PEAKING
• The peaking is the adjustment and checking for the roundness and the curvature of the shell plates around the
vertical joints.
• Peaking as an inspection point of view we check before & after the welding of Vertical joint to find the extend of
distortion happened after welding. It has a tolerance of +/- mm
• It is mainly initiated by material rolling and/or welding stresses during new construction. Occasionally it can get
worse in service.
Peaking Measurement
The peaking of each tank shell shall be measured by a horizontal sweep board made of either solid wood/plywood or
may be made of any metal sheet; however the sweep board shall be stiff enough so that it will not bend or sag
otherwise the results will be erroneous.
The sweep board shall be true to the radius of the tank, either inside radius or outside radius. For measuring from
inside the tank, the sweep board shall be convex shaped in one side and straight on the other side. For measuring
from outside the tank, the sweep board shall be concave shaped in one side and straight on the other side. The length
of the sweep board shall be 36 inches (915mm) minimum. See sketch below:
BANDING
• Banding is the adjustment and checking the straightness and verticality for the shell plates around horizontal
joint (between shell courses) and it is also done before and after welding .
• Banding as an inspection point of view we check after the welding of Banding joint to find the extend of
distortion happened after welding. It has a tolerance of +/- mm
• It is less common and almost always the result of construction (or repair/alteration/reconstruction)
inaccuracies.
Banding Measurement
The banding of each tank shell shall be measured by a vertical sweep board made of either solid wood/plywood or
may be made of any metal sheet; however the sweep board shall be stiff enough so that it will not bend or buckle
otherwise the results will be erroneous.
The sweep board shall be truly straight. Measurements can be taken either from inside or from outside of the tank.
The length of the sweep board shall be 36 inches (915mm) minimum.
Procedure for Peaking survey:
• Visually inspect the tank circumference either from inside or from outside for any visible signs of deformation.
A high-power search light may be used and held parallel to the surface with the torch touching the surface may aid
in finding the deformations easily from inside the tank.
• Mark the geographical direction (north/ south etc.) or mark location in degrees to identify each measured location.
• Put the horizontal sweep board truly horizontal on the inside or outside surface as applicable on the tank shell
course. Check the gap between the sweep board and the tank shell and note down the value if there is
considerable gap (beyond inches or 13mm). For a more accurate positioning of the sweep board, slide the board
horizontally to fit it properly to the tank shell. A torch light & scale/measuring tape may be used to assess the gap
between the sweep board and the tank shell.
• The peaking shall preferably be measured on the vertical welds of the tank shells; however it can be measured on
any portions of the tank shell if there are visible signs of deformation.
• Minimum number of locations is not specified in the applicable codes/standards however as a good practice it
shall be 8 nos.
Procedure for Banding survey:
• Visually inspect the tank circumference either from inside or from outside for any visible signs of deformation. A high-
power search light may be used and held parallel to the surface with the torch touching the surface may aid in finding
the deformations easily from inside the tank.
• Mark the geographical direction (north/ south etc.) or mark location in degrees to identify each measured location.
• Put the vertical sweep board truly vertical on the inside or outside surface as applicable on the tank shell course.
Check the gap between the sweep board and the tank shell and note down the value if there is considerable gap
(beyond 1 inch or 25.4mm). For a more accurate positioning of the sweep board, slide the board vertically to fit it
properly to the tank shell. A torch light & scale/measuring tape may be used to assess the gap between the sweep
board and the tank shell.
• The banding shall preferably be measured on the horizontal/circumferential welds of the tank shells; however it can
be measured on any portions of the tank shell if there are visible signs of deformation.
• Minimum number of locations is not specified in the applicable codes/standards however as a good practice it shall
be 8 nos.
ACCEPTANCE CRITERIA AS PER API 650
• Deviations (Peaking) at vertical weld joints shall not exceed 13 mm (1/2 in.).
• Deviations (Banding) at horizontal weld joints shall not exceed 13 mm (1/2 in.)
ACCEPTANCE CRITERIA AS PER API 653
• Deviations (Peaking) at vertical weld joints shall not exceed 13 mm (1/2 in.).
• Deviations (Banding) at horizontal weld joints shall not exceed 25 mm (1 in.)

