SlideShare ist ein Scribd-Unternehmen logo
1 von 12
Downloaden Sie, um offline zu lesen
Technical
Document             Seismic Technical Guide

                     Hanger Wire Attachment



                     The International Building Code (IBC), through references to ASCE/SEI 7 Minimum Design Loads for Buildings
                     and Other Structures, American Society of Civil Engineers/Structural Engineering Institute (ASCE/SEI), The CISCA
                     Guidelines for Zones 3-4, The CISCA Guidelines for Zones 0-2, and ASTM International E 580/E 580M Standard
                     Practice for Installation of Ceiling Suspension Systems for Acoustical Tile and Lay-in Panels in Areas Subject to
                     Earthquake Ground Motions, defines the requirement for hanger wire and their supports and attachment methods.
                     However, there are exceptions and the application of hanger wires in a seismic design category can meet code
                     requirements in different ways.

                     USG® recommends that the design team, consulting engineers and code officials work together to analyze these
                     factors and determine the appropriate construction and application of hanger wire attachment. Because codes
                     continue to evolve, check with local officials prior to designing and installing a suspension system.

Guidelines         – 12-gauge, galvanized, soft-annealed steel wire
                   – Manufactured in accordance with ASTM A641
                   – Meets or Exceeds Federal Specification QQ-W-461H
                     Note: 12-gauge hanger wire produced by USG meets these requirements.


Performance Data      12-Gauge Wire                   Wire Tie Failure / Pullout Load
                      Typical 3 wrap tie1             270 lbs.
                      Tight 3 wrap tie                358 lbs.
                      Yields                          424 lbs.
                      Ultimate load                   +550 lbs.
                      Tensile Strength (Ksi)          80 max.
                    1 Per ASTM C636

                     Note: Tight wrap typically consists of three complete wraps within 1 in. Some jurisdictions may require four complete wraps for
                     bracing wires. These requirements may vary by jurisdiction.


Splice Options       Hanger wire splices are typical when the ceiling drop is greater than the length of the wire available and are
                     allowed in seismic ceiling construction. The industry standard is to loop and tie the wire ends with three tight
                     turns, or use a square knot. The square knot is the stronger of the two options at 550 lbs. versus 350 lbs.
                     for the loop and tie option.

                      12-Gauge Wire Splice            Wire Tie Failure
                      Loop and Tie                    350 lbs.
                      Square Knot                     550 lbs.
                     Note: Accessories by others for securing hanger wire splices should be evaluated for pullout and strength.
Application

                                         Hanger Wire Splices


         Loop and Tie Application
Step 1   Connect the hanger wire ends together
         through two loops.



Step 2   Wrap the hanger wire ends securely around
         itself with three complete turns within 1 in.




         Square Knot Application
Step 1   Create an approximate 5 in. bend in the
         end of each hanger wire




Step 2   With the short ends opposed, bring the right-hand
         end over the left-hand and loop the short end
         under and around the left-hand end, as shown.




Step 3   Loop the left-hand short end back up and
         around the right-hand loop, with the left-hand
         end over the right-hand end and bring the
         left-hand end under the loop of the right-hand
         end, as shown.

Step 4   Draw the knot tight.




Step 5   Wrap the hanger wire ends securely around
         itself with three complete turns within 1 in.




         Note: In the symmetry of the knot, the wire piece on the left emerges parallel from below the other loop, while the wire piece on the right emerges parallel from
         above the other loop. This appearance confirms you have tied the square knot correctly.
2
Application

Attachment to Tee



Insert the hanger wire ends through a wire hole in the tee and wrap the wire end securely around itself with three
complete turns within 3 in. Ensure the remaining wire end is secured so that it does not interfere with the place-
ment of ceiling panels.

USG Donn® main tees are produced with round hanger wire holes in the tee web at regular intervals. There are
also rectangular (convenience) holes located in the tee bulb at regular intervals. The typical location for the hanger
and bracing (splay) wires is in the round holes, but the rectangular (convenience) holes may also be used when
needed. We have load tested the rectangular (convenience) holes located in the tee bulb with 12 ga. hanger wire
on a 45° angle. The failure load is in excess of 400 lbs. This far exceeds the 200 lb. minimum prescribed by the
code for the connections of the bracing (splay) wires.

Note: USG has qualified the use of the rectangular (convenience) holes located in the tee bulb through comparison testing by
seismic shake-table analysis. In these tests the rectangular (convenience) holes located in the tee bulb were used for all hanger
wire attachments to the tee.


 Round Hanger Wire Hole Attachment
  Round Hanger Wire Hole Attachment                               Rectangular (Convenience) Hole Attachment
                                                                   Rectangular (Convenience) Hole Attachment

         hanger wire                                                               hanger wire


         round hanger                                                              rectangular
         wire hole                                                                 convenience hole




                                                                                                                                    3
Application

                                 Anchorage



                                 The International Building Code (IBC), through references to ASCE/SEI 7 Minimum Design Loads for Buildings
                                 and Other Structures, American Society of Civil Engineers/Structural Engineering Institute (ASCE/SEI), defines
                                 the requirements for component anchorage. The requirements are as follows: “Component attachments shall
                                 be bolted, welded, or otherwise positively fastened without consideration of frictional resistance produced by
                                 the effects of gravity. A continuous load path of sufficient strength and stiffness between the component and the
                                 supporting structure shall be provided. Local elements of the structure including connections shall be designed
                                 and constructed for the component forces where they control the design of the elements or their connections.

Anchors in Concrete or Masonry   Anchors in concrete shall be designed in accordance with Appendix D of ACI 318.

                                 Anchors in masonry shall be designed in accordance with ACI 530. Anchors shall be designed to be governed by
                                 the tensile or shear strength of a ductile steel element.

                 Exception:      Anchors shall be permitted to be designed so that the attachment that the anchor is connecting to the structure
                                 undergoes ductile yielding at a load level corresponding to anchor forces not greater than their design strength,
                                 or the minimum design strength of the anchors shall be at least 2.5 times the factored forces transmitted by the
                                 component.

Post-installed Anchors           Post-installed anchors in concrete shall be pre-qualified for seismic applications in accordance with ACI 355.2
in Concrete and Masonry          or other approved qualification procedures. Post-installed anchors in masonry shall be pre-qualified for seismic
                                 applications in accordance with approved qualification procedures.

Multiple Attachments             Determination of force distribution of multiple attachments at one location shall take into account the stiffness and
                                 ductility of the component, component supports, attachments, and structure and the ability to redistribute loads to
                                 other attachments in the group. Designs of anchorage in concrete in accordance with Appendix D of ACI 318 shall
                                 be considered to satisfy this requirement.




4
Application

                              Anchorage



Power Actuated Fasteners      Power actuated fasteners in concrete or steel shall not be used for sustained tension loads exceeding 100 lb
                              (445 N) or for brace applications in Seismic Design Categories D, E, or F unless approved for seismic loading.
                              Power actuated fasteners in steel are permitted in Seismic Design Category D, E or F if the gravity tension load
                              on any fastener does not exceed 250 lbs (1123 N) unless approved for seismic loading. Power actuated
                              fasteners in masonry are not permitted unless approved for seismic loading.

