
05.03.01 VIGA DE CIEMENTACIÓN - ENCOFRADO Y DESENCOFRADOm2 1.00 21.81 21.81
05.03.02 VIGA DE CIEMENTACIÓN - ACERO fy=4200 kg/cm2 kg 1.00 3.65 3.65
05.03.03 VIGA DE CIEMENTACIÓN - CONCRETO f'c=210 kg/cm2m3 1.00 264.58 264.58
05.03.04 VIGAS - ENCOFRADO Y DESENCOFRADO m2 1.00 25.51 25.51
05.03.05 VIGAS - ACERO fy=4,200 kg/cm2 kg 1.00 3.65 3.65
05.03.06 VIGAS - CONCRETO f'c=210 kg/cm2 m3 1.00 232.52 232.52
05.04 LOSAS 259.32
05.04.01 LOSAS ALIGERADAS 259.32
05.04.01.01 LOSA ALIGERADA - ENCOFRADO Y DESENCOFRADOm2 1.00 23.66 23.66
05.04.01.02 LOSA ALIGERADA - ACERO fy=4,200 kg/cm2 kg 1.00 3.65 3.65
05.04.01.03 LOSA ALIGERADA CONCRETO f'c=210 kg/cm2 m3 1.00 229.65 229.65
05.04.01.04 LOSA ALIGERADA - LADRILLO HUECO und 1.00 2.36 2.36
HOJA DE RESUMEN ESTRUCTURAS
13. 05.05 ESCALERAS 311.75
05.05.01 ESCALERA ENCOFRADO DESENCOFRADO m2 1.00 42.47 42.47
05.05.02 ESCALERA ACERO fy=4,200 kg/cm2 kg 1.00 3.65 3.65
05.05.03 ESCALERA - CONCRETO f'c=210 kg/cm2 m3 1.00 265.63 265.63
05.06 PLACAS DE CONCRETO 283.81
05.06.01 PLACA DE ESCALERA - ENCOFRADO DESENCOFRADOm2 1.00 23.38 23.38
05.06.02 PLACA DE ESCALERA - ACERO fy=4,200 kg/cm2 kg 1.00 3.65 3.65
05.06.03 PLACA DE ESCALERA - CONCRETO f'c=210 kg/cm2 m3 1.00 256.78 256.78
05.07 MUROS DE CONTENCION 286.80
05.07.01 MURO DE CONTENCION - ENCOFRADO DESENCOFRADOm2 1.00 23.38 23.38
05.07.02 MURO DE CONTENCION - ACERO fy=4,200 kg/cm2 kg 1.00 3.65 3.65
05.07.03 MURO DE CONTENCION - CONCRETO f'c=210 kg/cm2m3 1.00 259.77 259.77
06 ESTRUCTURAS DE MADERA Y COBERTURA 261.46
06.01 TIJERALES 257.46
06.01.01 TIJERAL DE MADERA pza 1.00 257.46 257.46
06.02 CORREAS DE MADERA 1.00
06.02.01 CORREA DE 3" x 2" m 1.00 1.00 1.00
06.03 COBERTURA 3.00
06.03.01 COBERTURA CALAMINA GALVANIZADA m2 1.00 1.00 1.00
06.03.02 CUMBRERA m 1.00 1.00 1.00
06.03.03 COLOCACION DE VENDAS 8" m 1.00 1.00 1.00
07 VARIOS 2.00
07.01 TRANSPORTE DE MATERIALES Y AGREGADOS 1.00
07.01.01 FLETE TERRESTRE glb 1.00 1.00 1.00
07.02 JUNTAS DE SEPARACION 1.00
07.02.01 RELLENO DE JUNTAS m 1.00 1.00 1.00
14. Item Descripción Und. Metrado Precio (S/.) Parcial (S/.)
01 MUROS Y TABIQUES DE ALBAÑILERIA 6,057.81
01.01 MUROS DE LADRILLO DE ARCILLA 6,057.81
01.01.01 MURO DE LADRILLO SOGA MEZC. C:A 1:5 m2 120.84 42.42 5,126.03
01.01.02 MURO DE LADRILLO CABEZA MEZC. C:A 1:5 m2 66.89 13.93 931.78
02 REVOQUES ENLUCIDOS Y MOLDURAS 3,887.26