Weitere ähnliche Inhalte

Was ist angesagt?

Was ist angesagt? (20)

Api 653 study guide
Api 653 study guideApi 653 study guide
Api 653 study guide
 
38785106 api-tank-design
38785106 api-tank-design38785106 api-tank-design
38785106 api-tank-design
 
Api 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answersApi 650 & 653 questions closed book with answers
Api 650 & 653 questions closed book with answers
 
QC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdfQC Welding Inspector Interview Question & Answers.pdf
QC Welding Inspector Interview Question & Answers.pdf
 
Oil chalk test-Penetrating Oil test
Oil chalk test-Penetrating Oil testOil chalk test-Penetrating Oil test
Oil chalk test-Penetrating Oil test
 
Piping inspector questions 1
Piping inspector questions  1 Piping inspector questions  1
Piping inspector questions 1
 
Chris brooks storage tanks inspection, maintenance and failure
Chris brooks   storage tanks inspection, maintenance and failureChris brooks   storage tanks inspection, maintenance and failure
Chris brooks storage tanks inspection, maintenance and failure
 
Inspection manual for piping
Inspection manual for pipingInspection manual for piping
Inspection manual for piping
 
Welding Inspection
Welding InspectionWelding Inspection
Welding Inspection
 
Shell rolling procedure
Shell rolling procedureShell rolling procedure
Shell rolling procedure
 
WPS & WPQ
WPS & WPQWPS & WPQ
WPS & WPQ
 
Tank design - powerpoint slides
Tank design - powerpoint slidesTank design - powerpoint slides
Tank design - powerpoint slides
 
Asme sec ix overview
Asme sec ix overviewAsme sec ix overview
Asme sec ix overview
 
Destructive test
Destructive testDestructive test
Destructive test
 
Aws d1.1 guides
Aws d1.1 guidesAws d1.1 guides
Aws d1.1 guides
 
Presentation on wpqr wps asme_ix
Presentation on wpqr wps asme_ixPresentation on wpqr wps asme_ix
Presentation on wpqr wps asme_ix
 
Piping sample report
Piping sample reportPiping sample report
Piping sample report
 
API_510_for_Exam.pdf
API_510_for_Exam.pdfAPI_510_for_Exam.pdf
API_510_for_Exam.pdf
 
Asme sec viii div 1 s
Asme sec viii div 1 sAsme sec viii div 1 s
Asme sec viii div 1 s
 
Welding defects
Welding defectsWelding defects
Welding defects
 

Ähnlich wie Peaking and Banding Survey Procedures

casing and cementing _ ADCO drilling manual
casing and cementing _ ADCO drilling manualcasing and cementing _ ADCO drilling manual
casing and cementing _ ADCO drilling manualEnriqueFigueroa42
 
Good practices in PSC work.ppt
Good practices in PSC work.pptGood practices in PSC work.ppt
Good practices in PSC work.pptssusercaf1a41
 
Inspection of Heat exchanger .pdf
Inspection of Heat exchanger .pdfInspection of Heat exchanger .pdf
Inspection of Heat exchanger .pdfTusharNayak32
 
Inspection of heat exchanger during manufacturing
Inspection of heat exchanger  during manufacturingInspection of heat exchanger  during manufacturing
Inspection of heat exchanger during manufacturingKhurramYousaf7
 
driling lecture 3.pdf
driling lecture 3.pdfdriling lecture 3.pdf
driling lecture 3.pdfnasastore
 
Maintenance of pocket type journal bearing D500 steam Turbine
Maintenance of pocket type journal bearing D500 steam TurbineMaintenance of pocket type journal bearing D500 steam Turbine
Maintenance of pocket type journal bearing D500 steam TurbineFaisal Nadeem
 
