2. Review of design criteria of existing system of
sewerage system.
Design of sewerage system.
Cost estimation of sewerage system as per
Delhi Schedule of Rates 2012 (DSR).
3. To transport water or waste water from
one location to another by means of
connecting pipes through gravity.
To provide a hygienic and healthy
environment.
Increases the aesthesis and property
value.
5. • Collects sanitary sewage & storm water run off in a single pipe system.
• Can cause serious water pollution problems due to combined sewer
overflows
• Caused by large variations in flow between dry and wet weather.
• This type of sewer design is no longer used in building new communities.
6. • Used for transporting sewage from houses and commercial buildings
• Sanitary sewers serving industrial areas also carry Industrial sewage.
• Sanitary sewage is collected with the help of sanitary sewer line
• The sanitary sewer is attached to a main sewer.
• The main sewer runs directly to the sewage treatment plant.
7. • A storm sewer collects storm water with the help of gutter & catch basin
• Gutter allow the storm water to drain from the street directly into the storm
sewer.
15. Design Period of Civil Work (Trunk,
Main Branch Sewer & Appurtenances) - 30 Years
Sewage Generated - 80% of Total Water supply
Flow Assumptions - Minimum Flow Varies
from 1/3 to ½ of average flow
Ground Water Infiltration -500 to 5,000 litres/km/day
Manning’s Roughness Coefficient - 0.013
Velocity of Flow - 0.60 m/s to 3.0 m/s
Rate of Flow - 80% Running Full
Minimum Size of Sewer - 150 mm
16. Minimum gradient for sewers shall be designed to
fulfill the requirement of self cleansing velocity
Present Peak Flow
(Cumec)
Recommended slope
1 in
0.002 165
0.003 250
0.005 320
0.010 500
0.015 770
0.020 835
0.030 1000
18. MANNINGS FORMULA
and
Q= A x V
Where
Q = Discharge
S = Slope of hydraulic gradient
D = Internal dia of pipe line
R = Hydraulic radius in m
V = Velocity in m/s
n = Manning's roughness coefficient
19. The Problem has been taken from the Manual on
Sewerage and sewage Treatment-1993 of Central Public
Health and Environmental Engineering Organization
(CPHEEO).
Layout Plan of Manual.
Ground Levels of various nodes.
Total Population of the Area is two Lacs.
Total Area = 101.02 ha.
20. Average Length of sewer line between Manhole = 30 m
Water supply = 150 L/C/day
Total Population = 2 lacs
Total Length of sewer line = 7275.12 m
Population Equivalent = (200000/7275.12)
= 27.49 Persons/m
Rate of Infiltration = 5000 Lit/Km/Day
Minimum cover to be provided over
the crown of the sewer = 1.0 m
Minimum velocity in sewer at peak flow = 0.6 m/s
Maximum Velocity in sewer = 2 m/s
Minimum size of the sewer = 150 mm
Peak factor = 3.0
21. Section From MH-69 to MH-70
Diameter of Sewer Line = 150 mm
Min. Velocity = 0.60 m/s
Slope of the sewer Line = 1 in 160
Detail Design
22. Layout Plan of the Area
Sewer Network
Hydraulic Design Sewer Lines
Colour Coding Plan of the Network
Typical L-section of Sewer Line
Typical Details of Appurtenances
Typical Details of Excavation Pipe Bedding
23. Sl.
No.
Description
of Item
Maximum Minimum
1 Ground Level 39.00 Mtr. 32.00 Mtr.
2 Discharge 0.625 Cumec 0.0027 Cumec
(2.70 Lit.)
3 Slope 1 in 1100 1 in 100
4 Velocity 1.83 m/s 0.61 m/s
5 Dia of Pipe 1000 mm 150 mm
25. Circular type manhole 0.91m
internal diameter (at
bottom) beyond 0.91m to
1.67m
129
Circular type manhole 1.22m
internal diameter (at
bottom) beyond 1.68 m to
2.29 m :
67
Circular type manhole 1.52 m
internal diameter (at
bottom) beyond 2.30 m :
60
26. Total Cost of Excavation(Rs.) = 25.16 Lacs
Total Cost Of Manholes (Rs.) = 33.83 Lacs
Total Cost of Pipes (Rs.) = 33.08 Lacs
Total Cost of Foot Rest (Rs.) = 3.69 Lacs
Cost of P.C.C. (1.2.4) (Rs.) = 1.69 Lacs
Total cost of the Project (Rs.) = 97.46 Lacs
Avg. cost / Km (Rs.) = 13.40 Lacs
27. Manual on sewerage and sewage treatment
(Second edition-1993)
Manual on sewerage and sewage treatment (Final
Draft-2012)
Delhi Schedule of Rates – 2012,
Delhi analysis of Rates Vol. I & II,
Environmental Engineering Vol. II, by S.K.Garg
(Twenty Second Edition)
Basic Environmental Engineering by Jeery
A.Nathson.