                 Exception:   Power actuated fasteners in concrete used for support of acoustical tile or lay-in panel suspended ceiling
                              applications and distributed systems where the service load on any individual fastener does not exceed
                              90 lb (400 N). Power actuated fasteners in steel where the service load on any individual fastener does
                              not exceed 250 lb (1,112 N).

                              Power Actuated Fasteners for Acoustical Tile or Lay-In Panel Suspended Ceiling Applications
                              Seismic Design Category D, E or F
                               Concrete                                                        Steel
                               Allowed for sustained tension loads exceeding 90 lb (400 N)     Allowed where gravity tension load on any fastener does not
                                                                                               exceed 250 lbs (1123 N)

                              Note: The load for suspension system hanger wires will not exceed 64 lbs. based on hanger wires spaced 4 ft. o.c. along heavy
                              duty main tees designed to carry 16 lbs/l.f. Also ASCE7-10 contains an exception allowing power actuated fasteners for support
                              of acoustical tile or lay-in panel suspended ceiling applications. ASCE7-02 and ASCE7-05 does not contain this exception. Please
                              check with the authority having jurisdiction as interpretation and enforcement of this may vary.


Friction Clips                Friction clips in Seismic Design Categories D, E or F shall not be used for supporting sustained loads in addition
                              to resisting seismic forces. C-type beam and large flange clamps are permitted for hangers provided they are
                              equipped with restraining straps equivalent to those specified in NFPA 13 Section 9.3.7. Lock nuts or equivalent
                              shall be provided to prevent loosening of threaded connections.




                                                                                                                                                             5
Construction

                                                Attachment to Structure
                         Construction
                         Attachment to Structure

                         Wood
                                                                                                           Wood
Wood                     Vertical
                                                                                                           Splay / Bracing
              Vertical                                                                          Splay
                         Wood Joist or Rafter
Wood Joist                                                                                                 Wood Joist or Rafter
of Rafter



                                                                                                           3" max.


                                                                                                                                                          1/4" diameter closed eye

                                                                                                                                                          screw with full thread
                                                                                                                                                          embedment (11/4" min.)
                                                                               wood joist
                         12 ga. hanger wire


                               3" x 1/4" diameter closed
                               eye screw with 1" min.                                                                                 12 ga. hanger
                               penetration into wood                                                                                  wire min. 3 turns

                              12 ga. hanger wire




                                Wood Joist or Rafter                                                          Wood Joist

                                          (3) 11/2" x 9 ga. staples or                                                  (3) 11/2" x 9 ga. staples or
                                          (3) stronghold "J" nails at                                                   (3) stronghold "J" nails at
                                          each wire loop                                                                each wire loop




                                                                             1" min.                          1" min.
                                                                                                                                                           wood joist
                                                                         wood joist
                                    12 ga. hanger wire                                                                           12 ga. hanger wire




Wood Truss
                                                                                                            Wood Truss
                                 Wood Truss
                                 web member                                                                 web member


                                 bottom chord                                                               bottom chord



                                 12 ga. hanger wire             saddle tie                                               saddle tie                       12 ga. hanger wire




             Note: Hanger or bracing wire anchors to the structure should be installed in such a manner that the direction of the anchor aligns as closely as possible with the
             direction of the wire.

6
Construction

                                                     Attachment to Structure


Wood                                      Bottom of Wood Joist
                 Vertical                 Typical Saddle Tie                                             Splay
Bottom of                                 saddle tie required for all
Wood Joist                                widths greater than 1/2"



                                                                   Note:
                                                                   saddle tie has double
                                                                   loop at support
                                                                   12 ga. hanger wire
                                                                   min. 3 turns
                          Bottom of Wood Joist
                                                                                                                                           Not Applicable


                                                                 1/4"   diameter drilled hole
                            typical saddle
                            tie with double
                            loop at support                    2" min.

                                                                 hanger wire


                 Wood I-Joist                                                                            Wood I-Joist
Wood I-Joist

                 wood I-joist                                                                            wood I-joist




                                12 ga. hanger wire            add 2 1/2" x 20 ga. stud* w/                   12 ga. hanger wire                        add 2 1/2" x 20 ga. stud* w/
                                min. 3 turns                  (1) #10 x 1" wood screw to                     min. 3 turns                              (1) #10 x 1" wood screw to
                                                              each of 3 joists. place stud flat                                                        each of 3 joists. place stud flat
                                                              and within 6" of splay wire.                                                             and within 6" of splay wire.

                                                               * alternate:                                                                            * alternate:
                                                               2 x 4 flat with 1-10d or 1-#10 x 3"                                                     2 x 4 flat with 1-10d or 1-#10 x 3"
                                                               screw to each of 3 truss bottom flanges                                                 screw to each of 3 truss bottom flanges
                                 Wood I-Joist Bottom Flange                                                             Wood I-Joist Bottom Flange
Wood I-Joist
Bottom Flange                                                                                                           Note: Do not insert screw
                                                                                                                        eyes parallel to laminations


                                                                                                                        1/4" diameter closed

                                 1/4" diameter closed                                                                   eye screw with
                                                                                                                        11/4" min. penetration
                                 eye screw with 11/4"
                                                                                                                        align with brace wire
                                 min. penetration at bottom flange

                                 12 ga. hanger wire min. 3 turns                                                                                        12 ga. hanger wire
                                                                                                                                                        min. 3 turns
                                                                            1"
                                                                            min.



                Note: Hanger or bracing wire anchors to the structure should be installed in such a manner that the direction of the anchor aligns as closely as possible with the
                direction of the wire.

                                                                                                                                                                                                 7
Construction

                                                     Attachment to Structure
                           Concrete
                                                                                                   Concrete
                           Vertical
Concrete                                                                                           Splay / Bracing
                 Vertical Clip Attachment                                                    Splay Attachment
                                                                                                 Clip
Clip                                                     5/16"
                                                             drill-in expansion anchor                                                               5/16"
                                                                                                                                                         drill-in expansion anchor
Attachment                                               minimum or approved fastener                                                                minimum or approved fastener



                                                                                                   structural concrete                                       45˚ max.
                          12 ga. metal angle                     structural concrete
                                                                                                   steel strap 1" wide x 2" long x 12 ga. min.                            3 turns

                           3 turns

                          12 ga. hanger wire                                                                                                  12 ga. hanger wire



                           Clip Attachment
                                                                                                   Clip Attachment
                                                         5/16"
                                                             drill-in expansion anchor                                                               5/16"
                                                                                                                                                         drill-in expansion anchor
                                                         minimum or approved shot pins                                                               minimum or approved shot pins


                                                                                                   structural concrete                                       45˚ max.
                           12 ga. metal angle                    structural concrete
                                                                                                   steel strap 1" wide x 2" long x 12 ga. min.                            3 turns

                           3 turns
                                                                                                                                             12 ga. hanger wire
                           12 ga. hanger wire


                                                                                                            Cast In Place Concrete
Cast In Place
Concrete
                                                                                                                                wire pigtail w/ 2" dia. loop & 4" tail


                                                                                                                                                             structural concrete
                               Cast In Place Concrete
                                                                                                            45˚ max.
                               wire pigtail w/ 2" dia.
                               loop & 4" tail
                                                                                                                          12 ga. hanger wire



                               structural concrete
                                                                                                           Cast In Place Concrete
                              12 ga. hanger wire
                                                                                                           wire pigtail w/ 2" dia. loop & 4" tail


                                                                                                                                                             structural concrete

                                                                                                              12 ga. hanger wire

                                                                                                                                          45˚ max.