Method of manual gauging
Method of manual gaugingMethod of manual gauging
Method of manual gaugingPrajapati_15
 
Mounting Instructions | C-More Serendipity Red Dot Sights | Optics Trade
Mounting Instructions | C-More Serendipity Red Dot Sights | Optics TradeMounting Instructions | C-More Serendipity Red Dot Sights | Optics Trade
Mounting Instructions | C-More Serendipity Red Dot Sights | Optics TradeOptics-Trade
 
Instruction Manual C-MORE Serendipity Mounting | Optics Trade
Instruction Manual C-MORE Serendipity Mounting | Optics TradeInstruction Manual C-MORE Serendipity Mounting | Optics Trade
Instruction Manual C-MORE Serendipity Mounting | Optics TradeOptics-Trade
 
Gaskets, types, construction, and application usage
Gaskets, types, construction, and application usageGaskets, types, construction, and application usage
Gaskets, types, construction, and application usagessusereb45b7
 
removable partial denture survey lines, path of insertion, guide planes
removable partial denture survey lines, path of insertion, guide planesremovable partial denture survey lines, path of insertion, guide planes
removable partial denture survey lines, path of insertion, guide planesrazan reyadh
 
Best practices day 4 am new
Best practices day 4 am newBest practices day 4 am new
Best practices day 4 am newAhmed Radwan
 
Jigs & fixture turning
Jigs & fixture turningJigs & fixture turning
Jigs & fixture turningengdida
 
Design and fabrication of bending machine
Design and fabrication of bending machineDesign and fabrication of bending machine
Design and fabrication of bending machineparamesr2020
 

Ähnlich wie Peaking and Banding Survey Procedures (20)

Well head replacement
Well head replacementWell head replacement
Well head replacement
 
Gauges ppt.pdf .
Gauges ppt.pdf                              .Gauges ppt.pdf                              .
Gauges ppt.pdf .
 
casing and cementing _ ADCO drilling manual
casing and cementing _ ADCO drilling manualcasing and cementing _ ADCO drilling manual
casing and cementing _ ADCO drilling manual
 
Good practices in PSC work.ppt
Good practices in PSC work.pptGood practices in PSC work.ppt
Good practices in PSC work.ppt
 
Inspection of Heat exchanger .pdf
Inspection of Heat exchanger .pdfInspection of Heat exchanger .pdf
Inspection of Heat exchanger .pdf
 
Inspection of heat exchanger during manufacturing
Inspection of heat exchanger  during manufacturingInspection of heat exchanger  during manufacturing
Inspection of heat exchanger during manufacturing
 
Kiln shell
Kiln shellKiln shell
Kiln shell
 
BHA.pdf
BHA.pdfBHA.pdf
BHA.pdf
 
driling lecture 3.pdf
driling lecture 3.pdfdriling lecture 3.pdf
driling lecture 3.pdf
 
Maintenance of pocket type journal bearing D500 steam Turbine
Maintenance of pocket type journal bearing D500 steam TurbineMaintenance of pocket type journal bearing D500 steam Turbine
Maintenance of pocket type journal bearing D500 steam Turbine
 
Method of manual gauging
Method of manual gaugingMethod of manual gauging
Method of manual gauging
 
Mounting Instructions | C-More Serendipity Red Dot Sights | Optics Trade
Mounting Instructions | C-More Serendipity Red Dot Sights | Optics TradeMounting Instructions | C-More Serendipity Red Dot Sights | Optics Trade
Mounting Instructions | C-More Serendipity Red Dot Sights | Optics Trade
 
Instruction Manual C-MORE Serendipity Mounting | Optics Trade
Instruction Manual C-MORE Serendipity Mounting | Optics TradeInstruction Manual C-MORE Serendipity Mounting | Optics Trade
Instruction Manual C-MORE Serendipity Mounting | Optics Trade
 