02.01 TARRAJEO PRIMARIO RAYADO m2 0.00 7.15 0.00
02.02 TARRAJEO EN MUROS EXTERIORES m2 0.00 13.22 0.00
02.03 TARRAJEO EN MUROS INTERIORES m2 0.00 12.35 0.00
02.04 TARRAJEO DE COLUMNAS 1,251.88
02.04.01 TARRAJEO DE COLUMNAS - SUPERFICIES m2 75.46 16.59 1,251.88
02.05 TARRAJEO DE VIGAS 886.70
02.05.01 TARRAJEO DE VIGAS - SUPERFICIES m2 50.96 17.40 886.70
02.06 VESTIDURAS 1,227.88
02.06.01 VESTIDURA DE DERRAMES CON CEMENTO m 178.73 6.87 1,227.88
02.07 ENCHAPES 327.68
02.07.01 ENCHAPE CON CERAMICO 0.20x0.30 m2 25.68 12.76 327.68
02.08 BRUÑAS 193.12
02.08.01 BRUÑAS PERIMETRALES m 136.00 1.42 193.12
03 CIELORRASOS 1,690.30
03.01 CIELORRASOS CON MEZCLA 1,690.30
03.01.01 TARRAJEO CON MEZCLA SOBRE CIELO RASO m2 123.20 13.72 1,690.30
03.02 CIELORRASOS SUSPENDIDOS 0.00
03.02.01 CIELO RASO CON BALDOSA DE FIBRA MINERAL m2 0.00 19.54 0.00
04 PISOS Y PAVIMENTOS 8,586.10
04.01 CONTRAPISOS 1,613.78
04.01.01 CONTRAPISO DE CEMENTO m2 111.99 14.41 1,613.78
04.02 PISOS 5,466.26
04.02.01 PISO DE CERAMICO 0.30x0.30 m2 4.20 40.09 168.38
04.02.02 PISO DE MADERA MACHIHEMBRADA m2 102.00 51.94 5,297.88
04.03 PISOS DE CONCRETO 0.00
04.03.01 PISO DE CEMENTO PULIDO m2 0.00 19.41 0.00
04.03.02 PISO DE CEMENTO COLOREADO m2 0.00 13.31 0.00
04.04 VEREDAS 1,506.06
04.04.01 VEREDA DE E=4" m2 47.60 31.64 1,506.06
05 CONTRAZOCALOS 448.84
05.01 CONTRAZOCALOS DE MADERA 448.84
05.01.01 CONTRAZOCALO DE MADERA CEDRO m 68.42 6.56 448.84
06 CARPINTERIA DE MADERA 2,695.95
06.01 PUERTAS 1,297.60
06.01.01 PUERTA APANELADA P01 und 8.00 129.76 1,038.08
06.01.02 PUERTA APANELADA P02 und 2.00 129.76 259.52
06.02 VENTANAS 1,398.35
06.02.01 VENTANAS DE MADERA m2 50.61 27.63 1,398.35
07 CARPINTERIA METALICA 310.24
07.01 ELEMENTOS METALICOS ESPECIALES 310.24
07.01.01 BARANDA METALICA m 12.55 24.72 310.24
08 VIDRIOS, CRISTALES Y SIMILARES 2,204.80
08.01 VIDRIOS, CRISTALES 2,204.80
08.01.01 VIDRIO DE COLOR SEMIDOBLE p2 551.20 4.00 2,204.80
09 PINTURA 624.01
09.01 PINTURA EN CIELORRASOS, MUROS Y OTROS 624.01
09.01.01 PINTURA EN VIGAS Y COLUMNAS m2 126.42 4.25 537.29
09.01.02 PINTURA EN MUROS EXTERIORES m2 0.00 6.05 0.00
09.01.03 PINTURA EN MUROS INTERIORES m2 0.00 3.55 0.00
09.01.04 PINTURA CON ESMALTE m2 12.55 6.91 86.72
10 VARIOS, LIMPIEZA Y JARDINERIA 120.20
10.01 LIMPIEZA FINAL DE OBRA m2 146.59 0.82 120.20
HOJA DE RESUMEN ARQUITECTURA