                Note: Hanger or bracing wire anchors to the structure should be installed in such a manner that the direction of the anchor aligns as closely as possible with the
                direction of the wire.

8
Construction

                                                       Attachment to Structure
                                                                                                           Steel

Steel                                                                                                      Splay / Bracing

                   Vertical      Steel                                                         Splay       Open-Web Steel Joist

Open-Web                         Vertical                                                                           top chord
Steel Joist
                                 Open-Web Steel Joist

                                 web member                                                                                                              12 ga. hanger wire
                                                                                                                                                         (wrap and tie around
                                                                                                                                                         tops of web members)
                                 bottom chord
                                                                                                          Open-Web Steel Joist
                                 12 ga. hanger                  typical saddle tie                                  top chord
                                 wire min. 3 turns


                                 Attach hanger wire to bottom chord only                                                                                 12 ga. hanger wire
                                 when designed to carry the vertical load of                                                                             (wrap and tie around
                                 the suspended ceiling system.                                                                                           tops of web members)


                               Steel Roof Deck                                                              Steel Roof Deck
Steel Roof Deck                                                                                                                                          2 #8 x 1/2"
                                                              #3 x 12" rebar
                                                                                                                                                         self tapping screws



                               20 ga. min. deck            hanger wire tie to #3                                   20 ga. min. deck
                                                           rebar with three wraps                                                                steel strap 3" wide
                                                           around rebar and one                                                                  x 4" long x 12 ga. minimum
                                                           wrap around wire                                                               12 ga. hanger wire
                              Steel Deck With Insulation Fill                                                                             min. 3 turns

Steel Deck With               #3 rebar x length
Insulation Fill               required to cover min.
                              of 4 high corrugations          non-structural concrete fill


                                                                                                                                      Not Applicable

                                     steel deck              12 ga. hanger wire
                                                             min. 3 turns

                       Steel Beam                                                                              Steel Beam
Steel Beam




                       structural concrete                                                                     structural concrete
                                                                structural steel                                                                         structural steel



                                                                                                                                             12 ga. metal angle
                                                       12 ga. metal angle

                                                                                                                                  12 ga. splayed
                                                                                                                                  seismic bracing wire
                                                       12 ga. hanger wire

                  Note: Hanger or bracing wire anchors to the structure should be installed in such a manner that the direction of the anchor aligns as closely as possible with the
                  direction of the wire.

                                                                                                                                                                                       9
Construction

                                                   Attachment to Structure

Steel
                   Vertical        Steel Deck With Concrete Fill                                     Splay
Steel Deck With                                                   structural concrete fill
Concrete Fill




                                   shot-in or expansion           steel deck
                                   anchor with eye bolt
                                                                  12 ga. hanger wire
                                                                  min. 3 turns



                               Steel Deck With Concrete Fill
                                                                                                              Steel Deck With Concrete Fill

                                                                   structural concrete fill                                                  structural concrete fill




                                                                                      steel deck                                                               steel deck
                                                                                                               5/16"(min.) drill-in
                               12 ga. hanger wire                                                                                                             12 ga. hanger wire
                               embedded in concrete                                                            expansion anchor. steel                        min. 3 turns
                                                                                                               strap 12 ga. x 1" wide min.



                        Steel Deck With Concrete Fill
                                                                 structural concrete fill




                        shot-in anchor 3/4" min. metal           steel deck
                        angle 12 ga. x 3/4" wide min.
                                                                 12 ga. hanger wire
                                                                 min. 3 turns




                  Note: Hanger or bracing wire anchors to the structure should be installed in such a manner that the direction of the anchor aligns as closely as possible with the
                  direction of the wire.




10
Testing and Inspection




Post-installed anchors shall be tested when deemed necessary by the authority having jurisdiction. Testing shall
be performed by an accepted testing facility, unless approval of an alternative is obtained in advance from the
engineer of record (EOR) for the project. If any anchor fails testing, test all anchors of the same type, not previously
tested until twenty (20) consecutive anchors pass, then resume the initial test frequency. The anchors tested shall
be only those anchors installed by the same trade. The authority having jurisdiction shall define acceptance/failure
criteria. The test values and all appropriate criteria shall be shown on the contract documents.

The test load may be applied by any method that will effectively measure the tension in the anchor, such as
direct pull with a hydraulic jack, calibrated spring loaded devices, or a calibrated torque wrench except that
displacement-controlled anchors such as drop-ins shall not be tested using a torque wrench.

When field testing of component anchorage is required by the authority having jurisdiction, the following criteria
shall apply unless otherwise specified:
 Anchor Type                           Test Value                            Percent Tested
 Support (Vertical)                    200 lbs. in tension                   10%
 Bracing (Splay)                       440 lbs. in tension                   50%
Note: Drilled-in or shot-in anchors typically require special approval prior to use in pre-stressed concrete.
Note: Shot-in anchors in concrete are not permitted for bracing wires.




                                                                                                                       11
Product Information                Purpose                           L.A. Research Report                    Safety First!
See usg.com for the most up-to- This seismic technical guide         Compliance                              Follow good safety/industrial
date product information.          (STG) is intended as a resource   Donn brand suspension systems           hygiene practices during
                                   for design professionals, to      manufactured by USG Interiors,          installation. Wear appropriate
Installation                       promote more uniform criteria     Inc., have been reviewed and            personal protective equipment.
Must be installed in compliance for plan review and jobsite          are approved by listing in the          Read MSDS and literature
with ASTM C636, ASTM E580, inspection of projects. This              following L.A. Research Report          before specification and
CISCA, and standard industry       STG indicates an accept-          number: 25764.                          installation.
practices.                         able method for achieving
                                   compliance with applicable        Notice
Code Compliance                                                      We shall not be liable for
                                   codes and regulations, although
The information presented                                            incidental and consequential
                                   other methods proposed by
is correct to the best of our                                        damages, directly or indirectly
                                   design professionals may be
knowledge at the date of                                             sustained, nor for any loss
                                   considered and adopted.
issuance. Because codes                                              caused by application of these
continue to evolve, check          ICC Evaluation Service, Inc.,     goods not in accordance with
with a local official prior to     Report Compliance                 current printed instructions or
designing and installing a ceiling Suspension systems                for other than the intended use.
system. Other restrictions and     manufactured by USG Interiors,    Our liability is expressly limited to
exemptions may apply. This         Inc., have been reviewed and      replacement of defective goods.
is only intended as a quick        are approved by listing in        Any claim shall be deemed
reference.                         ICC-ES Evaluation Report 1222.    waived unless made in writing
                                   Evaluation Reports are subject    to us within thirty (30) days from
                                   to reexamination, revision and    date it was or reasonably should
                                   possible cancellation. Please     have been discovered.
                                   refer to usgdesignstudio.com or
                                   usg.com for current reports.



