- 1. © 2013 pmwares
Managing multiple projects using
MS Project 2010
Free Webinar – 03-September-2013
Vivek Prakash
1
Use this presentation with the recording of the webinar available at following URL
http://www.youtube.com/pmwares or
http://pmwares.com/content/recordings-pmwares-free-webinars
- 2. © 2013 pmwares
Objectives
How can I add a sub project which is managed
by another team member in my project to track
complete project together?
How can I add, see status and track all my
projects in one master project?
How can I effectively share my resources across
projects, see their allocations, detect if there is
any over allocation and optimize usages?
2
- 3. © 2013 pmwares
Main Project:
Development Module.mpp
Sub Projects:
System Integration Testing.mpp
3
Add a sub project to a main project
We need to add sub project into the
main project
Create cross dependencies
- 4. © 2013 pmwares
Master Project:
Master Project - “Master Project.mpp”
Sub Projects:
Sub Project 1: “Development Module.mpp”
Sub Project 2: Create “System Integration Testing.mpp”
4
Creating a Master Project
Create a master project and add
projects to it
Create dependencies across projects
- 5. © 2013 pmwares
Unlinking Master and Sub Projects
5
Uncheck the “Link to project” check box disconnect
master and sub projects
Select inserted project Goto Task Tab Click Information Advance Tab
- 6. © 2013 pmwares
Making Subproject Read-Only in Master Project
6
Select inserted project Task Information Advance Tab
Check the Read Only check box to make Subproject read
only in Master Project
- 7. © 2013 pmwares
Resources Pool:
Resource Pool.mpp
Projects:
Use resources into “Development Module.mpp”
Use resources into “System Integration Testing.mpp”
7
Creating a Resource Pool
Create a resource pool and use
resources from pool into different
projects
- 8. © 2013 pmwares
Points to ponder
File containing resource list is called Resource Pool and file that is using
resource pool is called Sharer
If Share Resources option is disabled, it means you are using enterprise setup
and resource pool facility is not available. Use enterprise resource pool
If you close the resource pool file, you will find resources that are not used in
sharer are disappeared from sharer
If you open Resource Pool file without opening any Sharer file, you will be
prompted with three options
Open Resource Pool read only
Open Resource Pool in read-write mode but do not allow update of
resource pool through Sharer
Open Resource Pool in read-write mode and allow update of resource pool
through Sharer
If you open Sharer file without opening Resource Pool file, you will be
prompted to open Resource Pool as well
8
- 10. © 2013 pmwares
From Sharer
Open both Resource Pool and
Sharer files
In Sharer, Select Resource Tab
Resource Pool Share
Resources
Select “Use own resources"
From Resource Pool
Open both Resource Pool and
Sharer files
In Resource Pool, Select Project
Tab Resource Pool Share
Resources
Select the file to be
disconnected
Click “Break Link”
10
Disconnecting Resource Pool from Sharer
- 11. © 2013 pmwares
Linking tasks across projects
Linking tasks across projects without
creating a master projects
You have multiple projects and a task in one
project has dependency on a task in other
project
You do not intend to create a master project or
add a project into another projects
11
- 12. © 2013 pmwares 12
Linking tasks across projects
Open both the projects and select
New Window
Select both the project & click ok
Define dependenciesClose the window (new one)
- 13. © 2013 pmwares
To watch recording of earlier webinars, visit
http://www.pmwares.com/ and goto Tools & Resources
Contact Vivek Prakash at vivek@pmwares.com