Disha NEET Physics Guide for classes 11 and 12.pdf
Site planning-storage-facility.
1. STEPS
SITE
PLANNING
15 days 25-DAYS
Backfill
GROUND FLOOR
•10 DAYS
EXCAVATION 25 days
FORMWORK AND STEEL
REBARRING 45 days
ROOFING 35
DAYS
FOOTING DAYS
1 35 days
2 35 days COLUMN 1 => 35
3 35 days
4 35 days COLUMN 2 => 35
COLUMN 3 => 35
COLUMN 4 => 35
Here is a site planning that I designed for a practice in one of
the lesson of a Coursera course in 2016.
It can show all the details to follow for building a Storage
Facility. We can see the descriptions and the amount of days
that could be necessary to build this Store Facility. This type of
design can help those who are interesting in building this kind
of project. I am very happy about this Site Planning
presentation, and I am very excited about the result I got
presenting this as my task at Coursera Course.