Manufactured by                   usg.com                            The following are trademarks of USG     SC2522/rev. 9-10
USG Interiors, Inc.               seismicceilings.com                Interiors, Inc. or a related company:   © 2010, USG Interiors, Inc.
550 West Adams Street             sustainableceilings.com            Donn, USG, USG in stylized letters.     Printed in U.S.A.
Chicago, IL 60661                 usgdesignstudio.com

Weitere ähnliche Inhalte

Was ist angesagt?

Tecnical aplicacion1 abb
Tecnical aplicacion1 abbTecnical aplicacion1 abb
Tecnical aplicacion1 abbisaac diaz said
 
UHF partial discharge detection system for GIS Application guide for sensitiv...
UHF partial discharge detection system for GIS Application guide for sensitiv...UHF partial discharge detection system for GIS Application guide for sensitiv...
UHF partial discharge detection system for GIS Application guide for sensitiv...Power System Operation
 
Manual de instalacão de Cabo de Fibra Optica FO Autosustentada
Manual de instalacão de Cabo de Fibra Optica FO AutosustentadaManual de instalacão de Cabo de Fibra Optica FO Autosustentada
Manual de instalacão de Cabo de Fibra Optica FO AutosustentadaLemuel Sautier
 
Extra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableExtra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableLeonardo ENERGY
 
External Price Referencing in Europe, Pharma
External Price Referencing in Europe, PharmaExternal Price Referencing in Europe, Pharma
External Price Referencing in Europe, PharmaDragan Cirkovic
 
SAG TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG TENSION CALCULATION METHODS FOR OVERHEAD LINESSAG TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG TENSION CALCULATION METHODS FOR OVERHEAD LINESPower System Operation
 
48294078 i3130003-calculo-tracao-dos-cabos
48294078 i3130003-calculo-tracao-dos-cabos48294078 i3130003-calculo-tracao-dos-cabos
48294078 i3130003-calculo-tracao-dos-cabosMarcelo Moraes
 

Was ist angesagt? (8)

Tecnical aplicacion1 abb
Tecnical aplicacion1 abbTecnical aplicacion1 abb
Tecnical aplicacion1 abb
 
UHF partial discharge detection system for GIS Application guide for sensitiv...
UHF partial discharge detection system for GIS Application guide for sensitiv...UHF partial discharge detection system for GIS Application guide for sensitiv...
UHF partial discharge detection system for GIS Application guide for sensitiv...
 
Manual de instalacão de Cabo de Fibra Optica FO Autosustentada
Manual de instalacão de Cabo de Fibra Optica FO AutosustentadaManual de instalacão de Cabo de Fibra Optica FO Autosustentada
Manual de instalacão de Cabo de Fibra Optica FO Autosustentada
 
Extra High Voltage Underground Power Cable
Extra High Voltage Underground Power CableExtra High Voltage Underground Power Cable
Extra High Voltage Underground Power Cable
 
External Price Referencing in Europe, Pharma
External Price Referencing in Europe, PharmaExternal Price Referencing in Europe, Pharma
External Price Referencing in Europe, Pharma
 
SAG TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG TENSION CALCULATION METHODS FOR OVERHEAD LINESSAG TENSION CALCULATION METHODS FOR OVERHEAD LINES
SAG TENSION CALCULATION METHODS FOR OVERHEAD LINES
 
48294078 i3130003-calculo-tracao-dos-cabos
48294078 i3130003-calculo-tracao-dos-cabos48294078 i3130003-calculo-tracao-dos-cabos
48294078 i3130003-calculo-tracao-dos-cabos
 
Underground cables
Underground cablesUnderground cables
Underground cables
 

Ähnlich wie Seismic technical guide, hanger wire

Cable Ladder Bonding with Earth Wire, Is it Necessary?
Cable Ladder Bonding with Earth Wire, Is it Necessary?Cable Ladder Bonding with Earth Wire, Is it Necessary?
Cable Ladder Bonding with Earth Wire, Is it Necessary?Mike Hamilton
 
Scojet Catalog 2013
Scojet Catalog 2013Scojet Catalog 2013
Scojet Catalog 2013scojetinc
 
Structural Connection Design & Construction Aspect .pptx
Structural Connection Design & Construction Aspect .pptxStructural Connection Design & Construction Aspect .pptx
Structural Connection Design & Construction Aspect .pptxahmad705917
 
IRJET- Experimental Studies of Lateral Torsional Buckling on Castellated Beams
IRJET- Experimental Studies of Lateral Torsional Buckling on Castellated BeamsIRJET- Experimental Studies of Lateral Torsional Buckling on Castellated Beams
IRJET- Experimental Studies of Lateral Torsional Buckling on Castellated BeamsIRJET Journal
 
Etg 02-01 - sleepers, bearers and fastenings
Etg 02-01 - sleepers, bearers and fasteningsEtg 02-01 - sleepers, bearers and fastenings
Etg 02-01 - sleepers, bearers and fasteningsNECB
 
The influence of cable sag on the dynamic behaviour of cable stayed suspensio...
The influence of cable sag on the dynamic behaviour of cable stayed suspensio...The influence of cable sag on the dynamic behaviour of cable stayed suspensio...
The influence of cable sag on the dynamic behaviour of cable stayed suspensio...eSAT Journals
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976Southern Railway
 
Etd 02-04 - resilient rail fastenings for heavy duty concrete sleepers
Etd 02-04 - resilient rail fastenings for heavy duty concrete sleepersEtd 02-04 - resilient rail fastenings for heavy duty concrete sleepers
Etd 02-04 - resilient rail fastenings for heavy duty concrete sleepersNECB
 
Unit I Introduction theory and behaviour
Unit I Introduction theory and behaviourUnit I Introduction theory and behaviour
Unit I Introduction theory and behaviourSelvakumar Palanisamy
 
IRJET - Parametric Study of Cold Form Channel Section with and without Stiffe...
IRJET - Parametric Study of Cold Form Channel Section with and without Stiffe...IRJET - Parametric Study of Cold Form Channel Section with and without Stiffe...
IRJET - Parametric Study of Cold Form Channel Section with and without Stiffe...IRJET Journal
 
IRJET- Finite Element Investigation on Buckling Behaviour of Corrugated Web B...
IRJET- Finite Element Investigation on Buckling Behaviour of Corrugated Web B...IRJET- Finite Element Investigation on Buckling Behaviour of Corrugated Web B...
IRJET- Finite Element Investigation on Buckling Behaviour of Corrugated Web B...IRJET Journal
 
Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000Vikas Mehta
 
Optimization improvement in wire rope design
Optimization   improvement in wire rope designOptimization   improvement in wire rope design
Optimization improvement in wire rope designprjpublications
 

Ähnlich wie Seismic technical guide, hanger wire (20)

Cable Ladder Bonding with Earth Wire, Is it Necessary?
Cable Ladder Bonding with Earth Wire, Is it Necessary?Cable Ladder Bonding with Earth Wire, Is it Necessary?
Cable Ladder Bonding with Earth Wire, Is it Necessary?
 