Gaskets, types, construction, and application usage
Gaskets, types, construction, and application usageGaskets, types, construction, and application usage
Gaskets, types, construction, and application usage
 
removable partial denture survey lines, path of insertion, guide planes
removable partial denture survey lines, path of insertion, guide planesremovable partial denture survey lines, path of insertion, guide planes
removable partial denture survey lines, path of insertion, guide planes
 
safety while prestressed concrete
safety while prestressed concretesafety while prestressed concrete
safety while prestressed concrete
 
Surveyor
SurveyorSurveyor
Surveyor
 
Best practices day 4 am new
Best practices day 4 am newBest practices day 4 am new
Best practices day 4 am new
 
Jigs & fixture turning
Jigs & fixture turningJigs & fixture turning
Jigs & fixture turning
 
Design and fabrication of bending machine
Design and fabrication of bending machineDesign and fabrication of bending machine
Design and fabrication of bending machine
 

Mehr von Weld Maniac

What is wps important tips regarding to wps
What is wps important tips regarding to wpsWhat is wps important tips regarding to wps
What is wps important tips regarding to wpsWeld Maniac
 
Important qualification ranges must know about welder performance
Important qualification ranges must know about welder performanceImportant qualification ranges must know about welder performance
Important qualification ranges must know about welder performanceWeld Maniac
 
Coating Failures & Defects
Coating Failures & DefectsCoating Failures & Defects
Coating Failures & DefectsWeld Maniac
 
Welding electrodes Classification & baking
Welding electrodes Classification &  bakingWelding electrodes Classification &  baking
Welding electrodes Classification & bakingWeld Maniac
 
A QA/QC ENGINEER MUST KNOW THESE TABLE IN ASME SEC IX
A QA/QC ENGINEER MUST KNOW THESE TABLE IN ASME SEC IXA QA/QC ENGINEER MUST KNOW THESE TABLE IN ASME SEC IX
A QA/QC ENGINEER MUST KNOW THESE TABLE IN ASME SEC IXWeld Maniac
 
CONTINUOUSLY VARIABLE TRANSMISSION - CVT
CONTINUOUSLY VARIABLE TRANSMISSION - CVTCONTINUOUSLY VARIABLE TRANSMISSION - CVT
CONTINUOUSLY VARIABLE TRANSMISSION - CVTWeld Maniac
 

Mehr von Weld Maniac (6)

What is wps important tips regarding to wps
What is wps important tips regarding to wpsWhat is wps important tips regarding to wps
What is wps important tips regarding to wps
 
Important qualification ranges must know about welder performance
Important qualification ranges must know about welder performanceImportant qualification ranges must know about welder performance
Important qualification ranges must know about welder performance
 
Coating Failures & Defects
Coating Failures & DefectsCoating Failures & Defects
Coating Failures & Defects
 
Welding electrodes Classification & baking
Welding electrodes Classification &  bakingWelding electrodes Classification &  baking
Welding electrodes Classification & baking
 
A QA/QC ENGINEER MUST KNOW THESE TABLE IN ASME SEC IX
A QA/QC ENGINEER MUST KNOW THESE TABLE IN ASME SEC IXA QA/QC ENGINEER MUST KNOW THESE TABLE IN ASME SEC IX
A QA/QC ENGINEER MUST KNOW THESE TABLE IN ASME SEC IX
 
CONTINUOUSLY VARIABLE TRANSMISSION - CVT
CONTINUOUSLY VARIABLE TRANSMISSION - CVTCONTINUOUSLY VARIABLE TRANSMISSION - CVT
CONTINUOUSLY VARIABLE TRANSMISSION - CVT
 

Kürzlich hochgeladen

(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Kürzlich hochgeladen (20)

Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 

Peaking and Banding Survey Procedures

  • 1.
  • 2. PEAKING • The peaking is the adjustment and checking for the roundness and the curvature of the shell plates around the vertical joints. • Peaking as an inspection point of view we check before & after the welding of Vertical joint to find the extend of distortion happened after welding. It has a tolerance of +/- mm • It is mainly initiated by material rolling and/or welding stresses during new construction. Occasionally it can get worse in service. Peaking Measurement The peaking of each tank shell shall be measured by a horizontal sweep board made of either solid wood/plywood or may be made of any metal sheet; however the sweep board shall be stiff enough so that it will not bend or sag otherwise the results will be erroneous. The sweep board shall be true to the radius of the tank, either inside radius or outside radius. For measuring from
  • 3. inside the tank, the sweep board shall be convex shaped in one side and straight on the other side. For measuring from outside the tank, the sweep board shall be concave shaped in one side and straight on the other side. The length of the sweep board shall be 36 inches (915mm) minimum. See sketch below:
  • 4. BANDING • Banding is the adjustment and checking the straightness and verticality for the shell plates around horizontal joint (between shell courses) and it is also done before and after welding . • Banding as an inspection point of view we check after the welding of Banding joint to find the extend of distortion happened after welding. It has a tolerance of +/- mm • It is less common and almost always the result of construction (or repair/alteration/reconstruction) inaccuracies. Banding Measurement The banding of each tank shell shall be measured by a vertical sweep board made of either solid wood/plywood or may be made of any metal sheet; however the sweep board shall be stiff enough so that it will not bend or buckle otherwise the results will be erroneous. The sweep board shall be truly straight. Measurements can be taken either from inside or from outside of the tank. The length of the sweep board shall be 36 inches (915mm) minimum.
  • 5. Procedure for Peaking survey: • Visually inspect the tank circumference either from inside or from outside for any visible signs of deformation. A high-power search light may be used and held parallel to the surface with the torch touching the surface may aid in finding the deformations easily from inside the tank. • Mark the geographical direction (north/ south etc.) or mark location in degrees to identify each measured location. • Put the horizontal sweep board truly horizontal on the inside or outside surface as applicable on the tank shell course. Check the gap between the sweep board and the tank shell and note down the value if there is considerable gap (beyond inches or 13mm). For a more accurate positioning of the sweep board, slide the board horizontally to fit it properly to the tank shell. A torch light & scale/measuring tape may be used to assess the gap between the sweep board and the tank shell. • The peaking shall preferably be measured on the vertical welds of the tank shells; however it can be measured on any portions of the tank shell if there are visible signs of deformation. • Minimum number of locations is not specified in the applicable codes/standards however as a good practice it shall be 8 nos.
  • 6. Procedure for Banding survey: • Visually inspect the tank circumference either from inside or from outside for any visible signs of deformation. A high- power search light may be used and held parallel to the surface with the torch touching the surface may aid in finding the deformations easily from inside the tank. • Mark the geographical direction (north/ south etc.) or mark location in degrees to identify each measured location. • Put the vertical sweep board truly vertical on the inside or outside surface as applicable on the tank shell course. Check the gap between the sweep board and the tank shell and note down the value if there is considerable gap (beyond 1 inch or 25.4mm). For a more accurate positioning of the sweep board, slide the board vertically to fit it properly to the tank shell. A torch light & scale/measuring tape may be used to assess the gap between the sweep board and the tank shell. • The banding shall preferably be measured on the horizontal/circumferential welds of the tank shells; however it can be measured on any portions of the tank shell if there are visible signs of deformation. • Minimum number of locations is not specified in the applicable codes/standards however as a good practice it shall be 8 nos.
  • 7. ACCEPTANCE CRITERIA AS PER API 650 • Deviations (Peaking) at vertical weld joints shall not exceed 13 mm (1/2 in.). • Deviations (Banding) at horizontal weld joints shall not exceed 13 mm (1/2 in.) ACCEPTANCE CRITERIA AS PER API 653 • Deviations (Peaking) at vertical weld joints shall not exceed 13 mm (1/2 in.). • Deviations (Banding) at horizontal weld joints shall not exceed 25 mm (1 in.)