PSC Lecture PPT.pdf
PSC  Lecture PPT.pdfPSC  Lecture PPT.pdf
PSC Lecture PPT.pdf
 
Scojet Catalog 2013
Scojet Catalog 2013Scojet Catalog 2013
Scojet Catalog 2013
 
Structural Connection Design & Construction Aspect .pptx
Structural Connection Design & Construction Aspect .pptxStructural Connection Design & Construction Aspect .pptx
Structural Connection Design & Construction Aspect .pptx
 
3 is 694 pvc cables
3 is 694 pvc cables3 is 694 pvc cables
3 is 694 pvc cables
 
PSC Lecture PPT.pptx
PSC  Lecture PPT.pptxPSC  Lecture PPT.pptx
PSC Lecture PPT.pptx
 
401
401401
401
 
IRJET- Experimental Studies of Lateral Torsional Buckling on Castellated Beams
IRJET- Experimental Studies of Lateral Torsional Buckling on Castellated BeamsIRJET- Experimental Studies of Lateral Torsional Buckling on Castellated Beams
IRJET- Experimental Studies of Lateral Torsional Buckling on Castellated Beams
 
Etg 02-01 - sleepers, bearers and fastenings
Etg 02-01 - sleepers, bearers and fasteningsEtg 02-01 - sleepers, bearers and fastenings
Etg 02-01 - sleepers, bearers and fastenings
 
The influence of cable sag on the dynamic behaviour of cable stayed suspensio...
The influence of cable sag on the dynamic behaviour of cable stayed suspensio...The influence of cable sag on the dynamic behaviour of cable stayed suspensio...
The influence of cable sag on the dynamic behaviour of cable stayed suspensio...
 
Chapter4
Chapter4Chapter4
Chapter4
 
01 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 963213697601 guidelines for electrical work ace 9632136976
01 guidelines for electrical work ace 9632136976
 
Etd 02-04 - resilient rail fastenings for heavy duty concrete sleepers
Etd 02-04 - resilient rail fastenings for heavy duty concrete sleepersEtd 02-04 - resilient rail fastenings for heavy duty concrete sleepers
Etd 02-04 - resilient rail fastenings for heavy duty concrete sleepers
 
Unit I Introduction theory and behaviour
Unit I Introduction theory and behaviourUnit I Introduction theory and behaviour
Unit I Introduction theory and behaviour
 
Lj3519471951
Lj3519471951Lj3519471951
Lj3519471951
 
IRJET - Parametric Study of Cold Form Channel Section with and without Stiffe...
IRJET - Parametric Study of Cold Form Channel Section with and without Stiffe...IRJET - Parametric Study of Cold Form Channel Section with and without Stiffe...
IRJET - Parametric Study of Cold Form Channel Section with and without Stiffe...
 
IRJET- Finite Element Investigation on Buckling Behaviour of Corrugated Web B...
IRJET- Finite Element Investigation on Buckling Behaviour of Corrugated Web B...IRJET- Finite Element Investigation on Buckling Behaviour of Corrugated Web B...
IRJET- Finite Element Investigation on Buckling Behaviour of Corrugated Web B...
 
Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000
 
Presentation
PresentationPresentation
Presentation
 
Optimization improvement in wire rope design
Optimization   improvement in wire rope designOptimization   improvement in wire rope design
Optimization improvement in wire rope design
 

Mehr von vtsiri

Combustible Dust 2015 nfpa 644
Combustible Dust 2015 nfpa 644Combustible Dust 2015 nfpa 644
Combustible Dust 2015 nfpa 644vtsiri
 
Understanding Legionnaires’ Disease A Fact Sheet For Workers And Unions
Understanding Legionnaires’ Disease A Fact Sheet For Workers And UnionsUnderstanding Legionnaires’ Disease A Fact Sheet For Workers And Unions
Understanding Legionnaires’ Disease A Fact Sheet For Workers And Unionsvtsiri
 
Tree trimming update mi 2015
Tree trimming update mi 2015Tree trimming update mi 2015
Tree trimming update mi 2015vtsiri
 
Gi forklift and mat handling 2015
Gi forklift and mat handling 2015Gi forklift and mat handling 2015
Gi forklift and mat handling 2015vtsiri
 
Capacitive app note
Capacitive app noteCapacitive app note
Capacitive app notevtsiri
 
Trenching 2014 year in review
Trenching 2014 year in reviewTrenching 2014 year in review
Trenching 2014 year in reviewvtsiri
 
Industrial electrical safety
Industrial electrical safetyIndustrial electrical safety
Industrial electrical safetyvtsiri
 
2015 industrial hygiene & respiratory care
2015 industrial hygiene & respiratory care2015 industrial hygiene & respiratory care
2015 industrial hygiene & respiratory carevtsiri
 
Fy2014 mfc construction_1.2015
Fy2014 mfc construction_1.2015Fy2014 mfc construction_1.2015
Fy2014 mfc construction_1.2015vtsiri
 
Fy2014 mfc general industry 1.2015
Fy2014 mfc general industry 1.2015Fy2014 mfc general industry 1.2015
Fy2014 mfc general industry 1.2015vtsiri
 
Construction issues for 2015
Construction issues for 2015Construction issues for 2015
Construction issues for 2015vtsiri
 
OSHA record keeping update
OSHA record keeping  updateOSHA record keeping  update
OSHA record keeping updatevtsiri
 
Gi 2014 fire siosh
Gi 2014 fire sioshGi 2014 fire siosh
Gi 2014 fire sioshvtsiri
 
General Industry 2014 ppe newsletter
General Industry 2014 ppe newsletterGeneral Industry 2014 ppe newsletter
General Industry 2014 ppe newslettervtsiri
 
OSHA regulations Fall protection
OSHA regulations Fall protection OSHA regulations Fall protection
OSHA regulations Fall protection vtsiri
 
Gi2013 introduction to safety
Gi2013 introduction to safetyGi2013 introduction to safety
Gi2013 introduction to safetyvtsiri
 
1926 power transmission fall issues 2014
1926 power transmission fall issues 20141926 power transmission fall issues 2014
1926 power transmission fall issues 2014vtsiri
 
Scaffold safety email
Scaffold safety emailScaffold safety email
Scaffold safety emailvtsiri
 
Welding Safety 2014
Welding Safety 2014Welding Safety 2014
Welding Safety 2014vtsiri
 
Ladder safety
Ladder safetyLadder safety
Ladder safetyvtsiri
 

Mehr von vtsiri (20)

Combustible Dust 2015 nfpa 644
Combustible Dust 2015 nfpa 644Combustible Dust 2015 nfpa 644
Combustible Dust 2015 nfpa 644
 
Understanding Legionnaires’ Disease A Fact Sheet For Workers And Unions
Understanding Legionnaires’ Disease A Fact Sheet For Workers And UnionsUnderstanding Legionnaires’ Disease A Fact Sheet For Workers And Unions
Understanding Legionnaires’ Disease A Fact Sheet For Workers And Unions
 
Tree trimming update mi 2015
Tree trimming update mi 2015Tree trimming update mi 2015
Tree trimming update mi 2015
 
Gi forklift and mat handling 2015
Gi forklift and mat handling 2015Gi forklift and mat handling 2015
Gi forklift and mat handling 2015
 
Capacitive app note
Capacitive app noteCapacitive app note
Capacitive app note
 
Trenching 2014 year in review
Trenching 2014 year in reviewTrenching 2014 year in review
Trenching 2014 year in review
 
Industrial electrical safety
Industrial electrical safetyIndustrial electrical safety
Industrial electrical safety
 
2015 industrial hygiene & respiratory care
2015 industrial hygiene & respiratory care2015 industrial hygiene & respiratory care
2015 industrial hygiene & respiratory care
 
Fy2014 mfc construction_1.2015
Fy2014 mfc construction_1.2015Fy2014 mfc construction_1.2015
Fy2014 mfc construction_1.2015
 
Fy2014 mfc general industry 1.2015
Fy2014 mfc general industry 1.2015Fy2014 mfc general industry 1.2015
Fy2014 mfc general industry 1.2015
 
Construction issues for 2015
Construction issues for 2015Construction issues for 2015
Construction issues for 2015
 
OSHA record keeping update
OSHA record keeping  updateOSHA record keeping  update
OSHA record keeping update
 
Gi 2014 fire siosh
Gi 2014 fire sioshGi 2014 fire siosh
Gi 2014 fire siosh
 
General Industry 2014 ppe newsletter
General Industry 2014 ppe newsletterGeneral Industry 2014 ppe newsletter
General Industry 2014 ppe newsletter
 
OSHA regulations Fall protection
OSHA regulations Fall protection OSHA regulations Fall protection
OSHA regulations Fall protection
 
Gi2013 introduction to safety
Gi2013 introduction to safetyGi2013 introduction to safety
Gi2013 introduction to safety
 
1926 power transmission fall issues 2014
1926 power transmission fall issues 20141926 power transmission fall issues 2014
1926 power transmission fall issues 2014
 
Scaffold safety email
Scaffold safety emailScaffold safety email
Scaffold safety email
 
Welding Safety 2014
Welding Safety 2014Welding Safety 2014
Welding Safety 2014
 
Ladder safety
Ladder safetyLadder safety
Ladder safety
 

Kürzlich hochgeladen

A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaShree Krishna Exports
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...amitlee9823
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
A305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdfA305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdftbatkhuu1
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 

Kürzlich hochgeladen (20)

A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
Best Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in IndiaBest Basmati Rice Manufacturers in India
Best Basmati Rice Manufacturers in India
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
Call Girls Jp Nagar Just Call 👗 7737669865 👗 Top Class Call Girl Service Bang...
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
A305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdfA305_A2_file_Batkhuu progress report.pdf
A305_A2_file_Batkhuu progress report.pdf
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 

Seismic technical guide, hanger wire

  • 1. Technical Document Seismic Technical Guide Hanger Wire Attachment The International Building Code (IBC), through references to ASCE/SEI 7 Minimum Design Loads for Buildings and Other Structures, American Society of Civil Engineers/Structural Engineering Institute (ASCE/SEI), The CISCA Guidelines for Zones 3-4, The CISCA Guidelines for Zones 0-2, and ASTM International E 580/E 580M Standard Practice for Installation of Ceiling Suspension Systems for Acoustical Tile and Lay-in Panels in Areas Subject to Earthquake Ground Motions, defines the requirement for hanger wire and their supports and attachment methods. However, there are exceptions and the application of hanger wires in a seismic design category can meet code requirements in different ways. USG® recommends that the design team, consulting engineers and code officials work together to analyze these factors and determine the appropriate construction and application of hanger wire attachment. Because codes continue to evolve, check with local officials prior to designing and installing a suspension system. Guidelines – 12-gauge, galvanized, soft-annealed steel wire – Manufactured in accordance with ASTM A641 – Meets or Exceeds Federal Specification QQ-W-461H Note: 12-gauge hanger wire produced by USG meets these requirements. Performance Data 12-Gauge Wire Wire Tie Failure / Pullout Load Typical 3 wrap tie1 270 lbs. Tight 3 wrap tie 358 lbs. Yields 424 lbs. Ultimate load +550 lbs. Tensile Strength (Ksi) 80 max. 1 Per ASTM C636 Note: Tight wrap typically consists of three complete wraps within 1 in. Some jurisdictions may require four complete wraps for bracing wires. These requirements may vary by jurisdiction. Splice Options Hanger wire splices are typical when the ceiling drop is greater than the length of the wire available and are allowed in seismic ceiling construction. The industry standard is to loop and tie the wire ends with three tight turns, or use a square knot. The square knot is the stronger of the two options at 550 lbs. versus 350 lbs. for the loop and tie option. 12-Gauge Wire Splice Wire Tie Failure Loop and Tie 350 lbs. Square Knot 550 lbs. Note: Accessories by others for securing hanger wire splices should be evaluated for pullout and strength.
  • 2. Application Hanger Wire Splices Loop and Tie Application Step 1 Connect the hanger wire ends together through two loops. Step 2 Wrap the hanger wire ends securely around itself with three complete turns within 1 in. Square Knot Application Step 1 Create an approximate 5 in. bend in the end of each hanger wire Step 2 With the short ends opposed, bring the right-hand end over the left-hand and loop the short end under and around the left-hand end, as shown. Step 3 Loop the left-hand short end back up and around the right-hand loop, with the left-hand end over the right-hand end and bring the left-hand end under the loop of the right-hand end, as shown. Step 4 Draw the knot tight. Step 5 Wrap the hanger wire ends securely around itself with three complete turns within 1 in. Note: In the symmetry of the knot, the wire piece on the left emerges parallel from below the other loop, while the wire piece on the right emerges parallel from above the other loop. This appearance confirms you have tied the square knot correctly. 2
  • 3. Application Attachment to Tee Insert the hanger wire ends through a wire hole in the tee and wrap the wire end securely around itself with three complete turns within 3 in. Ensure the remaining wire end is secured so that it does not interfere with the place- ment of ceiling panels. USG Donn® main tees are produced with round hanger wire holes in the tee web at regular intervals. There are also rectangular (convenience) holes located in the tee bulb at regular intervals. The typical location for the hanger and bracing (splay) wires is in the round holes, but the rectangular (convenience) holes may also be used when needed. We have load tested the rectangular (convenience) holes located in the tee bulb with 12 ga. hanger wire on a 45° angle. The failure load is in excess of 400 lbs. This far exceeds the 200 lb. minimum prescribed by the code for the connections of the bracing (splay) wires. Note: USG has qualified the use of the rectangular (convenience) holes located in the tee bulb through comparison testing by seismic shake-table analysis. In these tests the rectangular (convenience) holes located in the tee bulb were used for all hanger wire attachments to the tee. Round Hanger Wire Hole Attachment Round Hanger Wire Hole Attachment Rectangular (Convenience) Hole Attachment Rectangular (Convenience) Hole Attachment hanger wire hanger wire round hanger rectangular wire hole convenience hole 3
  • 4. Application Anchorage The International Building Code (IBC), through references to ASCE/SEI 7 Minimum Design Loads for Buildings and Other Structures, American Society of Civil Engineers/Structural Engineering Institute (ASCE/SEI), defines the requirements for component anchorage. The requirements are as follows: “Component attachments shall be bolted, welded, or otherwise positively fastened without consideration of frictional resistance produced by the effects of gravity. A continuous load path of sufficient strength and stiffness between the component and the supporting structure shall be provided. Local elements of the structure including connections shall be designed and constructed for the component forces where they control the design of the elements or their connections. Anchors in Concrete or Masonry Anchors in concrete shall be designed in accordance with Appendix D of ACI 318. Anchors in masonry shall be designed in accordance with ACI 530. Anchors shall be designed to be governed by the tensile or shear strength of a ductile steel element. Exception: Anchors shall be permitted to be designed so that the attachment that the anchor is connecting to the structure undergoes ductile yielding at a load level corresponding to anchor forces not greater than their design strength, or the minimum design strength of the anchors shall be at least 2.5 times the factored forces transmitted by the component. Post-installed Anchors Post-installed anchors in concrete shall be pre-qualified for seismic applications in accordance with ACI 355.2 in Concrete and Masonry or other approved qualification procedures. Post-installed anchors in masonry shall be pre-qualified for seismic applications in accordance with approved qualification procedures. Multiple Attachments Determination of force distribution of multiple attachments at one location shall take into account the stiffness and ductility of the component, component supports, attachments, and structure and the ability to redistribute loads to other attachments in the group. Designs of anchorage in concrete in accordance with Appendix D of ACI 318 shall be considered to satisfy this requirement. 4
  • 5. Application Anchorage Power Actuated Fasteners Power actuated fasteners in concrete or steel shall not be used for sustained tension loads exceeding 100 lb (445 N) or for brace applications in Seismic Design Categories D, E, or F unless approved for seismic loading. Power actuated fasteners in steel are permitted in Seismic Design Category D, E or F if the gravity tension load on any fastener does not exceed 250 lbs (1123 N) unless approved for seismic loading. Power actuated fasteners in masonry are not permitted unless approved for seismic loading. Exception: Power actuated fasteners in concrete used for support of acoustical tile or lay-in panel suspended ceiling applications and distributed systems where the service load on any individual fastener does not exceed 90 lb (400 N). Power actuated fasteners in steel where the service load on any individual fastener does not exceed 250 lb (1,112 N). Power Actuated Fasteners for Acoustical Tile or Lay-In Panel Suspended Ceiling Applications Seismic Design Category D, E or F Concrete Steel Allowed for sustained tension loads exceeding 90 lb (400 N) Allowed where gravity tension load on any fastener does not exceed 250 lbs (1123 N) Note: The load for suspension system hanger wires will not exceed 64 lbs. based on hanger wires spaced 4 ft. o.c. along heavy duty main tees designed to carry 16 lbs/l.f. Also ASCE7-10 contains an exception allowing power actuated fasteners for support of acoustical tile or lay-in panel suspended ceiling applications. ASCE7-02 and ASCE7-05 does not contain this exception. Please check with the authority having jurisdiction as interpretation and enforcement of this may vary. Friction Clips Friction clips in Seismic Design Categories D, E or F shall not be used for supporting sustained loads in addition to resisting seismic forces. C-type beam and large flange clamps are permitted for hangers provided they are equipped with restraining straps equivalent to those specified in NFPA 13 Section 9.3.7. Lock nuts or equivalent shall be provided to prevent loosening of threaded connections. 5
  • 6. Construction Attachment to Structure Construction Attachment to Structure Wood Wood Wood Vertical Splay / Bracing Vertical Splay Wood Joist or Rafter Wood Joist Wood Joist or Rafter of Rafter 3" max. 1/4" diameter closed eye screw with full thread embedment (11/4" min.) wood joist 12 ga. hanger wire 3" x 1/4" diameter closed eye screw with 1" min. 12 ga. hanger penetration into wood wire min. 3 turns 12 ga. hanger wire Wood Joist or Rafter Wood Joist (3) 11/2" x 9 ga. staples or (3) 11/2" x 9 ga. staples or (3) stronghold "J" nails at (3) stronghold "J" nails at each wire loop each wire loop 1" min. 1" min. wood joist wood joist 12 ga. hanger wire 12 ga. hanger wire Wood Truss Wood Truss Wood Truss web member web member bottom chord bottom chord 12 ga. hanger wire saddle tie saddle tie 12 ga. hanger wire Note: Hanger or bracing wire anchors to the structure should be installed in such a manner that the direction of the anchor aligns as closely as possible with the direction of the wire. 6
  • 7. Construction Attachment to Structure Wood Bottom of Wood Joist Vertical Typical Saddle Tie Splay Bottom of saddle tie required for all Wood Joist widths greater than 1/2" Note: saddle tie has double loop at support 12 ga. hanger wire min. 3 turns Bottom of Wood Joist Not Applicable 1/4" diameter drilled hole typical saddle tie with double loop at support 2" min. hanger wire Wood I-Joist Wood I-Joist Wood I-Joist wood I-joist wood I-joist 12 ga. hanger wire add 2 1/2" x 20 ga. stud* w/ 12 ga. hanger wire add 2 1/2" x 20 ga. stud* w/ min. 3 turns (1) #10 x 1" wood screw to min. 3 turns (1) #10 x 1" wood screw to each of 3 joists. place stud flat each of 3 joists. place stud flat and within 6" of splay wire. and within 6" of splay wire. * alternate: * alternate: 2 x 4 flat with 1-10d or 1-#10 x 3" 2 x 4 flat with 1-10d or 1-#10 x 3" screw to each of 3 truss bottom flanges screw to each of 3 truss bottom flanges Wood I-Joist Bottom Flange Wood I-Joist Bottom Flange Wood I-Joist Bottom Flange Note: Do not insert screw eyes parallel to laminations 1/4" diameter closed 1/4" diameter closed eye screw with 11/4" min. penetration eye screw with 11/4" align with brace wire min. penetration at bottom flange 12 ga. hanger wire min. 3 turns 12 ga. hanger wire min. 3 turns 1" min. Note: Hanger or bracing wire anchors to the structure should be installed in such a manner that the direction of the anchor aligns as closely as possible with the direction of the wire. 7
  • 8. Construction Attachment to Structure Concrete Concrete Vertical Concrete Splay / Bracing Vertical Clip Attachment Splay Attachment Clip Clip 5/16" drill-in expansion anchor 5/16" drill-in expansion anchor Attachment minimum or approved fastener minimum or approved fastener structural concrete 45˚ max. 12 ga. metal angle structural concrete steel strap 1" wide x 2" long x 12 ga. min. 3 turns 3 turns 12 ga. hanger wire 12 ga. hanger wire Clip Attachment Clip Attachment 5/16" drill-in expansion anchor 5/16" drill-in expansion anchor minimum or approved shot pins minimum or approved shot pins structural concrete 45˚ max. 12 ga. metal angle structural concrete steel strap 1" wide x 2" long x 12 ga. min. 3 turns 3 turns 12 ga. hanger wire 12 ga. hanger wire Cast In Place Concrete Cast In Place Concrete wire pigtail w/ 2" dia. loop & 4" tail structural concrete Cast In Place Concrete 45˚ max. wire pigtail w/ 2" dia. loop & 4" tail 12 ga. hanger wire structural concrete Cast In Place Concrete 12 ga. hanger wire wire pigtail w/ 2" dia. loop & 4" tail structural concrete 12 ga. hanger wire 45˚ max. Note: Hanger or bracing wire anchors to the structure should be installed in such a manner that the direction of the anchor aligns as closely as possible with the direction of the wire. 8
  • 9. Construction Attachment to Structure Steel Steel Splay / Bracing Vertical Steel Splay Open-Web Steel Joist Open-Web Vertical top chord Steel Joist Open-Web Steel Joist web member 12 ga. hanger wire (wrap and tie around tops of web members) bottom chord Open-Web Steel Joist 12 ga. hanger typical saddle tie top chord wire min. 3 turns Attach hanger wire to bottom chord only 12 ga. hanger wire when designed to carry the vertical load of (wrap and tie around the suspended ceiling system. tops of web members) Steel Roof Deck Steel Roof Deck Steel Roof Deck 2 #8 x 1/2" #3 x 12" rebar self tapping screws 20 ga. min. deck hanger wire tie to #3 20 ga. min. deck rebar with three wraps steel strap 3" wide around rebar and one x 4" long x 12 ga. minimum wrap around wire 12 ga. hanger wire Steel Deck With Insulation Fill min. 3 turns Steel Deck With #3 rebar x length Insulation Fill required to cover min. of 4 high corrugations non-structural concrete fill Not Applicable steel deck 12 ga. hanger wire min. 3 turns Steel Beam Steel Beam Steel Beam structural concrete structural concrete structural steel structural steel 12 ga. metal angle 12 ga. metal angle 12 ga. splayed seismic bracing wire 12 ga. hanger wire Note: Hanger or bracing wire anchors to the structure should be installed in such a manner that the direction of the anchor aligns as closely as possible with the direction of the wire. 9
  • 10. Construction Attachment to Structure Steel Vertical Steel Deck With Concrete Fill Splay Steel Deck With structural concrete fill Concrete Fill shot-in or expansion steel deck anchor with eye bolt 12 ga. hanger wire min. 3 turns Steel Deck With Concrete Fill Steel Deck With Concrete Fill structural concrete fill structural concrete fill steel deck steel deck 5/16"(min.) drill-in 12 ga. hanger wire 12 ga. hanger wire embedded in concrete expansion anchor. steel min. 3 turns strap 12 ga. x 1" wide min. Steel Deck With Concrete Fill structural concrete fill shot-in anchor 3/4" min. metal steel deck angle 12 ga. x 3/4" wide min. 12 ga. hanger wire min. 3 turns Note: Hanger or bracing wire anchors to the structure should be installed in such a manner that the direction of the anchor aligns as closely as possible with the direction of the wire. 10
  • 11. Testing and Inspection Post-installed anchors shall be tested when deemed necessary by the authority having jurisdiction. Testing shall be performed by an accepted testing facility, unless approval of an alternative is obtained in advance from the engineer of record (EOR) for the project. If any anchor fails testing, test all anchors of the same type, not previously tested until twenty (20) consecutive anchors pass, then resume the initial test frequency. The anchors tested shall be only those anchors installed by the same trade. The authority having jurisdiction shall define acceptance/failure criteria. The test values and all appropriate criteria shall be shown on the contract documents. The test load may be applied by any method that will effectively measure the tension in the anchor, such as direct pull with a hydraulic jack, calibrated spring loaded devices, or a calibrated torque wrench except that displacement-controlled anchors such as drop-ins shall not be tested using a torque wrench. When field testing of component anchorage is required by the authority having jurisdiction, the following criteria shall apply unless otherwise specified: Anchor Type Test Value Percent Tested Support (Vertical) 200 lbs. in tension 10% Bracing (Splay) 440 lbs. in tension 50% Note: Drilled-in or shot-in anchors typically require special approval prior to use in pre-stressed concrete. Note: Shot-in anchors in concrete are not permitted for bracing wires. 11
  • 12. Product Information Purpose L.A. Research Report Safety First! See usg.com for the most up-to- This seismic technical guide Compliance Follow good safety/industrial date product information. (STG) is intended as a resource Donn brand suspension systems hygiene practices during for design professionals, to manufactured by USG Interiors, installation. Wear appropriate Installation promote more uniform criteria Inc., have been reviewed and personal protective equipment. Must be installed in compliance for plan review and jobsite are approved by listing in the Read MSDS and literature with ASTM C636, ASTM E580, inspection of projects. This following L.A. Research Report before specification and CISCA, and standard industry STG indicates an accept- number: 25764. installation. practices. able method for achieving compliance with applicable Notice Code Compliance We shall not be liable for codes and regulations, although The information presented incidental and consequential other methods proposed by is correct to the best of our damages, directly or indirectly design professionals may be knowledge at the date of sustained, nor for any loss considered and adopted. issuance. Because codes caused by application of these continue to evolve, check ICC Evaluation Service, Inc., goods not in accordance with with a local official prior to Report Compliance current printed instructions or designing and installing a ceiling Suspension systems for other than the intended use. system. Other restrictions and manufactured by USG Interiors, Our liability is expressly limited to exemptions may apply. This Inc., have been reviewed and replacement of defective goods. is only intended as a quick are approved by listing in Any claim shall be deemed reference. ICC-ES Evaluation Report 1222. waived unless made in writing Evaluation Reports are subject to us within thirty (30) days from to reexamination, revision and date it was or reasonably should possible cancellation. Please have been discovered. refer to usgdesignstudio.com or usg.com for current reports. Manufactured by usg.com The following are trademarks of USG SC2522/rev. 9-10 USG Interiors, Inc. seismicceilings.com Interiors, Inc. or a related company: © 2010, USG Interiors, Inc. 550 West Adams Street sustainableceilings.com Donn, USG, USG in stylized letters. Printed in U.S.A. Chicago, IL 60661 usgdesignstudio.com